Bond Project Status for Oak Cliff Area Project Name PB# Category Project Manager Status Est Construction Start Est Construction Complete Estimated Cost 9th St & 10th St - Zang to Madison PB06U005 Alley Reconstruction Wilkens Engman Design 4/11/2011 12/20/2011 $100,394 Argonne Dr. - Montclair Ave. to Lausanne Ave. PB06U362 Street Resurfacing Steve Schell Bond 4/26/2010 10/29/2010 $22,207 Avon St. - Westmount Av. to Cliffdale Av. PB06U281 Street Petitions Raj Guntnur Design 6/30/2011 6/30/2012 $118,917 Beckley Ave. (N) - 1909 Beckley Ave. to 2211 Beckley Ave. PB06U377 Street Resurfacing Steve Schell Bond 4/26/2010 10/29/2010 $115,632 Beckley Avenue - Tilden to Oakenwald Street PB06U727 Streetscape / Urban Design Cornelio Rivera Pre-Design 3/11/2011 3/25/2013 $114,924 Berkley & Newport - Waverly To Rugged PB06U009 Alley Reconstruction Wilkens Engman Design 4/11/2011 12/20/2011 $225,532 Bishop Ave - Neely to Colorado PB06U728 Streetscape / Urban Design Haytham Hassa Design 3/15/2011 11/15/2011 $3,701,270 Bridal Wreath Ln. - Deerfield Ln. to Periwinkle Dr. PB06U394 Street Resurfacing Steve Schell Bond 4/25/2011 10/28/2011 $36,119 Clarendon Dr. (W) - Zang Blvd. to Bishop Ave. PB06U413 Street Resurfacing Steve Schell Bond 4/25/2011 10/29/2010 $92,300 Cliffdale Ave. - Avon St. to Dead End PB06U284 Street Petitions Raj Guntnur Design 6/20/2011 6/30/2012 $308,865 Colorado Blvd. over Coombs Creek PB06U188 Bridge Repair and Modification Liong So Construction 12/7/2009 12/31/2010 $76,578 Delaware Ave. Bishop Ave. to Griffth Ave. PB06U435 Street Resurfacing Steve Schell Bond 4/25/2011 10/28/2011 $110,655 Edgefield Ave. (S) - Twelfth St. to Burlington Blvd. PB06U452 Street Resurfacing Steve Schell Bond 4/25/2011 10/28/2011 $79,385 Eighth St. (E) - Patton Ave. to Crawford St. PB03R143 Street Resurfacing Steve Schell Construction 5/18/2009 12/18/2009 $78,965 Eighth St. (E) - Patton Ave. to RL Thornton Frwy. PB06U454 Street Resurfacing Steve Schell Construction 4/27/2009 10/29/2010 $460,361 Englewood Road - Tilden to Oakenwald Street PB06U311 Street Reconstruction Local Streets Cornelio Rivera Pre-Design 7/11/2011 11/25/2012 $232,826 Tuesday, June 22, 2010 Page 1 of 4

Oak Cliff Street Projects

Embed Size (px)

Citation preview

Page 1: Oak Cliff Street Projects

Bond Project Status for Oak Cliff Area

Project Name PB# Category Project Manager Status Est Construction

Start

Est Construction

Complete

Estimated Cost

9th St & 10th St - Zang to Madison PB06U005 Alley Reconstruction Wilkens Engman Design 4/11/2011 12/20/2011 $100,394

Argonne Dr. - Montclair Ave. to Lausanne Ave. PB06U362 Street Resurfacing Steve Schell Bond 4/26/2010 10/29/2010 $22,207

Avon St. - Westmount Av. to Cliffdale Av. PB06U281 Street Petitions Raj Guntnur Design 6/30/2011 6/30/2012 $118,917

Beckley Ave. (N) - 1909 Beckley Ave. to 2211 Beckley Ave.

PB06U377 Street Resurfacing Steve Schell Bond 4/26/2010 10/29/2010 $115,632

Beckley Avenue - Tilden to Oakenwald Street PB06U727 Streetscape / Urban Design

Cornelio Rivera Pre-Design 3/11/2011 3/25/2013 $114,924

Berkley & Newport - Waverly To Rugged PB06U009 Alley Reconstruction Wilkens Engman Design 4/11/2011 12/20/2011 $225,532

Bishop Ave - Neely to Colorado PB06U728 Streetscape / Urban Design

Haytham Hassa Design 3/15/2011 11/15/2011 $3,701,270

Bridal Wreath Ln. - Deerfield Ln. to Periwinkle Dr. PB06U394 Street Resurfacing Steve Schell Bond 4/25/2011 10/28/2011 $36,119

Clarendon Dr. (W) - Zang Blvd. to Bishop Ave. PB06U413 Street Resurfacing Steve Schell Bond 4/25/2011 10/29/2010 $92,300

Cliffdale Ave. - Avon St. to Dead End PB06U284 Street Petitions Raj Guntnur Design 6/20/2011 6/30/2012 $308,865

Colorado Blvd. over Coombs Creek PB06U188 Bridge Repair and Modification

Liong So Construction 12/7/2009 12/31/2010 $76,578

Delaware Ave. Bishop Ave. to Griffth Ave. PB06U435 Street Resurfacing Steve Schell Bond 4/25/2011 10/28/2011 $110,655

Edgefield Ave. (S) - Twelfth St. to Burlington Blvd. PB06U452 Street Resurfacing Steve Schell Bond 4/25/2011 10/28/2011 $79,385

Eighth St. (E) - Patton Ave. to Crawford St. PB03R143 Street Resurfacing Steve Schell Construction 5/18/2009 12/18/2009 $78,965

Eighth St. (E) - Patton Ave. to RL Thornton Frwy. PB06U454 Street Resurfacing Steve Schell Construction 4/27/2009 10/29/2010 $460,361

Englewood Road - Tilden to Oakenwald Street PB06U311 Street Reconstruction Local Streets

Cornelio Rivera Pre-Design 7/11/2011 11/25/2012 $232,826

Tuesday, June 22, 2010 Page 1 of 4

Page 2: Oak Cliff Street Projects

Project Name PB# Category Project Manager Status Est Construction

Start

Est Construction

Complete

Estimated Cost

Fort Worth Ave. - Streetscape Design PB03R180 Streetscape / Urban Design

Syed Muntajibud Design $200,000

Fouraker St. - Cedar Hill Ave. to N. Tyler St. PB06U478 Street Resurfacing Steve Schell Bond 4/26/2010 10/29/2010 $135,415

Franklin St. (S) - Gladiolus Ln. to Cul-De-Sac PB06U480 Street Resurfacing Steve Schell Bond 4/25/2011 10/28/2011 $27,695

Hampton Rd. (S) - Twelfth St. to Clarendon Dr. PB06U509 Street Resurfacing Steve Schell Bond 4/16/2010 10/29/2010 $236,754

Handley Dr. - Greenbriar Ln. to Stemmons Ave. PB06U510 Street Resurfacing Steve Schell Bond 4/26/2010 10/29/2010 $60,241

Jefferson Blvd. (W) - Hampton Rd. to City Limits PB06U542 Street Resurfacing Steve Schell Bond 4/25/2011 10/28/2011 $768,332

Kessler Canyon Dr. - Kessler Pkwy. To Evergreen Hill Rd.

PB06U550 Street Resurfacing Steve Schell Bond 4/26/2010 10/29/2010 $65,474

Kessler Pkwy. - Edgefield Ave. to Colorado Blvd. PB06U551 Street Resurfacing Steve Schell Bond 4/26/2010 10/29/2010 $164,132

Kidd Springs Dr. - Tyler St. to Sylvan Ave. PB06U553 Street Resurfacing Steve Schell Bond 4/26/2010 10/29/2010 $25,398

Kiest/Five Mile Hike and Bike Trail PB03R284 Intergovernmental Partnership Projects

Yogi Patel Design 10/23/2010 8/28/2011 $450,000

La Senda Pl. - Greenbrier Ln. to Shady Ln. PB06U566 Street Resurfacing Steve Schell Bond 4/26/2010 10/29/2010 $17,230

Madison Ave. (S) - Jefferson Blvd. to Clarendon Dr. PB06U592 Street Resurfacing Steve Schell Bond 4/26/2010 10/29/2010 $234,073

Madison Ave. (S) - Pembroke Ave. to Twelfth St. PB03R332 Street Resurfacing Steve Schell Construction 4/26/2010 10/29/2010 $50,690

Marsalis & Lancaster - 11th to Jefferson PB06U021 Alley Reconstruction Wilkens Engman Design 4/11/2011 12/20/2011 $59,731

Marsalis & Lancaster - E. Tenth To E. Ninth PB06U022 Alley Reconstruction Wilkens Engman Design 4/11/2011 12/20/2011 $118,501

Mary Cliff Rd. - Ranier St. to Kings Hwy. PB06U596 Street Resurfacing Steve Schell Bond 4/25/2011 10/28/2011 $74,918

Oakenwald Street - Plowman Ave to Beckley Ave. PB06U315 Street Reconstruction Local Streets

Cornelio Rivera Pre-Design 7/11/2011 11/25/2012 $413,225

Oakenwald Street - Zang Blvd. to Plowman Ave PB06U316 Street Reconstruction Local Streets

Cornelio Rivera Pre-Design 7/11/2011 11/25/2012 $234,784

Tuesday, June 22, 2010 Page 2 of 4

Page 3: Oak Cliff Street Projects

Project Name PB# Category Project Manager Status Est Construction

Start

Est Construction

Complete

Estimated Cost

Oregon/Beckley connection to I-30 frontage Road PB06U796 Thoroughfares Haytham Hassa Delayed 12/10/2012 12/15/2013 $3,968,906

Owensons Dr. - Tyler St. to End of Circle Drive PB06U619 Street Resurfacing Steve Schell Bond 4/26/2010 10/29/2010 $44,798

Page Ave. (W) - Zang Blvd. toMadison Ave. PB06U622 Street Resurfacing Steve Schell Bond 4/25/2011 10/28/2011 $58,199

Plowman Avenue - Oakenwald St to Zang Ave PB06U318 Street Reconstruction Local Streets

Cornelio Rivera Pre-Design 7/11/2011 11/25/2012 $215,350

Plowman Avenue - Tilden to Oakenwald Street PB06U319 Street Reconstruction Local Streets

Cornelio Rivera Pre-Design 7/11/2011 11/25/2012 $319,439

Plymouth Rd. (N) - Superior St. to Davis St. PB06U634 Street Resurfacing Steve Schell Bond 4/25/2011 10/28/2011 $184,042

Polk St (S) - Ferndale Av to Clarendon Av PB06U764 Target Neighborhood Wilkens Engman Design 4/4/2011 12/23/2011 $1,876,454

Polk St (S) - Wilbur St to Ferndale Av PB06U765 Target Neighborhood Wilkens Engman Design 4/4/2011 12/23/2011 $673,886

Ranier Street - Mary Cliff Road - Montclair Avenue (N)

PB06U299 Street Petitions Kassem Elkhalil Design 6/7/2011 12/30/2011 $268,023

Steinman Avenue (300-322) 8th - Patton to Denver PB06U029 Alley Reconstruction Wilkens Engman Design 4/11/2011 12/20/2011 $75,302

Temple Dr. - Winnetka Ave. to Windomere Ave. PB06U691 Street Resurfacing Steve Schell Bond 4/26/2010 10/29/2010 $48,116

Tennant (509-517) Hampton - Jefferson to Tennant PB06U032 Alley Reconstruction Wilkens Engman Design 4/11/2011 12/20/2011 $35,736

Tilden Street - Beckley to Plowman Ave PB06U753 Streetscape / Urban Design

Cornelio Rivera Pre-Design 7/11/2011 11/25/2012 $72,716

Westmoreland (S) - Rockford to Kiest PB03R880 Street Resurfacing Steve Schell Construction 11/5/2007 $775,000

Westmoreland Rd (S) - 9th St to Sheldon Av PB06U352 Street Reconstruction Thoroughfares

Ashok Patel Design 6/8/2011 6/26/2012 $1,595,375

Westmount Av - Davis St to Avon St PB06U304 Street Petitions Kassem Elkhalil Design 6/7/2011 12/30/2011 $926,721

Westmount Ave. - Avon St. to Fort Worth Ave. PB06U305 Street Petitions Kassem Elkhalil Design 6/7/2011 12/30/2011 $721,282

Willow Crest Ln. - Boulder Dr. to Westmoreland Rd. PB06U711 Street Resurfacing Steve Schell Bond 4/25/2011 10/28/2011 $64,580

Tuesday, June 22, 2010 Page 3 of 4

Page 4: Oak Cliff Street Projects

Project Name PB# Category Project Manager Status Est Construction

Start

Est Construction

Complete

Estimated Cost

Zang Avenue - Plowman Ave to Oakenwald St PB06U760 Streetscape / Urban Design

Cornelio Rivera Pre-Design 7/11/2011 11/25/2012 $87,429

Zang Blvd. (S) - Twelfth St. to Clarendon Dr. PB06U721 Street Resurfacing Steve Schell Bond 4/26/2010 10/29/2010 $525,453