19
October 29, 2019

October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

October 29, 2019

Page 2: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

2

Boston Transportation Department

4

City of Boston• William Conroy

Project Manager

Tetra Tech, Inc.• Erik Maki, PE

Project Manager

PROJECT TEAM

Page 3: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

MEETINGS/SCHEDULE

3

Public Meetings to-date:

• June 30, 2016

• October 26, 2016

• February 28, 2017

• May 18, 2017

• November 15, 2017

• January 24, 2018

• March 28, 2018

• October 2019

Design Effort:

• Pre-design

August 2018

• 25% Preliminary Design

December 2019

Feb/Mar 25% Public Hearing (TBD)

• 75% Design - Summer 2020

• 100% Design – Winter 2020

• Advertise for Construction - March 2021

• FY22 - FY25

Construction phase ~ $150M

Page 4: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

AGENDA

• Corridor Overview

• Road Safety Audit

• Sullivan Square

• BRT

4

Page 5: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

CORRIDOR OVERVIEW:7,400 lf ~ 1.40 miles

• Road diet but maintain Regional connectivity• Two-way bike path and walking trail• Landscape buffer and lighting• New pedestrian crossings to BHCC, INDS Park & the Hood Park• SSQ new parcels A - B - C – D• SSQ underpass alignment -revision

CITY SQ

BHCC

HOODPARK

RYAN

5

Page 6: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

4

4 MIXING ZONE

Road Diet – Cross Section 6

Page 7: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

7

• Typical Minor Street Crossings from Neighborhood

• Baldwin Street• Essex Street• West School Street• Raised Crossing to

prioritize pedestrians and bikes over cars

• Interim Baldwin Crossing

• Source: Google Maps: Pond St, Brookline

RAISED CROSSINGS

Page 8: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

8

• August 14, 2019

• Reviewed crash data

• Field walk/tour

• Deficiencies noted

• Attendees• City, State

• Advocates

• Consultants

ROAD SAFETY AUDIT

Page 9: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

9

• Deficient or poor:• Sidewalks and surfaces

• Pedestrian and bike facilities

• ADA ramps

• Traffic Signal equipment

• Signs & markings

• High speed traffic

https://gis.massdot.state.ma.us/arcgis/rest/services/Roads/RoadSafetyAudits/MapServer/0/18160/attachments/19313

RSA - FINDINGS

Page 10: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

• Challenges:• Park flanked by Underpass

• No roadway adjacent to park

• Park became less accessible

• Complex underpass staging

• New signal delays

• Eversource High voltage electric

• Signal visibility with curve

10

A

B

C

D

E

F

G

(2018)

SULLIVAN SQUARE – 2018 PARCELS

Page 11: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

Existing MBTA Conduit

Existing PTC

Existing 12” Gas

Existing PTC

Existing 42” Gas (2)

Existing PTCs

Existing 48” MWRA Sewer

Relocate West St. Utilities

Relocate Mystic Av. Utilities

Relocate Exist 345kv PTC

Existing 78”x86” MWRA Sewer

Existing 30” Water

Existing 30” Gas (2)

Existing Utility Bridge

Existing 36” Gas

Existing PTCs

Existing 24” GasExisting 24” Water (2)

Proposed 115kv PTCRelocate All Exist Utilities Within Parcel A

``

Proposed Pump Station

Existing Pump Station

Ryan Playground

11

SULLIVAN SQUARE UTILITIES

Page 12: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

UNDERPASS – REVISED ALIGNMENT

• Ryan Playground• Local road

access/egress

• Expanded Open Space

• Expanded parking

• Portal Entrance

12

Ramp Roadway

Covered Deck

Bike/Multi-use Path

Park/Landscaping

Ryan Playground

Ryan Playground

2018 2019

E

Page 13: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

PARCEL LAYOUT/ OPEN SPACE

13

Development / Open Space

(Acres)

B

C

E

D

20192018

E

B

D

C

2018

1.53

0.72

0.41

0.63

0.66

0.25

Parcel No

A

B

C

D

E

P

2019

1.13

0.83*

0.41

0.82*

0.30*

0.59

* Includes new landscape area

P P

A A

Page 14: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

RYAN PLAYGROUND EXPANSION

14

Ryan Playground• Main & Alford St access

• 0.60 acre added to Park

• Better Access

NEWPARK

B D

UNDERPASS

RYAN PLAYGROUND

Page 15: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

15

2018

Page 16: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

16

Page 17: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

17

Page 18: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

18

Bus

HARBOR TRAIL

3-LANE UNDERPASS

RYAN PLAYGROUND

• Harbor Trail and BRT

• Crosswalk Safety

• Hybrid traffic signal

(Work in Progress)

BRT STATION & CROSSWALK FOR PED/BIKES

BRT

Page 19: October 29, 2019 - Boston...Microsoft PowerPoint - Final slides_Public Mtg No 8 - 10_29_19.pptx Author erik.maki Created Date 10/31/2019 2:32:57 PM

Thank you for your continued involvement!

FOR MORE INFO: https://www.cityofboston.gov/transportation/rutherford/

QUESTIONS?

NEXT MEETING:

TBD - February

19

Austin, TXLance Armstrong path Photo credit: Adam Coppola Photography