19
© 2013 McNees Wallace & Nurick LLC October 17, 2013 Robert A. Weishaar, Jr. ON SITE ENERGY – INTERPLAY WITH PJM DEMAND RESPONSE PROGRAMS Harrisburg, PA – Columbus, OH – State College, PA Lancaster, PA – Washington, DC – Scranton, PA

October 17, 2013 Robert A. Weishaar, Jr

  • Upload
    rich

  • View
    37

  • Download
    4

Embed Size (px)

DESCRIPTION

On Site Energy – Interplay With pjm Demand Response Programs . October 17, 2013 Robert A. Weishaar, Jr. Harrisburg, PA – Columbus, OH – State College, PA Lancaster, PA – Washington, DC – Scranton, PA. PJM Demand Side Response. - PowerPoint PPT Presentation

Citation preview

Page 1: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC

October 17, 2013Robert A. Weishaar, Jr.

ON SITE ENERGY – INTERPLAY WITH PJM DEMAND RESPONSE PROGRAMS

Harrisburg, PA – Columbus, OH – State College, PALancaster, PA – Washington, DC – Scranton, PA

Page 2: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC 2

PJM DEMAND SIDE RESPONSE The purpose of PJM Demand Response is to enable

Demand Resources under the direction and control of Curtailment Service Providers to respond to economic prices and/or emergency conditions

Demand Response can participate within the various PJM markets:

• Energy Day Ahead Market Real Time Market

• Ancillary Services Synchronized Reserve Regulation Day Ahead Scheduling Reserve

• Capacity Offer into auction up to 3 years in advance

Page 3: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC

ENERGY MARKETS - PJM ECONOMIC LOAD RESPONSE PROGRAM ("ELRP") All ELRP participation defined as:

• Clearing in the Day-Ahead ("DA") Market• Dispatched by PJM in the Real-Time Market

ELRP participant or CSP must submit load reduction bid offer to PJM

Curtailment must clear in the DA market or be dispatched by PJM in real-time to be eligible for settlement revenue

Load reductions eligible to be paid full LMP if LMP is at or above the Net Benefits Price (a.k.a. threshold price)

Net Benefits Price expected to correlate to energy cost of an efficient combined cycle natural gas plant

oAdjusts monthlyoPrice has ranged from approximately $23.00-$30.00/MWh

3

Page 4: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC

ENERGY MARKETS - PJM DEFAULT CUSTOMER BASELINE

A Customer Baseline ("CBL") is a proxy for what the load would have been absent the load reduction

All ELRP registrations require Customer Base Line ("CBL") certification

All customers must use a CBL with an error (relative root mean square error – "RRMSE") no greater than 20%

CBLs for customers with on-site generation are being determined mostly on a case-by-case basis

ELRP reduction is determined by the CBL minus the meter readings during PJM dispatched curtailment hours

4

Page 5: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC

ENERGY MARKETS - ELRP SUMMARY AND CAUTION

ELRP Revenue is determined by CBL Calculation CBL Calculation represents a moving target

• Presents some risk to curtailment amount• Could be manipulated to inflate ELRP revenue

Baseline manipulation viewed by FERC as manipulation of electric energy markets

• Potential penalties of $1 million per day per violation Daily decisions when/if to participate in the ELRP

program must not consider impact to future CBLs No payment for load reduction if LMP is less than

Net Benefits Price• Historically, LMP has been greater than the Net Benefits

Price about 50% of the time

5

Page 6: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC

ANCILLARY SERVICES MARKETS Synchronous Reserve Market

• Paid for standby service Emergency reserve that PJM can call quickly after a large

generator suddenly trips off-line Hourly payment just for being available to respond 25 – 40 events typically occur annually Total performance requirement of about 6 hours per year

• Must reduce load/increase generation within 10 minutes when ordered by PJM

• Requires 1-minute scan rate metering• Data submission within 24 hours • Consequences for non-performance

6

Page 7: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC

ANCILLARY SERVICES MARKETS Synchronous Reserve Market

• Hourly market participation Hourly synchronous reserve offer must clear the market to

receive payment Not all hours require PJM to procure Synchronous

Reserves from Demand Resources or result in a clearing price greater than $0

7

Page 8: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC

ANCILLARY SERVICES MARKETS Regulation Market

• Hourly market correcting for constantly occurring small load changes

• Requires 5-minute response time• Requires both load reduction and load increase• Sub-metering permitted

Performance not measured based on change to AEP pull

• Consequences for non-performance• Cannot simultaneously be participating in the

Synchronized Reserves Market

8

Page 9: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC 9

ANCILLARY SERVICES MARKETS Day Ahead Scheduling Reserve Market ("DASR")

• Reserves are additional capacity above the expected load• The purpose of the DASR market is to encourage and incent

generation and demand resources to provide the flexible capability to provide 30-minute reserves

• If a Resource is called-on in Real-Time, it must respond in 30 minutes

• Reserves are scheduled on a day-ahead basis in order to ensure that differences in forecasted loads and forced generator outages do not negatively impact system reliability

• The Day-Ahead Scheduling Reserve Requirement is calculated on an annual basis and is set at 6.91% for 2013

• The DASR market clears simultaneously with the DA Energy Market

• Limited revenue potential

Page 10: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC 10

INTERACTION OF RESERVE MARKET PRODUCTS

Resources can be capable of providing all three products:

• Synchronized Reserve, Regulation, and Day-Ahead Scheduling Reserve

All three cannot be provided simultaneously, only two products, at most

Page 11: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC 11

DEMAND RESOURCES IN THE CAPACITY MARKET

Demand Resources can offer curtailment capability as a forward capacity resource three years in advance of delivery year

• DR providers are required to provide the cleared demand response amount as capacity during the delivery year and will receive the capacity resource clearing price for this service

Must reduce load when requested by PJM All Call system within 2 hours of notification

Must provide customer-specific compliance and verification information within 45 days after the end of the month in which Load Management event occurred

Can participate in both ELRP and Capacity DR Programs

Note: Many aspects of RPM rules are being proposed to change, particularly those relating to DR

Page 12: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC 12

DEMAND RESOURCES

Page 13: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC 13

DR REGISTRATIONS

Page 14: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC 14

EMERGENCY DR EVENTSDelivery Year # of PJM Events

2005/2006 22006/2007 22007/2008 12008/2009 No Events2009/2010 12010/2011 72011/2012 12012/2013 22013/2014 72014/2015 Est. 5 to 92015/2016 Est. 5 to 9

Page 15: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC 15

RPM AUCTION CLEARING PRICES (ANNUAL PRODUCT)

Page 16: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC 16

RPM AUCTION CLEARING PRICES (ANNUAL PRODUCT)

Page 17: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC 17

DR PERFORMANCE ASSESSMENTS (PENALTIES)

Three penalties are applicable to customers participating in RPM as Demand Resources ("DR")

1. RPM Commitment Compliance2. Load Management Event Compliance3. Load Management Test Compliance

PJM penalties applied on pro-rata basis and may result in forfeiture of expected revenue or the forfeiture of expected revenue plus a penalty

DR performance for on-site generation typically measured using Guaranteed Load Drop ("GLD") method

Page 18: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC 18

RPM TIMETABLE

A complete listing of RPM activities and dates can be found at:

http://pjm.com/~/media/markets-ops/rpm/rpm-auction-info/rpm-auction-schedule.ashx

Page 19: October 17, 2013 Robert A. Weishaar, Jr

© 2013 McNees Wallace & Nurick LLC 19

AnyQuestions?

Robert A. Weishaar, Jr.McNees Wallace & Nurick LLC

Suite 401777 N. Capitol Street, NE

Washington, DC 20002-4292202-898-5700

717-260-1765 (fax)[email protected]