1 Joe Feskanin – Team Leader Elkin Mejia – Lehigh Intern Himanshu Katiyar– Lehigh Intern ESC Team Introduction

Nestle Waters Na Energy Analysis Project

Embed Size (px)

Citation preview

Page 1: Nestle Waters Na Energy Analysis Project

1

Joe Feskanin – Team Leader

Elkin Mejia – Lehigh Intern

Himanshu Katiyar– Lehigh Intern

ESC Team

Introduction

Page 2: Nestle Waters Na Energy Analysis Project

2

Objectives

1. Overview of Power Reduction Opportunities

2. To develop an open relationship between Nestle and the ESC

Page 3: Nestle Waters Na Energy Analysis Project

3

• The plants produce Nestle Pure Life and Deer Park water• Produce about 5 million bottles of water a day• They ship out typically 500 trucks a day• Energy costs are approximately $300,000 a month for each plant

• Newer plant intends on installing three more lines along with all additional support equipment needed• Newer plant will also install two to four additional injection molders• Will create room for up to an additional 100 employees in newer plant

Current Plants

Future Plans

Nestle Waters Background

Page 4: Nestle Waters Na Energy Analysis Project

4

Project Goals

• Create Flow diagrams of plants’ energy distribution for Nestle Waters to use as training tools for employees

• Find the breakdown of kWh a month among the plants’ major equipment categories/Pareto analysis

• Find ways for Nestle Waters to cut energy costs before 2010

• Compare the energy consumption between their new plant vs. a second old plant and locate the gaps between them

• Research feasibility of alternative energy sources

Page 5: Nestle Waters Na Energy Analysis Project

New Power Distribution Block Diagram: Plant I

5

Page 6: Nestle Waters Na Energy Analysis Project

6

Results: Plant I

Energy Consumption vs. Equipment (Percentage Distribution)

5,80415,31021,30337,18737,652

225,330255,660

390,820

535,323

642,079

0

100,000

200,000

300,000

400,000

500,000

600,000

700,000

800,000

900,000

1,000,000

Equipment

kWh

50.8% (3)

49.2% (4)

770,389

50.8% (2)

49.2% (1)

617,888

49.6% (2)

144,691

50.4% (1) 21.4% (1)

20.7% (2)

20.7% (3)

18.3% (4)

864,998

18.9% (5)

19.5% (1)

19.5% (2)

19.5% (3)

23.7% (8)

17.8% (9)

Equipment energy consumption (kWh) (Calculations are based on 5 lines running at full production for 29 service days at $.068/ kWh).

Page 7: Nestle Waters Na Energy Analysis Project

New Power Distribution Block Diagram: Plant II

7

Page 8: Nestle Waters Na Energy Analysis Project

Estimated Results: Plant II

8

Equipment energy consumption (kWh) (Calculations are based on production for 29 service days at $.068/ kWh).

Page 9: Nestle Waters Na Energy Analysis Project

9

Discussion