Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
OGFC & SMA Use in Georgia
Will Rogers
Technical Director
Georgia Asphalt Pavement Association
SMA & OGFC in Georgia
• Background
• SMA: Aggregate Requirements
• SMA: Design
• OGFC: Design
• Open-Graded Mix Comparison
• Open-Graded Mix: Current Policy
• Interesting Project
• SMA Family Feud
Background
• (Almost) All HMA Interstates in GA are SMA + Open-Graded Mix
– I-185 FM Columbus, GA to I-85 is 12.5mm SP + OGFC
• Open-Graded Mixes
– Began using w/o Polymers (Pop Corn Mix)
– Added Polymers after PG Grading System
– Began Using Permeable European Mix (PEM)
– Went Back to OGFC gradation
Background
• SMA:
– Started Using after NAPA/FHWA Scanning Tour of Europe in Mid/Late ‘90’s.
– Typically use 12.5mm SMA, but have used 19mm and 9.5mm NMAS
– Mineral Filler: Marble Dust -> Fly Ash -> ?
– Not Typically a Wearing Surface
SMA Aggregate Requirements
General Aggregate Requirements
General Aggregate Requirements
• Producing SMA Stone to Meet GDOT’s F&A Requirements…– VERY Difficult
– Few Quarries Could Meet Spec
– Quarry had to Shut Down All Other Production
– Generated Massive Amounts of Waste
– Stone was VERY Expensive
– Long Hauls
• Most Quarries HMA Stone Meets F&A According to AASHTO Caliper
General Aggregate Requirements
General Aggregate Requirements
• Before Notice to Contractors (402-3600):
– 2013: $107.02 per TN
– 2014: $99.12 per TN
– 2015: $127.95 per TN
• After Notice to Contractors (402-3600):
– 2016: $83.95 per TN
– 2017: $127.35 per TN
SMA Design
• Compactive Effort
– 35 Gyration OR 50 Blow Marshall
• RAP: Max 15%
• Apply COAC
• Fiber Stabilizers
– Mineral Fibers OR
– Cellulose Fibers
• Mineral Filler (QPL 81)
• PG 76-22
Mineral Filler Requirements
SMA Design
• Mineral Fillers
– Fly Ash**
– Marble Dust
– Carmeuse was Working on a Product from their Lime Production
SMA: I-520 in Augusta
SMA: I-520 in Augusta
SMA: I-520 in Augusta
SMA & OGFC in Georgia
• Background
• SMA: Aggregate Requirements
• SMA: Design
• OGFC: Design
• Open-Graded Mix Comparison
• Open-Graded Mix: Current Policy
• Interesting Project
• SMA Family Feud
OGFC: Design
OGFC: Design
• All Open-Graded Mixes Designed by GDOT per GDT 1141. Surface Capacity Method (KC Factor)
2. Modified Marshall Method (Stability & Flow)
3. Pyrex Bowl Method (Visual)
– Average AC Contents from 3 Methods• Modify by Field Experience if Needed
– Boil Test
• In Reality: #3 + Cantabro (typ. 15-19%, 20% Max)
Open-Graded Mix Comparison
OGFC
• Finer
• Less Void Space
• Easier to Clog
• Placed 0.75” Thick
• More Durable
PEM
• Coarser
• More Void Space
• Harder to Clog
• Placed 1.25” Thick
• Susceptible to Truck Rim Cuts
• Susceptible to Freezing Water
Open-Graded Mix Comparison
SCDOT
• Tack Application (Emulsion)– 0.05 – 0.15 Gal/SY
– (Residual): 0.0325 – 0.0975
– Min. 0.10 Gal/SY per Best Practices Document
• Placed on: Surface A
GDOT
• Tack Application (PG)– 0.06 – 0.08 Gal/SY
• Placed on: SMA*
Open-Graded Mixes: Current Policy
• PEM Has Been Removed from Active Use
• OGFC Being Placed @ 100 lbs/SY
• OGFC Occasionally Being Further Fined Up to Enhance Performance
Interesting Projects: I-95 in Camden County
• GDOT Covered CRCP in 1998-1999
• 19mm SMA + 12.5mm SMA + 90 lbs/SY OGFC
• Micro-Mill & Inlay let in December 2017
Interesting Project: I-95 in Camden County
Interesting Project: I-95 in Camden County
Interesting Project: I-95 in Camden County
SMA Family Feud
• 6 GA Contractors Surveyed on Headaches & Tips for SMA
• 4 Contractors Responded
SMA Family Feud: Headaches (4)
(3) #7 Stone Consistency
(3) Mineral Filler
(3) Sticky / Build-Up, Poor Flow
(2) Release Agent
SMA Family Feud: Tips & Tricks (3)
(2) Keep Rollers Tight to Paver
(3) TEMPERATURE! – Screed, Plant, Rolling
(2) Aggregate! – Mult. Bins, Partner w/ Supplier
Contractor 1• Consistency of aggregate is a MUST• Use mult. Bins for aggregates to blend consistency back
into the gradation blend• Coarser material works better (esp. the #7’s)• More material does better (coarse #7’s allow for the use of
89’s)• Hotter the better:
– Handling Issues– Locking down the MTV– Shadowing/Hot Lapping– Compaction
• Back Roller 150 – 180F. It will be a factor in compaction• In cooler temps, keep Breakdown Roller close to screed.
Hotter temps., may back off.
Contractor 1
• Consider Mineral Filler Source– Higher Density Fly Ash (Need higher % of mineral filler due
to compaction issues)
– Lower Density Fly Ash (Can replace some with rock dust)
– Marble Dust (need higher % due to compaction issues)
• Need depth for Compaction (Issues @ 1.5” & Below. 2” yields much better results)
• Finer Designs tend to be Easier:– Work with & Manage
– Improved Permeability in Lab & Field
Contractor 2
• Dealing w/ Fly Ash. The supply & hauling logistics & storage issues w/o finding a Storage Pig to Rent
• Aggregate Supply
– Variability!
• Boy Scout Motto: “BE PREPARED”
Contractor 3
• Doesn’t come out of the Trucks into the Paver very well
• Need a Clean-Out Area near Laydown Operations for Trucks
• Not Using Release Agent Correctly
• Plant Temps Must be Higher than Normal HMA
• Heated Screed on Paver to Help with Laydown
• Keeping Rollers up Tight with Laydown to get better Compaction & Rideability
Contractor 4
• Sensitivity to Temp. Becomes stiff quickly.
• Can’t Use Rubber Tire Roller
• Sticky & Often Build-Up in Trucks & on Tools
• Require Continuous Operation & Head of Material
• Ash & Lime Require 2 Silos for Fillers
• VERY Consistent #7 Stone
• Feed MTV Slowly when Steel is Cool
• 2 Breakdowns in Cooler Weather
Contractor 4
• Partner w/ Agg. Supplier
• Increase Release Agent: 5:1 from 15:1
• Set Screed Strike-Off higher or will Build Up & Tear Mat
• No More Hand Work than NECESSARY
• Don’t Run Buggy Low
• Fine Mastic can Build Up & Break Loose -> Fatty Blemishes in Mat
Questions?