27
Towards a Sustainable Implementation of Solar Thermal Power Plants Technology in the MENA www.dlr.de/enerMENA Optimized integration of CSP plants into Jordan's power plant portfolio Tobias Fichter, DLR The Joint German-Jordanian Workshop 2012 Amman February 27th – 29th

Optimized integration of CSP plants into Jordan's power

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Optimized integration of CSP plants into Jordan's power

Towards a Sustainable Implementation of Solar Thermal Power Plants Technology in the MENA

www.dlr.de/enerMENA

Optimized integration of CSP plants into Jordan's power plant portfolio Tobias Fichter, DLR

The Joint German-Jordanian Workshop 2012 Amman February 27th – 29th

Page 2: Optimized integration of CSP plants into Jordan's power

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 2 www.dlr.de/enerMENA

Content

1. Situation of Jordan 2. CSP – potential and characteristics 3. Methodology/ tool for efficient integration of renewable energy

technologies 4. Application to Jordan 5. Strategy for integration of renewable energy technologies in Jordan 6. Conclusion and future work

Page 3: Optimized integration of CSP plants into Jordan's power

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 3 www.dlr.de/enerMENA

Electricity Sector of Jordan Actual situation

2010: Installed Capacity: 3069 MW (+ 15,1% compared to 2009) Peak Load: 2650 MW (+ 15.2%) Generated Electricity: 14683 GWh (+ 3,3%)

Electricity generation heavily dominated by imported fossil fuels ≈ 80% by natural gas from Egypt

2011: Gas supply from Egypt interrupted several times due to terroristic attacks Thereby increased use of expensive HFO & LFO for power generation Price for natural gas from Egypt increased almost by a factor of 3 Annual natural gas supply restricted to about 3 billion m³/y

Page 4: Optimized integration of CSP plants into Jordan's power

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 4 www.dlr.de/enerMENA

Electricity Sector of Jordan Future development

Strong increase of peak load and annual electricity demand Large amount of new firm and flexible power generation capacity required Experienced increase of fossil fuel prices is likely to continue

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

2007 2012 2017 2022 2027 2032 2037 2042 2047

Year

Peak

Loa

d in

MW

Existing Generation CapacityEstimated by DLR in 2005Reality (Data ERC Jordan)

0

5

10

15

20

25

30

35

40

45

50

55

60

2007 2012 2017 2022 2027 2032 2037 2042 2047

Year

Gen

erat

ed E

lect

ricity

in T

Wh/

y

Estimated by DLR in 2005Reality (Data ERC Jordan)

Max 13 – 14 TWh/y by gas from Egypt

Page 5: Optimized integration of CSP plants into Jordan's power

Principle of Concentrating Solar Power Plants

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 5 www.dlr.de/enerMENA

Qualities of CSP Plants: Operating as peak, medium or base load power plant Firm & flexible capacity Power on demand Spinning reserve Combined generation of process heat for industry, cooling, desalination, etc.

Peak Load Base Load

Solar Field 2

Storage 2

3950 Flh

Storage 3

Solar Field 3

5700 Flh

Storage 4

Solar Field 4

7450 Flh 2200 Flh

Thermal Power Block

Solar Field 1

Storage 1

Electricity

Process Heat

Fuel

Solar Heat

SM 2 SM 3 SM 4 SM 1

Investment Costs

Page 6: Optimized integration of CSP plants into Jordan's power

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 6 www.dlr.de/enerMENA

Potential of Concentrating Solar Power in Jordan

Exclusion Criteria Urban areas

Population density

Hydrography

Land cover

Protected areas

Topography

Demand 2050: 53 TWh/y Potential CSP: 5884 TWh/y

DNI Classes [kWh/m²/y]

< 1900

1,900

2,000

2,100

2,200

2,300

2,400

2,500

2,600

2,700

Page 7: Optimized integration of CSP plants into Jordan's power

General Methodology Optimized Integration of CSP and other RE technologies in MENA countries

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 7 www.dlr.de/enerMENA

Resource & Site Assessment

REMix-CEM

Capacity Expansion Opimization Model

REMix-UCM

Unit Commitment Optimization Model

Optimal Capacity Expansion

(MW)

Optimal Unit Commitment

(MWh) Operation Costs

Investment Costs

Total Costs for

Electricity Supply

Power System Data

Techno-Economical Data

- Max Capacity - Resource time-series

Annuity of Investments

Page 8: Optimized integration of CSP plants into Jordan's power

Resource & Site Assessment Identification of hot spots for each technology

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 8 www.dlr.de/enerMENA

Identification of Hot Spots: Due to technology specific land exclusion and site ranking processes (e.g. valuing resource availability and distance from infrastructure)

Information for each Hot Spot:

Available area Maximum installable capacity Representative hourly resource profile (hourly values for DNI, GHI, wind speed)

Example!

HS-1

HS-3

HS-2

Page 9: Optimized integration of CSP plants into Jordan's power

REMix-CEM Capacity Expansion Optimization Model

Main Characteristics:

Time-frame: 25 – 40 years Methodology: Load Duration Curve analysis (several LDC per year)

Advantage: optimization of entire time-frame possible Disadvantage: - loss of short-term chronology - no consideration of inter-temporal constraints

Output: - optimized build schedule for new power plants - investment costs - rough estimation of operation costs

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 9 www.dlr.de/enerMENA

Page 10: Optimized integration of CSP plants into Jordan's power

REMix-UCM Unit Commitment Optimization Model

Main Characteristics: Time-frame: 1 year, 1h time-steps Methodology: Annual load curve analysis

Advantage: Taking into account inter-temporal constrains Disadvantage: computationally intensive, investigation of only 1 year Output: - Optimized unit commitment schedule - Detailed unit specific operation costs

Application: - complementary to REMix-CEM - identification of niche markets for CSP and other renewable energy technologies - within stepwise capacity expansion planning

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th

Slide 10 www.dlr.de/enerMENA

0

500

1000

1500

2000

2500

3000

01.07 02.07 03.07 04.07 05.07 06.07 07.07

Date

Load

in M

W

Hydro Industrial Units Combined-Cycle / natural gasGas Turbine / natural gas Steam Turbine / HFO CSP / peak-mediumPV Gas Turbines / LFO Import

Page 11: Optimized integration of CSP plants into Jordan's power

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 11 www.dlr.de/enerMENA

REMix-UCM: General Structure Minimizing total annual system costs

System & Unit Data

(MS-ACCESS)

FFP - EXIST

FFP - NEW

CSP - NEW

PV & WIND - NEW

Industrial Units

HYDRO - EXIST

Import / Export

MAIN

DEMAND

OUTPUT

Mixed Integer Linear Optimization Program written in GAMS

STORAGE - NEW

- Objective Function - Restrictions: - Meet hourly demand - Peak Capacity - Spinning Reserve - Tertiary Reserve - Power by Gas

Norm. Time-Series (txt-files)

- Load Curve - Generation Profiles: - CSP-SF - PV - Wind - Amb. Temp.

Results

(MS-ACCESS)

Evaluation

Examples of Output: - Total system costs - Ø electricity generation costs - Unit commitment - Unit specific marginal costs - No. of start-ups of each unit - Full load hours of each unit - Installed new capacity - Optimal configuration of CSP plants - Required tariff for RE-projects - …

Page 12: Optimized integration of CSP plants into Jordan's power

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 12 www.dlr.de/enerMENA

REMix-UCM Detailed modelling of power plants

Load [%]

Fuel

Cos

ts

Pmin

Pmax

S1

S2 Unit specific modelling Min./ max. load Parasitics Part load efficiency Min. on- & offline time Max. ramp rates Start-up & shut-down costs Variable & fix O&M costs Fuel costs Temperature influence (Investment costs) …

Ambient Temperature [°C]

1,0

15

Pel

Eta

Gas Turbine

Page 13: Optimized integration of CSP plants into Jordan's power

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 13 www.dlr.de/enerMENA

REMix-UCM Detailed modelling of CSP power generation

Power Block

Back-Up System

Storage

Solar Field

Output

CSP Model

Fuel

Power

Size of solar field (SM) and thermal energy storage capacity can be optimized Share and size of co-fire system can be determined

Page 14: Optimized integration of CSP plants into Jordan's power

Application of REMix-UCM to Jordan Case study: Investigation of niche markets

Question: CSP and PV already competitive today? Methodology: Comparing marginal costs of existing units with full costs of CSP and PV Investigation: Effects on total annual system costs when introducing max. 2x100 MW CSP plants and max. 200 MW PV into the existing power plant park Requisite: Detailed hourly modelling of existing power plant park with all relevant technical and economical restrictions

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 14 www.dlr.de/enerMENA

Page 15: Optimized integration of CSP plants into Jordan's power

Case Study: Niche Markets General Input Data

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 15 www.dlr.de/enerMENA

Data - Existing Units No. of Units Capacity# MW

Combined-Cycle Power Plants 6 2,020 Gas Turbine Power Plants 15 389 Steam Turbine Power Plants 12 1,018 Industrial Companies 5 102 Hydro Power 1 6 Wind - - Total 39 3,535

Site DataDNI 2487 kWh/m²/yGHI 2288 kWh/m²/y

Fuel PricesDateDollar-Euro EUR/1USDCrude Oil USD/bbl

World Market JordanNatural Gas 13.5 6.1 USD/MMBtuBunker Oil (HFO) 745 596 USD/mtDiesel (LFO) 1,047 837 USD/mt

02.07.20121.31

111.70

CSP PVNo. Of Units 2 1Netto Capacity of Unit MW 100 max 200Solar Multiple 1.5 xStorage Capacity Flh 6 xSpecific Investment Costs €/KW 5175 2200Operation Costs €/kWh 0.025 0.015Amortization Time y 30 20WAAC 7% 7%

Power System Data Year 2012Total Demand 17,391 GWhPeak Load 3,091 MWMinimum Load 1,172 MWNet Transfer Capacity 500 MWPeak Reserve Factor 10%Required Peak Capacity 3,400 MWInstalled Capacity 3,535 MWNatural Gas Availability 2.98 billion m³/yGAS 0.016 €/kWhth

HFO 0.043 €/kWhth

LFO 0.054 €/kWhth

Page 16: Optimized integration of CSP plants into Jordan's power

Case Study: Results

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 16 www.dlr.de/enerMENA

CSP already competitive in peak / upper mid-merit load segment

PV as “fuel saver” replacing expensive LFO

Main Results w/o RE w REAverage Generation Costs €/kWh 0.056 0.056Average Base Load Costs €/kWhAverage Mid-Merit Costs €/kWhAverage Peak Load Costs €/kWhLEC CSP €/kWh 0 0.148LEC PV €/kWh 0 0.121Full Load Hours CSP h 0 3575Full Load Hours PV h 0 2060Installed Conventional Capacity MW 3535 3535Installed CSP Capacity (netto) MW 0 200Installed PV Capacity MW 0 60Generation by Gas % 87.5 85.9Generation by HFO % 11.1 8.1Generation by LFO % 0.6 0.3Generation by Hydro % 0.3 0.3Generation by CSP % 0.0 4.4Generation by PV % 0.0 0.7Import % 0.5 0.3

0.190

0.0360.135

Page 17: Optimized integration of CSP plants into Jordan's power

Strategy for Integration of RE Technologies in Jordan Short-term…

CSP as peak / upper mid-merit power plants providing strongly required firm and flexible power capacity

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 17 www.dlr.de/enerMENA

CSP Configuration: - SM: 1 - 2 - TES: 3 - 6 h - Flh: 2000 - 4000

PV and Wind Power as “fuel saver“

Page 18: Optimized integration of CSP plants into Jordan's power

Strategy for Integration of RE Technologies in Jordan Mid- & long-term…

CSP becomes competitive with lower mid-merit and base load segment CSP as firm and flexible power capacity as backbone of electricity supply

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 18 www.dlr.de/enerMENA

CSP Configuration: - SM: 2 - 3.5 - TES: 6 - 18h - Flh: 4000 - 8000

Share of PV and Wind Power further increased

Fossil fuels used for peak load and in high efficient CC Units

Page 19: Optimized integration of CSP plants into Jordan's power

Conclusions and Future Work

Conclusions: CSP already competitive in peak and upper mid-merit load segment CSP only renewable energy technology which represents firm and flexible power capacity in MENA (no biomass, no pump-storage) Step-by-step integration will minimize subsidy requirements PV and Wind Power are important for saving expensive fossil fuels Large scale integration of renewable energy technologies will make Jordan more independent from future fossil price escalations Future Work: Up to now, developed tool mainly used for niche market identification Further development of tool Detailed calculation of capacity expansion Model must be validated with Jordan’s electricity generation companies

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th

Slide 19 www.dlr.de/enerMENA

Page 20: Optimized integration of CSP plants into Jordan's power

Thank You! Contact: Tobias Fichter: [email protected] Franz Trieb: [email protected]

Page 21: Optimized integration of CSP plants into Jordan's power

Back-Up Slides

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 21 www.dlr.de/enerMENA

Page 22: Optimized integration of CSP plants into Jordan's power

Objective Function: Minimization of Total Annual System Costs Main Restrictions:

Meet load in every hour of the year Providing enough Peak reserve, spinning reserve, and tertiary reserve Maximum annual natural gas availability

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 22 www.dlr.de/enerMENA

REMix-UCM Objective Function & major restrictions

Marginal Costs Full Costs

.min

__

_

⇒−+

+++++++

+++

=

EXPORTIMPORT

OPEXWIND

CAPEXWIND

OPEXPV

CAPEXPV

OPEXCSP

CAPEXCSP

OPEXNEWFFP

CAPEXNEWFFP

OPEXHYDRO

OPEXINDUSTRIAL

OPEXEXISTFFP

SYSTEMn

CCCCCCCCCC

CCCC

Page 23: Optimized integration of CSP plants into Jordan's power

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 23 www.dlr.de/enerMENA

REMix-UCM General Implementation

Modelling Language: GAMS (General Algebraic Modelling System) Optimization Method: Mixed Integer Linear Programming (MILP) Solver: Cplex Principle: Minimization of the objective function (total system costs) as a function of parameters and several constraints on these variables

Input Data GAMS

Cplex

Output Data

MILP

Page 24: Optimized integration of CSP plants into Jordan's power

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 24 www.dlr.de/enerMENA

REMix – UCM Process Chain Renewable Energy Technology Modelling

CSP: Solar Field Output

Technology: Parabolic Trough

PV: Electricity Generation

Technology: Polycrystalline Modules

WIND: Electricity Generation

Technology: Different Wind Turbines

INSEL

DNI CSP Hot-Spots

GHI

WIND Speed

PV Hot-Spots

WIND Hot-Spots

REMix-UCM

Hourly Resource Profiles

Normed hourly Generation Profiles

Unit Commitment

Page 25: Optimized integration of CSP plants into Jordan's power

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 25 www.dlr.de/enerMENA

Normed Generation Profiles INSEL: Integrated Simulation Environment Language

Block-oriented tool for simulation of renewable energies Blocks for PV und Wind turbines are incorporated in libraries CSP- (solar field, thermal storage, power block) implemented by DLR and integrated in INSEL

Output: normed hourly output of:

PV and Wind power electricity generation Thermal power output of Parabolic Trough solar field

Page 26: Optimized integration of CSP plants into Jordan's power

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 26 www.dlr.de/enerMENA

REMix – UCM Influence of Ambient Temperature

Ambient Temperature has great impact on gas and steam turbine performance Hourly temperature profiles at each power plant site are considered

Ambient Temperature [°C]

1,0

30

Pel

Eta

Steam Turbine

Parasitics

Ambient Temperature [°C]

1,0

15

Pel

Eta

Gas Turbine

Page 27: Optimized integration of CSP plants into Jordan's power

The Joint German-Jordanian Workshop 2012, Amman February 27th – 29th Slide 27 www.dlr.de/enerMENA

Example for unit specific input data

Technical & Economical Input Parameters Unit 1 … Unit 39

Sub N o de S1 … …U n it N a m e … …C a pac ity - brut to (P b) 373 … … M WC a pac ity - netto (P n) 362 … … M WFirs t Ye ar o f O p era tion 2 011 … …Las tYe ar o f O p era tion 2 046 … …U n it Typ e C C … …C o oling Ty pe D R Y … …Fue l G AS … …AltF uel LF O … …M a x. R a m p R a te 6.0 % … … of P b/m in

Parasit ics Pow er B lock @ m a x Lo ad 3.0 % … … of P b

E ffic ien cy @ m ax L oad - b rutto 52 .5% … …Effic ien cy @ m in L oad - brutto 42 .0% … …Sta rt-U p T im e - hot /w arm /c o ld 1/3/5 … … hM in im u m O nlin e/off line T im e 4 /2 … … hM in im u m L oad R ate 33% … … of P b

Fue l U s e fo r S tart 3 .5 … … M W hth/M W e l

O & M C osts - va riab le 3 .5 … … EU R /M W hO & M C osts - fix 0.7 % … … % o f Inv. C os tsN u m be r of Lab or 30 … … pers on sLab or C os ts 7 000 0 … … EU R /yAbrasio n C osts 11 .5 … … EU R /M W… … …