Operations Management Exercise 2: Product Design ProjectBy: Alvarado, Arielle; Benipayo, Mara; Ong Lopez, Albert; Sangalang, Jose Mari; Tenorio, Gian; Wong, Audren
3535313131313130282727272723232727272323232323232222222122212121222221223737353535322522161617161616111111116666222200I4 (4)S2 (6)I1 (3)D4 (4)V1 (10)I3 (4)I2 (4)V2 (2)D1 (1)D2 (2)D3 (1)S1 (5)P4 (5)P3 (5)P2 (4)P1 (2)
Answers to Questions 1 & 2:
PathLength (days)
P1-P2-P3-P4-S1-D2-I2-I3-I4-V237 (critical path)
P1-P2-P3-P4-S1-D2-D4-I1-I4-V236
P1-P2-P3-P4-S1-D1-D4-I1-I4-V235
P1-P2-P3-P4-S1-D3-D4-I1-I4-V235
P1-P2-P3-P4-S2-V1-V234
P1-P2-P3-P4-S1-V1-V233
Answer to Question 3:ACTIVITYLS-ESSLACKON CRITICAL PATH
P10-0
P22-2
P36-6
P411-11
S117-161
S216-16
D122-211
D221-21
D322-211
D423-23
I130-273
I223-23
I327-27
I431-31
V125-223
V231-31
Activities with Slack: S1, D1, D3, I1, V1