Office Maintenance

Embed Size (px)

Citation preview

  • 8/13/2019 Office Maintenance

    1/19

    DIVISION: NH Division, PWD, BAREILLY

    . At office / ( New N H No -30 ) BAREILLY

    1 2 3 5 6 7 8 9 10 11 12

    Dista

    Bareilly Lal Kuan 540 98 649.75 590.68 1130.68 1130.68 1130.68 f

    km93

    Bareilly Lal Kuan 600 98 649.75 590.68 1190.68 1190.68 1190.68 km03 Mini b

    Bareilly Lal Kuan 600 98 649.75 590.68 1190.68 1190.68 1190.68 on NH

    Bareilly Lal Kuan 600 98 649.75 590.68 1190.68 1190.68 1190.68 Total

    Cost O

    Bareilly Lal Kuan 470 98 649.75 590.68 1060.68 1060.68 1060.68 kmo to

    km76

    Bareilly Lal Kuan 500 98 649.75 590.68 1090.68 1090.68 1090.68 Total

    deduc

    Bareilly Local 380 380.00 hence

    1) Distances from quarry have been taken from the shortest route.

    2) Quarry rates have been taken of the respective circle applicable.

    3) Cartage rates has been taken approved by SE Lko. Circle in the RMR.

    4) Quarry rates are for approved quarry and RMR rates are minimum .

    N.H. Construction Division

    ROAD METAL RATES

    CIRCLE : 28th .Circle, N.H. P.W.D.

    NH CD PWD Bareilly km-250 of NH24Km.

    No.

    Quarry Quarry

    Rate

    Distence

    from

    Cost of

    cartage

    Cost of

    cartage

    Coarse Sand

    Total

    (3+7)

    I.S.

    Transit

    Total of

    col.

    Trade

    Tax on

    G.Total of

    col

    Stone Ballast ( 22.4-53 mm)

    16mm-22.4mm/ 11.2mm/13.2mm/ 10-16mm

    11.2-2.8 mm / 2.3-9.5 (6.7mm)

    Stone grit 5.6 mm and below

    Stone Dust

    P.W.D. Bareilly P.W.D. Bareilly P.W.D. Bare

    Fine Sand

    JUNIOR ENGINEER EXECUTIVE ENGINEER SUPERINTENDING E

    N.H. Construction Division 28th Circle N

  • 8/13/2019 Office Maintenance

    2/19

    S. No. Description Unit Quantity Rate Rs Cost Rs2.4 (vi) Scraping of Bricks Dismantled from Brick Work

    including Stacking.

    Unit = numbers

    Taking output = 1000 numbers

    A In lime/Cement mortar

    a) Labour

    Mate day 0.140 130.00 18.20

    Mazdoor day 3.500 125.00 437.50

    b) Overhead charges @10% input on (a) 45.57

    c) Contractor's profit @10% input on (a+b) 50.13

    Rate per1000 Nos = a+b+c 551.40

    Rate per No ( a+b+c)/1000 say 0.60

    2.4 (viii) Scarping Plaster in Lime or Cement Mortar

    from Brick/ Stone Masonry

    Unit = sqm

    Taking output = 100 sqm

    a) Labour

    Mate day 0.160 130.00 20.80

    Mazdoor for scarping and loading day 4.000 125.00 500.00

    b) Machinery

    Tractor-trolley hour 0.320 234.00 74.88

    c) Overhead charges @10% input on (a+b) 59.57

    d) Contractor's profit @10% input on (a+b+c) 65.52

    Cost for 100 sqm = a+b+c+d 720.77

    Rate per sqm = (a+b+c+d)/100 7.21

    say 7.20

    2.4 (ii) Dismantling Brick / Tile work

    2.4 (ii) B In cement mortar

    a) Labour

    Mate day 0.030 130.00 3.90

    Mazdoor for dismantling, loading and

    unloadin

    day 0.750 125.00 93.75

    b) Machinery

    Tractor-trolley hour 0.270 234.00 63.18

    c) Overhead charges @10% input on (a+b) 16.08

    d) Contractor's profit @10% input on (a+b+c) 17.69

    Cost for 1.25 cum = a+b+c+d 194.60

    Rate per cum = (a+b+c+d)/ 1.25 155.68

    say 155.70

    Analysis Of Rates

    Junior Engineer Assistant Engineer

  • 8/13/2019 Office Maintenance

    3/19

    CL.

    No.

    S. No.Description Unit Quantity Rate Rs Cost Rs

    12.6 Sub-

    Ana

    Unit = 1 cum

    Taking output = 1 cum

    a) Materials

    Cement tonne 0.51 5900.00 3009.00

    Coarse Sand cum 1.05 1090.68 1145.22

    b) Labour

    Mate day 0.04 130.00 5.20

    Mazdoor day 0.90 125.00 112.50

    Total Material and Labour = (a+b) say 4271.90

    CL.

    No.

    S. No.Description Unit Quantity Rate Rs Cost Rs

    13.1 1300 &

    2200

    Unit = cum

    Taking output = 1 cum

    a) Material

    Bricks Ist class(excluding 10% c.p.) each 500.00 3.35 1675.00

    Cement mortar 1:3 (Rate as in Item

    12.6 A sub-analysis)

    cum 0.24 4271.90 1025.26

    b) Labour

    Mate day 0.06 130.00 7.80

    Mason day 0.80 260.00 208.00

    Mazdoor day 0.80 125.00 100.00

    Add for scaffolding @ 5 per cent of

    cost of material and labour

    150.80

    a+b 3166.86

    c) Overhead charges @10% input on

    (a+b)

    316.69

    a+b+c 3483.54

    d) Contractor's profit @10% input on

    (a+b+c)

    348.35

    a+b+c+d 3831.90

    Rate per cum (a+b+c+d) 3831.90

    say 3831.90

    Cement Mortar 1:3 (1 cement : 3 Coarse sand)

    Brick masonry work in 1:3 in sub-structure complete

    Brick masonry work in 1:3 in sub-structure complete excluding pointing and

    plastering, as per drawing and Technical Specifications

    Analysis Of Rates

    Junior Engineer Assistant Engineer

  • 8/13/2019 Office Maintenance

    4/19

    CL.

    No.

    S. No.Description Unit Quantity Rate Rs Cost Rs

    12.8 1500,1

    700 &

    2100

    Plain M15 Cement Concrete in Open

    Foundation complete as per Drawing and

    Technical Specifications.

    PCC Grade M15

    Unit = cum

    Taking output = 15 cum

    a) Material

    Cement tonne 4.13 5900.00 24367.00

    Coarse sand cum 6.75 1090.68 7362.10

    40 mm Aggregate cum 8.10 1130.68 9158.52

    20 mm Aggregate cum 4.05 1190.68 4822.26

    10 mm Aggregate cum 1.35 1190.68 1607.42

    b) Labour

    Mate day 0.86 130.00 111.80

    Mason day 1.50 260.00 390.00

    Mazdoor day 20.00 125.00 2500.00

    c) Machinery

    Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 150.00 900.00

    Generator 63 KVA hour 6.00 320.00 1920.00

    add35% Escallation charges 987.00

    Cost of Labour, Material & Machinery

    (a+b+c)

    54126.11

    d) Formwork @ 4 per cent on cost of

    concrete i.e. cost of material, labour and

    machinery

    2165.04

    a+b+c+d 56291.15

    e) Overhead charges @10% input on

    (a+b+c+d)

    5629.12

    a+b+c+d+e 61920.27

    f) Contractor's profit @10% input on

    (a+b+c+d+e)

    6192.03

    Cost for 15 cum = a+b+c+d+e+f 68112.29

    Rate per cum = (a+b+c+d+e+f)/15 4540.82

    say 4540.80

    PCC M 15 / Plain Cement Concrete in Open foundation

    Analysis Of Rates

    Junior Engineer Assistant Engineer

  • 8/13/2019 Office Maintenance

    5/19

    CL.

    No.

    S. No.Description Unit Quantity Rate Rs Cost Rs

    9.1 408 Plain cement concrete 1:3:6 mix with

    crushed stone aggregate 40 mm nominal

    size mechanically mixed, placed in

    foundation and compacted by vibrationincluding curing for 14 days.

    Unit = cum

    Taking output = 15 cum

    a) Labour

    Mate day 0.640 130.00 83.20

    Mason day 1.000 260.00 260.00

    Mazdoor day 15.000 125.00 1875.00

    b) Material

    40mm Aggregate at site cum 13.800 1130.68 15603.41

    Coarse Sand at site cum 6.900 1090.68 7525.70

    Cement at site tonne 3.300 5900.00 19470.00

    Cost of water KL 18.000 50.00 900.00

    c) Machinery

    Concrete mixer0.4/ 0.28 cum hour 6.000 150.00 900.00

    Generator set 33 KVA hour 6.000 240.00 1440.00

    Water tanker6 KL capacity hour 3.000 200.00 600.00

    Add 35% Escallation charges 1029.00

    d) Overhead charges @10% input on

    (a+b+c)

    4968.63

    e) Contractor's profit @10% input on

    (a+b+c+d)

    5465.49

    Cost for 15 cum = a+b+c+d+e 60120.44

    Rate per cum = (a+b+c+d+e)/15 4008.03

    say 4008.00

    PCC 1:3:6 in Foundation

    Analysis Of Rates

    Junior Engineer Assistant Engineer

  • 8/13/2019 Office Maintenance

    6/19

    Analyised Basic Rates Of Materials

    M.S. Sheet 1.6 mm thick

    as per mareket Sqm 1.00 690.00 690.00

    cost for local cartage no 1.00 10.00 10.00

    loading/unloading Sqm 1.00 3.00 3.00

    Hence Rate per Sqm 703.00

    Providing & fixing M.S.Sheets on roof

    of A.E." s camp Office in side lab &

    A.O.office& store room no: 5

    a) Labour

    for dismantling of old damaged M.S.

    Sheets, verga, & making base etc. Sqm 1.00 l.s 25.00

    for fitting of New M.S.Sheets include-

    ing nuts & bolts ,black smith & all

    labour t&p etc. Sqm 1.00 l.s 50.00

    b) Material

    M.S. Sheet 1.6 mm thick Sqm 1.00 538.00 538.00c) Overhead charges @10% input on

    (a+b) 61.30

    a+b+c 674.30

    d) Contractor's profit @10% input on

    (a+b+c) 67.43

    a+b+c+d 741.73

    Rate per Sqm (a+b+c+d) 741.70

    CL.

    No.

    S. No.Description Unit Quantity Rate Rs Cost Rs

    13.3 1300 &

    2200

    Unit = 10 sqm

    Taking output = 10 sqm

    a) Material

    Cement mortar 1:3 (Rate as in Item 12.6) cum 0.144 4271.90 615.15

    b) Labour

    Mate day 0.04 130.00 5.20

    Mason day 0.50 260.00 130.00

    Mazdoor day 0.50 125.00 62.50

    a+b 812.85

    c) Overhead charges @10% input on (a+b) 81.29

    a+b+c 894.14

    d) Contractor's profit @10% input on (a+b+c) 89.41

    Rate per 10 sqm (a+b+c+d) 983.55

    98.36

    say 98.40

    ( As per market rate)

    Plastering with cement mortar (1:3) Cement : coarse sand

    Analysis Of Rates

    Junior Engineer Assistant Engineer

  • 8/13/2019 Office Maintenance

    7/19

    3.13 304

    Ordinary soil

    Unit = cum

    Taking output = 10 cum

    Manual Means (Depth upto 3 m)a) Labour

    Mate day 0.320 130.00 41.60

    Mazdoor day 8.000 125.00 1000.00

    b) Overhead charges @10% input on (a) 104.16

    c) Contractor's profit @10% input on (a+b) 114.58

    Cost for 10 cum = a+b+c 1260.34

    Rate per cum = (a+b+c)/10 126.03

    say 126.00

    CL.

    No.

    S. No.Description Unit Quantity Rate Rs Cost Rs

    13.3 1300 &

    2200

    Unit = 10 sqm

    Taking output = 10 sqm

    a) Material

    Cement mortar 1:3 (Rate as in Item 12.6) cum 0.144 4271.90 615.15

    b) Labour

    Mate day 0.04 130.00 5.20

    Mason day 0.50 260.00 130.00Mazdoor day 0.50 125.00 62.50

    a+b 812.85

    c) Overhead charges @10% input on (a+b) 81.29

    a+b+c 894.14

    d) Contractor's profit @10% input on (a+b+c) 89.41

    Rate per 10 sqm (a+b+c+d) 983.55

    98.36

    say 98.40

    Earth work in excavation of foundation of structures

    Plastering with cement mortar (1:3) Cement : coarse sand

    Earth work in excavation of foundation of structures as per drawing and technical specification,

    Analysis Of Rates

    Junior Engineer Assistant Engineer

  • 8/13/2019 Office Maintenance

    8/19

    Analyised Basis on Market Rates Of Materials

    a) Urinal sheets no 3 850.00 2550.00

    b) w.c. sheets no 2 850.00 1700.00

    c) wash basin no 2 1800.00 3600.00

    d) Cystern system no 2 3000.00 6000.00

    e) Tapes no 6 350.00 2100.00

    f)G.I.pipe ft 22 80.00 1760.00g) drainage pipe ft 20 25.00 500.00

    h) other fitting job 1 1200.00 1200.00

    i) labour charges job 1 2500.00 2500.00

    j)pvc water tank 200 liter capcity job 2 3000.00 6000.00

    Total 27910.00

    Fittings into Toilets/ bath atteched with E.E.,S room/A.E.ist/A.E.iiird /A.O.room

    a) Urinal sheets no 1 950.00 950.00

    b) w.c. sheets uropion type no 1 4250.00 4250.00

    c) wash basin no 1 1800.00 1800.00

    d) Cystern system no 1 4000.00 4000.00

    e) Tapes no 3 350.00 1050.00f)G.I.pipe ft 15 80.00 1200.00

    g) drainage pipe ft 18 25.00 450.00

    h) other fitting job 1 1000.00 1000.00

    i) labour charges job 1 2500.00 2500.00

    j)pvc water tank 200 liter capcity job 1 3000.00 3000.00

    Total 20200.00

    Junior Engineer Assistant Engineer

    Fittings into Toilets/ bath for General office stoff

  • 8/13/2019 Office Maintenance

    9/19

    Providing and laying of floor tiles

    taking output = 4.00 sqft (0.372sqm)

    a) Cost of Tile sqft 4.00 84.00 336.00

    b) cost of cement kg 6.00 6.00 36.00

    c) coarse sand kg 20.00 1.20 24.00

    d) labour for laying ft 4.00 22.00 88.00

    e) over heads charges/westages job 1.00 20.00 20.00Total 504.00

    Hence Rate per sqm 1354.80

    Providing and laying of wall tiles

    taking output = 10.50sqft(0.9765sqm)

    a) Cost of Tile sqft 10.50 36.00 378.00

    b) cost of cement kg 10.50 6.00 63.00

    c) coarse sand kg 1.00 1.00 1.00

    d) labour for laying ft 10.50 20.00 210.00

    e) over heads charges/westages job 1.00 20.00 20.00

    Total 672.00

    Hence Rate per sqm 688.20

    Supply & Fixing steel grills,sections in old

    taking area 1.00 sqm

    1.00 sqm l/s @ 25kg per sqm kg 25.00 70.00 1750.00

    Hence rate per sqm 1750.00

    Supply & Fixing glass pannels in old

    taking area 1.00sqm (10.76 sqft ) sqft 10.76 75.00 807.00

    market rate Rs 75 per sqft

    Hence rate per sqm 807.00

    (a+b+c+d+e)/.372

    (a+b+c+d+e)/0.9765

    Analysis Of Rates

  • 8/13/2019 Office Maintenance

    10/19

    L B H

    1

    Cum 1 2.30 0.23 3.50 1.85

    1 2.45 0.23 3.50 1.97

    Repair of A E iiird room

    L=2x (4.8+3.2)/2

    parapet

    wall of roof

    at A.E iiird

    room

    1 8.00 0.35 0.35 0.98

    parapet

    wall of roof

    at store

    room no 5

    1 20.20 0.35 0.4 2.83

    side wall 1 5.50 0.35 3.75 7.22

    Total Cum 14.85

    2 Scraping of Bricks Dismantled from Brick Workincluding Stacking.( obtain from dismantled brick

    work.)

    10% nos of

    total bricks

    nos 684 684.00

    Sqm 2 3.60 3.00 21.60

    2 4.40 3.00 26.40

    2 2.80 2.40 13.44

    2 2.00 2.40 9.60

    2 2.50 2.40 12.00

    2 1.70 2.40 8.16

    2 2.802.40

    13.44

    2 2.20 2.40 10.56

    2 4.80 0.60 5.76

    1 3.20 0.60 1.92

    store

    g.room no 1

    1 4.40 2.00 8.80

    Total Sqm 131.68

    Providing & fixing M.S.Sheets on roof

    including supply of all materials & labour

    for dismanteling of old damages etc

    and for new fittings,fixing etc complete

    In A.E." s camp Office in side lab Sqm 1 3.15 2.20 6.93

    1 4.30 1.10 4.73

    In A.O. Room 1 4.60 2.20 10.12

    In store godown room no: 5 1 5.40 5.15 27.81

    Total Sqm 49.59Earth Work in excavation in foundation

    in ordinary soil etc i/c all lead & lift, all

    labour T & P etc. Complete. For constru-

    ction of new General Toilets & w.c for

    official use . Cum 2 5.35 0.75 0.75 6.02

    2 2.45 0.75 0.75 2.76

    1 2.35 0.75 0.75 1.32

    1 2.55 0.75 0.75 1.43

    Total Cum 11.53

    5

    3

    Detail of Measurements

    Name of work : Repair and Maintenance of Divisonal Office N.H. C.D. Pwd Bareilly.

    S. No.Item of work

    Details Unit No Measurements Qty

    A.E.iiird

    room toilet

    A.E.Ist room

    toilet

    in Item 1

    Repair of store godwn room no 1 ,

    L=2(L+B)=2x (5.45+4.65)

    H=(3.1+4.4)/2

    Dismantling Brick / Tile work of old damaged

    Toi lets , Bath rooms ( to chnge techanical room

    /A.E. and disposal of dismamtled material up to lead

    of 1000m. All labour T&p etc complete.

    partion wall

    between

    toilet& bath

    4

    in AE iiird

    room

    E.E.,s room

    toilet

    constructio

    n of urinals

    & bath for

    office staff

    Scarping Plaster in Lime or Cement Mortar from

    Brick/ Stone Masonry ( damaged surface of old

    plaster )

  • 8/13/2019 Office Maintenance

    11/19

    Plain cement concrete 1:3:6 mix with crushed

    stone aggregate 40 mm nominal size mechanically

    mixed, placed in foundation and compacted by

    vibration including curing for 14 days.( in

    foundation & flooring of urinals,toilets)

    Cum 2 5.35 0.75 0.15 1.20

    2 2.45 0.75 0.15 0.55

    1 2.35 0.75 0.15 0.26

    1 2.55 0.75 0.15 0.29

    in flooring 1 4.80 2.40 0.15 1.73

    in flooring 2 2.10 1.50 0.15 0.95

    Cum 4.98

    Brick masonry work in 1:3 in sub-

    structure complete excluding

    pointing and plastering, as per

    drawing and Technical Specificationsparapet

    wall of roof

    at A.E.room

    Cum 1 8.00 0.35 0.35 0.98

    Cum 2 5.35 0.50 0.75 4.01

    2 2.45 0.50 0.75 1.84

    1 2.35 0.50 0.75 0.88

    1 2.55 0.50 0.75 0.96

    Cum 2 5.35 0.23 3.00 7.38

    2 2.45 0.23 3.00 3.38

    1 2.35 0.23 3.00 1.62

    1 2.55 0.23 3.00 1.76

    1 20.20 0.35 0.35 2.47

    h= ( 3.45+4.75 )/2 =4.10 1 5.50 0.35 4.10 7.89

    Total Cum 33.18

    Plain M15 Cement Concrete in Open Foundation

    complete as per Drawing and TechnicalSpecifications. In plinth of new urinals & toilets and

    its flooring.complete.

    cum 2 5.35 0.30 0.02 0.06

    2 2.45 0.30 0.02 0.03

    1 2.35 0.30 0.02 0.01

    1 2.55 0.30 0.02 0.02

    cum 2 5.35 2.45 0.05 1.31

    1 2.55 2.35 0.05 0.30

    for J.E. ( T ) room in flooring 1 3.30 2.40 0.05 0.40

    Total Cum 2.13

    6

    7

    B = (0 .69 + 0.30 ) /2 = 0.50

    8

    constructio

    n of urinals

    & bath for

    office staff

    parapet

    wall of roof

    at store

    room no 1

    constructio

    n of urinals

    & bath for

    office staff

    constructio

    n of urinals

    & bath for

    office staff

    constructio

    n of urinals

    & bath for

    office staff

    in flooring

  • 8/13/2019 Office Maintenance

    12/19

    9 Plastering with cement mortar

    (1:3) Cement : coarse sand over brick

    work and over old damaged dismantled

    portion & complete.parapet

    wall of roof

    at A.E.roomSqm 1 9.70 1.05 10.19

    parapet

    wall of roof

    at store

    room no 51 20.20 1.05 21.21

    on new side

    wall 1 5.15 3.75 19.31

    Sqm 2 4.90 3.00 29.40

    2 2.55 3.00 15.30

    2 2.80 2.40 13.44

    2 2.00 2.40 9.60

    2 2.50

    2.40

    12.00

    2 1.70 2.40 8.16

    A.E.iiird

    room toilet

    2 2.80 2.40 13.44

    2 2.20 2.40 10.56

    L=2(4.9+2.35) 2 7.25 2.10 30.45

    in side w.c 4 2.35 2.10 19.74

    in side w.c 4 2.45 2.10 20.58

    L=2(2.12+2.22) 2 4.34 2.10 18.23

    2 4.30 0.60 5.162 3.80 0.60 4.56

    office H/C Misc. 2 4.50 2.10 18.901 4.40 1.80 7.923 2.20 1.65 10.89

    Total Sqm 299.04Providing & Repreparing falls ceelling at

    place of old damaged as under

    Sqm 1 3.15 2.20 6.93

    2 4.30 1.10 9.46

    In A.O. Room 3 3.60 2.20 23.76

    Total Sqm 40.15

    providing and fixing urinals sheets,Tapes

    washbasin,water supply/drainage fittings

    W.C.fittings, cysterns

    fittings etc. complete .

    ( in combine bath & toilets )

    with atached E.E.,s room job 1 1.00

    with aatached A.E. ist room job 1 1.00

    with attech A.E. i iird room job 1 1.00

    with attech Accountant officer room job 1 1.00

    Genaral w.c.,urinals for office stoff job 1 1.00

    Providing and laying of floor tiles

    including supply of all materials such as

    tiles,cement,c.sand,labour etc&complete

    for E.E.,S room Sqm 1 6.30 4.30 27.09

    for A.E ist/ iind room Sqm 1 5.30 3.30 17.49

    for A.E. iiird room 1 4.40 3.15 13.86

    Toilet with attech A.E. ist room 1 2.50 2.10 5.25

    Toilet with attech A.E. iiird room 1 2.80 2.20 6.16

    Toilet with attech E.E.,s room 1 2.80 2.00 5.60

    Genaral w.c.,urinals for office stoff 1 4.80 2.40 11.52

    2 2.10 1.50 6.30

    Total Sqm 93.27

    12

    10

    with ateched E.E.,s room ,toilet

    11

    In A.E." s camp Office in side lab

    in room

    A.E.iiird

    A.E.Ist room

    toilet

    E.E.,s room

    toilet

    in Item 1

  • 8/13/2019 Office Maintenance

    13/19

    Providing and laying of wall tiles in baths

    including supply of all materials such as

    tiles,cement,c.sand,labour etc&complete L+B

    Toilet with attech E.E. ,s room L=(2.8+2.0) Sqm 2 4.80 2.10 20.16

    with attech A.E. ist room L=2(2.5+1.7) Sqm 2 4.20 2.10 17.64

    with attech A.E. iiird room L=2(2.8+2.2) 2 5.00 2.10 21.00

    Genaral w.c.,urinals for office stoff L=2(4.9+2.35) 2 7.25 2.10 30.45

    in side w.c 4 2.35 2.10 19.74

    in side w.c 4 2.45 2.10 20.58

    L=2(2.12+2.22) 2 4.34 2.10 18.23

    Total Sqm 88.83Supply & Fixing steel grills,sections in old

    existing windows in rooms , & ventiletors

    into bathrooms.

    A.E. iiird room & camp room window Sqm 4 0.80 1.10 3.52

    3 1.65 1.10 5.45

    V 2 0.90 0.45 0.81

    Store room w 1 0.90 1.30 1.17

    Total Sqm 10.95

    Supply & Fixing glass pannels in old

    windows replesed to damaged pannels Sqm 2.00 2.00

    Supply of wooden furniture as under&

    complete

    A - Tables of size - 6'x4' ft Nos 2 2 B - Chairs Nos 40 40

    C - Chairs with cussion Nos 8 8

    D- Benches Nos 4 4

    Supply of Steel Almirah with Box cell

    6 Nos each including fittings locks in

    each and complete. Nos 2 2

    Supply of ceilling Fans & fittings

    complete Nos 4 4

    19 Supplying & fittings of coolers Nos 5 5

    Supply of computers with assesaries

    required for work official work. Nos 2 2

    21 Supplying of computr Tables Nos 2 2

    Apply priming coat over new steel and

    other metal surface after and includingprepairing the surface throughly cleaning

    oil grease dirt etc and scoured with wire

    brushes, fine steel /wood scrappers sand

    papering and knoting including cost of all

    materials, labour abd t&p[ etc required

    for proper completion of work. door Sqm 8 1.00 2.00 16.00

    door 7 0.75 2.00 10.50

    window 4 1.65 2.00 13.20

    window 7 0.80 2.00 11.20

    window 2 0.90 1.25 2.25

    Total Sqm 53.15

    Painting first coat over priming coat

    ( excluding cost of priming coat)

    painting with medium quality enemelpaint on wooden/ steel door & windows

    and complete. In EE,room , AE ist, AE iiird

    rooms , camp rooms , AO room, and in

    their bath/ Toilets. Complete the work door Sqm 8 1.00 2.00 16.00

    door 7 0.75 2.00 10.50

    window 4 1.65 2.00 13.20

    window 7 0.80 2.00 11.20

    window 2 0.90 1.25 2.25

    Total Sqm 53.15

    Same as in item no 18 above but

    subseqent coat after first coat onasabove Sqm same as above 53.15

    24

    17

    18

    20

    22

    23

    13

    14

    15

    16

  • 8/13/2019 Office Maintenance

    14/19

    One priming coat & one coat of dry

    distemper on new / old surface including

    supply of all materials , labour , t&p etc.

    complete.

    for E.E.,S room Sqm 2 6.30 3.40 42.84

    2 4.30 3.40 29.24

    ceilling 1 6.30 4.30 27.09

    for A.E ist/ iind room Sqm 2 5.30 3.40 36.04

    2 3.30 3.40 22.44

    ceilling 1 5.30 3.30 17.49for A.E. iiird room 2 4.40 3.60 31.68

    2 3.15 3.60 22.68

    ceilling 1 4.40 3.15 13.86

    Toilet with attech A.E. ist room 2 2.50 1.30 6.50

    2 2.10 1.30 5.46

    ceilling 1 2.50 2.10 5.25

    Toilet with attech A.E. iiird room 2 2.80 1.10 6.16

    2 2.20 1.10 4.84

    ceilling 1 2.80 2.20 6.16

    Toilet with attech E.E.,s room 2 2.80 1.30 7.28

    2 2.00 1.30 5.20

    ceilling 1 2.80 2.00 5.60

    Genaral w.c.,urinals for office stoff 2 4.80 0.90 8.64

    2 2.40 0.90 4.324 2.10 0.90 7.56

    4 1.50 0.90 5.40

    ceilling 1 4.80 2.40 11.52

    ceilling 2 2.10 1.50 6.30

    Toilet with attech A.O.,s room 2 2.10 1.10 4.62

    2 1.70 1.10 3.74

    ceilling 1 6.30 4.30 27.09

    J.E. ( T ) Room 2 3.30 3.00 19.80

    2 2.40 3.00 14.40

    ceilling 1 6.30 4.30 27.09

    Total Sqm 409.20

    Same as above item no 20 but for each

    coat of distemper after the first coat &

    complete. Sqm same as above 409.20Replece old damaged Electric wiring with

    New Fittings Electric wirings in Rooms &

    bath etc. Complete the work. job 1 1.00

    25

    26

    Junior Engineer Assistant Engineer

    27

  • 8/13/2019 Office Maintenance

    15/19

    S. No. Item of work Unit Qty. Rate Per Amount

    1 Dismantling Brick / Tile work of old damaged Toilets,

    Bath rooms ( to chnge techanical room /A.E. and

    disposal of dismamtled material up to lead of 1000m.

    All labour T&p etc complete. Cum 14.85 155.70 Cum 2312.22

    2 Scraping of Bricks Dismantled from Brick Workincluding Stacking.( obtain from dismantled brick

    work.) Nos 684.00 0.60 Nos 410.40

    3 Scarping Plaster in Lime or Cement Mortar from

    Brick/ Stone Masonry ( damaged surface of old

    plaster ) Sqm 131.68 7.20 Sqm 948.096

    Providing and Fixing of M.S.Sheets on

    roof of AE iiird / AO/ Store godwn room

    including supplying of sheets nuts & bolts

    all materials , labour for fixing etc comp-

    lete .

    Earth Work in excavation in foundation

    in ordinary soil etc i/c all lead & lift, all

    labour T & P etc. Complete. For constru-

    ction of new General Toilets & w.c for

    official use .

    6 Plain cement concrete 1:3:6 mix with crushed

    stone aggregate 40 mm nominal size

    mechanically mixed, placed in foundation and

    compacted by vibration including curing for 14

    days.( in foundation & flooring of urinals,toilets)Cum 4.98 4008.00 Cum 19956.83

    Brick masonry work in 1:3 in sub-structure complete excluding

    pointing and plastering, as per

    drawing and Technical Specifications

    in construction of new urinals,Toilets,

    & side wall of store godown room no 1

    & reconstruction of parapet wall of roofs

    by dismanteling of old damaged parapets

    complete the work.

    8 Plain M15 Cement Concrete in Open Foundationcomplete as per Drawing and Technical

    Specifications. In plinth of new urinals & toilets

    and its flooring.complete.

    Cum 2.13 4540.80 Cum 9669.07

    Plastering with cement mortar

    (1:3) Cement : coarse sand over brick

    work and over old damaged dismantled

    portion & complete.

    BILL OF QUANTITY

    4

    36780.90Sqm741.7049.59Sqm

    Name of work : Repair and Maintenance of Divisonal Office N.H. C.D. Pwd Bareilly.

    1452.94

    7

    Cum 33.18 3831.90 Cum 127140.53

    5

    Cum 11.53 126.00 Cum

    29425.09

    9

    Sqm 299.04 98.40 Sqm

  • 8/13/2019 Office Maintenance

    16/19

    Providing & Repreparing falls ceelling at

    place of old damaged as under

    ( as per market rates )

    providing and fixing urinals sheets,Tapes

    washbasin,water supply/drainage fittings

    W.C.fittings, cysterns

    fittings etc. complete .

    ( in combine bath & toilets )with atached E.E.,s room job 1.00 20200.00 Job 20200.00

    with aatached A.E. ist room job 1.00 20200.00 Job 20200.00

    with attech A.E. iiird room job 1.00 20200.00 Job 20200.00

    with attech Accountant officer room job 1.00 20200.00 Job 20200.00

    Genaral w.c.,urinals for office stoff job 1.00 27910.00 Job 27910.00

    Providing and laying of floor tiles

    including supply of all materials such as

    tiles,cement,c.sand,labour etc&complete

    Providing and laying of wall tiles in baths

    including supply of all materials such as

    tiles,cement,c.sand,labour etc&completeSupply & Fixing steel grills,sections in old

    existing windows in rooms , & ventiletors

    into bathrooms.

    Supply & Fixing glass pannels in old

    windows replesed to damaged pannels

    Supply of wooden furniture as under&

    complete

    A - Tables of size 6' x 4' ft Nos 2 11500.00 Nos 23000.00

    B - Chairs Nos 40 1600.00 Nos 64000.00

    C - Chairs 8 3500.00 Nos 28000.00

    D - Benches Nos 4 650.00 Nos 2600.00

    Supply of Steel Almirah with Box cell

    6 Nos each including fittings locks in

    each and complete.

    Supply of ceilling Fans & fittings

    complete

    19 Supplying & fittings of coolers Nos 5 9000.00 Nos 45000.00

    Supply of computers with assesaries

    required for work official work.

    21 Supplying of computr Tables Nos 2 3500.00 Nos 7000.00

    Apply priming coat over new steel and

    other metal surface after and including

    prepairing the surface throughly cleaning

    oil grease dirt etc and scoured with wire

    brushes, fine steel / wood scrappers sand

    papering and knoting including cost of all

    materials, labour abd t&p[ etc required

    for proper completion of work.

    S.I. ( chapter 15 new item 1 )

    400.00 Sqm 16060.00

    11

    10

    Sqm 40.15

    1354.80 Sqm 126362.20

    13

    Sqm 88.83 688.20 Sqm

    12

    Sqm 93.27

    16

    15

    Sqm 2.00 807.00

    14

    Sqm 10.95 1750.00

    Sqm 1614.00

    61132.81

    19153.75Sqm

    36000.00

    18

    Nos 4 2000.00 Nos 8000.00

    17

    Nos 2 18000.00 Nos

    22

    Sqm 53.15 17.00

    112000.00

    Sqm 903.55

    20

    Nos 2 56000.00 Nos

  • 8/13/2019 Office Maintenance

    17/19

    Painting first coat over priming coat

    ( excluding cost of priming coat)

    painting with medium quality enemel

    paint on wooden/ steel door & windows

    and complete. In EE,room , AE ist, AE iiird

    rooms , camp rooms , AO room, and in

    their bath/ Toilets. Complete the work

    S.I. ( chapter 15 new item 2 )Same as in item no 23 above but

    subseqent coat after first coat onasabove

    One priming coat & one coat of dry

    distemper on new / old surface including

    supply of all materials , labour , t&p etc.

    complete. ( S.I.no 681 )

    Same as above item no 20 but for each

    coat of distemper after the first coat &

    complete. ( S.I. no 682 )Replece old damaged Electric wiring with

    New Fittings Electric wirings in Rooms &

    bath etc. Complete the work.

    938527.73

    Junior Engineer Assistant Engineer

    24

    Sqm 53.15 20.00 Sqm 1063.00

    1328.75Sqm25.0053.15Sqm

    23

    27

    job 1.00 35000.00 Job 35000.00

    9002.40

    26

    Sqm 409.20 11.00 Sqm 4501.20

    Sqm

    25

    409.20 22.00 Sqm

  • 8/13/2019 Office Maintenance

    18/19

    S. No. Item of work Unit Rate Remarks

    1

    Dismantling of Brick work and disposal of dismantled

    material upto a lead of 1000m . Cum 155.70

    2Scraping of Bricks Dismantled from Brick Work including

    Stacking. 0.60

    3 Scarping Plaster in Lime or Cement Mortar from Brick/ StoneMasonry 7.20

    4 Earth work in excavation in foundation of structures

    as per drawing and technical specifications.

    Cum 126.00

    5 Cement concrete with 4cm gauge approved stone

    ballast, approved coarse sand cement in the

    proportion of 6:3:1 icluding supply of the all material,

    labour and T & P etc. required for proper comletion of

    the work Cum 4008.00

    6 First Class Brick Work in 1:3 Cement and Coarse sand

    Cum 3831.90

    7 Plastering with cement mortar (1:3) Cement : coarse

    sand Sqm 98.40

    8 PCC M 15 / Plain Cement Concrete in Open foundation Cum 4540.80

    9 Providing & fixing M.S.Sheets on roof Sqm 741.70

    10 Fittings into Toilets/ bath for General office stoff Nos 27910.00

    11 Fittings into Toilets/ bath atteched EE/AE room Nos 20200.00

    12 Providing and laying of floor tiles Sqm 1354.80

    14 Providing and laying of wall tiles Sqm 688.20

    15 Providing and laying of wall tiles Sqm 1750.00

    16 Supply & Fixing glass pannels in old Sqm 807.00

    Assistant engineer Executive Engineer Suprintending Engineer

    NH, PWD, Bareilly NH, PWD, Bareilly 28Th Circle, PWD, Bareilly

    Ceritication of Rates

    It is to certified that the rate of the following items of work i.e. for item No. 1 to 31

    It is also certified that I am component to approve the rates of all these items as per

    Name of work : Repair and Maintenance of Divisonal Office N.H. C.D. Pwd Bareilly.

  • 8/13/2019 Office Maintenance

    19/19

    S.No. Item of Work Amount

    Repair and Maintenance of Divisonal

    Office N.H. C.D. Pwd Bareilly.

    Total - A 938527.73

    2 W.C. Establishment 1.5% on A 14077.92

    3 Labour cess 1% on A 9385.28

    Total 961990.92

    961991.00

    Say Rs . 9.62 Lacs

    Junior Engineer Assistant Engineer Executive Engineer

    NH, PWD, Bareilly NH, PWD, Bareilly NH, PWD, Bareilly

    Suprintending Engineer

    28th Circle NH, PWD, Bareilly

    Summary of Cost

    Name of work : Repair and Maintenance of Divisonal Office N.H.C.D.Pwd

    1

    938527.73

    Bareilly ( 2012 - 2013 )