Activity ID Activity Name OriginalDuration
Start Finish
LS100 Engineering Re-start 0 18-Apr-13
LS110 Issue of final spec, BOQ & Good For
Construction drawing by Engg
135 18-Apr-13 30-Aug-13
Interior Wo
Interior Works and Customised Furnitures 166 18-Apr-13 30-Sep-13
IN100 Engineering Re-start 0 18-Apr-13
IN110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg
166 18-Apr-13 30-Sep-13
Chillers
Chillers 89 18-Apr-13 15-Jul-13
CH100 Engineering Re-start 0 18-Apr-13
CH110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg
89 18-Apr-13 15-Jul-13
AHU + Pu
AHU + Pumps + Lowside HVAC Works 105 18-Apr-13 31-Jul-13
HV100 Engineering Re-start 0 18-Apr-13
HV110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg
105 18-Apr-13 31-Jul-13
Electrificat
Electrification Works 105 18-Apr-13 31-Jul-13
EL310 Engineering Re-start 0 18-Apr-13
EL320 Issue of final spec, BOQ & Good ForConstruction drawing by Engg
105 18-Apr-13 31-Jul-13
Transform
Transformer Supply 105 18-Apr-13 31-Jul-13
TR100 Engineering Re-start 0 18-Apr-13
TR110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg
105 18-Apr-13 31-Jul-13
DG Set
DG Set 105 18-Apr-13 31-Jul-13
DG100 Engineering Re-start 0 18-Apr-13
DG110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg
105 18-Apr-13 31-Jul-13
UPS
UPS 166 18-Apr-13 30-Sep-13
UP100 Engineering Re-start 0 18-Apr-13UP110 Issue of final spec, BOQ & Good For
Construction drawing by Engg166 18-Apr-13 30-Sep-13
LT Panel
LT Panel 166 18-Apr-13 30-Sep-13
LT100 Engineering Re-start 0 18-Apr-13
LT110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg
166 18-Apr-13 30-Sep-13
IBMS and
IBMS and Fire Detection System 166 18-Apr-13 30-Sep-13
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
Engineering Re-start
30-Sep-13, Interior Works and Customised Fu
Engineering Re-start
15-Jul-13, Chillers
Engineering Re-start
31-Jul-13, AHU + Pumps + Lowside HVAC Works
Engineering Re-start
31-Jul-13, Electrification Works
Engineering Re-start
31-Jul-13, Transformer Supply
Engineering Re-start
31-Jul-13, DG Set
Engineering Re-start
30-Sep-13, UPS
Engineering Re-start
30-Sep-13, LT Panel
Engineering Re-start
30-Sep-13, IBMS and Fire Detection System
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 2 of 18 TASK filter: All Activities
Oracle Corporation
7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise
3/18
Activity ID Activity Name OriginalDuration
Start Finish
IB100 Engineering Re-start 0 18-Apr-13
IB110 Issue of final spec, BOQ & Good For
Construction drawing by Engg
166 18-Apr-13 30-Sep-13
Office Furn
Office Furnitures 196 18-Apr-13 30-Oct-13
OF100 Engineering Re-start 0 18-Apr-13
OF110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg
196 18-Apr-13 30-Oct-13
Office Chai
Office Chairs 227 18-Apr-13 30-Nov-13
OC100 Engineering Re-start 0 18-Apr-13
OC110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg
227 18-Apr-13 30-Nov-13
Loose Fur
Loose Furnitures( Chairs + Kitchen furnitures etc) 227 18-Apr-13 30-Nov-13
LF100 Engineering Re-start 0 18-Apr-13
LF110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg
227 18-Apr-13 30-Nov-13
Kitchen Eq
Kitchen Equipments 257 18-Apr-13 30-Dec-13
KE100 Engineering Re-start 0 18-Apr-13
KE110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg
257 18-Apr-13 30-Dec-13
Signage
Signage 257 18-Apr-13 30-Dec-13
SI100 Engineering Re-start 0 18-Apr-13
SI110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg
257 18-Apr-13 30-Dec-13
Horticulture
Horticulture 257 18-Apr-13 30-Dec-13
HO100 Engineering Re-start 0 18-Apr-13
HO110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg
257 18-Apr-13 30-Dec-13
Blinds/Proj
Blinds/Projectors 257 18-Apr-13 30-Dec-13
BP100 Engineering Re-start 0 18-Apr-13
BP110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg
257 18-Apr-13 30-Dec-13
VC Equipm
VC Equipments 257 18-Apr-13 30-Dec-13
VC100 Engineering Re-start 0 18-Apr-13
VC110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg
257 18-Apr-13 30-Dec-13
Admin Item
Admin Items 257 18-Apr-13 30-Dec-13
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
Engineering Re-start
30-Oct-13, Office Furnitures
Engineering Re-start
30-Nov-13, Office Chairs
Engineering Re-start
30-Nov-13, Loose Furnitures( Chairs +
Engineering Re-start
30-Dec-13, Kitchen Equipments
Engineering Re-start
30-Dec-13, Signage
Engineering Re-start
30-Dec-13, Horticulture
Engineering Re-start
30-Dec-13, Blinds/Projectors
Engineering Re-start
30-Dec-13, VC Equipments
Engineering Re-start
30-Dec-13, Admin Items
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 3 of 18 TASK filter: All Activities
Oracle Corporation
7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise
4/18
Activity ID Activity Name OriginalDuration
Start Finish
AD100 Engineering Re-start 0 18-Apr-13
AD110 Issue of final spec, BOQ & Good For
Construction drawing by Engg
257 18-Apr-13 30-Dec-13
Building OBuilding Occupancy/ Completion Certificate 257 18-Apr-13 30-Dec-13
OC310 Engineering Re-start 0 18-Apr-13
OC320 Issue of final spec, BOQ & Good ForConstruction drawing by Engg
257 18-Apr-13 30-Dec-13
No 2PackaNo 2Package 282 10-Jul-12 18-Apr-13
A1000 Start Of Project 0 10-Jul-12
A1010 Building Layout redesign basis MD's review atsite on 30.03.13
0 30-Mar-13
A1020 Tata Power reapproved building layout onrevised layout (Zero Date for Engineering)
0 18-Apr-13
ProcuremeProcurement -- Contracts & Commercial 836 17-Jul-12 30-Oct-14
No 3FloorsNo 3Floors 836 17-Jul-12 30-Oct-14
ConsultantConsultant/Architecture Finalisation 487 17-Jul-12 15-Nov-13
AR120 RFP 7 17-Jul-12 23-Jul-12
AR130 Receipt of Bid 14 24-Jul-12 06-Aug-12
AR140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 07-Aug-12 20-Aug-12
AR150 Commercial Negotiation by Contracts &Commercial
7 21-Aug-12 27-Aug-12
AR160 Vendor recommendation and OAF by Contractsand Commercial
7 28-Aug-12 03-Sep-12
AR170 Release of LOI/PO 7 04-Sep-12 10-Sep-12
AR180 NTP Date 0 11-Sep-12
AR190 Order Supply Completion 431 11-Sep-12 15-Nov-13Soil InvestiSoil Investigation 116 17-Jul-12 09-Nov-12
SO120 RFP 7 17-Jul-12 23-Jul-12
SO130 Receipt of Bid 14 24-Jul-12 06-Aug-12
SO140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 07-Aug-12 20-Aug-12
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
Engineering Re-start
30-Dec-13, Building Occupancy/ Co
Engineering Re-start
18-Apr-13, No 2Package
f Project
Building Layout redesign basis MD's review at site on 30.03.13
Tata Power reapproved building l ayout on revised layout (Zero
30-Oct-
30-Oct-
15-Nov-13, Consultant/Architecture Finali
TP Date
09-Nov-12, Soil Investigation
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 4 of 18 TASK filter: All Activities
Oracle Corporation
7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise
5/18
Activity ID Activity Name OriginalDuration
Start Finish
SO150 Commercial Negotiation by Contracts &Commercial
7 21-Aug-12 27-Aug-12
SO160 Vendor recommendation and OAF by Contractsand Commercial 7 28-Aug-12 03-Sep-12
SO170 Release of LOI/PO 7 04-Sep-12 10-Sep-12
SO180 NTP Date 0 11-Sep-12
SO190 Order Supply Completi on- soi l i nvestigati on 60 11-Sep-12 09-Nov-12
AR200 Finish- Soil investigation 0 09-Nov-12
Energy CoEnergy Consultant 210 03-Oct-12 30-Apr-13
EN120 RFP 7 03-Oct-12 09-Oct-12
EN130 Receipt of Bid 14 10-Oct-12 23-Oct-12
EN140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 24-Oct-12 06-Nov-12
EN150 Commercial Negotiation by Contracts &Commercial
7 07-Nov-12 13-Nov-12
EN160 Vendor recommendation and OAF by Contractsand Commercial
7 14-Nov-12 20-Nov-12
EN170 Release of LOI/PO 7 21-Nov-12 27-Nov-12
EN180 NTP Date 0 28-Nov-12EN190 Order Supply Completion 154 28-Nov-12 30-Apr-13
Sheet PilingSheet Piling 270 31-Aug-12 27-May-13
PL220 Order Erection Completion 270 31-Aug-12 27-May-13
PL120 RFP 7 25-Oct-12 31-Oct-12
PL130 Receipt of Bid 21 01-Nov-12 21-Nov-12
PL140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 22-Nov-12 05-Dec-12
PL150 Commercial Negotiation by Contracts &Commercial
7 06-Dec-12 12-Dec-12
PL160 Vendor recommendation and OAF by Contractsand Commercial
7 13-Dec-12 19-Dec-12
PL170 Release of LOI/PO 7 20-Dec-12 26-Dec-12
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
TP Date
Finish- Soil investigation
30-Apr-13, Energy Consultant
NTP Date
27-May-13, Sheet Pil ing
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 5 of 18 TASK filter: All Activities
Oracle Corporation
7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise
6/18
Activity ID Activity Name OriginalDuration
Start Finish
PL180 NTP Date 0 28-Jan-13
PL190 Order Supply Completion 90 28-Jan-13 27-Apr-13
PL200 Sheet Piling Completion 120 28-Jan-13 27-May-13
AR210 Finish--Sheet Piling 0 27-May-13
Civil & StrCivil & Structural Works 523 08-Feb-13 15-Jul-14
A1180 RFP 7 08-Feb-13 14-Feb-13
A1190 Receipt of Bid 14 15-Feb-13 28-Feb-13
A1200 Bid Clarification and evaluation(Technical +
Commercial) meeting ( Post Bid Meeting)
14 01-Mar-13 14-Mar-13
A1210 Commercial Negotiation by Contracts &Commercial
7 15-Mar-13 21-Mar-13
A1220 Vendor recommendation and OAF by Contractsand Commercial
7 22-Mar-13 28-Mar-13
A1230 Release of LOI/PO 7 29-Mar-13 04-Apr-13
A1240 NTP Date 0 15-Sep-13
A1250 Order Supply Completion 250 15-Sep-13 22-May-14
A1260 Order Erection Completion 270 19-Oct-13 15-Jul-14Elevators /Elevators / Lifts 476 25-Apr-13 13-Aug-14
EL110 RFP 7 25-Apr-13 01-May-13
EL120 Receipt of Bid 14 02-May-13 15-May-13
EL130 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 16-May-13 29-May-13
EL140 Commercial Negotiation by Contracts &Commercial
7 30-May-13 05-Jun-13
EL150 Vendor recommendation and OAF by Contractsand Commercial
7 06-Jun-13 12-Jun-13
EL160 Release of LOI/PO 7 13-Jun-13 19-Jun-13
EL180 NTP Date 0 15-Nov-13
EL190 Order Supply Completion 212 15-Nov-13 14-Jun-14
EL220 Order Erection Completion 220 06-Jan-14 13-Aug-14
PlumbingPlumbing Works and Fire protection System 372 31-Aug-13 06-Sep-14
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
NTP Date
Finish--Sheet Piling
15-Jul-14, Civil &
NTP Date
13-Aug-14, Ele
NTP Date
06-Sep-14, P
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 6 of 18 TASK filter: All Activities
Oracle Corporation
7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise
7/18
Activity ID Activity Name OriginalDuration
Start Finish
PF110 RFP 7 31-Aug-13 06-Sep-13
PF120 Receipt of Bid 21 07-Sep-13 27-Sep-13
PF130 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 28-Sep-13 11-Oct-13
PF140 Commercial Negotiation by Contracts &Commercial
14 12-Oct-13 25-Oct-13
PF150 Vendor recommendation and OAF by Contractsand Commercial
7 26-Oct-13 01-Nov-13
PF160 Release of LOI/PO 7 02-Nov-13 08-Nov-13
PF180 NTP Date 0 08-Mar-14
PF190 Order Supply Completion 150 08-Mar-14 04-Aug-14PF220 Order Erection Completion 150 10-Apr-14 06-Sep-14
STP & WTSTP & WTP(PHE) System 362 31-Aug-13 27-Aug-14
PH120 RFP 7 31-Aug-13 06-Sep-13
PH130 Receipt of Bid 21 07-Sep-13 27-Sep-13
PH140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 28-Sep-13 11-Oct-13
PH150 Commercial Negotiation by Contracts &Commercial 14 12-Oct-13 25-Oct-13
PH160 Vendor recommendation and OAF by Contractsand Commercial
7 26-Oct-13 01-Nov-13
PH170 Release of LOI/PO 7 02-Nov-13 08-Nov-13
PH180 NTP Date 0 01-Mar-14
PH190 Order Supply Completion 150 01-Mar-14 28-Jul-14
PH220 Order Erection Completion 150 31-Mar-14 27-Aug-14
Car Lifts &Car Lifts & Stackers 365 31-Aug-13 30-Aug-14LS120 RFP 7 31-Aug-13 06-Sep-13
LS130 Receipt of Bid 21 07-Sep-13 27-Sep-13
LS140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 28-Sep-13 11-Oct-13
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
NTP Date
27-Aug-14, S
NTP Date
30-Aug-14, C
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 7 of 18 TASK filter: All Activities
Oracle Corporation
7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise
8/18
Activity ID Activity Name OriginalDuration
Start Finish
LS150 Commercial Negotiation by Contracts &Commercial
14 12-Oct-13 25-Oct-13
LS160 Vendor recommendation and OAF by Contractsand Commercial 7 26-Oct-13 01-Nov-13
LS170 Release of LOI/PO 7 02-Nov-13 08-Nov-13
LS180 NTP Date 0 01-Mar-14
LS190 Order Supply Completion 153 01-Mar-14 31-Jul-14
LS220 Order Erection Completion 153 31-Mar-14 30-Aug-14
Interior WoInterior Works and Customised Furnitures 395 01-Oct-13 30-Oct-14
IN120 RFP 7 01-Oct-13 07-Oct-13
IN130 Receipt of Bid 21 08-Oct-13 28-Oct-13
IN140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 29-Oct-13 11-Nov-13
IN150 Commercial Negotiation by Contracts &Commercial
14 12-Nov-13 25-Nov-13
IN160 Vendor recommendation and OAF by Contractsand Commercial
7 26-Nov-13 02-Dec-13
IN170 Release of LOI/PO 7 03-Dec-13 09-Dec-13
IN220 Order Erection Completion 270 03-Feb-14 30-Oct-14
IN180 NTP Date 0 01-Apr-14
IN190 Order Supply Completion 150 01-Apr-14 28-Aug-14
ChillersChillers 395 16-Jul-13 14-Aug-14
CH120 RFP 7 16-Jul-13 22-Jul-13
CH130 Receipt of Bid 21 23-Jul-13 12-Aug-13
CH140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 13-Aug-13 26-Aug-13
CH150 Commercial Negotiation by Contracts &
Commercial
14 27-Aug-13 09-Sep-13
CH160 Vendor recommendation and OAF by Contractsand Commercial
7 10-Sep-13 16-Sep-13
CH170 Release of LOI/PO 7 17-Sep-13 23-Sep-13
CH180 NTP Date 0 02-Jan-14
CH190 Order Supply Completion 165 02-Jan-14 15-Jun-14
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
NTP Date
30-Oct-
NTP Date
14-Aug-14, Chi
NTP Date
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 8 of 18 TASK filter: All Activities
Oracle Corporation
7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise
9/18
Activity ID Activity Name OriginalDuration
Start Finish
CH220 Order Erection Completion 195 01-Feb-14 14-Aug-14
AHU + PuAHU + Pumps + Lowside HVAC Works 394 01-Aug-13 29-Aug-14HV120 RFP 7 01-Aug-13 07-Aug-13
HV130 Receipt of Bid 21 08-Aug-13 28-Aug-13
HV140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 29-Aug-13 11-Sep-13
HV150 Commercial Negotiation by Contracts &Commercial
14 12-Sep-13 25-Sep-13
HV160 Vendor recommendation and OAF by Contractsand Commercial
7 26-Sep-13 02-Oct-13
HV170 Release of LOI/PO 7 03-Oct-13 09-Oct-13
HV180 NTP Date 0 01-Feb-14
HV190 Order Supply Completion 90 03-Mar-14 31-May-14
HV220 Order Erection Completion 150 02-Apr-14 29-Aug-14
ElectrificatElectrification Works 441 01-Aug-13 15-Oct-14
EL330 RFP 7 01-Aug-13 07-Aug-13
EL340 Receipt of Bid 21 08-Aug-13 28-Aug-13
EL350 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 29-Aug-13 11-Sep-13
EL360 Commercial Negotiation by Contracts &Commercial
14 12-Sep-13 25-Sep-13
EL370 Vendor recommendation and OAF by Contractsand Commercial
7 26-Sep-13 02-Oct-13
EL380 Release of LOI/PO 7 03-Oct-13 09-Oct-13
EL390 NTP Date 0 01-Feb-14
EL400 Order Supply Completion 150 01-Feb-14 30-Jun-14EL430 Order Erection Completion 150 19-May-14 15-Oct-14
TransformTransformer Supply 426 01-Aug-13 30-Sep-14
TR120 RFP 7 01-Aug-13 07-Aug-13
TR130 Receipt of Bid 21 08-Aug-13 28-Aug-13
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
29-Aug-14, A
NTP Date
15-Oct-1
NTP Date
30-Sep-14
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 9 of 18 TASK filter: All Activities
Oracle Corporation
7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise
10/18
Activity ID Activity Name OriginalDuration
Start Finish
TR140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 29-Aug-13 11-Sep-13
TR150 Commercial Negotiation by Contracts &Commercial
14 12-Sep-13 25-Sep-13
TR160 Vendor recommendation and OAF by Contractsand Commercial
7 26-Sep-13 02-Oct-13
TR170 Release of LOI/PO 7 03-Oct-13 09-Oct-13
TR180 NTP Date 0 01-Feb-14
TR190 Order Supply Completion 180 01-Feb-14 30-Jul-14
TR220 Order Erection Completion 212 03-Mar-14 30-Sep-14
DG SetDG Set 426 01-Aug-13 30-Sep-14DG120 RFP 7 01-Aug-13 07-Aug-13
DG130 Receipt of Bid 21 08-Aug-13 28-Aug-13
DG140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 29-Aug-13 11-Sep-13
DG150 Commercial Negotiation by Contracts &Commercial
14 12-Sep-13 25-Sep-13
DG160 Vendor recommendation and OAF by Contractsand Commercial
7 26-Sep-13 02-Oct-13
DG170 Release of LOI/PO 7 03-Oct-13 09-Oct-13
DG180 NTP Date 0 01-Feb-14
DG190 Order Supply Completion 180 01-Feb-14 30-Jul-14
DG220 Order Erection Completion 212 03-Mar-14 30-Sep-14
UPSUPS 365 01-Oct-13 30-Sep-14
UP120 RFP 7 01-Oct-13 07-Oct-13
UP130 Receipt of Bid 21 08-Oct-13 28-Oct-13
UP140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 29-Oct-13 11-Nov-13
UP150 Commercial Negotiation by Contracts &Commercial
14 12-Nov-13 25-Nov-13
UP160 Vendor recommendation and OAF by Contractsand Commercial
7 26-Nov-13 02-Dec-13
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
NTP Date
30-Sep-14
NTP Date
30-Sep-14
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 10 of 18 TASK filter: All Activities
Oracle Corporation
7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise
11/18
Activity ID Activity Name OriginalDuration
Start Finish
UP170 Release of LOI/PO 7 03-Dec-13 09-Dec-13
UP180 NTP Date 0 01-Apr-14
UP190 Order Supply Completion 121 01-Apr-14 30-Jul-14
UP220 Order Erection Completion 153 01-May-14 30-Sep-14
LT PanelLT Panel 364 01-Oct-13 29-Sep-14
LT120 RFP 7 01-Oct-13 07-Oct-13
LT130 Receipt of Bid 21 08-Oct-13 28-Oct-13
LT140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 29-Oct-13 11-Nov-13
LT150 Commercial Negotiation by Contracts &Commercial
14 12-Nov-13 25-Nov-13
LT160 Vendor recommendation and OAF by Contractsand Commercial
7 26-Nov-13 02-Dec-13
LT170 Release of LOI/PO 7 03-Dec-13 09-Dec-13
LT180 NTP Date 0 03-Apr-14
LT190 Order Supply Completion 120 03-Apr-14 31-Jul-14
LT220 Order Erection Completion 150 03-May-14 29-Sep-14
IBMS andIBMS and Fire Detection System 380 01-Oct-13 15-Oct-14
IB120 RFP 7 01-Oct-13 07-Oct-13
IB130 Receipt of Bid 21 08-Oct-13 28-Oct-13
IB140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 29-Oct-13 11-Nov-13
IB150 Commercial Negotiation by Contracts &Commercial
14 12-Nov-13 25-Nov-13
IB160 Vendor recommendation and OAF by Contractsand Commercial
7 26-Nov-13 02-Dec-13
IB170 Release of LOI/PO 7 03-Dec-13 09-Dec-13
IB180 NTP Date 0 01-Apr-14
IB190 Order Supply Completion 120 01-Apr-14 29-Jul-14
IB220 Order Erection Completion 150 19-May-14 15-Oct-14
Office FurnOffice Furnitures 350 31-Oct-13 15-Oct-14
OF120 RFP 7 31-Oct-13 06-Nov-13
OF130 Receipt of Bid 21 07-Nov-13 27-Nov-13
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
NTP Date
29-Sep-14,
NTP Date
15-Oct-1
NTP Date
15-Oct-1
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 11 of 18 TASK filter: All Activities
Oracle Corporation
7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise
12/18
Activity ID Activity Name OriginalDuration
Start Finish
OF140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 28-Nov-13 11-Dec-13
OF150 Commercial Negotiation by Contracts &Commercial
14 12-Dec-13 25-Dec-13
OF160 Vendor recommendation and OAF by Contractsand Commercial
7 26-Dec-13 01-Jan-14
OF170 Release of LOI/PO 7 02-Jan-14 08-Jan-14
OF180 NTP Date 0 01-Jun-14
OF190 Order Supply Completion 60 01-Jun-14 30-Jul-14
OF220 Order Erection Completion 107 01-Jul-14 15-Oct-14
Office ChaiOffice Chairs 319 01-Dec-13 15-Oct-14
OC120 RFP 7 01-Dec-13 07-Dec-13
OC130 Receipt of Bid 21 08-Dec-13 28-Dec-13
OC140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 29-Dec-13 11-Jan-14
OC150 Commercial Negotiation by Contracts &Commercial
14 12-Jan-14 25-Jan-14
OC160 Vendor recommendation and OAF by Contractsand Commercial
7 26-Jan-14 01-Feb-14
OC170 Release of LOI/PO 7 02-Feb-14 08-Feb-14
OC180 NTP Date 0 01-Jun-14
OC190 Order Supply Completion 60 01-Jun-14 30-Jul-14
OC220 Order Erection Completion 107 01-Jul-14 15-Oct-14
Loose FurLoose Furnitures( Chairs + Kitchen furnitures etc) 319 01-Dec-13 15-Oct-14
LF120 RFP 7 01-Dec-13 07-Dec-13
LF130 Receipt of Bid 21 08-Dec-13 28-Dec-13LF140 Bid Clarification and evaluation(Technical +
Commercial) meeting ( Post Bid Meeting)14 29-Dec-13 11-Jan-14
LF150 Commercial Negotiation by Contracts &Commercial
14 12-Jan-14 25-Jan-14
LF160 Vendor recommendation and OAF by Contractsand Commercial
7 26-Jan-14 01-Feb-14
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
NTP Date
15-Oct-1
NTP Date
15-Oct-1
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 12 of 18 TASK filter: All Activities
Oracle Corporation
7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise
13/18
Activity ID Activity Name OriginalDuration
Start Finish
LF170 Release of LOI/PO 7 02-Feb-14 08-Feb-14
LF180 NTP Date 0 02-Jun-14
LF190 Order Supply Completion 60 02-Jun-14 31-Jul-14LF220 Order Erection Completion 106 02-Jul-14 15-Oct-14
Kitchen EqKitchen Equipments 300 31-Dec-13 26-Oct-14
KE120 RFP 7 31-Dec-13 06-Jan-14
KE130 Receipt of Bid 21 07-Jan-14 27-Jan-14
KE140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 28-Jan-14 10-Feb-14
KE150 Commercial Negotiation by Contracts &
Commercial
14 11-Feb-14 24-Feb-14
KE160 Vendor recommendation and OAF by Contractsand Commercial
7 25-Feb-14 03-Mar-14
KE170 Release of LOI/PO 7 04-Mar-14 10-Mar-14
KE180 NTP Date 0 30-May-14
KE190 Order Supply Completion 120 30-May-14 26-Sep-14
KE220 Order Erection Completion 120 29-Jun-14 26-Oct-14
SignageSignage 300 31-Dec-13 26-Oct-14
SI120 RFP 7 31-Dec-13 06-Jan-14
SI130 Receipt of Bid 21 07-Jan-14 27-Jan-14
SI140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 28-Jan-14 10-Feb-14
SI150 Commercial Negotiation by Contracts &Commercial
14 11-Feb-14 24-Feb-14
SI160 Vendor recommendation and OAF by Contrac 7 25-Feb-14 03-Mar-14
SI170 Release of LOI/PO 7 04-Mar-14 10-Mar-14
SI180 NTP Date 0 28-Aug-14
SI190 Order Supply Completion 15 28-Aug-14 11-Sep-14
SI220 Order Erection Completion 15 12-Oct-14 26-Oct-14
HorticultureHorticulture 300 31-Dec-13 26-Oct-14
HO120 RFP 7 31-Dec-13 06-Jan-14
HO130 Receipt of Bid 21 07-Jan-14 27-Jan-14
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
NTP Date
26-Oct-
NTP Date
26-Oct-
NTP Date
26-Oct-
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 13 of 18 TASK filter: All Activities
Oracle Corporation
7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise
14/18
Activity ID Activity Name OriginalDuration
Start Finish
HO140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 28-Jan-14 10-Feb-14
HO150 Commercial Negotiation by Contracts &Commercial
14 11-Feb-14 24-Feb-14
HO160 Vendor recommendation and OAF by Contractsand Commercial
7 25-Feb-14 03-Mar-14
HO170 Release of LOI/PO 7 04-Mar-14 10-Mar-14
HO180 NTP Date 0 18-Aug-14
HO190 Order Supply Completion 30 18-Aug-14 16-Sep-14
HO220 Order Erection Completion 60 28-Aug-14 26-Oct-14
Blinds/ProjBlinds/Projectors 299 31-Dec-13 25-Oct-14BP120 RFP 7 31-Dec-13 06-Jan-14
BP130 Receipt of Bid 21 07-Jan-14 27-Jan-14
BP140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 28-Jan-14 10-Feb-14
BP150 Commercial Negotiation by Contracts &Commercial
14 11-Feb-14 24-Feb-14
BP160 Vendor recommendation and OAF by Contractsand Commercial
7 25-Feb-14 03-Mar-14
BP170 Release of LOI/PO 7 04-Mar-14 10-Mar-14
BP180 NTP Date 0 28-Aug-14
BP190 Order Supply Completion 28 28-Aug-14 24-Sep-14
BP220 Order Erection Completion 30 26-Sep-14 25-Oct-14
VC EquipmVC Equipments 300 31-Dec-13 26-Oct-14
VC120 RFP 7 31-Dec-13 06-Jan-14
VC130 Receipt of Bid 21 07-Jan-14 27-Jan-14
VC140 Bid Clarification and evaluation(Technical +
Commercial) meeting ( Post Bid Meeting)
14 28-Jan-14 10-Feb-14
VC150 Commercial Negotiation by Contracts &Commercial
14 11-Feb-14 24-Feb-14
VC160 Vendor recommendation and OAF by Contractsand Commercial
7 25-Feb-14 03-Mar-14
VC170 Release of LOI/PO 7 04-Mar-14 10-Mar-14
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
NTP Date
25-Oct-
NTP Date
26-Oct-
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 14 of 18 TASK filter: All Activities
Oracle Corporation
7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise
15/18
Activity ID Activity Name OriginalDuration
Start Finish
VC180 NTP Date 0 28-Aug-14
VC190 Order Supply Completion 29 28-Aug-14 25-Sep-14
VC220 Order Erection Completion 30 27-Sep-14 26-Oct-14Admin ItemAdmin Items 295 31-Dec-13 21-Oct-14
AD120 RFP 7 31-Dec-13 06-Jan-14
AD130 Receipt of Bid 21 07-Jan-14 27-Jan-14
AD140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 28-Jan-14 10-Feb-14
AD150 Commercial Negotiation by Contracts &Commercial
14 11-Feb-14 24-Feb-14
ADI160 Vendor recommendation and OAF by Contractsand Commercial 7 25-Feb-14 03-Mar-14
AD170 Release of LOI/PO 7 04-Mar-14 10-Mar-14
AD180 NTP Date 0 28-Aug-14
AD190 Order Supply Completion 10 28-Aug-14 06-Sep-14
AD220 Order Erection Completion 15 07-Oct-14 21-Oct-14
Building OBuilding Occupancy/ Completion Certificate 290 31-Dec-13 16-Oct-14
OC330 RFP 7 31-Dec-13 06-Jan-14
OC340 Receipt of Bid 21 07-Jan-14 27-Jan-14
OC350 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)
14 28-Jan-14 10-Feb-14
OC360 Commercial Negotiation by Contracts &Commercial
14 11-Feb-14 24-Feb-14
OC370 Vendor recommendation and OAF by Contractsand Commercial
7 25-Feb-14 03-Mar-14
OC380 Release of LOI/PO 7 04-Mar-14 10-Mar-14
OC390 NTP Date 0 07-Sep-14
OC400 Order Supply Completion 30 07-Sep-14 06-Oct-14
OC430 Order Erection Completion 30 17-Sep-14 16-Oct-14
ConstructiConstruction-- Project Department 411 15-Sep-13 30-Oct-14
LB--LowerLB--Lower Basement 367 15-Sep-13 16-Sep-14
Civil & StrCivil & Structural Works 91 15-Sep-13 14-Dec-13
A1270 Excavation 30 15-Sep-13 14-Oct-13
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
NTP Date
21-Oct-1
NTP Date
16-Oct-1
NTP Date
30-Oct-
16-Sep-14,
14-Dec-13, Civil & Structural Works
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 15 of 18 TASK filter: All Activities
Oracle Corporation
7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise
16/18
Activity ID Activity Name OriginalDuration
Start Finish
AR220 Finish --Excavation 0 14-Oct-13
A1280 Lower Basement 61 15-Oct-13 14-Dec-13
AR230 Finish--Lower Basement 0 14-Dec-13PlumbingPlumbing Works and Fire protection System 31 08-Mar-14 07-Apr-14
PF210 Lower Basement 31 08-Mar-14 07-Apr-14
Interior WoInterior Works and Customised Furnitures 15 01-Apr-14 15-Apr-14
IN210 Lower Basement 15 01-Apr-14 15-Apr-14
AHU + PuAHU + Pumps + Lowside HVAC Works 50 18-Mar-14 06-May-14
HV210 Lower Basement 50 18-Mar-14 06-May-14
ElectrificatElectrification Works 28 01-Feb-14 28-Feb-14
EL420 Lower Basement 28 01-Feb-14 28-Feb-14
IBMS andIBMS and Fire Detection System 15 01-Apr-14 15-Apr-14
IB210 Lower Basement 15 01-Apr-14 15-Apr-14
SignageSignage 5 12-Sep-14 16-Sep-14
SI210 Lower Basement 5 12-Sep-14 16-Sep-14
Blinds/ProjBlinds/Projectors 6 10-Sep-14 15-Sep-14
BP210 Lower Basement 6 10-Sep-14 15-Sep-14
Admin ItemAdmin Items 5 07-Sep-14 11-Sep-14
AD210 Lower Basement 5 07-Sep-14 11-Sep-14
UB--UpperUB--Upper Basement 281 15-Dec-13 21-Sep-14
Civil & StrCivil & Structural Works 48 15-Dec-13 31-Jan-14
A1290 Upper Basement 48 15-Dec-13 31-Jan-14
AR240 Finish--Upper Basement 0 31-Jan-14
PlumbingPlumbing Works and Fire protection System 20 08-Apr-14 27-Apr-14
PF230 Upper Basement 20 08-Apr-14 27-Apr-14
Interior WoInterior Works and Customised Furnitures 15 16-Apr-14 30-Apr-14
IN230 Upper Basement 15 16-Apr-14 30-Apr-14
AHU + PuAHU + Pumps + Lowside HVAC Works 20 07-May-14 26-May-14
HV230 Upper Basement 20 07-May-14 26-May-14
ElectrificatElectrification Works 30 01-Mar-14 30-Mar-14
EL440 Upper Basement 30 01-Mar-14 30-Mar-14
IBMS andIBMS and Fire Detection System 15 16-Apr-14 30-Apr-14
IB230 Upper Basement 15 16-Apr-14 30-Apr-14
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
Finish --Excavation
Finish--Lower Basement07-Apr-14, Plumbing Works
15-Apr-14, Interior Works
06-May-14, AHU + Pump
28-Feb-14, Electrification Work
15-Apr-14, IBMS and Fire
16-Sep-14,
15-Sep-14,
11-Sep-14,
21-Sep-14,
31-Jan-14, Civil & Structural Wor
Finish--Upper Basement
27-Apr-14, Plumbing Wor
30-Apr-14, Interior Works
26-May-14, AHU + Pu
30-Mar-14, Electrification W
30-Apr-14, IBMS and Fire
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 16 of 18 TASK filter: All Activities
Oracle Corporation
7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise
17/18
Activity ID Activity Name OriginalDuration
Start Finish
SignageSignage 5 17-Sep-14 21-Sep-14
SI230 Upper Basement 5 17-Sep-14 21-Sep-14
Blinds/ProjBlinds/Projectors 5 16-Sep-14 20-Sep-14BP230 Upper Basement 5 16-Sep-14 20-Sep-14
Admin ItemAdmin Items 5 12-Sep-14 16-Sep-14
AD230 Upper Basement 5 12-Sep-14 16-Sep-14
GFL-- GroGFL-- Ground Floor 242 01-Feb-14 30-Sep-14
Civil & StrCivil & Structural Works 25 01-Feb-14 25-Feb-14
A1300 Ground Floor 25 01-Feb-14 25-Feb-14
AR250 Finish--Ground Floor 0 25-Feb-14
PlumbingPlumbing Works and Fire protection System 20 28-Apr-14 17-May-14PF240 Ground Floor 20 28-Apr-14 17-May-14
Interior WoInterior Works and Customised Furnitures 30 01-May-14 30-May-14
IN240 Ground Floor 30 01-May-14 30-May-14
AHU + PuAHU + Pumps + Lowside HVAC Works 15 27-May-14 10-Jun-14
HV240 Ground Floor 15 27-May-14 10-Jun-14
ElectrificatElectrification Works 30 31-Mar-14 29-Apr-14
EL450 Ground Floor 30 31-Mar-14 29-Apr-14
IBMS andIBMS and Fire Detection System 30 01-May-14 30-May-14
IB240 Ground Floor 30 01-May-14 30-May-14
SignageSignage 5 22-Sep-14 26-Sep-14
SI240 Ground Floor 5 22-Sep-14 26-Sep-14
Blinds/ProjBlinds/Projectors 5 21-Sep-14 25-Sep-14
BP240 Ground Floor 5 21-Sep-14 25-Sep-14
VC EquipmVC Equipments 5 26-Sep-14 30-Sep-14
VC240 Ground Floor 5 26-Sep-14 30-Sep-14
Admin ItemAdmin Items 5 17-Sep-14 21-Sep-14
AD240 Ground Floor 5 17-Sep-14 21-Sep-14
FFL-- 1st FFFL-- 1st Floor 222 26-Feb-14 05-Oct-14
Civil & StrCivil & Structural Works 26 26-Feb-14 23-Mar-14
A1310 1st Floor 26 26-Feb-14 23-Mar-14
AR260 Finish--1st Floor 0 23-Mar-14
PlumbingPlumbing Works and Fire protection System 15 18-May-14 01-Jun-14
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
21-Sep-14,
20-Sep-14,
16-Sep-14,
30-Sep-14
25-Feb-14, Civil & Structural W
Finish--Ground Floor
17-May-14, Plumbing W
30-May-14, Interior W
10-Jun-14, AHU + Pu
29-Apr-14, Electrification
30-May-14, IBMS and
26-Sep-14,
25-Sep-14,
30-Sep-14
21-Sep-14,
05-Oct-14
23-Mar-14, Civil & Structural
Finish--1st Floor
01-Jun-14, Plumbing
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 17 of 18 TASK filter: All Activities
Oracle Corporation
7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise
18/18
Activity ID Activity Name OriginalDuration
Start Finish
PF250 1st Floor 15 18-May-14 01-Jun-14
Interior WoInterior Works and Customised Furnitures 31 31-May-14 30-Jun-14
IN250 1st Floor 31 31-May-14 30-Jun-14AHU + PuAHU + Pumps + Lowside HVAC Works 15 11-Jun-14 25-Jun-14
HV250 1st Floor 15 11-Jun-14 25-Jun-14
ElectrificatElectrification Works 32 30-Apr-14 31-May-14
EL460 1st Floor 32 30-Apr-14 31-May-14
IBMS andIBMS and Fire Detection System 31 31-May-14 30-Jun-14
IB250 1st Floor 31 31-May-14 30-Jun-14
SignageSignage 5 27-Sep-14 01-Oct-14
SI250 1st Floor 5 27-Sep-14 01-Oct-14
Blinds/ProjBlinds/Projectors 5 26-Sep-14 30-Sep-14
BP250 1st Floor 5 26-Sep-14 30-Sep-14
VC EquipmVC Equipments 5 01-Oct-14 05-Oct-14
VC250 1st Floor 5 01-Oct-14 05-Oct-14
Admin ItemAdmin Items 5 22-Sep-14 26-Sep-14
AD250 1st Floor 5 22-Sep-14 26-Sep-14
SFL-- 2ndSFL-- 2nd Floor 201 24-Mar-14 10-Oct-14
TFL-- 3rdTFL-- 3rd Floor178 21-Apr-14 15-Oct-14
FFL -- 4thFFL -- 4th Floor 158 16-May-14 20-Oct-14
FFL -- 5thFFL -- 5th Floor 137 11-Jun-14 25-Oct-14
Roof + MuRoof + Mumty Floor 127 26-Jun-14 30-Oct-14
O N D J F M A M J J A S O N D J F M A M J J A S O N D J
2013 2014 15
30-Jun-14, Interior
25-Jun-14, AHU + P
31-May-14, Electrificat
30-Jun-14, IBMS an
01-Oct-14,
30-Sep-14
05-Oct-14
26-Sep-14,
10-Oct-1Finish--2 nd Floor
15-Oct-1Finish-3 rd Floor
20-Oct-1Finish--4 th Floor
25-Oct-Finish --5 th Floor
30-Oct-Finish--Roof + M
Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43
Actual Work
Remaining Work
Critical Remaining ...
Milestone
Page 18 of 18 TASK filter: All Activities