Network Design OptimizationV1

  • Upload
    dstar13

  • View
    219

  • Download
    0

Embed Size (px)

Citation preview

  • 8/10/2019 Network Design OptimizationV1

    1/22

    1

    Current problems of hydrological networks design and optimization.

    Introduction

    A hydrological network is composed of a group of stations (gauges) that are designed and operated to

    make observations under special observation programs and address a single objective or a set of interrelated

    objectives. Observation data collected in the network can be used, for example, only for a water resources

    assessment, a development plan, a project design, or for designing flood protection measures including flood

    forecasting. In most cases, however, a hydrological network is designed for addressing a set of interrelated

    objectives. In this case, a network usually consists of several types of gauges and stations. For example, a

    flood-warning network might include both stream and stage gauges, meteorological stations, precipitation

    network, snow courses and agrometeorological stations and posts providing information on the state of soil

    cover (soil water storage at various horizons, soil freezing depth, etc.).

    Today, more than ever before, the range of hydrological networks objectives and the uses of

    collected data has extended. Along with conventional uses of hydrological information, such as water

    resources assessment, project design, water resources planning, hydrological forecasting and water quality

    control, such applications of hydrological data as environmental monitoring, flow accounting and monitoring

    of water quality in transboundary water bodies, development of local hydrological forecasting and flood-

    warning systems, monitoring of water allocation processes and provision of data for management of water

    utilization systems are gaining in importance.

    Hydrological network optimization is a slow and evolutionary process, starting with a minimum

    number of stations, and increasing gradually (as necessary) until an optimum network is attained. An

    optimum network is achieved when the amount and quality of data collected and information processed is

    economically justifiable and it meets the users needs.

    1. Evolution of methods for hydrological network design and optimization

    Most consideration to the issues of hydrological network design and optimization was given in the

    USA, Russia and Canada. The most comprehensive review of the history of network design since the 1930s

    up to the present was provided by the scientists from Trent University (Watershed Science Centre)( Richard

    S. Pyrce, 2004), some of which is cited here.

    Initially, the design of early hydrological network was governed almost exclusively for some specific

  • 8/10/2019 Network Design OptimizationV1

    2/22

    2

    project, for example, flood mitigation, irrigation or dam construction. The increased need for data during the

    Second World War, for economic efforts in support of the war or for military operations, led to the

    realization that something more was needed than an ad hoc series of hydrological stations installed without

    much reference to one another. This led to the development of a rationale for the design of hydrological

    networks based on a quasi-uniform areal coverage to take account of the particular characteristics of the

    element being measured. However, much of the literature on network design at that time concentrated on

    offering practical advice based on experience. Nemec and Askew (1986) referred to this as the basic

    pragmatic approach.

    As early as the late 1930s, the first attempts were made to use statistical estimates of error in

    computing areal precipitation as a basis for choosing optimum gauge density (Wilm et al., 1939).

    In Russia, the first attempts at network design were made at the State Hydrological Institute (SHI). In

    1934, the Director of SHI V. Glushkov proposed an approach based on a so-called geographic-hydrological

    method (Glushkov, 1933). One of the principles for network design was to satisfy spatial and linear

    interpolation of hydrological regime elements. This approach was further developed by I. Karasev (1968,

    1972, 1980,1988).

    Main principles and criteria for establishing an optimum network suggested by Karasev are based on

    continuous representation of fields of hydrological elements. Optimum network design on rivers with natural

    or slightly disturbed regimes is based on continuous representation of a field of hydrological elements which

    can be assessed by zonal stream-flow characteristics. This can be achieved by establishing most of the

    stations so that they close zonal-representative areas of watersheds (Azr). Density of stations, i.e. distance

    between central points of the basins, should offer a possibility to accurately estimate discharge characteristics

    in ungauged basins. At the same time, stations should be located far enough from each other so as to detect

    changes (gradient) of a norm of a hydrological element. On the assumption of homogeneity of the field of

    elements within a hydrological region, two main criteria, correlation and gradient, for watershed area closed

    by a station were suggested. Optimum watershed area Ao covered by one station should satisfy the

    following relation:

    gr Ao< Ac,

    Where Agr Ac are the gradient and correlation criteria satisfying correspondingly the smallest and the

    largest distance between the centres of the basins under consideration.

    On rivers with watershed area A Ao, networks are

    designed depending on the aims of studying conditions of formation and forecasting.

    In most cases, optimum value of A corresponds to medium watersheds for which zonal type of

  • 8/10/2019 Network Design OptimizationV1

    3/22

    3

    discharge formation is characteristic. For small (azonal) rivers with watershed area A A, large

    (polyzonal) rivers, with A A , and rivers with human-affected discharge, a site by site principle depending

    on the structure river systems would be justifiable. Most early approaches to planning and optimization of

    hydrological networks were based on a conclusion that a network should be comprised of two parts: a group

    of base stations including those with continuous time-series, and a group of secondary stations to be operated

    for relatively short periods (5 to 10 years) until sufficient data are collected to provide reliable correlation

    with factors observed at base stations. Optimum networks should also provide methods for determining with

    any required accuracy streamflow characteristics at any ungauged point.

    In the late 1970s and 1980s, statistical approaches and regression analysis had widespread

    application in network design (Moss and Karlinger, 1974; Benson and Matalas, 1967)

    Moss and Tasker (1991) compared and tested two U.S. based network design technologies: 1) the

    Network Analysis for Regional Information (NARI) (Moss et al., 1982; Moss and Tasker, 1991)) and 2) the

    Network Analysis Using Generalized Least Squares (NAUGLS). Both methods have a common objective: to

    maximize regional information within a limited budget and time horizon. NARI evolved to fill a need

    highlighted by a national study of the U.S. Geological Surveyss streamflow data collection program (Benson

    and Carter, 1973). The NARI method is based on a regional regression approach (Benson and Matalas, 1967)

    for the definition of streamflow parameters, and its output is and evaluation of the likelihood of various

    levels of improvement in the regression relations that may that may be obtained by the collection of

    additional streamflow data. The strength of this approach is that a stream gauge manager can develop a

    network strategy based on any one of a combination of stations.

    The NAUGLS procedure used a generalized least square estimator proposed by Stediner and Tasker

    (1985) to estimate parameters of a regression model of stream flow characteristics on physiographic

    characteristics.

    Further attempts to design networks applied socio-economic approach and the information theory.

    Mawdsley et al. (1990) discussed a design procedure using a simplified Bayesian decision theory model to

    examine the economic value of data for the design of flood protection hydrometric network.

    Various methodologies have been recently developed for practical application in hydrological

    network design. Network design theory continues to develop constantly evolving new approaches making

    maximum use of statistical and regression methods.

    Hydrological observation data should provide computations and forecast of hydrological

    characteristics for certain basins with account of their area and physiographic features. Therefore,

  • 8/10/2019 Network Design OptimizationV1

    4/22

    4

    hydrological network should represent the impact on hydrological regime of both zonal and azonal factors as

    well as natural anomalies of a region.

    The existing methods of calculating discharge form ungauged river basins and basins with short

    observation periods are based on the method of hydrological analogy. Therefore, the key criterion in solving

    the problems of efficiency of a hydrological network is the possibility to select reliable analogues to

    ungauged rivers of a region.

    As hydrometeorological processes develop within geographical space, it is feasible to use state-of-

    the-art GIS-technologies to describe them objectively (Bobrovitskaya et all, 2003; 2004].

    A state-of-the-art HYDRONET technology developed in Russia (Bobrovitskaya, Kokorev at all,

    2001; Bobrovitskaya, Kokorev at all, 2004, 2009) enables one to:

    1) reveal homogeneity in observation series;

    2) obtain quantitative estimates of representativeness for each gauging station used in the analysis;

    3) explore the the effective relationships with correlation coefficients that make it possible to use

    them directly in computations to extend observation series;

    4) calculate errors of interpolation of a study hydrometeorological characteristic (maximum,

    minimum annual water flow and sediment discharge or meteorological characteristics, such as precipitation,

    air temperature and others) at each node of a standard network depending on the number of stations and

    natural variations of a study characteristic;

    5) depict the results of estimation of interpolation errors on a map;

    6) analyze the distribution of interpolation errors on a map with account of location of population

    centres, motor- and railways, deposits, power lines, pipeline routes etc in order to identify the number and

    location of gauging stations to establish or renovate.

    Besides, the tool provides a diversity of functions to be used in hydrological computations (annex 1).

    Among the basic analytical techniques used in network design in the present time are:

    a) cartographic analysis;

    b) correlation and regression methods;

    c) probabilistic and deterministic modelling;

    d) regionalization techniques.

    Each method has particular applications and the choice depends on the type of problems to be

    addressed, limitations of observation data, planned expenditures, population density and economic potential

    of a region, etc. In Russia, a genetic principle making use of cartographic analysis and regionalization

    techniques was applied in hydrological network design. Fundamental research into the problem of zoning of

  • 8/10/2019 Network Design OptimizationV1

    5/22

    5

    the Russian territory with respect to hydrological regime formation, types of river recharge, intra-annual flow

    distribution, etc. (Kuzin, 1960) was initiated in the period of the hydrological network formation.

    By the late 1940s and 1950s, expanding international cooperation led to increased interest for

    intergovernmental organizations to offer guidance on technological development. The World Meterological

    organization (WMO) responded by the late 1950s by initiating a program on operational hydrology and by

    1965 published the first Guide to Hydrometeorological Practices which included a chapter on the Design

    of Networks (WMO, 1965). In 2008, a revised fifth edition of the Guide was published.

    Since it has been recognized that establishment of a full-scale and complete network is either

    impossible or impractical in todays world (Guide, 2008), various surrogate approaches are used instead of

    designing a full-scale network providing information for addressing any objectives. For example, a common

    substitution is to maximize information contentin lieu of optimizing the economic value of the data (Guide,

    2008). If information is used properly, it can be expected to contribute to the economic worth resulting from

    a decision. It is quite obvious, however, that economic impact of information is not linearly related to its

    magnitude. This is not applicable to areas with dense hydrological network but would prove useful in poorly

    gauged basins.

    The WMO advocated that an optimum network should not be attempted until a minimum number of

    stations had not been established. This minimum network is intended as a first step to satisfy the most serious

    gaps, from the perspective of water resources development. Because of the small density of the minimum

    network, it is important that the records at all stations be of good quality.

    Major indicator of adequacy is the area covered by observations from each gauge in a network.

    According to the WMO recommendations, the density of hydrological network should provide reliable

    determination of hydrological characteristics within a certain region. Recommended minimum network

    densities for various physiographic regions are given in the Guide (2008).

    Most recently, Perks et al. (1996) studied the adequacy of hydrometeorological observations in six

    physiographic regions identified by WMO. It was found that the WMO recommendations for minimum

    density were not reached in all the regions. Network densities of polar, arid and coastal regions are close to

    the recommended ones, while mountainous and inland regions have densities 3 to 5 times lower than those

    recommended by WMO.

    On the whole, different countries and regions use different approaches to network planning, which

    will be illustrated here by several examples.

    2. Principles of hydrological network optimization with regard to economic and geographical

    conditions of individual countries

    2.1 Recent approaches to network design

  • 8/10/2019 Network Design OptimizationV1

    6/22

    6

    The United States hydrometric network.

    Since 1889, the U.S. Geological Survey (USGS) has operated a multi-purpose stream-gauging network.

    Today the USGS operates and maintains more than 85% of the U.S. stream gauging operations, including

    over 7,000 continuous-record stream gauging stations in the United States, Puerto Rico, and the Trust

    Territories of the Pacific Islands. The principles that have guided the USGS network are that:

    many partners contribute funding for the operation of gauging stations to collaboratively achieve

    federal mission goals and the individual goals of the funding agencies;

    all data is freely available to all partners and the public;

    the USGS operates the network on behalf of all partners to achieve economy and standardization of

    the availability and quality of data.

    Five key categories of federal purposes of the stream gauging network are:

    1. Interstate and international transfers measures the ability of the network to provide accepted,

    neutral data for the U.S. to use in the allocation of water transferred across the lines or

    international borders.

    2. Water budgets the goal is to be able to account for the contribution of water from each river

    basin to water resources of the country and playing a fundamental role in national water

    policies and planning.

    3.

    Flooding the goal is to provide streamflow information for populations at risk fromflooding. Real-time information is needed to provide current streamflow conditions to guide

    emergency decisions and to provide information critical to produce accurate and timely flood

    forecasts and flood zoning maps.

    4. Water quality.

    5. Long-term changes the goal is to monitor and characterize trends in streamflow in

    representative streams within each of the nations ecoregions.

    At the end of the last century the USGS developed a national NSIP program (The National

    Streamflow Information Program).

    At the core of the NSIP is a set of the USGS-funded stream gauges that are continuously operated to

    fulfill five Federal Goals:

    1. Interstate and International Waters (506 stations);

    2. Streamflow Forecasts (3,245 stations);

    3. River Basin Outflows (445 stations);

    4. Sentinel Watersheds (874 stations);

  • 8/10/2019 Network Design OptimizationV1

    7/22

    7

    5. Water Quality (210 stations).

    The proposed NSIP network would have approximately 5,280 stream monitoring gauges, of which

    approximately 1,350 would be new or reactivated gauges. Under full NSIP implementation stream gauges in

    the network will have:

    real-time data delivery;

    the ability to withstand the impact of a 200-year flood and still be operational;

    provide accurate data fro the full range of anticipated flows.

    An original approach was used for the Marylands stream gauging network modernization (Cleaves

    and Doheny, 2000). The network plan had been guided by discussions and recommendations of a

    stream-gauging workshop and by 102 responses to a questionnaire sent to 500 users of streamgauge

    data in 1998. Recommendations in November 1999 included that Marylands streamgauging

    network be increased from 97 gauges to 157 gauges.

    The additional gauges were to be activated in stages according to six priority

    management goals:

    1. Core network (20 gauges to be reactivated, 2 new gauges)

    2. Small watersheds (11 gauges to be reactivated, 10 new gauges)

    3. Coastal plain harmful algal blooms (7 stations to be reactivated, 1 new gauge)

    4. Flood Hazard (2 stations to be reactivated, 3 new stations)5. Clean Water Action Plan (2 new gauges)

    6. Unmet Coverage (2 new gauges).

    The Canadian hydrometric network. The Canadian Federal Hydrometric Network was established in the

    1890s. Since the mid-1960s up to the mid-1970s, global concern was raised of the needs of hydrometric

    data which led to a substantial increase in the number of hydrological stations. By 1975, the Canadian

    hydrometric network expanded to 3,300 stations, and then during the 1980s the number of stations remained

    relatively stable. A national survey of users of hydrometric data (Environment Canada, 1989) found that

    there was a shortage of stream gauges in Canada. It was determined that 2,000 new stations would meet the

    current and future information needs. However, instead of continued growth of the Canadian hydrometric

    network, cuts to the network were beginning to appear by the early 1990s due to increased budget pressure.

    An initial federal government budget reduction of 35% was anticipated to result in the closure of 1,100

    hydrometric stations across Canada over a three year period starting in 1995/96. A Water Monitoring

    Program Re-Engineering Strategy was developed by the Federal Government (Yuzyk et al., 1995) to focus

  • 8/10/2019 Network Design OptimizationV1

    8/22

    8

    on seven key items: rationalization, integrated planning, harmonization, modernization, commercial services,

    organization, and people. It was decided that all future monitoring would emphasize information production,

    be results driven, client focused, and minimize net costs, thus the strategy applied a business approach to

    monitoring based on the true costing of services. The actual stream gauge rationalization resulted in a total

    network reduction of 21% or 724 gauging stations; the provinces experienced similar pressures resulting in a

    19% reduction in provincially operated stations between 1990-1998. Federal funding for the network had

    declined since the mid-1970s; in 1975, the federal funding proportion was 60%, by 1989 it was 48%, and by

    1998 it was only 41%, ultimately contributing to a reduction of s tations within the network.

    The intent was to moth-ball stations, rather than decommission them. Environment Canada initiated

    a series of cooperative ventures to rationalize the network including consultations with federal departmental

    managers, provincial partners, improved management approaches, expanded partnerships, and alternative

    delivery mechanisms (Pilon et al., 1996). The rationalization process was also aimed at establishing which

    sites would continue to be important from an environmental perspective. The key issues facing the future of

    the Canadian hydrometric network were identified as:

    I) flow prediction capabilities,

    II) climate change,

    III) water export,

    IV) ecosystem health.

    Strengthened partnership would be necessary to sustain and enhance the network, and a comprehensive

    evaluation of the economic value of Canadas hydrometric value would be necessary. Environment Canada

    decided to focus its attention on national and international levels of ecosystem health, to be pursued through

    a strong support for long-term studies that contribute to the prediction of climate change impacts on

    Canadian hydrology.

    Generally, about 80% of the active hydrometric stations were initially constructed to serve a specific

    water management purpose, however over time the data from these stations also served other interests. The

    remaining 20% of the hydrometric stations were strategically located to document hydrological

    characteristics and processes required to understand the regional hydrology. Currently there are 2,500 water

    level and streamflow stations being operated under the Federal-Provincial and Federal-Territorial CSA; more

    than 720 are designated as federal stations, about 980 as provincial or territorial stations, and 781 as federal-

    provincial or federal-territorial stations. A further 92 stations are fully cost-recovered from other parties, and

    another 302 stations are contributed by other organizations, bringing the total number of active stations to

    ~2,870. An additional 5,500 hydrometric stations are no longer active, although their data are stored in the

    accessible HYDAT database (Water Survey Branch, 2002).

  • 8/10/2019 Network Design OptimizationV1

    9/22

    9

    Most of the hydrometric stations are located in the southern half of the country where population and

    economic pressures are the greatest; as a result, the adequacy of the network to describe hydrologic

    characteristics decreases significantly to the north. The federal Canadian hydrometric network was fully

    modernized with employment of new field methods and technologies, advanced data management, and real-

    time on-line access to hydrometric information.

    The European Union. The overall objective of the European Environmental Agency (EEA) is to obtain

    timely, quantitative and comparable information on the status of inland waters from all EEA member states

    so that valid temporal and spatial comparisons can be made and so that key environmental problems

    associated with Europes inland waters can be defined, quantified and monitored. The primary focus of the

    EEA is water quality, however the network also addresses surface water and groundwater quantity. Europe

    has a dense network of approximately 19,000 flow measurement stations at an average density of one station

    per 270 km2, which is justifiable considering Europes wide physical diversity, the anthropogenic factors of

    population density and land use, and river types and hydrograph regimes.

    Two broad categories of water quantity monitoring stations are considered:

    1. Statutory monitoring arising from national or international obligations, or to provide

    information for the business and operational needs of the regulators, suppliers, users and

    reclaimers of water;

    2. Surveillance monitoring to characterize and allow appraisals to be carried out on the state of

    water resources, and in conjunction with water quality measures and biodiversity, and the state of

    the water environment.

    A general surveillance network to obtain information on the general quality of rivers within the EEA

    would consist of:

    1. A basic network made up of approximately 1,425 (80%) Representative (or Index) rivers that

    are a subset of the network and ideally provide long-term summary estimates of the regional or

    national picture (selected on the basis of 1 gauge/2,000 km2), and about 355 (20%) Reference

    rivers which characterize hydrologic regimes in undisturbed catchments (selected on the basis of

    1 gauge/2,000 km2).

    2. An Impact network to record and characterize the effects of anthropomorphic interference with

    natural hydrological regimes, consisting of approximately 1,590 rivers selected, where for < 50

    inhabitants/km2,there would be one river per 10,000 km

    2and for >100 inhabitants/km

    2there

    would be one river per 1,000 km2.

    3.

    Approximately 450 Baseline rivers with catchment areas greater than 2,500 km2

    , to characterize

  • 8/10/2019 Network Design OptimizationV1

    10/22

    10

    the general runoff behavior of a region. Additional important rivers/canals in each country

    should also be included bringing the total up to 650 rivers. The results can be extrapolated to

    characterize other ungauged sites.

    4. Approximately 100 Flux rivers to assess sediment loads or contaminants entering Europes seas

    or crossing international boundaries in conjunction with other quality measurements.

    Nixon (1996) described a stream gauge network design for the EEA. He suggested a so-called

    stratification technique. For example, a statistical population of all rivers (e.g. all rivers in Europe) can be

    subdivided in to sub-populations (e.g., all the small, high altitude streams in Europe) and random site

    allocation can be applied to each sub-population (strata) separately. Stream order was suggested as an

    indicator of a river size. Using this approach the number of river reaches/river lengths meeting the criteria

    associated with each of the matrix cells would have to be defined, likely involving a GIS database of the river

    network.

    The Finnish surface water monitoring network. During the late 90s,the monitoring objectives and

    structure of the Finnish network were clarified to improve cost-efficiency (Puupponen, 1998). A decision

    was made to concentrate on water balance stations, spatial estimation stations for the transfer of discharge

    data to small natural catchments, and operational stations for the daily operation of water resources projects.

    The evaluation recommended a remarkable network reduction of 321 stations out of the existing 721 to be

    either closed or removed from the national network. However the number of closed stations was only 50

    stations and the remainder continued operating primarily outside the Water Resources Administration.

    The third step comprised of statistical analyses of the spatial estimation stations and a decision was

    made on the future extent of this sub-network. Cluster analysis and the Network Analysis Using Generalized

    Least Squares NAUGLS (see Moss and Tasker, 1991) were applied to mean discharge and various extreme

    discharge parameters. The resulting conclusion was to reduce the network down to 397 stations. The annual

    costs of the Water Resources Administration for the operation of the new modernized national hydrometric

    network decreased by approximately 32%.

    2.2. The Russian hydrological network.

    Federal Service for Hydrometeorology and Environmental Monitoring of the Russian Federation

    (Roshydromet) is the federal executive body that provides state services in the field of environmental

    monitoring, including hydrological regime of surface water bodies (river, lake and reservoir water regime). In

    order to study water regimes and monitor hydrological processes, a network of hydrological stations and

    posts was established in the Russian Federation. Roshydromet operates 24 Interregional Territorial Branches

  • 8/10/2019 Network Design OptimizationV1

    11/22

    11

    (UGMS).

    The Russian hydrological network began to develop as early as the 1874s-1884s. By 1914, the

    network expanded to 1,134 stations, of which 202 performed monitoring of stream flow. Initially, as in many

    other countries, the Russian hydrological network was designed to address specific objectives. At the first

    stage, it was intended for monitoring hydrological regimes for the purposes of construction of railways,

    railway river crossings, dams, etc. It was only in 1908 when a hydrological service was organized in Russia

    after a devastating flooding of the Ob River which hit all central provinces and caused extensive damage and

    loss of life. A number of stations were put into operational regime in order to produce regular hydrological

    forecasts.

    By 1929, all stations were integrated into a basic observation network, and the number of stations

    increased to 2,708 (863 for streamflow monitoring).

    By 1940, the number of stations in the former USSR network was 4,247 including 2,021 for

    streamflow monitoring. However, this number still did not meet the demands of practical hydrology and the

    developing economy, and a new network development plan was adopted in 1940 envisaging expanding of the

    network to more than 10,000 stations.

    During the Second World War, many stations were destroyed, and their total number somewhat

    decreased compared with 1940, but immediately after the end of the war, a second prospective development

    plan was adopted in 1946 which was completed by 1962 bringing the total number of stations to 6,143, of

    which 4,766 performed monitoring of stream flow.

    The third development plan adopted in 1974-1975 outlined further development of the network.

    Although the plan was to be fully implemented by 1990, the network expanded to 7,083 hydroposts (5,478

    for streamflow monitoring) already in 1980, resulting in an optimum number of stations envisaged by the

    first development plan.

    In the period after 1990, the former USSR experienced substantial economic difficulties which led to

    a drastic reduction of the observation network. In the end of the 1980s, the network reduced severely by

    31%. During the last decade, the reduction ceased, and the Russian hydrological network is currently

    gradually recovering (see Table 1).

    Table 1 Changes in total number of hydrological stations and posts in 1986-2010

    Number of active Type

  • 8/10/2019 Network Design OptimizationV1

    12/22

    12

    stationsriver lake

    1986 4481 3967 514

    1992 3670 3262 4081995 3423 3037 386

    1997 3114 2752 362

    1998 3089 2733 356

    1999 3053 2703 350

    2000 3059 2708 351

    2010 3069 2715 354

    Table 2 shows current quantitative and qualitative characteristics of the Russian network by UGMS.

    As for qualitative characteristics, there are 2,715 (88.5%) river stations and 354 (11.5%) lake stations. Stream

    flow is observed at 2,165 (70.5 %) stations (GP1), and sediment discharge at 688 (22.4%). The Russian

    hydrological network now comprises 1,283 reference stations and 1,433 basic (noncontinuous) stations

    funded from the Federal budget. There are also 354 supplementary stations (SS) fully cost-recovered from

    various organizations.

    The structure, composition and methodologies applied in the Russian hydrological network are

    regulated by prescriptive guidance (or guides) providing uniformity and compatibility of observation data.

    Division of stations into reference and noncontinuos (or basic) ones enables one to initiate or cease

    observations in one sites ensuring their continuity in others.

    Reference hydroposts are the most essential having long observation series which may be used in

    various generalizations, national water resources assessments, water regime studies, as well as for developing

    techniques of hydrological forecasting, including hydrological models. These amount to only 42% of the

    total number of stations.

    Table 2 Composition of the Russian hydrological network as of 01.10.2010

    Number of active

    stations in 2010 Information Reference Basic Suppl.UGMS

    total GP SS

    GP1Sediment

    dischargeGP SS GP SS GP SS GP SS

  • 8/10/2019 Network Design OptimizationV1

    13/22

    13

    1 2 3 4 5 6 7 8 9 10 1 2 13 14

    Bashkiria 68 58 10 50 17 46 5 21 5 6 1 -

    Upper-Volga 110 93 17 83 21 85 17 27 1 3 3 13 3

    Far East 158 153 5 88 21 112 5 65 0 18 -

    Transbaikalia 185 174 11 147 51 91 3 114 8 8 2 2

    West Siberia 222 197 25 169 72 101 8 80 5 4 3 43 7

    Irkutsk 181 136 45 98 36 87 37 69 26 7 8 11 1

    Kaliningrad

    CGMS15 15 - 13 - 5 - 7 - 3 -

    Kamchatka 80 80 - 74 25 46 - 46 - 25 -

    Kolyma 42 38 4 25 8 28 - 12 1 5 1 -

    Murmansk 55 40 15 40 1 30 14 19 9 1 -

    Ob-Irtysh 162 147 15 96 36 92 62 2 9 16 7

    Volga 102 83 19 73 48 60 16 26 6 7 1 20 2

    Maritime 74 71 3 55 15 66 3 41 1 6 4 -

    Sakhalin 41 41 0 37 3 25 - 17 - 4 - -

    North 228 216 12 173 6 180 10 94 10 05 17 1

    North-West 218 175 43 154 5 83 31 70 17 2 8 23 8

    North Caucasus 254 238 16 199 135 126 11 87 4 17 2 34 -

    Mid Siberia 219 195 24 158 74 128 14 74 8 20 6 1 -

    Tatarstan 33 21 12 21 7 18 12 5 4 5 1 -

    Ural 144 115 29 94 0 99 23 38 11 8 3 19 5

    Central 192 160 32 115 25 106 21 57 8 0 0 13 4

    Central

    Chernozem

    87 84 3 76 27 67 2 33 - 2 9 -

    Chukotka 18 18 - 12 7 15 - 9 - 2 -

    Yakutsk 181 167 14 115 48 117 6 79 5 2 36 2

    Total: 3069 2715 354 2165 688 1813 238 1152 131 1252 181 312 42

    As it was already defined, major indicator of a network adequacy is the average area served by one

    hydrological station, which is also referred to as hydrological network density. As of 1.10.2010, the Russian

    hydrological network density was 1 station per 5,250 km2, with 1 station per 7,860 km

    2 for information

  • 8/10/2019 Network Design OptimizationV1

    14/22

    14

    network solely (Table 3). Fifteen years ago the network density was 1 stations per 3,400 km 2in comparison

    with the US network density of 1 station per 1,338 km2, the Canadian per 3,691 km

    2, the French per 203

    km2, and the Japanese per 67 km

    2.

    Table 3. Hydrological network density by UGMS

    Area served by one

    station, km2

    UGMS Populatio

    n density,

    inh/km2

    Total

    number of

    stations

    Number

    of

    informatio

    n stations

    informatio

    n network

    whole

    network

    1 Bashkiria 28.5 68 51 2813 2110

    2 Upper-Volga 30.0 110 102 2577 2390

    3 Far East 2.12 158 117 10290 7620

    4 Transbaikalia 2.73 185 94 8148 4140

    5 West Siberia 11.1 222 109 7892 3875

    6 Irkutsk 3.36 181 124 6123 4195

    7 Kaliningrad CGMS 63.2 15 5 3000 1000

    8 Kamchatka 0.76 80 46 9130 5250

    9 Kolyma 0.40 42 28 16095 10730

    10 Murmansk 6.16 55 44 3238 2590

    11 Ob-Irtysh 3.5 162 92 27047 15360

    12 Volga 30.5 102 76 4711 3510

    13 Maritime 12.5 74 69 2402 2240

    14Sakhalin

    6.28 4125 3485 2125

    15 North 3.15 228 190 5969 4974

    16 North-West 23.0 218 114 3136 1640

    17 North Caucasus 44.0 254 137 4357 2350

    18 Mid Siberia 0.85 219 142 23843 15460

    19 Tatarstan 55.6 33 30 2409 2190

    20 Ural 25.7 144 122 3925 3325

  • 8/10/2019 Network Design OptimizationV1

    15/22

    15

    21 Central 63.0 192 127 4452 2945

    22 Central Chernozem 44.8 87 69 2459 1950

    23 Chukotka 0.07 18 15 49180 40983

    24 Yakutsk 0.3 181 123 25090 17050

    Total: 3069 2051 7860 5250

    In 2006, Roshydromet began to implement a project Modernization and technical re-equipment of

    Roshydromets institutions and organizations. The project is aimed to improve the level of services in the

    field of hydrometeorology and other related fields provided to the government of the Russian Federation,

    other authorities, and population through re-equipment of its technical and technological facilities andstrengthening of institutional and management structure. Three pilot network modernization projects are

    being currently implemented in the Kuban, Oka and Ussuri river basins.

    Modernization objectives being addressed under the above mentioned projects include optimum

    design and re-equipment of hydrological stations with modern instruments for water level and discharge

    observations, including automated hydrological stations for water level, flow velocity and discharge

    measurements.

    2.3 Hydrological network modernization and optimization: case-study of the Kuban River

    Optimization of hydrological networks in each of the above mentioned regions was governed by

    general principles developed by the State Hydrological Institute. The principles take account of physiography

    and socio-economic features of the regions. Optimum location of reference and basic (noncontinuous)

    stations was evaluated to satisfy the requirements of spatial and linear interpolation of the hydrological

    regime characteristics with the use of correlation and regression analyses. Optimum location of the

    information hydrological network (IHN) was analyzed to meet more extensive set of requirements.

    Data observed at the IHN are intended for hydrological forecasting services and providing the

    population with timely warnings on the state of water bodies, floods and other extreme hydrological events,

    as well as for provision of information for water-economy complexes. The IHN stations are either included in

    the basic hydrological network or purposely established.

    The whole Kuban basin is divided into upper, middle and lower reaches depending on physiographic

    characteristics and the level of economic development.

    Stations located in the Kuban upper reaches and the heads of its tributaries should provide data to be

  • 8/10/2019 Network Design OptimizationV1

    16/22

    16

    used in the models for forecasting discharge formation of small and medium rivers in the basin. Such models

    are based on the account of discharge formation factors of a watershed and use large input datasets including

    data on snow water content, precipitation, soil moisture, etc. Distributed-parameter models are particularly

    sensitive to network densities (1 gauge per 200 to 400 km2) and the content of observations.

    Regression models using discharge characteristics of small and medium rivers as predictors are

    commonly used for outlets. Usually, such models are well enough provided with data derived from the IHN.

    Moreover, an opportunity exists to select just a few the most informative stations depending on the type of a

    forecasting model applied.

    In order to provide information for flash flood simulation in the Kuban basin the following was

    suggested:

    to establish several automated stations in areas with elevation more than 1,500 m, primarily in the

    upper reaches of the Ullukam, Uchkulan, Teberda, Aksaut, Bolshaya Laba and Pshish rivers.

    to establish automated meteorological stations at the same sites and simultaneously with the

    automated hydrological stations;

    to establish several meteorological, snow and precipitation measuring sites in areas with elevation

    more than 1,500 m near the Main and the Lateral Caucasus ranges, and to equip them with either

    satellite or radio communication facilities to ensure timely provision of information to data

    collecting centres; to increase the number of stations on small foothill rivers.

    Timely flood forecasting is also critical for the middle Kuban. However, in contrast to the upper

    reaches, different type of models enabling calculation of flood wave transformation and movement are

    required. In this case, flood forecasting models use data from stations located along the length of rivers. A

    chain of such stations makes it possible to forecast flood wave propagation in river systems. There is a

    diversity of approaches to solving such tasks. One of the simplest and most common methods is the method

    of corresponding levels and discharges which consists in establishing a regression relationship between these

    characteristics at adjacent stations. Stations at this reach of a river should be located to meet the requirements

    of the lead-time of a forecast which is determined by lag time of a flood wave.

    For the middle and upper Kuban, a crucial task to be solved when designing a network is provision of

    real-time information (both calculations and forecasts) for water resources utilization systems. One of the

    most developed water resources utilization systems Krasnodarskoye reservoir, with a number of water

    distribution units and high regulating storage capacity, is located in the middle and lower Kuban. The

  • 8/10/2019 Network Design OptimizationV1

    17/22

    17

    hydroposts located in these reaches should meet the objectives of water level monitoring and control and

    forecasting flash flood propagation, as well as should ensure reliable calculations and forecasting of inflow to

    hydraulic structures and the Krasnodarskoye reservoir.

    To meet these needs, 18 new hydrological stations were established, and modernization of already

    existing stations was initiated with installation of automated hydrological stations for continuous water level

    monitoring and transmission of the observed data to the purposely established data collection centre in

    Rostov-on-Don (see Figure 1).

    Figure 1 Location of operating and newly established stations of the North Caucasus UGMS in the

    Kuban River basin

    Conclusions

    It seems obvious that decisions on designing comprehensive observation systems can be made only in each

    specific case with due account of socio-economic conditions and attraction of investments of interested

    authorities and branches of national economy.

    Optimum network design involves, first of all, identification of zonal and azonal elements in the

    hydrological process and separation of the specific from the general. This task can be solved through

  • 8/10/2019 Network Design OptimizationV1

    18/22

    18

    hydrological zoning of an area. Hydrological zoning consists in classifying regions with regard to uniformity

    of physiographic and hydrological conditions, which offers a possibility to make a proper generalization of

    main regime characteristics within each region and extrapolate them to ungauged basins using methods of

    hydrological analogy. Hydrological zoning is based on the homogeneity of discharge formation conditions

    which is estimated from interrelations between water balance elements. Hydrological zoning of an area takes

    account of medium and small rivers comprising the majority (98-99%) of a channel network. As a result,

    each part of an area under consideration should be included into one of the hydrologic regions. Basic

    hydrological network should be designed to comply with principles of optimum spatial and temporal

    resolution of observations.

    As is known, reliability of hydrological characteristics depends not only on the accuracy of

    observations, but also on the mathematical background for interpretation of the results. Therefore, a need

    arises to optimize not only networks and means and methods of observations, but also procedures and

    techniques of data processing, especially with regard to on-line data processing.

    Information hydrological network should provide data for flood forecasting models as well as models

    for calculation and forecasting of inflow to hydraulic structures and reservoirs. Currently, the Russian

    information network does not to a full extent meet the requirements of the communities, water-economy

    complexes, agriculture, recreation, and others. Information on the state of a river is transferred first of all to

    data collection and forecasting centres, and only after that it returns to local users in the form of forecasts.

    That is why development of optimization procedures for data collection and dissemination is of critical

    importance.

    One of the most important objectives of hydrological networks is provision of observations within the

    environmental monitoring system (EMS). In Russia, environmental monitoring of rivers, canals, lakes and

    reservoirs is performed by the basic hydrological network and the state water quality observational network,

    providing that specific types of observations required for environmental monitoring are included in its

    observation program.

    Location of the EMS stations is defined by the requirements of water use and water quality

    monitoring. Such monitoring is performed on the basis of channel water balances, channel sediment

    balances, and estimation of chemical pollutants concentration. Water quality control implies estimation not

    only of concentration of contaminants and sediments, but also of their discharge over a certain period, which

    enables identification and forecasting trends in hydrochemical regime. The above aspects should also be

    addressed in designing optimum hydrological networks.

    Summing up the above considered issues, one can mention that, in spite of the variety of requirements

    to hydrological network optimization, there are no insoluble contradictions between them. As such, network

  • 8/10/2019 Network Design OptimizationV1

    19/22

    19

    optimization procedures may require increased network density in some parts of a basin and reduced number

    of stations in others.

    It should be also noted that economic aspects such as costs to design and maintain a network should

    also be taken into account in network planning and optimization. It appears that hydrological network

    operation and maintenance should be funded from federal and regional budgets, but, as the analysis has

    shown, many countries are now facing the problem of attracting funds from business and other entities using

    hydrological information.

    References

    V.G. Glushkov (1933) Geographical and hydrological method Izv. GGI, 1933, No 57-58. (in Russian)

    Bobrovitskaya N.N., A.A. Kokorev (2009) Development of a hydrological network of observation in

    conditions of global warming (an example of Yakutia, Eastern Siberiya), 12-th Riversymposium, Brisbane,

    Australia.

    Bobrovitskaya N.N., Bestsennaya M.A., Kokorev A.V. and Nedogarko I.V.(2001) Research network

    and its data to estimate transboundary transfer of water, sediments and pollutants. Hydrological Challenges in

    Transboundary Water Resources Management. International Conference Koblenz, Germany 25-27

    September 2001, pp.201-205.

    I. F. Karasev (1968) On the principles of hydrological network design and prospective development Trudy GGI, 1968,

    No164, 3- 36. (in Russian)

    I. F. Karasev (1972) On the structure and principles of basic network rationalization Meteorologiya I Gidrologiya,

    1972, No 5, 54-62. (in Russian)

    I. F. Karasev River hydrometry and water resources accounting Gidrometeoizdat, 1980, 310 p. (in Russian)

    I. F. Karasev, V.A. Lobanov (1988) Assessment of efficiency of spatial interpolation of streamflow

    characteristics and optimum hydrological network in the USSR - Trudy GGI, 1988, No 325, 3-13. (in

    Russian)

    P.S. Kuzin Classification of rivers and hydrological zoning of the USSR, Gidrometeoizdat (1960) 455

    p. (in Russian)

    Benson, M.A. and Matalas, N.C., 1967. Synthetic hydrology based on regional statistical parameters.

    Water Resources Research, 3: 931-935.

    Moss, M.E. and Karlinger, M.R., 1974. Surface water network design by regression analysis. Water

    Resources Research, 10: 427-433.

    Mawdsley, J.A., Ball, D.B. and Adeloye, A.J., 1990. Evaluating a streamgauge network: a case study of

  • 8/10/2019 Network Design OptimizationV1

    20/22

    20

    data value for flood protection schemes. In: Economic and social benefits of meteorological and

    hydrological services. WMO 733, Geneva, Switzerland, 325-332.

    Moss, M.E. and Tasker, G.D., 1991. An intercomparison of hydrological network-design

    technologies.Hydrological Sciences Journal, 36: 209-221

    Nemec, J. and Askew, A.J., 1986. Mean and variance in network-design philosophies. In: Moss, M.E.

    (ed.),Integrated Design of Hydrological Networks, Proceedings of the Budapest Symposium, IAHS

    PublicationNo.158, 123-131.

    Nixon, S.C. (ed.), 1996. European Freshwater Monitoring Network Design. European Topic Centre on

    Inland Waters, Topic report no. 10/96, European Environment Agency (http://reports.eea.eu.int).

    Perks, A., McLaurin, I., Harvey, K., Wedel, J., Johnson, B. and Warner, L., 1991. Hydrometric data

    collection and interpretation in the Prairie Provinces and Northwest Territories. Canadian Journal of Civil

    Engineering, 18: 58-66.

    Puupponen, M. 1998. Structural development of the Finnish National Hydrometric Monitoring

    Network. Monographs of the Boreal Environment Research No.12, Finnish Environment Institute, Finland,

    108p.(www.vyi.fi/eng/orginfo/publica/ber/monogr/berm_12.htm)

    Richard S. Pyrce, Ph.D., 2004, Review and Analysis of Stream Gauge Networks for the Ontario Stream

    Gauge Rehabilitation Project.Watershed Science Centre (Trent University, Peterborough, Ontario)

    Stedinger, J.R. and Tasker, G.D., 1985. Regional hydrologic analysis ordinary, weighted and

    generalizedleast squares compared. Water Resources Research, 21: 1421-1432.

    Water Survey Branch, 2002. The Water Survey of Canada Program Hydrometric Program.

    (www.msc.ec.gc.ca/wsc/hydrometric)

    Wilm, H.G., Nelson, A.Z. and Storey, H.C., 1939. An analysis of precipitation measurements on

    mountainwatersheds. Monthly Weather Review 67(6), 163-172

    World Meteorological Organization, 1965. Guide to Hydrometeorological Practices (1st ed.).

    WMONo.168.TP.82, Geneva, Switzerland.

    World Meteorological Organization, 2008. Guide to Hydrometeorological Practices (1st ed.).

    WMONo.168. Geneva, Switzerland.

    Yuzyk, T., Allen, P., Cantin, J-F., Kamp, L., Renouf, M., Wedel, R., Brimley, B., Day, T., Pilon, P. and

    Tassone, B., 1995. Water Monitoring Programs Re-engineering Strategy: Hydrometric Program

    Rationalization. Environment Canada, Ottawa.

    ANNEX 1

    FEDERAL STATE-FINANCED ORGANIZATION The State Hydrological Institute (FSFO

  • 8/10/2019 Network Design OptimizationV1

    21/22

    21

    SHI)

    The Valdai Branch of FSFO SHI

    Dr. N. N. Bobrovitskaya, A. V. Kokorev, Senior Research Fellow

    HYDRONET-2011:

    AUTOMATED HYDROLOGICAL NETWORK DATA ANALYSIS TECHNOLOGY

    WITH THE AIM OF ITS OPTIMIZATION

    ST. PETERSBURG, VALDAI

    2011

    TABLE OF CONTENTS

  • 8/10/2019 Network Design OptimizationV1

    22/22

    22

    pgs.

    INTRODUCTION

    1 THE PRINCIPAL FOUNDATIONS OF THE NETWORK ANALYSISMETHOD USED IN THE PROGRAM

    2 INITIAL/INPUT/SOURCE DATA PREPARATION

    3

    THE PROGRAM STRUCTURE, ITS MAIN MENU, SELECTING

    THE STUDY AREA AND THE HYDROLOGICAL

    CHARACTERISTIC

    4 THE DATA CORRELATION FUNCTIONAL WINDOW

    4.1 Implementation of the Correlation function task

    4.2 Implementation of the Representativeness task

    4.3 Implementation of the Effective Correlations task

    4.4 Implementation of the Interpolation task

    4.5 The Additional parameters menu option

    4.6 The Schematic map of the network menu option

    5 THE ANALOGS FUNCTIONAL WINDOW OF THE PROGRAM

    5.1 The Select object menu option

    5.2 The List of analogs menu option

    5.3 The Correlation graph menu option

    5.4 The Cross-integral curve menu option

    5.5 The Chronological graph menu option

    5.6 The Correlation analysis menu option

    6 THE STATISTICS FUNCTIONAL WINDOW

    BIBLIOGRAPHY