Upload
phamhanh
View
268
Download
7
Embed Size (px)
Citation preview
OFFSHORE CONSTRUCTION SPECIALISTS
TOPSIDE FLOATOVER PRE-QUALIFICATION DOCUMENT
TOPSIDE FLOATOVER PRE-QUALIFICATION DOCUMENT
Offshore Construction Specialists (OCS)
36 Kian Teck Road Singapore 628781 Tel: +65 6898-0210 Fax: +65 6898-0209
Web: http://www.offshore-ocs.com
Contact Information
Contact: Company Position: Email Address:
Keith Jackson Managing and Technical Director [email protected]
Seto Jian Operations Manager [email protected]
William Wijaya Project Manager [email protected]
Loke Kah Poh Project Manager [email protected]
Rakul Remanan Engineering Manager [email protected]
Alastair Wong Construction & Equipment Manager Fery Wijaya
[email protected] Construction Manager
Henry Chuy [email protected]
Subcontracts & Procurement Manager
OFFSHORE CONSTRUCTION SPECIALISTS
TOPSIDE FLOATOVER
PRE-QUALIFICATION DOCUMENT
PRE QUALIFICATION Offshore Construction Specialists Pte Ltd. Page 2 of 15
TABLE OF CONTENTS 1.0 INTRODUCTION .................................................................................................................................... 3 1.1 TOPSIDE FLOATOVER EXPERIENCE ................................................................................................. 4
2.0 ORGANISATION CHART ...................................................................................................................... 5
3.0 TYPICAL FLOAOVER BARGE ORGANISATION CHART .................................................................... 7
4.0 PLANNING AND EXECUTION .............................................................................................................. 9
5.0 OCS CLIENT BASE ............................................................................................................................. 11
6.0 TOPSIDE FLOATOVER - TRACK RECORD ...................................................................................... 12
7.0 ISO CERTIFICATION........................................................................................................................... 13
8.0 NATA CERTIFICATION ....................................................................................................................... 15
OFFSHORE CONSTRUCTION SPECIALISTS
TOPSIDE FLOATOVER
PRE-QUALIFICATION DOCUMENT
PRE QUALIFICATION Offshore Construction Specialists Pte Ltd. Page 3 of 15
1.0 INTRODUCTION
Offshore Construction Specialists (OCS) was formed in 2007 from a core group of experienced marine construction engineers with an extensive track record working with major contractors.
The company provides construction management, engineering and strategic support equipment services primarily to the offshore oil and gas sector focusing on the installation of pipelines, platforms, tanker moorings and related facilities. In addition to engineering, OCS also provides turnkey services for pipeline burial, pipeline pre-commissioning & drying, flexible flow line installation and umbilical installation on a subcontract basis to marine contractors.
The company has grown steadily since incorporation and now employs 60 personnel of whom over 36 are civil/structural and mechanical engineers along with an equipment group comprising of mechanics and technicians to operate in-house developed equipment. The engineers and technician work hand in hand to ensure all projects are properly engineered and operationally practical
Our personnel are experienced and all came from the same background as the main marine contractor. We help the major marine contractor plan the work such that the topside float over activity has the least impact on the vessel construction operations. We are proactive in highlighting potential issues and ensuring both parties win. OCS understands the importance of getting the job done safely and efficiently to minimise operational costs for all concerned.
OFFSHORE CONSTRUCTION SPECIALISTS
TOPSIDE FLOATOVER
PRE-QUALIFICATION DOCUMENT
PRE QUALIFICATION Offshore Construction Specialists Pte Ltd. Page 4 of 15
1.1 TOPSIDE FLOATOVER EXPERIENCE
OCS personnel have completed the following major jacket Launch projects for different customers;
No. Client Operator Project Descrip. Jacket Weight
(mT)
Floatover Barge Used
Year Comp
1 Shell
Philippines
Shell Philippines Malampaya CPP 11,000 H-541 2001
2 PTTEP PTTEP (Thailand) Arthit CPP 18,000 Int650 2007
3 CLJOC CLJOC (Vietnam) SuTuVang CPP 16,500 Int650 2008
4
Conoco Philips, Indones
ia
Conoco Philips,
Indonesia North Belut CPP 14,000 S45 2009
5 Caspian Hydro LUKOIL Filanovsky
Stage 2 IRP-2 8500 TMB On Going
6 Caspian Hydro LUKOIL Filanovsky
Stage 2 LQP-2 1500 TMB On Going
OCS is equipped to handle large projects or discrete project elements depending on the specific needs of the customer. During the preparation for topside float over or any offshore work the safety of personnel, equipment and environment plays a vital role in the success of a project and as such, HAZID’s shall be conducted prior to any operations. These meetings are attended by key engineers and supervisors and all potential risks are identified and mitigation measures put in place to ensure they are as low as reasonably practicable.
OFFSHORE CONSTRUCTION SPECIALISTS
TOPSIDE FLOATOVER
PRE-QUALIFICATION DOCUMENT
PRE QUALIFICATION Offshore Construction Specialists Pte Ltd. Page 5 of 15
2.0 ORGANIS ATION CHART
KEY PERSONNEL CONTACTS Keith Jackson Managing and Technical Director [email protected] Seto Jian Operations Manager [email protected] William Wijaya Project Manager [email protected] Loke Kah Poh Project Manager [email protected] Rakul Remanan Engineering Manager [email protected] Alastair Wong Construction & Equipment Manager Fery Wijaya
[email protected] Construction Manager
Henry Chuy [email protected]
Subcontracts & Procurement Manager [email protected]
Refer to the next page for OCS Organisation Chart
PRE QUALIFICATION Offshore Construction Specialists Pte Ltd. Page 6 of 15
Updated as 06 Apr 2017
WILLIAM WIJAYAPROJECT MANAGER
OCS MIDDLE EAST &
NORTH AFRICA
DLB-01 MANAGEMENT OPERATIONS / HSE
PROJECT &
CONSTRUCTION MANAGEMENT
PROCUREMENT &
SUBCONTRACTSENGINEERING OCS UK
OCS DESIGN PVT LTD INDIA
OCS USAACCOUNTS
& ADMINSTRATION
NATHAN WILLIAMSCOUNTRY MANAGER
SETO JIAN OPERATIONS & HSE
MANAGER
KP LOKEPROJECT MANAGER
HENRY CHUY SUBCONTRACT & PROCUREMENT
MANAGER
RAKUL REMANANENGINEERING
MANAGER
WILLIAM HUNTCOUNTRY MANAGER
NG BEE KIMACCOUNTS
HR & ADMIN LEAD
LELAND TAYLOR COUNTRY MANAGER
VIVIANAKEVIN KOH
BUYER
ALASTAIR WONGCONSTRUCTION &
EQUIPMENT MANAGER
FERY WIJAYACONSTRUCTION
MANAGER
CHARLES TANSENIOR
BUYER/EXPEDITOR
FERLINDA LOW Buyer ADMINISTRATION ACCOUNTS
MELVIN TANIT ENGINEER
TRACY TEEPROJECT SECRETARY
& DOCUMENT
CONTROLLER
SAMI CHEE HR ADMINISTRATOR
MONICA ZHANG ACCOUNTANT
GILBERT GREJALDOACCOUNT EXECUTIVE
LEOW FEE PENG ACCOUNT ASSISTANT
ENGINEERING DRAFTING
HERYANTHOLEAD NAVAL ARCHITECT
PRAVIN THORATLEAD STRUCTURAL
ENGINEER
OCS DESIGN PVT LTD, INDIA
UDAY SARATHYLEAD PIPELINE
ENGINEER
CHAYUTRA LEAD DRAFTING
ARYO PRAKOSOLAWRENCE S.C
SENIOR DRAFTSMANS
VINOTH KUMARKHAING ZAR AUNG
DRAFTSMANS
TAUFAN SAINUL
NAVAL ARCHITECTS
SUDHAKAR RADITYA ANDY
SENIOR STRUCTURAL ENGINEERS
MOHAN CHANDSENIOR PIPELINE
ENGINEER
TUKARAM SENIOR DRAFTSMAN
SAVOYRAHUL
NAVAL ARCHITECT
KUNAL KHADKESENIOR STRUCTURAL
ENIGINEER
STRATEGIC EQUIPMENT TEAM
FIELD CONSTRUCTION
SUPEVISION TEAMOPERATIONS
SAYED DEDI MPRE-COM ENGINEER
MYO MYINT THUEQUIPMENT ENGINEER
CHINNA SENIOR MACHINIST
ZAKARIABUDIMAN
KRISBEL MOHD SLAMET
TECHNICIANS / MECHANICS
WILLSON HALLJAMES C
FIELD SUPERINTENDENT
JAMIE JLEON COAD
DAVID WOODFIELD FOREMENS
SETTHA Y IVAN CHAIADI CAHYAOPERATIONS ENGINEERS
AARON LIAN ZHONG ZHIYUAN
SENIOR FIELDENGINEERS
CHIA WIN LOONGDAVID SHAWMOHD HAZIQWANG ZHENG
FIELDENGINEERS
Singapore Head Office
Middle East & North Africa Office
India Office
UK Office
USA Office
KEITH JACKSONMANAGING DIRECTOR
OCS AUSTRALIA
Australia Office
LEGEND
OCS ORGANISATION CHART
KEITH JACKSONMANAGING & TECHNICAL DIRECTOR
LENI TALAVERAADMIN ASSISTANT
& RECEPTIONIST
RONIGROUTING
SUPERVISOR
PRIYAZIA AI AKBARSTRUCTURAL ENGINEERS
SADHASIVAMPANKAJ
STRUCTURAL ENIGINEERS
KARUN DASPIPELINE ENGINEER
OFFSHORE CONSTRUCTION SPECIALISTS
TOPSIDE FLOATOVER
PRE-QUALIFICATION DOCUMENT
PRE QUALIFICATION Offshore Construction Specialists Pte Ltd. Page 7 of 15
3.0 TYPICAL FLOAOVER BARGE ORGANIS ATION CHART
Figure 3.1 Typical Floatover PMT/Engineering
Figure 3.2 Typical Float over barge management
Typically, OCS personnel requirements for 24 hour operations specifically for launching activity are as follows: • 1 x Floatover Superintendent • 1 x Floatover Foreman • 1 X Construction Manager • 1 x Operations Engineer • 1 x Snr Field Engineer
OFFSHORE CONSTRUCTION SPECIALISTS
TOPSIDE FLOATOVER
PRE-QUALIFICATION DOCUMENT
PRE QUALIFICATION Offshore Construction Specialists Pte Ltd. Page 8 of 15
• 1 x Field Engineers (optional to add if situation arises) All other support personnel and equipment are normally provided by main contractor. OCS can provide additional personnel as required. Where specifically required, OCS can provide an option for provision of the entire support/launch spread. Customer requirements for this option can be discussed on a case by case basis.
OFFSHORE CONSTRUCTION SPECIALISTS
TOPSIDE FLOATOVER
PRE-QUALIFICATION DOCUMENT
PRE QUALIFICATION Offshore Construction Specialists Pte Ltd. Page 9 of 15
4.0 PLANNING AND EXECUTION
OCS will cover the following scope areas during planning and execution of Topside Floatover projects.
4.1 Topside Scope
OCS will review the scope of work taking particular note of the following: • Topside weight, dimension and physical constraints • Topside Barge capabilities and constraints – loose or tight slot • Critical ballast system • Deck Support Frame integration with barge • Leg Mating Units (LMU) design (and coordinate with vendor) • LMU’s Elastomer testing program • Deck Support Units • Use of Sand jacks • Requirement for Quick recoverable system • Fendering design • Floatover Engineering (OCS shall perform this as it is an intergral part of the floatover) • Topside Transportation Engineering • Float Over equipment requirement/specification • Mooring requirements • Ballasting configurations. • Float over site verification/anchoring plans • Float Over Barge rig up plans • Execution methodology
4.2 Equipment Layout, preparation and Rig up
Based on a review of the scope of work and the other critical parameters listed in 4.1 above OCS will prepare a most appropriate float over layout for the work. In most cases these equipment are available and provided by main contractor which OCS will review their suitability and proposes checks and verification to ensure the serviceability of these equipment. Based on the topside float over equipment assessment, OCS will provide a layout of the float over equipment on the barge assigned by the client. In certain cases OCS can provide the float over barge/spread on which to base the required equipment for the float over operation. This layout will then be the basis for the float over barge rig up.
4.3 Equipment Testing
OCS will ensure that all float over support equipment (winches and mooring equipment including power packs, ballast system, power supply, cutting equipment, survey and motion
OFFSHORE CONSTRUCTION SPECIALISTS
TOPSIDE FLOATOVER
PRE-QUALIFICATION DOCUMENT
PRE QUALIFICATION Offshore Construction Specialists Pte Ltd. Page 10 of 15
monitoring system, etc) is fully tested before leaving the rig up yard. Client representatives will be invited to witness the testing programme.
4.4 Load out OCS personnel will be present during topside load out operation to ensure that all aspect of the load out that affects the float over will be monitored and any problem observed can be rectified immediately and escalation of issues impacting the float over operations at site will be avoided.
4.5 Execution Procedures
OCS will provide project specific execution procedures for every project which address all elements of the Topside float over project. These procedures must be approved by the client prior to offshore operation. OCS will ensure that the procedures address all constraints posed by specific project site conditions.
4.6 HAZID
Specific HAZID and risk identification sessions will be conducted to identify and propose mitigation measures for site hazards which may be posed by operations. This will be conducted as early as possible; otherwise, the latest to be conducted will be just before topside loadout.
4.7 Personnel
OCS will provide a team of qualified personnel to prepare and supervise the work at the rig up yard as well as float over execution as site. Key personnel will be the same for both who supervise the rig up and testing of the equipment on the float over barge and float over activity. The OCS typical float over management organization chart as shown in section 3.
OFFSHORE CONSTRUCTION SPECIALISTS
TOPSIDE FLOATOVER
PRE-QUALIFICATION DOCUMENT
PRE QUALIFICATION Offshore Construction Specialists Pte Ltd. Page 11 of 15
5.0 OCS CLIENT BASE
OCS has built up a significant customer base during four (8) years of operations. OCS past and present clients are listed below. References can be provided on request:
NO CLIENT NAME 1 Asia Petroleum Developments / Salamander Energy (Indonesia) 2 Bumi Amarda 3 Chevron (Thailand) 4 Clough Sapura JV (Australia) 5 DOF Subsea. 6 EMAS (Singapore) 7 Franklin Offshore (Singapore) 8 Galoc ( Philippines) 9 GFI (Thailand) 10 Global Industries (Malaysia)/Technip 11 Hako Offshore (Singapore) 12 Heerema (Netherlands) 13 HESS (Indonesia) 14 Kangean Energy (Indonesia) 15 Larsen & Toubro (Malaysia/ India) 16 M3 Energy (Malaysia) 17 McConnell Dowell CCC JV (Australia) 18 MRTS Engineering Ltd (Russia) 19 Newfield Peninsula Malaysia (Malaysia) 20 Nippon Steel (Indonesia) 21 NorCE (Singapore) 22 NuCoastal (Thailand) 23 Offshore Marine Contractors 24 Origin Energy (Australia) 25 PT Timas Suplindo (Indonesia) 26 Sapura Acergy (Malaysia) 27 Sarku (Malaysia) 28 Sea Drill (Singapore) 29 Star Petroleum (Indonesia) 30 Swiber (Singapore) 31 TLO Sapura Crest (Malaysia) 32 Vietsovpetro (VSP) (Vietnam)
OFFSHORE CONSTRUCTION SPECIALISTS
TOPSIDE FLOATOVER
PRE-QUALIFICATION DOCUMENT
PRE QUALIFICATION Offshore Construction Specialists Pte Ltd. Page 12 of 15
6.0 TOPSIDE FLOATOVER - TRACK RECORD Refer to attached.
EXPERIENCE LIST DATABASE
SUBJECT: TOPSIDE FLOATOVER (MALAMPAYA CPP TOPSIDE) via Heerema
Project Details:‐ The Malampaya field is located off the coast of Palawan Island in the Philippines. The Malampaya Project is a gas development project to deliver gas to supply power plants within the Philippines by early 2002. The wells are in 850 m water depth and will be produced to a production platform in approximately 42 to 44 m water depths (LAT). The platform is designed to separate the gas, condensate and saturated water to the required specifications for export and disposal. The development plan consists of eight (8) Malampaya subsea wells and two (2) Camago, all tied back via subsea production manifolds. The well fluids combine and flow via two (2) 16” x 33 km multiphase subsea flowlines to the platform. The Topside Facility will be supported on a Concrete Gravity Structure (CGS), which is also used to store the condensate.
Structure Information:‐ Topside Type: CPP 4‐legged Dimension: LxWxH 101m x 52m x 24m Jacket Weight: 11,000mT
(factored weight)
Water Depth:‐ 43m (LAT) Floatover barge:‐ H‐541
(160mx42mx10.7m) Supported on DSF: Yes
DSU (Elastomer) on DSF: No
LMU: Yes on CGS
Elastomer in LMU: Yes on CGS
Sand Jacks in LMU: Yes on CGS
Gap Type: Tight Slot with mating lines
Pictures:
Project Scope:‐ This scope was managed by OCS personnel prior to incorporation of OCS, to illustrate the individuals’ experience of the personnel involved. The scope was for the Transportation and installation of the Malampaya Topside by float over using the barge H541.The topside float over installation was completed in August 2001.
EXPERIENCE LIST DATABASE
SUBJECT: DECK FLOATOVER (ARTHIT APP Deck Floatover) PTTEP
Project Details:‐ PTT Exploration and Production Company Limited (PTTEP) in partnership with Chevron and MOECO developed the Arthit field located in the Gulf Of Thailand. The Arthit field lies 35 km due east of the existing Bongkot Field, approx. 625 km from Rayong Province, and 250 km northeast of the town of Songkhla, Thailand. The water depth is approx. 80 meters. The Arthit Field facilities comprises of:
The bridge‐linked Arthit Central Facilities, including the Arthit Process Platform (APP), the Arthit Quarters Platform (AQP), the Arthit Wellhead Platform‐1 (AWP‐1), and a flare platform;
Five (5) wellhead platforms (AWP‐2, AWP‐3, AWP‐4, AWP‐5 & AWP‐6);
Gathering pipelines connecting the remote wellhead platforms to APP;
A gas export pipeline to Arthit PLEM then to Erawan; and
A condensate export pipeline to Bongkot FSO2.
Structure Information:‐ Deck Type: 8‐legged deckDimension (LxBxH)m 75.5 x 65.9 x 55.3Deck Weight: 17,998 mT
(Factored weight) Water Depth:‐ 78.1 m (MSL)Floatover barge:‐ Intermac 650
(650’ x 170’ x 40’) Supported on DSF: Yes
DSU (Elastomer) on DSF: Yes
LMU : Yes
LMU and Elastomer: Yes on deck
Sand jacks in transition Yes (on jacket leg)
Gap Type Loose slot
Pictures:
Project Scope:‐ This scope was managed by OCS personnel prior to incorporation of OCS, to illustrate the individuals’ experience of the personnel involved. The project scope was for the transportation and installation of the APP Deck by Float Over utilizing the barge Intermac 650. The float over operation was completed on 2007
EXPERIENCE LIST DATABASE
SUBJECT: CPP TOPSIDE FLOATOVER (CuuLong STV CPP TOPSIDE) via J Ray McDermott
Project Details:‐ CuuLong Joint Operating Company (CLJOC) embarked on the development of the SuTuComplex located in about 53m water depth in Block 15‐1 offshore Vietnam. The SuTuVang Field consists of a Central Procession Platform with pipelines and tie‐in to the existing WHP‐A.
Structure Information:‐ Topside Type: CPP 8‐legged Dimension: LxWxH 68m x 80m x 40m Jacket Weight: 16500mT
(factored weight)
Water Depth:‐ 53 m (MSL) Floatover barge:‐ Intermac 650
(650’ x 170’ x 40’) Supported on DSF: Yes
DSU (Elastomer) on DSF: Yes (OKI)
LMU: Yes on jacket leg
Elastomer in LMU: Yes on jacket Leg
Sand Jacks in LMU: Yes on jacket Leg
Gap Type: Loose Slot
Pictures:
Project Scope:‐ This scope was managed by OCS personnel prior to incorporation of OCS, to illustrate the individuals’ experience of the personnel involved. The scope was for the installation for STV CPP complex which entails STV platform and associated pipeline using the construction barge DB30. The topside installation using float over was completed in August 2008.
EXPERIENCE LIST DATABASE
SUBJECT: DECK FLOATOVER (North Belut CPP Deck Floatover)
Project Details:‐ Conoco Phillips Indonesia (COPI) is undertaking the development of the North Belut Field, located in Block B of the Indonesian sector of the Natuna Sea. The North Belut field is located approximately 60km East North‐East of the Belanak FPSO installed on the Belanak Field. The North Belut development comprises of:
a) 1 Centre Processing Platform (North Belut Central Processing Platform (NBCPP))
b) 2 Wellhead Jackets and Platforms ‐ Wellhead Platform C (WHP‐C) and Wellhead Platform D (WHP‐D).
NBCPP will be an 8‐legged jacket platform, whilst WHP‐C and WHP‐D will be four piles 20‐slots platforms. WHP‐D will be connected with a bridge to NBCPP.
Structure Information:‐ Deck Type: 4‐legged deck Dimension 24m x 46.5m Deck Weight: 14,000 mT
(factored weight) Water Depth:‐ 54 m (MSL) Float over barge:‐ S45
(180.0m x 42.0m x 11.5m)
Pictures:
Project Scope:‐ OCS scope for this project was to second a Client Site Representative to Conoco Phillips Indonesia North Belut project to oversee the installation engineering, rig up, installation procedure preparation, site coordination/supervision for the CPP jacket and CPP Deck Installation. CPP Deck Floatover was completed in 2009
OFFSHORE CONSTRUCTION SPECIALISTS
TOPSIDE FLOATOVER
PRE-QUALIFICATION DOCUMENT
PRE QUALIFICATION Offshore Construction Specialists Pte Ltd. Page 13 of 15
7.0 ISO CERTIFICATION OCS is an ISO9001 (2008) certified company, with the certificate as below:-
OFFSHORE CONSTRUCTION SPECIALISTS
TOPSIDE FLOATOVER
PRE-QUALIFICATION DOCUMENT
PRE QUALIFICATION Offshore Construction Specialists Pte Ltd. Page 14 of 15