Upload
truongthu
View
218
Download
3
Embed Size (px)
Citation preview
Pakistan Civil Aviation Authority
New Benazir Bhutto International Airport
Brief for
PUBLIC ACCOUNTS COMMITEE
23 January, 2014
New Benazir Bhutto International Airport
2
• Project Overview
• Project History
• NBBIAP Design Evolution
• Project Phases
• Salient Design Features
• Progress Overview
• Peripheral Facilities
Sequence
3
Project Overview
4
Project History
• Project Conceived : 1984
• Land Acquisition : 1984-2004
• GOP Directives to Start Planning of NBBIA : 2003-2004
• Hiring of Project Management Consultants : 2004-2006
• Master Plan by LBG : Sept. 2006
• Site Preparatory Work(Package 0) Separate Contract : Feb, 2007
• Appointment of Design Consultants : Mar, 2007
• Ground-breaking Performed : Apr, 2007
5
Project History (Contd.)
PC-I approved (Conceptual Master Plan) : Mar, 2008
Airside Infrastructure design finalization (Package-I Only) : Mar, 2008
Package I, Airside Infrastructure (Civil Works) : Aug, 2008
6
CONSULTANTS
•M/s Louis Berger Group (Project Management Consultants)
• M/s LBG-ECIL JV (Feb 2006 - Feb 2011)
• M/s NESPAK (CMSS) (Feb 2010 - May 2012)
•M/s CPG Airports (Design Consultants for PTB)
•M/s ADPi – NESPAK JV (Design Consultants for the project except PTB)
•M/s AA Associates (Design Consultants – Dec 2013)
Consultants
7
CONTRACTORS
•M/s HCL – IKAN JV (Package 0 – Site Preparation Works)
•M/s CRFG-CWE-TTP JV (Package 2 – PTB Pile Foundations)
•M/s Sambu – Sachal JV (Package 3A – PTB Pile Caps)
•M/s Lagan-Technical-Habib JV (Package 1 / 8A – Air / Landside Infra str.)
•M/s CSCEC – FWO JV (Package 3 – Passenger Terminal Bldg.)
•M/s Beixin – Gammon JV (Package 8C-1 – ATC, FCR & RR Bldg.)
•M/s Siemens Pakistan (Package 7A – AFL System)
(Package 8B – Power & Telecom Network)
•M/s Al- Tariq Constructors (Package 6 – Hydrant Refueling System)
•M/s Izhar Steel Pvt. Ltd (Package 10 – Cargo Complex)
•M/s Abid Brothers - Gul Gardens JV (Package 8C – II Landscaping Works)
Contractors
8
NBBIAP
Design Evolution
9
Secondary Runway
Main Runway Secondary
Runway
Passenger Terminal
Building Car Park – 2000
Grid Station
Cargo
Complex
State Lounge
Apron
General Aviation
Rapid Exit
Taxiway
Isolated
Bay ATC Tower
MASTER PLAN : PRESENT SCOPE
10
Project Phases
11
Phase- I : Airside Infrastructure
• Aprons
• Taxiways
• Runways
• Airfield Lighting System (AFL)
• Air Traffic Control Tower
• Operational buildings
• Navigational Aids
• Hydrant Refueling System (HRS)
PROJECT PHASES
12
Phase- II : Landside Infrastructure
• Internal Road Network
• Telecom & Power Distribution Network
• Departure Level Bridge
• Underpasses (03 Sets)
• Road / Street Lighting System
• Water Works and Sewage Treatment Plants
• Fire Hydrant System
• Electrical power Sub-stations
• Cargo Complex and Allied Facilities
PROJECT PHASES
13
Phase- III : Passenger Terminal Building
• Passenger Terminal Building Civil work
• Building Management Systems
• Baggage Handling Systems
• Flight Information Display System
• Other Technical Systems (Master Clock, Fire Alarm & CCTV)
• Heating, Ventilation, & Air Conditioning
• Passenger Boarding Bridges (15 Nos.)
• PTB Furniture, Signage, Counters and Trolleys
• Power Supply (incl. Standby Generators)
PROJECT PHASES
14
Comparison of Facilities
15
Comparison of Facilities
Description Existing New
Passenger Handling Capacity 3 M/annum 9 M/annum
Cargo Handling Capacity 40,000 MT 200,000 MT
Runway 01 02
Taxiways 03 09
Rapid Exit Taxiways Nil 03
Parallel Taxiways Nil 01
Aprons 01 05
Passenger Boarding Bridges Nil 09
16
Comparison of Facilities
Description Existing New
Check-in Counters 20 90
Self Check-in Kiosk Nil 18
Car Park Capacity 400 2000
Air Traffic Control Tower Shared Basis Dedicated
Fire Crash Rescue Building Shared Basis Dedicated
17
Progress Overview
18
Overall Financial / Physical Progress (As of 31 Dec, 2013)
Financial Progress : 42 %
Physical Progress : 70.38 %
Physical Progress : 85 %
(excluding PTB)
Capital Outlay (Till date) : Rs. 36.04 Billion
.
19
Progress : Air/Land Side Infrastructure
Summary:
Runways & Taxiways : 98 %
Aprons : 85 %
Airfield Lighting System : 91 %
ATC Complex, FCR & RR Bldg : 53 %
Hydrant Refueling System : 98 %
Road Network : 80 %
Cargo Complex : 85 %
Boundary wall / Fencing / Watch towers : 80 %
Overall :85 %
Time For Completion : June, 2014 20
Progress : Passenger Terminal Building
Overall Physical Progress : 68.87 %
• Grey Structure completion : 98 %
• Steel Structure completion : 99 %
• Curtain walls : 40 %
• Equipment installation : Yet to begin
* The local JV partner M/s FWO is considerably behind schedule
and is being constantly pushed to enhance pace of progress.
21
Peripheral Facilities
22
Directive number PM Sectt UO 10-PMP/DS(1A-2)/2005 (Vol II) dated May 10, 2006 Requisite funds be provided by Federal Govt (PSDP) to WAPDA/ NHA/ Irrigation Department Punjab etc to expedite provision of peripheral facilities to BBIAP Project
Prime Minister’s Directive
23
President’s Directive
The Honourable President of Islamic Republic of
Pakistan was pleased to direct the Planning
Commission (March 2011) to monitor the progress
and assist CAA in resolving issues pertaining to
Peripheral Facilities
24
Road Network
25
New Benazir
Bhutto International
Airport
Road Network Plan : NHA (Original Plan)
1
2
3
26
Peripheral Facilities : Road Network
• Layout plan of the external road network to be finalized by National
Highway Authority in coordination with the Ministry of Planning &
Development
• Required Completion Time : 18 Months
27
Electric Power Supply
28
132 KV Grid Station
Electrical Power Supply
Initial installed capacity = 52 MVA
29
Peripheral Facilities : Electric Power Supply
CAA deposited its share of Rs. 332 M (17 Sep, 2012).
Contract for 132 KV Grid Station awarded by IESCO to M/s SIEYUAN of
China on 08 Apr’ 13. Construction site handed over to IESCO.
Construction of Main Power Line transmission towers started by IESCO.
30
Bulk Water Supply
31
Rain Water Harvesting • Punjab Small Dams organization has proposed 05 nos. potential rain
water dam sites for NBBIAP
• Feasibility Studies to be initiated to identify Three (03) potential Rain
water dam sites for NBBIAP
• Subsequent construction of most feasible rain water dam site
• Estimate for feasibility studies prepared by Punjab Small Dams
Organization
• Pre-qualification notice to be floated in national print media on 27th
Jan, 2014
32
Pakistan Civil Aviation Authority
THANK YOU