Project Name – 4-Laning from Km 42.00 to Km 177.00 in Khed- Sinnar (NH50) in the State of Maharashtra . Brief Note on Project 1. Brief of the Project : Khed – Sinner section of NH – 50 from Km. 42 to Km. 177 has been taken for four laning under NHDP, phase – IV on BOT (DBFOT) basis. DPR consultant for this Project is M/s CEG Jaipur. The work has been awarded to M/s Khed Sinner Expressway Ltd. (KSEL) (M/s IL & FS Transportation Networks Ltd) on 28.03.2013 and agreement has been signed with Concessionaire on. 08.05.2013 & Date of Appointment has been fixed on 12.02.2014. This stretch passes through 3 Districts viz. Pune, Ahmednagar and Nashik District. The schedule date of completion of 4 lanning was August 2016. The work in Nashik & Ahmedngar district is completed, but the project is delayed due to LA issues especially Bypasses in Pune district. The EOT for the Project has been approved by of Competent Authority in NHAI HQ New Delhi upto 10.08.2017. 1.2. Location: Four Laning of Khed – Sinnar Section of NH-50 starts from Km 42+000 on NH–50 (Pune-Nashik Section) at Khed in Pune District and passes through Naryangaon (Pune District), Sangamner (Ahmednagar District) and ends at Km. 177+000 near Sinnar (Nashik District). The existing road is of single carriageway comprising of two lanes with hard shoulders on either side. 1.3. Features: (158) 15.01.2017 - Brief Note on Khed Sinnar.

nhai.org.innhai.org.in/spw/ProjectDetails/(158) 15.01.2017 - Brief... · Web viewIn Pune District, Land Acquisition is already delayed due to opposition of farmers for bypasses in

Embed Size (px)

Citation preview

Project Name – 4-Laning from Km 42.00 to Km 177.00 in Khed-Sinnar (NH50) in the State of Maharashtra.

Brief Note on Project

1. Brief of the Project :Khed – Sinner section of NH – 50 from Km. 42 to Km. 177 has been taken for four

laning under NHDP, phase – IV on BOT (DBFOT) basis. DPR consultant for this

Project is M/s CEG Jaipur. The work has been awarded to M/s Khed Sinner

Expressway Ltd. (KSEL) (M/s IL & FS Transportation Networks Ltd) on 28.03.2013

and agreement has been signed with Concessionaire on. 08.05.2013 & Date of

Appointment has been fixed on 12.02.2014. This stretch passes through 3 Districts

viz. Pune, Ahmednagar and Nashik District. The schedule date of completion of 4

lanning was August 2016.

The work in Nashik & Ahmedngar district is completed, but the project is delayed due

to LA issues especially Bypasses in Pune district. The EOT for the Project has been

approved by of Competent Authority in NHAI HQ New Delhi upto 10.08.2017.

1.2. Location: – Four Laning of Khed – Sinnar Section of NH-50 starts from Km

42+000 on NH–50 (Pune-Nashik Section) at Khed in Pune District and passes

through Naryangaon (Pune District), Sangamner (Ahmednagar District) and ends at

Km. 177+000 near Sinnar (Nashik District). The existing road is of single

carriageway comprising of two lanes with hard shoulders on either side.

1.3. Features:Length : 137.946 km

Major bridge : 9

Flyovers : 2

VUP : 7

PUP/CUP : 25

Toll Plaza : 2

Busbay : 33

Truck laybye : 4

1.4. Photographs : Attached.

(158) 15.01.2017 - Brief Note on Khed Sinnar.

- 2 –

1.5. TPC,Cost as per Financial Agreement, Escrow & Grants details.

TPC - 1348.20 Cr Cost as per Financial Agreement – 1961.28 Crs. Debt – 1100 Crs. Equity –564.68 Crs. VGF - 296.60 Crs.

1.6. Land Acquisition Status, Land Encumbrances, utility shifting(i) Land Acquisition Status:

Total land required : 840.00 ha

Available land : 280.00 ha

Land to be acquired : 560.00 ha

3 (A) completed : 942.22 ha

3 (D) completed : 496.90 ha

3 (G) completed : 458.43 ha

(ii) Forest Land

Required : 54 ha

Diverted : 54 ha

Electrical utility shifting has been completed for Nashik & Ahmednagar

district and is in progress for Pune district.

Water pipe line shifting work in Ahmednagar & Pune District is in progress.

1.7. Status of Approvals / Clearances

Environmental Clearance Obtained on 21/03/2013.

Forest Clearance Obtained for Pune, Nashik & Ahmednagar Districts.

CRZC Not Applicable

WLC Not required

(158) 15.01.2017 - Brief Note on Khed Sinnar.

- 3 –

1.8. Any Court / Tribunal orders – NIL.

1.9. Status of Award of Project Packages and Physical / Financial Progress in %

Concession Agreement Signed – 08.05.2013

Appointed Date - 12.02.2014

Scheduled date of completion - 09.08.2016

Likley Date of Completion - 10.08.2017 (EOT approved)

Physical Progress - 78% (As on January2017.)

Financial Progress - 88.78% (As on January2017.)

4 lanning Length Completed - 106.20 Km as against total length of 137.946 Km as on 31st January 2016.

2. Issues pending with other Ministries with input on last joint review / letters to that Ministry. – NIL.

3. Issues pending with State Government with input on last joint review / letters to State Government.

ii) In Pune District, Land Acquisition is already delayed due to opposition of

farmers for bypasses in Pune Dist. Shri Sanjay Patil, Dy. Collector (LA) 13,

Pune has been transferred and relieved on 13.09.2016. Since last more than

four months, no full time CALA has been posted and all payment

disbursement and LA work has been stopped causing stoppage of work and

resentment amongst land owners due to non-payment. Full time CALA may

be posted as SLAO No. 13 at the earliest.

iii) Delay in disbursement of compensation for land, particularly in Pune

district. This needs to be expedited on priority basis.

iv) Declaration of Award for Kalamb bypass in Pune District u/s 3 (G) of NH Act 1956 need to be expedited.

************************

(158) 15.01.2017 - Brief Note on Khed Sinnar.

(158) 15.01.2017 - Brief Note on Khed Sinnar.

(158) 15.01.2017 - Brief Note on Khed Sinnar.

(158) 15.01.2017 - Brief Note on Khed Sinnar.

(158) 15.01.2017 - Brief Note on Khed Sinnar.