View
220
Download
0
Embed Size (px)
Citation preview
8/6/2019 Once the Basic Well Models Were Built
1/4
Once the basic well models were built, the other objectives that should be fulfilled are:
To determine which types of artificial lift methods (ALM) are applicable and the mostsuitable for the lifting of fluids produced in field;
To assure that selected ALM and equipment will be able to maintain optimum drawdown,so the future reservoir management and completion can be conducted efficiently;
To provide the required input for proper completion selection and design;To assure that the selected Artificial Lift System (ALS) will enable production of desired
reservoir fluids at the acceptable rate;To assure enough flexibility in order to manage some technical uncertainties and mitigate
risk (changeable well performance characteristics, equipment reliability factors etc.);To analyze relative costs and economic benefits of various ALS and determine economic
viability including risk assessment of some reservoir and fluid uncertainties.
Introduction
Correct selection of an artificial-lift method is important to the long term profitability ofmost producing oil wells. Proper artificial lift method selection is also very important for
gas wells that load up with liquid and for coalbed methane wells that must be dewatered. Awrong ALM selection can reduce production and increase operating costs substantially.
The workflow that could be applied for the selection of the best ALM for the oil and gaswells is a comprehensive step-by-step procedure that features the following activities:
Collecting and reviewing production and pressure histories for currently tested wells:a. Analysis of the wells history enabled identification of specific behavior of each
particular well.b. Pressure survey data, PVT reports, reservoir characteristics, fluid data (laboratory
analysis related to various downhole production problems- emulsion, hydrate, organicscales, sands and salt deposition) were collected and summarized.
c. The quality of data was checked and reviewed and used for modeling purposes.Additional data should be requested to identify subsurface uncertainties impacts on future
well performance. As there are a lot of uncertainties related to future production profile,the wells can be classified into different classes and for each group of wells the range of
productivity indices needs to be defined (base case, minimal and maximum)
The collected information was included into developed multi-criteria ranking model andassigned to various factors (completion, production, efficiency etc.). The importance of
each factor is qualified and used for generating the AL selection matrix. It is allowed toeliminate some ALM with lowest score and to continue the process of selection including
technical, economic and risk parameters.
To finalize the ALM selection process, the integrated (technical/economic and risk)evaluation of preliminary selected methods/systems should be applied.
Fulfilling of the future needs related to well completion and mitigation of the expectedproblems (well performance changes, real time monitoring and control, chemical injection,
plugging with organic and inorganic scales, unexpected problems with suddenly increasedwater cut etc).The methodology and action workflow is shown on Fig. 1.
8/6/2019 Once the Basic Well Models Were Built
2/4
Preliminary Artificial Lift Selection
The preliminary selection of the best ALS for the life of project on oil and gas field canbe done by using multi-criteria model (ranking matrix). The most pertinent parameters
could be grouped into six general classes. Within general classes (macro level) we haveextracted the subclasses of parameters (micro level) with defined importance (evaluation),
as shown on Fig. 2.
By using the evaluations of particular ALM (sucker rod pump, electrical submersiblepump, progressive cavity pumps, continuous and intermittent gas lift, etc) and theimportance of particular parameters on micro level, the evaluation matrices can be
generated.
The level of importance of a certain parameter alters as a function of final effectiveness ofthe applied method. If, during the application of selected method(s), it is found out that
there is a discrepancy and well production results are not in accordance with predictedbehavior, then the extracted parameters have to be reanalyzed, the estimation corrected, and
the newly achieved estimation will be used for the next case.
Multi-riteria Model Structure and Features
The general factors (Fig. 3) required for developing the analytical multi-criteria model onmacro-level are:
Applied completion systems (WCF);Well and reservoir production history (QHF);
Pressure history data (PHF);Current well performance (WPF);
Expected problems (EPF);Costs, Efficiency and Logistics (CELF).
These evaluations are the results of the following:
Characteristics of the past and current well performance;Expected problems;
Knowledge and experience of experts and field personnel;Natural, technical and economical limitations;
Defined rules depending on applicability of analyzed artificial lift methods;Advantages and disadvantages of analyzed ALM;
Five-level evaluation can be used in for preliminary selection using MCM (Table 1).
The evaluation of zero (0) for certain criteria automatically eliminates the possibility ofapplying some of the methods. The Level of importance of certain parameter alters as a
function of final effectiveness of the applied method. The rank of some parameters can bechanged if it is found out that there is a discrepancy between expected and real system
behavior and rank corrections is a part of learning process and model modifications. Thekey element of the model is the general factor classes factor on macro level (GFC).
8/6/2019 Once the Basic Well Models Were Built
3/4
(2)
where:
k stands for general classn - is number of subclasses
Final evaluation of production method application possibility is equal to geometricalaverage of Integrated Evaluation Factor (IEF, eq.2 for particular general factor classes. The
number of general factor classes is variable so that IEF for each well includes only thoseparameters for which there is a possibility to be defined.
(1)
If there is a lack of information about well and if it is not possible to define estimation of
some factors, a number of multipliers can be reduced. The influence of the parameters forwhich there are no data should minimized since their influence has not been taken into
account.Example of ALM selection and final result for preliminary selection is shown in Table 2.
Structure of Economic Model
Economic evaluation of preliminary selected artificial lift methods and required
investment are the major parameters influencing on final recommendation. The detailedeconomic study should be done with an aim to get economical parameters for various
conditions and preliminary selected ALM including various vendors. As results of suchanalysis it is possible to generate comparative economic plots as reliable tools for making
proper decision.
The key elements of the economic model are shown in Fig. 4.
As shown in the figure, the economic model consists of:Expected oil/gas price database;
Estimated prices for energy, chemicals, workover, maintenance;Price list for selected equipment.
The module for capital expenditure (CAPEX) should be used to calculate the required
capital investment for the preliminary selected artificial lift methods.Results of comparative economic analysis including the revenue from selling the oil only
can be presented in terms of the discount cash flow and net present value (NPV).
For the ALM selection, the net oil production, the ultimate net cash flow and discountedpresent value of the total net cash flow are usually sufficient to make a right decision and to
select the best ALM method according to the reservoir, well and market conditions.
From the presented plots in Fig. 5 it is obvious that Electrical Submersible Pump (ESP)
and Progressive Cavity Pump with a downhole motor (PCPDM) shows the bestperformance indicators expressed in terms of discount cash flow (DCF).
The difference between ESP and PCPDM is being larger after DCF reached the maximumvalue (correspond to 3-4 years after production started). It is also related with the water cut
8/6/2019 Once the Basic Well Models Were Built
4/4
changes and the behavior of ESP and PCP under conditions when the stable viscous
emulsion could be generated.
After the discounted net cash flow was generated the NPV of various ALM (Fig. 6) canbe determined and using risk analysis the probability distribution for NPV could help in
making the final decision, as shown in Fig. 7. The final plots (Fig. 8) show the comparisonbetween the most probably NPV for ESP, PCPDM and CGL. Based on the obtained results
of discounted cash flow and risk analysis of NPV, ESP and PCPDM are the most preferredALM method on this randomly selected field.
Conclusion
The preliminary selection of the artificial lift selection needed for detailed technical andeconomical analysis can be prepared by using multi-criteria model which is generally
described in the paper. Using available information (well completion, fluid properties,results of analysis and interpretation, current well performance data) the evaluation
matrices should be generated. The expert evaluations used in the model are based on theaccumulated experience and published knowledge.
Once the preliminary ALM is selected, the comprehensive economic evaluation methods
for the making final decision and selection the best ALM should be applied. The economicmodel is slightly modified by using a changeable product (oil/gas) prices, production rates
influenced by a well performance, estimated target run life of selected equipment andequipment capabilities of a various vendors.
The initial step is to make detailed design and to decide what equipment will be required
to accomplish the expected production rate. Among the most common economic indicatorsof economic evaluation, the discounted cash-flow rate of return (DCFR) and net present
value (NPV) are used for final ALM selection. In general, no one method is by itself asufficient basis for judgment. It must be recognized that such a quantified profitability
measure should be used in combination with other methods, like risk analysis, to includesome unpredictable factors and uncertainties that cannot be accounted for (reservoir/well
and equipment uncertainties). Using risk analysis of NPV in terms of number of wells,well performance/productivity, costs of equipment and chemicals, manner how to handle
the anticipated problems(scale, hydrate, emulsion, corrosion, etc.), estimated run life ofequipment and etc, the most reliable and efficient ALM can be selected.