78
An Overview of the Scope and Purpose of NFPA 25 An Overview of the Scope and Purpose of NFPA 25

Nfpa 25 Presentation

  • Upload
    akm1966

  • View
    184

  • Download
    19

Embed Size (px)

Citation preview

Page 1: Nfpa 25 Presentation

An Overview of the Scope and Purpose of NFPA 25

An Overview of the Scope and Purpose of NFPA 25

Page 2: Nfpa 25 Presentation

Russ is the Chairman and CEO of Telgian, Inc. whose subsidiaries include Fire Materials Group and TVA Fire and Life Safety. He holds a degree from the University of Nevada, Las Vegas and a Level IV certification from NICET in Fire Sprinkler Layout. He is a licensed contractor in 40 states and has 25 years of experience in the design, installation, and testing of fire protection systems. Telgian provides a wide range of fire protection and life safety services including fire systems engineering and design, code consulting, loss control engineering, installation, and the inspection and testing. Russ has worked on projects throughout North America, Central and South America, the Far East, and Europe. He serves as a principal on the NFPA 25 technical committee and theNFPA 5000 (building code) correlating committee. Russ conducts seminars throughout North America for Authorities Having Jurisdiction, Contractors, and Engineers on a variety of subjects and is a member of AFSA, NFPA, NFSA, and SFPE.

Page 3: Nfpa 25 Presentation

Russ Leavitt, S.E.T.

Telgian, Inc2615 S Industrial Park Ave.

Tempe, AZ 85282

PH: (480) 753-5444Email: [email protected]

Russ Leavitt, S.E.T.

Telgian, Inc2615 S Industrial Park Ave.

Tempe, AZ 85282

PH: (480) 753-5444Email: [email protected]

Page 4: Nfpa 25 Presentation

NFPA 13AFirst published in 1940Last edition 1987No mandatory language

NFPA 25Technical committee appointed in 1990First edition 1992

NFPA 13AFirst published in 1940Last edition 1987No mandatory language

NFPA 25Technical committee appointed in 1990First edition 1992

Page 5: Nfpa 25 Presentation

LET’S REVIEW WHYLET’S REVIEW WHY

Page 6: Nfpa 25 Presentation

80% of System Failures can be attributed to a lack of

maintenance!

80% of System Failures can be attributed to a lack of

maintenance!

Page 7: Nfpa 25 Presentation
Page 8: Nfpa 25 Presentation

Leading causes of failures:System shut off (66%)Lack of other Maintenance (10%)Damaged Component (2%)

Leading causes of failures:System shut off (66%)Lack of other Maintenance (10%)Damaged Component (2%)

Page 9: Nfpa 25 Presentation

NFPA 25 2008 EditionNFPA 25 2008 Edition

Two-thirds of all failures are because of a shut water control valve!

Think about it—We could eliminate 2/3 of failures by simply keeping control valves open!

Two-thirds of all failures are because of a shut water control valve!

Think about it—We could eliminate 2/3 of failures by simply keeping control valves open!

Page 10: Nfpa 25 Presentation

NFPA 25 2008 EditionNFPA 25 2008 Edition

The Objective of NFPA 25 is to eliminate the failures that

are caused by the lack of maintenance.

The Objective of NFPA 25 is to eliminate the failures that

are caused by the lack of maintenance.

Page 11: Nfpa 25 Presentation

NFPA 25 is widely adopted.

NFPA 25 is not widely enforced.

NFPA 25 is widely misinterpreted by both

contractors and jurisdictions.

NFPA 25 is widely adopted.

NFPA 25 is not widely enforced.

NFPA 25 is widely misinterpreted by both

contractors and jurisdictions.

Page 12: Nfpa 25 Presentation

The objective of this seminar to create a greater awareness regarding the scope and purpose of NFPA 25

The objective of this seminar to create a greater awareness regarding the scope and purpose of NFPA 25

Page 13: Nfpa 25 Presentation

Let’s take a Look Let’s take a Look

Page 14: Nfpa 25 Presentation

Chapter 1 – AdministrationChapter 2 – Referenced PublicationsChapter 3 – DefinitionsChapter 4 – General RequirementsChapter 5 – Sprinkler SystemsChapter 6 – Standpipe and Hose SystemsChapter 7 – Private Fire Service Mains

Chapter 1 – AdministrationChapter 2 – Referenced PublicationsChapter 3 – DefinitionsChapter 4 – General RequirementsChapter 5 – Sprinkler SystemsChapter 6 – Standpipe and Hose SystemsChapter 7 – Private Fire Service Mains

Page 15: Nfpa 25 Presentation

Chapter 8 – Fire PumpsChapter 9 – Water Storage TanksChapter 10 – Water Spray Fixed SystemsChapter 11 – Foam-Water Sprinkler SystemsChapter 12 - Water Mist SystemsChapter 13 – Valves, Valve Components, TrimChapter 14 - Obstruction InvestigationChapter 15 - ImpairmentsAnnexes/Supplements

Chapter 8 – Fire PumpsChapter 9 – Water Storage TanksChapter 10 – Water Spray Fixed SystemsChapter 11 – Foam-Water Sprinkler SystemsChapter 12 - Water Mist SystemsChapter 13 – Valves, Valve Components, TrimChapter 14 - Obstruction InvestigationChapter 15 - ImpairmentsAnnexes/Supplements

Page 16: Nfpa 25 Presentation

Minimum requirementsWater-based systemsCoordinate with NFPA 72Covers systems installed in accordance with generally accepted practicesNot intended to reveal installation flaws or code of compliance violationsDoes not apply to 13D systems

Minimum requirementsWater-based systemsCoordinate with NFPA 72Covers systems installed in accordance with generally accepted practicesNot intended to reveal installation flaws or code of compliance violationsDoes not apply to 13D systems

Page 17: Nfpa 25 Presentation

Ensure reasonable degree of protection for life and propertyEnsure reasonable degree of

protection for life and property

Page 18: Nfpa 25 Presentation

Chapter 2Chapter 2

Page 19: Nfpa 25 Presentation

Chapter 3Chapter 3

Page 20: Nfpa 25 Presentation

NFPA Official Definitions (3.2)“Approved”“AHJ”“Listed”“Shall”“Should”

NFPA Official Definitions (3.2)“Approved”“AHJ”“Listed”“Shall”“Should”

Page 21: Nfpa 25 Presentation

Inspection (3.3.18)Testing (3.3.34)Maintenance (3.3.20)Qualified (3.3.28)

Inspection (3.3.18)Testing (3.3.34)Maintenance (3.3.20)Qualified (3.3.28)

Page 22: Nfpa 25 Presentation

Chapter 4Chapter 4

Page 23: Nfpa 25 Presentation

Owner shall provide ready access (4.1.1)Owner responsible for maintaining system (4.1.2)Tasks performed by competent personnel (4.1.2.2)Owner shall notify all parties as required before testing or shutting down system (4.1.3)

Owner shall provide ready access (4.1.1)Owner responsible for maintaining system (4.1.2)Tasks performed by competent personnel (4.1.2.2)Owner shall notify all parties as required before testing or shutting down system (4.1.3)

Owner shall make repairs promptly (4.1.4)All tasks to be performed by qualified personnel

(4.1.2.2 and 4.1.4.1)

Owner shall make repairs promptly (4.1.4)All tasks to be performed by qualified personnel

(4.1.2.2 and 4.1.4.1)

Page 24: Nfpa 25 Presentation

Owner shall evaluate all changes to occupancy, use, or materials stored (4.1.5)Where changes occur, owner shall contract with qualified consultant and the AHJ to evaluate systems (4.1.6)Correct any deficiency found (4.1.6.1)

Owner shall evaluate all changes to occupancy, use, or materials stored (4.1.5)Where changes occur, owner shall contract with qualified consultant and the AHJ to evaluate systems (4.1.6)Correct any deficiency found (4.1.6.1)

Owner shall ensure responsible occupants know how to shut system down (4.1.7) Information signs (4.1.8) Note: This is a retroactive requirement!When system is returned to service following an impairment is shall be verified to be working properly (4.2.2)

Owner shall ensure responsible occupants know how to shut system down (4.1.7) Information signs (4.1.8) Note: This is a retroactive requirement!When system is returned to service following an impairment is shall be verified to be working properly (4.2.2)

Page 25: Nfpa 25 Presentation

Made available to the AHJ upon request (4.4.1)Maintained by owner (4.4.3)Original records kept for life of building (4.4.4)Subsequent records kept for a period of one year after next scheduled task (4.4.5)

Made available to the AHJ upon request (4.4.1)Maintained by owner (4.4.3)Original records kept for life of building (4.4.4)Subsequent records kept for a period of one year after next scheduled task (4.4.5)

Page 26: Nfpa 25 Presentation

Performance testing allowed if approved by the AHJ (4.6.1.1.1)If water supplies, including pumps are taken out of service during testing and maintenance impairment procedures must be followed unless under constant attendance by qualified personnel (4.6.3)Test results are compared to original test or most recent test results (4.6.4)

Performance testing allowed if approved by the AHJ (4.6.1.1.1)If water supplies, including pumps are taken out of service during testing and maintenance impairment procedures must be followed unless under constant attendance by qualified personnel (4.6.3)Test results are compared to original test or most recent test results (4.6.4)

Page 27: Nfpa 25 Presentation

Chapter 5Chapter 5

Page 28: Nfpa 25 Presentation

Table 5.1 Summary of Sprinkler System Inspection, Testing, and

Maintenance

Table 5.1 Summary of Sprinkler System Inspection, Testing, and

Maintenance

Page 29: Nfpa 25 Presentation

Inspection of Sprinklers From the floor (5.2.1.1)Omit areas above ceilings (5.2.1.1.4)Condition of sprinklers (5.2.1.1.2)

PaintedCorroded or LoadedDamagedOrientation

Inspection of Sprinklers From the floor (5.2.1.1)Omit areas above ceilings (5.2.1.1.4)Condition of sprinklers (5.2.1.1.2)

PaintedCorroded or LoadedDamagedOrientation

Page 30: Nfpa 25 Presentation

Inspection of Sprinklers Glass bulbs (5.2.1.1.3)Recalled Sprinklers (5.2.1.1.6)Obstructions limited to clearance below the sprinkler (5.2.1.2)

Inspection of Sprinklers Glass bulbs (5.2.1.1.3)Recalled Sprinklers (5.2.1.1.6)Obstructions limited to clearance below the sprinkler (5.2.1.2)

Page 31: Nfpa 25 Presentation

Inspection of Pipe and FittingsFrom the floor (5.2.2)Omit areas above ceilings (5.2.2.3)Condition of pipe and fittings (5.2.2.1)

DamageLeakage and Corrosion

Inspection of Pipe and FittingsFrom the floor (5.2.2)Omit areas above ceilings (5.2.2.3)Condition of pipe and fittings (5.2.2.1)

DamageLeakage and Corrosion

Page 32: Nfpa 25 Presentation

Inspection of Pipe and Fittings

External loads (5.2.2.2)

Inspection of Pipe and Fittings

External loads (5.2.2.2)

Page 33: Nfpa 25 Presentation

Inspection of Hangers and Braces

From the floor (5.2.3)Omit areas above ceilings (5.2.3.3)Condition of hangers and braces (5.2.3.1)

DamagedLoose

Inspection of Hangers and Braces

From the floor (5.2.3)Omit areas above ceilings (5.2.3.3)Condition of hangers and braces (5.2.3.1)

DamagedLoose

Page 34: Nfpa 25 Presentation

Inspection of other componentsSpare sprinklers (5.2.1.3)Gauges (5.2.4.)Buildings for freeze protection (5.2.5)Alarm Devices (5.2.6)Hydraulic Nameplate (5.2.7)

Inspection of other componentsSpare sprinklers (5.2.1.3)Gauges (5.2.4.)Buildings for freeze protection (5.2.5)Alarm Devices (5.2.6)Hydraulic Nameplate (5.2.7)

Page 35: Nfpa 25 Presentation
Page 36: Nfpa 25 Presentation
Page 37: Nfpa 25 Presentation
Page 38: Nfpa 25 Presentation
Page 39: Nfpa 25 Presentation
Page 40: Nfpa 25 Presentation
Page 41: Nfpa 25 Presentation

Testing of componentsSprinklersGauges replaced or tested with calibrated gauge every 5 years (5.3.2)

Testing of componentsSprinklersGauges replaced or tested with calibrated gauge every 5 years (5.3.2)

Page 42: Nfpa 25 Presentation
Page 43: Nfpa 25 Presentation

MaintenanceReplacement sprinklers must have the required characteristics for the application (5.4.1)Only new sprinklers shall be used (5.4.1.2)Dry sprinkler replacement (5.4.1.4.2.1)

MaintenanceReplacement sprinklers must have the required characteristics for the application (5.4.1)Only new sprinklers shall be used (5.4.1.2)Dry sprinkler replacement (5.4.1.4.2.1)

Page 44: Nfpa 25 Presentation
Page 45: Nfpa 25 Presentation
Page 46: Nfpa 25 Presentation

MaintenanceDry pipe systems shall be kept dry at all times (5.4.2)Compressors maintained in accordance with manufacturers instructions (5.4.2.3)

MaintenanceDry pipe systems shall be kept dry at all times (5.4.2)Compressors maintained in accordance with manufacturers instructions (5.4.2.3)

Page 47: Nfpa 25 Presentation
Page 48: Nfpa 25 Presentation

MaintenanceComponent Action Requirements

Table 5.5.1 Summary of Component Replacement Action RequirementsMain drain test required if upstream valves were operated (5.5.1.2)Design review not required

(5.5.1.3)

MaintenanceComponent Action Requirements

Table 5.5.1 Summary of Component Replacement Action RequirementsMain drain test required if upstream valves were operated (5.5.1.2)Design review not required

(5.5.1.3)

Page 49: Nfpa 25 Presentation

All remaining system chapters are organized

in a similar format.

All remaining system chapters are organized

in a similar format.

Page 50: Nfpa 25 Presentation

Chapter 13Chapter 13

Page 51: Nfpa 25 Presentation

Table 13.1InspectionsTestingMaintenance

Table 13.1InspectionsTestingMaintenance

Page 52: Nfpa 25 Presentation

General ProvisionsAll valves shall be protected from damage (13.2.3)Verify for adequate drainage beforeopening valve or drain (13.2.4)

General ProvisionsAll valves shall be protected from damage (13.2.3)Verify for adequate drainage beforeopening valve or drain (13.2.4)

Page 53: Nfpa 25 Presentation

General ProvisionsMain drain test shall be conducted annually (13.2.5)Main drain test shall be conducted quarterly where sole water supply is through a backflow preventer or pressure reducing valve (13.2.5.1)10 percent reduction in residual requires investigation (13.2.5.2)

General ProvisionsMain drain test shall be conducted annually (13.2.5)Main drain test shall be conducted quarterly where sole water supply is through a backflow preventer or pressure reducing valve (13.2.5.1)10 percent reduction in residual requires investigation (13.2.5.2)

Page 54: Nfpa 25 Presentation

CONTROLCONTROL VALVESVALVES

Page 55: Nfpa 25 Presentation

Control ValvesSystems with more than one control valve shall have a sign on each valve referring to the existence and location of the other valves (13.3.1.1) Retroactive

Control ValvesSystems with more than one control valve shall have a sign on each valve referring to the existence and location of the other valves (13.3.1.1) Retroactive

Page 56: Nfpa 25 Presentation

Control ValvesAll valves shall be inspected monthly if supervised or weekly if not (13.3.2.1 and 13.3.2.1.1)All valves must be operated annually (13.3.3.1)Valve supervisory switches shall be tested semi-annually (13.3.3.5.1)

Control ValvesAll valves shall be inspected monthly if supervised or weekly if not (13.3.2.1 and 13.3.2.1.1)All valves must be operated annually (13.3.3.1)Valve supervisory switches shall be tested semi-annually (13.3.3.5.1)

Page 57: Nfpa 25 Presentation
Page 58: Nfpa 25 Presentation
Page 59: Nfpa 25 Presentation

Chapter 14Chapter 14

Page 60: Nfpa 25 Presentation

InspectionInternal inspection at 5 year intervals by opening the end of one main and removing a sprinkler toward the end of one branch line (14.2.1)When uncorrected conditions exist (14.2.2) the system shall receive a four point inspection every 5 years (14.2.3.2)

InspectionInternal inspection at 5 year intervals by opening the end of one main and removing a sprinkler toward the end of one branch line (14.2.1)When uncorrected conditions exist (14.2.2) the system shall receive a four point inspection every 5 years (14.2.3.2)

Page 61: Nfpa 25 Presentation

InspectionPipe passing into freezer or cold storage rooms shall be internally inspected annually (14.3)Alternative nondestructive examinations are permitted (14.2.1.1 and 14.3.1)

InspectionPipe passing into freezer or cold storage rooms shall be internally inspected annually (14.3)Alternative nondestructive examinations are permitted (14.2.1.1 and 14.3.1)

Page 62: Nfpa 25 Presentation

Chapter 15Chapter 15

Page 63: Nfpa 25 Presentation

Coordinator (15.2)Tagging (15.3)Preplanned Impairments (15.5)

Coordinator (15.2)Tagging (15.3)Preplanned Impairments (15.5)

Page 64: Nfpa 25 Presentation

Emergency Impairments (15.6)Restoring the system to service (15.7)

Emergency Impairments (15.6)Restoring the system to service (15.7)

Page 65: Nfpa 25 Presentation
Page 66: Nfpa 25 Presentation
Page 67: Nfpa 25 Presentation
Page 68: Nfpa 25 Presentation
Page 69: Nfpa 25 Presentation
Page 70: Nfpa 25 Presentation
Page 71: Nfpa 25 Presentation
Page 72: Nfpa 25 Presentation
Page 73: Nfpa 25 Presentation
Page 74: Nfpa 25 Presentation
Page 75: Nfpa 25 Presentation
Page 76: Nfpa 25 Presentation
Page 77: Nfpa 25 Presentation
Page 78: Nfpa 25 Presentation

Questions and AnswersQuestions and Answers