Tom McLean

Technical Officer

FCERM Branch

Welsh Government

[email protected]

02920 370 244

New FCERM Project Appraisal

Guidance for Wales

Kevin Keating

Principal Engineer

Mott MacDonald

[email protected]

0151 482 9983

Page 2: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

Quick Project Overview

Page 3: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

What We Have Now

• Flood and Coastal

Defence Project

Appraisal Guidance

(FCDPAG), 2001

• Flood and Coastal Erosion

Risk Management

Appraisal Guidance

(FCERM-AG), 2010

Page 4: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

• Simplify & Demystify

• 5 Case Business Model (5CM)

• Scalability

• Wider Benefits

• Wellbeing of Future Generations

• Natural Flood Risk Management

The Brief

Page 5: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

May 2016

March 2017

A New PAG for Wales

• Appointed Mott MacDonald

• Review Existing Guidance

• User Survey

• Interview Risk Management Authorities

• Workshops

• Draft Nearing Completion

Page 6: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

A New PAG for WalesThe next steps…

April 2017

July 2017

• Finalise Draft Guidance

• Share with Key Stakeholders

• Case Study Trialling

• Publish

Page 7: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

User Feedback

Page 8: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

“Problem definition could take a

more holistic approach (wider

than strictly FCERM) which could

generate more scope for

integrated solutions”…

Problem Definition:

“FCERM-AG always

seems to over

complicate a process”

Environmental issues: “The

guidance is poor for this

aspect…. links with

ecosystem services and the

use of appraisals for NFM

approaches is critical.”

“Not a balanced

approach - Members

have said that there is

too much emphasis on

environmental

considerations“

vs

vs

What users told us

Page 9: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

What users told us

“Generally we use

Consultants for our

PAR’s so it’s difficult to

answer the questions”…

“PARs were best produced as a joint effort between LA and consultants”

“Currently skills and

resources are the biggest

constraint in producing

PARs in-house”

“Would like to see MCM

training for officers

rolled out so they can

better check consultant’s

output or undertake basic

analysis themselves”

Page 10: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

Thoughts on Existing Guidance

Page 11: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

Thoughts on Existing Guidance

• Treasury Green Book

– Value for money, objective led appraisal, 5CM, proportionate

• FCERM AG (& FCDPAG)

– Useful, too long & too much in it (>250 pages), 5CM?

– That much wrong with PAGN (30 pages)?

• Scottish Guidance

– Simpler and more accessible, 5CM?

• England’s 6 Year Prog. & Partnership Funding policy

Page 12: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

Applying the 5CM

Page 13: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

What’s in a business case?Enable a decision to invest (in an FCERM asset)

Exploring options &

preferred approach

Funding – how

much, who from and

when?

Maintaining the asset /

investment

Community & political buy-in

Management

Page 14: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

Better Business Cases – The 5CM

5 Themes or “Cases”

Strategic Case

Economic Case

Commercial Case

Financial Case

Management Case

Evolving Development

1. Strategic Outline Case

2. Outline Business Case

3. Full Business Case

(Or Short Form Business Case)

Page 15: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

The 5CM Stages in Detail

Mandate

& Initial

Assurance

OBC

Assurance

SOC

Assurance

FBC or

SFBC

Assurance

Existing data

Define

problem

Engage

Objectives

Do Nothing

Options

Eco. + Strat.

“cases”

OBC planning

New data (GI,

env, topo etc)

Modelling

Optioneering

Engage

Assess options

Id. scheme

Outline design

All 5 “cases”

FBC planning

New data (GI,

env., topo etc)

Engage

Consents

Secure funding

Procure

contractor

Update 5

“cases”

Planning

SOC OBC FBC Delivery

Detailed

design

Engage

Construction

Handover

Deliver

outcomes

Short Form

Direct to OBC

Page 16: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

Guidance Structure & The 5CM

Sections:

1 & 2. Introduction & Policy Setting

3. Strategic Outline Case (SOC)

Section for each “case” of the 5CM

4. Outline Business Case (OBC)

Section for each “case” of the 5CM

5. Full Business Case

6. Short Form Business Case

Page 17: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

Wales vs England

Page 18: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

Different Legislation

Well-being of Future

Generations Act

Page 19: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

Different Prioritisation Process

Page 20: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

Different Emphasis on Economics

Multi-Coloured Manual – key guidance and data

BUT: Value for money criteria for preferred option:

1. BCR > 1

2. Incremental BCR > 1 (cf. Do Minimum)

Result: Less focus on economics / simplified

Remember: No OM1 driver in Wales

Page 21: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

Always Shortlist a NFM / MSfW Option

Upstream

NFM

Page 22: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

Similar on Socio-Economic Benefits

• Wider objectives… Jobs, amenity, regeneration

• Multiple funding sources

• “Joined up” investment

Page 23: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal
Page 24: New FCERM Project Appraisal Guidance for Wales · Tom McLean Technical Officer FCERM Branch Welsh Government Thomas.Mclean@wales.gsi.gov.uk 02920 370 244 New FCERM Project Appraisal

Questions?

Tom Mclean is Welsh Government’s Project Manager

Tel: 02920 370 244

Email: [email protected]

Natalie Newton is Mott MacDonald’s Project Manager

Tel: 02920 467 871

Email: [email protected]