Riverbanks Zoo and Garden Phase II, Seals and Sea Lions
03.14-03.18
2016
RIVERBANKS ZOO AND GARDEN PHASE II, SEALS AND SEA LION EXHIBIT:
EXHIBIT POOL, VIEWING & HOLDING BUILDINGS
Perspective of the New SSL Exhibit from the Main Entrance Plaza
Perspective of the North End Of the SSL Exhibit
Perspective of the Stadium Seating Area Looking East
Perspective of the Stadium Seating Area Looking South
Perspective of the Northwest Corner of the Viewing Building
Exhibit Pool Window at the Entrance to the Viewing Building
The Interior of the Viewing Building Ready to Receive Guests
The Interior of the Viewing Building Ready to Receive Guests
Perspective of the Southwest Corner of the Viewing Building
Perspective of the South Entrance to the Viewing Building
The Rustic Fencing Progresses Between Viewing and Tortoise
Pedestrian Walkway Tie-In to the South Plaza at the Viewing Building
Perspective of the Stadium Seating Area From the Viewing Deck
Perspective of the Western Portion of the Viewing Deck
Perspective of the Southern Portion of the Viewing Deck
Perspective of the Holding Building from the Upper Viewing Deck
Perspective of the Holding Building from the Upper Viewing Deck
Perspective of the Viewing Building from the Holding Building
Perspective of the Viewing Building from the Holding Building
Perspective of the Viewing Building from the Holding Building
Eastern Perspective of the Holding Building
Holding and Quarantine Pools Filled with the LSS Start Up
Interior of the Holding Building Ready to Receive Animals
Northwestern Perspective of the Holding Building
Hard and Softscape Completed Around the Buildings
Fencing Completed Between LSS and Bird Buildings
Concrete and Asphalt Placement Completed at Access Road
Riverbanks Zoo and Garden Phase III, Pedestrian Bridge
03.14-03.18
2016
RIVERBANKS ZOO AND GARDEN PHASE III, PEDESTRIAN BRIDGE PROJECT
Foundations for the South Elevator Tower have been Placed
Elevator Pit CIP Walls Stripped and Ready for Waterproofing
Bridge Abutment Foundation Completed for the South Side
Micropiles Begin for the North Elevator Tower Footings
Perspective of the New Front Entry from the North Tower Site
One Week Look Ahead The Life Support Systems Commissioning process is to be completed this week; with
Owner Training for the Defender Filters and Ozone Generators completed yesterday. The
Final Inspections from the City of Columbia as well as the Fire Marshal where received this
week. Owner and Architect Inspections and Punch for the completed Hardscape work is
scheduled for next week. Preparations for the turn over of Phase II, Holding and Viewing
Buildings to the Owner are ongoing.
The Pedestrian Bridge Project is
making progress with the Foundation
Footings placed and vertical cast in
place wall erection beginning for the
South Tower. Micropiles are being
installed starting today for the North
Tower, and should be completed next
week. The additional storm piping for
the North Site was completed
yesterday. Pyramid Masonry to begin
next week and will start erection of the
CMU walls on the South Tower.
YOUR NEW SEAL AND SEA LION EXHIBIT COMING SOON