Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
July 2015 | Initial Study
NEW MURRAY MIDDLE SCHOOL Sierra Sands Unified School District
Prepared for:
Sierra Sands Unified School District Contact: Pamela Pence, Program Manager
113 West Felspar Avenue Ridgecrest, California 93555
760.499.5300
Prepared by:
PlaceWorks Contact: Barbara Heyman, Associate Principal
3 MacArthur Place, Suite 1100 Santa Ana, California 92707
714.966.9220 [email protected] www.placeworks.com
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Table of Contents
July 2015 Page i
Section Page
1. INTRODUCTION ............................................................................................................. 1
1.1 PROJECT LOCATION ...................................................................................................................... 1 1.2 ENVIRONMENTAL SETTING ..................................................................................................... 2 1.3 SIERRA SANDS UNIFIED SCHOOL DISTRICT ................................................................... 19 1.4 PROJECT DESCRIPTION ............................................................................................................. 19 1.5 EXISTING ZONING AND GENERAL PLAN ....................................................................... 36 1.6 DISCRETIONARY ACTIONS ...................................................................................................... 37
2. ENVIRONMENTAL CHECKLIST .................................................................................. 39
2.1 BACKGROUND ................................................................................................................................ 39 2.2 ENVIRONMENTAL FACTORS POTENTIALLY AFFECTED .......................................... 41 2.3 DETERMINATION (TO BE COMPLETED BY THE LEAD AGENCY) ........................ 41 2.4 EVALUATION OF ENVIRONMENTAL IMPACTS ............................................................... 42
3. ENVIRONMENTAL ANALYSIS ..................................................................................... 51
3.1 AESTHETICS .................................................................................................................................... 51 3.2 AGRICULTURE AND FORESTRY RESOURCES .................................................................. 52 3.3 AIR QUALITY ................................................................................................................................... 54 3.4 BIOLOGICAL RESOURCES ......................................................................................................... 62 3.5 CULTURAL RESOURCES ............................................................................................................. 66 3.6 GEOLOGY AND SOILS ................................................................................................................ 71 3.7 GREENHOUSE GAS EMISSIONS ............................................................................................. 80 3.8 HAZARDS AND HAZARDOUS MATERIALS ....................................................................... 83 3.9 HYDROLOGY AND WATER QUALITY .................................................................................. 94 3.10 LAND USE AND PLANNING ................................................................................................... 101 3.11 MINERAL RESOURCES .............................................................................................................. 103 3.12 NOISE ................................................................................................................................................ 104 3.13 POPULATION AND HOUSING ............................................................................................... 117 3.14 PUBLIC SERVICES ........................................................................................................................ 118 3.15 RECREATION ................................................................................................................................ 120 3.16 TRANSPORTATION/TRAFFIC ................................................................................................ 120 3.17 UTILITIES AND SERVICE SYSTEMS ..................................................................................... 132 3.18 MANDATORY FINDINGS OF SIGNIFICANCE ................................................................. 135
4. REFERENCES ............................................................................................................ 137
5. LIST OF PREPARERS ................................................................................................ 141
LEAD AGENCY ............................................................................................................................................ 141 PLACEWORKS .............................................................................................................................................. 141
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Table of Contents
Page ii PlaceWorks
APPENDICES
Appendix A.1 Record of Categorical Exclusion for Lease of New School Site
Appendix A.2 Record of Categorical Exclusion for the Demolition of Murray Middle School
Appendix B Environmental Condition of Property Report
Appendix C.1 Air Quality and Greenhouse Gas Analysis
Appendix C.2 Health Risk Assessment Technical Memorandum
Appendix D Biological Technical Report
Appendix E.1 Historic Resource Assessment
Appendix E.2 Cultural Resources Records Search
Appendix E.3 Paleontological Records Search
Appendix F.1 Geotechnical Engineering Investigation and Geologic/Seismic Hazards Evaluation
Appendix F.2 Fault Rupture Hazard Investigation Report
Appendix F.3 Amendment to Geotechnical Engineering Investigation and Geologic/Seismic Hazards Evaluation
Appendix F.4 Update, Geotechnical Engineering Investigation
Appendix G.1 Phase I Environmental Site Assessment
Appendix G.2 Preliminary Environmental Assessment Report, New Murray Middle School
Appendix G.3 Remedial Action Workplan
Appendix H Hydrology Study
Appendix I Noise Analysis
Appendix J Traffic Impact Analysis
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Table of Contents
July 2015 Page iii
List of Figures
Figure Page
Figure 1 Regional Location ................................................................................................................................. 3
Figure 2 Local Vicinity ......................................................................................................................................... 5
Figure 3 Legal Description Map ......................................................................................................................... 7
Figure 4 Aerial Photograph, New Campus ...................................................................................................... 9
Figure 5 Site Map, Existing Campus ............................................................................................................... 11
Figure 6 Site Photographs, Existing Campus ................................................................................................. 13
Figure 7 Site Photographs, New Campus ....................................................................................................... 15
Figure 8 Historical Photograph, New Campus .............................................................................................. 17
Figure 9 Aerial Photograph, Existing Campus .............................................................................................. 21
Figure 10 Surrounding Uses, New Campus ..................................................................................................... 23
Figure 11 Site Plan, New Campus ...................................................................................................................... 25
Figure 12 Soil Removal and Reburial Areas ..................................................................................................... 29
Figure 13 Demolition, Existing Campus ........................................................................................................... 33
Figure 14 Geologic Map ...................................................................................................................................... 73
Figure 15 Area Fault Map .................................................................................................................................... 75
Figure 16 Earthquake Location Map ................................................................................................................. 77
Figure 17 Proposed Hydrology Map ................................................................................................................. 99
Figure 18 Existing Circulation Network and Lane Configurations ............................................................ 125
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Table of Contents
Page iv PlaceWorks
List of Tables
Table Page
Table 1 Proposed School Buildings Specifications ...................................................................................... 20
Table 2 Maximum Daily Construction Emissions ....................................................................................... 56
Table 3 Annual Construction Emissions ....................................................................................................... 57
Table 4 Maximum Daily Construction Emissions, Mitigated .................................................................... 58
Table 5 Maximum Daily Operation Emissions ............................................................................................ 59
Table 6 Annual Operation Emissions ............................................................................................................ 59
Table 7 Net Project-Related GHG Emissions ............................................................................................. 82
Table 8 Organochlorine Pesticide Concentrations Identified .................................................................... 89
Table 9 Existing Runoff, 100-Year Storm ..................................................................................................... 96
Table 10 Estimated Runoff, Proposed Conditions, 100-Year Storm ......................................................... 96
Table 11 Proposed Retention Basins ............................................................................................................... 97
Table 12 Existing Conditions Traffic Noise Levels (New School Site) ................................................... 105
Table 13 Maximum Allowable Noise Exposure by Land Use1.................................................................. 107
Table 14 Project Offsite Contributions, Existing Conditions .................................................................... 109
Table 15 Overall Project Offsite Contributions ........................................................................................... 110
Table 16 Vibration Levels Produced by Common Construction Equipment ......................................... 113
Table 17 Typical Construction Equipment Noise Level............................................................................. 115
Table 18 Study Area Intersections Traffic Controls and Jurisdictions ..................................................... 122
Table 19 Relationship Between Delay Values and Levels of Service ........................................................ 123
Table 20 Existing Conditions Intersection Levels of Service .................................................................... 123
Table 21 Cumulative Projects .......................................................................................................................... 127
Table 22 Intersection Levels of Service, 2017 Without-Project Conditions............................................ 127
Table 23 Project-Generated Traffic ................................................................................................................ 128
Table 24 Intersection Levels of Service, Existing plus Project Conditions ............................................. 129
Table 25 Intersection Levels of Service, 2017 plus Project Conditions ................................................... 129
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Abbreviations and Acronyms
July 2015 Page v
AAQS ambient air quality standards
AB Assembly Bill
ACM asbestos-containing materials
ADT average daily traffic
amsl above mean sea level
AQMP air quality management plan
AST aboveground storage tank
BAU business as usual
bgs below ground surface
BMP best management practices
CAA Clean Air Act
CAFE corporate average fuel economy
CalARP California Accidental Release Prevention Program
CalEMA California Emergency Management Agency
Cal/EPA California Environmental Protection Agency
CAL FIRE California Department of Forestry and Fire Protection
CALGreen California Green Building Standards Code
Cal/OSHA California Occupational Safety and Health Administration
CalRecycle California Department of Resources, Recycling, and Recovery
Caltrans California Department of Transportation
CARB California Air Resources Board
CBC California Building Code
CCAA California Clean Air Act
CCR California Code of Regulations
CDE California Department of Education
CDFW California Department of Fish and Wildlife
CEQA California Environmental Quality Act
CERCLA Comprehensive Environmental Response, Compensation and Liability Act
cfs cubic feet per second
CGS California Geologic Survey
CMP congestion management program
CNDDB California Natural Diversity Database
CNEL community noise equivalent level
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Abbreviations and Acronyms
Page vi PlaceWorks
CO carbon monoxide
CO2e carbon dioxide equivalent
Corps US Army Corps of Engineers
CSO combined sewer overflows
CUPA Certified Unified Program Agency
CWA Clean Water Act
dB decibel
dBA A-weighted decibel
DPM diesel particulate matter
DTSC Department of Toxic Substances Control
EIR environmental impact report
EPA United States Environmental Protection Agency
EPCRA Emergency Planning and Community Right-to-Know Act
FEMA Federal Emergency Management Agency
FHWA Federal Highway Administration
FTA Federal Transit Administration
GHG greenhouse gases
GWP global warming potential
HCM Highway Capacity Manual
HQTA high quality transit area
HVAC heating, ventilating, and air conditioning system
IPCC Intergovernmental Panel on Climate Change
Ldn day-night noise level
Leq equivalent continuous noise level
LBP lead-based paint
LCFS low-carbon fuel standard
LOS level of service
LST localized significance thresholds
MW moment magnitude
MCL maximum contaminant level
MEP maximum extent practicable
mgd million gallons per day
MMT million metric tons
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Abbreviations and Acronyms
July 2015 Page vii
MPO metropolitan planning organization
MT metric ton
MWD Metropolitan Water District of Southern California
NAHC Native American Heritage Commission
NOX nitrogen oxides
NPDES National Pollution Discharge Elimination System
O3 ozone
OES California Office of Emergency Services
PM particulate matter
POTW publicly owned treatment works
ppm parts per million
PPV peak particle velocity
RCRA Resource Conservation and Recovery Act
REC recognized environmental condition
RMP risk management plan
RMS root mean square
RPS renewable portfolio standard
RWQCB Regional Water Quality Control Board
SB Senate Bill
SCAG Southern California Association of Governments
SCAQMD South Coast Air Quality Management District
SIP state implementation plan
SLM sound level meter
SoCAB South Coast Air Basin
SOX sulfur oxides
SQMP stormwater quality management plan
SRA source receptor area [or state responsibility area]
SUSMP standard urban stormwater mitigation plan
SWP State Water Project
SWPPP Storm Water Pollution Prevention Plan
SWRCB State Water Resources Control Board
TAC toxic air contaminants
TNM transportation noise model
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Abbreviations and Acronyms
Page viii PlaceWorks
tpd tons per day
TRI toxic release inventory
TTCP traditional tribal cultural places
USFWS United States Fish and Wildlife Service
USGS United States Geological Survey
UST underground storage tank
UWMP urban water management plan
V/C volume-to-capacity ratio
VdB velocity decibels
VHFHSZ very high fire hazard severity zone
VMT vehicle miles traveled
VOC volatile organic compound
WQMP water quality management plan
WSA water supply assessment
July 2015 Page 1
1. Introduction
Sierra Sands Unified School District (SSUSD or District) is evaluating the potential environmental
consequences associated with the New Murray Middle School project. The District proposes to relocate the
existing Murray Middle School program from 921 East Inyokern Road to a 47-acre site at the northwest
corner of Drummond Avenue and Knox Road, near the City of Ridgecrest on property owned by the United
States Department of Defense (DOD). The project includes acquiring the new school site via a 25-year,
renewable lease from the DOD, constructing and operating the new campus, and demolishing the existing
school.
Because the proposed project would be on federal land owned by DOD and would be state and federally
funded, it is required to undergo environmental review pursuant to both the California Environmental
Quality Act (CEQA) and National Environmental Policy Act (NEPA). NEPA requirements have been
satisfied; DOD has prepared and approved two Categorical Exclusions for the project (see Appendices A.1
and A.2).
This document satisfies the requirements of CEQA. This initial study has been prepared to determine
whether an Environmental Impact Report (EIR) or a Negative Declaration is required. If the Initial Study
concludes that the project may have a significant effect on the environment, an EIR must be prepared.
Otherwise, a Negative Declaration or Mitigated Negative Declaration (MND) is prepared. The information in
this Initial Study supports the conclusion for preparation of a MND.
1.1 PROJECT LOCATION
The proposed project encompasses two project sites that are slightly over one mile apart in the Naval Air
Weapons Station (NAWS) China Lake, North Range, adjacent to the City of Ridgecrest in Kern County,
California.
The existing Murray Middle School site is at 921 East Inyokern Road. The school is on the south side of
East Inyokern Road between North Lauristen Road and North Richmond Road, within the secured
premises of China Lake. Access to the site is via the main gate at the intersection of China Lake
Boulevard and Inyokern Road. The site is approximately one mile east of North China Lake Boulevard
(US 395 Business Route).
The proposed new Murray Middle School site is at 200 E. Drummond Avenue, on the northwest corner
of Drummond Avenue and Knox Road. Drummond Avenue abuts the southern property line, while
Knox Road abuts the eastern property line. The northern property line generally aligns with Burroughs
Avenue and/or the northern boundary of Burroughs High School located at 500 East French Avenue.
The site is approximately one-quarter mile east of North China Lake Boulevard.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 2 PlaceWorks
The City of Ridgecrest is in the Western Mojave Desert region of California, approximately 150 miles
northeast of Los Angeles. Figure 1, Regional Location, and Figure 2, Local Vicinity, illustrate the location of the
project sites in their regional and local contexts. Figure 3, Legal Description Map, demonstrates the dimensions
of the new school site, and Figure 4, Aerial Photograph, New Campus, is an aerial view of the proposed school
site.
1.2 ENVIRONMENTAL SETTING
1.2.1 Existing Land Use
1.2.1.1 EXISTING CAMPUS
The existing Murray Middle School was originally built in 1945, although some buildings on the campus are
newer. Enrollment was 590 during the 2013–2014 school year (CDE 2015). Over half the students are
dependents of people working on base. The campus consists of several buildings surrounding a central quad:
three permanent classroom buildings, three portable classrooms, an administration building, a cafeteria, and a
music building. Two other permanent buildings, the gymnasium and locker room building, are south and
southeast, respectively, of the buildings clustered around the quad. Numerous portable buildings south of the
main complex of buildings, plus two warehouse buildings in the southeast part of the campus, house the
District transportation department, temporary bus yard, garage, food services offices, and warehouses. There
are hardcourts to the west and east of the main complex of buildings, and a track and field in the northeast
part of the campus. Vehicular access is from Inyokern Road along the north campus boundary, and the
school’s parking lot is in the north-central part of campus. The parent drop-off lane is alongside Inyokern
Road on the north campus boundary.
Community use of the campus is limited due to the location of the campus inside the base and thus subject
to limited access. The school day extends from 7:25 AM to 2:20 PM, consisting of seven periods about 55
minutes each. The school year is consistent with that of the District’s traditional calendar year, which typically
begins near Labor Day and ends in June the following year. Figure 5, Site Map, Existing Campus, demonstrates
the layout of the existing facilities. Figure 6, Site Photographs, Existing Campus, depicts the condition of the
existing school site.
1.2.1.2 NEW CAMPUS
The proposed new school site is vacant and consists of disturbed desert habitat. Remnants of a former
housing development (e.g., abandoned underground utilities, including gas, water, sewer, and storm drains)
are present on the northern portion of the site, and concrete pads and footers that once supported an
electrical substation are near the southeast corner of the site. The residences were built between 1959 and
1961 and were demolished in 2002 (see Appendix B, “Environmental Condition of Property Report”). Figure
7, Site Photographs, New Campus, depicts the existing condition of the new school site. Figure 8, Historical
Photograph, New Campus, shows the condition of the project area prior to the demolition of the naval homes.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 3
Figure 1 Regional Location
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 4 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 5
Figure 2 Local Vicinity
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 6 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 7
Figure 3 Legal Description Map
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 8 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 9
Figure 4 Aerial Photograph, New Campus
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 10 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 11
Figure 5 Site Map, Existing Campus
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 12 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 13
Figure 6 Site Photographs, Existing Campus
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 14 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 15
Figure 7 Site Photographs, New Campus
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 16 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 17
Figure 8 Historical Photograph, New Campus
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 18 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 19
1.2.2 Surrounding Land Use
1.2.2.1 EXISTING CAMPUS
The existing campus is surrounded to the east, south, and west by vacant land; land to the south and west was
formerly developed as single-family housing. To the north of the campus, opposite Inyokern Road, are a
training facility used by China Lake and Bennington Plaza—the main commercial center on the base—which
includes a commissary, post office, barber shop, gymnasium, and a theater (Chattel 2012). Figure 9, Aerial
Photograph, Existing Campus, shows the conditions of the existing school.
1.2.2.2 NEW CAMPUS
The surrounding area at the proposed new school site is interspersed vacant land and suburban development.
Burroughs High School is directly east and opposite of Knox Road. Farther east is a solar panel farm on the
naval station. Southeast of the site is currently vacant; however, it is slated for development of a parking lot
as a part of the proposed improvements at Burroughs High School. Leroy Jackson Park Sports Complex (a
Ridgecrest city park) and the rear of a commercial strip mall along China Lake Boulevard are south of the
site. Immediately west and north of the site are vacant, undeveloped areas within the fences of China Lake.
Farther west is another commercial use along China Lake Boulevard, and farther north is Las Flores
Elementary School. Figure 10, Surrounding Uses, New Campus, shows the conditions of the surrounding area.
1.3 SIERRA SANDS UNIFIED SCHOOL DISTRICT
Sierra Sands Unified School District spans 970 square miles in northeastern Kern and northwestern San
Bernardino counties. The District operates seven elementary schools, two middle schools, one high school,
one continuation high school, and one adult school. Districtwide enrollment in the 2013–2014 school year
was 4,933 (CDE 2015).
1.4 PROJECT DESCRIPTION
The proposed project is the relocation of the existing Murray Middle School program to a new school site.
As a part of the project, the District would lease the new site from DOD and construct a new middle school
campus. Once the new campus is in operation, the existing school would be demolished.
1.4.1 Proposed Land Use
1.4.1.1 LEASE OF NEW SCHOOL SITE
Development of the new Murray Middle School would require leasing a 47-acre site from DOD. Only the
eastern 31 acres (or two-thirds) would be developed, and the western third would remain in its current
undeveloped state. A seven-foot-high chain link fence would be installed around the main campus; the access
driveways and parking lots would not be within the fenced area.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 20 PlaceWorks
1.4.1.2 PROPOSED FACILITIES
School Buildings
As illustrated in Figure 11, Site Plan, New Campus, the proposed school buildings would be built generally in
the northeast quadrant of the new school site. The District proposes construction of four sets of one-story
buildings, with a total building area of 68,243 square feet and heights ranging from 20 to 30 feet. The
buildings would house 28 teaching stations, gymnasium with stage, kitchen/cafeteria (multipurpose room),
administration, music and art, and library. The gymnasium would have one basketball court and pull-out
bleachers for up to 300 spectator seats. The buildings would surround a landscaped courtyard with the
administration and multipurpose/kitchen buildings east of the quad, the gymnasium/locker room and
art/music buildings to the north, and the remaining classroom buildings to the west and south. Table 1,
Proposed School Buildings Specifications, summarizes the proposed improvements.
Table 1 Proposed School Buildings Specifications Building Uses Teaching Stations Area (square feet) Height (feet)
D1 Classrooms, computer classroom, information center, textbook room
41
33,944 SF total buildings D1-D5
20
D2 Science classrooms, science labs, classroom, collaboration room
6 20
D3 Classrooms 5 20
D4 Classrooms 5 20
D5 Classrooms 5 20
A1 Administration 0 14,846 SF total buildings A1-A2
20
A2 Multipurpose Room, Kitchen 0 20
B Gym, locker room 0 19,453 SF total buildings B, C
30
C Music/art (1 choir classroom, 1 band classroom, 1 art classroom)
3 20
Total Not applicable 28 68,243 Not applicable 1 The information center is not counted here as a teaching station.
Outdoor Athletic Facilities
Outdoor athletic facilities would surround the school buildings. Four basketball courts are proposed to the
north of the buildings, a natural turf soccer/football field with a dirt track is proposed to the west, and a dirt
softball field to the southwest.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 21
Figure 9 Aerial Photograph, Existing Campus
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 22 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 23
Figure 10 Surrounding Uses, New Campus
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 24 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 25
Figure 11 Site Plan, New Campus
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 26 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 27
Access, Circulation, and Parking
The main vehicular entrance to the campus would be via a one-way loop driveway of approximately 1,300
linear feet in the southern part of the campus. Ingress and egress would be from Drummond Avenue and
separated by approximately 400 feet. Due to the short distance between the two access points, egress would
be restricted to right-turn only, toward China Lake Boulevard. The drop-off lane, lined with trees, would be
along the loop driveway. The school’s main parking lot with 87 stalls is proposed at the southeast corner of
the site; access would be from the loop driveway. A motorized arm gate would separate 8 visitor stalls from
the remaining 79 stalls. Four ADA parking spaces would also be provided at the northeast corner of the
campus; separate access would be from Knox Road. The campus would have a total of 91 off-street parking
spaces. The bus drop-off lane would be a one-way southbound loop on the east side of the campus with
entry and exit from Knox Road. A fire lane would extend behind the campus from the driveway at the
northeast corner, generally continuing behind the northern and western school buildings to the loop driveway
in the southern part of the campus.
Lighting
Only parking and security lighting is proposed throughout the campus; no night time field lighting would be
installed.
1.4.1.3 UTILITIES
Water
A network of water lines would be installed: 2- to 4-inch domestic water lines and 4- and 10-inch fire water
lines. Two water lines, a 4-inch domestic water line and a 10-inch fire water line, would extend to the center
of Drummond Avenue next to the west site boundary. From the ends of these water lines, a 12-inch water
main would be installed in Drummond Avenue and run about 105 feet north to an existing 12-inch water
main in Drummond Avenue.
Sewer
A network of sewer pipes and laterals ranging from four to eight inches in diameter would be installed. An
eight-inch pipe would extend to the northern part of the Burroughs High School campus, where it would
connect to an existing sewer main operated by NAWS China Lake.
Drainage
Project development would include construction of nine storm water retention basins. Basins 1, 2, 4, 5, 6,
and 7 would provide drainage for the main building area and the stadium and softball field. Basin 3 would
provide drainage for vacant land in the western part of the project site. Basins 8 and 9 would provide
drainage for the parking lots and vacant land in the southern part of the site. The proposed retention basins
would infiltrate the estimated runoff from the site into the soil in postproject conditions from a 10-year, 5-
day storm. The retention basins would not have outlets, except for basins 5 and 6, which would have outlets
into Basin 7.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 28 PlaceWorks
1.4.1.4 OPERATION
Similar to the existing program, the new Murray Middle School program would serve grades 6 through 8. The
new campus would provide up to 896 seats, assuming a conservative loading factor of 32 seats per classroom.
The school would employ between 60 and 65 certificated and classified employees.
The project would not change the existing Murray Middle School attendance boundary. Most students would
continue to be bused to school or dropped off. A few would walk, bicycle, or skateboard to school. The
busing program is anticipated to be similar to the one at the existing school. Between seven and eight school
buses would be used for over a third of the student enrollment, which would continue to be bused.
Due to its proximity to Burroughs High School, however, the start time of the new Murray campus would
change to 8:05 AM; the existing Murray program starts at 7:20 AM and ends at 2:20 PM. Burroughs’ start
time would remain at 7:25 AM. Teachers typically arrive 15 minutes prior to school starting and leave 15
minutes after the last bell. The school year would run from August to May, and summer school would be
offered occasionally at the campus, if needed. After-school enrichment and daycare programs would generally
end at 5:00 PM.
The new campus would be available for use by the District and other District schools, such as Burroughs
High School, for staff development, student performances, athletic events, overflow parking, curricular
collaboration, and ceremonial events. When the facilities are not used by the District, they would be available
for use by DOD and the community via the Civic Center Act (Education Code §§ 38130–38139).
1.4.1.5 CONSTRUCTION
In October 2015, or soon after the Board of Education approves the project, the District would commence
soil removal activities in connection with grading activities. Grading would occur generally on the eastern 31
acres of the 47-acre site where the improvements are proposed; the western third would remain in its current
condition. The construction area would be cleared of existing vegetation and all above- and below-ground
structures, including utilities that served the previous residential uses in the northern portion of the proposed
new campus. If site clearing and vegetation removal occurs during bird breeding season, between February 1
and August 31, a preconstruction nesting bird survey would be conducted in compliance with the federal
Migratory Bird Treaty Act (16 U.S.C. §§ 703–712). If active nests are observed during the survey, a no-
construction buffer would be placed around the active nests. The size of the buffer would depend upon the
species present. Construction within the buffer area would resume after a qualified biologist confirms that the
birds are no longer nesting.
Due to previous uses of pesticides (dieldrin and aldrin) on the northern portion of the site (former base
housing), soil remediation would be required in the affected areas. Soil in four general areas has been
identified for removal, as described below and illustrated in Figure 12, Soil Removal and Reburial Areas:
Area A. Soil will be removed from an area of 203,430 square feet (4.7 acres) to depths ranging from 0.5
to 2.5 feet below ground surface (bgs), defined by seven subareas. This portion of the removal action will
generate an estimated 6,982 cubic yards of soil.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 29
Figure 12 Soil Removal and Reburial Areas
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 30 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 31
Area B. Soil will be removed from an area of 179,160 square feet (4.1 acres) to depths ranging from 0.5
to 3.0 feet bgs, defined by eight subareas. This portion of the removal action will generate an estimated
5,555 cubic yards of soil.
Area C. Soil will be removed from an area of 128,930 square feet (3.0 acres) to depths ranging from 0.5
to 3.0 feet bgs, defined by seven subareas. This portion of the removal action will generate an estimated
4,965 cubic yards of soil.
Area D. Soil will be removed from an area of 40,351 square feet (0.9 acres) to depths ranging from 0.5 to
3.0 feet bgs, defined by six subareas. This portion of the removal action will generate an estimated 1,620
cubic yards of soil.
The estimated volume of impacted soil that requires removal is 20,077 cubic yards, including a 5 percent
contingency to account for the results of postremoval confirmation soil sampling. Almost all of the removed
soil can be managed as nonhazardous waste, but a very small volume (<10 cubic yards) will require
management as non-RCRA (Resource Conservation and Recovery Act) hazardous waste.
The District has entered into an agreement with the Department of Toxic Substances Control (DTSC) to
complete all site investigations and response actions under the oversight of the DTSC. The District has
prepared a Removal Action Workplan with three remedial options:
Alternative 1 (No Action). This alternative is required as a baseline to which all other remedial
alternatives can be compared. This alternative involves taking no action toward a remedy nor active
management to achieve the remediation goal of developing a school on the project site.
Alternative 2 (Soil Excavation and Offsite Disposal). This option involves the excavation and offsite
disposal of soil impacted by pesticides. An estimated 20,077 cubic yards of impacted soil would be
excavated to depths ranging from 0.5 to 3.0 feet bgs. Once the impacted soil is removed, confirmation
soil samples would be collected from the exposed excavation sidewalls and bottoms to confirm that the
site specific cleanup goals have been met and the removal action objectives have been achieved. Because
the site is considered to be balanced with respect to soil import/export, a similar volume of clean soil
(20,077 cubic yards) would need to be imported to compensate for the impacted soil that would be
removed. Exported soil would likely be taken to the Lancaster Landfill and Recycling Center, which is 83
miles southwest of Ridgecrest, and/or the Antelope Valley Public Landfill, which is 95 miles southwest
of Ridgecrest. It is not known at this time where soil would be imported from. Excavation and offsite
disposal would be an effective means of removing impacted soil and would meet the remediation goal.
Alternative 3 (Soil Excavation and Onsite Burial, Capping, and Land Use Covenant). As with
Alternative 2, Alternative 3 involves the excavation and removal of an estimated 20,077 cubic yards of
pesticide-impacted soil. However, rather than disposing of this soil offsite, it would be placed in an
engineered onsite burial cell (Figure 12) and covered by a protective soil cap, in accordance with
engineering design plans approved by the DTSC. Individual soil removal areas would be backfilled
immediately after soil samples confirm that all of the contaminated soil in that area/subarea has been
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 32 PlaceWorks
removed (to the burial cell) and DTSC has reviewed the lab data and provided informal approval to
backfill. A small amount of non-RCRA hazardous soil (<10 cubic yards) would be disposed of offsite,
either at the Kettleman or Buttonwillow landfills, approximately 200 and 150 miles west of Ridgecrest,
respectively. The remainder would be loaded into end-dump trucks and transferred to the burial cell.
Once the burial cell has been backfilled to a depth no shallower than two feet below grade, an engineered
cap would be constructed above the buried soil. The cap would consist of a permeable geotextile mat
overlain by a two-foot-thick soil cover of clean soil reserved during excavation of the burial cell. The
cover soil would be applied, compacted, and graded in accordance with the approved design plans to
promote drainage and minimize wind and water erosion. Once completed, the cap would be hydroseeded
with acceptable desert vegetation to establish a vegetated root mat that would minimize erosion and
facilitate evapotranspiration. The cap would be subject to long-term inspections and maintenance to
ensure that it would continue to function as intended. A land use restriction would also be applied to the
burial site, and future development options would be limited.
Alternative 3 is preferred because it is most cost-effective, easily implemented, and protective of future
occupants of the proposed school and the environment. Because it is also the most likely alternative to be
approved by DTSC, this Initial Study only analyzes the impacts associated with Alternative 3.
Although it is anticipated that soil remediation activities would commence shortly after the project is
approved by the Board of Education in fall 2015, construction of the proposed school improvements atop
the areas impacted by contaminated soil cannot commence until DTSC concurs that they have been
appropriately remediated for school development and/or issues a letter of No Further Action for the entire
removal process.
Once approved by DTSC, site grading would be completed, followed by the necessary trenching (for utility
hookups to buildings). The building foundation, buildings, and utilities would then be constructed. Finally, the
area surrounding the buildings would be covered with concrete and asphalt; curb cut-breaks and driveways
would be added; sidewalks located along the perimeter of the proposed new school site would be improved;
and landscaping, site fencing, and any final work would be completed. The new campus would open in fall
2017.
Once the new Murray Middle School is operating, the existing middle school at 921 Inyokern Road would
close. Nonschool uses, including the temporary bus yard, District transportation department, warehouse,
garage, and administrative food services, would remain in operation at the existing site. Although the Navy
has not confirmed whether it will maintain the existing classroom facilities, for the purposes of this initial
study, it is assumed the District would demolish them in the fourth quarter of 2017. The buildings proposed
for demolition are depicted in Figure 13, Demolition, Existing Campus. Demolition of the existing school would
require testing of the building materials for the presence of asbestos-containing material and lead-based
paint. If asbestos or lead is found, the contaminated material would be abated in accordance with all
applicable requirements, including East Kern Air Pollution Control District Rule 423, and the materials would
be properly disposed of. Uncontaminated materials would be recycled, to the extent feasible, and remaining
debris disposed of at an approved landfill.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 33
Figure 13 Demolition, Existing Campus
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 34 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 35
Construction Best Management Practices
The District requires its construction contractor to comply with all applicable rules and regulations in
carrying out the construction of the proposed project. Project implementation would also comply with the
District’s Construction Best Management Practices (BMP), which are established and refined as part of the
District’s current building efforts.
Construction Traffic. The District requires its contractors to submit a worksite traffic control plan to the
City of Ridgecrest and to the China Lake Police Department for review prior to construction. The plan
would show the location of haul routes, construction hours, protective devices, warning signs, and access to
abutting properties.
Construction Air Emissions. The District requires its construction contractors to comply with all
applicable East Kern Air Pollution Control District (EKAPCD) rules (e.g., Rule 402, Fugitive Dust) and
regulations in carrying out construction activities. To reduce the potential for significant hazardous emissions,
the District or its contractor would:
Maintain slow speeds with all vehicles;
Load impacted soil directly into transportation trucks to minimize soil handling;
During dumping, minimize soil drop height into transportation trucks or stockpiles;
During transport, cover or enclose trucks transporting soils, maintain a freeboard height of at least 12
inches, and repair trucks exhibiting spillage due to leaks;
Place stockpiled soil in areas shielded from prevailing winds;
During active demolition and debris removal, apply water every 4 hours to the area within 100 feet of the
structure being demolished to reduce vehicle trackout;
Use a gravel apron to reduce mud/dirt trackout from unpaved truck exit routes;
During demolition activities, apply water to disturbed soils, both after demolition is completed and at the
end of each day of cleanup;
Prohibit demolition activities when wind speeds exceed 25 miles per hour;
Implement the following for construction combustion equipment:
Use Tier 2 vehicles or the equivalent alternative fueled or catalyst equipped diesel construction
equipment, where practicable, including all off-road and portable diesel powered equipment.
Ensure that idling time will be minimized by either shutting equipment off when not in use or
reducing the time of idling to 5 minutes as a maximum.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 36 PlaceWorks
Construction Noise. The District requires the construction contractor to keep properly functioning
mufflers on all internal combustion and vehicle engines used in construction. The District requires its
construction contractor to provide advance notice of the start of construction to include all noise sensitive
receptors, businesses, and residences adjacent to the new school site and specifically when and where
construction activities will occur and provide contact information for filing noise complaints. During
construction activities, the construction contractor will, to the extent feasible, locate portable equipment and
shall store and maintain equipment away from the adjacent residents; will require all mobile or stationary
internal combustion engine powered equipment or machinery be equipped with exhaust and air intake
silencers in proper working order; and will require all construction equipment be properly maintained with
operating mufflers and air intake silencers as effective as those originally installed by the manufacturer. The
District requires its construction contractors to comply with all applicable noise ordinances of the affected
jurisdiction(s) and when necessary to comply with all applicable noise ordinances.
Cultural Resources. If a cultural resource (i.e., historic or prehistoric artifact, fossilized shell, or bone) is
discovered during ground-disturbing activities, the District requires that the construction contractor stop all
work within the immediate area and notify the District, and that the find be evaluated by a qualified
archaeologist and/or paleontologist. If the find is determined to be potentially significant, the archaeologist,
in consultation with the District and DOD, shall develop a treatment plan. All work in the immediate vicinity
of the unanticipated discovery shall cease until the qualified archaeologist and/or paleontologist has evaluated
the discovery or the treatment plan has been implemented.
Hazardous Materials Management. The District requires its construction contractor to remediate
hazardous materials at the new school site under supervision of the District. The potential hazards at the
existing campus are generally limited to asbestos-containing materials; lead-based paint; fluorescent light
tubes and ballasts; and lab chemicals, paints, and solvents. The District will also ensure that all remediation for
the proposed New Murray Middle School project is performed pursuant to the Remedial Action Workplan,
and with the oversight of DTSC.
1.5 EXISTING ZONING AND GENERAL PLAN
The Commanding Officer of NAWS China Lake has authority for all land use decisions on the facility. The
facility land use plan is the Comprehensive Land Use Management Plan issued in 2005. The existing school
and proposed school sites are in the North Range of China Lake. The new school site is in the Mainsite Land
Management Unit, which has the station headquarters, principal laboratories, and most of the administrative
and support functions of China Lake; it is the largest developed area at the station. The sites are in an area
designated as a buffer zone between offbase parts of the City of Ridgecrest and mission-related parts of
China Lake (Fox 2012).
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
July 2015 Page 37
1.6 DISCRETIONARY ACTIONS
1.6.1 Lead Agency
Sierra Sands Unified School District is the lead agency under CEQA for the proposed project. As part of the
project approval process, the District Board of Education must adopt the MND (including this Initial Study)
as adequate in complying with the requirements of CEQA before taking any action on the proposed project.
The board is required to consider the information in the MND while making a decision to approve or deny
the proposed project. In accordance with CEQA requirements, the analysis in the MND provides
environmental review for the whole of the proposed project, including the planning, construction, and
ongoing operation.
1.6.2 Responsible Agencies
A public agency other than the lead agency that has discretionary approval power over a project is a
responsible agency, according CEQA Guidelines. The responsible agencies and their corresponding approvals
for the proposed project include:
United States Department of Navy (authority for all land use decisions on the facility, including approval
of lease agreement and Facilities Alteration Request)
Department of Toxic Substances Control (letter of No Further Action)
Lahontan Regional Water Quality Control Board (National Pollution Discharge Elimination System
Permit; issuance of waste discharge requirement; construction of stormwater runoff permits)
City of Ridgecrest Public Works (approval of offsite improvements permits, such as grading and drainage
plans; permits for curb cuts for driveways; and various street and signage improvements, if required).
City of Ridgecrest Police Department (approval of police services)
Kern County Fire Department (approval of the fire access and safety plan)
1.6.3 Reviewing Agencies
Reviewing agencies do not have discretionary powers to approve or deny the proposed project or actions
needed to implement it, but may review the Initial Study for adequacy and accuracy. Potential reviewing
agencies include:
Bureau of Land Management
California Department of Education
Department of Transportation (Caltrans)
Department of Fish and Game
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
1. Introduction
Page 38 PlaceWorks
Division of the State Architect
Native American Heritage Commission
City of Ridgecrest Planning and Public Services Department
Office of Historic Preservation
East Kern Air Pollution Control District
July 2015 Page 39
2. Environmental Checklist
2.1 BACKGROUND
1. Project Title: New Murray Middle School
2. Lead Agency Name and Address: Sierra Sands Unified School District 113 Feldspar Ridgecrest, CA 93555
3. Contact Person and Phone Number: Pamela Pence, Program Manager 760.499.5300
4. Project Location: The project would be carried out on two sites: the existing Murray Middle School campus at 921 East Inyokern Road and the new school site proposed at the northwest corner of Drummond Avenue and Knox Avenue on the Naval Air Weapons Station China Lake, near the City of Ridgecrest in northeastern Kern County.
5. Project Sponsor’s Name and Address: Sierra Sands Unified School District 113 Feldspar Ridgecrest, CA 93555
6. General Plan Designation: The Department of the Navy regulates station land use. The Commanding Office has authority for all land use decisions on the facility. The Comprehensive Land Use Management Plan identifies the new school site in the Mainsite Land Management Unit, which is an area designated as a buffer zone between off-base parts of the City of Ridgecrest and mission-related parts of China Lake (Fox 2012).
7. Zoning: The site is within the jurisdiction of China Lake; see General Plan Designation above.
8. Description of Project: The project involves the lease of a 47-acre site for relocation of the existing Murray Middle School program. The new campus would include classroom buildings with a total of 28 teaching stations, a gymnasium, an administration building, and a multipurpose/kitchen building; a track and field; a baseball field; and outdoor basketball courts. The school would have a capacity of 896 seats. The existing Murray Middle School campus would be demolished after the opening of the new school.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
2. Environmental Checklist
Page 40 PlaceWorks
9. Surrounding Land Uses and Setting: Burroughs High School is across Knox Road, directly east of the new campus site. Southeast of the site is vacant; however, development of a parking lot has been approved as a part of the improvements at Burroughs High School. Leroy Jackson Park Sports Complex (a city park) and the rear of a commercial strip mall off China Lake Boulevard are south of the site. Immediately west and north of the site are vacant, undeveloped areas within the fenced area of China Lake.
10. Other Public Agencies Whose Approval Is Required:
United States Department of Navy
Department of Toxic Substances Control
Lahontan Regional Water Quality Control Board
City of Ridgecrest Public Works
City of Ridgecrest Police Department
Kern County Fire Department
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
2. Environmental Checklist
July 2015 Page 41
2.2 ENVIRONMENTAL FACTORS POTENTIALLY AFFECTED
The environmental factors checked below would be potentially affected by this project, involving at least one
impact that is a “Potentially Significant Impact,” as indicated by the checklist on the following pages.
Aesthetics Agricultural and Forest Resources Air Quality
Biological Resources Cultural Resources Geology / Soils
Greenhouse Gas Emissions Hazards & Hazardous Materials Hydrology / Water Quality
Land Use / Planning Mineral Resources Noise
Population / Housing Public Services Recreation
Transportation / Traffic Utilities / Service Systems Mandatory Findings of Significance
2.3 DETERMINATION (TO BE COMPLETED BY THE LEAD AGENCY)
On the basis of this initial evaluation:
I find that the proposed project COULD NOT have a significant effect on the environment, and a
NEGATIVE DECLARATION will be prepared.
I find that although the proposed project could have a significant effect on the environment, there
will not be a significant effect in this case because revisions in the project have been made by or agreed to by the project proponent. A MITIGATED NEGATIVE DECLARATION will be prepared.
I find that the proposed project MAY have a significant effect on the environment, and an
ENVIRONMENTAL IMPACT REPORT is required.
I find that the proposed project MAY have a “potentially significant impact” or “potentially
significant unless mitigated” impact on the environment, but at least one effect 1) has been adequately analyzed in an earlier document pursuant to applicable legal standards, and 2) has been addressed by mitigation measures based on the earlier analysis as described on attached sheets. An ENVIRONMENTAL IMPACT REPORT is required, but it must analyze only the effects that remain to be addressed.
I find that although the proposed project could have a significant effect on the environment, because
all potentially significant effects (a) have been analyzed adequately in an earlier EIR or NEGATIVE DECLARATION pursuant to applicable standards, and (b) have been avoided or mitigated pursuant to that earlier EIR or NEGATIVE DECLARATION, including revisions or mitigation measures that are imposed upon the proposed project, nothing further is required.
Signature Date
Printed Name For
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
2. Environmental Checklist
Page 42 PlaceWorks
2.4 EVALUATION OF ENVIRONMENTAL IMPACTS
1) A brief explanation is required for all answers except “No Impact” answers that are adequately supported by the information sources a lead agency cites in the parentheses following each question. A “No Impact” answer is adequately supported if the referenced information sources show that the impact simply does not apply to projects like the one involved (e.g., the project falls outside a fault rupture zone). A “No Impact” answer should be explained where it is based on project-specific factors, as well as general standards (e.g., the project would not expose sensitive receptors to pollutants, based on a project-specific screening analysis).
2) All answers must take account of the whole action involved, including off-site as well as on-site, cumulative as well as project-level, indirect as well as direct, and construction as well as operational impacts.
3) Once the lead agency has determined that a particular physical impact may occur, then the checklist answers must indicate whether the impact is potentially significant, less than significant with mitigation, or less than significant. “Potentially Significant Impact” is appropriate if there is substantial evidence that an effect may be significant. If there are one or more “Potentially Significant Impact” entries when the determination is made, an EIR is required.
4) “Negative Declaration: Less Than Significant With Mitigation Incorporated” applies where the incorporation of mitigation measures has reduced an effect from “Potentially Significant Impact” to a “Less Than Significant Impact.” The lead agency must describe the mitigation measures, and briefly explain how they reduce the effect to a less than significant level.
5) Earlier analyses may be used where, pursuant to the tiering, program EIR, or other CEQA process, an effect has been adequately analyzed in an earlier EIR or negative declaration. Section 15063(c)(3)(D). In this case, a brief discussion should identify the following:
a) Earlier Analyses Used. Identify and state where they are available for review.
b) Impacts Adequately Addressed. Identify which effects from the above checklist were within the scope of and adequately analyzed in an earlier document pursuant to applicable legal standards, and state whether such effects were addressed by mitigation measures based on the earlier analysis.
c) Mitigation Measures. For effects that are “Less than Significant with Mitigation Measures Incorporated,” describe the mitigation measures which were incorporated or refined from the earlier document and the extent to which they address site-specific conditions for the project.
6) Lead agencies are encouraged to incorporate into the checklist references to information sources for potential impacts (e.g., general plans, zoning ordinances). Reference to a previously prepared or outside document should, where appropriate, include a reference to the page or pages where the statement is substantiated. A source list should be attached, and other sources used or individuals contacted should be cited in the discussion.
7) Supporting Information Sources: A source list should be attached, and other sources used or individuals contacted should be cited in the discussion.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
2. Environmental Checklist
July 2015 Page 43
8) This is only a suggested form, and lead agencies are free to use different formats; however, lead agencies should normally address the questions from this checklist that are relevant to a project’s environmental effects in whatever format is selected.
9) The explanation of each issue should identify:
a) the significance criteria or threshold, if any, used to evaluate each question; and
b) the mitigation measure identified, if any, to reduce the impact to less than significant.
Issues
Potentially Significant
Impact
Less Than Significant
With Mitigation
Incorporated
Less Than Significant
Impact No
Impact
I. AESTHETICS. Would the project: a) Have a substantial adverse effect on a scenic vista? X b) Substantially damage scenic resources, including, but not
limited to, trees, rock outcroppings, and historic buildings within a state scenic highway?
X
c) Substantially degrade the existing visual character or quality of the site and its surroundings? X
d) Create a new source of substantial light or glare which would adversely affect day or nighttime views in the area? X
II. AGRICULTURE AND FORESTRY RESOURCES. In determining whether impacts to agricultural resources are
significant environmental effects, lead agencies may refer to the California Agricultural Land Evaluation and Site Assessment Model (1997) prepared by the California Dept. of Conservation as an optional model to use in assessing impacts on agriculture and farmland. In determining whether impacts to forest resources, including timberland, are significant environmental effects, lead agencies may refer to information compiled by the California Department of Forestry and Fire Protection regarding the state’s inventory of forest land, including the Forest and Range Assessment Project and the Forest Legacy Assessment project; and forest carbon measurement methodology provided in Forest Protocols adopted by the California Air Resources Board. Would the project:
a) Convert Prime Farmland, Unique Farmland, or Farmland of Statewide Importance (Farmland), as shown on the maps prepared pursuant to the Farmland Mapping and Monitoring Program of the California Resources Agency, to non-agricultural use?
X
b) Conflict with existing zoning for agricultural use, or a Williamson Act contract? X
c) Conflict with existing zoning for, or cause rezoning of, forest land (as defined in Public Resources Code Section 12220(g)), timberland (as defined by Public Resources Code Section 4526), or timberland zoned Timberland Production (as defined by Government Code Section 51104(g))?
X
d) Result in the loss of forest land or conversion of forest land to non-forest use? X
e) Involve other changes in the existing environment which, due to their location or nature, could result in conversion of Farmland, to non-agricultural use or conversion of forest land to non-forest use?
X
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
2. Environmental Checklist
Page 44 PlaceWorks
Issues
Potentially Significant
Impact
Less Than Significant
With Mitigation
Incorporated
Less Than Significant
Impact No
Impact
III. AIR QUALITY. Where available, the significance criteria established by the applicable air quality management or air
pollution control district may be relied upon to make the following determinations. Would the project: a) Conflict with or obstruct implementation of the applicable air
quality plan? X
b) Violate any air quality standard or contribute substantially to an existing or projected air quality violation? X
c) Result in a cumulatively considerable net increase of any criteria pollutant for which the project region is non-attainment under an applicable federal or state ambient air quality standard (including releasing emissions which exceed quantitative thresholds for ozone precursors)?
X
d) Expose sensitive receptors to substantial pollutant concentrations? X
e) Create objectionable odors affecting a substantial number of people? X
IV. BIOLOGICAL RESOURCES. Would the project: a) Have a substantial adverse effect, either directly or through
habitat modifications, on any species identified as a candidate, sensitive, or special status species in local or regional plans, policies, or regulations, or by the California Department of Fish and Game or U.S. Fish and Wildlife Service?
X
b) Have a substantial adverse effect on any riparian habitat or other sensitive natural community identified in local or regional plans, policies, regulations or by the California Department of Fish and Game or U.S. Fish and Wildlife Service?
X
c) Have a substantial adverse effect on federally protected wetlands as defined by Section 404 of the Clean Water Act (including, but not limited to, marsh, vernal pool, coastal, etc.) through direct removal, filling, hydrological interruption, or other means?
X
d) Interfere substantially with the movement of any native resident or migratory fish or wildlife species or with established native resident or migratory wildlife corridors, or impede the use of native wildlife nursery sites?
X
e) Conflict with any local policies or ordinances protecting biological resources, such as a tree preservation policy or ordinance?
X
f) Conflict with the provisions of an adopted Habitat Conservation Plan, Natural Community Conservation Plan, or other approved local, regional, or state habitat conservation plan?
X
V. CULTURAL RESOURCES. Would the project: a) Cause a substantial adverse change in the significance of a
historical resource as defined in § 15064.5? X
b) Cause a substantial adverse change in the significance of an archaeological resource pursuant to § 15064.5? X
c) Directly or indirectly destroy a unique paleontological resource or site or unique geologic feature? X
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
2. Environmental Checklist
July 2015 Page 45
Issues
Potentially Significant
Impact
Less Than Significant
With Mitigation
Incorporated
Less Than Significant
Impact No
Impact
d) Disturb any human remains, including those interred outside of formal cemeteries? X
VI. GEOLOGY AND SOILS. Would the project: a) Expose people or structures to potential substantial adverse
effects, including the risk of loss, injury, or death involving:
i) Rupture of a known earthquake fault, as delineated on the most recent Alquist-Priolo Earthquake Fault Zoning Map, issued by the State Geologist for the area or based on other substantial evidence of a known fault? Refer to Division of Mines and Geology Special Publication 42.
X
ii) Strong seismic ground shaking? X
iii) Seismic-related ground failure, including liquefaction? X
iv) Landslides? X
b) Result in substantial soil erosion or the loss of topsoil? X c) Be located on a geologic unit or soil that is unstable, or that
would become unstable as a result of the project, and potentially result in on- or off-site landslide, lateral spreading, subsidence, liquefaction or collapse?
X
d) Be located on expansive soil, as defined in Table 18-1-B of the Uniform Building Code (1994), creating substantial risks to life or property?
X
e) Have soils incapable of adequately supporting the use of septic tanks or alternative waste water disposal systems where sewers are not available for the disposal of waste water?
X
VII. GREENHOUSE GAS EMISSIONS. Would the project: a) Generate greenhouse gas emissions, either directly or
indirectly, that may have a significant impact on the environment?
X
b) Conflict with an applicable plan, policy or regulation adopted for the purpose of reducing the emissions of greenhouse gases?
X
VIII. HAZARDS AND HAZARDOUS MATERIALS. Would the project: a) Create a significant hazard to the public or the environment
through the routine transport, use, or disposal of hazardous materials?
X
b) Create a significant hazard to the public or the environment through reasonably foreseeable upset and accident conditions involving the release of hazardous materials into the environment?
X
c) Emit hazardous emissions or handle hazardous or acutely hazardous materials, substances, or waste within one-quarter mile of an existing or proposed school?
X
d) Be located on a site which is included on a list of hazardous materials sites compiled pursuant to Government Code Section 65962.5 and, as a result, would it create a significant hazard to the public or the environment?
X
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
2. Environmental Checklist
Page 46 PlaceWorks
Issues
Potentially Significant
Impact
Less Than Significant
With Mitigation
Incorporated
Less Than Significant
Impact No
Impact
e) For a project located within an airport land use plan or, where such a plan has not been adopted, within two miles of a public airport or public use airport, would the project result in a safety hazard for people residing or working in the project area?
X
f) For a project within the vicinity of a private airstrip, would the project result in a safety hazard for people residing or working in the project area?
X
g) Impair implementation of or physically interfere with an adopted emergency response plan or emergency evacuation plan?
X
h) Expose people or structures to a significant risk of loss, injury or death involving wildland fires, including where wildlands are adjacent to urbanized areas or where residences are intermixed with wildlands?
X
i) Does the proposed school site contain one or more pipelines, situated underground or aboveground, which carry hazardous substances, acutely hazardous materials or hazardous wastes, unless the pipeline is a natural gas line that is used only to supply natural gas to that school or neighborhood?
X
j) Does the project site contain a current or former hazardous waste disposal site or solid waste disposal site and, if so, have the wastes been removed?
X
k) Is the project site a hazardous substance release site identified by the state Department of Health Services in a current list adopted pursuant to § 25356 for removal or remedial action pursuant to Chapter 6.8 of Division of the Health and Safety Code?
X
IX. HYDROLOGY AND WATER QUALITY. Would the project: a) Violate any water quality standards or waste discharge
requirements? X
b) Substantially deplete groundwater supplies or interfere substantially with groundwater recharge such that there would be a net deficit in aquifer volume or a lowering of the local groundwater table level (e.g., the production rate of pre-existing nearby wells would drop to a level which would not support existing land uses or planned uses for which permits have been granted)?
X
c) Substantially alter the existing drainage pattern of the site or area, including through the alteration of the course of a stream or river, in a manner which would result in a substantial erosion or siltation on- or off-site
X
d) Substantially alter the existing drainage pattern of the site or area, including through the alteration of the course of a stream or river, or substantially increase the rate or amount of surface runoff in a manner which would result in flooding on- or off-site?
X
e) Create or contribute runoff water which would exceed the capacity of existing or planned storm water drainage systems or provide substantial additional sources of polluted runoff?
X
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
2. Environmental Checklist
July 2015 Page 47
Issues
Potentially Significant
Impact
Less Than Significant
With Mitigation
Incorporated
Less Than Significant
Impact No
Impact
f) Otherwise substantially degrade water quality? X g) Place housing within a 100-year flood hazard area as mapped
on a federal Flood Hazard Boundary or Flood Insurance Rate Map or other flood hazard delineation map?
X
h) Place within a 100-year flood hazard area structures which would impede or redirect flood flows? X
i) Expose people or structures to a significant risk of loss, injury or death involving flooding, including flooding as a result of the failure of a levee or dam?
X
j) Inundation by seiche, tsunami, or mudflow? X
X. LAND USE AND PLANNING. Would the project: a) Physically divide an established community? X b) Conflict with any applicable land use plan, policy, or regulation
of an agency with jurisdiction over the project (including, but not limited to the general plan, specific plan, local coastal program, or zoning ordinance) adopted for the purpose of avoiding or mitigating an environmental effect?
X
c) Conflict with any applicable habitat conservation plan or natural community conservation plan? X
XI. MINERAL RESOURCES. Would the project: a) Result in the loss of availability of a known mineral resource
that would be a value to the region and the residents of the state?
X
b) Result in the loss of availability of a locally important mineral resource recovery site delineated on a local general plan, specific plan or other land use plan?
X
XII. NOISE. Would the project result in: a) Exposure of persons to or generation of noise levels in excess
of standards established in the local general plan or noise ordinance, or applicable standards of other agencies?
X
b) Exposure of persons to or generation of excessive groundborne vibration or groundborne noise levels? X
c) A substantial permanent increase in ambient noise levels in the project vicinity above levels existing without the project? X
d) A substantial temporary or periodic increase in ambient noise levels in the project vicinity above levels existing without the project?
X
e) For a project located within an airport land use plan or, where such a plan has not been adopted, within two miles of a public airport or public use airport, would the project expose people residing or working in the project area to excessive noise levels?
X
f) For a project within the vicinity of a private airstrip, would the project expose people residing or working in the project area to excessive noise levels?
X
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
2. Environmental Checklist
Page 48 PlaceWorks
Issues
Potentially Significant
Impact
Less Than Significant
With Mitigation
Incorporated
Less Than Significant
Impact No
Impact
XIII. POPULATION AND HOUSING. Would the project: a) Induce substantial population growth in an area, either directly
(for example, by proposing new homes and businesses) or indirectly (for example, through extension of roads or other infrastructure)?
X
b) Displace substantial numbers of existing housing, necessitating the construction of replacement housing elsewhere?
X
c) Displace substantial numbers of people, necessitating the construction of replacement housing elsewhere? X
XIV. PUBLIC SERVICES. Would the project result in substantial adverse physical impacts associated with the provision of
new or physically altered governmental facilities, need for new or physically altered governmental facilities, the construction of which could cause significant environmental impacts, in order to maintain acceptable service ratios, response times or other performance objectives for any of the public services:
a) Fire protection? X b) Police protection? X c) Schools? X d) Parks? X e) Other public facilities? X
XV. RECREATION. a) Would the project increase the use of existing neighborhood
and regional parks or other recreational facilities such that substantial physical deterioration of the facility would occur or be accelerated?
X
b) Does the project include recreational facilities or require the construction or expansion of recreational facilities which might have an adverse physical effect on the environment?
X
XVI. TRANSPORTATION/TRAFFIC. Would the project: a) Conflict with an applicable plan, ordinance or policy
establishing measures of effectiveness for the performance of the circulation system, taking into account all modes of transportation including mass transit and non-motorized travel and relevant components of the circulation system, including but not limited to intersections, streets, highways and freeways, pedestrian and bicycle paths, and mass transit?
X
b) Conflict with an applicable congestion management program, including, but not limited to level of service standards and travel demand measures, or other standards established by the county congestion management agency for designated roads or highways?
X
c) Result in a change in air traffic patterns, including either an increase in traffic levels or a change in location that results in substantial safety risks?
X
d) Substantially increase hazards due to a design feature (e.g., sharp curves or dangerous intersections) or incompatible uses (e.g., farm equipment)?
X
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
2. Environmental Checklist
July 2015 Page 49
Issues
Potentially Significant
Impact
Less Than Significant
With Mitigation
Incorporated
Less Than Significant
Impact No
Impact
e) Result in inadequate emergency access? X f) Conflict with adopted policies, plans, or programs regarding
public transit, bicycle, or pedestrian facilities, or otherwise decrease the performance or safety of such facilities?
X
g) Result in inadequate parking capacity? X
XVII. UTILITIES AND SERVICE SYSTEMS. Would the project: a) Exceed waste water treatment requirements of the applicable
Regional Water Quality Control Board? X
b) Require or result in the construction of new water or waste water treatment facilities or expansion of existing facilities, the construction of which could cause significant environmental effects?
X
c) Require or result in the construction of new storm water drainage facilities or expansion of existing facilities, the construction of which could cause significant environmental effects?
X
d) Have sufficient water supplies available to serve the project from existing entitlements and resources or are new or expanded entitlements needed?
X
e) Result in a determination by the waste water treatment provider, which serves or may serve the project that it has adequate capacity to serve the project’s projected demand in addition to the provider’s existing commitments?
X
f) Be served by a landfill with sufficient permitted capacity to accommodate the project’s solid waste disposal needs? X
g) Comply with federal, state, and local statutes and regulations related to solid waste? X
XVIII. MANDATORY FINDINGS OF SIGNIFICANCE. a) Does the project have the potential to degrade the quality of
the environment, substantially reduce the habitat of a fish or wildlife species, cause a fish or wildlife population to drop below self-sustaining levels, threaten to eliminate a plant or animal community, reduce the number or restrict the range of a rare or endangered plant or animal or eliminate important examples of the major periods of California history or prehistory?
X
b) Does the project have impacts that are individually limited, but cumulatively considerable? (“Cumulatively considerable” means that the incremental effects of a project are considerable when viewed in connection with the effects of past projects, the effects of other current projects, and the effects of probable future projects.)
X
c) Does the project have environmental effects which will cause substantial adverse effects on human beings, either directly or indirectly?
X
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
2. Environmental Checklist
Page 50 PlaceWorks
This page intentionally left blank.
July 2015 Page 51
3. Environmental Analysis
3.1 AESTHETICS
a) Have a substantial adverse effect on a scenic vista?
No Impact. A scenic vista is considered an area that is visually or aesthetically pleasing, providing scenic
quality and view access. The City of Ridgecrest General Plan mentions scenic resources visible from the
city—four mountain ranges bounding the Indian Wells Valley and desert landscapes (Matrix 2008). The
proposed new school site is flat. Proposed buildings would be similar in height to the existing buildings at
Burroughs High School east of the site and the commercial uses west and northwest of the site. Project
implementation would not affect scenic vistas in the area, and the new structures would not obstruct
designated scenic views.
Demolition of the existing campus would have no adverse impact on scenic vistas visible from surrounding
roadways and land uses. No impact to a scenic vista would occur, and no mitigation measures are necessary.
b) Substantially damage scenic resources, including, but not limited to, trees, rock outcroppings,
and historic buildings within a state scenic highway?
Less Than Significant Impact. The City of Ridgecrest General Plan specifies several scenic corridors in the
City, including West Inyokern Road, North and South China Lake Boulevard, East and West Ridgecrest
Boulevard, West Bowman Road, College Heights Boulevard, West Drummond Avenue and Jacks Ranch
Road. The proposed new school site is not along any of the identified scenic corridors, the nearest of which
is North China Lake Boulevard 500 feet west of the site. There are no designated state scenic highways in the
project region (Caltrans 2011). The sites do not contain any historic buildings (see Section 5.5) or rock
outcroppings. There are no trees on the new school site. The proposed project would install and maintain
new landscaping that would enhance the visual quality to the site.
The existing campus was evaluated for historic significance by Chattel Architecture, Planning & Preservation
in 2012 (Appendix E.1) and found not to be eligible for listing on the California Register of Historic
Resources; thus, there are no historical buildings on the existing campus. There are trees on the campus, but
they are ornamental landscape trees characteristic of urban areas in the Mojave Desert and are not significant
scenic resources. Project development would not damage a scenic resource within a state scenic highway, and
impacts would be less than significant. No mitigation is required.
c) Substantially degrade the existing visual character or quality of the site and its surroundings?
Less Than Significant Impact. The visual character of the new school site is related to the quality of
streetscape, building(s), or other man-made or natural features, that define the area. The proposed new school
site is vacant and vegetated with desert scrub vegetation dominated by saltbush (Atriplex confertifolia). Several
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 52 PlaceWorks
roadways in poor condition remain onsite from previous residential development. Development of the
proposed middle school would change the visual character of the site. However, the visual character of the
proposed middle school would fit with the appearance of the nearby school and commercial uses, and the
project would not substantially degrade the visual character of the site or surroundings.
The existing campus is surrounded to the west, east, and south by vacant land; thus, demolition of the
campus and vacation of the site would not substantially degrade the visual character of the site compared to
surrounding land. Visual impacts are not significant, and no mitigation measures are required.
d) Create a new source of substantial light or glare, which would adversely affect day or nighttime
views in the area?
Less Than Significant Impact. The proposed project would not add significant new sources of light or
glare and would not adversely affect day or nighttime views in the area of the proposed new school site.
Sources of illumination as part of the proposed project would include security lighting, internal classroom
lighting, vehicle lights, and parking lot lights. Lighting would be installed in a manner to minimize glare for
pedestrians and drivers, and minimize spillover light. In addition, the District would apply design standards
that would reduce impacts that would adversely affect day or nighttime views, such as window shades and
glare shields. Finally, new lamp enclosures and poles would be painted or would have a natural color finish to
reduce reflection. The exterior finish of the proposed buildings would not include any highly reflective
surfaces, aside from standard glass windows.
Demolition of the existing campus would remove sources of light and glare from that site. Therefore, the
potential impact on daytime or nighttime views would be less than significant, and no mitigation measures are
required.
3.2 AGRICULTURE AND FORESTRY RESOURCES
In determining whether impacts to agricultural resources are significant environmental effects, lead agencies
may refer to the California Agricultural Land Evaluation and Site Assessment Model (1997) prepared by the
California Department of Conservation as an optional model to use in assessing impacts on agriculture and
farmland. In determining whether impacts to forest resources, including timberland, are significant
environmental effects, lead agencies may refer to information compiled by the California Department of
Forestry and Fire Protection regarding the state’s inventory of forest land, including the Forest and Range
Assessment Project and the Forest Legacy Assessment project; and forest carbon measurement methodology
provided in Forest Protocols adopted by the California Air Resources Board. Would the project:
a) Convert Prime Farmland, Unique Farmland, or Farmland of Statewide Importance (Farmland),
as shown on the maps prepared pursuant to the Farmland Mapping and Monitoring Program of
the California Resources Agency, to non-agricultural use?
No Impact. The proposed project would not convert Prime Farmland, Unique Farmland, or Farmland of
Statewide Importance to nonagricultural uses. The proposed new school site is mapped as Vacant or
Disturbed Land on the California Important Farmland Finder maintained by the Division of Land Resource
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 53
Protection (DLRP 2015). No agricultural uses exist in the project area. According to the Farmland Mapping
and Monitoring Program, the sites and surrounding area contain no Prime Farmland, Unique Farmland, or
Farmland of Statewide Importance (DLRP 2015).
The existing campus site is mapped as Urban and Built-Up Land on the Farmland Finder (DLRP 2015);
demolition of the existing campus would have no impact on mapped farmland. No farmland impacts would
occur, and no mitigation measures are necessary.
b) Conflict with existing zoning for agricultural use, or a Williamson Act contract?
No Impact. The proposed project would not conflict with agricultural zoning or a Williamson Act contract.
Although the new school site is on federal land, the City of Ridgecrest has designated the site as Urban
Reserve (UR), which is a designation held for land in reserve for future urban expansion. Limited animal
keeping is permitted in the UR district but crops and orchards are not permitted; thus, the UR zone is not
considered an agricultural zone. The site is surrounded to the south by RSP (Recreational/School/Public
Use) zoning, to the west by General Commercial (GC) zoning, and to the east by Burroughs High School,
which is also on UR zoning. There is no agricultural use onsite. The existing campus site is also in the Urban
Reserve zoning district.
Williamson Act contracts restrict the use of privately owned land to agriculture and compatible open-space
uses under contract with local governments; in exchange, the land is taxed based on actual use rather than
potential market value. There are no Williamson Act contracts in effect on the sites of the new middle school
or the existing middle school (DLRP 2013).
Therefore, the proposed project would not conflict with an existing agricultural use or with a Williamson Act
contract, and no impact would occur. No mitigation measures are necessary.
c) Conflict with existing zoning for, or cause rezoning of, forest land (as defined in Public
Resources Code Section 12220(g)), timberland (as defined by Public Resources Code
Section 4526), or timberland zoned Timberland Production (as defined by Government Code
Section 51104(g))?
No Impact. The proposed project would not conflict with existing zoning or cause rezoning of forest land,
timberland, or timberland zoned Timberland Production. The zoning designation on the sites of the new and
existing middle schools is Urban Reserve. Both sites are in the Mainsite Land Management Unit, the largest
developed area at China Lake. The site does not contain forestland, and the zoning does not allow for
timberland production. No impacts would occur, and no mitigation measures are required.
d) Result in the loss of forest land or conversion of forest land to non-forest use?
No Impact. Project development would not cause the loss of forest land or the conversion of forest land to
nonforest use. The proposed new school site is disturbed land with desert scrub vegetation. The surrounding
areas are largely urban in character and are not forested. In addition, the sites’ zoning designation is Urban
Reserve, which does not permit forestry use. No forest land is present on the existing campus, and demolition
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 54 PlaceWorks
of the existing campus would not cause a loss of forest land. No forestry impacts would occur, and no
mitigation measures are required.
e) Involve other changes in the existing environment which, due to their location or nature, could
result in conversion of Farmland, to non-agricultural use or conversion of forest land to non-
forest use?
No Impact. Project implementation would not result in the conversion of farmland or forest land to
nonagricultural or nonforest uses. There are no forested areas or designated farmland near the proposed new
school site that may be affected by project implementation. There is no farmland near the existing campus,
and demolition of the existing campus would not cause conversion of farmland to nonagricultural use.
Therefore, the proposed project would not result in the loss of farmland or forest land. No impact would
occur, and no mitigation measures are required.
3.3 AIR QUALITY
The Air Quality section addresses the impacts of the proposed project on ambient air quality and the
exposure of people, especially sensitive individuals, to unhealthful pollutant concentrations. A background
discussion on the air quality regulatory setting, meteorological conditions, existing ambient air quality in the
vicinity of the new school site, and air quality modeling can be found in Appendix C.1. A health risk
assessment (HRA) that evaluates the potential impacts of toxic air emissions on the proposed project is
provided in Appendix C.2.
The primary air pollutants of concern for which ambient air quality standards (AAQS) have been established
are ozone (O3), carbon monoxide (CO), coarse inhalable particulate matter (PM10), fine inhalable particulate
matter (PM2.5), sulfur dioxide (SO2), nitrogen dioxides (NO2), and lead (Pb). Areas are classified under the
federal and California Clean Air Act as in either attainment or nonattainment for each criteria pollutant based
on whether the AAQS have been achieved. The project sites are in eastern Kern County in the Mojave Desert
Air Basin (MDAB), which is managed by the Eastern Kern Air Pollution Control District (EKAPCD). The
MDAB is currently designated a “moderate” nonattainment area for California and National O3 AAQS and
nonattainment under the California PM10 AAQS.
Where available, the significance criteria established by the applicable air quality management or air pollution
control district may be relied upon to make the following determinations. Would the project:
a) Conflict with or obstruct implementation of the applicable air quality plan?
Less Than Significant Impact. EKAPCD is responsible for preparing the air quality management plan
(AQMP) for the eastern Kern County portion of the MDAB in coordination with the Kern County Council
of Governments (KCOG). In 2003, EKAPCD prepared the “Ozone Attainment Demonstration,
Maintenance Plan, and Redesignation Request for the Eastern Kern County Federal Planning Area.”
EKAPCD prepares its AQMP in coordination with the KCOG. Because the AQMP takes into account
growth within eastern Kern County based on regional projections from KCOG, only large projects that
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 55
exceed regional employment, population, and housing planning projections have the potential to be
inconsistent with the regional inventory compiled as part of EKAPCD’s AQMPs.
The proposed project involves construction of the new Murray Middle School campus and demolition of
several buildings at the existing campus. The project is not considered a regionally significant project that
would significantly affect regional vehicle miles traveled and warrant Intergovernmental Review by the
KCOG pursuant to the CEQA Guidelines (CEQA Guidelines § 15206). The project also would not have the
potential to substantially affect housing, employment, and population projections within the region, which
form the basis for the AQMP projections. Furthermore, the net increase in regional emissions for which the
MDAB is in nonattainment generated by the proposed project would be less than the EKAPCD’s emissions
thresholds (see Section 3.3(b), below). These thresholds are established to identify projects that have the
potential to generate a substantial amount of criteria air pollutants. Because the proposed project would not
exceed these thresholds, it would not be considered by the EKAPCD to be a substantial emitter of criteria air
pollutants. Therefore, the proposed project would not conflict with or obstruct implementation of
EKAPCD’s AQMP. Impacts would be less than significant and no mitigation measures are required.
b) Violate any air quality standard or contribute substantially to an existing or projected air quality
violation?
Less Than Significant Impact With Mitigation Incorporated. The following describes project-related
impacts from short-term construction activities and long-term operation of the proposed project.
Short-Term Air Quality Impacts
Construction activities would result in the generation of air pollutants. These emissions would primarily be 1)
exhaust emissions from off-road diesel-powered construction equipment; 2) dust generated by grading,
earthmoving, and other construction activities; 3) exhaust emissions from on-road vehicles and 4) off-gas
emissions of volatile organic compounds (VOCs) from application of asphalt, paints, and coatings.
Construction activities would occur on approximately 31.17 acres of the new 47-acre campus, and demolition
would occur on 2.51 acres of the existing 29.4-acre campus. Construction at the new campus would involve
site preparation; soil remediation; asphalt demolition; grading; utility trenching; construction of the classroom
buildings, administration building, multipurpose/kitchen building, gym/locker room, and music/art building;
installation of the proposed fields; asphalt paving; and architectural coating. Demolition at the existing
campus would take place after the completion of construction at the new campus and would involve several
buildings and the courtyard. Construction activities would start as early as fall 2015 and would take
approximately two years. Construction emissions were estimated with the California Emissions Estimator
Model (CalEEMod), version 2013.2.2, based on the project’s preliminary construction schedule, phasing, and
equipment list provided by the District. The construction schedule and equipment mix are based on
preliminary engineering and are subject to changes during final design and as dictated by field conditions.
Eastern Kern County is currently designated “moderate” nonattainment under California and National O3
AAQS and nonattainment under the California PM10 AAQS. EKAPCD Rule 402, Fugitive Dust, requires
fugitive dust control measures—such as improve road surface, control vehicular traffic speed, and apply dust
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 56 PlaceWorks
suppressants—to reduce the amount of suspended particulate matter emitted from fugitive dust sources
(EKAPCD 2011). By complying with EKAPCD Rule 402, not only would the regional and localized
concentration of PM10 and PM2.5 be reduced, the potential risk of exposing sensitive receptors and onsite
workers to valley fever would also be minimized. Criteria air pollutants from construction activities are
compared to the EKAPCD’s significance thresholds in Table 2, Maximum Daily Construction Emissions, and
Table 3, Annual Construction Emissions.
Table 2 Maximum Daily Construction Emissions
Source
Maximum Daily Emissions (lbs/day)1
VOC NOx SO2 PM10 Total2 PM2.5 Total2
Year 2015
Site Preparation/Soil Remediation + Soil Remediation Haul
14 139 <1 16 10
New School Asphalt Demolition + Asphalt Demo Debris Haul
3 31 <1 3 1
Fine Grading & Utility Trenching 1 8 <1 3 2
Year 2016
Fine Grading & Utility Trenching 1 7 <1 3 2
Asphalt Paving 1 8 <1 1 1
Building Construction 2 15 <1 1 1
Year 2017
Building Construction 2 13 <1 1 1
Building Construction & Architectural Coating 23 16 <1 1 1
Architectural Coating 20 2 <1 <1 <1
Finishing/Landscaping 1 3 <1 <1 <1
Existing School Demolition + Building Demo Debris Haul + Asphalt Demo Debris Haul
4 35 <1 5 2
Maximum Daily Emissions 23 139 <1 16 10
EKAPCD Threshold 137 137 N/A N/A N/A
Exceeds Threshold No Yes N/A N/A N/A
Source: CalEEMod Version 2013.2.2. Notes: lbs = pounds; N/A = not applicable; bold = exceeds threshold. 1 Construction phasing is based on the preliminary information and equipment list provided by the District. Where specific information regarding project-related
construction activities was not available, construction assumptions were based on CalEEMod defaults, which are based on construction surveys conducted by the South Coast Air Quality Management District of construction equipment and phasing for comparable projects.
2 PM10 and PM2.5 fugitive dust emissions assume application of EKAPCD Rule 402, which includes watering disturbed areas a minimum of two times per day, reducing speed limit to 15 miles per hour on unpaved surfaces, replacing ground cover quickly, and street sweeping.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 57
Table 3 Annual Construction Emissions
Source
Annual Emissions (tons/year)1
VOC NOx SO2 PM10 Total2 PM2.5 Total2
2015 <1 3 <1 <1 <1
2016 <1 1 <1 <1 <1
2017 1 1 <1 <1 <1
EKAPCD Threshold 25 TPY 25 TPY 27 TPY 15 TPY N/A
Exceeds Threshold No No No No N/A
Source: CalEEMod Version 2013.2.2. Notes: TPY = tons per year; N/A = not applicable. 1 Construction phasing is based on the preliminary information and equipment list provided by the District. Where specific information regarding project-related
construction activities was not available, construction assumptions were based on CalEEMod defaults, which are based on construction surveys conducted by the South Coast Air Quality Management District of construction equipment and phasing for comparable projects.
2 PM10 and PM2.5 fugitive dust emissions assume application of EKAPCD Rule 402, which includes watering disturbed areas a minimum of two times per day, reducing speed limit to 15 miles per hour on unpaved surfaces, replacing ground cover quickly, and street sweeping.
As shown in Table 3, criteria air pollutant emissions from construction activities would not exceed the
EKAPCD annual thresholds. Additionally, as shown in Table 2, VOC emissions from construction activities
would not exceed the EKAPCD daily VOC threshold. However, NOx emissions during phases that include
soil remediation hauls (rough grading soil haul activity) would exceed the EKAPCD daily NOx threshold.
Therefore, the worst-case, project-related construction activities would have the potential to expose sensitive
receptors to substantial pollutant concentrations without incorporation of mitigation measures.
Table 4, Maximum Daily Construction Emissions, Mitigated, shows the emissions that would be generated with
implementation of Mitigation Measure AQ-1. This measure requires using construction equipment with Tier
3 engines for site preparation and soil remediation activities. As shown in the table, NOx emissions would be
reduced to below the EKAPCD daily threshold. Therefore, with incorporation of mitigation, project-related
construction activities impacts would be less than significant.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 58 PlaceWorks
Table 4 Maximum Daily Construction Emissions, Mitigated
Source
Maximum Daily Emissions (lbs/day)1, 3
VOC NOx SO2 PM10 Total2 PM2.5 Total2
Year 2015
Site Preparation/Soil Remediation + Soil Remediation Haul
5 54 <1 12 7
New School Asphalt Demolition + Asphalt Demo Debris Haul
3 31 <1 3 1
Fine Grading & Utility Trenching 1 8 <1 3 2
Year 2016
Fine Grading & Utility Trenching 1 7 <1 3 2
Asphalt Paving 1 8 <1 1 1
Building Construction 2 15 <1 1 1
Year 2017
Building Construction 2 13 <1 1 1
Building Construction & Architectural Coating 23 16 <1 1 1
Architectural Coating 20 2 <1 <1 <1
Finishing/Landscaping 1 3 <1 <1 <1
Existing School Demolition + Building Demo Debris Haul + Asphalt Demo Debris Haul
4 35 <1 5 2
Maximum Daily Emissions 23 54 <1 12 7
EKAPCD Threshold 137 137 N/A N/A N/A
Exceeds Threshold No No N/A N/A N/A
Source: CalEEMod Version 2013.2.2. Notes: lbs = pounds; N/A = not applicable. 1 Construction phasing is based on the preliminary information and equipment list provided by the District. Where specific information regarding project-related
construction activities was not available, construction assumptions were based on CalEEMod defaults, which are based on construction surveys conducted by the South Coast Air Quality Management District of construction equipment and phasing for comparable projects.
2 PM10 and PM2.5 fugitive dust emissions assume application of EKAPCD Rule 402, which includes watering disturbed areas a minimum of two times per day, reducing speed limit to 15 miles per hour on unpaved surfaces, replacing ground cover quickly, and street sweeping.
3 Includes implementation of Mitigation Measure AQ-1, which requires using construction equipment with Tier 3 engines for site preparation and soil remediation activities.
Long-Term Operation-Related Air Quality Impact
Long-term air pollutant emissions by the project would be generated by area sources (e.g., landscape fuel use,
aerosols, and architectural coatings), energy use associated with the proposed buildings, and the project-
related vehicle trips. Criteria air pollutant emissions were modeled using CalEEMod. Criteria air pollutants are
compared to the EKAPCD’s significance thresholds in Table 5, Maximum Daily Operation Emissions, and in
Table 6, Annual Operation Emissions. As shown in Table 5 and Table 6, criteria air pollutant emissions from
operation activities would not exceed the EKAPCD daily and annual thresholds.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 59
Table 5 Maximum Daily Operation Emissions
Source
Maximum Daily Emissions (lbs/Day)
VOC NOx SO2 PM10 Total PM2.5 Total
Existing
Area 4 <1 <1 <1 <1
Energy <1 <1 <1 <1 <1
Mobile Sources 4 2 <1 3 1
Total Emissions 8 3 <1 3 1
Proposed Project
Area 3 <1 <1 <1 <1
Energy <1 <1 <1 <1 <1
Mobile Sources 6 3 <1 4 1
Total Emissions 8 3 <1 4 1
Net Change
Area -1 <1 <1 <1 <1
Energy -0.028 -0.257 -0.002 -0.020 -0.020
Mobile Sources 2 1 <1 1 <1
Total Emissions 1 1 <1 1 <1
EKAPCD Threshold 137 137 N/A N/A N/A
Exceeds Threshold No No N/A N/A N/A
Source: CalEEMod Version 2013.2.2. Notes: lbs = pounds; N/A = not applicable. Highest winter or summer emissions are reported. Totals may not equal 100 percent due to rounding.
Table 6 Annual Operation Emissions
Source
Annual Emissions (Tons/Year)
VOC NOx SO2 PM10 Total PM2.5 Total
Existing
Area 1 <1 <1 <1 <1
Energy <1 <1 <1 <1 <1
Mobile Sources <1 <1 <1 <1 <1
Total Emissions 1 <1 <1 <1 <1
Proposed Project
Area <1 <1 <1 <1 <1
Energy <1 <1 <1 <1 <1
Mobile Sources 1 <1 <1 1 <1
Total Emissions 1 <1 <1 1 <1
Net Change
Area -0.235 <1 <1 <1 <1
Energy -0.005 -0.047 <1 -0.004 -0.004
Mobile Sources <1 <1 <1 <1 <1
Total Emissions -0.026 <1 <1 <1 <1
EKAPCD Threshold 25 TPY 25 TPY 27 TPY 15 TPY N/A
Exceeds Threshold No No No No N/A
Source: CalEEMod Version 2013.2.2. Notes: TPY = tons per year; N/A = not applicable. Highest winter or summer emissions are reported. Totals may not equal 100 percent due to rounding.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 60 PlaceWorks
Mitigation Measure
AQ-1 The Sierra Sands Unified School District (District) shall specify in the construction bid that
the construction contractor(s) shall use equipment that meets the United States
Environmental Protection Agency’s (EPA) Certified Tier 3 off-road emissions standards for
off-road diesel-powered construction equipment greater than 50 horsepower. Any emissions
control device used by the contractor shall achieve emissions reductions that are no less than
what could be achieved by a Level 3 diesel emissions control strategy for a similarly sized
engine, as defined by California Air Resources Board regulations. Prior to construction, the
project engineer shall ensure that all construction management and grading plans clearly
show compliance with USEPA Tier 3 or higher emissions standards for construction
equipment over 50 horsepower. During construction, the construction contractor shall
maintain a list of all operating equipment in use on the project site for verification by the
Building and Safety Division Official or designee. The construction equipment list shall state
the makes, models, and numbers of construction equipment onsite. Equipment shall be
properly serviced and maintained in accordance with the manufacturer’s recommendations.
Construction contractors shall also ensure that all nonessential idling of construction
equipment is restricted to five minutes or less in compliance with California Air Resources
Board’s Rule 2449.
c) Result in a cumulatively considerable net increase of any criteria pollutant for which the project
region is nonattainment under an applicable federal or state ambient air quality standard
(including releasing emissions which exceed quantitative thresholds for ozone precursors)?
Less Than Significant Impact. The eastern Kern County portion of the MDAB is currently designated a
“moderate” nonattainment area under California and National O3 AAQS and nonattainment under the
California PM10 AAQS (CARB 2014a). Any project that does not exceed or can be mitigated to less than the
EKAPCD significance levels, used as the threshold for determining major projects, does not add significantly
to a cumulative impact (EKAPCD 1996). With mitigation, construction emissions would not exceed
EKAPCD’s significant thresholds. Operational emissions would also not exceed EKAPCD’s significance
thresholds. Consequently, the proposed project would not result in a cumulatively considerable contribution
to ozone or particulate matter concentrations in the MDAB. Project emissions would have a less than
significant impact on cumulative emissions, and no mitigation measures are required.
d) Expose sensitive receptors to substantial pollutant concentrations?
Less Than Significant Impact. The proposed project could expose sensitive receptors to elevated pollutant
concentrations if it would cause or contribute significantly to elevated pollutant concentration levels.
Localized concentrations refer to the amount of pollutant in a volume of air (ppm or µg/m3) and can be
correlated to potential health effects to sensitive populations. Emissions that do not exceed the daily or
annual EKAPCD emissions thresholds are considered to result in less than significant localized impacts. As
identified above in Section 3.3(b), with mitigation, the project would not result in regional emissions in excess
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 61
of the EKAPCD’s significance threshold values. Therefore, localized air quality impacts from the project
would be less than significant, and no mitigation measures are required.
Carbon Monoxide Hotspots
Areas of vehicle congestion have the potential to create pockets of CO called hotspots. These pockets have
the potential to exceed the state one-hour standard of 20 ppm or the eight-hour standard of 9 ppm. Under
existing and future vehicle emission rates, a project would have to increase traffic volumes at a single
intersection by more than 44,000 vehicles per hour—or 24,000 vehicles per hour where vertical and/or
horizontal air does not mix—in order to generate a significant CO impact (BAAQMD 2011). The proposed
project would generate 766 average daily vehicle trips during a weekday, 267 trips during the morning peak
hour, and 89 trips during the evening peak hour (see Section 3.16, Transportation/Traffic), which is significantly
less than the volumes cited above. In addition, the potential for CO hotspots to be generated in the MDAB is
extremely low because of the improvements in vehicle emission rates and control efficiencies. The MDAB is
designated in attainment for CO under both the California AAQS and National AAQS. Typical projects
would not expose sensitive receptors to substantial pollutant concentrations, and analysis of CO hotspots is
not warranted. Therefore, impacts are less than significant, and no mitigation measures are required.
Health Risk Assessment
Recent air pollution studies have shown an association between proximity to major air pollution sources and a
variety of health effects, which are attributed to a high concentration of air pollutants. Guidance from the
California Air Resources Board (CARB) and the California Air Pollutant Control Officer’s Association
recommends the evaluation of various emission sources within 1,000 feet of sensitive land uses (i.e.,
residences, schools, daycare centers, and hospitals). An HRA was prepared for the construction of the New
Murray Middle School, as required by Public Resources Code Section 21151.8 and Education Code Section
17213 (see Appendix C-2).
Properties within a quarter-mile radius (1,320 feet) were surveyed to identify facilities that have the potential
to generate hazardous and acutely hazardous air emissions. In addition, the EKAPCD and the Kern County
Agricultural Commissioner’s Office were contacted to assist in the identification of potential emitters. The
EKAPCD identified no permitted stationary sources, mobile sources, or nonpermitted sources within the
quarter-mile radius of the new school site. The Kern County Agricultural Commissioner’s Office did not
identify any agricultural fields or pesticide usage within a quarter-mile radius of the proposed school site.
Additionally, a data search using the California Pesticide Information Portal (CalPIP) reported no pesticide
use in 2010 (most recent year available). Based on the findings of the HRA, no stationary or mobile sources
within a quarter-mile radius of the school site would result in hazardous air emissions that could impact
students and staff at the new Murray Middle School. Therefore, health risk impacts are considered less than
significant, and no mitigation measures are required.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 62 PlaceWorks
e) Create objectionable odors affecting a substantial number of people?
Less Than Significant Impact. The proposed project would not result in objectionable odors. The
threshold for odor is if a project creates an odor nuisance pursuant to EKAPCD Rule 419, Nuisance, which
states:
A person shall not discharge from any source whatsoever such quantities of air
contaminants or other material which cause injury, detriment, nuisance, or annoyance to any
considerable number of persons or to the public or which endanger the comfort, repose,
health or safety of any such persons or the public or which cause or have a natural tendency
to cause injury or damage to business or property.
The type of facilities that are considered to have objectionable odors include wastewater treatments plants,
compost facilities, landfills, solid waste transfer stations, fiberglass manufacturing facilities, paint/coating
operations (e.g., auto body shops), dairy farms, petroleum refineries, asphalt batch plants, chemical
manufacturing, and food manufacturing facilities. The uses proposed by the project do not fall within the
aforementioned land uses. Emissions from construction equipment, such as diesel exhaust and VOCs from
architectural coatings and paving activities, may generate odors. However, these odors would be low in
concentration, temporary, and are not expected to affect a substantial number of people. No significant
impacts would occur, and no mitigation measures are required.
3.4 BIOLOGICAL RESOURCES
The information and analysis in this section are based in part on the Biological Resources Technical Report
for the Sierra Sands Unified School District, Murray Middle School, Alden Environmental, Inc., August 6,
2013. A complete copy of this report is included as Appendix D to this Initial Study.
a) Have a substantial adverse effect, either directly or through habitat modifications, on any species
identified as a candidate, sensitive, or special status species in local or regional plans, policies, or
regulations, or by the California Department of Fish and Game or U.S. Fish and Wildlife Service?
Less Than Significant Impact With Mitigation Incorporated. No sensitive animal or plant species were
observed on the proposed new school site during a general biological survey of the site on March 27, 2013,
and a focused rare plant survey on April 25, 2013. No sensitive vegetation communities were identified onsite
during either of these surveys. The site has been disturbed by past residential development. One vegetation
community, disturbed white bursage scrub, and two other land cover types (disturbed habitats and developed
areas) were identified onsite. Vegetation in the disturbed white bursage scrub is sparse, showing evidence of
past residential development. Plants other than the dominant white bursage, Ambrosia dumosa, are scattered
creosote bush (Larrea tridentata) and brittlebush (Encelia farinosa). Disturbed habitat consists of dirt roads and
bare, unvegetated, previously developed areas. Developed areas include paved roads and a defunct power
transmission facility. No sensitive plant or animal species are expected to occur onsite. The new school would
disturb an approximately 47-acre site, but the project would not disturb habitat where sensitive species are
expected.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 63
Burrowing Owl
One burrowing owl, Athene cunicularia, was observed in the southwest corner of the site during field work for
the Categorical Exclusion under NEPA in November–December 2011. Burrowing owl is listed as a California
Species of Special Concern by the California Department of Fish and Wildlife (CDFW),1 but is not listed
under the federal or state endangered species acts. Subsequent field work found no evidence of owl
occupation onsite.
Nesting burrowing owls and other nesting migratory birds are protected under the federal Migratory Bird
Treaty Act (MBTA). If site clearing occurs outside the avian breeding season (February 1 through September
1), then no impacts to MBTA-protected species would occur, and no mitigation would be required. However,
this impact would be potentially significant if vegetation clearance was conducted during the bird breeding
season, February 1 to September 1. Implementation of Mitigation Measure BIO-1 would reduce this
potentially significant impact to less than significant.
Desert Tortoise
The NEPA Categorical Exclusion concluded that the habitat onsite could support the desert tortoise
(Gopherus agassizii), and consequently, it has the potential to occur onsite. Desert tortoise is listed as threatened
under both the federal and state endangered species acts. Tortoises were not identified onsite during field
work for the Categorical Exclusion or the biological technical report, which does not anticipate them onsite.
Nonetheless, project development could impact desert tortoise, and this impact is potentially significant.
Implementation of Mitigation Measure BIO-2 would reduce this impact to less than significant.
Mitigation Measures
BIO-1 If site clearing occurs during the bird breeding season, February 1 to September 1, a
preconstruction survey shall be conducted three days prior to clearing or grading activities to
determine if breeding or nesting avian species are in the impact area. If no nesting birds (or
birds displaying breeding or nesting behavior) are present, then clearing may proceed. If
nesting birds are present, a noconstruction buffer will be placed around the active nest(s).
The size of the buffer will depend on the species present and will be determined in
conjunction with the Naval Air Weapons Station, China Lake Environmental Management
Division. Construction in these areas shall not be resumed until the biologist has confirmed
that the birds are no longer nesting.
BIO-2 Prior to construction, a desert tortoise protection education program shall be presented to
all construction personnel to ensure that they are aware of the significance to the project
should this species occur onsite during construction. The education program will include:
The legal and sensitive status of the tortoise.
1 California Species of Special Concern are vertebrate animal species native to California that are listed under the federal endangered species act but not the state endangered species act; or could become qualified for listing under the state endangered species act due to small populations or to serious, noncyclical declines in population or range (CDFW 2013).
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 64 PlaceWorks
A brief discussion of tortoise life history and ecology.
Mitigation measures designed to reduce adverse effects to tortoises.
Protocols to follow, if a tortoise is encountered, including appropriate contact point(s).
A final site clearance survey shall be conducted within 7 days of the start of construction to
confirm that no tortoises are onsite. As identified in the NEPA Categorical Exclusion, the
clearance survey will be conducted by a USFWS-approved biologist in accordance with the
current US Fish and Wildlife Service desert tortoise protocol. If a tortoise is found in the
project area, activities should be modified to avoid injuring or harming it. If activities cannot
be modified, then construction will be postponed until a desert tortoise relocation procedure
can be implemented, in conjunction with the Navy’s Environmental Management Division
and the USFWS.
b) Have a substantial adverse effect on any riparian habitat or other sensitive natural community
identified in local or regional plans, policies, regulations, or by the California Department of Fish
and Game or U.S. Fish and Wildlife Service?
No Impact. Sensitive natural communities are communities that are considered rare in the region by
regulatory agencies; known to provide habitat for sensitive animal or plant species; or known to be important
wildlife corridors. Riparian habitats occur along the banks of rivers and streams. No sensitive natural
community or riparian habitat was observed onsite, and no impact would occur. No mitigation measures are
required.
c) Have a substantial adverse effect on federally protected wetlands as defined by Section 404 of the
Clean Water Act (including, but not limited to, marsh, vernal pool, coastal, etc.) through direct
removal, filling, hydrological interruption, or other means?
No Impact. Wetlands are defined under the federal Clean Water Act as land that is flooded or saturated by
surface water or groundwater at a frequency and duration sufficient to support and that normally does
support, a prevalence of vegetation adapted to life in saturated soils. Wetlands include areas such as swamps,
marshes, and bogs. No potential jurisdictional areas were identified onsite, including wetlands jurisdictional to
the US Army Corps of Engineers pursuant to the Clean Water Act. No impact would occur, and no
mitigation measures are needed.
d) Interfere substantially with the movement of any native resident or migratory fish or wildlife
species or with established native resident or migratory wildlife corridors, or impede the use of
native wildlife nursery sites?
Less Than Significant Impact With Mitigation Incorporated. A majority of the site is surrounded by
developed land uses. There are no regional or local wildlife corridors onsite. However, as stated above, project
implementation would remove vegetation that could support nesting migratory birds protected under the
federal Migratory Bird Treaty Act. Implementation of Mitigation Measure BIO-1 would reduce this impact to
less than significant. No additional mitigation measures are required.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 65
Mitigation Measure
e) Conflict with any local policies or ordinances protecting biological resources, such as a tree
preservation policy or ordinance?
No Impact. The project site is on federal land, and no local policies are applicable to the site. The Biological
Resources Technical Report prepared for the project site was conducted in compliance with state and federal
requirements, and as appropriate, applicable regulatory requirements have been applied to the project as a
part of the project description or as mitigation (i.e., Mitigation Measures BIO-1 and BIO-2). Therefore, no
impact would occur, and no mitigation measures are required.
f) Conflict with the provisions of an adopted Habitat Conservation Plan, Natural Community
Conservation Plan, or other approved local, regional, or state habitat conservation plan?
Less than Significant Impact with Mitigation Incorporated. The project sites are within the plan area of
one regional conservation plan that has been adopted by the US Bureau of Land Management (BLM), and a
second regional conservation plan is under preparation.
West Mojave Plan
The West Mojave Plan (WMP), adopted by BLM in 2006, covers 9.3 million acres of the western portion of
the Mojave Desert in California, including parts of Inyo, Los Angeles, Kern, San Bernardino, and Riverside
counties. The WMP is an interagency habitat conservation plan (HCP) that was prepared by the BLM in
collaboration with federal and state agencies, and NAWS China Lake is a participating agency.
The purpose of the WMP is to conserve and protect the desert tortoise (Gopherus agassizii) and nearly 100
other sensitive plant and wildlife species, as well as the habitats on which these species depend, and provide
developers of public and private projects with a streamlined program for compliance with FESA and CESA
by reducing delays and expenses, eliminating uncertainty, and applying the costs of compensation and
mitigation equitably to all agencies and parties. The WMP allows incidental take of covered species and is
consistent with the resource management plans adopted by each of the region’s five military bases as well as
with the Desert Tortoise Recovery Plan. The term of the WMP is 30 years.
In 2009 the US District Court for Northern California issued a summary judgment requiring a lower court to
take further action on the off-highway vehicle route designations in the WMP. New route designations must
be made by September 2015 (Alden Environmental 2013; BLM 2015).
Land use and resource conservation policies at the new and existing school sites are established by the
commanding officer of China Lake. After implementation of Mitigation Measures BIO-1 and BIO-2, project
development would not have substantial impacts on sensitive resources protected under the WMP or
otherwise conflict with the WMP.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 66 PlaceWorks
Draft Desert Renewable Energy Conservation Plan
The draft Desert Renewable Energy Conservation Plan (DRECP) covers 22.5 million acres of federal and
nonfederal lands in the California deserts and adjacent lands in Imperial, Inyo, Kern, Los Angeles, Riverside,
San Bernardino, and San Diego counties. It is a collaboration between state (e.g., California Energy
Commission, CDFW) and federal (e.g., BLM, USFWS) agencies, with input from local governments,
environmental organizations, industry, and other interested parties to provide effective protection,
conservation, and management of desert ecosystems while allowing for appropriate development and timely
permitting of renewable energy projects. Portions of China Lake, including the project sites, are in the
DRECP area.
The draft DRECP and associated environmental impact report/environmental impact statement (EIR/EIS)
were recently circulated for public review (CEC 2015). If approved, the DRECP would result in an efficient
and effective biological mitigation and conservation program, providing renewable energy project developers
with binding, long-term endangered species permit assurances and facilitating the review and approval of
renewable energy and associated infrastructure, such as electric transmission lines necessary for renewable
energy development within the Mojave and Colorado desert regions of California (Alden Environmental
2013).
The new school site is leased by the Sierra Sands Unified School District as a prospective school site. No
renewable energy projects are proposed onsite, and the project would not conflict with the DRECP. No
impact would occur.
3.5 CULTURAL RESOURCES
The information and analysis in this section is based in part on the following technical studies:
Murray Middle School Historic Resource Assessment, Chattel Architecture, Planning & Preservation, April 11,
2012. A complete copy of this report is included as Appendix E.1 to this Initial Study.
Record of Categorical Exclusion for the Lease of 32 Acres to Sierra Sands Unified School District for Construction of a
New Middle School, Department of the Navy: Commanding Officer, Naval Air Weapons Station, China
Lake, August 6, 2012. A complete copy of this report is included as Appendix A.1.
Record of Categorical Exclusion for the Demolition of Murray Middle School, Department of the Navy:
Commanding Officer, Naval Air Weapons Station, China Lake, September 12, 2012. A complete copy of
this report is included as Appendix A.2.
Cultural Resources Records Search, South San Joaquin Valley Information Center, December 20, 2013. A
complete copy of this report is included as Appendix E.2.
Paleontological Records Search for the Proposed Burroughs High School and Murray Middle School Project, in the City of
Ridgecrest, Kern County, Natural History Museum of Los Angeles County, February 26, 2014. A complete
copy of this report is included as Appendix E.3.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 67
a) Cause a substantial adverse change in the significance of a historical resource as defined in
§ 15064.5?
Less Than Significant Impact. Section 15064.5 defines historic resources as resources listed or determined
to be eligible for listing by the State Historical Resources Commission, a local register of historical resources,
or the lead agency. Generally a resource is considered “historically significant” if it meets one of the
following criteria:
i) Is associated with events that have made a significant contribution to the broad patterns of
California’s history and cultural heritage;
ii) Is associated with the lives of persons important in our past;
iii) Embodies the distinctive characteristics of a type, period, region or method of construction,
or represents the work of an important creative individual, or possesses high artistic values;
iv) Has yielded, or may be likely to yield, information important in prehistory or history.
Existing School
Description
Buildings of the existing campus are one story and designed in modest International style, characterized by
flat roofs with wide overhanging eaves, no ornamentation, and large banks of wood sash windows that span
almost the full length of northern elevations. Four buildings were built in 1945: the administration building
and three classroom buildings. Later additions to the campus—the auditorium, music, and gymnasium
buildings—are clearly distinguished from 1945 campus buildings and generally have low-sloped gable roofs
and clerestory windows. The administration building, three classroom buildings, auditorium, and music
building are arranged around a courtyard at the center of campus.
Timeline
The existing Murray Middle School campus, originally Burroughs High School, was built in 1945. A high
school was built off-station in Ridgecrest in 1959 so that off-station residents would not need a pass. That
off-base school is now Mesquite Continuation High School. Burroughs High School is the only traditional
comprehensive high school operated by the District. Burroughs High School is at 500 East French Avenue
opposite Knox Road east of the site for the proposed new middle school and is outside the current China
Lake security perimeter. Murray Middle School has operated at its current site since 1960.
Assessment
The existing Murray Middle School campus was part of an effort by the Navy to establish community
facilities on and near the station during 1944 to 1946 so that scientists and their families could move to
Ridgecrest for work at China Lake, known at that time as Naval Ordinance Test Station Inyokern. Murray
Middle School therefore qualifies for listing on the California Register of Historic Resources (CRHR) under
Criterion 1.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 68 PlaceWorks
The existing campus is not associated with the lives of persons important in our past, and thus does not
qualify for CRHR listing under Criterion 2. Burroughs High School is not directly associated with Captain
Sherman Burroughs, the station’s first commanding officer.
The original campus was designed by prominent Los Angeles architect Henry Gogerty in an International
Style and is significant under Criterion 3. The school campus exemplifies elements of the style: emphasis on
horizontality, lack of ornamentation, interplay between wall and roof planes, and relationship between
interior and exterior spaces.
Murray Middle School does not appear likely to yield information important in prehistory or history and
therefore does not meet Criterion 4.
Once a resource has been determined to satisfy at least one National Register criteria, it must be assessed for
“integrity.” Integrity refers to the ability of a property to convey its significance, and the degree to which the
property retains the identity, including physical and visual attributes, for which it is significant under the four
basic criteria. The National Register recognizes seven aspects or qualities of integrity: location, design, setting,
materials, workmanship, feeling, and association. To retain its historic integrity, a property must possess
several, and usually most, of these aspects.
The integrity of design, materials, and workmanship of the current structures have been greatly
compromised by the replacement of banks of windows on east elevations with blank wall surfaces. These
windows were a character-defining feature of the International style and an important design element of
campus buildings. In addition, the existing school appears to have lost its integrity of setting through
construction of several additions to the administration building, construction of the music building between
two classroom buildings, and loss of landscaping. Additions to the administration building had a substantial
impact on the campus entrance, closing off the northern entrance to the central courtyard and diminishing
the prominence of the northern entrance to the administration building. Furthermore, construction of the
music building interrupted the relationship of Classroom buildings 2 and 3 with each other and with the
central courtyard. Integrity of setting was further compromised through the loss of landscaping in the central
courtyard. Historical photographs and aerials show the courtyard with a lawn and multiple trees. The
courtyard is now only soil, with one tree planted in a concrete planter in the center of each quadrant. Without
the housing immediately south of the school, Murray Middle School loses part of its setting as a school in the
center of residential area.
The existing Murray Middle School campus has potential significance under criteria 1 and 3, but lacks
sufficient integrity for eligibility. Since it is not eligible for listing in the California Register, it is not a historical
resource under CEQA. Therefore, demolition of the existing Murray Middle School campus would not
damage a historical resource.
New Campus Site
The proposed new school site is vacant, and there are no historic buildings onsite. Several roadways in poor
condition remain in the northern half of the site from residential development built between 1953 and 1973
and demolished between 1995 and 2004, as shown on historical topographic maps and aerial photographs
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 69
(USGS 1953; USGS 1973; Google Earth 2015). No cultural artifacts were identified in a foot survey of the
site conducted by archaeologists in late 2011 (DOD 2012). No cultural resources within the new school site
were identified in a cultural resources records search by the South San Joaquin Valley Information Center at
California State University Bakersfield (SSJVIC 2013). Development of the new campus site would not
substantially change the significance of a historical resource.
Other Nearby Historic Resources
Seven historic resources in the China Lake area are eligible listing in the National Register of Historic Places:
Administration Building, Dispensary, Michelson Lab, Theater, Senior Officer Quarters, Hangar 1, and
Lauritsen Laser & Optical Lab. None of these resources were identified as located adjacent to the existing
school or the proposed new campus site. Therefore, demolition of the existing campus and development of
the new facility site would not substantially change the significance of nearby historical resources.
Conclusions
Project implementation would not have a direct or indirect impact on historic resources. Impacts would be
less than significant, and no mitigation is needed.
b) Cause a substantial adverse change in the significance of an archaeological resource pursuant to
§ 15064.5?
Less Than Significant Impact With Mitigation Incorporated. No cultural resources were identified in a
foot survey of the site by qualified archaeologists. Two small obsidian stone scatters, both ineligible for
CRHR listing, were identified within one mile of the new school site in previous cultural resources studies of
nearby sites. However, there are abundant Native American cultural resources in China Lake—for instance,
the Coso Rock Art District, a National Historic Landmark, and Coso Hot Springs, listed on the National
Register of Historic Places. Both areas are in the northern part of the North Range of China Lake. One
prehistoric lithic scatter was identified offsite and within 0.5 mile of the proposed new campus site in a
cultural records search by the Southern San Joaquin Valley Information Center; the listing/eligibility status of
this site was not indicated (SSJVIC 2013). While a large area of the proposed school site is within an area
previously developed with residential uses, buried archaeological resources may still exist, especially in areas
that were not previously developed, and project grading and construction activities could damage such
resources. With the implementation of CUL-1, this potentially significant impact would be reduced to less
than significant.
Demolition of the existing campus and removal of the demolition debris would disturb soil that was
previously disturbed during construction of the school. No impact to buried archaeological resources would
result, and no mitigation measures would be required for demolition activities at the existing campus.
Mitigation Measure
CUL-1 The District shall retain a qualified archaeologist to periodically monitor all ground-
disturbing activities. The qualified archaeologist shall meet the Secretary of the Interior’s
Professional Qualifications Standards (48 Federal Register 44738-39). The archaeologist must
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 70 PlaceWorks
have knowledge of both prehistoric and historical archaeology. The methods of
archaeological monitoring, including timing, location, types of artifacts anticipated, and
procedures for additional analysis, if necessary, shall be described in an archaeological
monitoring plan. The extent and duration of the monitoring program will be dependent on
the grading plans and the level of sensitivity assessed. The archaeologist shall determine the
required duration and extent of monitoring. The construction manager shall adhere to the
stipulations of the archaeological monitoring plan. The archaeologist shall have the authority
to halt any project-related activities adversely impacting potentially significant resources. If
archaeological resources are uncovered, they must be recovered and curated with the
facilities acceptable to the District and DOD. Suspension of ground disturbances in the
vicinity of the discoveries shall not be lifted until the archaeological monitor has evaluated
discoveries to assess whether they are classified as historical resources or unique
archaeological sites, pursuant to CEQA and federal requirements.
c) Directly or indirectly destroy a unique paleontological resource or site or unique geologic
feature?
Less Than Significant Impact With Mitigation Incorporated. The proposed new school site is on the
floor of the Indian Wells Valley and has an east slope of about 1 percent; there are no known unique
geological features onsite. While a large area of the proposed school site was previously developed with
residential uses, the possibility exists that fossils are buried in areas not previously developed. With the
implementation of CUL-2, the potentially significant impact on paleontological resources would be reduced
to less than significant.
Demolition of the existing campus and removal of the demolition debris would disturb soil that was
previously disturbed during construction of the school. No impact to buried paleontological resources would
result, and no mitigation measures would be required for demolition activities at the existing campus.
Mitigation Measure
CUL-2 The District shall retain a qualified paleontologist to periodically monitor ground-disturbing
activities. The paleontologist shall determine the minimum depth of excavations requiring
monitoring. The paleontologist shall have the authority to halt any project-related activities.
If paleontological resources are uncovered, they must be recovered, analyzed in accordance
with DOD and CEQA guidelines, and curated with facilities acceptable to the District and
DOD.
d) Disturb any human remains, including those interred outside of formal cemeteries?
Less Than Significant Impact. Considering the extensive cultural resources present within the project area,
it is possible that human remains would be uncovered during construction activities. California Health and
Safety Code Section 7050.5 requires that if human remains are discovered, disturbance of the site shall halt
and remain halted until the coroner has conducted an investigation into the circumstances, manner, and cause
of any death, and the recommendations concerning the treatment and disposition of the human remains
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 71
have been made to the person responsible for the excavation, or to his or her authorized representative. If the
coroner determines that the remains are not subject to his or her authority and if the coroner has reason to
believe the human remains to be those of a Native American, he or she shall contact, by telephone within 24
hours, the Native American Heritage Commission. The project would comply with existing law, and potential
impacts to human remains would be less than significant. No mitigation is required.
3.6 GEOLOGY AND SOILS
The information and analysis in this section are based in part on the following technical studies:
Geotechnical Engineering Investigation and Geologic/Seismic Hazards Evaluation, Proposed Murray Middle School,
Ridgecrest, California, BSK Associates, November 9, 2012. A complete copy of this report is included as
Appendix F.1 of this Initial Study.
Fault Rupture Hazard Investigation Report, Proposed Murray Middle School, Ridgecrest, California, BSK Associates,
October 17, 2012. A complete copy of this report is included as Appendix F.2.
Amendment to Geotechnical Engineering Investigation and Geologic/Seismic Hazards Evaluation [Rigid Concrete
Pavement Design], Proposed Murray Middle School, Ridgecrest, California, BSK Associates, December 12, 2013. A
complete copy of this report is included as Appendix F.3.
Update Geotechnical Engineering Investigation, Proposed Murray Middle School, Ridgecrest, California, BSK
Associates, February 4, 2015. A complete copy of this report is included as Appendix F.4.
a) Expose people or structures to potential substantial adverse effects, including the risk of loss,
injury, or death involving:
i) Rupture of a known earthquake fault, as delineated on the most recent Alquist-Priolo
Earthquake Fault Zoning map, issued by the State Geologist for the area or based on other
substantial evidence of a known fault? Refer to Division of Mines and Geology Special
Publication 42.
Less Than Significant Impact. Multiple splays or traces of the Little Lake fault zone, oriented in
various directions, are within several miles of the new school site (see Figure 14, Geologic Map). Most of
the splays are classified as active.2 An Alquist-Priolo Earthquake Fault Zone is centered on one splay of
the Little Lake Fault Zone about 1,800 feet west of the new school site (see Figure 15, Area Fault Map).
An active fault splay was identified under the easternmost part of the Burroughs High School campus—
that is, the football/soccer stadium and a practice field (see Figure 15)—by a fault study investigation in
2008. Historically, the Little Lake Fault has produced periodic earthquake swarms with magnitudes
generally less than 5.6 (see Figure 16, Earthquake Location Map). The latest swarm occurred in 1995 and
2 The referenced splays are designated post-glacial on fault maps in the Fault Rupture Hazard Investigation. Active faults are those showing evidence of surface displacement within approximately the last 11,500 years, that is, the time since the last major glacial epoch, or “ice age”.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 72 PlaceWorks
was located 9 miles northeast of the new school site. The magnitude of an earthquake is a measure of
the energy released by the earthquake. Each one-point increase in magnitude represents a tenfold increase
in ground motion amplitude and a 32-fold increase in energy. That is, a magnitude 7 earthquake produces
100 times (10 x 10) the ground motion amplitude of a magnitude 5 earthquake.
BSK Associates completed a Fault Rupture Hazard Investigation for the new school site in October
2012; the investigation included a geologic literature review; subsurface exploration via two trenches; and
preparation of the investigation report.
A fault zone was identified passing through the west part of the proposed new school site oriented
north-northeast to south-southwest (that is, north 22 degrees east). A thick open fracture—about three
feet below ground surface—suggests recent movement on the fault, consistent with an active fault. One
exploratory trench extended east-west across nearly the entire new school site; the second, much shorter
and in the western part of the site, was excavated to determine the direction of the fault identified in the
first trench. The fault hazard investigation report recommended that structures for human occupancy be
set back at least 50 feet from the fault zone. No other fault zones were identified onsite in the fault
rupture hazard investigation.
Project development of the new school would comply with recommendations in the Fault Hazard
Investigation Report, and the proposed project would not expose people or structures to substantial
hazards from surface rupture of a known active fault. Impacts would be less than significant. No
mitigation is required.
ii) Strong seismic ground shaking?
Less Than Significant Impact. A fault zone, which appears to be active, was identified onsite (see
Section 3.6.a.i above). Numerous other splays of the Little Lake Fault Zone—many of them classified as
active—have been mapped in the Indian Wells Valley. Other known active faults in the region include the
Garlock Fault about 12 miles south of the new school site, and the Tank Canyon Fault about 23 miles to
the east (see Figure 5 in the Fault Rupture Hazard Investigation, Appendix F.2 of this Initial Study). Periodic
earthquake swarms on the Little Lake Fault have been recorded, with magnitudes generally less than 5.6.
Strong ground shaking is very likely to occur onsite during the design lifetime of the proposed new
school. Seismic design criteria for the proposed structures are included in the Updated Geotechnical
Engineering Investigation (see Appendix F.4). Compliance with recommendations of the Geotechnical
Engineering Investigation report is required. Therefore, project development would not expose people or
structures to substantial hazards from strong ground shaking, and impacts would be less than significant.
No mitigation is necessary.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 73
Figure 14 Geologic Map
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 74 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 75
Figure 15 Area Fault Map
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 76 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 77
Figure 16 Earthquake Location Map
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 78 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 79
iii) Seismic-related ground failure, including liquefaction?
Less Than Significant Impact. Liquefaction refers to loose, saturated sand or silt deposits that behave
as a liquid and lose their load-supporting capability when strongly shaken. Loose granular soils and silts
that are saturated by relatively shallow groundwater are susceptible to liquefaction. Groundwater under
the new school site is about 105 feet below ground surface (bgs) (Mielke 2015). Thus, liquefaction
potential onsite is considered very low. In addition, the site is not mapped in a zone of required
investigation for liquefaction by the California Geological Survey. Project development would not subject
people or structures to substantial hazards due to liquefaction, and impacts would be less than significant.
No mitigation is required.
iv) Landslides?
No Impact. Development of the new school would not subject people or structures to landslide
hazards, as the site and surroundings have an east slope of about 1 percent. No impact would occur, and
no mitigation is needed.
b) Result in substantial soil erosion or the loss of topsoil?
Less Than Significant Impact. Since the area of the proposed new school is greater than one acre, the
construction contractor would be required to comply with National Pollutant Discharge Elimination System
(NPDES) General Construction Permit requirements and would be required to prepare and comply with the
requirement of a Stormwater Pollution Prevention Program (SWPPP). The requirement of a SWPPP has
been incorporated into the project description as a best management practice (BMP), with two major
objectives: to help identify the sources of sediment and other pollutants that could affect the quality of
stormwater discharges, and to describe and ensure implementation of measures to reduce or eliminate
sediment and other pollutants in stormwater as well as non-stormwater discharges. Furthermore, the SWPPP
BMPs would: (1) prevent pollutants from contacting stormwater during all phases of construction; (2)
provide a site description; (3) implement proposed postconstruction controls; and (4) provide for non-
stormwater management. Implementation of these mandatory control measures would ensure that the
proposed project would not violate water quality standards or waste discharge requirements during
construction. Therefore, with adherence to the abovementioned regulations, including adherence to the
requirements of the NPDES General Construction Permit and a SWPPP, implementation of the proposed
project would not violate water quality standards and waste discharge requirements.
Demolition of the existing campus would comply with the above-referenced regulatory requirements. The
proposed project would have a less than significant impact, and no mitigation is required.
c) Be located on a geologic unit or soil that is unstable, or that would become unstable as a result
of the project, and potentially result in on- or off-site landslide, lateral spreading, subsidence,
liquefaction, or collapse?
Less Than Significant Impact. Development of the new school would not cause hazards from liquefaction
or landslides, as substantiated above in Sections 3.6.a.iii and 3.6.a.iv, respectively. Lateral spreading is the
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 80 PlaceWorks
downslope movement of surface sediment due to liquefaction in a subsurface layer. Hazards arising from
lateral spreading would be very low due to the very low liquefaction potential onsite.
Ground Subsidence
The major causes of ground subsidence are withdrawal of groundwater and of oil. The new school site is not
in an area susceptible to subsidence due to petroleum or groundwater withdrawal.
Collapsible Soils
Hydrocompaction is the consolidation of loose dry soils from the infiltration of water. Materials of unusually
low density deposited in areas of low rainfall undergo significant compaction when they become thoroughly
wetted. Consolidation tests on samples of subsurface site soils show that soils at the new school site do not
appear to have a potential for hydrocompaction. Impacts would be less than significant, and no mitigation is
necessary.
d) Be located on expansive soil, as defined in Table 18-1-B of the Uniform Building Code (1994),
creating substantial risks to life or property?
Less Than Significant Impact. The soil in the upper 50 feet across the new school site generally consists
of medium to very dense sand and silty sand that may be considered to have a low expansion potential.
However, the upper two feet of sandy clay is considered moderately expansive; shallow foundations
susceptible to damage from expansive soils will require excavation of the moderately expansive soil. The
geotechnical investigation report recommends excavation of existing soils to five feet below existing grade, or
two feet below the bottom of foundation footings, whichever is greater; and provides recommendations for a
foundation design to minimize hazards from expansive soils. Development of the new school would comply
with recommendations of the geotechnical investigation report, and thus would not cause substantial hazards
arising from expansive soils. Impacts would be less than significant, and no mitigation is required.
e) Have soils incapable of adequately supporting the use of septic tanks or alternative waste water
disposal systems where sewers are not available for the disposal of waste water?
No Impact. Project development would include the installation of sewer pipes and laterals connecting to an
existing sewer near Burroughs High School. The project would not require the use of septic tanks or other
alternative wastewater disposal systems, and no impact would occur.
3.7 GREENHOUSE GAS EMISSIONS
Scientists have concluded that human activities are contributing to global climate change by adding large
amounts of heat-trapping gases, known as greenhouse gases (GHGs), into the atmosphere. The primary
source of these GHG is fossil fuel use. The Intergovernmental Panel on Climate Change (IPCC) has
identified four major GHG—water vapor, carbon dioxide (CO2), methane (CH4), and ozone (O3)—that are
the likely cause of an increase in global average temperatures observed within the 20th and 21st centuries.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 81
Other GHG identified by the IPCC that contribute to global warming to a lesser extent include nitrous oxide
(N2O), sulfur hexafluoride (SF6), hydro fluorocarbons, per fluorocarbons, and chlorofluorocarbons.3, 4
This section analyzes the project’s contribution to global climate change impacts in California through an
analysis of project-related GHG emissions. Information on manufacture of cement, steel, and other “life-
cycle” emissions that would occur as a result of the project are not applicable and are not included in the
analysis.5 A background discussion on the GHG regulatory setting and GHG modeling can be found in
Appendix C.1 to this Initial Study.
Where available, the significance criteria established by the applicable air quality management or air pollution
control district may be relied upon to make the following determinations. Would the project:
a) Generate greenhouse gas emissions, either directly or indirectly, that may have a significant
impact on the environment?
Less Than Significant Impact. Global climate change is not confined to a particular project area and is
generally accepted as the consequence of global industrialization over the last 200 years. A typical project,
even a very large one, does not generate enough greenhouse gas emissions on its own to influence global
climate change significantly; hence, the issue of global climate change is, by definition, a cumulative
environmental impact.
The proposed project would generate GHG emissions from vehicle trips generated by the project, energy use
(indirectly from purchased electricity use and directly through fuel consumed for building heating), area
sources (e.g., equipment used on-site, consumer products, coatings), water/wastewater generation, and waste
disposal. Annual GHG emissions were calculated for construction and operation of the project. Annual
average construction emissions were amortized over 30 years and included in the emissions inventory to
account for GHG emissions from the construction phase of the project. Project-related GHG emissions are
shown in Table 7, Net Project-Related GHG Emissions. The proposed project at buildout would result in a net
decrease of 30 metric tons of carbon dioxide-equivalent (MTCO2e) emissions per year compared to existing
conditions and would not exceed the EKAPCD’s bright-line threshold of 22,680 MTCO2e. Because the
3 Water vapor (H2O) is the strongest GHG and the most variable in its phases (vapor, cloud droplets, ice crystals). However, water
vapor is not considered a pollutant, but part of the feedback loop rather than a primary cause of change. 4 Black carbon contributes to climate change both directly, by absorbing sunlight, and indirectly, by depositing on snow (making it melt faster) and by interacting with clouds and affecting cloud formation. Black carbon is the most strongly light-absorbing component of PM emitted from burning fuels. Reducing black carbon emissions globally can have immediate economic, climate, and public health benefits. California has been an international leader in reducing emissions of black carbon, with close to 95 percent control expected by 2020 due to existing programs that target reducing PM from diesel engines and burning activities (CARB 2014b). However, state and national GHG inventories do not yet include black carbon due to ongoing work resolving the precise global warming potential of black carbon. Guidance for CEQA documents does not yet include black carbon. 5 Life cycle emissions include indirect emissions associated with materials manufacture. However, these indirect emissions involve numerous parties, each of which is responsible for GHG emissions of their particular activity. The California Resources Agency, in adopting the CEQA Guidelines Amendments on GHG emissions found that lifecycle analyses was not warranted for project-specific CEQA analysis in most situations, for a variety of reasons, including lack of control over some sources, and the possibility of double-counting emissions (see Final Statement of Reasons for Regulatory Action, December 2009). Because the amount of materials consumed during the operation or construction of the proposed project is not known, the origin of the raw materials purchased is not known, and manufacturing information for those raw materials are also not known, calculation of life cycle emissions would be speculative. A life-cycle analysis is not warranted (OPR 2008).
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 82 PlaceWorks
GHG emissions associated with the project would not exceed the EKAPCD’s bright-line threshold, the
proposed project’s cumulative contribution to GHG emissions is less than significant and no mitigation
measures are required.
Table 7 Net Project-Related GHG Emissions Source MTCO2e/year1 Percent of Total
Existing
Area <1 <1%
Energy 381 48%
Mobile 340 43%
Waste 49 6%
Water 18 2%
Total 788 100%
Proposed Project
Area <1 <1%
Energy1 185 24%
Mobile 456 60%
Waste 74 10%
Water 24 3%
Amortized Construction Emissions2 18 2%
Total 758 100%
Net Change
Area <1 NA
Energy1 -196 NA
Mobile 116 NA
Waste 25 NA
Water 6 NA
Amortized Construction Emissions2 18 NA
Total Emissions -30 NA
EKAPCD’s Bright-Line Threshold 22,680 NA
Exceeds Bright-Line Threshold No NA
Source: CalEEMod, Version 2013.2.2. Notes: Totals may not equal to the sum of the values shown due to rounding. MTCO2e = metric tons of carbon dioxide-equivalent. 1 For purposes of this GHG analysis, buildings on proposed land uses are assumed to comply with the 2013 Building and Energy Efficiency. Standards, which are
25 and 30 percent more energy efficient for residential and nonresidential buildings, respectively, than the 2008 standards. This analysis assumes new buildings of all land use types exceed the 2008 standards by 30 percent. Includes applicable water efficiency improvements required under CALGreen.
2 Total construction emissions are amortized over 30 years.
b) Conflict with an applicable plan, policy or regulation adopted for the purpose of reducing the
emissions of greenhouse gases?
Less Than Significant Impact. In accordance with AB 32, the California Air Resources Board (CARB)
developed the Scoping Plan to outline the state’s strategy to achieve 1990 level emissions by year 2020. To
estimate the reductions necessary, CARB projected statewide 2020 business as usual (BAU) GHG emissions
and identified that the state as a whole would be required to reduce GHG emissions by 28.5 percent from
year 2020 BAU to achieve the targets of AB 32 (CARB 2008). Since release of the 2008 Scoping Plan, CARB
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 83
has updated the 2020 GHG BAU forecast to reflect GHG emissions in light of the economic downturn and
measures not previously considered in the 2008 Scoping Plan baseline inventory. The revised BAU 2020
forecast shows that the state would have to reduce GHG emissions by 21.6 percent from BAU without Pavley
and the 33 percent renewable portfolio standard (RPS), or 15.7 percent from the adjusted baseline (i.e., with
Pavley and 33 percent RPS) (CARB 2012).
Since adoption of the 2008 Scoping Plan, state agencies have adopted programs identified in the plan, and
the legislature has passed additional legislation to achieve the GHG reduction targets. Statewide strategies to
reduce GHG emissions include the Low Carbon Fuel Standard (LCFS), California Appliance Energy
Efficiency regulations, California Building Standards (i.e., CALGreen and the 2013 Building and Energy
Efficiency Standards), 33 percent RPS, and changes in the corporate average fuel economy standards (e.g.,
Pavley I and California Advanced Clean Cars Program). The project would comply with these state GHG
emissions reduction measures and would not obstruct implementation of the CARB Scoping Plan.
KCOG’s 2014 Regional Transportation Plan/Sustainable Communities Strategy (RTP/SCS) was adopted on
June 19, 2014. It identifies a forecast development pattern to accommodate the region’s future transportation,
employment, and housing needs, while promoting conservation of natural resources and open space areas.
The 2014 RTP/SCS also identifies multimodal transportation investments, including active transportation
strategies (e.g., bike ways and sidewalks), transportation demand management, transportation systems
management, and operations and maintenance to the existing multimodal transportation system (KCOG
2014). The 2014 RTP/SCS incorporates local land use projections and circulation networks from the cities’
and counties’ general plans. The projected regional development pattern, including location of land uses and
residential densities in local general plans, when integrated with the proposed regional transportation network
identified in the 2014 RTP/SCS, would reduce per capita vehicular travel-related GHG emissions and achieve
the GHG reduction per capita targets for the KCOG region. The SCS does not require that local general
plans, specific plans, or zoning be consistent with the SCS, but provides incentives for consistency for
governments and developers. The proposed project’s design, construction, and operation will be reviewed
and approved by the China Lake command and the City of Ridgecrest; therefore, it would not interfere with
KCOG’s ability to implement the regional strategies outlined in the 2014 RTP/SCS to achieve the GHG
reduction goals and strategies for passenger vehicles and light duty trucks.
3.8 HAZARDS AND HAZARDOUS MATERIALS
The information in this Section is based in part on the following technical studies:
Phase I Environmental Site Assessment, New Murray Middle School (northwest Corner E. French Drive and E.
Drummond Avenue, Ridgecrest, California 93555), PlaceWorks, December 27, 2013. A complete copy of
this report is included as Appendix G.1 of this Initial Study.
Preliminary Environmental Assessment Report (PEA), New Murray Middle School, PlaceWorks, December 9,
2014. A complete copy of this report is included as Appendix G.2
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 84 PlaceWorks
Remedial Action Workplan, New Murray Middle School, PlaceWorks, April 29, 2015. A complete copy of this
report is included as Appendix G.3.
a) Create a significant hazard to the public or the environment through the routine transport, use or
disposal of hazardous materials?
Less Than Significant Impact. Construction of the proposed new school would not require extensive or
ongoing use of acutely hazardous materials or substances. While grading and construction may involve
activities requiring the transport, storage, use, or disposal of some hazardous materials, such as onsite fueling
or servicing of construction equipment, the activities would be short term and would be subject to federal,
state, and local health and safety requirements.
The types of hazardous materials associated with operation of the proposed new Murray Middle School
campus would be similar to those at the existing campus. They would generally be limited to chemicals
associated with school labs, which would be used in small amounts; and maintenance, janitorial, and repair
products, such as commercial cleansers, lubricants, paints, etc. All hazardous materials used in science labs
would be stored, handled, and disposed of in accordance with county, state, and federal laws that protect
public safety. Furthermore, the storage, handling, and disposal of hazardous materials are regulated by the
USEPA, Occupational Safety and Health Administration (OSHA), and the Kern County Environmental
Health Services Department.6 The requirements of these agencies would be incorporated into the design and
operation of the school. This would include providing for and maintaining appropriate storage areas for
hazardous materials and installing or affixing appropriate warning signs and labels.
Compliance with applicable health and safety requirements, including manufacturers’ product labels, would
ensure that no significant hazard to the public, the students, or the environment would result through the
routine transport, use, or disposal of hazardous materials. No mitigation is required.
b) Create a significant hazard to the public or the environment through reasonably foreseeable
upset and accident conditions involving the release of hazardous materials into the
environment?
Less Than Significant Impact. As discussed above, operation of the new school would not result in a
significant hazard or release hazardous materials into the environment. Storage, transport, and disposal of
hazardous materials onsite would be conducted in accordance with the requirements of the agencies
mentioned in the previous impact analysis, and there are no reasonably foreseeable upsets and accidental
conditions related to the use of hazardous materials during the operation of the proposed facility.
Operational impacts would be less than significant, and no mitigation measures are required.
Additionally, as discussed above, general construction activities would comply with federal, state, and local
health and safety requirements, and these types of routine construction activities are not expected to result in
the release of hazardous materials in the environment. It is possible, however, that soil remediation activities
6 The Kern County Environmental Health Services Department is the Certified Unified Program Agency (CUPA) for Kern County outside of the City of Bakersfield; the Certified Unified Program coordinates and makes consistent enforcement of several state and local laws governing hazardous materials.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 85
could result in an upset or accident that could release hazardous materials into the environment. Two
pesticides are of particular interest: dieldrin and aldrin. They are generally considered nonvolatile, but can
adhere to soil particles and become airborne contaminants. As provided in the Removal Action Workplan
(RAW), during remediation activities, dust control measures would be performed to reduce the potential for
fugitive dust and migration of contamination in compliance with requirements in Kern County APCD Rule
402. Air monitoring for dust would be performed within the active work zone (i.e., “exclusion zone”) to
ensure the health and safety of remediation workers. Air monitoring would also be conducted at the
perimeter of the project site (i.e., “fenceline locations”) to ensure that unsafe concentrations of dust are not
migrating offsite. An upwind/downwind sampling approach would be used for fenceline monitoring, with
monitoring positions established based on an ongoing assessment of the prevailing wind direction. The
project site perimeter would be secured with fencing fitted with windscreens to minimize the offsite
migration of windborne dust. The generation of dust would be controlled with water applied as a light spray
to soil stockpiles, exposed excavation surfaces, excavator buckets, and internal roadways, as necessary. Onsite
meteorological monitoring would be performed concurrently with the soil removal activities to ensure that all
necessary precautions have been taken. Ambient weather conditions (e.g., wind speed, wind direction,
temperature, and relative humidity) would be monitored using a portable, onsite meteorological station with
data logging capability. The dust control and monitoring program is written into the RAW and would be
overseen by DTSC to ensure that all site activities are in compliance with the RAW. Impacts to the public and
the environment due to the release of hazardous fugitive dust would be less than significant, and no
mitigation measures would be required.
Underground utility lines remain onsite from former residential use of the site. Such lines may contain
asbestos. Naval safety policy requires the construction contractor and/or the District to contact SOHD if the
project discovers suspect asbestos-containing materials (ACM). Any required abatement and removal of ACM
would be conducted under existing state and federal regulations. Impacts concerning the potential release of
these materials into the environment would be less than significant, and no mitigation measures would be
required.
Demolition of the existing campus would comply with regulations of the above-referenced agencies. Given
the age of the existing campus, buildings on the campus could contain ACM, and their removal would be
conducted in accordance with applicable state and federal regulations. Impacts would be less than significant,
and no mitigation measures would be required.
c) Emit hazardous emissions or handle hazardous or acutely hazardous materials, substances, or
waste within one-quarter mile of an existing or proposed school?
Less than Significant Impact. There are two schools within 0.25 mile of the new school site: Burroughs
High School opposite Knox Road east of the site; and Pierce Elementary School at 674 North Gold Canyon
Street, about 925 feet southeast of the site. Project construction would emit diesel exhaust, which is
considered hazardous. However, construction would be temporary, and hazards from air emissions are
estimated for several decades of exposure; therefore, diesel emissions from project construction would not
pose substantial hazards to persons at either existing school. Additionally, as discussed above in section (b),
during remediation activities, dust control and monitoring would be performed to reduce the potential for
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 86 PlaceWorks
migration of fugitive dust containing dieldrin and aldrin. Dust control measures would comply with
requirements contained in Kern County APCD Rule 402 and overseen by the DTSC to ensure that all
remediation activities are in compliance with established standards.
The proposed project does not include any facilities (e.g., emergency generator) that would emit hazardous
emissions or require a permit from the East Kern Air Pollution Control District. Operation of the new
middle school would be similar to that of the existing school. Limited hazardous substances would be used
during operations, such as janitorial supplies. With adherence to applicable state and federal policies and
regulations related to hazardous materials, these limited hazardous substances would not result in emissions
that would adversely affect nearby schools. Impacts from the proposed project would be less than significant,
and no mitigation measures are required.
There are no existing schools within 0.25 mile of the existing campus; the nearest school, Richmond
Elementary School, is about 2,400 feet to the north (Google Earth 2015). Demolition of the existing campus
would not emit hazardous substances within 0.25 mile of a school, and no impact would occur.
d) Be located on a site which is included on a list of hazardous materials sites compiled pursuant to
Government code Section 65962.5 and, as a result, would it create a significant hazard to the
public or the environment?
Less Than Significant Impact.
New School Site
The Phase I Environmental Site Assessment (ESA) for the new school site included an environmental
database review (see Appendix G.1) that identified the following hazardous materials sites within 0.5 mile of
the new school site.
Burroughs High School, at 500 East French Street and opposite Knox Road east of the new school site,
is listed as a small quantity generator of hazardous wastes (SQG) on the Resources Conservation and
Recovery Act (RCRA) Generator List.
Charlon & Simolon, Inc. at 723 China Lake Boulevard, located roughly 0.5 mile west of the new school
site, is listed on the Cortese List, which identifies hazardous waste sites selected for remedial action and
underground storage tank (UST) properties having a reportable release. The site is also listed as a Leaking
Underground Storage Tank (LUST) site for a gasoline release that affected soil; the case was closed in
1990.
The Town Center Mall at Drummond Road, about 0.5 mile west-northwest of the new school site, is
listed as a Landfill or Solid Waste Disposal Site. The operator was the US Department of Navy-China
Lake. The facility closed in 1989 (CalRecycle 2015).
The database search was updated on January 26, 2015, through searches of the following databases:
GeoTracker, maintained by the State Water Resources Control Board; EnviroStor, maintained by the
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 87
Department of Toxic Substances Control (DTSC); and EnviroMapper, maintained by the USEPA. The
search radii and the center of the search area were the same as used in the aforementioned database search.
The new middle school site is listed on the EnviroStor database for a school site investigation, that is, the
above-mentioned Phase I Environmental Site Assessment.
Pierce Elementary School, at 674 North Gold Canyon Street in the City of Ridgecrest and the naval
station—about 925 feet southeast of the new school site—is listed on the EnviroStor database as a
Military Cleanup Site. The potential contaminants of concern and potential media affected are
unspecified. The case is open; a site assessment was conducted in 2006.
Vieweg Elementary School, at 348 Rowe Street in the City of Ridgecrest and the naval station—about
2,350 feet north of the new school site—is listed on the EnviroStor database as a Military Cleanup Site.
The potential contaminants of concern and potential media affected are unspecified. The case is open; a
site assessment was conducted in 2006.
China Lake Annex 1, at the northeast corner of China Lake Boulevard and Drummond Avenue, is listed
as a Military Evaluation Site on EnviroStor. The case is inactive; the listing states that evaluation was
needed as of 2005.
One Hour Cleaners, at 820A China Lake Boulevard and about 1,120 feet west of the new school site, is
listed as an SQG on the EnviroMapper database.
Home Depot USA #1089, at 575 North China Lake Boulevard, about 1,250 feet southwest of the new
school site, is listed as an SQG on the EnviroMapper database.
No offsite recognized environmental conditions (RECs) were identified in the Phase I Environmental Site
Assessment.7 None of the offsite database listings identified above in the updated search is considered an
environmental concern for the new school site. Impacts from listed hazardous materials sites would be less
than significant.
Recognized Environmental Conditions
The following RECs were identified on the new school site by the Phase I ESA:
Lead Residues in Soil: Due to the potential use of lead-based paint (LBP) in residential structures that
historically occupied the new school site, it is possible that elevated concentrations of lead could be
present in shallow soil in the northern portion of the site.
Pesticide Residues in Soil: Organochlorine pesticides (OCPs), presumably for termite control in
residential structures that historically occupied the northern portion of the proposed new school site,
7 An REC is the presence or likely presence of any hazardous substance or petroleum products in, on, or at a property: due to release to the environment; under conditions indicative of a release to the environment; or under conditions that pose a material threat of a future release to the environment.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 88 PlaceWorks
were detected in shallow soil. Although the results of a human health risk evaluation concluded that the
risks posed by these detected compounds fall within the acceptable range, the number of samples
actually collected on the site for this overall risk evaluation was somewhat limited, and it remains possible
that elevated concentrations of OCPs could be present in shallow soil on the northern portion of the
site. Additionally, arsenic residues may be present in soil due to the historical use of arsenical herbicides
prior to 1950. Therefore, it is possible that elevated concentrations of arsenic also may be present in
shallow soil in in the northern portion of the site.
Asbestos Containing Material: The Navy conducted an ACM cleanup in 2012 on the northern portion
of the site that historically was occupied with residential structures. Documents related to this cleanup
effort were provided by China Lake personnel. Minor ACM debris was observed in this area of the site at
the time reconnaissance was completed for the Phase I. In addition, utility pipelines abandoned in place
may contain ACM. Contractors should be made aware of the possible presence of ACM, and further
debris cleanup and possibly pipeline removal may be required before commencing with future grading
and/or construction plans.
Preliminary Environmental Assessment
A Preliminary Environmental Assessment (PEA) was completed by PlaceWorks in December 2014, including
soil sampling and testing investigating two RECs identified in the Phase I ESA—lead residues and pesticide
residues in soil—as well as additional environmental concerns identified by the DTSC: residues of
polychlorinated biphenyls (PCBs), dioxin, and furans that could be present in site soils due to the reported
historical use of oil on roads for dust control.
Sampling
Soil samples were collected from borings at 35 locations onsite at depths of up to 3 feet bgs.
24 soil borings from the northern part of the site analyzed for OCPs, arsenic, and lead.
Five borings from the southern part of the site analyzed for PCBs, dioxins, and furans.
Six borings from in and near the former electrical substation analyzed for PCBs.
Testing
The following test methods were used:
USEPA Method 6010B: Lead
USEPA Method 6020: Arsenic
USEPA Method 8081A: OCPs
USEPA Method 8082: PCBs
USEPA Method 8290: Dioxins/Furans
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 89
Test Results and Preliminary Screening Levels
Regional screening levels for some of the contaminants evaluated are set by the USEPA. California Human
Health Screening Levels are set by the Office of Environmental Health Hazard Assessment.
Lead
Lead was identified at concentrations ranging up to 14.3 mg/kg; that is, background, naturally occurring
concentrations. The preliminary screening level for lead is 80 mg/kg; thus, lead does not pose a threat to
human health or the environment and is not considered a constituent of potential concern (COPC) for the
site.
Arsenic
Arsenic concentrations ranged from 0.86 to 13.1 mg/kg, with a median of 1.6 mg/kg and a 95 percent upper
confidence limit (UCL) of 4.1 mg/kg. The preliminary screening level for arsenic is 12 mg/kg. The detection
of arsenic at a concentration above the preliminary screening level in a single soil sample does not pose a
threat to human health or the environment for the following reasons: 1) at 13.1 mg/kg, the concentration
only slightly exceeds the preliminary screening level of 12 mg/kg; 2) the 95 percent UCL for the arsenic data
set is only 4.1 mg/kg, which is more representative of the actual hazard posed by arsenic concentrations
distributed throughout the site; and 3) the concentration was detected at a depth of 2.5 feet bgs (the arsenic
concentration in the overlying surface sample at this location was 1.53 mg/kg) and therefore is not readily
accessible for direct human exposure. Therefore, arsenic is not considered a COPC for the site.
Organochlorine Pesticides
Two organochlorine pesticides, aldrin and dieldrin, were identified at concentrations above preliminary
screening levels, as shown in Table 8, Organochlorine Pesticide Concentrations Identified. All of the detected OCPs
were considered COPCs.
Table 8 Organochlorine Pesticide Concentrations Identified
Pesticide
No. of Samples1
No. of Detections
Maximum Concentration
(µg/kg)
Preliminary Screening Level
(µg/kg)1
No. Exceeding Preliminary
Screening Level
Aldrin 38 13 502 31 2
Chlordane (total) 38 20 110 1,800 0
Chlordane (alpha) 38 18 58.4 1,800 0
Chlordane (gamma) 38 18 52.0 1,800 0
4,4’-DDD 38 3 2.93 2,200 0
4,4’-DDE 38 20 130 1,600 0
4,4’-DDT 38 18 87.2 1,900 0
Dieldrin 38 27 9,820 33 17
Heptachlor Epoxide 38 2 10.8 59 0 Source: PlaceWorks 2014. 1 µg/kg = micrograms per kilogram
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 90 PlaceWorks
Polychlorinated Biphenyls
Polychlorinated biphenyls (PCBs) were identified in two samples at estimated concentrations below the
concentration that can be quantified by the relevant test method. The estimated concentrations are below the
preliminary screening level of 300 µg/kg. However, PCBs were considered COPCs to assess their
contribution to the overall health risk and hazard at the site.
Dioxins/Furans
All concentrations of dioxins and furans detected from within the revised campus boundary were below the
preliminary screening level of 4.9 nanogram per kilogram (ng/kg). One concentration detected, 36.3 ng/kg,
was from a sampling location outside of the revised campus boundary. Dioxins and furans were considered
COPCs to assess their contribution to the overall health risk and hazard at the site.
Human Health Screening Evaluation
Three exposure pathways were evaluated: soil ingestion, skin absorption, and dust inhalation. Two categories
of health risks were evaluated, non-carcinogenic risks and carcinogenic risks. Non-carcinogenic risks for each
chemical and each exposure pathway are evaluated as a hazard quotient comparing average daily intake to a
reference dose or reference concentration. A hazard index is then calculated by summing the hazard quotients
for all COPCs and all pathways; the DTSC considers a hazard index of 1.0 or greater to be unacceptable for
new school sites. Carcinogenic risks are evaluated as excess cancer risk calculated by multiplying the lifetime
average daily intake by a toxicity value. The DTSC uses a risk threshold of 1 x 10-6 for new school sites.
The total cancer risk estimated from the human health screening evaluation is 3.0 x 10-4, and the total
noncancer hazard index is 3.2. Both the estimated cancer and noncancer risks exceed DTSC thresholds. The
main contributors to the estimated cancer risk are dieldrin and aldrin; after removing these two contributors
from the data, the cancer risk is estimated at 9.1 x 10-7, below the DTSC threshold. The main contributors to
noncancer risk are also dieldrin and aldrin; removing these contributors from the data leaves a remaining
hazard index of 0.12, below the DTSC threshold.
The PEA recommended soil remediation for dieldrin and aldrin contamination in four general areas in the
northern part of the site, where the former base housing was located (Figure 12, Soil Removal and Reburial
Areas):
Area A. Soil will be removed from an area of 203,430 square feet (4.7 acres) to depths ranging from 0.5
to 2.5 feet bgs, as defined by seven subareas. This portion of the removal action will generate an
estimated 6,982 cubic yards of soil.
Area B. Soil will be removed from an area of 179,160 square feet (4.1 acres) to depths ranging from 0.5
to 3.0 feet bgs, as defined by eight subareas. This portion of the removal action will generate an estimated
5,555 cubic yards of soil.
Area C. Soil will be removed from an area of 128,930 square feet (3.0 acres) to depths ranging from 0.5
to 3.0 feet bgs, as defined by seven subareas. This portion of the removal action will generate an
estimated 4,965 cubic yards of soil.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 91
Area D. Soil will be removed from an area of 40,351 square feet (0.9 acres) to depths ranging from 0.5 to
3.0 feet bgs, as defined by six subareas. This portion of the removal action will generate an estimated
1,620 cubic yards of soil.
The estimated volume of impacted soil that requires removal is 20,077 cubic yards, including a 5 percent
contingency to account for the results of postremoval confirmation soil sampling. Almost all of the removed
soil can be managed as nonhazardous waste; a very small volume (<10 cubic yards) would require
management as non-RCRA hazardous waste.
Remedial Action Workplan
The District has entered into an agreement with DTSC to complete all site investigations and response
actions under the oversight of the DTSC. The Removal Action Workplan (RAW) has been prepared and
recommends the below remedial options.
Alternative 1 (No Action). This alternative is required as a baseline by which all other remedial
alternatives can be compared. This alternative involves taking no action toward a remedy or active
management to achieve the remediation goal of developing a school on the project site;
Alternative 2 (Soil Excavation and Offsite Disposal). This option involves the excavation and offsite
disposal of soil impacted by pesticides. An estimated 20,077 cubic yards of impacted soil would be
excavated to depths ranging from 0.5 to 3.0 feet bgs. Once the impacted soil is removed, confirmation
soil samples would be collected from the exposed excavation sidewalls and bottoms to confirm that the
site specific cleanup goals have been met and the removal action objectives have been achieved. Because
the site is considered to be balanced with respect to soil import/export, a similar volume of clean soil
(20,077 cubic yards) would need to be imported. Exported soil would likely be brought to the Lancaster
Landfill and Recycling Center, which is approximately 83 miles southwest of Ridgecrest, and/or the
Antelope Valley Public Landfill, which is about 95 miles southwest of Ridgecrest. It is not known at this
time where the soil would be imported from. Excavation and offsite disposal would be an effective means
of removing impacted soil and would meet the remediation goal.
Alternative 3 (Soil Excavation and Onsite Burial, Capping, and Land Use Covenant). As with Alternative
2, Alternative 3 involves the excavation and removal of an estimated 20,077 cubic yards of pesticide-
impacted soil. However, rather than offsite disposal, the excavated soil would be placed in an engineered
onsite burial cell (Figure 12) and covered by a protective soil cap, in accordance with engineering design
plans approved by the DTSC. Individual soil removal areas would be backfilled immediately after soil
samples confirm that all of the contaminated soil for that area/subarea has been removed (to the burial
cell) and DTSC has reviewed the lab data and provided informal approval to backfill. A small amount of
non-RCRA hazardous soil (<10 cubic yards) would be disposed of offsite either at the Kettleman or
Buttonwillow landfills, approximately 200 and 150 miles west of Ridgecrest, respectively. The remainder
would be loaded into end-dump trucks and transferred to the burial cell.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 92 PlaceWorks
Once the burial cell has been backfilled to a depth no shallower than two feet below grade, an engineered
cap would be constructed above the buried soil. The cap would consist of a permeable geotextile mat
overlain by a two-foot thick soil cover constructed using the clean soil reserved during excavation of the
burial cell. The cover soil would be applied, compacted, and graded in accordance with the approved
design plans to promote drainage and minimize wind and water erosion. Once completed, the cap would
be hydroseeded with acceptable desert vegetation to establish a vegetated root mat that would minimize
erosion and facilitate evapotranspiration. The cap would be subject to long-term inspections and
maintenance to ensure that it continues to function as intended. A land use restriction would also be
applied to the burial site, and future development options would be limited.
While the RAW identifies three potential options, Alternative 3 has been identified as the preferred alternative
because it is most cost-effective, easily implemented, and protective of future occupants of the proposed
school and the environment. Consequently, the analysis provided throughout this Initial Study considers the
impacts associated with Alternative 3.
Soil remediation activities would commence after the project is approved by the Board of Education and the
RAW is approved by DTSC. As all soil removal activities would be conducted under the oversight of DTSC
and in accordance with established methods and procedures, and actual construction of the proposed school
would not commence until after DTSC concurred that the proposed school site has been fully remediated for
school development and issued a letter of Certification of Removal Action, impacts related to hazardous
materials on the property would be less than significant. Compliance with the requirements imposed by
DTSC would reduce potentially significant impacts to less than significant. No mitigation measures are
required.
Existing School Site
Three environmental databases—GeoTracker, EnviroStor, and EnviroMapper—were searched for listings on
and within 0.25 mile of the existing school site on January 26, 2015.
Murray Middle School is listed on the GeoTracker database as a Military Cleanup Site. The substance(s)
released and potential media affected are not specified. The case is open, and site assessment was
conducted in 2006, but no further information on the current status is provided on GeoTracker. The
campus is also listed as a leaking underground storage tank (LUST) site for release of waste oil, motor oil,
hydraulic oil, and lubricating oil that affected soil. The LUST case was closed in 1997.
The Navy Exchange Gas Station near the northeast corner of Richmond Road and King Avenue about
550 feet northeast of the campus is listed on GeoTracker as a LUST site. A release of gasoline affected
groundwater other than drinking water. The case is open, and verification monitoring was ongoing in
2009.
Neither of the above listings are environmental concerns with respect to the demolition of the existing
campus. Furthermore, the proposed project would result in the relocation of the school occupants to the
proposed new site, which would be remediated to acceptable standards as a part of the proposed project.
Therefore, impacts would be less than significant, and no mitigation is required.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 93
e) For a project located within an airport land use plan or, where such a plan has not been adopted,
within two miles or a public airport or public use airport, would the project result in a safety
hazard for people residing or working in the project area?
Less Than Significant Impact. The closest airport to the project sites is Armitage Airfield on base, 2.9
miles north of the proposed middle school site and 2.4 miles northeast of the existing campus. The proposed
school site is not aligned with any of the three airfield runways.8 All proposed buildings at the new middle
school would be one story, and the highest building would be the gymnasium building at 30 feet, no higher
than existing buildings at Burroughs High School, opposite Knox Road from the new school site.
Development of the new middle school and demolition of the existing school would not create any
substantial hazards related to aircraft approaching or departing Armitage Airfield, and no mitigation measures
are required.
f) For a project within the vicinity of a private airstrip, would the project result in a safety hazard
for people residing or working in the project area?
Less Than Significant Impact. The nearest private heliport to either project site is the Ridgecrest
Community Helicopter Heliport at 1081 North China Lake Boulevard in Ridgecrest, about 1,950 feet
northwest of the proposed school site (Airnav.com 2015). Over congested areas, helicopters must maintain
an altitude of at least 1,000 feet above the highest obstacle within 2,000 feet of the aircraft, except as needed
for takeoff and landing (Code of Federal Regulations, Title 14, § 91.119). Helicopters operating to or from
this heliport would comply with existing regulations regarding operating altitudes. Project development would
not cause substantial hazards related to helicopters, and no mitigation is needed.
g) Impair implementation of or physically interfere with an adopted emergency response plan or
emergency evacuation plan?
No Impact. China Lake’s Emergency Management Office (EMO) is responsible for emergency preparedness
and emergency response on base. Development of the proposed middle school and demolition of the
existing middle school would not interfere with implementation of EMO emergency response plans. The
District would prepare and implement an emergency evacuation plan for the proposed school in accordance
with CDE requirements. No impact would occur.
h) Expose people or structures to a significant risk of loss, injury or death involving wildland fires,
including where wildlands are adjacent to urbanized areas or where residences are intermixed
with wildlands?
No Impact. The proposed project would not expose people or structures to the risk of wildland fires. The
school sites and surrounding properties are entirely developed with urban uses, and the areas surrounding the
sites do not contain highly flammable brush or grass. No Fire Hazard Severity Zones are mapped on or near
the site by the California Department of Forestry and Fire Prevention (CAL FIRE 2007). No impact would
occur, and no mitigation measures are necessary.
8 However, Runway 14/32 is aligned with the easternmost part of the Burroughs High School campus east of the proposed middle school site.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 94 PlaceWorks
i) Does the proposed school site contain one or more pipelines, situated underground or
aboveground, which carry hazardous substances, acutely hazardous materials or hazardous
wastes, unless the pipeline is a natural gas line that is used only to supply natural gas to that
school or neighborhood?
Less Than Significant Impact. There are underground utilities in abandoned roadways in the north half of
the new school site from past residential uses. These utilities have been abandoned and would be removed
during site preparation. Therefore, the aforementioned utilities would not pose hazards to people at the new
school, and impacts would be less than significant.
j) Does the project site contain a current or former hazardous waste disposal site or solid waste
disposal site and, if so, have the wastes been removed?
No Impact. No current or former hazardous waste disposal site or solid waste disposal site was identified on
the new school site in the Phase I ESA or on the existing campus in a search of three databases conducted on
January 26, 2015. No impact would occur, and no mitigation is needed.
k) Is the project site a hazardous substance release site identified by the state Department of
Health Services in a current list adopted pursuant to § 25356 for removal or remedial action
pursuant to Chapter 6.8 of Division of the Health and Safety Code?
Less than Significant Impact. The DTSC maintains a list of Hazardous Waste and Substances Sites
pursuant to Health and Safety Code Section 25356 consisting of listed and delisted federal Superfund sites;
State Response sites; and military investigation sites. The new school site is not listed as any of the types of
hazardous materials sites specified in Section 25356.
The existing campus is listed on the GeoTracker database as a military cleanup site. The substance(s) released
and potential media affected are not specified. The case is open, and site assessment was conducted in 2006,
but no further information on the current status is provided on GeoTracker. The District is not proposing to
build or operate a new or expanded school at the existing campus, but to move the students to the proposed
project site and demolish the existing school. Impacts would be less than significant, and no mitigation is
needed.
3.9 HYDROLOGY AND WATER QUALITY
a) Violate any water quality standards or waste discharge requirements?
Less Than Significant Impact. A significant impact would occur if the proposed project resulted in the
discharge of pollutants into receiving waters, which could occur from the disturbance of soils associated with
construction activities. The proposed new school would be constructed on a site that is larger than one acre.
Since the new school site is greater than one acre, the construction contractor would be required to comply
with NPDES General Construction Permit requirements and would be required to prepare and comply with
the requirement of a SWPPP. The requirement of a SWPPP has been incorporated into the project
description as a BMP, as explained further above in Section 3.6.b. Therefore, with adherence to the
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 95
abovementioned regulations, including adherence to the requirements of the NPDES General Construction
Permit and a SWPPP, implementation of the proposed project would not violate water quality standards and
waste discharge requirements.
Demolition of the existing campus would comply with the above-referenced regulatory requirements. The
proposed project would have a less than significant impact, and no mitigation is required.
b) Substantially deplete groundwater supplies or interfere substantially with groundwater recharge
such that there would be a net deficit in aquifer volume or a lowering of the local groundwater
table level (e.g., the production rate of pre-existing nearby wells would drop to a level which
would not support existing land uses or planned uses for which permits have been granted)?
Less Than Significant Impact. The projects are above the Indian Wells Valley Groundwater Basin
(IWVGB) (PlaceWorks 2013). The new school site is permeable, but is not used for intentional groundwater
recharge. The IWVGB spans 597 square miles or 38,200 acres, the vast majority of which is vacant permeable
land. Thus, development of parts of the 47-acre new school site with impermeable uses would not have a
substantial adverse impact on groundwater recharge. The project would not involve groundwater wells and
would not directly withdraw water from the IWVGB. The project would relocate the existing Murray Middle
School program to the new site; the students who would attend the new school already attend the existing
middle school just over one mile from the new school site. The project therefore would not increase regional
water demand.
Demolition of the existing campus would temporarily use a small amount of water for uses such as dust
control. Demolition would not deplete groundwater supplies and would not interfere with groundwater
recharge.
Impacts to groundwater recharge and groundwater supply would be less than significant, and no mitigation is
needed.
c) Substantially alter the existing drainage pattern of the site or area, including through the
alteration of the course of a stream or river, in a manner which would result in a substantial
erosion or siltation on- or off-site.
Less Than Significant Impact. The new school site slopes east with a grade of about 1 percent. Several
shallow washes cross the site; and there are degraded roadways in the north half of the site remaining from
previous residential development. Drainage is by surface flow eastward. The new school site has been divided
into four existing drainage subareas mapped on the existing hydrology map (see Hydrology Study in
Appendix H).
Subareas 1 and 2, comprising approximately the northern half of the site, consist of graded pads and streets
from the former development. Subarea 1 spans 16.9 acres of the northern and northwestern part of the site.
Drainage is generally northerly, with slopes of about 1 percent grade. Subarea 2, 3.7 acres in the north-central
part of the site, drains easterly to Knox Avenue with a 0.5 percent grade.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 96 PlaceWorks
Subareas 3 and 4 are in the southern half of the site and consist of vacant desert land. Subarea 3 is 7.3 acres
in the southwest part of the site. Drainage in this area is southerly, exiting the drainage area along its
southeast boundary into Drainage Area 4. Subarea 4, 13.3 acres mostly in the southeast quadrant of the site,
drains southeasterly to the intersection of Knox Avenue and Drummond Avenue.
Runoff from a 100-year storm in existing conditions is estimated below in Table 9, Existing Runoff, 100-Year
Storm.
Table 9 Existing Runoff, 100-Year Storm
Drainage Subarea Runoff, 100-year storm, cubic feet per second Area, acres
1 25.87 16.89
2 6.07 3.71
3 11.93 7.28
4 22.88 13.29
Total 66.75 41.17
Source: Mielke 2015.
Runoff from a 100-year storm with the new school is estimated below in Table 10, Estimated Runoff, Proposed
Conditions, 100-Year Storm. Runoff would increase from 66.75 in existing conditions to 82.55 in proposed
conditions, an increase of 15.8 cubic feet per second (cfs) or about 24 percent over existing conditions.
Table 10 Estimated Runoff, Proposed Conditions, 100-Year Storm Drainage Subarea Proposed Land Cover Type Runoff, 100-year storm,
cubic feet per second Area, acres
1 School (including hardcourts and retention basin)
9.68 3.53
2 School (including building, hardscape, and part of track and
field)
3.25 1.18
3 Vacant land 11.92 6.78
4 School (including buildings, landscaping, hardscape, and
retention basin)
13.34 7.08
5 Baseball field (mostly) 4.14 1.87
6 Baseball field (mostly) 2.37 0.98
7 Baseball field and retention basin 8.49 4.03
8 Vacant land and retention basin 9.58 4.55
9 School (including parking lot and retention basin)
8.21 3.33
10 Vacant land 11.57 7.28
Total Not applicable 82.55 40.61
Source: Mielke 2015.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 97
Project development would include construction of nine retention basins, described in Table 11 and mapped
on Figure 17, Proposed Hydrology Map. Note that the drainage areas of all nine proposed retention basins
correspond to proposed drainage subareas 1 through 9. The only exception is Basin 7, which would
accommodate drainage from subarea 7 and receive drainage from Basins 5 and 6. The proposed retention
basins would infiltrate into the soil the estimated runoff from the site in postproject conditions from a 10-
year, 5-day storm. The retention basins would not have outlets, except for basins 5 and 6, which would have
outlets discharging into Basin 7. Drainage from the site at project completion in a 10-year, 5-day storm would
be reduced compared to existing conditions, and impacts would be less than significant.
Table 11 Proposed Retention Basins
Basin1
Tributary Area
Required Volume Design Volume Square feet Portion impervious
1 153,778 0.40 13,584 50,277
2 51,606 0.40 4,559 1,203
3 295,441 0.02 1,305 2,239
4 308,532 0.40 27,254 70,089
5 81,638 0.15 2,704 1,709
6 42,874 0.15 1,420 1,911
7 Basin 5 + Basin 6 + Basin 7 =
300,143
0.15 9,942 14,901
8 198,147 0.02 875 10,666
9 145,084 0.40 12,816 13,089
Source: Mielke 2015. 1 The drainage areas for all 9 proposed retention basins correspond to proposed drainage subareas 1 through 9; except for Basin 7, which would accommodate
drainage from subarea 7 and would receive drainage from Basins 5 and 6. Data for the 9 basins are not totaled, as totals would double-count data for basins 5 and 6.
Site preparation, grading, and construction activities on the new school site would disturb and expose large
quantities of soil. Disturbance and exposure of soil could dramatically increase soil erosion and
sedimentation if effective control measures were not used. Erosion controls and sediment controls in the
project SWPPP would be implemented during site preparation, grading, and construction of the new school.
Erosion control BMPs include mulch, geotextiles, mats, hydroseeding, earth dikes, and swales. Sediment
control BMPs include barriers such as straw bales, sandbags, fiber rolls, and gravel bag berms; desilting basins;
and cleaning measures such as street sweeping.
The existing campus slopes east with a grade of about 0.5 percent. Drainage is downgrade eastward.
Demolition of the existing campus would not change the drainage pattern on that site. The project would not
change the course of a stream or river, and no consequent erosion or siltation would occur. Impacts would be
less than significant.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 98 PlaceWorks
d) Substantially alter the existing drainage pattern of the site or area, including through the
alteration of the course of a stream or river, or substantially increase the rate or amount of
surface runoff in a manner which would result in flooding on- or off-site?
Less Than Significant Impact. The proposed project would not substantially alter the existing drainage
patterns of the site or area in a manner that would result in flooding on- or offsite. The project would
develop about 8.5 acres of impervious areas, and thus would increase runoff on the site. Please see (c), above,
for additional discussion of stormwater drainage at the new school site.
In addition, the proposed project would be required to comply with the requirements of the NPDES General
Construction Permit, as well as with the BMPs identified in the project-specific SWPPP. Compliance with
these requirements would ensure that the proposed project would not adversely affect the local drainage
system in a manner that would result in substantial flooding on- or offsite.
Demolition of the existing campus would remove the impervious surfaces on that site, thus reducing runoff
from the site. Demolition would not increase flooding on- or offsite. Impacts would be less than significant
for the proposed project, and no mitigation is required.
e) Create or contribute runoff water which would exceed the capacity of existing or planned storm
water drainage systems or provide substantial additional sources of polluted runoff?
Less Than Significant Impact. The project includes proposed detention/infiltration basins on the new
school site that would accommodate site drainage. In postproject conditions, about 8.5 acres, or about 18
percent of the project site, would be developed with impervious surfaces; the remainder of the site would
remain permeable. Considering the limited portion of the site that would be impervious at project
completion, plus the proposed detention/infiltration basins, project development would not substantially
increase runoff from the site and would not significantly impact offsite stormwater drainage systems. The
project would not require construction of new or expanded offsite storm drainage infrastructure, and no
adverse impact on storm drainage systems would occur.
Demolition of the existing campus would reduce runoff from that site and would have no adverse impact on
storm drainage capacity. Demolition would comply with the same regulatory requirements as construction of
the new campus. Project water quality impacts would be less than significant, as substantiated above in
Sections 3.6.b and 3.9.a. No mitigation measures are required.
f) Otherwise substantially degrade water quality?
Less Than Significant Impact. The project construction and demolition contractor(s) would be required to
prepare and implement a SWPPP (see discussion in Section 3.6.b, above). Erosion control and sediment
control BMPs are summarized above in Section 3.9.c; SWPPPs also prescribe other categories of BMPs such
as prohibitions of discharges of material other than stormwater; and management of materials and wastes.
After compliance with existing regulations, project impacts on water quality or water pollution would be less
than significant, and no mitigation is required.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 99
Figure 17 Proposed Hydrology Map
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 100 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 101
g) Place housing within a 100-year flood hazard area as mapped on a federal Flood Hazard
Boundary or Flood Insurance Rate Map or other flood hazard delineation map?
No Impact. The new school site is designated by the Federal Emergency Management Agency (FEMA) as
within flood zone X, indicating that it is outside of 100-year and 500-year flood zones (FEMA 2014). The
proposed project would not introduce any new flood hazards or place structures or people within a 100-year
flood hazard zone. Furthermore, the proposed project would not relocate or create new housing. The existing
campus is also in Zone X; demolition of the existing campus would have no adverse impacts related to 100-
year flood zones. No impact would occur, and no mitigation is required.
h) Place within a 100-year flood hazard area structures which would impede or redirect flood flows?
No Impact. The new school site is designated by FEMA as outside of 100-year and 500-year flood zones.
The proposed project would not introduce any new flood hazards or place structures within a flood zone that
would impede or redirect flood flows. Demolition of the existing campus would have no adverse impacts
related to 100-year flood zones. No impact would occur, and no mitigation is required.
i) Expose people or structures to a significant risk of loss, injury or death involving flooding,
including flooding as a result of the failure of a levee or dam?
Less than Significant Impact. There are no dams in the region that would pose a flood risk to people or
structures on the new school site, and no impact would occur. The new school site is not in an area
designated by FEMA as protected from 100-year floods by levees. the Demolition of the existing campus
would not create a flood hazard due to levee or dam failure. No mitigation is required.
j) Inundation by seiche, tsunami, or mudflow?
No Impact. A seiche is a surface wave created when a body of water is shaken, usually by earthquake activity.
There are no surface water bodies near the new school site that could pose a flood risk to the site due to a
seiche. A tsunami is a series of ocean waves caused by a sudden displacement of the ocean floor, most often
due to earthquakes. The new school site is 121 miles inland and separated from the Pacific Ocean by several
mountain ranges; thus, there is no tsunami flood hazard onsite. Finally, the site is not adjacent to any
significant slopes and therefore is not subject to hazard associated with mudslides. The analysis for the
proposed new school site also applies to the existing campus site. Impacts associated with seiches, tsunamis,
or mudslides would not be significant, and no mitigation is required.
3.10 LAND USE AND PLANNING
a) Physically divide an established community?
No Impact. The project sites are on the China Lake Naval Air Weapons Station near the City of Ridgecrest.
Surrounding land uses of the proposed school site include Burroughs High School to the east, a city park and
sports complex to the south, commercial uses to the west, and vacant land to the north that are a part of the
fenced area of China Lake. Development of the new school would be compatible with the surrounding
institutional and park uses and would not divide an established community. The existing campus is
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 102 PlaceWorks
surrounded by vacant land to the east, west, and south, and commercial uses to the north; after its demolition,
the property would revert back to China Lake. No impact would occur, the project would not divide an
established community, and no mitigation measures would be required.
b) Conflict with any applicable land use plan, policy, or regulation of an agency with jurisdiction
over the project (including, but not limited to the general plan, specific plan, local coastal
program, or zoning ordinance) adopted for the purpose of avoiding or mitigating an
environmental effect?
Less Than Significant Impact. Both project sites are in the Mainsite Land Management Unit in the North
Range of China Lake, which is regulated by the Department of the Navy. The Mainsite Land Management
Unit is a buffer area between the City of Ridgecrest and mission-related parts of the base. It contains the
station headquarters, principal laboratories, and most of the administrative and support functions of the
station, and it is the largest developed area at the station. The sites are mapped as disturbed areas on the
China Lake Comprehensive Land Use Management Plan. The existing campus is designated for school use
(Fox 2013) and within the fenced perimeter of the station. The new school site is outside the fence line.
While the new school site has not been designated for school use, it is within the buffer zone and has been
identified by the Navy as an acceptable site for the relocation for the existing Murray Middle School program.
Additionally, although the new school site is not within the jurisdiction of the City of Ridgecrest and is
identified as Military use in its General Plan Map, the city’s zoning map designates the site as Urban Reserve
(UR), which is land held in reserve for future urban expansion. According to the city municipal code, the
proposed school use would be an acceptable, but conditioned use under the UR designation. Since the lead
agency for the proposed project is the District and the new school site is technically on federal property, no
substantial conflicts with the city’s land use plan and zoning designation would occur. Impacts would be less
than significant. No mitigation measures are required.
c) Conflict with any applicable habitat conservation plan or natural community conservation plan?
Less than Significant Impact with Mitigation Incorporated.
West Mojave Plan
The project sites are in the plan area of the WMP, which covers approximately 9.3 million acres of the
western portion of the Mojave Desert, including parts of Inyo, Los Angeles, Kern, and San Bernardino
counties. The WMP is an interagency Habitat Conservation Plan that is being prepared by the Bureau of
Land Management (BLM) in collaboration with federal and state agencies as well as the cities and counties in
the HCP area. China Lake is in the WMP area and is a participating agency.
The purpose of the WMP is to conserve and protect the desert tortoise (Gopherus agassizii) and nearly 100
other sensitive plant and wildlife species as well as the habitats on which these species depend, while also
providing developers of public and private projects with a streamlined program for compliance with FESA
and CESA. The WMP allows incidental take of covered species on 3.2 million acres of public lands and 2.9
million acres of private lands within the WMP area, and it would be consistent with the resource management
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 103
plans adopted by each of the region’s five military bases as well as with the Desert Tortoise Recovery Plan.
The term of the WMP is 30 years.
In 2009 the US District Court for Northern California issued a summary judgment requiring a lower court to
take further action on the off-highway vehicle route designations in the WMP. New route designations must
be made by September 2015 (Alden Environmental 2013; BLM 2015).
Land use and resource conservation policies at the new and existing school sites are established by the
commanding officer of China Lake. After implementation of Mitigation Measures BIO-1 and BIO-2, project
development would not have substantial impacts on sensitive resources protected under the WMP or
otherwise conflict with the WMP.
Desert Renewable Energy Conservation Plan
A DRECP is under preparation for over 22 million acres of the California desert, and portions of China
Lake, including the project sites, are within the DRECP area. The draft DRECP and associated EIR/EIS
were circulated for a public comment period extending from September 26, 2014, to February 23, 2015.The
proposed new school site is leased by SSUSD as a prospective school site; no renewable energy projects
subject to the DRECP are proposed onsite; and no impact would occur. No mitigation measures are required.
3.11 MINERAL RESOURCES
a) Result in the loss of availability of a known mineral resource that would be a value to the region
and the residents of the state?
No Impact. No mineral resource zones have been designated on or near the new school or existing school
sites, and the California Geological Survey has not designated an aggregate mineral resource production-
consumption zone in the Indian Wells Valley (Miller 2012). The nearest known and inferred significant
mineral resources to the new school site mapped by the California Geological Survey are near the town of
Johannesburg, about 17 miles south of the site (CGS 1999). No known mineral resources valuable to the
region and the state exist onsite. The nearest mines to the new school site mapped on the Office of Mine
Reclamation’s Mines Online website are two sand and gravel mines, the Potlatch Mine and the Bowman Mine,
both about 5 miles west of the sites (OMR 2015). Project implementation would not cause a loss of
availability of known mineral resources. No impact would occur, and no mitigation measures are required.
b) Result in the loss of availability of a locally important mineral resource recovery site delineated
on a local general plan, specific plan or other land use plan?
No Impact. No mining sites are designated in the City of Ridgecrest General Plan. The proposed new
school site is surrounded by a high school, commercial uses, and fenced premises of the station that would
preclude use of the site for mining. Demolition of the existing campus would not cause a loss of availability
of known mineral resources. Project implementation would have no impact on a mineral resource recovery
site, and no mitigation is required.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 104 PlaceWorks
3.12 NOISE
Noise is defined as unwanted sound and is known to have several adverse effects on people, including hearing
loss, speech and sleep interference, physiological responses, and annoyance. Based on these known adverse
effects of noise, the federal government, the State of California, and Kern County have established criteria to
protect public health and safety and to prevent disruption of certain human activities. Characterization of
noise and vibration, existing regulations, and calculations for construction noise and vibration levels can be
found in Appendix I to this Initial Study.
Terminology and Noise Descriptors The following are brief definitions of terminology used in this chapter:
Noise. Sound that is loud, unpleasant, unexpected, or otherwise undesirable.
Decibel (dB). A unitless measure of sound on a logarithmic scale.
A-Weighted Decibel (dBA). An overall frequency-weighted sound level in decibels that approximates
the frequency response of the human ear.
Equivalent Continuous Noise Level (Leq). The energy-average noise level over a specified
measurement period (typically one hour). The Leq metric is a single numerical value that represents the
equivalent amount of variable sound energy received by a receptor over the specified duration.
Statistical Sound Level (Ln). The statistical sound levels, or n-exceeded sound levels, are noise metrics
that represent fractional percentages of the measurement period that are exceeded for ‘n’ percent of the
time. For example, the L50 noise level represents the noise level that is exceeded 50 percent of the time
(i.e., half the time the noise level exceeds this level and half the time the noise level is less than this level).
This level is also representative of the level that is exceeded 30 minutes in an hour. Similarly, the L02, L08,
and L25 represent the noise levels that are exceeded 2, 8, and 25 percent of the time, respectively (or 1, 5,
and 15 minutes per hour). These statistical sound levels are typically used to demonstrate compliance
with a noise ordinance for stationary noise sources.
Day-Night Sound Level (Ldn or DNL). The energy-average of the A-weighted sound levels occurring
during a 24-hour period, with 10 dB added to the sound levels occurring during the period from 10:00
PM to 7:00 AM.
Community Noise Equivalent Level (CNEL). The energy average of the A-weighted sound levels
occurring during a 24-hour period with 5 dB added to the sound levels occurring during the period from
7:00 PM to 10:00 PM and 10 dB added to the sound levels occurring during the period from 10:00 PM to
7:00 AM.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 105
Note: For general community/environmental noise, CNEL and Ldn values rarely differ by more than 1 dB.
As a matter of practice, Ldn and CNEL values are considered to be equivalent/ interchangeable and are
treated as such in this assessment.
Existing Conditions The project site is on the edge of a developed area of the City of Ridgecrest and subject to noise from
transportation and stationary sources. The area currently consists of school, residential, recreational,
commercial, and medical uses.
Nearby Noise Sources
On-Road Vehicles
On-road vehicles represent the most prominent source of noise near the proposed new school site and
existing campus. The majority of traffic and resultant noise are associated with China Lake Boulevard for the
new site and Inyokern Road for the existing facility. Existing traffic noise conditions at the new school site
were modeled using the Federal Highway Administration’s (FHWA) Traffic Noise Prediction computer
model. Table 12, Existing Conditions Traffic Noise Levels (New School Site) lists the calculated existing noise levels
on roadways in the vicinity of the project site at 50 feet from the roadway centerline.
Table 12 Existing Conditions Traffic Noise Levels (New School Site)
Roadway Segment
Daily Traffic
Volumes
Noise Level at 50 Feet
(dBA CNEL)
Distance to Noise Contour (feet)
70 dBA CNEL
65 dBA CNEL
60 dBA CNEL
Drummond Ave. N Norma St. to China Lake Blvd. 8,600 67.0 31 68 146
Drummond Ave. China Lake Blvd. to French Ave. 3,800 62.0 15 32 68
Las Flores Ave. N Norma St. to China Lake Blvd. 6,200 65.1 24 51 110
Las Flores Ave. China Lake Blvd. to French Ave. 2,200 59.2 10 21 44
French Ave. N Alvord St. to China Lake Blvd. 3,000 58.6 9 19 40
French Ave. China Lake Blvd. to Las Flores Ave. 5,000 64.2 21 44 95
French Ave. Las Flores Ave to Drummond Ave. 6,000 65.0 23 50 108
Ridgecrest Blvd. N Norma St. to China Lake Blvd. 9,300 65.1 24 51 109
Ridgecrest Blvd. China Lake Blvd. to Sunland St 11,100 68.1 37 80 173
China Lake Blvd./US 395/SR 178 Ward Ave. to Drummond Ave. 14,600 67.9 36 78 167
China Lake Blvd./US 395/SR 179 Drummond Ave. to Las Flores Ave. 15,000 68.0 37 79 170
China Lake Blvd./US 395/SR 180 Las Flores Ave. to French Ave. 16,000 68.3 38 82 178
China Lake Blvd./US 395/SR 181 French Ave. to Ridgecrest Blvd. 20,400 69.3 45 97 209
China Lake Blvd./US 395/SR 182 Ridgecrest Blvd. to Upjohn Ave. 17,100 68.5 40 86 186 Source: FHWA Highway Traffic Noise Prediction Model based on traffic information found in Section 3.16, Transportation/“Traffic”. Calculations included in Appendix I.
Airports
The nearest public airport is Inyokern Airport, located approximately 9.4 miles west of the proposed new
school site. The nearest private airport is Armitage Field at the naval air weapons station, approximately 3.4
miles to the northwest. Additionally, Ridgecrest Community Hospital Heliport and Southern California
Edison Ridgecrest Service Center Heliport are approximately 0.5 miles northwest and 1.4 miles south of the
project site, respectively. Aircraft overflights are sporadically heard, but are not a substantial contributor to
community noise levels in the vicinity of the project site.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 106 PlaceWorks
Stationary-Source Noise
The existing school ground is shared with the District’s maintenance warehouse. Sound levels from bus
movements, mechanical equipment, and repair activities at the District facilities may occasionally be heard at
the existing school campus. Surrounding the existing school and maintenance facility to the east, south, and
west are vacant land. North of the school site, across Inyokern Road, is a training facility used by the Navy, as
well as Bennington Plaza, which includes a commissary, post office, barber shop, gymnasium, and theater.
Stationary-source noise from Bennington Plaza would mostly consist of vehicle-related activities in the
parking lots, along with noise from heaters, ventilation systems, pumps, compressors, and air conditioning
equipment at the commercial uses.
Stationary-source noise from commercial operations near the proposed new school site results primarily from
mechanical sources and systems, including HVAC systems, refrigeration equipment, and loading/unloading
activities, primarily from the commercial/ warehousing uses to the west. Noise from the adjacent Burroughs
High School (to the east) includes periodic outdoor student activity throughout the day, as well as drop-off
and pick-up traffic at the beginning and end of school hours.
Sensitive Receptors
Certain land uses are particularly sensitive to noise and vibration. These uses include residences, schools,
hospital facilities, houses of worship, and open space/recreation areas where quiet environments are
necessary for the enjoyment, public health, and safety of the community. Commercial and industrial uses are
not considered noise- and vibration-sensitive uses.
The nearest sensitive receptor to the new middle school location is Burroughs High School (360 feet away),
across French Avenue. Other sensitive receptors include Pierce Elementary School, residences off of La
Mirage Lane, Leroy Jackson Park, the Ridgecrest Public Library, commercial buildings to the west, Spring Hill
Suites and Hampton Inn, Ridgecrest Regional Hospital, and the buildings to the north, all of which are at
least 1,000 feet from the center of the project site.
There are no sensitive receptors in the immediate vicinity of the existing middle school facility.
Applicable Noise and Vibration Regulations
To limit population exposure to physically and/or psychologically damaging as well as intrusive noise levels,
the federal government, the State of California, various county governments, and most municipalities in the
state have established standards and ordinances to control noise.
City of Ridgecrest
Health & Safety Element, Noise Goals
The goal of the Noise section of the Health and Safety Element is to “maintain a desirable quality of life and
protect citizens’ health and welfare by reducing noise sources within the community and lessening the effects
of noise sources which cannot be avoided.” There are twenty policies included which support this goal, and a
Maximum Allowable Noise Exposure by Land Use table, which is modified from the state’s, shown in Table
13, Maximum Allowable Noise Exposure by Land Use.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 107
Table 13 Maximum Allowable Noise Exposure by Land Use1
Land Use
Noise Level (CNEL)
0-55 56-60 61-65 66-70 71-75 75-80 >81
Residential –Low Density Single-Family, Duplex, Mobile Homes
Residential – Multiple Family, Group Homes
Motels / Hotels
Schools, Libraries, Churches, Hospitals, Extended Care Facilities
Auditoriums, Concert Halls, Amphitheaters
Sports Arenas, Outdoor Spectator Sports
Playgrounds, Neighborhood Parks
Golf Courses, Riding Stables, Water Recreation, Cemeteries
Office Buildings, Business Commercial and Professional
Industrial, Manufacturing, Utilities, Agriculture
Normally Acceptable. Specified land use is satisfactory, based on the assumption than any buildings involved are of normal, conventional construction, without any special noise insulation requirements.
Conditionally Acceptable. New construction or development should be undertaken only after a detailed analysis of the noise reduction requirements is made and needed insulation features have been included in the design.
Normally Unacceptable. New construction or development should generally be discouraged. If new construction or development does proceed, a detailed analysis of the noise reduction requirements must be made and needed noise insulation features included in the design. Outdoor areas must be shielded.
Unacceptable. New construction or development should not be undertaken.
1 Table 8-1 in the Ridgecrest General Plan
Municipal Code
Aside from Section 4-15.101 of the Ridgecrest Municipal Code, which prohibits “loud or unusual noise or
vibration unreasonably disturbing, offending, injuring or annoying the normal sensibilities of occupants of
neighboring properties,” the City of Ridgecrest does not have specific (numerical) noise level limits.
Kern County
Exterior or Interior Noise
Chapter 8.36 Noise Control of the Kern County Code does not include interior or exterior noise level limits.
Construction Noise
With the exception of emergency work or work that has been exempted by the development services agency
director for a limited time, noise from construction is prohibited between the hours of 9:00 PM and 6:00 AM
on weekdays and 9:00 PM and 8:00 AM on weekends if it is audible at a distance of 150 feet from the
construction site and the site is within 1,000 feet of a residence.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 108 PlaceWorks
Vibration Standards
Section 4-15.101 of the Ridgecrest Municipal Code prohibits “Loud or unusual noise or vibration
unreasonably disturbing, offending, injuring or annoying the normal sensibilities of occupants of neighboring
properties.” Kern County does not specify any vibration standards in its County Code or General Plan. For
the purpose of this analysis, criteria set by the Federal Transit Administration will be utilized to evaluate
potential vibration impacts.
Based on the FTA Noise and Vibration Impact Guidelines (FTA 2006), an impact would occur if
construction activities would generate vibration that is strong enough to cause vibration-induced architectural
damage to existing residences. The threshold for vibration-induced architectural damage is 0.2 peak particle
velocity (PPV) in inches per second (in/sec) for typical wood-framed buildings. The threshold for human
annoyance is 0.1 PPV in/sec for sensitive receptors.
Would the project:
a) Result in exposure of persons to or generation of noise levels in excess of standards established
in the local general plan or noise ordinance, or applicable standards of other agencies?
Less Than Significant Impact. This section includes a discussion of potential noise impacts from project-
related traffic and stationary source noise, and evaluates impacts to the project in terms of land use and noise
compatibility.
Project-Related Traffic Noise
To determine if a project would cause a substantial noise increase from project-related traffic, consideration
must be given to the magnitude of the increase at the potentially affected receptors. In general, for
community noise, a noise level increase of 3 dBA is considered barely perceptible, while an increase of 5 dBA
is considered clearly noticeable. For conservatism, an increase of 3 dBA is often used as a threshold for a
substantial increase. A significant noise impact is determined when noise-sensitive receptors along a roadway
segment are subject to three conditions: (1) exposed to ambient noise levels over the 60 dBA CNEL
residential standard (for the “normally acceptable” category), (2) experience a cumulative noise increase
(future minus existing) over 3 dBA, and (3) the project contribution is 1 dBA or more.
The closing of the existing Murray Middle School campus would reduce the number of daily vehicle trips in
the vicinity of the existing campus, resulting in a decrease in traffic-related noise levels. Therefore, closure of
the existing campus would result in a decrease in traffic-related noise along Inyokern Road and other nearby
roadways that service the existing school facility and, as a result, there would be no impacts due to traffic
noise.
Per the project’s traffic study, the middle school would redirect approximately 1,610 daily vehicle trips from
the existing school location to roadway segments around the project site. Most of this traffic would occur in
the morning when school begins and in the afternoon when it ends.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 109
To assess the project’s potential contribution to ambient noise along road segments that may be affected by
project-generated traffic, the FHWA Highway Traffic Noise Prediction Model (RD-77-108) was used to
calculate roadway-related noise levels for pertinent scenarios associated with the new campus. The daily traffic
noise averaged over a 24-hour period was calculated at 50 feet from the study-area roadway segments for
existing and future (i.e., when the new school is proposed to open) time frames; with and without the project.
The noise level modeling results for the existing and existing-plus-project scenario are shown in Table 14,
Project Offsite Contributions, Existing Conditions. The table presents the noise level contours for selected study
area segments. The pertinent details of all the noise prediction model calculations are included in Appendix I.
Table 14 Project Offsite Contributions, Existing Conditions
Roadway Segment
CNEL at 50 feet (dBA)
Existing, No Project
Existing, Plus Project
Project Contribution
Potential Impact?
Drummond Ave. N Norma Street to China Lake Blvd. 67.0 67.2 0.2 no
Drummond Ave. China Lake Blvd. to French Ave. 62.0 62.9 0.9 no
Las Flores Ave. N Norma Street to China Lake Blvd. 65.1 65.2 0.1 no
Las Flores Ave. China Lake Blvd. to French Ave. 59.2 59.3 0.1 no
French Ave. N Alvord Street to China Lake Blvd. 58.6 58.7 0.1 no
French Ave. China Lake Blvd. to Las Flores Ave. 64.2 64.8 0.6 no
French Ave. Las Flores Ave. to Drummond Ave. 65.0 65.5 0.5 no
Ridgecrest Blvd. N Norma Street to China Lake Blvd. 65.1 65.1 0.0 no
Ridgecrest Blvd. China Lake Blvd. to Sunland St 68.1 68.2 0.1 no
China Lake Blvd./US 395/SR 178 Ward Ave. to Drummond Ave. 67.9 68.0 0.1 no
China Lake Blvd./US 395/SR 179 Drummond Ave. to Las Flores Ave. 68.0 68.0 0.0 no
China Lake Blvd./US 395/SR 180 Las Flores Ave. to French Ave. 68.3 68.3 0.0 no
China Lake Blvd./US 395/SR 181 French Ave. to Ridgecrest Blvd. 69.3 69.4 0.1 no
China Lake Blvd./US 395/SR 182 Ridgecrest Blvd. to Upjohn Ave. 68.5 68.6 0.1 no
Source: FHWA Highway Traffic Noise Prediction Model by PlaceWorks; based on traffic information found in Section 3.16, Transportation/“Traffic”.
As shown in Table 14, in no case would project-generated traffic result in a 3 dB increase in ambient noise
associated with vehicle traffic. In fact, the maximum project contribution is 0.9 dBA. Thus, impacts to the
existing environment from the project would be less than significant.
The noise level modeling results for the overall increases and project contributions are shown in Table 15,
Overall Project Offsite Contributions.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 110 PlaceWorks
Table 15 Overall Project Offsite Contributions
Roadway Segment
CNEL at 50 feet (dBA)
Existing
2017 With
Project
Overall, Cumulative
Increase Project
Contribution Potential Impact?
Drummond Ave. N Norma St. to China Lake Blvd. 67.0 67.5 0.5 0.2 no
Drummond Ave. China Lake Blvd. to French Ave. 62.0 63.1 1.1 0.9 no
Las Flores Ave. N Norma St. to China Lake Blvd. 65.1 65.4 0.2 0.1 no
Las Flores Ave. China Lake Blvd. to French Ave. 59.2 59.5 0.2 0.1 no
French Ave. N Alvord St. to China Lake Blvd. 58.6 58.8 0.2 0.1 no
French Ave. China Lake Blvd. to Las Flores Ave.
64.2 64.9 0.7 0.6 no
French Ave. Las Flores Ave. to Drummond Ave.
65.0 65.6 0.6 0.5 no
Ridgecrest Blvd. N Norma St. to China Lake Blvd. 65.1 66.1 1.0 0.0 no
Ridgecrest Blvd. China Lake Blvd. to Sunland St 68.1 68.7 0.6 0.1 no
China Lake Blvd./US 395/SR 178 Ward Ave. to Drummond Ave. 67.9 68.6 0.8 0.1 no
China Lake Blvd./US 395/SR 179 Drummond Ave. to Las Flores Ave.
68.0 68.6 0.7 0.0 no
China Lake Blvd./US 395/SR 180 Las Flores Ave. to French Ave. 68.3 68.9 0.6 0.0 no
China Lake Blvd./US 395/SR 181 French Ave. to Ridgecrest Blvd. 69.3 70.0 0.7 0.1 no
China Lake Blvd./US 395/SR 182 Ridgecrest Blvd. to Upjohn Ave. 68.5 69.2 0.7 0.1 no
Source: FHWA Highway Traffic Noise Prediction Model by PlaceWorks; based on traffic information found in Section 3.16, Transportation/“Traffic”.
As shown in Table 15, the overall traffic noise increase (2017 with Project minus Existing) along the study
area segments ranges from 0.2 to 1.1 dBA, and the project contribution would be no more than 0.9 dBA.
Since the cumulative increases for all segments would be well below the 3 dBA noise increase threshold and
project contributions for all segments would be below the 1 dBA project-related noise increase threshold,
changes in traffic noise due to implementation of the project would not result in significant long-term,
traffic-related noise impacts to offsite uses. Thus, impacts to the future environment from the project would
be less than significant.
Although there would be greater short-term increases in traffic noise when cars arrive and depart at the
beginning and end of the school day, this would be limited to relatively short periods in the morning and
afternoon, during less sensitive portions of the day. Additionally, with the exception of Burroughs High
School (which would also have drop-off and pick-up activities at roughly the same times of day as the
project), there are no sensitive receptors within 1,000 feet of the project. Potential noise impacts from
project-related vehicle activity would be less than significant.
In summary, with implementation of the project, changes in traffic noise would be less than significant. No
mitigation would be required.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 111
Stationary-Source Noise
The closing of the existing Murray Middle School campus would eliminate stationary sources of noise
currently associated with its use, including noise from students, HVAC, and landscape maintenance.
Therefore, closure of the existing campus would result in no impacts due to stationary noise.
The nearest sensitive receptor to the new middle school location is Burroughs High School (360 feet away),
across French Avenue. Other sensitive receptors include Pierce Elementary School, residences off of La
Mirage Lane, Leroy Jackson Park, the Ridgecrest Public Library, commercial buildings to the west, Spring Hill
Suites and Hampton Inn, Ridgecrest Regional Hospital, and the buildings to the north, all of which are at
least 1,000 feet from the center of the proposed project site. Stationary noise may occur with operation new
mechanical equipment, such as HVAC equipment, at the proposed school site. Occasionally, delivery and
haul-off trucks (such as garbage trucks) would also enter and leave the site. In addition, onsite noise may be
generated by classroom bells, student conversations during recess/break periods, physical education athletic
activities at the campus playfields, and periodic landscaping maintenance activities.
The new drop-off areas and the classrooms would be at least 1,200 feet and 1,800 feet, respectively, from the
nearest residential homes off La Mirage Lane. Due to distance attenuation and because traffic flows on
French Avenue and Drummond Avenue would generally overshadow noise from stationary sources and other
campus activities at the project site, noise from the onsite school activities would not result in substantial
noise impacts during the daytime hours at noise-sensitive uses in the vicinity of the project.
Additionally, the outdoor playfields at the proposed campus would be at least 1,700 feet from the nearest
residential homes across off La Mirage Lane. While physical education and/or other athletic activities at the
campus playfields may sporadically be audible at nearby, offsite locations, these project-related sounds are not
expected to notably increase the daytime community noise environment. Moreover, the use of outdoor
playfields at the middle school would only occur for two to three hours at a time and would be during the
middle of the day (when nearby sensitive receptors would be least likely to be at home). There would be no
playfield activities in the evenings (i.e., after dusk), as no field lighting is proposed for the middle school.
Impacts associated with playfields use at the proposed middle school would not result in significant impacts
related to noise.
Noise Compatibility
The Noise Element of the City of Ridgecrest’s General Plan provides objectives, policies, and
implementation programs that are intended to achieve and maintain land use compatibility with
environmental noise levels and to ensure that city residents will be protected from excessive noise intrusion,
both now and in the future.
The noise standards specified in the Noise Element of the City of Ridgecrest General Plan are a guideline to
evaluate the acceptability of the noise levels generated by vehicular traffic. These standards are used for
assessment of long-term traffic-related noise impacts on land uses.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 112 PlaceWorks
The Noise Element also establishes the noise/land use compatibility criteria to be used in determining
whether a new use is appropriate within a given noise environment. As shown in Table 13, school classrooms
are considered to be normally acceptable in environments with exterior noise levels that reach up to 60 dBA
CNEL and conditionally acceptable in environments where exterior noise levels reach up to 70 dBA CNEL.
New school construction in areas where exterior noise levels range between 60 and70 dBA CNEL should be
undertaken only after detailed analysis of the noise reduction requirements are made and needed noise
insulation features in the design are determined. Conventional construction—which would typically provide
an interior noise reduction of 20 to 25 dBA with closed windows and fresh air supply systems or air
conditioning—will normally suffice to provide adequate noise insulation characteristics.
Neither the City of Ridgecrest Municipal Code nor the Kern County Code have numerical exterior or interior
noise level standards. The state interior noise level standard of 45 dBA CNEL for classrooms will be used for
purposes of this evaluation.
The closing of the existing Murray Middle School campus would result in the removal of sensitive uses, and
noise levels would decrease in the vicinity of the existing campus. Therefore, closure of the existing campus
would result in no impacts due to noise compatibility.
Based on future with-project traffic noise level contour calculations, classrooms at the new school site will be
located in areas with noise levels below 60 dBA CNEL. Normal building construction will be sufficient to
reduce interior noise levels to 45 dBA CNEL or below. Impacts due to noise compatibility are less than
significant at the project site. and no mitigation is necessary.
b) Result in exposure of persons to or generation of excessive groundborne vibration or
groundborne noise levels?
Less Than Significant Impact.
Operations Vibration (new site only)
Operation of the project would not include any notable sources of vibrational energy and, thus, would not
generate substantial levels of vibration. Therefore, operations of the proposed project would not result in
significant groundborne vibration, and no mitigation measures are needed.
Construction Vibration
Construction activities can possibly generate varying degrees of ground vibration, depending on the
construction procedures, construction equipment used, and proximity to vibration-sensitive uses. Operation
of construction equipment generates vibrations that spread through the ground and diminish in amplitude
with distance.
Table 16, Typical Vibration Levels Produced by Common Construction Equipment Items, shows the peak particle
velocities (PPV) of some common construction equipment and (loaded) haul trucks.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 113
Table 16 Vibration Levels Produced by Common Construction Equipment
Equipment
Peak Particle Velocity in inches per second
at 25 ft. at 50 ft. at 150 ft.
Vibratory Roller 0.210 0.074 0.014
Large Bulldozer 0.089 0.031 0.006
Loaded Trucks 0.076 0.027 0.005
Jackhammer 0.035 0.012 0.002
Small Bulldozer 0.003 0.001 0.000
Source: Federal Transit Administration: Transit Noise and Vibration Impact Assessment, 2006.
Vibration-inducing construction equipment typically used at development projects could include bulldozers,
jackhammers, and haul trucks. Construction equipment would be limited to relatively small equipment items,
such as forklifts, delivery/dump trucks, loaders/backhoes, rubber-tired dozers, a grader, scrapers, excavators,
a paver, rollers, concrete saws, and a crane, which do not generate substantial levels of vibration.
The existing school facilities would be demolished following the transfer of students to the new campus site.
The project would construct new classroom and administration buildings, football and baseball fields, hard
courts, parking lots, and parent and bus drop-off areas at the proposed (new) site. For purposes of this
analysis and to consider worst-case conditions, the construction of the new school will require soil
remediation, which has been assumed to involve the removal and replacement of 20,077 cubic yards of soil.
Other construction phases would center on trenching for utilities, the erection of buildings, the installation of
hardscape (such as parking lots), and the installation of softscape facilities (such as athletic fields).
Construction activities would start as early as October 2015 and would take approximately 20 months.
Architectural Damage due to Vibration
Building damage is not a factor for normal projects, with the occasional exception of blasting and pile driving
during construction (FTA 2006). The threshold at which there is a risk of architectural damage to typical
wood-framed buildings is 0.2 in/sec (FTA 2006). No blasting, pile driving, or hard rock ripping/crushing
activities are anticipated to be required for the development. Relatively small construction equipment
generates vibration levels less than 0.1 PPV in/sec at 25 feet away.
There are no vibration-sensitive uses within approximately 500 feet of the existing middle school facilities.
Due to the large distances between the closest buildings and the demolition site, the maximum construction-
related vibration levels would be well below the 0.2 PPV in/sec criteria for vibration-induced architectural
damage at nearby sensitive structures.
The nearest offsite structures to construction activities at the new school site are the commercial buildings to
the west (270 feet from the edge of construction) and Burroughs High School (360 feet away). Additionally,
houses along Sahara Drive and Bonita Street are approximately 1100 feet to the south of the project site
boundary. As with the existing facility, given the large distances between the closest buildings and the project
site, the maximum construction-related vibration levels would be well below the 0.2 PPV in/sec criteria for
vibration-induced architectural damage at the nearest structures.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 114 PlaceWorks
Therefore, architectural-damage vibration impacts from construction at both the existing facility and at the
project site would be less than significant, and no mitigation measures are necessary.
Vibration Annoyance
The effect of groundborne vibration on buildings near a construction site varies depending on soil type,
ground strata, and receptor building construction. The generation of vibration can range from no perceptible
effects at the lowest vibration levels, to low rumbling sounds and perceptible vibrations at moderate levels, to
slight damage at the highest levels. Vibration is typically noticed nearby when objects in a building generate
noise from rattling windows or picture frames. It is typically not perceptible outdoors and, therefore, impacts
are based on the distance to the nearest building (FTA 2006). For human annoyance, the criteria of 0.1 PPV
in/sec is the level at which continuous vibration begins to annoy people. Small construction equipment
generates vibration levels less than 0.1 PPV in/sec at 25 feet away.
There are no vibration-sensitive uses within approximately 500 feet of the existing middle school facilities.
Due to the large distances between the closest buildings and the demolition site, the maximum construction-
related vibration levels would be well below the 0.1 PPV in/sec criteria for vibration-induced annoyance at
nearby sensitive structures.
For the project site, the Burroughs High School buildings are approximately 725 feet away from the center of
construction activity. Since vibration dissipates quickly with distance, the maximum construction-related
vibration level would be much less than 0.1 PPV in/sec at the high school classrooms and would be well
below the criteria for vibration-induced annoyance. Therefore, construction vibration impacts related to
annoyance would be less than significant.
Therefore, vibration annoyance impacts from construction at both the existing facility and at the project site
would be less than significant and no mitigation measures are necessary.
Vibration Summary
In summary, both construction and operational activities would not create substantial groundborne vibration
or groundborne noise. This impact would be less than significant and no mitigation measures are needed.
c) Result in a substantial permanent increase in ambient noise levels in the project vicinity above
levels existing without the project?
Less Than Significant Impact.
The proposed new school’s offsite traffic noise level increases and onsite stationary-source noise level
increases are addressed in the response to question a) above.
Per that previous discussion and assessment, there would be no substantial permanent noise level increases
and such impacts would be less than significant. No mitigation would be required.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 115
d) Result in a substantial temporary or periodic increase in ambient noise levels in the project
vicinity above levels existing without the project?
Less Than Significant Impact. Temporary noise would be generated during construction activities. In
typical construction projects, demolition and grading activities usually generate the highest noise levels since
these activities typically involve the largest construction equipment.
Project construction would require demolition at the existing school site, as well as asphalt demolition, site
preparation, rough grading, utility trenching, building construction, fine grading, paving, and
finishing/landscaping at the new school site. In general, construction equipment for the project (at both sites)
would be limited to relatively small equipment such as forklifts, delivery/dump trucks, loaders/backhoes,
rubber-tired dozers, a grader, scrapers, excavators, a paver, rollers, concrete saws, and a crane. The total
duration for school construction would be approximately 20 months.
As shown in Table 17, Typical Construction Equipment Noise Level, operational noise levels associated with most
construction equipment range between 80 and 88 dBA at 50 feet. Construction equipment typically moves
from one location on the site to another during each phase and does so with varying power levels.
Table 17 Typical Construction Equipment Noise Level
Type of Equipment Range of Maximum Sound Levels Measured
(dBA at 50 ft.) Suggested Maximum Sound Levels for Analysis
(dBA at 50 ft.)
Jack Hammers 75–85 82
Pneumatic Tools 78–88 85
Pumps 74–84 80
Dozers 77–90 85
Scrapers 83–91 87
Haul Trucks 83–94 88
Cranes 79–86 82
Portable Generators 71–87 80
Rollers 75–82 80
Tractors 77–82 80
Front-End Loaders 77–90 86
Hydraulic Backhoe 81–90 86
Hydraulic Excavators 81–90 86
Graders 79–89 86
Air Compressors 76–89 86
Trucks 81–87 86
Source: Bolt, Beranek & Newman; Noise Control for Buildings and Manufacturing Plants, 1987.
Given the distances to nearby receptor locations, construction equipment items can be analyzed as localized
point sources. Noise from such localized point sources decreases by approximately 6 dB with each doubling
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 116 PlaceWorks
of distance from the source to any given receptor. Thus, noise from a particular equipment item that
produced a sound level of 86 dBA at 50 feet would be expected to have a sound level of 80 dBA at 100 feet,
74 dBA at 200 feet, 68 dBA at 400 feet, 62 dBA at 800 feet, 56 dBA at 1,600 feet, and so forth.
Implementation of the project would involve demolition of the school’s existing buildings at 921 East
Inyokern Road, which would last approximately one month. Due to the short duration of the activities, the
lack of noise-sensitive receptors in the immediate vicinity, and since activities would occur during the least
noise-sensitive portion of the day, demolition noise at the existing location would be less than significant.
At the new school site, the loudest phases of construction activity—site preparation and rough grading—
would reach levels of 64 to 65 dBA Leq at Burroughs High School, the nearest sensitive receptor, and could
reach maximum levels of 68 dBA Lmax (calculations included in Appendix I). After exterior-to-interior noise
reduction (which is typically from 20 to 25 dB), these levels would not be loud enough to disrupt classroom
activities at the high school.
Other nearby sensitive receptors include Pierce Elementary School, residences off of La Mirage Lane, Leroy
Jackson Park, the Ridgecrest Public Library, commercial buildings to the west, Spring Hill Suites and
Hampton Inn, Ridgecrest Regional Hospital, and the buildings to the north; all of which are at least 1,000
feet from the center of construction activities.
Construction of the new school will require soil remediation, which has been assumed to involve the removal
and replacement of 20,077 cubic yards of soil, for a worst-case analysis. The project would construct new
classroom and administration buildings, football and baseball fields, hard courts, parking lots, and parent and
bus drop-off areas.
According to the Kern County Code, construction is prohibited between the hours of 9:00 PM and 6:00 AM
on weekdays and 9:00 PM and 8:00 AM on weekends if it is audible at a distance of 150 feet from the
construction site and the site is within 1,000 feet of a residence. While the implementation of the project
would result in a temporary increase in ambient noise resulting from the use of construction equipment,
these potentially audible increases would be beyond the 1,000 foot threshold for residential land uses. With
distance attenuation, the construction noise levels would not be expected to markedly effect the general
community noise environment (particularly in comparison to much-closer traffic flows). Additionally, any
increase in noise levels would cease upon completion of construction.
Since receptors would experience average exterior noise levels of less than 60 dBA Leq, since construction
activities would occur during the least noise-sensitive portion of the day, and since construction activities
would be short-term, noise impacts due to construction would be less than significant, and no mitigation
measures would be necessary.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 117
e) For a project located within an airport land use plan or, where such a plan has not been adopted,
within two miles of a public airport or public-use airport, would the project expose people
residing or working in the area to excessive noise levels?
No Impact. There are no public-use airports within two miles of the project site. The nearest public airport
to both project sites is Inyokern Airport. Aircraft overflights are sporadically heard, but do not cause a
substantial noise impact in the vicinity of the project site.
The proposed project would relocate the existing middle school program from its current location, which is
only 1.3 miles away from Inyokern Airport to the new site, approximately 9.4 miles to the west (AirNav,
Google-Earth 2015).
At this increased distance from the airport, the project would reduce the contribution of aircraft noise to
school children and faculty attending Murray Middle School. Therefore, the project would have a beneficial
impact as it relates to noise associated with airport operations, and no impact would occur. No mitigation is
required.
f) For a project within the vicinity of a private airstrip, would the project expose people residing or
working in the project area to excessive noise levels?
No Impact. Ridgecrest Community Hospital Heliport and Southern California Edison Ridgecrest Service
Center Heliport are approximately 0.5 miles northwest and 1.4 miles south of the project site, respectively
(AirNav, Google-Earth 2015). However, operations at these heliports are sporadic and would not generate
substantial amounts of noise to users in the project area.
Besides these private heliports, the nearest private airport is Armitage Field at the Naval Air Weapons Station-
China Lake. Aircraft overflights from Armitage Field are sporadically heard, but do not cause a substantial
noise impact in the vicinity of the existing or proposed project sites. The project would relocate the middle
school from its current location to the new school campus site, both of which are approximately the same
distance from Armitage Field (i.e., approximately 3.4 miles, per AirNav and Google-Earth 2015). Thus, there
would be effectively no change to aircraft noise exposure from operations at this military airport. No impact
would occur and no mitigation is required.
3.13 POPULATION AND HOUSING
a) Induce substantial population growth in an area, either directly (for example, by proposing new
homes and businesses) or indirectly (for example, through extension of roads or other
infrastructure)?
Less Than Significant Impact. Population growth is typically related to the development of new residential
uses and employment opportunities. The proposed project would not induce population growth in the
project area, nor would it create the need for additional housing. The project involves the construction of
new school facilities to relocate Murray Middle School outside of the fenced area of China Lake. The new
school would have a capacity of 896 seats, similar to the existing campus. Its operation would not attract
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 118 PlaceWorks
growth to the area or region, but accommodate the existing demand. Construction of the new school and
demolition of the existing school, however, would generate a small number of temporary construction jobs.
Because the unemployment rate in Kern County in December 2014 was estimated as 9.9 percent by the state
(EDD 2014), it is likely that construction employment would be absorbed from the existing labor force rather
than attracting new workers into the region. Therefore, impacts would be less than significant, and no
mitigation is needed.
b) Displace substantial numbers of existing housing, necessitating the construction of replacement
housing elsewhere?
No Impact. The proposed school site and existing campus site do not currently contain any residences or
housing units; project development would not require construction of replacement housing. No impact
would occur, and no mitigation measures are necessary.
c) Displace substantial numbers of people, necessitating the construction of replacement housing
elsewhere?
No Impact. There are no residents on the proposed or existing school sites, and the project would not
require construction of replacement housing. No impact would occur, and no mitigation is required.
3.14 PUBLIC SERVICES
Would the project result in substantial adverse physical impacts associated with the provision of new or
physically altered governmental facilities, need for new or physically altered governmental facilities, the
construction of which could cause significant environmental impacts, in order to maintain acceptable service
ratios, response times or other performance objectives for any of the public services:
a) Fire protection?
Less Than Significant Impact. Because the existing Murray Middle School is within the fenced perimeters
of China Lake, fire protection and emergency medical services are currently provided by the China Lake
Federal Fire Department (CLFD). With the proposed relocation of the campus to outside the station’s fenced
area, fire and emergency protection services would instead be provided by the Kern County Fire Department
(KCFD). KCFD’s closest fire station to the proposed new school site is Fire Station 74 at 139 East Las Flores
Road, approximately 0.3 mile south of the new site. While Fire Station 74 would be the primary responder to
the new school site in the event of an emergency,9 the KCFD has a mutual aid agreement with CLFD, and
CLFD would provide assistance in the event of an emergency exceeding what KCFD could handle. Although
the proposed project would not increase enrollment at Murray Middle School, placement of the new facility
outside the fenced station perimeter would require a new agency to provide the service. According to the
KCFD, the existing fire protection facilities would be able to serve the new school facility, and with the naval
station less than one-half mile from the new school site and the CLFD mutual aid agreement, the proposed
project would not generate a need for a new fire station or expansion of the existing one. Demolition of the
9 KCFD operates a second fire station in Ridgecrest—Station 77 at 815 West Dolphin Avenue, about 2.6 miles southwest of the project site.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 119
existing school, like construction of the proposed school, would create a very slight short-term increase in
potential demands for emergency medical services. Considering the existing KCFD and CLFD firefighting
resources in the region, the short-term demolition activities would not create a need for a new fire station
either. The proposed project would result in no significant impacts to fire protection services, and no
mitigation is required.
b) Police protection?
Less Than Significant Impact. Police protection services at the existing Murray Middle School campus are
currently provided by the China Lake Police Department. With the proposed relocation of the program to a
site outside of the fenced station perimeter, law enforcement services would be transitioned to the City of
Ridgecrest Police Department at 100 West California Avenue, which is approximately 1.5 miles southwest of
the project site. The Ridgecrest Police Department provides police protection services to other District
schools outside the station and would be able to handle the additional services required by the new school.
Construction of the new school facility and demolition of the existing campus would not be substantial and
would not create a need for increased police protection services that could necessitate the expansion of
existing or construction of new police facilities. Impacts would be less than significant, and no mitigation is
required.
c) Schools?
No Impact. School service needs are usually related to residential population. The project would not increase
population and would therefore not increase the demand for schools. However, the relocation of the existing
Murray Middle School would have beneficial impacts on school services and facilities, because physical access
to the campus would be improved, and the new facilities would be an improvement over existing facilities. No
impact would occur, and no mitigation measures are required.
d) Parks?
No Impact. Increases in demands for park facilities are generally caused by population increases, which in
turn result from new development of residential and job-generating land uses. The new middle school facility
would not result in the development of new residential or job-generating land uses that would create a
demand for park facilities. Additionally, project students would not be required to use off-campus recreational
facilities. The proposed campus would include recreational facilities that would be available during normal
school hours, as well as to the public under the Civic Center Act when not used by the school, District, or
DOD. Overall, the proposed project would have a beneficial impact on park facilities. No impact would
occur, and no mitigation measures are necessary.
e) Other public facilities?
No Impact. The proposed project is the reconstruction of an existing public school on a new site.
Operation of the project would be similar to existing conditions and would not result in adverse physical
impacts associated with the provision of new or physically altered facilities to maintain acceptable service
ratios for any public service. No new or altered government facilities would be required. Demolition of the
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 120 PlaceWorks
existing campus would have no impact on other public facilities, including libraries. The proposed project
would have no impact, and no mitigation is required.
3.15 RECREATION
a) Would the project increase the use of existing neighborhood and regional parks or other
recreational facilities, such that substantial physical deterioration of the facility would occur or
be accelerated?
No Impact. The proposed project would include athletic facilities consisting of a track and field, a ball field,
and hardcourts. These facilities would be available for use during school operations and would also be
available for community use pursuant to the Civic Center Act when not used by the school, District, or DOD.
The project would not require students to use offsite parks or recreational facilities, including Leroy Jackson
Park Sports Complex, which is the closest park to the new school site. Athletic facilities on the existing
campus that would be demolished would be replaced by facilities at the rebuilt school. No adverse impact
would occur, and no mitigation measures are necessary.
b) Does the project include recreational facilities or require the construction or expansion of
recreational facilities, which might have an adverse physical effect on the environment?
No Impact. The proposed project would not result in population growth, necessitating the construction of
offsite recreational facilities. The project would result in the reconstruction of recreational facilities and
structures in the place of facilities at the existing Murray Middle School campus. The environmental effects
associated with the construction of these facilities are examined throughout this document. After
implementation of the mitigation measures identified in this document, construction of proposed
recreational facilities would not have significant adverse physical effects on the environment. Demolition of
the existing school would not require construction of new or expanded recreational facilities. No additional
impact would occur, and no additional mitigation measures are necessary.
3.16 TRANSPORTATION/TRAFFIC
a) Conflict with an applicable plan, ordinance or policy establishing measures of effectiveness for
the performance of the circulation system, taking into account all modes of transportation
including mass transit and non-motorized travel and relevant components of the circulation
system, including but not limited to intersections, streets, highways and freeways, pedestrian
and bicycle paths, and mass transit?
Less Than Significant Impact. This analysis has been prepared to determine potential traffic impacts from
construction and operation of the new Murray Middle School campus. The following describes the
circulation network in the vicinity of the new school site, estimates project-related trips with foreseeable
cumulative projects in the study area, calculates intersection levels of service (LOS), and evaluates potential
traffic impacts related to the operation of the new school site combined with ambient growth and cumulative
projects.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 121
Existing Conditions
Study area roadways and intersections are shown on Figure 18, Existing Circulation Network and Lane
Configurations. The following describes the study area roadways and intersections.
Roadways
Drummond Avenue is a four-lane, east-west street that abuts the south side of the school site. It is classified
as an arterial roadway in the City of Ridgecrest General Plan. Vehicular access to school, and student drop-
off and pick-up area would be provided by a one-way loop driveway off Drummond Avenue. The speed limit
on Drummond Avenue is 35 miles per hour (mph) east of China Lake Boulevard, which is the segment that
runs adjacent to the school site, and 40 mph west of China Lake Boulevard.
Knox Avenue is a four-lane roadway that abuts the east side of the school site. It runs between the proposed
middle school site and the existing Burroughs High School campus. A bus drop-off area and a service area
driveway would be provided on Knox Avenue. Knox Avenue is a north-south roadway in the immediate
vicinity of the project site. It continues south of the school site as French Avenue, curving in a westerly
direction and becoming an east-west roadway. Knox Avenue is classified as a collector/local road; French
Avenue is classified as a secondary road between the school site and China Lake Boulevard and as a
collector/local road west of China Lake Boulevard. The speed limit on French Avenue is 40 mph between
the school site and China Lake Boulevard and 25 mph west of China Lake Boulevard.
China Lake Boulevard/US 395 (Business) is a four-lane, north-south roadway located approximately one-
half mile west of the school site. It is classified as a state highway north of Ridgecrest Boulevard and as an
arterial roadway south of Ridgecrest Boulevard. It is designated as State Highway 178 north of Ridgecrest
Boulevard and as US 395 (Business) throughout the study area. The speed limit on China Lake Boulevard is
35 mph.
Las Flores Avenue is a four-lane, east-west street located approximately one-half mile south of the school
site. It is classified as a secondary road west of China Lake Boulevard and as a collector/local road east of
China Lake Boulevard. The speed limit on Las Flores Avenue is 35 mph east of China Lake Boulevard and 40
mph west of China Lake Boulevard.
Ridgecrest Boulevard is a two- to four-lane east-west street located approximately one mile south of the
school site. It has two lanes west of China Lake Boulevard and four lanes east of China Lake Boulevard. It is
classified as an arterial road west of China Lake Boulevard and as a state highway east of China Lake
Boulevard (State Highway 178). The speed limit on Ridgecrest Boulevard is 40 mph east of China Lake
Boulevard and 25 mph west of China Lake Boulevard.
Intersections
Six intersections were analyzed and are described in Table 18. As shown, the study area intersections are
under Caltrans and City of Ridgecrest jurisdictions.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 122 PlaceWorks
Existing Traffic Volumes
Manual traffic counts were taken at the study area intersections when school was in session, during the
morning peak period from 7 to 9 AM. The one-hour interval of peak traffic flow within the two-hour
monitoring period was identified for each intersection for the morning peak hour. Only the morning peak
hour is addressed because the school would not typically impact the late afternoon commuter peak period.
The school-generated traffic at the beginning of the school day would coincide with the morning commuter
peak hour, which has been evaluated in this study. The school traffic at the end of the school day would,
however, occur during the early afternoon generally between 2 and 3 PM when traffic volumes on the study
area roadways are lower. The school would not typically have an impact on the late afternoon commuter peak
hour, which occurs generally from 5 to 6 PM. The afternoon peak hour has not, therefore, been evaluated in
detail.
Intersection Operations
Roadway capacity is generally limited by the ability to move vehicles through intersections. An LOS is a
standard performance measurement to describe the operating characteristics of a street system in terms of
the level of congestion or delay experienced by motorists. Service levels range from A through F, which relate
to traffic conditions from best (uncongested, free-flowing conditions) to worst (total breakdown with stop-
and-go operation). The methodology used to assess the operation of a signalized intersection is based on the
Highway Capacity Manual (HCM). The intersection LOS analysis is based on the traffic volumes observed
during peak hour conditions. The peak hours selected for analysis are the highest volumes that occur in four
consecutive 15-minute periods from 7 to 9 AM on weekdays. Per the HCM methodology, overall average
intersection delay at signalized intersections was calculated, and the worst-case approach delay was calculated
at unsignalized intersections. The level of service corresponds to the delay calculated. Table 19, Relationship
Between Delay Values and Levels of Service, describes the level of service concept and the operating conditions
expected under each level of service for signalized and unsignalized intersections.
Table 18 Study Area Intersections Traffic Controls and Jurisdictions Intersection Traffic Control Jurisdiction
Signalized Intersections
Knox Avenue/Drummond Avenue Traffic Signal City of Ridgecrest
China Lake Boulevard/Drummond Avenue Traffic Signal Caltrans
China Lake Boulevard/Las Flores Avenue Traffic Signal Caltrans
China Lake Boulevard/French Avenue Traffic Signal Caltrans
China Lake Boulevard/Ridgecrest Boulevard
Traffic Signal Caltrans
Unsignalized Intersection
French Avenue/Las Flores Avenue Cross-Street Stop City of Ridgecrest
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 123
Table 19 Relationship Between Delay Values and Levels of Service
Level of Service
Delay Value (seconds per vehicle)
Unsignalized Intersections Unsignalized Intersections
A 0.0 to 10.0 0.0 to 10.0
B > 10.0 to 20.0 > 10.0 to 15.0
C > 20.0 to 35.0 > 15.0 to 25.0
D > 35.0 to 55.0 > 25.0 to 35.0
E > 55.0 to 80.0 > 35.0 to 50.0
F > 80.0 > 50.0
Source: HCM 2010.
Existing traffic conditions at study area intersections were analyzed to determine their operating conditions
during the morning peak hour. Based on the peak hour traffic volumes, the turning movement counts, and
the existing number of lanes at each intersection, the average vehicle delay values at the six intersections in
the study area were calculated, and the corresponding LOS were determined at each intersection. The
software Synchro Version 9 was used to determine the LOS at the study area intersections. The 2000
Highway Capacity Manual (HCM 2000) intersection methodology presents LOS in terms of control delay (in
seconds per vehicle). Table 20, Existing Conditions Intersection Levels of Service, indicates that five of the study
area intersections currently operate at LOS B and one intersection operates at LOS C during the morning
peak hour. According to City of Ridgecrest and Caltrans criteria, LOS C is considered acceptable for
intersection operations. Therefore, no intersections currently operate at unacceptable LOS.
Table 20 Existing Conditions Intersection Levels of Service Intersection Delay, seconds Level of Service
Signalized Intersections
Knox Avenue/Drummond Avenue 16.8 B
China Lake Boulevard/Drummond Avenue 22.0 C
China Lake Boulevard/Las Flores Avenue 16.0 C
China Lake Boulevard/French Avenue 20.2 C
China Lake Boulevard/Ridgecrest Boulevard 27.6 C
Unsignalized Intersections
French Avenue/Las Flores Avenue 16.0 C
Notes: Intersection turn movement volumes and LOS calculation worksheets included in Appendix J.
Transit Service
The City of Ridgecrest operates four Ridgerunner Transit bus routes in the project area. The Roadrunner L2
line runs along Drummond Avenue and French Avenue, immediately adjacent to the proposed school site
and along parts of China Lake Boulevard and Ridgecrest Boulevard. The Coyote L1 line runs along China
Lake Boulevard south of Ridgecrest Boulevard and along Ridgecrest Boulevard east of China Lake
Boulevard. The Rattlesnake L3 line runs along China Lake Boulevard and on Drummond Avenue, Las Flores
Avenue, French Avenue, and Ridgecrest Boulevard west of China Lake Boulevard. The Joshua Tree L4 line
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 124 PlaceWorks
runs along China Lake Boulevard near the project site, extending to the Community of Inyokern in
unincorporated Kern County to the west.
Bicycle Facilities
Class 2 (striped and signed on-road) bike lanes currently exist on both sides of the road on the segments of
Drummond Avenue between Knox Avenue and China Lake Boulevard, on French Avenue from Drummond
Avenue to China Lake Boulevard; and on North China Lake Boulevard (SR-178). No bike lanes currently
exist on the segment of French Avenue adjacent to the project site north of Drummond Avenue.
Pedestrian Facilities
There are sidewalks on both sides of all roadways described above, except for Knox Avenue north of
Drummond Avenue. Marked crosswalks with push button detectors and pedestrian crossing signals are
already in place at the intersection of Drummond Avenue and French Avenue.
Future Baseline 2017 Traffic Conditions
Ambient growth has been added to traffic volumes on surrounding roadways in addition to traffic generated
by the development of future projects that have been approved, but not yet built and/or for which
development applications have been filed and are under consideration by governing agencies. This ambient
growth rate is added to existing traffic volumes to account for area-wide growth not reflected by cumulative
development projects. The future baseline traffic conditions without the proposed school were estimated for
the near-term year of 2017 by considering the effects of general ambient regional growth and the cumulative
increase in traffic volumes that would be generated by other development projects proposed in the area. The
year 2017 was used as the future analysis year because that is anticipated to be the first year of occupancy for
the proposed school. Future year traffic forecasts for 2017 traffic conditions have been based upon five years
of ambient growth at 1 percent per year, which results in a total growth of 5.1 percent.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 125
Figure 18 Existing Circulation Network and Lane Configurations
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 126 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 127
A list of cumulative projects anticipated to contribute traffic to any study area facility by project opening year
2017 was developed based on a review of the City of Ridgecrest’s Tract/Housing Units Status Report. The
list consists of cumulative projects that are reasonably and foreseeably anticipated to be constructed and
operational by 2017. The cumulative volumes of traffic that would be generated by seven projects anticipated
to be constructed and operational by 2017 are summarized in Table 21, Cumulative Projects.
Table 21 Cumulative Projects
Project Location Units
Trips
Daily AM Peak Hour
Tract 6912 Brianna and Del Rosa 23 220 17
Tract 6992 NE Corner Richmond & Upjohn 24 230 18
Tract 7112 NW Corner Kendall & S. Norma 51 490 38
Tract 7184 NE Corner China Lake & E. Dolphin 21 200 16
Tract 6731 N of NW Corner Kendall & S. Norma 120 1,150 90
Tract 6691 NW Corner of Mahan & Ridgecrest Bl 223 2,130 167
Tract 7188 NW Corner of Mahan & Drummond 40 380 30
Total 502 4,800 376
Note: The daily trip generation rate for single-family detached residences in Trip Generation (9th ed.) is 9.52, about 0.5 percent less than the trip generation estimate used in this table. The AM peak hour generation rate in Trip Generation is 0.75, the same rate used in this table.
The cumulative development projects assumed in this traffic analysis are estimated to generate 4,800 trip-ends
per day during a typical weekday, with approximately 376 vehicle trips during the AM peak hour. The volumes
of traffic that would be generated by the other proposed development projects were distributed onto the
study area roadway network to quantify the cumulative impacts of these projects.
To assess future background traffic conditions at the time of project opening year, existing traffic was
combined with the anticipated ambient growth and the traffic from cumulative developments anticipated to
operate in 2017. The intersection operations for the 2017 No Project traffic conditions have been calculated
and are given in Table 22, Intersection Delay and LOS, 2017 No Project Conditions.
As shown on Table 22, all intersections would operate at acceptable LOS during the morning peak hour for
the year 2017 scenario without the proposed project.
Table 22 Intersection Levels of Service, 2017 Without-Project Conditions Intersection Delay, seconds Level of Service
Signalized Intersections
Knox Avenue/Drummond Avenue 17.5 B
China Lake Boulevard/Drummond Avenue 21.2 C
China Lake Boulevard/Las Flores Avenue 19.0 B
China Lake Boulevard/French Avenue 21.8 C
China Lake Boulevard/Ridgecrest Boulevard 28.9 C
Unsignalized Intersections
French Avenue/Las Flores Avenue 16.4 C
Notes: Intersection turn movement volumes and LOS calculations included in Appendix J.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 128 PlaceWorks
Project-Generated Traffic
The project would have a capacity of 896 students. The trip generation was calculated based on rates in the
ITE Trip Generation Manual (9th ed.) for Land Use 522, Middle/Junior High School. Table 23, Project Trip
Generation, shows the trip generation rates and project trip generation for the AM and PM peak hours and
daily trips.
Table 23 Project-Generated Traffic AM Peak Hour PM student dismissal PM Peak Hour2 Daily
Trip Generation per Student1 0.54 0.30 0.16 1.62
Trips 484 269 143 1,610 1 Trip generation rates provided by the ITE Trip Generation Manual, 9th edition. 2 Peak hour of the adjacent streets, during 4 to 6 PM.
Table 23 shows that the school would generate an estimated 484 vehicle trips during the morning peak hour,
269 during the afternoon student dismissal hour, 143 trips during the afternoon traffic peak hour, and 1,610
trips per day. It should be noted that the traffic impact analysis assumes that all these trips are new to the
street network, which is a conservative assessment because some of this traffic already exists from the
existing Murray Middle School site.
To quantify the increase in traffic at each intersection resulting from the proposed project, the traffic that
would be generated by the school during the morning peak hour was geographically distributed onto the
roadway network based on the anticipated student boundaries and the observed traffic patterns on the study
area roadway network. It should be noted that the student drop-off exit loop is restricted to prohibit
southbound left turns (right-turn out only). The trip distribution percentages are applied to the project trip
generation to determine the traffic volumes forecast to be added at each intersection (i.e., trip assignment).
Existing plus Project Conditions
To assess Existing plus Project traffic conditions, existing traffic is combined with project traffic. The
intersection operations for the Existing plus Project traffic conditions have been calculated and are shown in
Table 24, Intersection Delay and LOS, Existing plus Project Conditions. According to the City of Ridgecrest and
Caltrans standards, an intersection would be significantly impacted if the project would result in a change in
the level of service from an acceptable LOS A, B, or C to an unacceptable LOS D, E, or F. Table 24 shows
the existing traffic conditions, the traffic conditions with the addition of the school traffic, and the increase in
the delay values associated with the project. Table 24 indicates that all study area intersections would continue
to operate at an acceptable LOS, and none of the study area intersections would be significantly impacted by
the proposed school project according to the City of Ridgecrest and Caltrans significance criteria. Traffic
impacts under existing conditions would be less than significant. No mitigation measures are required.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 129
Table 24 Intersection Levels of Service, Existing plus Project Conditions
Intersection
Existing Conditions Existing plus Project Conditions
Delay, Seconds LOS Delay, Seconds LOS
Signalized Intersections
Knox Avenue/Drummond Avenue 17.5 B 19.9 B
China Lake Blvd/Drummond Avenue 21.2 C 23.6 C
China Lake Blvd/Las Flores Avenue 19.0 B 17.4 B
China Lake Blvd/French Avenue 21.8 C 20.1 C
China Lake Blvd/Ridgecrest Blvd 28.9 C 27.7 C
Unsignalized Intersections
French Avenue/Las Flores Avenue 16.4 C 18.5 C
Notes: Intersection turn movement volumes and LOS worksheets are included in Appendix J.
2017 plus Project Conditions
Traffic Volumes
Project-generated traffic volumes were added to 2017 without-project traffic volumes to forecast 2017 with-
project traffic volumes. The comparative delay values and levels of service for the year 2017 analysis scenario
are shown in Table 25, Intersection Levels of Service, 2017 plus Project Conditions. As shown, all intersections would
operate at acceptable LOS B or C, and none of the study area intersections would be significantly impacted
by the proposed school project. Traffic impacts in 2017 when the school is projected to open would be less
than significant. No mitigation measures are required.
Table 25 Intersection Levels of Service, 2017 plus Project Conditions
Intersection
2017 No Project Conditions 2017 plus Project Conditions
Delay, Seconds LOS Delay, Seconds LOS
Signalized Intersections
Knox Avenue/Drummond Avenue 17.5 B 20.7 C
China Lake Blvd/Drummond Avenue 21.2 C 23.6 C
China Lake Blvd/Las Flores Avenue 19.0 B 15.5 B
China Lake Blvd/French Avenue 21.8 C 22.8 C
China Lake Blvd/Ridgecrest Blvd 28.9 C 33.7 C
Unsignalized Intersections
French Avenue/Las Flores Avenue 16.4 C 19.6 C
Notes: Intersection LOS worksheets included in Appendix J.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 130 PlaceWorks
Construction Traffic Impacts
Construction of the proposed new school and demolition of the existing school would generate various
levels of truck and automobile traffic throughout the duration of the construction period. At the proposed
new school site (and as a worst case scenario, as compared to demolition of the existing campus), the
construction-related traffic includes construction workers traveling to and from the site as well as trucks
hauling construction materials to the site and excavation material away from the site. The construction phase
that would generate the greatest number of truck trips would be the soil haul phase for soil remediation,
which would generate approximately 100 truck trips per day. Other construction phases would not exceed 22
trips per day in average. The construction truck trips would be spread out throughout the workday, averaging
approximately 12 trips per hour during the soil haul phase. This level of construction-related traffic would
not result in a significant traffic impact on the study area street network because it would be minor compared
to the volumes of traffic that are already on the street network. No significant impacts would occur during
construction activities at the existing campus or the proposed new campus. No mitigation measures would be
required.
b) Conflict with an applicable congestion management program, including, but not limited to level
of service standards and travel demand measures, or other standards established by the county
congestion management agency for designated roads or highways?
Less Than Significant Impact. The Congestion Management Program (CMP) for Kern County is
administered by the Kern Council of Governments, which serves as the congestion management agency. The
CMP, included in the Kern County Regional Transportation Plan, indicates that the CMP roadways nearest to
the project site are China Lake Boulevard and Ridgecrest Boulevard (State Route 178). According to the CMP,
LOS E is the minimum LOS standard for the roadways on the Kern County CMP network. As detailed in
response a), the study area intersections along the CMP roadways would continue to operate at LOS B and C
for the “with-project” scenarios, which is better than the minimum CMP standard of LOS E. The proposed
project would not, therefore, exceed a level of service standard established by the county congestion
management agency for designated roads or highways, and the project’s impacts on the CMP roadways would
be less than significant. No mitigation measures are required.
c) Result in a change in air traffic patterns, including either an increase in traffic levels or a change
in location that results in substantial safety risks?
No Impact. The project would not change air traffic levels. The nearest airfield to the site is Armitage
Airfield, three miles to the north of the new school site and 2.4 miles northwest of the existing campus. All
proposed buildings would be one story—the gymnasium would be about 30 feet high and the remaining
buildings would each be about 20 feet high. Therefore, the project would not change air traffic patterns. No
impact would occur, and no mitigation is required.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 131
d) Substantially increase hazards due to a design feature (e.g., sharp curves or dangerous
intersections) or incompatible uses (e.g., farm equipment)?
No Impact. The project would include a circular one-way driveway off Drummond Avenue dedicated for
student drop-off and pickup, one circular one-way bus drop-off driveway on Knox Avenue, and a service
entrance on Knox Avenue on the northeast corner of the site. There would be sufficient separation between
the driveways dedicated for private autos and school buses. In addition, pedestrian pathways would be
separated from the main access driveways, and none of the pedestrians pathways would cross a driveway. At
the student drop-off driveway, there would be a separation of approximately 400 feet from the entrance to
the exit on Drummond Avenue. No left turns out would be allowed at that driveway, minimizing merging
conflicts on Drummond Avenue. The segment on Drummond Avenue is flat, providing clear line of sight for
cars exiting the student drop-off driveway. The project would not add incompatible uses to area roadways.
Therefore, there would be no impact. No mitigation is required.
e) Result in inadequate emergency access?
No Impact. In addition to the site access driveways described in Section 3.16.d, the new school site plan
includes two fire lanes: one extending from near Knox Avenue near the northeast corner of the campus
across the northern part of the campus to the track, and the second extending north from the loop driveway,
passing next to the west end of the D buildings. The project site plan includes emergency access compliant
with California Fire Code and CDE standards. No adverse impact would occur, and no mitigation is needed.
f) Conflict with adopted policies, plans, or programs regarding public transit, bicycle, or pedestrian
facilities, or otherwise decrease the performance or safety of such facilities?
No Impact. The new school site is served by bicycle lanes, sidewalks, and transit. Project development would
not interfere with the bicycle lanes, sidewalks near the project site, and the operation of Ridgerunner transit
bus service. No impact would occur, and no mitigation is needed.
g) Result in inadequate parking capacity?
No Impact. The new school’s main parking lot of 87 stalls would be east of the driveway, with access from
the driveway; a motorized arm gate would separate 8 visitor stalls from the remaining 79 stalls. Four ADA
parking spaces would also be provided at the northeast corner of the campus from a separate driveway along
Knox Road. A total of 91 off-street parking spaces would be provided. The City of Ridgecrest’s requirement
for off-street parking for elementary and junior high schools is: One space for each teacher, administrator and
custodian, plus sufficient space for safe and convenient bus loading and unloading of students (Municipal
Code §§ 20-20.5). School operation is estimated to employ 60 to 65 faculty, administrators, and other staff. A
bus drop-off lane would be built next to Knox Avenue. The project would accommodate the parking demand
for all employees and provide a cushion for vendors and parents that would occasionally park. The project
would meet City of Ridgecrest requirement for off-street parking for a middle school, and no adverse impact
would occur. No mitigation is required.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 132 PlaceWorks
3.17 UTILITIES AND SERVICE SYSTEMS
a) Exceed waste water treatment requirements of the applicable Regional Water Quality Control
Board?
Less Than Significant Impact. The China Lake Environmental Management Office enforces federal, state,
and local environmental regulations on the station. During construction of the proposed project, the
District’s construction contractor would be required to obtain an NPDES General Construction Permit from
the SWRCB, which would outline wastewater discharge requirements and BMPs, and would require
preparation of a SWPPP. The SWPPP will include BMPs for minimizing water pollution and the project’s
effluent quality criteria would be specified, as determined by the SWRCB, based on receiving water guidelines
and waste load allocations. The District’s construction contractor will be required to comply with the effluent
quality criteria specified within the NPDES General Construction Permit for the construction activities
associated with the new school site and demolition activities associated with the existing campus. Impacts
from the proposed project would therefore have no significant impact on wastewater treatment requirements,
and no mitigation is required.
b) Require or result in the construction of new water or waste water treatment facilities or
expansion of existing facilities, the construction of which could cause significant environmental
effects?
No Impact. Implementation of the proposed project would not require or result in the construction of new
water or wastewater treatment facilities or the expansion of existing facilities.
Water Treatment
Water treatment facilities filter and/or disinfect water before it is delivered to customers. The Indian Wells
Valley Water District (IWVWD) supplies water to the existing school and to the proposed school site. All of
the IWVWD’s water supplies are groundwater from the Indian Wells Valley Groundwater Basin. Wells 9A, 10,
11, and 13 produce water containing arsenic at levels exceeding the maximum contaminant level (MCL) of 10
parts per billion (ppb). Two arsenic removal facilities were completed in August 2011 in order to remove
arsenic from wells 9A, 10, 11, and 13. With treatment, water entering the IWVWD’s distribution system from
these wells will be below the 10 ppb MCL for arsenic. (Krieger & Stewart 2011; IWVWD 2012). In
December 2013 the IWVWD circulated an Initial Study/MND for a proposed sludge-drying bed next to
Treatment Plant No. 2 that would dry iron/arsenic residue (inert sludge) from both treatment plants; the dry
sludge would be disposed of offsite (Krieger & Stewart 2013). The project would not expand enrollment at
Murray Middle School and thus would not increase water use. Thus, the project would not require new or
expanded water treatment facilities. Demolition of the existing campus would not require construction of
new or expanded water treatment facilities. No impact would occur.
Wastewater Treatment
Wastewater treatment for the existing school and the proposed school site is provided by the City of
Ridgecrest at its Regional Wastewater Treatment Plant (RWTP) on the base. The RWTP has capacity of 3.6
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 133
million gallons per day (mgd); wastewater flows through the plant in 2010 were 2,936 acre-feet per year, or
2.62 mgd (Krieger & Stewart 2011). The project would not expand enrollment at Murray Middle School and
thus would not increase wastewater generation at the school. Demolition of the existing school would not
generate wastewater and would not impact wastewater treatment capacity. Therefore, the project would not
require new or expanded wastewater treatment facilities. No impact would occur.
c) Require or result in the construction of new storm water drainage facilities or expansion of
existing facilities, the construction of which could cause significant environmental effects?
Less Than Significant Impact. The area of the new school site currently consists almost entirely of
pervious surface; there are a few roads in poor condition in the north half of the site remaining from
previous residential development onsite and remnants of a former substation. The project would include the
development of nine retention basins onsite to detain and infiltrate runoff from a 10-year, 5-day storm (see
Section 3.9.c, Table 11, and Figure 17, Proposed Hydrology Map). All drainage from a 10-year, 5-day storm in
postproject conditions would be contained and infiltrated into soil by the proposed retention basins, and the
project would not discharge runoff from such a storm offsite. Thus, the project would not require
construction of new or expanded offsite stormwater drainage facilities. The environmental effects associated
with the construction of onsite retention basins are examined throughout this document. Development of
any necessary onsite stormwater drainage improvements would be required to comply with the NPDES
regulations and applicable naval environmental policies. Compliance with the policies of the NPDES General
Construction Permit and all other applicable regional policies would ensure that construction of any new
stormwater facility improvements would not result in adverse impacts. Demolition of the existing campus
would reduce impervious surfaces, and thus runoff, from that site. The proposed project would have no
significant impact on stormwater drainage facilities, and no mitigation is required.
d) Have sufficient water supplies available to serve the project from existing entitlements and
resources, or are new or expanded entitlements needed?
No Impact. The IWVWD would supply water to the project. The project would not expand enrollment of
Murray Middle School and therefore would not increase water demand by the school. In addition, the District
would comply with local, regional, and state water conservation policies and would follow standard BMPs,
including Title 22 regulations, in order to reduce water consumption. The IWVWD forecasts that it will have
adequate water supplies to meet water demands in its service area through the 2015–2035 period (Krieger &
Stewart 2011). The proposed project would result in no need for new or expanded entitlements. Demolition
of the existing school would create a brief need for a small amount of water for uses such as dust control,
but not enough to impact IWVWD water supplies. No impact would occur, and no mitigation is required.
e) Result in a determination by the waste water treatment provider, which serves or may serve the
project that it has adequate capacity to serve the project’s projected demand in addition to the
provider’s existing commitments?
No Impact. No impact to wastewater treatment capacity would occur, as substantiated above in Section
3.17.b.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 134 PlaceWorks
f) Be served by a landfill with sufficient permitted capacity to accommodate the project’s solid
waste disposal needs?
Less Than Significant Impact. The proposed project would be served by landfills with sufficient permitted
capacity to accommodate the project’s solid waste disposal needs, as supported below.
Operation
The project would not expand enrollment of the school and thus would not increase operational solid waste
generation from the school. Waste associated with project operations would continue to be brought to the
Indian Wells Valley, Ridgecrest Recycling and Sanitary Landfill operated by Kern County Waste Management
Department, which currently serves the existing Murray campus. This landfill has permitted throughput of
701 tons per day; remaining capacity of 5,037,428 cubic yards, or about 3,778,000 tons; average daily disposal
in 2011 of about 173.4 tons;10 and an estimated closing date of 2045 (CalRecycle 2015a, 2015b). No impact
would occur related to the disposal of the project’s operational waste.
Demolition and Construction
The project would generate demolition debris from demolition of the existing middle school and
construction waste and debris from construction of the new facility. Requirements for disposal, recycling, and
reuse of nonhazardous and hazardous construction and demolition debris from the new and existing schools
are set forth in the Record of Categorical Exclusion for Construction of a New Middle School, and Record
of Categorical Exclusion for Demolition of Murray Middle School, included as Appendices A.1 and A.2 to
this Initial Study. Ridgecrest Recycling and Sanitary Landfill accepts construction and demolition debris and
includes a green waste composting facility. The project would comply with naval environmental policy. As a
result, impacts would be less than significant, and no mitigation measures are necessary.
Contaminated Soil
In addition to demolition and construction debris, the project would require remediation of contaminated
soil at the new school site, which may involve removal and offsite disposal of up to approximately 20,077
cubic yards of soil (see Section 3.8.d for further description). Contaminated soil would be disposed of at one
or both of the following landfills in the Antelope Valley in northern Los Angeles County:
The Lancaster Landfill and Recycling Center in the City of Lancaster is about 83 miles south-southwest
of the project site. The Lancaster Landfill and Recycling Center has permitted throughput of 5,100 tons
per day; remaining capacity of 14,514,648 cubic yards, or about 10,900,000 tons; average daily disposal in
2013 of about 402 tons per day; and an estimated closing date of 2044 (CalRecycle 2015b, CalRecycle
2015c).11,12
10 Total of 48,480 tons disposed in 2011 divided by 350 days; the landfill is open 7 days per week. 11 The Lancaster Landfill and Recycling Center consists of two units: Unit 1, the solid waste landfill described above; and Unit 2, a greenwaste composting facility irrelevant to the proposed disposal of contaminated soil. 12 Total of 100,544 tons disposed in 2013 divided by 250 days; the Lancaster Landfill and Recycling Center is open five days per week.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
July 2015 Page 135
The Antelope Valley Public Landfill in the City of Palmdale is about 95 miles south-southwest of the
project site. The Antelope Valley Public Landfill has permitted throughput of 3,564 tons per day;
remaining capacity of 20,400,000 cubic yards or 15,300,000 tons; average daily disposal of about 2,328
tons per day; and an estimated closing date of 2042 (CalRecycle 2015b, CalRecycle 2015d).
The Lancaster Landfill and Recycling Center and Antelope Valley Public Landfill have sufficient capacity—
separately or combined—for the proposed disposal of contaminated soil, and impacts of such disposal on
landfill capacity would be less than significant. No mitigation measures are necessary.
g) Comply with federal, state, and local statutes and regulations related to solid waste?
Less Than Significant Impact. During construction and operation of the proposed project and demolition
of the existing campus, the District would comply with applicable military, county, and state solid waste
diversion, reduction, and recycling mandates. China Lake adheres to applicable federal, state, and county
environmental regulations. As a lessee of the project site, the District would also comply with Assembly Bill
939 (AB 939), the Integrated Waste Management Act of 1989, which requires source reduction, reuse,
recycling, and composting programs to reduce tonnage of solid waste going to landfills by 50 percent.
Assembly Bill 1826 (California Public Resources Code §§ 42649.8 et seq.), signed into law in September 2014,
requires recycling of organic matter by businesses, and multifamily residences of five of more units,
generating such wastes in amounts over certain thresholds. The law takes effect in 2016. The proposed school
would include a storage area for recyclable organic matter in compliance with AB 1826.
The District would make every reasonable effort to reuse and/or recycle the construction debris that would
otherwise be taken to a landfill and would also dispose of hazardous wastes, including paint used during
construction, only at facilities permitted to receive them, and in accordance with local, state, and federal
regulations. The proposed project would comply with all applicable federal, state, and local statues and
regulations related to solid waste disposal, and impacts would be less than significant. No mitigation measures
are necessary.
3.18 MANDATORY FINDINGS OF SIGNIFICANCE
a) Does the project have the potential to degrade the quality of the environment, substantially
reduce the habitat of a fish or wildlife species, cause a fish or wildlife population to drop below
self-sustaining levels, threaten to eliminate a plant or animal community, reduce the number or
restrict the range of a rare or endangered plant or animal or eliminate important examples of the
major periods of California history or prehistory?
Less Than Significant Impact With Mitigation Incorporated. Buried archaeological resources and fossils
could be present in site soils. The proposed project would have the potential to degrade the quality of the
environment if archeological or paleontological resources are accidentally damaged during construction
activities. Mitigation measures are included in this Initial Study to minimize impacts of project development
on such resources. Therefore, with the imposition of these measures, project implementation would not
eliminate important examples of major periods of California history or prehistory.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
3. Environmental Analysis
Page 136 PlaceWorks
Parts of the new school site support disturbed white bursage scrub habitat; the balance of the site consists of
disturbed habitats and developed areas. Project development could impact desert tortoise (Gopherus agassizii):
the NEPA Categorical Exclusion concluded that desert tortoise could occur onsite, although the biological
technical report concluded that the species is not anticipated to occur onsite. Mitigation Measure BIO-2 is
included in this Initial Study to minimize impacts of project development on desert tortoise. Project
implementation would not otherwise reduce the habitat of fish and wildlife species, cause a fish or wildlife
population to drop below self-sustaining levels, threaten to eliminate a plant or animal community, or reduce
the number or restrict the range of a rare or endangered plant or animal. Impacts to biological resources
from project implementation would be less than significant with mitigation incorporated.
b) Does the project have impacts that are individually limited, but cumulatively considerable?
(“Cumulatively considerable” means that the incremental effects of a project are considerable
when viewed in connection with the effects of past projects, the effects of other current projects,
and the effects of probable future projects.)
Less Than Significant Impact With Mitigation Incorporated. Project development would not have the
potential to have impacts that are individually limited but cumulatively considerable. Where the proposed
project would have no impact, it would not contribute to cumulative impacts. In addition, issues specific to
site conditions, such as site geology and soils, do not have cumulative effects. The proposed project is not
growth inducing and would therefore not contribute to the cumulative effects of population growth. The
cumulative impacts due to hydrology and water quality, noise, and traffic would be reduced to less than
significant levels by adhering to local, regional, state, and federal regulations. Impacts related to air quality
would be reduced to acceptable standards with the imposition of Mitigation Measure AQ-1. No cumulatively
considerable impacts would result from the proposed project, and no mitigation measures are necessary.
c) Does the project have environmental effects, which will cause substantial adverse effects on
human beings, either directly or indirectly?
Less Than Significant Impact With Mitigation Incorporated. The project would comply with all local,
state, and federal laws governing general welfare and environmental protection. The implementation of
required mitigation measures specified in this Initial Study would reduce impacts to less than significant.
Project impacts on human beings, either directly or indirectly, would be less than significant, and no additional
mitigation measures are necessary.
July 2015 Page 137
4. References
Airnav.com. 2015, January 26. Airport Information. http://www.airnav.com/airports/.
Alden Environmental. 2013, January 22. Biological Technical Report for the Town of Yucca Valley General
Plan Update.
Bay Area Air Quality Management District (BAAQMD). 2011, Revised. California Environmental Quality
Act Air Quality Guidelines.
Bureau of Land Management (BLM). 2015, July 8. Introduction – West Mojave Plan.
http://www.blm.gov/ca/st/en/fo/cdd/wemo_intro.html.California Department of Forestry and
Fire Prevention (CAL FIRE). 2007, November 7. Very High Fire Hazard Severity Zones in SRA:
Kern County. http://frap.fire.ca.gov/webdata/maps/kern/fhszs_map.15.pdf.
California Air Pollution Control Officers Association (CAPCOA). 2013. California Emissions Estimator
Model (CalEEMod). Version 2013.2.2. Prepared by: ENVIRON International Corporation and the
California Air Districts.
California Air Resources Board (CARB). 2014a, August 22. Area Designations Maps/State and National.
http://www.arb.ca.gov/desig/adm/adm.htm.
———. 2014b, May 15. Proposed First Update to the Climate Change Scoping Plan: Building on the
Framework, http://www.arb.ca.gov/cc/scopingplan/scopingplan.htm x.
———. 2013, October 23. Proposed 2013 Amendments to Area Designations for State Ambient Air Quality
Standards. http://www.arb.ca.gov/regact/2013/area13/area13isor.pdf.
———. 2012, Status of Scoping Plan Recommended Measures,
http://www.arb.ca.gov/cc/scopingplan/status_of_scoping_plan_measures.pdf.
———. 2011, June 15. Eastern Kern Air Quality Management Plans.
http://www.arb.ca.gov/planning/sip/planarea/easternkern/easternkern.htm.
———. 2008, October. Climate Change Proposed Scoping Plan, a Framework for Change.
California Department of Education (CDE). 2015, January 26. Dataquest.
http://data1.cde.ca.gov/dataquest/.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
4. References
Page 138 PlaceWorks
California Department of Finance (CDF). 2014, May. E-5 Population and Housing Estimates for Cities,
Counties, and the State, January 2011- 2014.
http://www.dof.ca.gov/research/demographic/reports/estimates/e-5/2011-20/view.php.
California Department of Fish and Wildlife (CDFW). 2013, August 14. California Species of Special
Concern. http://www.dfg.ca.gov/wildlife/nongame/ssc/.
California Department of Resources Recycling and Recovery (CalRecycle). 2015a, January 28. Facility/Site
Summary Details: Ridgecrest Recycling and Sanitary Landfill.
http://www.calrecycle.ca.gov/SWFacilities/Directory/15-AA-0059/Detail/.
California Department of Resources Recycling and Recovery (CalRecycle). 2015b, January 28. Landfill
Tonnage Reports. http://www.calrecycle.ca.gov/SWFacilities/Landfills/Tonnages/.
California Department of Resources Recycling and Recovery (CalRecycle). 2015c, April 9. Facility/Site
Summary Details: Lancaster Landfill and Recycling Center. .
http://www.calrecycle.ca.gov/SWFacilities/Directory/19-AA-0050/Detail/.
California Department of Resources Recycling and Recovery (CalRecycle). 2015d, April 9. Facility/Site
Summary Details: Antelope Valley Public Landfill.
http://www.calrecycle.ca.gov/SWFacilities/Directory/19-AA-5624/Detail/.
California Energy Commission (CEC). 2015, January 27. Desert Renewable Energy Conservation Plan: Draft
DRECP and EIR/EIS. http://www.drecp.org/draftdrecp/.
California Geological Survey (CGS). 1999. Mineral Land Classification of Southeastern Kern County. Open
File Report 99-15, Plate 2A. ftp://ftp.consrv.ca.gov/pub/dmg/pubs/ofr/OFR_99-15/OFR_99-
15_Plate2A.pdf.
Department of Toxic Substances Control (DTSC). 2015, January 26. EnviroStor.
http://www.envirostor.dtsc.ca.gov/public/.
Division of Land Resource Protection (DLRP). 2015, January 26. California Important Farmland Finder.
http://maps.conservation.ca.gov/ciff/ciff.html.
Division of Land Resource Protection (DLRP). 2013, November 19. Kern County Williamson Act FY
2013/2014 Sheet 3 of 3. ftp://ftp.consrv.ca.gov/pub/dlrp/wa/Kern_e_13_14_WA.pdf.
Eastern Kern Air Pollution Control District (EKAPCD). 2012a, August. EPA Determinations that Seven
Areas in California Have Attained the 1997 Ozone National Ambient Air Quality Standard. EPA
Fact Sheet. http://www.kernair.org/Documents/Announcements/Attainment/Fact%20Sheet.pdf.
———. 2012b, July 12. Annual AB 2588 Air Toxics Report for 2011.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
4. References
July 2015 Page 139
———. 2011. Rule 402 Fugitive Dust.
http://www.kernair.org/Rule%20Book/4%20Prohibitions/402_Fugitive_Dust.pdf.
———. 2007. Suggested Air Pollutant Mitigation Measures for Construction Sites for Kern County APCD.
———. 2000. Rule 210.1, New and Modified Source Review Rule.
———. 1996. Guidelines for the Implementation of the California Environmental Quality Act (CEQA) of
1970, As Amended.
Employment Development Department (EDD). 2015, January 27. Report 400C: Monthly Labor Force Data
for Counties. http://www.calmis.ca.gov/file/lfmonth/countyur-400c.pdf
Federal Emergency Management Agency (FEMA). 2014. GIS flood hazard map layer.
Fox, Tim (Community Plans Liaison Officer). 2013, January 7. Phone call. NAWS China Lake.
———. 2012, December 12. Phone call. NAWS China Lake.
Google Earth. 2015, January 28.
Governor’s Office of Planning and Research (OPR). 2008, June. Technical Advisory, CEQA and Climate
Change: Addressing Climate Change Through CEQA Review.
http://www.opr.ca.gov/ceqa/pdfs/june08-ceqa.pdf.
Kern Council of Governments (KCOG) 2014, June 19. 2014 Regional Transportation Plan/Sustainable
Communities Strategy. http://www.kerncog.org/images/docs/rtp/2014_RTP.pdf.
Krieger & Stewart, Incorporated. 2011, May. Indian Wells Valley Water District 2010 Urban Water
Management Plan. http://www.iwvwd.com/Newsletter/178-64P4-UWMP2010-
FINAL%2005182011.pdf.
———. 2013, December . Indian Wells Valley Water District Initial Study and Mitigated Negative
Declaration for Arsenic Treatment Facilities Sludge Drying Bed. http://www.iwvwd.com/wp-
content/uploads/2013/12/IS-Draft-MND-for-IWVWD-Arsenic-Tmt-Sludge-Dry-Bed-Dec-
2013.pdf.
Mielke, Chris, P.E., QSD. 2015, June 1. Hydrology Report for Murray Middle School.
Naval Air Weapons Station China Lake (NAWS) and Bureau of Land Management (BLM). 2005, May.
Comprehensive Land Use Management Plan (CLUMP) for Naval Air Weapons Station China Lake,
California. http://www.chinalakeleis.com/documents/china_lake_clump_may_2005.pdf.
NAWS China Lake Environmental Management Division. 2012, June. Integrated Cultural Resources
Management Plan for Naval Air Weapons Station, China Lake, Inyo, Kern, and San Bernardino
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
4. References
Page 140 PlaceWorks
Counties, California.
http://www.chinalakeleis.com/system/assets/38/original/nawscl_eis_leis_icrmp_oct2012.pdf.
Office of Environmental Health Hazard Assessment (OEHHA). 2012, June. Air Toxics Hot Spots Program
Risk Assessment Guidelines. Technical Support Document for Exposure Assessment and Stochastic
Analysis.
Office of Mine Reclamation (OMR). 2015, January 27. Mines Online.
http://maps.conservation.ca.gov/mol/mol-app.html.
PlaceWorks. 2014, February. Geological and Environmental Hazards Report for: New Murray Middle School.
PlaceWorks. 2013, December 27. Phase I Environmental Site Assessment, New Murray Middle School
(Northwest Corner E. French Drive and E. Drummond Avenue, Ridgecrest, California 93555).
PlaceWorks. 2013, February. Pipeline Safety Hazard Assessment for: New Murray Middle School.
State Water Resources Control Board (SWRCB). 2015, January 26. GeoTracker.
http://geotracker.waterboards.ca.gov/default.asp.
US Geological Survey (USGS). 1953. Ridgecrest Quadrangle topographic map.
http://ngmdb.usgs.gov/img4/ht_icons/Browse/CA/CA_Ridgecrest_298771_1953_62500.jpg
US Geological Survey (USGS). 1973. Ridgecrest North quadrangle topographic map.
http://ngmdb.usgs.gov/img4/ht_icons/Browse/CA/CA_Ridgecrest%20North_101897_1973_2400
0.jpg
July 2015 Page 141
5. List of Preparers
LEAD AGENCY
Pamela Pence, Program Manager
PLACEWORKS
Barbara Heyman, Associate Principal / Project Manager
Ron Cavagrotti, Senior Scientist
Nicole Vermilion, Manager, Air Quality and Greenhouse Gas Analysis
Bob Mantey, Manager, Noise, Vibration, and Acoustics
Fernando Sotelo, Transportation Planner
Michael Milroy, Associate
John Vang, J.D., Project Planner
Stephanie Chen, Planner, Air Quality/GHG and Transportation
Natalie Foley, Planner, Noise
Cary Nakama, Graphic Artist
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
5. List of Preparers
Page 142 PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix A.1 Record of Categorical Exclusion for Lease of New School Site
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix A.2 Record of Categorical Exclusion for the Demolition of Murray Middle School
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix B Environmental Condition of Property Report
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix C.1 Air Quality and Greenhouse Gas Analysis
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix C.2 Health Risk Assessment Technical Memorandum
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix D Biological Technical Report
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix E.1 Historic Resource Assessment
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix E.2 Cultural Resources Records Search
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix E.3 Paleontological Records Search
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix F.1 Geotechnical Engineering Investigation and Geologic/Seismic Hazards Evaluation
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix F.2 Fault Rupture Hazard Investigation Report
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix F.3 Amendment to Geotechnical Engineering Investigation and Geologic/Seismic Hazards Evaluation
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix F.4 Update, Geotechnical Engineering Investigation
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix G.1 Phase I Environmental Site Assessment
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix G.2 Preliminary Environmental Assessment Report, New Murray Middle School
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix G.3 Remedial Action Workplan
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix H Hydrology Study
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix I Noise Analysis
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
July 2015
Appendix J Traffic Impact Analysis
N E W M U R R A Y M I D D L E S C H O O L I N I T I A L S T U D Y S I E R R A S A N D S U N I F I E D S C H O O L D I S T R I C T
Appendix
PlaceWorks
This page intentionally left blank.