Page 1: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

The better the quest ion. The better the answer.The better the world works.

Oil and Gas Megaprojects Axel Preiss, EY

ÖGEW/DGMK Herbsttagung 2015 Vienna, 19. November 2015

The better the quest ion. The better the answer.The better the world works.

Page 2: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

The better the quest ion. The better the answer.The better the world works.

Are Oil and Gas Megaproject overruns of more than US$500 billion possible?

ÖGEW/DGMK Herbsttagung 2015 Vienna, 19. November 2015

The better the quest ion. The better the answer.The better the world works.

Vorführender
Präsentationsnotizen
Picture emphasis on need to rethink how things are done, innovation, etc.
Page 3: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

The better the quest ion. The better the answer.The better the world works.

EY’s Global Oil & Gas Capability: Capital Projects

Introduction

The better the quest ion. The better the answer.The better the world works.

Page 4: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

Page 4 ÖGEW/DGMK Herbsttagung 2015

EY at a glance

Our Purpose: Building a better working world We are committed to building a better working world – one with increased trust and confidence in business, sustainable growth, development of talent in all its forms, and greater collaboration.

1,400+ 96 Houston office

10,000 Global oil and gas professionals

Global Oil & Gas Centers

We serve all of the Top 10 oil and gas companies on the Forbes Global 2000 list, auditing 26% of them.

years of service

professionals

15

Market leadership

Industry leadership

Page 5: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

Page 5 ÖGEW/DGMK Herbsttagung 2015

EY and Capital Projects

EY within Capital Projects

• We support multiple companies through their capital projects; from business case through development and execution, into operations

• We deliver a broad range of services related to capital projects – Spanning from independent project reviews on behalf of oil companies, to supporting contractors in delivering on time and budget

• We have a global group of 400 experts focusing on Capital Projects within oil and gas

Page 6: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

Page 6 ÖGEW/DGMK Herbsttagung 2015

Spotlight on Oil and Gas Megaprojects Thought Leadership - Megaprojects Series EY and O&G megaprojects

• Spotlight on oil and gas megaprojects kicks off a series that explores capital projects in oil and gas, reviews performance trends and outlines the root causes behind industry wide poor delivery performance.

Vorführender
Präsentationsnotizen
EY studied 365 megaprojects with proposed capital investment of US$1b or greater in the upstream, liquefied natural gas (LNG), pipeline and refining sectors. These included projects that have been proposed but haven’t reached FID as well as those that have passed final investment decision (FID) but have not begun operations. The projects were evaluated on two criteria - Cost and Time. Of the 365 projects reviewed, cost data was available for 205 and time data for 242.
Page 7: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

Page 7 ÖGEW/DGMK Herbsttagung 2015

These projects comprise a sizable Investment…

In its 2014 World Energy Investment Outlook, the International Energy Agency (IEA) estimates a cumulative investment of US$22.4t in the global oil and gas sector (2014-35).

Our own research into current capital projects found 365 projects currently in development & expected to go into production prior to 2020 (projects over US$1bn)…combined total spend is forecast at some US$2.6t

Page 8: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

The better the quest ion. The better the answer.The better the world works.

Built it, paid it. Delayed it? Paid more?

EY’s Spotlight on Megaprojects Report

The better the quest ion. The better the answer.The better the world works.

Page 9: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

Page 9 ÖGEW/DGMK Herbsttagung 2015

Megaprojects Report…the Numbers Don’t Lie Our Research shows that project performance (to budget & schedule) is consistently poor!

Page 10: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

Page 10 ÖGEW/DGMK Herbsttagung 2015

Project Performance - Results By Region

Cost & schedule overruns were common in all industry segments & regions. Overall, 64% of the projects are facing cost overruns and 73% report schedule delays.

Current project estimated completion costs - Av. 59% above the initial estimate. In absolute terms, the cumulative cost of these projects has increased to US$1.7t from an original estimate of US$1.2t.

North America

58% of projects face cost overruns

55% of projects face schedule delays

51% is the average project budget overrun

Latin America

57% of projects face cost overruns

71% of projects face schedule delays

102% is the average project budget overrun

Africa

67% of projects face cost overruns

82% of projects face schedule delays

51% is the average project budget overrun

Europe

53% of projects face cost overruns

74% of projects face schedule delays

57% is the average project budget overrun

Middle East

89% of projects face cost overruns

87% of projects face schedule delays

68% is the average project budget overrun

Asia-Pacific

68% of projects face cost overruns

80% of projects face schedule delays

57% is the average project budget overrun

Page 11: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

Page 11 ÖGEW/DGMK Herbsttagung 2015

What about post FID performance? Performance post FID is similarly poor despite completion being some way off in the distance.

Page 12: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

Page 12 ÖGEW/DGMK Herbsttagung 2015

Root causes of cost overruns and delays

Industry research suggests that non-technical issues are responsible for the majority of the overruns.

Poor Procurement of Contractors

Poor Contractor Management

Portfolio & Project Commercial Context

Project Development

Project Delivery Regulatory Challenges

Geopolitical Challenges

JV set up & management

Poor Portfolio Management & Changing Risk

Appetite

Ineffective Project Management

HSE Risk & Local Content

Geopolitical & Security Issues

Access to Funding

Inadequate Planning

Regulatory Delay & Policy Uncertainty

Financial & Supplier Market

Uncertainty

Aggressive Estimates &

Optimism Bias

Human Capital Deficit

Inadequate Infrastructure

Civil & Workforce Disruption

External Factors Internal Factors

Page 13: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

The better the quest ion. The better the answer.The better the world works.

How do other megaproject challenges weigh in?

Megaprojects Series Continued

The better the quest ion. The better the answer.The better the world works.

Page 14: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

Page 14 ÖGEW/DGMK Herbsttagung 2015

The Megaprojects Series - Moving forward

• Navigating Geopolitics - Released

• Building Portfolios for Success - Released

• JV relationships in Megaprojects - Released

• Megaproject Planning and Sanction

• Megaproject Delivery

• Regulatory Challenges for Megaprojects

• Spotlight on Megaprojects - Data Update and Review

Articles in the series:

Vorführender
Präsentationsnotizen
Removed “future” from “Future articles in the series” as ‘released’ indicates that the others are to come
Page 15: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

Page 15 ÖGEW/DGMK Herbsttagung 2015

Oil & Gas Megaprojects Joint Ventures Use of JV’s to drive growth and minimize risk We evaluated our original Megaprojects database to analyse JV cost and schedule performance across a subset of projects where ownership structure was clearly identifiable: 205 JV projects (US$ 1.58t) and 128 Non-JV projects (US$ 0.75t).

We assessed the key challenges facing organisations and management teams in the current environment.

Page 16: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

Page 16 ÖGEW/DGMK Herbsttagung 2015

JVs can provide the benefits of collaboration and risk sharing (a key for the large projects in the Oil & Gas industry) while maintaining corporate independence and avoiding the economic and political risk associated with a merger or acquisition.

Oil & Gas Megaprojects Joint Ventures Why are JV’s increasingly common in O&G?

Capital intensity

Risk mitigation

Access to technology

Access to resources

Supply chain optimization

Market positioning and scale

Regulatory requirements

Political sensitivity

Vorführender
Präsentationsnotizen
Cut text from graphics
Page 17: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

Page 17 ÖGEW/DGMK Herbsttagung 2015

Oil & Gas Megaprojects Joint Ventures Performance Challenges Total

JVs

Total

Non-JVs

Vorführender
Präsentationsnotizen
Renewed graphics
Page 18: Oil and Gas Megaprojects Axel Preiss, EY - Service - …...The better the question. The better the an swer. The better the world works. Oil and Gas Megaprojects Axel Preiss, EY ÖGEW/DGMK

Page 18 ÖGEW/DGMK Herbsttagung 2015

Vielen Dank für Ihre Aufmerksamkeit!

Q&A

Vorführender
Präsentationsnotizen