Operations Management Exercise 2: Product Design ProjectBy: Alvarado, Arielle; Benipayo, Mara; Ong Lopez, Albert; Sangalang, Jose Mari; Tenorio, Gian; Wong, Audren

3535313131313130282727272723232727272323232323232222222122212121222221223737353535322522161617161616111111116666222200I4 (4)S2 (6)I1 (3)D4 (4)V1 (10)I3 (4)I2 (4)V2 (2)D1 (1)D2 (2)D3 (1)S1 (5)P4 (5)P3 (5)P2 (4)P1 (2)

Answers to Questions 1 & 2:

PathLength (days)

P1-P2-P3-P4-S1-D2-I2-I3-I4-V237 (critical path)

P1-P2-P3-P4-S1-D2-D4-I1-I4-V236

P1-P2-P3-P4-S1-D1-D4-I1-I4-V235

P1-P2-P3-P4-S1-D3-D4-I1-I4-V235

P1-P2-P3-P4-S2-V1-V234

P1-P2-P3-P4-S1-V1-V233

Answer to Question 3:ACTIVITYLS-ESSLACKON CRITICAL PATH

P10-0

P22-2

P36-6

P411-11

S117-161

S216-16

D122-211

D221-21

D322-211

D423-23

I130-273

I223-23

I327-27

I431-31

V125-223

V231-31

Activities with Slack: S1, D1, D3, I1, V1