NOBP Schedule- EPC-Floor Wise- Packagewise

Embed Size (px)

Citation preview

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    1/18

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    2/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    LS100 Engineering Re-start 0 18-Apr-13

    LS110 Issue of final spec, BOQ & Good For

    Construction drawing by Engg

    135 18-Apr-13 30-Aug-13

    Interior Wo

    Interior Works and Customised Furnitures 166 18-Apr-13 30-Sep-13

    IN100 Engineering Re-start 0 18-Apr-13

    IN110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg

    166 18-Apr-13 30-Sep-13

    Chillers

    Chillers 89 18-Apr-13 15-Jul-13

    CH100 Engineering Re-start 0 18-Apr-13

    CH110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg

    89 18-Apr-13 15-Jul-13

    AHU + Pu

    AHU + Pumps + Lowside HVAC Works 105 18-Apr-13 31-Jul-13

    HV100 Engineering Re-start 0 18-Apr-13

    HV110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg

    105 18-Apr-13 31-Jul-13

    Electrificat

    Electrification Works 105 18-Apr-13 31-Jul-13

    EL310 Engineering Re-start 0 18-Apr-13

    EL320 Issue of final spec, BOQ & Good ForConstruction drawing by Engg

    105 18-Apr-13 31-Jul-13

    Transform

    Transformer Supply 105 18-Apr-13 31-Jul-13

    TR100 Engineering Re-start 0 18-Apr-13

    TR110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg

    105 18-Apr-13 31-Jul-13

    DG Set

    DG Set 105 18-Apr-13 31-Jul-13

    DG100 Engineering Re-start 0 18-Apr-13

    DG110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg

    105 18-Apr-13 31-Jul-13

    UPS

    UPS 166 18-Apr-13 30-Sep-13

    UP100 Engineering Re-start 0 18-Apr-13UP110 Issue of final spec, BOQ & Good For

    Construction drawing by Engg166 18-Apr-13 30-Sep-13

    LT Panel

    LT Panel 166 18-Apr-13 30-Sep-13

    LT100 Engineering Re-start 0 18-Apr-13

    LT110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg

    166 18-Apr-13 30-Sep-13

    IBMS and

    IBMS and Fire Detection System 166 18-Apr-13 30-Sep-13

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    Engineering Re-start

    30-Sep-13, Interior Works and Customised Fu

    Engineering Re-start

    15-Jul-13, Chillers

    Engineering Re-start

    31-Jul-13, AHU + Pumps + Lowside HVAC Works

    Engineering Re-start

    31-Jul-13, Electrification Works

    Engineering Re-start

    31-Jul-13, Transformer Supply

    Engineering Re-start

    31-Jul-13, DG Set

    Engineering Re-start

    30-Sep-13, UPS

    Engineering Re-start

    30-Sep-13, LT Panel

    Engineering Re-start

    30-Sep-13, IBMS and Fire Detection System

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 2 of 18 TASK filter: All Activities

    Oracle Corporation

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    3/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    IB100 Engineering Re-start 0 18-Apr-13

    IB110 Issue of final spec, BOQ & Good For

    Construction drawing by Engg

    166 18-Apr-13 30-Sep-13

    Office Furn

    Office Furnitures 196 18-Apr-13 30-Oct-13

    OF100 Engineering Re-start 0 18-Apr-13

    OF110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg

    196 18-Apr-13 30-Oct-13

    Office Chai

    Office Chairs 227 18-Apr-13 30-Nov-13

    OC100 Engineering Re-start 0 18-Apr-13

    OC110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg

    227 18-Apr-13 30-Nov-13

    Loose Fur

    Loose Furnitures( Chairs + Kitchen furnitures etc) 227 18-Apr-13 30-Nov-13

    LF100 Engineering Re-start 0 18-Apr-13

    LF110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg

    227 18-Apr-13 30-Nov-13

    Kitchen Eq

    Kitchen Equipments 257 18-Apr-13 30-Dec-13

    KE100 Engineering Re-start 0 18-Apr-13

    KE110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg

    257 18-Apr-13 30-Dec-13

    Signage

    Signage 257 18-Apr-13 30-Dec-13

    SI100 Engineering Re-start 0 18-Apr-13

    SI110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg

    257 18-Apr-13 30-Dec-13

    Horticulture

    Horticulture 257 18-Apr-13 30-Dec-13

    HO100 Engineering Re-start 0 18-Apr-13

    HO110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg

    257 18-Apr-13 30-Dec-13

    Blinds/Proj

    Blinds/Projectors 257 18-Apr-13 30-Dec-13

    BP100 Engineering Re-start 0 18-Apr-13

    BP110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg

    257 18-Apr-13 30-Dec-13

    VC Equipm

    VC Equipments 257 18-Apr-13 30-Dec-13

    VC100 Engineering Re-start 0 18-Apr-13

    VC110 Issue of final spec, BOQ & Good ForConstruction drawing by Engg

    257 18-Apr-13 30-Dec-13

    Admin Item

    Admin Items 257 18-Apr-13 30-Dec-13

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    Engineering Re-start

    30-Oct-13, Office Furnitures

    Engineering Re-start

    30-Nov-13, Office Chairs

    Engineering Re-start

    30-Nov-13, Loose Furnitures( Chairs +

    Engineering Re-start

    30-Dec-13, Kitchen Equipments

    Engineering Re-start

    30-Dec-13, Signage

    Engineering Re-start

    30-Dec-13, Horticulture

    Engineering Re-start

    30-Dec-13, Blinds/Projectors

    Engineering Re-start

    30-Dec-13, VC Equipments

    Engineering Re-start

    30-Dec-13, Admin Items

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 3 of 18 TASK filter: All Activities

    Oracle Corporation

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    4/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    AD100 Engineering Re-start 0 18-Apr-13

    AD110 Issue of final spec, BOQ & Good For

    Construction drawing by Engg

    257 18-Apr-13 30-Dec-13

    Building OBuilding Occupancy/ Completion Certificate 257 18-Apr-13 30-Dec-13

    OC310 Engineering Re-start 0 18-Apr-13

    OC320 Issue of final spec, BOQ & Good ForConstruction drawing by Engg

    257 18-Apr-13 30-Dec-13

    No 2PackaNo 2Package 282 10-Jul-12 18-Apr-13

    A1000 Start Of Project 0 10-Jul-12

    A1010 Building Layout redesign basis MD's review atsite on 30.03.13

    0 30-Mar-13

    A1020 Tata Power reapproved building layout onrevised layout (Zero Date for Engineering)

    0 18-Apr-13

    ProcuremeProcurement -- Contracts & Commercial 836 17-Jul-12 30-Oct-14

    No 3FloorsNo 3Floors 836 17-Jul-12 30-Oct-14

    ConsultantConsultant/Architecture Finalisation 487 17-Jul-12 15-Nov-13

    AR120 RFP 7 17-Jul-12 23-Jul-12

    AR130 Receipt of Bid 14 24-Jul-12 06-Aug-12

    AR140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 07-Aug-12 20-Aug-12

    AR150 Commercial Negotiation by Contracts &Commercial

    7 21-Aug-12 27-Aug-12

    AR160 Vendor recommendation and OAF by Contractsand Commercial

    7 28-Aug-12 03-Sep-12

    AR170 Release of LOI/PO 7 04-Sep-12 10-Sep-12

    AR180 NTP Date 0 11-Sep-12

    AR190 Order Supply Completion 431 11-Sep-12 15-Nov-13Soil InvestiSoil Investigation 116 17-Jul-12 09-Nov-12

    SO120 RFP 7 17-Jul-12 23-Jul-12

    SO130 Receipt of Bid 14 24-Jul-12 06-Aug-12

    SO140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 07-Aug-12 20-Aug-12

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    Engineering Re-start

    30-Dec-13, Building Occupancy/ Co

    Engineering Re-start

    18-Apr-13, No 2Package

    f Project

    Building Layout redesign basis MD's review at site on 30.03.13

    Tata Power reapproved building l ayout on revised layout (Zero

    30-Oct-

    30-Oct-

    15-Nov-13, Consultant/Architecture Finali

    TP Date

    09-Nov-12, Soil Investigation

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 4 of 18 TASK filter: All Activities

    Oracle Corporation

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    5/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    SO150 Commercial Negotiation by Contracts &Commercial

    7 21-Aug-12 27-Aug-12

    SO160 Vendor recommendation and OAF by Contractsand Commercial 7 28-Aug-12 03-Sep-12

    SO170 Release of LOI/PO 7 04-Sep-12 10-Sep-12

    SO180 NTP Date 0 11-Sep-12

    SO190 Order Supply Completi on- soi l i nvestigati on 60 11-Sep-12 09-Nov-12

    AR200 Finish- Soil investigation 0 09-Nov-12

    Energy CoEnergy Consultant 210 03-Oct-12 30-Apr-13

    EN120 RFP 7 03-Oct-12 09-Oct-12

    EN130 Receipt of Bid 14 10-Oct-12 23-Oct-12

    EN140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 24-Oct-12 06-Nov-12

    EN150 Commercial Negotiation by Contracts &Commercial

    7 07-Nov-12 13-Nov-12

    EN160 Vendor recommendation and OAF by Contractsand Commercial

    7 14-Nov-12 20-Nov-12

    EN170 Release of LOI/PO 7 21-Nov-12 27-Nov-12

    EN180 NTP Date 0 28-Nov-12EN190 Order Supply Completion 154 28-Nov-12 30-Apr-13

    Sheet PilingSheet Piling 270 31-Aug-12 27-May-13

    PL220 Order Erection Completion 270 31-Aug-12 27-May-13

    PL120 RFP 7 25-Oct-12 31-Oct-12

    PL130 Receipt of Bid 21 01-Nov-12 21-Nov-12

    PL140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 22-Nov-12 05-Dec-12

    PL150 Commercial Negotiation by Contracts &Commercial

    7 06-Dec-12 12-Dec-12

    PL160 Vendor recommendation and OAF by Contractsand Commercial

    7 13-Dec-12 19-Dec-12

    PL170 Release of LOI/PO 7 20-Dec-12 26-Dec-12

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    TP Date

    Finish- Soil investigation

    30-Apr-13, Energy Consultant

    NTP Date

    27-May-13, Sheet Pil ing

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 5 of 18 TASK filter: All Activities

    Oracle Corporation

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    6/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    PL180 NTP Date 0 28-Jan-13

    PL190 Order Supply Completion 90 28-Jan-13 27-Apr-13

    PL200 Sheet Piling Completion 120 28-Jan-13 27-May-13

    AR210 Finish--Sheet Piling 0 27-May-13

    Civil & StrCivil & Structural Works 523 08-Feb-13 15-Jul-14

    A1180 RFP 7 08-Feb-13 14-Feb-13

    A1190 Receipt of Bid 14 15-Feb-13 28-Feb-13

    A1200 Bid Clarification and evaluation(Technical +

    Commercial) meeting ( Post Bid Meeting)

    14 01-Mar-13 14-Mar-13

    A1210 Commercial Negotiation by Contracts &Commercial

    7 15-Mar-13 21-Mar-13

    A1220 Vendor recommendation and OAF by Contractsand Commercial

    7 22-Mar-13 28-Mar-13

    A1230 Release of LOI/PO 7 29-Mar-13 04-Apr-13

    A1240 NTP Date 0 15-Sep-13

    A1250 Order Supply Completion 250 15-Sep-13 22-May-14

    A1260 Order Erection Completion 270 19-Oct-13 15-Jul-14Elevators /Elevators / Lifts 476 25-Apr-13 13-Aug-14

    EL110 RFP 7 25-Apr-13 01-May-13

    EL120 Receipt of Bid 14 02-May-13 15-May-13

    EL130 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 16-May-13 29-May-13

    EL140 Commercial Negotiation by Contracts &Commercial

    7 30-May-13 05-Jun-13

    EL150 Vendor recommendation and OAF by Contractsand Commercial

    7 06-Jun-13 12-Jun-13

    EL160 Release of LOI/PO 7 13-Jun-13 19-Jun-13

    EL180 NTP Date 0 15-Nov-13

    EL190 Order Supply Completion 212 15-Nov-13 14-Jun-14

    EL220 Order Erection Completion 220 06-Jan-14 13-Aug-14

    PlumbingPlumbing Works and Fire protection System 372 31-Aug-13 06-Sep-14

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    NTP Date

    Finish--Sheet Piling

    15-Jul-14, Civil &

    NTP Date

    13-Aug-14, Ele

    NTP Date

    06-Sep-14, P

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 6 of 18 TASK filter: All Activities

    Oracle Corporation

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    7/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    PF110 RFP 7 31-Aug-13 06-Sep-13

    PF120 Receipt of Bid 21 07-Sep-13 27-Sep-13

    PF130 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 28-Sep-13 11-Oct-13

    PF140 Commercial Negotiation by Contracts &Commercial

    14 12-Oct-13 25-Oct-13

    PF150 Vendor recommendation and OAF by Contractsand Commercial

    7 26-Oct-13 01-Nov-13

    PF160 Release of LOI/PO 7 02-Nov-13 08-Nov-13

    PF180 NTP Date 0 08-Mar-14

    PF190 Order Supply Completion 150 08-Mar-14 04-Aug-14PF220 Order Erection Completion 150 10-Apr-14 06-Sep-14

    STP & WTSTP & WTP(PHE) System 362 31-Aug-13 27-Aug-14

    PH120 RFP 7 31-Aug-13 06-Sep-13

    PH130 Receipt of Bid 21 07-Sep-13 27-Sep-13

    PH140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 28-Sep-13 11-Oct-13

    PH150 Commercial Negotiation by Contracts &Commercial 14 12-Oct-13 25-Oct-13

    PH160 Vendor recommendation and OAF by Contractsand Commercial

    7 26-Oct-13 01-Nov-13

    PH170 Release of LOI/PO 7 02-Nov-13 08-Nov-13

    PH180 NTP Date 0 01-Mar-14

    PH190 Order Supply Completion 150 01-Mar-14 28-Jul-14

    PH220 Order Erection Completion 150 31-Mar-14 27-Aug-14

    Car Lifts &Car Lifts & Stackers 365 31-Aug-13 30-Aug-14LS120 RFP 7 31-Aug-13 06-Sep-13

    LS130 Receipt of Bid 21 07-Sep-13 27-Sep-13

    LS140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 28-Sep-13 11-Oct-13

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    NTP Date

    27-Aug-14, S

    NTP Date

    30-Aug-14, C

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 7 of 18 TASK filter: All Activities

    Oracle Corporation

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    8/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    LS150 Commercial Negotiation by Contracts &Commercial

    14 12-Oct-13 25-Oct-13

    LS160 Vendor recommendation and OAF by Contractsand Commercial 7 26-Oct-13 01-Nov-13

    LS170 Release of LOI/PO 7 02-Nov-13 08-Nov-13

    LS180 NTP Date 0 01-Mar-14

    LS190 Order Supply Completion 153 01-Mar-14 31-Jul-14

    LS220 Order Erection Completion 153 31-Mar-14 30-Aug-14

    Interior WoInterior Works and Customised Furnitures 395 01-Oct-13 30-Oct-14

    IN120 RFP 7 01-Oct-13 07-Oct-13

    IN130 Receipt of Bid 21 08-Oct-13 28-Oct-13

    IN140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 29-Oct-13 11-Nov-13

    IN150 Commercial Negotiation by Contracts &Commercial

    14 12-Nov-13 25-Nov-13

    IN160 Vendor recommendation and OAF by Contractsand Commercial

    7 26-Nov-13 02-Dec-13

    IN170 Release of LOI/PO 7 03-Dec-13 09-Dec-13

    IN220 Order Erection Completion 270 03-Feb-14 30-Oct-14

    IN180 NTP Date 0 01-Apr-14

    IN190 Order Supply Completion 150 01-Apr-14 28-Aug-14

    ChillersChillers 395 16-Jul-13 14-Aug-14

    CH120 RFP 7 16-Jul-13 22-Jul-13

    CH130 Receipt of Bid 21 23-Jul-13 12-Aug-13

    CH140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 13-Aug-13 26-Aug-13

    CH150 Commercial Negotiation by Contracts &

    Commercial

    14 27-Aug-13 09-Sep-13

    CH160 Vendor recommendation and OAF by Contractsand Commercial

    7 10-Sep-13 16-Sep-13

    CH170 Release of LOI/PO 7 17-Sep-13 23-Sep-13

    CH180 NTP Date 0 02-Jan-14

    CH190 Order Supply Completion 165 02-Jan-14 15-Jun-14

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    NTP Date

    30-Oct-

    NTP Date

    14-Aug-14, Chi

    NTP Date

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 8 of 18 TASK filter: All Activities

    Oracle Corporation

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    9/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    CH220 Order Erection Completion 195 01-Feb-14 14-Aug-14

    AHU + PuAHU + Pumps + Lowside HVAC Works 394 01-Aug-13 29-Aug-14HV120 RFP 7 01-Aug-13 07-Aug-13

    HV130 Receipt of Bid 21 08-Aug-13 28-Aug-13

    HV140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 29-Aug-13 11-Sep-13

    HV150 Commercial Negotiation by Contracts &Commercial

    14 12-Sep-13 25-Sep-13

    HV160 Vendor recommendation and OAF by Contractsand Commercial

    7 26-Sep-13 02-Oct-13

    HV170 Release of LOI/PO 7 03-Oct-13 09-Oct-13

    HV180 NTP Date 0 01-Feb-14

    HV190 Order Supply Completion 90 03-Mar-14 31-May-14

    HV220 Order Erection Completion 150 02-Apr-14 29-Aug-14

    ElectrificatElectrification Works 441 01-Aug-13 15-Oct-14

    EL330 RFP 7 01-Aug-13 07-Aug-13

    EL340 Receipt of Bid 21 08-Aug-13 28-Aug-13

    EL350 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 29-Aug-13 11-Sep-13

    EL360 Commercial Negotiation by Contracts &Commercial

    14 12-Sep-13 25-Sep-13

    EL370 Vendor recommendation and OAF by Contractsand Commercial

    7 26-Sep-13 02-Oct-13

    EL380 Release of LOI/PO 7 03-Oct-13 09-Oct-13

    EL390 NTP Date 0 01-Feb-14

    EL400 Order Supply Completion 150 01-Feb-14 30-Jun-14EL430 Order Erection Completion 150 19-May-14 15-Oct-14

    TransformTransformer Supply 426 01-Aug-13 30-Sep-14

    TR120 RFP 7 01-Aug-13 07-Aug-13

    TR130 Receipt of Bid 21 08-Aug-13 28-Aug-13

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    29-Aug-14, A

    NTP Date

    15-Oct-1

    NTP Date

    30-Sep-14

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 9 of 18 TASK filter: All Activities

    Oracle Corporation

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    10/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    TR140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 29-Aug-13 11-Sep-13

    TR150 Commercial Negotiation by Contracts &Commercial

    14 12-Sep-13 25-Sep-13

    TR160 Vendor recommendation and OAF by Contractsand Commercial

    7 26-Sep-13 02-Oct-13

    TR170 Release of LOI/PO 7 03-Oct-13 09-Oct-13

    TR180 NTP Date 0 01-Feb-14

    TR190 Order Supply Completion 180 01-Feb-14 30-Jul-14

    TR220 Order Erection Completion 212 03-Mar-14 30-Sep-14

    DG SetDG Set 426 01-Aug-13 30-Sep-14DG120 RFP 7 01-Aug-13 07-Aug-13

    DG130 Receipt of Bid 21 08-Aug-13 28-Aug-13

    DG140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 29-Aug-13 11-Sep-13

    DG150 Commercial Negotiation by Contracts &Commercial

    14 12-Sep-13 25-Sep-13

    DG160 Vendor recommendation and OAF by Contractsand Commercial

    7 26-Sep-13 02-Oct-13

    DG170 Release of LOI/PO 7 03-Oct-13 09-Oct-13

    DG180 NTP Date 0 01-Feb-14

    DG190 Order Supply Completion 180 01-Feb-14 30-Jul-14

    DG220 Order Erection Completion 212 03-Mar-14 30-Sep-14

    UPSUPS 365 01-Oct-13 30-Sep-14

    UP120 RFP 7 01-Oct-13 07-Oct-13

    UP130 Receipt of Bid 21 08-Oct-13 28-Oct-13

    UP140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 29-Oct-13 11-Nov-13

    UP150 Commercial Negotiation by Contracts &Commercial

    14 12-Nov-13 25-Nov-13

    UP160 Vendor recommendation and OAF by Contractsand Commercial

    7 26-Nov-13 02-Dec-13

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    NTP Date

    30-Sep-14

    NTP Date

    30-Sep-14

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 10 of 18 TASK filter: All Activities

    Oracle Corporation

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    11/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    UP170 Release of LOI/PO 7 03-Dec-13 09-Dec-13

    UP180 NTP Date 0 01-Apr-14

    UP190 Order Supply Completion 121 01-Apr-14 30-Jul-14

    UP220 Order Erection Completion 153 01-May-14 30-Sep-14

    LT PanelLT Panel 364 01-Oct-13 29-Sep-14

    LT120 RFP 7 01-Oct-13 07-Oct-13

    LT130 Receipt of Bid 21 08-Oct-13 28-Oct-13

    LT140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 29-Oct-13 11-Nov-13

    LT150 Commercial Negotiation by Contracts &Commercial

    14 12-Nov-13 25-Nov-13

    LT160 Vendor recommendation and OAF by Contractsand Commercial

    7 26-Nov-13 02-Dec-13

    LT170 Release of LOI/PO 7 03-Dec-13 09-Dec-13

    LT180 NTP Date 0 03-Apr-14

    LT190 Order Supply Completion 120 03-Apr-14 31-Jul-14

    LT220 Order Erection Completion 150 03-May-14 29-Sep-14

    IBMS andIBMS and Fire Detection System 380 01-Oct-13 15-Oct-14

    IB120 RFP 7 01-Oct-13 07-Oct-13

    IB130 Receipt of Bid 21 08-Oct-13 28-Oct-13

    IB140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 29-Oct-13 11-Nov-13

    IB150 Commercial Negotiation by Contracts &Commercial

    14 12-Nov-13 25-Nov-13

    IB160 Vendor recommendation and OAF by Contractsand Commercial

    7 26-Nov-13 02-Dec-13

    IB170 Release of LOI/PO 7 03-Dec-13 09-Dec-13

    IB180 NTP Date 0 01-Apr-14

    IB190 Order Supply Completion 120 01-Apr-14 29-Jul-14

    IB220 Order Erection Completion 150 19-May-14 15-Oct-14

    Office FurnOffice Furnitures 350 31-Oct-13 15-Oct-14

    OF120 RFP 7 31-Oct-13 06-Nov-13

    OF130 Receipt of Bid 21 07-Nov-13 27-Nov-13

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    NTP Date

    29-Sep-14,

    NTP Date

    15-Oct-1

    NTP Date

    15-Oct-1

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 11 of 18 TASK filter: All Activities

    Oracle Corporation

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    12/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    OF140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 28-Nov-13 11-Dec-13

    OF150 Commercial Negotiation by Contracts &Commercial

    14 12-Dec-13 25-Dec-13

    OF160 Vendor recommendation and OAF by Contractsand Commercial

    7 26-Dec-13 01-Jan-14

    OF170 Release of LOI/PO 7 02-Jan-14 08-Jan-14

    OF180 NTP Date 0 01-Jun-14

    OF190 Order Supply Completion 60 01-Jun-14 30-Jul-14

    OF220 Order Erection Completion 107 01-Jul-14 15-Oct-14

    Office ChaiOffice Chairs 319 01-Dec-13 15-Oct-14

    OC120 RFP 7 01-Dec-13 07-Dec-13

    OC130 Receipt of Bid 21 08-Dec-13 28-Dec-13

    OC140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 29-Dec-13 11-Jan-14

    OC150 Commercial Negotiation by Contracts &Commercial

    14 12-Jan-14 25-Jan-14

    OC160 Vendor recommendation and OAF by Contractsand Commercial

    7 26-Jan-14 01-Feb-14

    OC170 Release of LOI/PO 7 02-Feb-14 08-Feb-14

    OC180 NTP Date 0 01-Jun-14

    OC190 Order Supply Completion 60 01-Jun-14 30-Jul-14

    OC220 Order Erection Completion 107 01-Jul-14 15-Oct-14

    Loose FurLoose Furnitures( Chairs + Kitchen furnitures etc) 319 01-Dec-13 15-Oct-14

    LF120 RFP 7 01-Dec-13 07-Dec-13

    LF130 Receipt of Bid 21 08-Dec-13 28-Dec-13LF140 Bid Clarification and evaluation(Technical +

    Commercial) meeting ( Post Bid Meeting)14 29-Dec-13 11-Jan-14

    LF150 Commercial Negotiation by Contracts &Commercial

    14 12-Jan-14 25-Jan-14

    LF160 Vendor recommendation and OAF by Contractsand Commercial

    7 26-Jan-14 01-Feb-14

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    NTP Date

    15-Oct-1

    NTP Date

    15-Oct-1

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 12 of 18 TASK filter: All Activities

    Oracle Corporation

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    13/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    LF170 Release of LOI/PO 7 02-Feb-14 08-Feb-14

    LF180 NTP Date 0 02-Jun-14

    LF190 Order Supply Completion 60 02-Jun-14 31-Jul-14LF220 Order Erection Completion 106 02-Jul-14 15-Oct-14

    Kitchen EqKitchen Equipments 300 31-Dec-13 26-Oct-14

    KE120 RFP 7 31-Dec-13 06-Jan-14

    KE130 Receipt of Bid 21 07-Jan-14 27-Jan-14

    KE140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 28-Jan-14 10-Feb-14

    KE150 Commercial Negotiation by Contracts &

    Commercial

    14 11-Feb-14 24-Feb-14

    KE160 Vendor recommendation and OAF by Contractsand Commercial

    7 25-Feb-14 03-Mar-14

    KE170 Release of LOI/PO 7 04-Mar-14 10-Mar-14

    KE180 NTP Date 0 30-May-14

    KE190 Order Supply Completion 120 30-May-14 26-Sep-14

    KE220 Order Erection Completion 120 29-Jun-14 26-Oct-14

    SignageSignage 300 31-Dec-13 26-Oct-14

    SI120 RFP 7 31-Dec-13 06-Jan-14

    SI130 Receipt of Bid 21 07-Jan-14 27-Jan-14

    SI140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 28-Jan-14 10-Feb-14

    SI150 Commercial Negotiation by Contracts &Commercial

    14 11-Feb-14 24-Feb-14

    SI160 Vendor recommendation and OAF by Contrac 7 25-Feb-14 03-Mar-14

    SI170 Release of LOI/PO 7 04-Mar-14 10-Mar-14

    SI180 NTP Date 0 28-Aug-14

    SI190 Order Supply Completion 15 28-Aug-14 11-Sep-14

    SI220 Order Erection Completion 15 12-Oct-14 26-Oct-14

    HorticultureHorticulture 300 31-Dec-13 26-Oct-14

    HO120 RFP 7 31-Dec-13 06-Jan-14

    HO130 Receipt of Bid 21 07-Jan-14 27-Jan-14

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    NTP Date

    26-Oct-

    NTP Date

    26-Oct-

    NTP Date

    26-Oct-

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 13 of 18 TASK filter: All Activities

    Oracle Corporation

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    14/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    HO140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 28-Jan-14 10-Feb-14

    HO150 Commercial Negotiation by Contracts &Commercial

    14 11-Feb-14 24-Feb-14

    HO160 Vendor recommendation and OAF by Contractsand Commercial

    7 25-Feb-14 03-Mar-14

    HO170 Release of LOI/PO 7 04-Mar-14 10-Mar-14

    HO180 NTP Date 0 18-Aug-14

    HO190 Order Supply Completion 30 18-Aug-14 16-Sep-14

    HO220 Order Erection Completion 60 28-Aug-14 26-Oct-14

    Blinds/ProjBlinds/Projectors 299 31-Dec-13 25-Oct-14BP120 RFP 7 31-Dec-13 06-Jan-14

    BP130 Receipt of Bid 21 07-Jan-14 27-Jan-14

    BP140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 28-Jan-14 10-Feb-14

    BP150 Commercial Negotiation by Contracts &Commercial

    14 11-Feb-14 24-Feb-14

    BP160 Vendor recommendation and OAF by Contractsand Commercial

    7 25-Feb-14 03-Mar-14

    BP170 Release of LOI/PO 7 04-Mar-14 10-Mar-14

    BP180 NTP Date 0 28-Aug-14

    BP190 Order Supply Completion 28 28-Aug-14 24-Sep-14

    BP220 Order Erection Completion 30 26-Sep-14 25-Oct-14

    VC EquipmVC Equipments 300 31-Dec-13 26-Oct-14

    VC120 RFP 7 31-Dec-13 06-Jan-14

    VC130 Receipt of Bid 21 07-Jan-14 27-Jan-14

    VC140 Bid Clarification and evaluation(Technical +

    Commercial) meeting ( Post Bid Meeting)

    14 28-Jan-14 10-Feb-14

    VC150 Commercial Negotiation by Contracts &Commercial

    14 11-Feb-14 24-Feb-14

    VC160 Vendor recommendation and OAF by Contractsand Commercial

    7 25-Feb-14 03-Mar-14

    VC170 Release of LOI/PO 7 04-Mar-14 10-Mar-14

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    NTP Date

    25-Oct-

    NTP Date

    26-Oct-

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 14 of 18 TASK filter: All Activities

    Oracle Corporation

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    15/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    VC180 NTP Date 0 28-Aug-14

    VC190 Order Supply Completion 29 28-Aug-14 25-Sep-14

    VC220 Order Erection Completion 30 27-Sep-14 26-Oct-14Admin ItemAdmin Items 295 31-Dec-13 21-Oct-14

    AD120 RFP 7 31-Dec-13 06-Jan-14

    AD130 Receipt of Bid 21 07-Jan-14 27-Jan-14

    AD140 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 28-Jan-14 10-Feb-14

    AD150 Commercial Negotiation by Contracts &Commercial

    14 11-Feb-14 24-Feb-14

    ADI160 Vendor recommendation and OAF by Contractsand Commercial 7 25-Feb-14 03-Mar-14

    AD170 Release of LOI/PO 7 04-Mar-14 10-Mar-14

    AD180 NTP Date 0 28-Aug-14

    AD190 Order Supply Completion 10 28-Aug-14 06-Sep-14

    AD220 Order Erection Completion 15 07-Oct-14 21-Oct-14

    Building OBuilding Occupancy/ Completion Certificate 290 31-Dec-13 16-Oct-14

    OC330 RFP 7 31-Dec-13 06-Jan-14

    OC340 Receipt of Bid 21 07-Jan-14 27-Jan-14

    OC350 Bid Clarification and evaluation(Technical +Commercial) meeting ( Post Bid Meeting)

    14 28-Jan-14 10-Feb-14

    OC360 Commercial Negotiation by Contracts &Commercial

    14 11-Feb-14 24-Feb-14

    OC370 Vendor recommendation and OAF by Contractsand Commercial

    7 25-Feb-14 03-Mar-14

    OC380 Release of LOI/PO 7 04-Mar-14 10-Mar-14

    OC390 NTP Date 0 07-Sep-14

    OC400 Order Supply Completion 30 07-Sep-14 06-Oct-14

    OC430 Order Erection Completion 30 17-Sep-14 16-Oct-14

    ConstructiConstruction-- Project Department 411 15-Sep-13 30-Oct-14

    LB--LowerLB--Lower Basement 367 15-Sep-13 16-Sep-14

    Civil & StrCivil & Structural Works 91 15-Sep-13 14-Dec-13

    A1270 Excavation 30 15-Sep-13 14-Oct-13

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    NTP Date

    21-Oct-1

    NTP Date

    16-Oct-1

    NTP Date

    30-Oct-

    16-Sep-14,

    14-Dec-13, Civil & Structural Works

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 15 of 18 TASK filter: All Activities

    Oracle Corporation

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    16/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    AR220 Finish --Excavation 0 14-Oct-13

    A1280 Lower Basement 61 15-Oct-13 14-Dec-13

    AR230 Finish--Lower Basement 0 14-Dec-13PlumbingPlumbing Works and Fire protection System 31 08-Mar-14 07-Apr-14

    PF210 Lower Basement 31 08-Mar-14 07-Apr-14

    Interior WoInterior Works and Customised Furnitures 15 01-Apr-14 15-Apr-14

    IN210 Lower Basement 15 01-Apr-14 15-Apr-14

    AHU + PuAHU + Pumps + Lowside HVAC Works 50 18-Mar-14 06-May-14

    HV210 Lower Basement 50 18-Mar-14 06-May-14

    ElectrificatElectrification Works 28 01-Feb-14 28-Feb-14

    EL420 Lower Basement 28 01-Feb-14 28-Feb-14

    IBMS andIBMS and Fire Detection System 15 01-Apr-14 15-Apr-14

    IB210 Lower Basement 15 01-Apr-14 15-Apr-14

    SignageSignage 5 12-Sep-14 16-Sep-14

    SI210 Lower Basement 5 12-Sep-14 16-Sep-14

    Blinds/ProjBlinds/Projectors 6 10-Sep-14 15-Sep-14

    BP210 Lower Basement 6 10-Sep-14 15-Sep-14

    Admin ItemAdmin Items 5 07-Sep-14 11-Sep-14

    AD210 Lower Basement 5 07-Sep-14 11-Sep-14

    UB--UpperUB--Upper Basement 281 15-Dec-13 21-Sep-14

    Civil & StrCivil & Structural Works 48 15-Dec-13 31-Jan-14

    A1290 Upper Basement 48 15-Dec-13 31-Jan-14

    AR240 Finish--Upper Basement 0 31-Jan-14

    PlumbingPlumbing Works and Fire protection System 20 08-Apr-14 27-Apr-14

    PF230 Upper Basement 20 08-Apr-14 27-Apr-14

    Interior WoInterior Works and Customised Furnitures 15 16-Apr-14 30-Apr-14

    IN230 Upper Basement 15 16-Apr-14 30-Apr-14

    AHU + PuAHU + Pumps + Lowside HVAC Works 20 07-May-14 26-May-14

    HV230 Upper Basement 20 07-May-14 26-May-14

    ElectrificatElectrification Works 30 01-Mar-14 30-Mar-14

    EL440 Upper Basement 30 01-Mar-14 30-Mar-14

    IBMS andIBMS and Fire Detection System 15 16-Apr-14 30-Apr-14

    IB230 Upper Basement 15 16-Apr-14 30-Apr-14

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    Finish --Excavation

    Finish--Lower Basement07-Apr-14, Plumbing Works

    15-Apr-14, Interior Works

    06-May-14, AHU + Pump

    28-Feb-14, Electrification Work

    15-Apr-14, IBMS and Fire

    16-Sep-14,

    15-Sep-14,

    11-Sep-14,

    21-Sep-14,

    31-Jan-14, Civil & Structural Wor

    Finish--Upper Basement

    27-Apr-14, Plumbing Wor

    30-Apr-14, Interior Works

    26-May-14, AHU + Pu

    30-Mar-14, Electrification W

    30-Apr-14, IBMS and Fire

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 16 of 18 TASK filter: All Activities

    Oracle Corporation

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    17/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    SignageSignage 5 17-Sep-14 21-Sep-14

    SI230 Upper Basement 5 17-Sep-14 21-Sep-14

    Blinds/ProjBlinds/Projectors 5 16-Sep-14 20-Sep-14BP230 Upper Basement 5 16-Sep-14 20-Sep-14

    Admin ItemAdmin Items 5 12-Sep-14 16-Sep-14

    AD230 Upper Basement 5 12-Sep-14 16-Sep-14

    GFL-- GroGFL-- Ground Floor 242 01-Feb-14 30-Sep-14

    Civil & StrCivil & Structural Works 25 01-Feb-14 25-Feb-14

    A1300 Ground Floor 25 01-Feb-14 25-Feb-14

    AR250 Finish--Ground Floor 0 25-Feb-14

    PlumbingPlumbing Works and Fire protection System 20 28-Apr-14 17-May-14PF240 Ground Floor 20 28-Apr-14 17-May-14

    Interior WoInterior Works and Customised Furnitures 30 01-May-14 30-May-14

    IN240 Ground Floor 30 01-May-14 30-May-14

    AHU + PuAHU + Pumps + Lowside HVAC Works 15 27-May-14 10-Jun-14

    HV240 Ground Floor 15 27-May-14 10-Jun-14

    ElectrificatElectrification Works 30 31-Mar-14 29-Apr-14

    EL450 Ground Floor 30 31-Mar-14 29-Apr-14

    IBMS andIBMS and Fire Detection System 30 01-May-14 30-May-14

    IB240 Ground Floor 30 01-May-14 30-May-14

    SignageSignage 5 22-Sep-14 26-Sep-14

    SI240 Ground Floor 5 22-Sep-14 26-Sep-14

    Blinds/ProjBlinds/Projectors 5 21-Sep-14 25-Sep-14

    BP240 Ground Floor 5 21-Sep-14 25-Sep-14

    VC EquipmVC Equipments 5 26-Sep-14 30-Sep-14

    VC240 Ground Floor 5 26-Sep-14 30-Sep-14

    Admin ItemAdmin Items 5 17-Sep-14 21-Sep-14

    AD240 Ground Floor 5 17-Sep-14 21-Sep-14

    FFL-- 1st FFFL-- 1st Floor 222 26-Feb-14 05-Oct-14

    Civil & StrCivil & Structural Works 26 26-Feb-14 23-Mar-14

    A1310 1st Floor 26 26-Feb-14 23-Mar-14

    AR260 Finish--1st Floor 0 23-Mar-14

    PlumbingPlumbing Works and Fire protection System 15 18-May-14 01-Jun-14

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    21-Sep-14,

    20-Sep-14,

    16-Sep-14,

    30-Sep-14

    25-Feb-14, Civil & Structural W

    Finish--Ground Floor

    17-May-14, Plumbing W

    30-May-14, Interior W

    10-Jun-14, AHU + Pu

    29-Apr-14, Electrification

    30-May-14, IBMS and

    26-Sep-14,

    25-Sep-14,

    30-Sep-14

    21-Sep-14,

    05-Oct-14

    23-Mar-14, Civil & Structural

    Finish--1st Floor

    01-Jun-14, Plumbing

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 17 of 18 TASK filter: All Activities

    Oracle Corporation

  • 7/28/2019 NOBP Schedule- EPC-Floor Wise- Packagewise

    18/18

    Activity ID Activity Name OriginalDuration

    Start Finish

    PF250 1st Floor 15 18-May-14 01-Jun-14

    Interior WoInterior Works and Customised Furnitures 31 31-May-14 30-Jun-14

    IN250 1st Floor 31 31-May-14 30-Jun-14AHU + PuAHU + Pumps + Lowside HVAC Works 15 11-Jun-14 25-Jun-14

    HV250 1st Floor 15 11-Jun-14 25-Jun-14

    ElectrificatElectrification Works 32 30-Apr-14 31-May-14

    EL460 1st Floor 32 30-Apr-14 31-May-14

    IBMS andIBMS and Fire Detection System 31 31-May-14 30-Jun-14

    IB250 1st Floor 31 31-May-14 30-Jun-14

    SignageSignage 5 27-Sep-14 01-Oct-14

    SI250 1st Floor 5 27-Sep-14 01-Oct-14

    Blinds/ProjBlinds/Projectors 5 26-Sep-14 30-Sep-14

    BP250 1st Floor 5 26-Sep-14 30-Sep-14

    VC EquipmVC Equipments 5 01-Oct-14 05-Oct-14

    VC250 1st Floor 5 01-Oct-14 05-Oct-14

    Admin ItemAdmin Items 5 22-Sep-14 26-Sep-14

    AD250 1st Floor 5 22-Sep-14 26-Sep-14

    SFL-- 2ndSFL-- 2nd Floor 201 24-Mar-14 10-Oct-14

    TFL-- 3rdTFL-- 3rd Floor178 21-Apr-14 15-Oct-14

    FFL -- 4thFFL -- 4th Floor 158 16-May-14 20-Oct-14

    FFL -- 5thFFL -- 5th Floor 137 11-Jun-14 25-Oct-14

    Roof + MuRoof + Mumty Floor 127 26-Jun-14 30-Oct-14

    O N D J F M A M J J A S O N D J F M A M J J A S O N D J

    2013 2014 15

    30-Jun-14, Interior

    25-Jun-14, AHU + P

    31-May-14, Electrificat

    30-Jun-14, IBMS an

    01-Oct-14,

    30-Sep-14

    05-Oct-14

    26-Sep-14,

    10-Oct-1Finish--2 nd Floor

    15-Oct-1Finish-3 rd Floor

    20-Oct-1Finish--4 th Floor

    25-Oct-Finish --5 th Floor

    30-Oct-Finish--Roof + M

    Noida Office Buildin Construction Pro ect1- epc-floor-package 24-Jun-13 16:43

    Actual Work

    Remaining Work

    Critical Remaining ...

    Milestone

    Page 18 of 18 TASK filter: All Activities

    Oracle Corporation