    ORAP means (Operational Reliability AnalysisProgram) is a service provided by Strategic Power

    Systems, Inc. (SPS) to owners/operators and

    Original Equipment Manufacturers (OEMs) for

    monitoring the Reliability, Availability andMaintainability (RAM) of the total plant, both simple

    and combined-cycle, including gas and steam

    turbines.

  • 7/31/2019 ORAP Data Entry Presentation

    4/18

    Common Questions

    How Often Should I Submit Data?

    -At a minimum monthly, but optional daily or weekly

    What Type of Information Should I Enter?

    - Events

    - Operational Data

    - Counter Readings

  • 7/31/2019 ORAP Data Entry Presentation

    5/18

    Events Examples

    Failure to Start: used for instantaneous trip prior to completion of startsequence or unit did not start in the startup time defined by dispatcher.

    -Start was initiated and unit could not achieve flame, it was discovered that ignitor

    cable was cracked, needed replacement.

    - Start was initiated, unit achieved flame, breaker would not close due to faulty relay.

  • 7/31/2019 ORAP Data Entry Presentation

    6/18

    Events Examples

    Forced Outage Automatic Trip (FOA): A trip from a state of operation

    when a component failure or other condition which causes the unit to beshut down automatically by the control system.

    - Unit tripped on high lube oil temperature, due to a shorted transmitter. Replaced

    transmitter and the unit returned to service.

    Forced Outage Manual Trip (FOM): Shutdown from a state of operationwhen a component failure or other condition which resulted in a decision bythe appropriate personnel to manually trip/remove the unit from service. This

    event type can also be used in cases where human actions result in the

    tripping of a unit from a state of operation.

    - A rise in vibrations was experienced and the unit was shut down to investigate. A

    failed vibration sensor was discovered, replaced and the unit returned to service.- A crane operator accidentally damaged the lube oil skid while removing the

    generator housing from unit#2 for major repair work. After replacement of the

    damaged pumps and piping, unit#1 was restarted.

  • 7/31/2019 ORAP Data Entry Presentation

    7/18

    Operational Data (monthly) Gross Output of Unit Over Stated Time Period

    Gas Fuel Consumption (mmBTU)

    Factored Hours Total hours unit run on gas and distillate.

    Service Hours Number of Hours Unit in Operation.

    Unavailable Hours Will Import From Events.

    Reserve Hours Hours Not Considered as Service Hours or Unavailable Hours.

    Successful Starts Number of Starts Resulting in Breaker Closure.

    Attempted Starts Start Attempts on a Unit. Difference between successful and

    attemted starts MUST equal the number ofFailure to Start Events reported.

  • 7/31/2019 ORAP Data Entry Presentation

    8/18

    Counter Readings

    Service Hours Lifetime total for the package.

    Factored Hours Lifetime total factored fired hours.

    Fired Starts Start where flame achieved in gas turbine. Lifetime total.

    Total Starts Number of times that the start button was pushed. Trip Count Number of times the unit tripped.

  • 7/31/2019 ORAP Data Entry Presentation

    9/18

    RAM Summary

  • 7/31/2019 ORAP Data Entry Presentation

    10/18

    RAM Summary

  • 7/31/2019 ORAP Data Entry Presentation

    11/18

    RAM Summary

  • 7/31/2019 ORAP Data Entry Presentation

    12/18

    RAM Summary

  • 7/31/2019 ORAP Data Entry Presentation

    13/18

    RAM Summary

  • 7/31/2019 ORAP Data Entry Presentation

    14/18

    RAM Summary

  • 7/31/2019 ORAP Data Entry Presentation

    15/18

    RAM Summary

  • 7/31/2019 ORAP Data Entry Presentation

    16/18

    RAM Summary

  • 7/31/2019 ORAP Data Entry Presentation

    17/18

    Non Disclosure Agreement

  • 7/31/2019 ORAP Data Entry Presentation

    18/18

    THANKS