Adnan Siddiqui, P.E.PrincipalConcepSys Solutions LLC
ConcepSys Solutions LLC
Audience Poll
Academia - Is capital project management training part of your curriculum?
▪ Separate course
▪ Integrated with another course
Industry - What type of projects are you leading?
▪ Retrofits and revamps
▪ Greenfield
▪ Size of project team
About Me
ConcepSys Solutions LLC
New Tools
Multidiscipline Interface Management Matrix
Project Pre-Mortem
Failure Mode and Effect Analysis (FMEA)
New Skills
Working with Generation Y
Social and Emotional Intelligence
ConcepSys Solutions LLC
New interface management tool presented in Harvard Business Review article:
“AreYour Engineers Talking to Each Other ..”
November 2007
Authors researched failure on complex projects such as Airbus Super Jumbo
Applicable to complex mega capital projects.
ConcepSys Solutions LLC
ConcepSys Solutions LLC
ConcepSys Solutions LLC
Conducted at start of project Group session with key team members from
ALL levels Should be independently facilitated Attendees are asked to complete the
statement
“The project failed because ….”
Results should be analyzed using an FMEA
ConcepSys Solutions LLC
Six Sigma tool to develop a risk management plan for project execution
Categorize negative project outcomes (impacts) on:
Severity of impact
Ability to detect
Likelihood of occurrence
Enables formal risk planning and monitoring
ConcepSys Solutions LLC
Category Risk Impact S (severity rating)
Schedule Availability of reactor design specialist
Reactor design and procurement is delayed
9
Procurement Qualified fabrication supplier for reactor is booked with other orders
Reactor fabrication and project completion is delayed
9
ConcepSys Solutions LLC
Cause(s) O (occurrence rating) Current controls D (detection rating)
Failure to request specialist time in advance to work on reactor design
3 Requesting specialist time is a milestone on the project schedule which is reviewed weekly for upcoming activities
1
Failure to commit and reserve shop space in time
9 Request advanced funds to commit reactor purchase order and priortize completion of reactor design specifications
3
ConcepSys Solutions LLC
RPN (risk priority number) Recommended actions Responsibility and target completion
date Action taken
27 Continue current control Project Manager
243 Biweekly communication meeting with supplier to understand the shop workload
Procurment Manager
ConcepSys Solutions LLC
Category Risk ImpactS (severity
rating) Cause(s)
O (occurrence
rating)
Current controls
D (detection rating)
RPN (risk priority
number)
Recommended actions
Responsibility and target
completion date
Action taken
Schedule Availability of reactor design specialist
Reactor design and procurement is delayed
9 Failure to request specialist time in advance to work on reactor design
3 Requesting specialist time is a milestone on the project schedule which is reviewed weekly for upcoming activities
1 27 Continue current control
Project Manager
Procurement
Qualified fabrication supplier for reactor is booked with other orders
Reactor fabrication and project completion is delayed
9 Failure to commit and reserve shop space in time
9 Request advanced funds to commit reactor purchase order and priortize completion of reactor design specifications
3 243 Biweekly communication meeting with supplier to understand the shop workload
Procurment Manager
ConcepSys Solutions LLC
Who is Generation Y?
Graduating college in 2000 or later?
Experienced an explosion in Technology, Media, Telecommunications (TMT)
Generation Y myths
Not hard working
Unreliable
Not willing to put the time in
Short attention span
ConcepSys Solutions LLC
Attracting
Company career sites on social networks e.g. Facebook
Company profiles on Vault.com
Training
Mentorship (traditional and reverse)
Rotation programs
Electronic courses
Team based training
ConcepSys Solutions LLC
Retaining
Managing expectations
▪ Company culture
▪ Career path
▪ Organizational hierarchy norms
Coaching not babysitting
ConcepSys Solutions LLC
Technical excellence is not the only criteria for great project managers
Do you to have to manage ..
Global teams?
Less face-to-face meetings?
Diversity?
If so, are you the socially intelligent project manager who succeeds in these situations?
ConcepSys Solutions LLC
Empathy
Do you understand what motivates other people, even those from different backgrounds?
Are you sensitive to others’ needs?
Attunement
Do you listen attentively and think about how others feel?
Are you attuned to others’ moods?
ConcepSys Solutions LLC
Organizational Awareness
Do you appreciate the culture and values of the group or organization?
Do you understand social networks and know their unspoken norms?
Influence
Do you persuade others by engaging them in discussion and appealing to their self-interests?
Do you get support from key people?
ConcepSys Solutions LLC
Developing Others
Do you coach and mentor others with compassion and personally invest time and energy in mentoring?
Do you provide feedback that people find helpful for their professional development?
Inspiration
Do you articulate a compelling vision, build group pride, and foster a positive emotional tone?
Do you lead by bringing out the best in people?
ConcepSys Solutions LLC
Teamwork
Do you solicit input from everyone on the team?
Do you support all team members and encourage cooperation?
ConcepSys Solutions LLC
Contact me via:
Subscribe to my project management blog at
http://tinyurl.com/pmblog
Connect to me on LinkedIn at: