North South Link Capacities Sales Organization Considering Future France – Spain Developments. 5 th SG meeting of S-GRI in Madrid. Context. ERGEG – South GRI : regional step for an opened gas market in Europe Increasing France-Spain interconnection capacities - PowerPoint PPT Presentation
Citation preview
GRTgaz
NorthSouth Link Capacities Sales Organization Considering Future France – Spain
Developments
5th SG meeting of S-GRI in Madrid
GRTgaz
Context
ERGEG – South GRI : regional step for an opened gas market in Europe
Increasing France-Spain interconnection capacities • TIGF-ENAGAS: Larrau and Biriatou (2013)• TIGF-GRTgaz-ENAGAS: new capacity MidCat
(2015)
GRTgaz
+55GWh/d in 2013 to Spain
+87GWh/d in 2013 to Spain
+180GWh/d in 2015 to Spain
230GWh/d end 2010
Capacities
+230GWh/d in 2015 to France
+165GWh/d in 2013 to France
+35GWh/d in 2013 to France
GRTgaz
Sales Capacities Mechanisms
OSP : for existing or decided capacities• Capacities sold for 4 years maximum• The aim : new market players would have the possibility to subscribe
capacities
OS : futures capacities• Ask the market • Engage shippers to subscribe the new capacities once available • Subscription period 10-15 years• The aim: helping investment decision
Both mechanisms will be used to ensure selling capacities in the NorthSouth link
Two different situations treated independently:• North to South Link• South to North Link
GRTgaz
North to South Link
Totally booked Link• Last OSP result (January 2008): demand exceeds offer, all capacities
subscribed• Capacity developments in the North zone (Tansières, LNG terminals…)
Open Season in 2008 for new capacities available on 1st January 2015
Until then, existing capacities will be sold by OSP
GRTgaz
North to South Link: Calendar
OSP mi-2010 (dispo avril 2011)
OSP mi-2011(dispo avril 2012)OSP mi-2012
(dispo avril 2013)
GRTgaz
South to North Link
Underbooked Link• Last OSP result (January 2008) : 10% of total capacities subscribed,
200GWh/d available after 2011• New capacities Larrau + Biriatou in 2013 : 200GWh/d• Other possible developments from now to 2015 :
MidCat Le Verdon Fos Storage South of France
Interconnection project with Spain: MidCat• Open Season in 2009 about South to North Link coordinated with MidCat• Additional needs in the North to South Link might be taken into account
Capacities available on 1st January 2015
Until then, existing capacities will be sold by OSP
Possible congestion on the South to North Link
Capacity South to North still available
GRTgaz
South to North Link: Calendar
GRTgaz
Schedule Proposal
2008 Open Season North to South Linkcapacities available on 1st January 2015
2009 Open Season South to North Link NS additional needs might be taken into account
capacities available on 1st January 2015
OSP in North to South Link until 1st January 2015• mid-2010 OSP North to South Link; capacities available in April 2011• mid-2011 OSP North to South Link; capacities available in April 2012• mid-2012 OSP North to South Link; capacities available in April 2013
OSP in South to North Link, until 1st January 2015• Existing capacities for identified needs until the end 2014• OSP every month