18

Oil and Gas Research Program

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Oil and Gas Research Program
Page 2: Oil and Gas Research Program

Oil and Gas Research Program

North Dakota

Industrial Commission

Application

Project Title: Center for Gas Utilization

Applicant: University of North Dakota Institute

for Energy Studies

Principal Investigator: Steven A. Benson, PhD

Date of Application: August 14, 2012

Amount of Request: $700,000

Total Amount of Proposed Project: $3,000,000

Duration of Project: 9/1/2012-8/31/2015

(3 years)

Point of Contact (POC): Steve Benson

POC Telephone: 701-777-5177

POC E-Mail Address:

[email protected]

POC Address:

366V Upson II 243 Centennial Drive Stop 8153 Grand Forks, ND 58202-8153

Page 3: Oil and Gas Research Program

TABLE OF CONTENTS

Please use this table to fill in the correct corresponding page number.

Transmittal and Commitment Letter 0

Abstract 1

Project Description 2

Standards of Success 8

Background/Qualifications 8

Management 11

Timetable 12

Budget 12

Confidential Information 13

Patents/Rights to Technical Data 13

Statement of status on Other Project Funding 13

Affidavit of Tax Liability 13

Letter of Support A-1

Budget Summary (narrative) A-2

Page 4: Oil and Gas Research Program

ABSTRACT

Shale oil booms, especially the Williston Basin, have significantly increased domestic oil production and

are projected to continue producing oil for at least the next 20-30 years. In the Williston Basin, over 200

million cubic feet of gas is flared off each day which represents 30% of the natural gas recovered. The

flared gas not only represents an unused fuel source, but also accounts for over 4 million tons of CO2

emissions on an annual basis.

Objectives: In order to utilize flared gas and reduce emissions, the University of North Dakota, through

the Institute for Energy Studies’ Center for Gas Utilization, proposes to identify, design, construct, test,

and deploy small scale modular equipment to convert natural gas to methanol and electricity. This work

will be conducted through a strategic alliance between UND’s Institute for Energy Studies and Blaise

Energy. The proposed effort to develop a small scale polygeneration system to produce methanol and

electricity from produced gas involves the following steps:

Identify the optimum scalable polygeneration technologies through a detailed engineering

analysis of the technical and economic feasibility of several technology options,

Design, construct, and test a polygeneration prototype at a Blaise Energy generation site,

Determine performance impacts due to changes in gas flow and properties (composition and

liquid component type and abundance),

Overall system efficiency and cost of production of electricity and methanol,

Key operational and design parameters to provide accurate cost information for a full-scale

commercial system.

Educate the next generation of energy experts by having graduate and undergraduate students

work with IES faculty and engineering staff in all aspects of the program.

Expected Results:

The proposed efforts provide key technical and economic information on a working polygeneration

prototype system that is capable of converting up to 2 million cubic feet of gas per day into methanol and

electricity along with separated liquids and carbon dioxide. These results will be summarized in quarterly

reports and a final report that will provide detailed explanation design and performance of the

polygeneration system. The report will also identify specific strategies to utilize flare gas and convert the

gas into an economically beneficial products (methanol and electricity) while minimizing emissions.

Further, the quarterly reports and the final report will be provided for comments and revision.

Duration: 3 years (9/1/2012-8/31/2015)

Total Project Cost:

$700,000 – Requested from North Dakota Oil and Gas Council

$300,000 – Provided by the North Dakota Department of Commerce Center of Research Excellence

$2,000,000 – Provided by Blaise Energy

$3,000,000 – Total Project Cost

Participants:

North Dakota Industrial Commission, North Dakota Department of Commerce Center of Excellence

Program, Blaise Energy, and The University of North Dakota Institute for Energy Studies.

Page 5: Oil and Gas Research Program

PROJECT DESCRIPTION

Objectives:

The proposed effort will demonstrate the feasibility of a scalable polygeneration system that

utilizes flare gas to produce electricity and methanol. A portion of the proposed effort is support Blaise

Energy and the ND Department of Commerce Center of Research Center of Excellence Program (CORE).

This proposal requests additional support of the NDIC Oil and Gas Program.

The key objectives of the work are:

1. To design and construct a small scale polygeneration system that will be used to convert up to

2,000,000 cubic feet per day of natural gas to electricity and methanol.

2. To test the system at a Blaise Energy site for up to 18 months. The tests will address the key issues:

What is the impact of changing gas flow rates on the production of electricity and methanol?

What is the impact of changing gas composition on the system performance?

What is the impact of other components in gas, such as abundance of liquids in gas supplies,

on the ability to produce products?

What is the impact of low H2S concentrations in the gas polishing system and to catalyst life?

What is the appropriate sizing of the electricity generator and methanol system to optimize

the production of product streams to meet changing market needs and to maximize profit?

3. To determine overall system efficiency and cost of production of electricity and methanol.

4. To determine key operational and design parameters to provide accurate cost information for a

commercial system.

5. To maintain contact with potential commercial sponsors, reporting progress and opportunities for the

polygeneration system in their applications. This effort will be continued throughout the duration of

the project.

6. To educate the next generation of energy experts by having graduate and undergraduate student

participate in the demonstration and commercialization efforts.

Methodology:

UND proposes to work with project sponsors to demonstrate and commercialize a polygeneration

system that integrates several technologies and has the potential to produce four product streams that

include electricity, methanol, carbon dioxide (enhanced methanol production and enhanced oil recovery

(EOR)), and C-3+ liquids. The overall system is illustrated in Figure 1. The Phase I effort will focus on

identifying an optimum methanol production technology and integrating with the electricity generation

system, followed by a field test of the integrated system. UND and partner, Blaise Energy, will work

together to demonstrate and commercialize the system. Blaise Energy is currently utilizing gas to produce

electricity using a combustion system. Blaise Energy is also working on a system to separate the liquids

from the gas to improve the operability of the combustion system. A gas to liquids system will be used to

convert the methane rich produced gas to methanol and possibly other liquids. A Blaise Energy

Partner/Investor is interested in installing the integrated system at numerous sites within the Williston

Basin.

In order to complete the objectives and above methodology, the following tasks are proposed.

Task 1: Project Management and Planning

Page 6: Oil and Gas Research Program

The purpose of this task is coordination and planning of the project with the NDIC Oil and Gas Program

and project participants. This task will be performed over the course of the project.

Figure 1. Overall concept of the polygeneration system to produce electricity, methanol, CO2 and C-3+

Liquids.

Task 2: Integrated Concept Design

The integrated concept design of the polygeneration technology will be developed through discussion

with project sponsors, review of technical literature, and commercial application of technology

components. Sponsor input will provide information on following:

Optimum size of the system based on the quantity of produced gas to be converted,

Composition range of the produced gas (range and a design fuel composition),

Scalability of the system

Range of operating conditions – power generation capacity and methanol generation capacity,

Identification of the gas to liquid vendor systems to be analyzed (catalytic, partial oxidation,

combined) in Task 3.

Emissions control requirements

Task 3: Initial Technology and Economic Feasibility analysis

The overall goal of this task is to conduct a technology and economic feasibility study of the Phase I

polygeneration concept as defined in Task 2. The proposed polygeneration concept is anticipated to be

comprised of a gas liquid separator, gas-fired combustion generator, steam generator, methane to

methanol system, and auxiliary equipment (storage tanks, gas cleanup, emission controls). Process flow

diagrams for the polygeneration process will be developed and major heat and material balances will be

generated using ASPEN Plus simulation software. A qualified A&E firm will be identified and hired to

support UND and Blaise Energy in the feasibility analysis. The A&E firm will utilize and refine process

Page 7: Oil and Gas Research Program

flow diagrams and heat and material balance streams from UND to reflect the additional details and

adjustments required to accurately represent a full range of operating conditions. The outputs of the

refined study will be:

General process flow diagram identifying all major process equipment for the combined

electricity and methanol generation system.

Material and energy balances around the combined power and methanol generation system

and around all major pieces of equipment (heating/cooling duties and power requirements).

Equipment definition list with associated vendor and/or in-house fabrication quotations.

Estimation of plant performance based on a developed auxiliary load list obtained from

equipment quotations or through an in-house database.

A conceptual site plan detailing the arrangement of the polygeneration system in an existing

Blaise Energy Investor facility.

Development of feasibility level capital cost estimates for the Phase I polygeneration system.

This capital cost estimate will indicate the all-in costs for the facility including infrastructure

from the site fence line, interconnection to existing facilities, equipment costs, construction

costs, construction indirects, and owner’s costs.

A definition of consumable quantities and costs inclusive of waste streams to estimate the

operating and maintenance costs (both fixed and variable).

Estimate of the cost methanol and electricity produced using the economic criteria provided

by sponsors for all cases.

A quantification and definition of the air and water emissions and solid wastes produced by

the polygeneration system including offsite disposal options.

A definition of toxicological effects of substances used in the process and associated

regulatory requirements.

An evaluation of the ability to reduce or mitigate the production of potentially hazardous

materials.

Identification of precautions for safe handling of fuels produced and associated waste

streams.

The above information will be used to determine process and cost advantages of the proposed

technology as well as the key success drivers and risk factors. This will provide items to focus and

address for the remainder of the project.

Task 4: Prototype Process Design

The purpose of this task is to design a prototype polygeneration system. The system will be built

using design parameters generated in Tasks 2 and 3.

Subtask 4.1 - Design of Gas Separation and Electrical Generation System: The design of the

gas separation and electrical generation system will be conducted by Blaise Energy and designed

to provide gas, electricity, and steam to the gas to liquids train. The system will be designed to

accept up to 2,000,000 cubic feet per day (CFD) of produced gas from a Blaise Energy Investor

gas gathering location. If necessary, reductions in the levels of H2S will be conducted using a

ZnO sulfur capture system to meet catalyst specifications. The resulting cleaned gas will be piped

to both the generator and gas to liquids unit.

Subtask 4.2 - Design of Gas-to-Liquids System: The GTL system will be based on results of

Task 3. A system will be selected and the design will be based on the vendor. It is anticipated that

the unit will be mounted on a 40ft flatbed trailer. The system will be designed to allow for easy

integration with the gas separation and electrical generation system. Storage tanks for products

will be sized and piping and associated equipment will be designed for transfer to a tanker truck

Page 8: Oil and Gas Research Program

for delivery to market. The system will be designed to include the ability to sample liquid and gas

phase material within the system during operation.

Subtask 4.3 – Design of On-line Gas and Liquids Sampling and Analysis System: State of

the art analytical systems will be installed to provide real time analysis of process streams in the

system. These systems will include laser gas analyzers, gas chromatographs, and process mass

spectrometers. Analyzers will also be used to monitor any emissions, if present, from the overall

system.

Task 5: Prototype Process Procurement and Construction

Subtask 5.1 - Construction of polygeneration system: This sub-task will involve sourcing

materials to construct the gas separation and electricity generator, gas to liquids system, and

associated piping and equipment. Tie-ins to the produced gas will also be included in this period.

Other equipment to be included in the installation include flue gas monitors (CO2 and SO2),

temperature sensors, pressure gauges, and mass flow meters for use to monitor system

performance. The unit will be constructed by Blaise Energy, GTL equipment vendor, and UND

Institute for Energy Studies engineers.

Subtask 5.2 - Installation and integration of system: Installation at the Blaise Energy Investor

site will be performed by a site contractor with supervision from UND. Instrumentation will be

installed to monitor process conditions of the unit and also simultaneously obtain information on

well production.

Subtask 5.3 -Shakedown testing: This sub-task will involve system start-up and shakedown

testing. The shake-down testing will be conducted in three separate phases.

1. Phase 1 will be geared toward testing the gas and liquid sampling system. The system will be

subjected to varying levels of gas flow rates, electrical generation rates and methanol

production rates. Apart from getting baseline operating data, this will allow the operators to

get trained in using the system.

2. Phase 2 will be geared toward testing the gas separation and clean up component of the

system. Operators will be trained on the system. The capability to recycle gas cleanup sorbent

to the adsorber will be tested and ability to measure/deduce recycle flow rates developed.

3. Phase 3 will target shakedown of the integrated electrical and steam generation system with

the gas to liquids unit. This is one of critical steps for the project. The generator will be tested

for operation under different operating conditions. The gas and liquid feed system will also be

tested to ensure that it can be fed to and removed from the system in a reliable and

measurable manner.

Task 6: Initial Operation of Prototype in Laboratory

A laboratory at UND will be developed to allow for continuous monitoring of the operation of the

prototype system in the field. The laboratory will be equipped with the ability to have access to and

ability to control selected system control features. Samples of gas and liquids will be characterized at

UND.

Task 7: Field testing of Prototype

The testing will consist of longer term testing of the integration of the operation of the gas

separation, electrical and steam generation, and the gas to liquid system under vary conditions for

electricity and methanol generation. It is anticipated that this testing will be conducted over an 18 month

time period to also examine the effects of seasonal temperature changes.

Task 8: Final Process Assessment (Technical and Economic Feasibility) and Recommendation

Page 9: Oil and Gas Research Program

The technology and economic feasibility study conducted in task 3 will be updated. From the

work performed in Tasks 5, 6, and 7, we will incorporate the data into a detailed and evaluation of the

technical and economic feasibility of the integrated process. This effort will be on-going throughout the

project and a recommendation will be made relative to the installation of additional systems at other well

sites. As part of the final report for the project an updated technology and economic feasibility study will

be conducted and a final report will be issued that details the proposed polygeneration system.

Anticipated Results:

The proposed work will produce many results including a working polygeneration pilot-scale

system capable of converting up to 2 million cubic feet of gas a day into methanol. The system will also

generate electricity that can be used to help power the system as well as supplemental power for the well

site. The polygeneration will provide the following results:

Reduce natural gas flaring in North Dakota

Improve local air quality through the reduction of gas flaring

Create new jobs in North Dakota

Advance North Dakota as a leader in green well completion technologies

Other results of the project will be quarterly reports and a final report that will include a detailed

explanation and supporting experimental, and pilot-scale testing results of the polygeneration system. The

report will also identify specific strategies to utilize flare gas and convers the gas into an economically

beneficial product with emission and environmental benefits. Further, the quarterly reports and the final

report will be provided for comments and revision.

Facilities and Resources:

The pilot system will be a skid-mounted mobile system capable of being transported to different

locations. The system will contain all necessary components to take the flare gas and convert it to

methanol and electricity.

The initial lab-scale testing will be conducted at UND. UND has placed great emphasis on

research and development programs. During the past several decades UND has made a strong

commitment toward acquiring the resources and tools to conduct basic and applied research in a wide

variety of disciplines. At the same time, UND has also been working to improve curricula, promote best

practices, advance knowledge and professional development in fields of specialization, and encourage

scholarly interaction and accessibility among faculty and students. The continued growth in research and

development has resulted in a classification of UND as a high research activity university

The UND department of Chemical Engineering has a 19kW pilot scale entrained flow

combustion system capable of firing coal and biomass, a 5 kW natural gas fired combustor, and a 10 kW

gasification system. The combustion systems can be integrated with a baghouse for particulate control

and a wet scrubber system for sulfur control. The flue gas from these systems can be used to study CO2

capture. UND currently uses a 1 kg fixed bed reactor system to capture CO2 using solid sorbents. The

reactor system is equipped with a steam generator for sorbent regeneration. This reactor system has been

used to test the adsorption and regeneration behavior of several solid sorbents. These conversion systems

are all equipped with the following flue gas analyzers that can continuously sample flue gas:

Non-dispersive Infrared Absorption Spectroscopy for SO2 and CO/CO2 analysis using the Teledyne

Analytical Instrument-IR 7000 and the Liston Scientific Enviromax respectively.

Paramagnetic type O2 Analyzer - using the Teledyne analytical instrument-3000M series.

Page 10: Oil and Gas Research Program

A Datatest Model DT 5000 NOx analyzer that utilizes chemiluminescence technology for precise

continuous measurement of the NOx.

Two Horriba five gas analyzers capable of measuring NOx, SOx, CO, O2 and CO2.

UND Chemical Engineering also has a simultaneous thermogravimetric/differential scanning

calorimeter (TGA/DSC). Simultaneous measures of weight loss or gain and exothermic and endothermic

reactions/transformations associated with decomposition and adsorption processes can made as a function

of temperature and atmosphere. The UND Engineering Department also has access to Aspen Plus process

modeling software which will be used in the proposed research.

Techniques to Be Used, Their Availability and Capability:

The electricity generators will utilize existing and “off the shelf” equipment from vendors already

in the industry. The gas cleaning and condition equipment will utilize proven methods and systems such

as membranes and filters. These methods will ensure that the constructed system is able to be skid

mounted and integrated into the overall pilot system design. The components are readily available since

they are “off the shelf” equipment.

The specific methanol technology to be used will be identified during the course of the project.

The technologies being considered are all technically sound and proven at large scale commercial scales.

The technologies are readily available and capable of being integrated into a skid mounted small-scale

systems.

Environmental and Economic Impacts while Project is Underway:

If successful, the project will have positive environmental and economic impacts during and beyond the

project timeline. The proposed work will reduce flare gas emissions which will reduce local CO2

emissions and improve local air quality through the reduction in emissions associated with flaring. In

addition, the project will produce a methanol commodity that can be sold to a wide variety of industrial

companies that utilize methanol.

Ultimate Technological and Economic Impacts:

The proposed project will identify a technology solution to help reduce flare emissions in the Bakken

region while at the same time providing an increased revenue supply. As of April 2012, approximately

221 million cubic feet of gas are flared each day which corresponds to 6.6 billion cubic feet per month. If

this wasted fuel supply is converted to methanol, this represents a potential methanol market of $105

million a month at a methanol price of $1.32 per gallon. The electricity produced will help reduce

associated power costs at the well site, and is also classified as a “recycled” energy in North Dakota. It is

also anticipated that long term deployment and commercialization of the polygeneration system will lead

to additional jobs in North Dakota through the design, fabrication, and operation of commercial systems.

Why the Project is Needed:

Annually, 150 billion cubic meters of natural gas is flared or vented on a global level, releasing

400 million tons of carbon dioxide emissions. Approximately 5.5 Billion cubic feet, or almost one third of

the gas produced in North Dakota, is flared each month because of the lack of infrastructure to capture the

gas or otherwise monetize it. This represents an estimated 1900 wells flaring in North Dakota alone, with

over $11 million in lost revenue (at $2/MCF) each month. Compounding the effects of lost revenue is the

waste of natural resources emitting as much CO2 into the atmosphere as approximately 350,000 cars and

an estimated 167,000 tons of CO2 each month. Compounding the emissions, the additional electrical load

Page 11: Oil and Gas Research Program

to service the new wells is putting a strain on the local electrical grid. In some areas, rural electrical

utilities are running out of capacity to keep up with the load and are struggling to add “peaking” plants

and high capacity lines to bring in additional power from coal plants. Several local coops are also

hundreds of wells behind for grid connection. The 200+ additional new wells being drilled each month

are outpacing gas and electric infrastructure and creating increased demand for site and grid power.

STANDARDS OF SUCCESS

Project success will be demonstrated through a successful feasibility, design, construction, and

demonstration of the polygeneration system. The polygeneration system will be deemed successful upon

demonstrated production of electricity and methanol from natural gas at a well site. The completion of the

project report and presentation of the results will also serve as key standards for the proposed project.

The key industries in North Dakota that will benefit for the results of this project are the oil and gas

industry as well as North Dakota itself, and the local communities in the Williston Basin. The

development and implementation of the polygeneration system will turn a waste source into a valuable

product that can be sold for profit. The polygeneration system also will help the oil and gas companies

meet pending flare reduction policies and adopt greener well site completion practices. North Dakota and

local communities will benefit from the increase in jobs associated with the design, construction,

installation, and operation/maintenance of the polygeneration systems as well as benefit from improved

air quality due to the decrease in flare gas emissions.

BACKGROUND/QUALIFICIATIONS

The Center of Excellence for Gas Utilization at UND is aimed at developing commercial technologies to

improve the utilization gases produced from industrial sources. These sources include gas produced from

petroleum wells and from combustion and gasification sources. The technologies include gas cleanup

(removal of impurities), gas separation, and gas conversion. Currently funded programs within the Center

for Gas Utilization (CGU) include: $3.7 million effort to separate carbon dioxide from combustion flue

gas streams funded by the U.S. Department of Energy and Industry (NDIC, ALLETE, BNI, and

SaskPower), $860,000 effort to remove mercury from flue gas from taconite production plants funded by

the U.S. Environmental Protection Agency, Minnesota Department of Natural Resources, and Taconite

industry; and $462,000 effort to evaluate syngas production using underground lignite gasification

approved for funding from the North Dakota Industrial Commission and Industry (Great Northern

Properties).

The CGU proposes to expand its efforts to demonstrate and commercialize an integrated system that will

convert natural gas currently being flared to methanol, electricity, and other liquid fuels. Annually, 150

billion cubic meters of natural gas is flared or vented on a global level, releasing 400 million tons of

carbon dioxide emissions. Approximately 5.5 Billion cubic feet, or almost one third of the gas produced

in North Dakota, is flared each month because of the lack of infrastructure to capture the gas or otherwise

monetize it. This represents an estimated 1900 wells flaring in North Dakota alone, with over $11 million

in lost revenue (at $2/MCF) each month. Compounding the effects of lost revenue is the waste of natural

resources emitting as much CO2 into the atmosphere as approximately 350,000 cars and an estimated

167,000 tons of CO2 each month. Compounding the emissions, the additional electrical load to service the

new wells is putting a strain on the local electrical grid. In some areas, rural electrical utilities are running

out of capacity to keep up with the load and are struggling to add “peaking” plants and high capacity lines

to bring in additional power from coal plants. Several local coops are also hundreds of wells behind for

grid connection. The 200+ additional new wells being drilled each month are outpacing gas and electric

infrastructure and creating increased demand for site and grid power.

Page 12: Oil and Gas Research Program

There are several technologies that are emerging as having potential to convert natural gas to methanol

economically at the scale appropriate for small scale stranded gas sites. The technologies include

catalytic, non-catalytic partial oxidation, or combined partial oxidation-catalytic processes (Aasberg-

Petersen and others, 2011, Pawlak and others, 2012, and Wender, 1996). Some of the processes involve

stream reforming natural gas to a synthesis gas (H2 and CO) followed by a catalytic process to produce

methanol. Converting synthesis gas to methanol has been used extensively in converted coal gasification

derived syngas to methanol and other fuels and chemicals (Benson and Sondreal, 2010). The reaction is

exothermic, and the heat of reaction can be used to heat the process. The conditions used to produce

methanol are about 5 MPa (50 atmospheres) and a temperature of 270°C (518°F). The selectivity of the

synthesis is very high with a >99.5% conversion to methanol from syngas possible. The processes

involved in converting synthesis gas to methanol and other chemicals and fuels are illustrated in Figure 2.

Methanol is currently being used to produce gasoline in a methanol-to-gasoline complex in New Zealand

as well as other locations in the world. Methanol is converted to gasoline by the Mobil process, where the

methanol is first dehydrated and converted to produce DME:

2CH3OH → CH3OCH3 + H2O

A zeolite catalyst, ZSM-5, is then used to give a gasoline with 80% C5 + hydrocarbon products.

Figure 2. Synthesis pathways for the production of selected fuels from syngas (MTBE = methyl tertiary-

butyl ether, BTX = benzene, toluene, xylene) (Wender, 1996).

References

Aasberg-Petersen,K., I. Dybkjær, C.V. Ovesen, N.C. Schjødt, J. Sehested, S.G. Thomsen, Natural gas to

synthesis gas - Catalysts and catalytic processes, Journal of Natural Gas Science and Engineering 3

(2011) 423-459.

Benson, S.A., and E.A. Sondreal, Gasification of Lignites of North America, Lignite Energy Council,

2010.

Pawlak, N., V. I. Vedeneev, and A.L. Tots, Gas Technologies LLC, US Patent 8,202,916, June 19, 2012.

Wender, I., Reactions of Synthesis gas, Fuel Processing Technology 48 (I 996) 189-297.

Qualifications

A qualified team has been put together to manage and conduct the proposed work. Blaise Energy

has had extensive experience with converting flare gas into electricity and has received NDIC support on

previous and current projects. Below are short resumes of the key participants in the proposed project.

Page 13: Oil and Gas Research Program

Project Manager – Dr. Steven A. Benson

Dr. Steve Benson, Chair of Petroleum Engineering, Director Institute for Energy Studies and Professor of

Chemical Engineering in the College of Engineering and Mines at the University of North Dakota, has

more than 25 years of experience in fuel and product production and the behavior of fuels in energy

conversion systems. Steve’s principal areas of interest and expertise include: 1) educating the next

generation of energy experts; and 2) performing research and developing technologies to improve the

performance of fuel recovery/development, energy conversion, carbon product manufacturing, and

pollution control systems. Prior to his current position, Steve held positions of Senior Research Manager

and Associate Director for Research at the Energy & Environmental Research Center. He was

responsible for leading a group of 30 highly specialized chemical, mechanical, geological, and civil

engineers along with physical and chemical scientists whose aim was to solve problems associated with

the performance and reliability of combustion and gasification systems for clients worldwide. Steve has a

B.S. in Chemistry from Minnesota State University (Moorhead) and a Ph.D. in Fuel Science from the

Pennsylvania State University. He has authored and co-authored over 200 publications.

Co-Project Manager – Dr. Nicholas Lentz

Dr. Nicholas Lentz, Associate Director for Energy Technology Applications Institute for Energy Studies,

has more than 5 years of experience in the identification and development of new analytical methods for

the advancement of elemental and small molecule analysis in a wide range of matrices including coal and

coal by-products, CO2 capture solutions, oil and gas fuels; analysis for combustion flue gas, syngas, fuel

oil, and biowaste; and experimental design and analysis related to control technologies to remove mercury

and other elements from combustion and gasification systems. Prior to his current position, Dr. Lentz was

a Center for Air Toxic Metals (CATM) Program Area Manager and Research Scientist at the Energy &

Environmental Research Center where he was responsible for managing a portfolio of measurement based

research projects in the Analytical Measurement Area of CATM as well as experimental design and

analysis related control technologies to remove mercury, trace metals, and halogens from combustion and

gasification systems. Dr. Lentz has a B.S. in Chemistry from Bemidji State University and Ph.D. in

Analytical Chemistry from Iowa State University. He has authored and co-authored numerous

publications.

Project Engineer – Mr. Charles Thumbi

Charles Thumbi, Research Engineer within the Institute of Energy Studies at the University of North

Dakota has 5 years of experience in the areas of process modeling, process design and development, and

performing R&D on energy conversion systems as well as emission control technologies. Mr. Thumbi’s

areas of interest and expertise include: 1) Process design; and 2) Process and product development

through collaborative research. Prior to his current position, Charles was a process engineer with Arkema

Inc. where he was responsible for process optimization and debottlenecking to improve performance and

reliability, process development and product design, capital project management, implementation of

energy and environmental control strategies and plans in energy savings and pollution prevention efforts,

as well as participation in safety related activities related to manufacturing processes. Charles has a BSc.

in Chemical Engineering from The University of Minnesota as well as a MSc in Chemical Engineering

from the University of North Dakota.

Project Engineer – Mr. Daniel Laudal

Dan Laudal is a Research Engineer for the Institute for Energy Studies at the University of North Dakota.

Mr. Laudal received his B.S. in Chemical Engineering from UND in 2006. His principal areas of

Page 14: Oil and Gas Research Program

expertise include design and operation of bench and pilot scale equipment for the conversion of various

types of fuels as well as gas cleanup technologies including warm-gas-cleanup and carbon capture. Prior

to his position at the IES, Mr. Laudal spent 4 years as a Research Engineer at the Energy and

Environmental Research Center at UND where his work focused on design and operation of advanced

process systems including several types of gasification and combustion systems. Mr. Laudal also spent 2

years in Williston, ND as a Well Services Field Engineer for Schlumberger Oil Field Services, where he

focused on well cementing operations in the Bakken Formation.

Project Engineer – Mr. Harry Feilen

Harry Feilen, Engineer, Institute for Energy Studies. Mr. Feilen has more than 20 years of experience

welding, fabricating, and building everything for lab scale size projects to full size buildings. Mr.

Feilen’s principal areas of interest include 1) developing himself and the next generation to the level of

energy experts, 2) performing research and developing technologies to improve the performance of fuel

recovery/development, energy conversion, carbon product manufacturing, and pollution control systems,

and 3) advancing his education to the next level. Prior to his current position, Mr. Feilen was a student

employee for the Chemical Engineering Department at UND where he applied his experience and

knowledge to facilitate the building, operating, and improving of the experiments for several graduate

students. Mr. Feilen also was a T.A. for the Chemistry Department at UND and taught Chemistry 121

Lab. Mr. Feilen is a former United States Marine (8 years of active duty) and a Gulf War Veteran. He has

a B.S. in Management from the University of Mary.

MANAGEMENT

The overall project management structure is illustrated in Figure 3. Dr. Benson and Dr. Lentz will

oversee the project and work with project sponsors to plan and conduct the project to meet all milestones

and scheduled completion dates. Project meetings and conference calls will be held on a weekly basis to

review project timelines, upcoming milestones/deliverables, costs and challenges associated with the

completion of the projects. Microsoft Project management tools will be utilized. Project review meetings

with sponsors will also be held on a quarterly basis to ensure communication and discussion of

accomplishments, plans and management of project risks. Meetings with industry co-sponsors will also

occur to update them on technical progress and seek input on commercial scale-up and applicability. The

milestones for the project are listed in Table 1. Each milestone will be evaluated during the course of the

project.

Figure 3. Project Management Structure.

Page 15: Oil and Gas Research Program

Table 1. Milestones and verification methods.

TIMETABLE

A schedule for the polygeneration project is listed in Table 2. The project has a three year duration with

construction of the pilot-scale system commencing during the first quarter of 2013. Additional projects

will be conducted and identified as they become available/identified and will be added to the CGU

research portfolio.

Table 2. Gantt Chart for the Polygeneration Project

BUDGET

Task Title/Description

Planned

Completion Date

Actual

Completion

Date Verification Method

1 Submit Project Management Plan 9/1/2012 Project Management Plan file

1 Complete Kick-off Meeting 9/15/2012 Briefing Document & Meeting Results

2 Integrated Concept Design

11/29/2012

Topical Report file

3 Complete Initial Technical and

Economic Feasibility Study 11/30/2012 Topical Report file

4 Prototype Process Design - Down-select optimum technology

1/31/2013 Results reported in the quarterly report

5 Prototype Process Procurement and

Construction – Complete construction 7/31/2013 Results reported in the quarterly report

6 Initial Operation of Prototype in Laboratory

8/31/2013 Results reported in the quarterly report

7 Field testing Prototype 12/31/2014 Briefing Document &Meeting Results

8 Final Process Assessment 8/31/15 Final Report

1 Quarterly/Annual report Each quarter/year Quarterly/Annual Report files

Page 16: Oil and Gas Research Program

The project budget is summarized in Table 3. The project currently has cost share support from Blaise

Energy as summarized in the attached letter of support. We also have support from the Department of

Commerce for co-funding for the project shown in the ND COE column.

Table 3. Project budget summary.

CONFIDENTIAL INFORMATION

No confidential information is present in the proposal.

PATENTS/RIGHTS TO TECHNICAL DATA

Blaise Energy has patents pending on equipment configurations, processes, and methods for the

transformation of flared natural gas into electricity.

STATUS OF ONGOING PROJECTS (IF ANY)

The North Dakota Industrial Commission is currently co-funding along with the US DOE, ALLETE, BNI

and SaskPower a CO2 separation and capture project called CACHYSTM

. The three year project is at the

end of the first year and the project has met or exceeded expectations.

The ND Industrial Commission is co-funding a project along with Great Northern Properties to examine

the feasibility of Underground Coal Gasification for deep lignite seams. The two year project is in the

process of being initiated.

The ND Industrial Commission is co-funding a project with Blaise Energy to determine the economic

viability of electrical generation into the grid from flare gas.

Affidavit of Tax Liability

The University of North Dakota does not have any outstanding tax liabilities with the State of North

Dakota.

Project Associated Expense

NDIC's

Share ND COE

Other

Project

Sponsor's

Other

Project

Sponsor's Total Project

Salary 178,573 180,468 359,041

Fringe Benefits 63,969 59,903 123,872

Travel 9,000 12,500 21,500

Phone 300 300 600

Postage 300 300 600

Office Supplies 1,200 1,350 2,550

Copies/Duplicating 600 679 1,279

Natural Gas/Site Support 0 0 500,000 500,000

Supplies 5,000 37,500 42,500

Operating Fees & Services 7,000 7,000 14,000

Subcontracts 260,000 260,000

Equipment 333,000 1,240,000 1,573,000

F&A (overhead) 101,058 101,058

Total 700,000 300,000 1,500,000 500,000 3,000,000

Page 17: Oil and Gas Research Program
Page 18: Oil and Gas Research Program

Budget Summary

Salaries-Faculty: Salary of $58,560 is included for UND faculty working on research as described in the

scope of work. A 5% annual increase in base salary is included in the salary total over the three year

project. The funds requested may include summer salaries and/or academic year salaries.

Salaries-Regular: Salary of $114,665 is included for UND administrative staff, research engineers, or

engineer. A 5% annual increase in base salary is included in the salary total over the three year project.

UND administrative staff will assist in setting up travel, manage the accounts and maintain the budget.

Two research engineers and an engineer will work on research and related tasks described in the scope of

work.

Salaries-Other: Salary of $5,348 is included for Student Lab Assistant to assist and gain experience

working on a research project. A 5% annual increase in base salary is included in the salary total over

the three year project.

Fringe Benefits: are estimated at 30% of salary of UND faculty, 40% for UND staff, and 10% for other

employees. Amounts shown for fringes are estimates determined by historical data and provided for

proposal evaluation purposes only. Actual fringe benefit costs will be charged to the grant according to

each employee’s actual benefits.

Travel: totaling $9,000 will include expenses to travel on project related trips including meeting with the

NDIC Oil and Gas Research Division, travel to meet with Blaise Energy-cost share partner, travel to the

Western part of ND to conduct research and testing as describe in the scope.

Office Supplies, Phone, Postage, Duplicating: totaling $2,400 are included to be used over the course of

the project and may include items such as pens, pencils, paper clips, printer paper and toner cartridges,

notebooks, post-it notes, computer discs, presentation materials, duplicating charges, and other

miscellaneous items required to complete the project.

Lab Supplies/Operating Fees and Services: totaling $12,000 is included for related supplies required to

complete the scope of work and may include cost for safety equipment required to perform the scope of

work as described in the proposal.

Equipment: totaling $1,233,000 is included for the purchase of major equipment related to this project.

Indirect Costs: The indirect cost rate of 38% included in this proposal is the federally approved rate for

the University of North Dakota. Indirect costs are calculated based on the Modified Total Direct Costs

(MTDC), defined as the Total Direct Costs of the project less individual items of equipment greater than

$5000, subcontracts in excess of the first $25,000 for each award, and tuition remission. Indirect costs are

an unallowable expense on North Dakota Center of Excellence research dollars.