Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Nepal: Upper Trishuli 1 Hydro Project
Project Preparation Missions
March 16-23 and April 19-24, 2015
AIDE-MÉMOIRE
I. Background
1. This Aide Memoire provides a summary of key findings from two due diligence missions that were
undertaken, respectively, from March 16-23, 20151, and April 19-24, 2015. Both missions were with respect
to the Upper Trishuli (UT1) Hydro Project - a run-of-river project with an installed capacity is 216 MW to
produce an estimated 1,533.1 GWh per year – located on the Trishuli River in Rasuwa District of central Nepal.
2. The first mission (the WB mission2) was led by Sandeep Kohli, Task Team Leader (TTL), and Patrice
Caporossi, the Co-Task Team Lead (Co-TTL), while the second mission, was led by International Finance
Corporation (IFC) (the UT1 Lenders’ mission) included representatives from various commercial and
developmental financial institutions, as well as WBG members, including MIGA3. From the World Bank,
Pravin Karki, Arnaud Braud, and Leanne Farrell – covering respectively, technical, commercial, and
environmental aspects of due diligence, were part of this UT1 Lenders mission.
3. On April 25, 2015 just at the end of the UT1 Lenders’ mission, the first of two devastating earthquakes
struck Nepal. This earthquake with epicenter at Barpak, Gorkha, killed over 9,000 people, and injured over
23,000. There was widespread damage in Rasuwa District, including at the UT1 site. Road access to the site
was cut off, and there were casualties reported. The earthquake was followed by several aftershocks which
are continuing till date. Another very significant earthquake followed on May 12, 2015, with an epicenter
northeast of the Gorkha earthquake.
4. As a result of these tragic occurrences, further discussions on the project halted, as attention focused
on search, rescue, and then reconstruction. An early May, 2015 planned mission by the WB Lead Social
Specialist, Chaohua Zhang was cancelled.
5. Following two devastating earthquakes, the government as well as the partner communities are now
re-focusing on the larger hydro-power agenda, and making plans for re-engagement. In light of these
developments, this Aide Memoire is being shared to document the findings from past missions, while
recognizing that the post-quake picture has changed significantly. Therefore some of the discussions,
observations and findings may no longer be as pertinent, but are included more for record keeping.
Furthermore, there will be a need to adjust timelines, tasks, and priorities. In particular, an assessment of post-
quake damage to the site, as well as a review of design from an earthquake resilience standpoint will be needed.
1 The Nepal leg of the WB mission was followed by a smaller team (Sandeep Kohli, Patrice Caporossi, and Arnaud Braud), going
to Singapore (March 24-25), and Seoul, South Korea (March 26-27), to meet respectively, potential lenders and senior
representatives from the sponsors. In Singapore, Andre Van Hoeck (Principal Investment Officer), Katherine Koh
(Investment Officer), and John Grosebeek (Principal Syndications Officer) from IFC also joined. Andre Van Hoeck, was also
present in Seoul.
2 The WB team: Sandeep Kohli (TTL, Sr. Energy Specialist), Patrice Caporossi (Co-TTL, Sr. Infrastructure Finance Specialist),
Pravin Karki (Sr. Hydropower Specialist),Tang Jie (Program Leader), Rabin Shrestha (Sr. Energy Specialist), Drona Raj Ghimire
(Environment Specialist), Gregory Scopelitis (Energy Specialist), Arnaud Braud (Infrastructure Finance Specialist), Gunjan
Gautam, (Consultant), Barsha Pandey (Consultant) from IDA and Cristina Celentano (Investment Analyst) from IFC. Alina Thapa
(Team Assistant) provided the administrative and logistical support in the country office.
3 From MIGA, Jaeyoung Jin (Underwriter), Petal Jean Hackett (Economist), Dessislav Dobrev (Lawyer), Junglim Hahm (Korea
Representative) and Kate Wallace (Environmental and Social Specialist) joined the mission.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Aide Memoire, UT1 -2- August 19, 2015
The World Bank is going to look into these factors, and such a review is also being undertaken by the project
sponsors and IFC, as a part of the planning.
II. The World Bank Mission (March 16-27, 2015)
6. A World Bank (WB) preparation mission for UT1 was carried out with the following itinerary: (a) Nepal
(March 16-23), (b) Singapore (March 24-25), and (c) South Korea (March 26-27). The team was led by
Sandeep Kohli, Task Team Leader (TTL), and Patrice Caporossi, the Co-Task Team Lead (Co-TTL), with
the objective of conducting due diligence on the Nepal Upper Trishuli 1 (UT1) hydropower project.
7. The team met with officials from the Ministry of Finance (MoF), the Ministry of Energy (MoE), the
Nepal Electricity Authority (NEA), the Department of Electricity Development (DoED), the Investment Board
Nepal (IBN), the Nepal Rastra Bank (NRB), and local commercial banks. The mission team also consulted
with development partners including Asian Development Bank (ADB) and Department for International
Development (DFID). The names of officials met during the mission are listed in Annex 1 and more details of
the discussions are in Annex 2.
8. MoE as the relevant Line Ministry, and NEA as the power off-taker, are the key counterparts for UT1.
The Nepal Water and Energy Development Corporation (NWEDC), is the Project Company, responsible for
project development and operations. The South Korean utility, KOSEP, is the lead investor in NWEDC,
alongside IFC and other partners. As per NWEDC, the construction wrap is to be provided by a joint venture
between DAELIM and KYERYONG (D&K JV), two South Korean companies. The WB team met with
representatives from all these organizations during this mission.
9. The WB team visited the UT1 project site, where they were briefed on the project structure. The UT1
project plan included: (i) underground tunneling works of about 10km (intake, headrace); (ii) a 10km, 220kV
transmission line; (iii) an underground power house; (iv) access roads totaling 18km; and (v) environmental
and social management plan. A concrete weir with radial gates (as opposed to a regular dam) is proposed to
create a head of 350 m of water. A five year construction period was anticipated.
10. Key findings and conclusions from the mission were presented at a wrap up meeting at MoE, chaired by
the Energy Secretary, Mr. Rajendra Kishore Kshatri, on March 22, 2015. As agreed at the wrap up meeting
this AM will be classified as a public document as per the World Bank’s Access to Information Policy.
III. The UT1 Lenders’ Mission (April 19-24, 2015)
11. The UT1 Lenders’ Mission was led by IFC, and included a visit by representatives from potential
lenders to UT1 – International Finance Institutions, Development Finance Institutions, and commercial banks.
In parallel, the Project Review Panel (PRP) consisting of experts linked to hydropower development, also
visited the project site during the same period, reviewing the project details with the sponsors. The PRP
members included a Geotechnical expert, a general hydropower/dams expert and an Environmental and Social
expert. The Lender’s Engineer, Montgomery Watson Harza, and representatives of the KOSEP and JADE
joint venture, as the Owner’s Engineer, were a part of these discussions.
12. The sponsors presented the visiting representatives with the details of the EPC structure, which
includes the following seven sub-contracts or packages:
PKG1: Access Road
PKG2: Head-works & Curtain Grouting
PKG3: Headrace Tunnel
PKG4: Vertical Shaft & Power House
Aide Memoire, UT1 -3- August 19, 2015
PKG5: Hydro-Mechanical Works
PKG6: Electro-Mechanical Works
PKG7: Transmission Line
Pravin Karki as the WB representative, was present during these important PRP discussions. Initial feedback
from the PRP panel, showed no substantial issues with the project.
13. The lenders’ appraisal team for the UT1 project included IFC (Mandated Lead Arranger), other
Development Finance Institutions (ADB, FMO, Proparco, EIB, CDC, and OFID), commercial banks
(Societe Generale, BTMU, and SMBC), and advisors (Synergy as sponsors’ Financial Advisor, Shearman
and Sterling as lenders’ counsel, MWH as lenders’ Independent Engineer). The WB was represented by
Arnaud Braud.
14. Meetings were held with the UT1 sponsors (KOSEP, Daelim, Kyerong, Jade). The agenda included
project presentations (sponsors, technical, financial, E&S, and legal), lenders’ discussion, and meetings with
MoE and MoF. IFC, MIGA, and WB also met NEA, the off-taker, separately.
15. Key outcome from commercial discussions were:
DFIs and commercial lenders confirmed interest in financing the project and did not raise major
issues with the current project structure.
Progress of the project documents (Project Development Agreement (PDA) and Power Purchase
Agreement (PPA)) were the main concern. The list of open issues were significant (including
contract currency, government guarantee language, tariff level) and negotiations had remained
slow. Discussions on the PPA with NEA were still at an early stage.
Participants appreciated the availability of IDA guarantees. Some lenders expressed willingness
for the Letter of Credit to be for six months instead of three (to be negotiated between sponsors
and NEA). Following the meetings in Singapore (from the previous mission), three commercial
banks participated in the mission (SocGen, BTMU, and SMBC) with a strong appetite for a first
project in Nepal under the IDA loan guarantee.
MoF was very supportive of the project, confirming to the lenders’ group the full support of the
government, including its commitment to support NEA’s obligations. The Minister noted that a
dollar financed project required a level of dollar indexation in the PPA tariff.
MoE has asked NEA to share the transmission line with UT1. Parties are studying technical
options. This would require an amendment of the grid connection agreement.
Environmental and Social Assessment
16. From the environmental and social pre-appraisal review, the World Bank Group (WBG) and other
participating lenders agreed that NWEDC has made good progress on establishing sound environmental and
social management systems and is addressing various Environmental and Social (E&S) issues. In conjunction,
there were areas where additional actions were suggested to effectively manage E&S risks and impacts and
meet IFC Performance Standards (or IFC PS, which are the applicable standards for all WBG entities in private
sector led projects) and other relevant international standards. In the wrap up meeting with NWEDC, the WBG
and representatives of potential lenders, highlighted a series of critical path and other priority actions related
to E&S management. These would need either demonstrable progress or resolution prior to financial close.
Action items discussed are outlined in Annex 3.
Aide Memoire, UT1 -4- August 19, 2015
17. Next Steps for E&S: WBG is drafting a project Environmental and Social Review Summary (ESRS)
and Environmental and Social Action Plan (ESAP), which will document all major issues related to E&S
management as per IFC PS requirements, as well as related pending actions to ensure full compliance with
IFC PS, performance indicators and proposed timeframes for their achievement. As next steps, the draft ESRS
and ESAP will be discussed and agreed with NWEDC. Prior to their finalization, specialists from WBG will
visit the project to confirm and revise as necessary, the preliminary findings outlined in Annex 3 (in particular
to account for changes to project context in light of the earthquake), further define required management
actions, and document the project’s achievement of Free, Prior and Informed Consent (FPIC) and Broad
Community Support (BCS) of the affected indigenous communities.
18. E&S Related Disclosure: As per WBG policies on information disclosure, the final ESRS, including
ESAP, need to be publicly disclosed at least 60 days prior to the WBG Board date. If a decision is taken that
the project will use the NEA transmission line towers for power transmission, additional Environment
Assessment documentation as per World Bank Safeguard Policies (e.g., presumably an ESMF) for this
component will also need to be finalized and disclosed in the same timeframe.
19. Climate Change Screening: As per IDA 17 requirements, projects have to be screened for climate
and disaster risks. NWEDC has commissioned studies for screening climate change and disaster risks,
including the threat of a Glacier Lake Outburst Flood (GLOF).
Proposed Timeline:
20. Board Date: WBG team originally planned to present the proposed project to the World Bank Board
in July, 2015. As a result of the earthquake, a delay in this schedule is expected. However, with normalcy
gradually returning, there is a greater need for the additional power, and as next steps, discussions on Project
Development Agreement and PPA should commence soon with financial advisory support by appropriate
consultants to Ministry of Energy, and Nepal Electricity Authority being facilitated by the World Bank.
Successful conclusion of the PDA will be a very important first step in moving forward on the project.
21. The team has already begun work on reviewing aspects of dam safety under the Kali Gandaki TA
initiative, and additional efforts in this regard will also be expedited.
Aide Memoire, UT1 -5- August 19, 2015
Annex 1: List of Officials Met
Ministry of Finance
Mr. Madhu Kumar Marasini, Joint Secretary, IECCD
Mr. Hari P. Pandey, Under Secretary
Ministry of Energy
Mr. Rajendra Kishore Kshatri, Secretary
Mr. Keshab Dhoj Adhikari, Joint Secretary
Department of Electricity Development
Mr. Dinesh Kumar Ghimire, Director General
Mr. Madhu Bhetuwal, Deputy Director General
Nepal Electricity Authority
Mr. Mukesh Raj Kafle, Managing Director
Mr. Kanhaiya Kumar Manandhar, DMD
Mr. Sher Singh Bhat, DMD
Mr. Anil Rajbhandari, Director
Mr. Hitendra Dev Shakya, Director
Mr. Rabindra Chaudhary, ESSD
Investment Board Nepal
Mr. Radhesh Pant, CEO
Asian Development Bank
Mr. Tika Limbu, Portfolio Head
Mr. Pushkar Manandhar, Energy Officer
Department of International Development
Ms. Ashufta Alam
Nepal Investment Bank Ltd.
Mr. Jyoti Prasad Pandey, CEO
Prime Commercial Bank
Mr. Narayan Das Maharjan, CEO
Laxmi Bank
Mr. Sudesh Khaling, CEO
Aide Memoire, UT1 -6- August 19, 2015
Annex 2: Partnerships – From WB Mission in March, 2015
1. Discussions with MoE
Energy Table and Connection Agreement concluded between developer and the NEA.
Parallel transmission line issue: (NEA and also the developer will be building the transmission
line of same voltage which will run parallel to each other for almost 8.3 kms)
Two options discussed at MoE:
o Loop in loop out arrangement at Trishuli 3A hub. This would lead to change in energy
table and thus change in connection agreement, this is an unlikely option
o Taller towers to carry NEA line as well as UT1 line (8.3 km), however, maintenance
could be an issue.
Estimated cost of UT1: During discussions at NEA it was mentioned that the cost estimation
seemed high, but that their internal team was capable of reviewing the cost. Health and safety
cost in particular were singled out as pretty high.
PPA negotiation: The tariff negotiation was on-going, the negotiated tariff should be based on
cost, but discussions were ongoing on what cost estimates to use. Since there is no provision to
revise the PPA later, it is the best estimate that is considered for the PPA rate.
Excess Power from UT1: The issue of excess wet season power in early period of the contract
was discussed. MoE pointed out that over the contract period there would be need for a lot more
power than even UT1, and that with regional exchange, spillage was not likely.
PDA agreement: Negotiations were on-going on; foreign exchange risk issue was a key point.
Preparation of sector and NEA analysis
2. During the mission the team met with NEA’s Directors for System Planning, Power Trade, Finance,
Transmission, Generation, Distribution & Consumer Services and Internal Audit. The objective was to
understand the strategic and operational issues of NEA as well as gather historical data, forecast and corporate
plans for the next few years sufficient to conduct a diagnostic of NEA and develop a view on NEA’s financial
sustainability and off-take credibility. Additionally, the team discussed this issue with ADB and PwC who are
leading a more comprehensive financial modeling to design a restructuring plan for NEA.
3. The team agreed with NEA on a set of data and plans to be provided by NEA to allow a satisfactory
completion of this analysis as part of the due diligence for IDA’s support to Upper Trishuli 1. The team would
like to highlight the time-sensitivity of the data requests and encourage NEA to revert in a timely manner. The
team will follow up on these requests with NEA.
B.3 Discussions with other DFIs (ADB and DFID)
Discussions with ADB and follow up in Kathmandu
ADB team briefed about ADB’s ongoing and pipeline projects. ADB projects mainly are focused on
implementation of high voltage transmission line and cross border links.
ADB recently appointed consulting firm (Deloitte) to carry out review of the power trading company.
Meeting with DFID (UK)
4. DFID is a significant player in Nepal hydropower sector, and in particular has funded staff and advisors
for the IBN for the last 3-4 years. DFID is discussing with other IFIs regarding continuation of support.
5. CDC (private sector arm of DFID) has Nepal as one of its two priority frontier markets (alongside
Northern Nigeria).
Aide Memoire, UT1 -7- August 19, 2015
B.4 Discussions with Banks in Kathmandu
6. The team met with representatives from Laxmi Bank and Nepal Investment Bank, in order to better
understand local banks’ appetite and capacity to finance large hydropower projects. The two banks have
recently financed small hydropower projects (ranging from 3 to 23MW) and both expressed interest for further
lending to the sector. The sector is considered profitable and regulation requires local banks to have 12% of
their exposure in agriculture and power sector. The banks are open to long tenor possibly up to 16 years
(including 4 year grace). However, given the short term nature of their deposits, they cannot fix the rates and
have to reset them, by consensus within the lenders’ group, every 6 months. This uncertainty on the rates would
be difficult for UT1 sponsors. Also, the banks have restrained capital and can only lend a few millions each.
Usually they syndicate 7-8 banks on a hydropower deal but a local bank tranche for UT1 would require more
which would add complexity.
7. The local banks met considered the risk of NEA defaulting as a sovereign risk and therefore saw
limited benefits in the World Bank guaranteeing this risk. The local banks are mostly concerned by equity
injection and construction risk. They often mitigate the latter by asking for corporate guarantees.
Aide Memoire, UT1 -8- August 19, 2015
Annex 3: Environmental and Social Safeguards
1. A group of E&S experts from World Bank, IFC, MIGA, ADB, FAO, SMBC, plus the Lenders’ Engineer’s
environmental and social consultant, conducted a 2-day site visit to the project area during the mission.
The group visited the project access road and main camp at Mailung, observed the weir location from a
viewpoint near Dhunche, and also drove up the river valley to the Langtang Khola confluence to
understand the basin-level development context and socio-environmental conditions. The group also met
and held discussions with Halvard Kassa (independent fish expert), representatives from Langtang
National Park, representatives from the Dhunche office of WWF-Nepal and another local NGO working
with local communities in the national park, NESS consultants (who had recently completed an E&S
construction audit of the project), and project affected people from Gogane, Mailung and Haku Besi
villages.
2. The World Bank Group (WBG) and other participating lenders agreed that NWEDC has made solid
progress on establishing sound environmental and social management systems and addressing various
E&S issues, but that additional actions are needed to effectively manage E&S risks and impacts and meet
IFC Performance Standards (the applicable standards for all WBG entities) and other relevant international
standards. Key issues discussed with NWEDC focused on issues considered most critical path / urgent,
requiring evidence of progress prior to Board decisions by WBG and other lenders. However, because of
the earthquake immediately following the mission, these will need to be revisited when the project is taken
up again for financial consideration, and adjustments made to account for the changed reality on the ground.
3. Critical path: Access road safety, stabilization, and rehabilitation: Because access road construction
was ongoing at the time of the mission, E&S management issues related to the road were flagged as of
utmost urgency, and include in particular the following:
a. Landslide risks: The mission requested NWEDC to conduct a geotechnical assessment of the potential
for road construction to trigger a landslide, and develop a controlled blasting/hillside cutting
management plan. . This has become even more important in the post-earthquake context. Such an
assessment should cover the full road alignment, and in particular the areas of recent and historic
landslides and where villagers reside uphill and could be potentially threatened if a landslide were to
be triggered.
b. Road safety: A full road safety plan was requested to be developed immediately for the access road,
as local residents were already making use of the sections of completed road alongside project vehicles.
When access road construction is started up again, community use cannot be reasonably prevented by
NWEDC, but needs to be accounted for in safety-related protocols, communications/signage, and other
measures to minimize and mitigate the risks of accidents involving local community members or their
livestock.
c. Road stabilization and rehabilitation: The mission requested development of a stabilization and
rehabilitation plan for the access road, and at least some progress on its implementation within a
portion of the already-constructed road stretch. The urgency of this action may be reconsidered in the
post-earthquake context, but such a plan will still be needed when access road construction resumes.
Stabilization and rehabilitation works should also cover the downhill segment of the road, where
existing vegetation is damaged or destroyed by rockfalls and dumping of spoils related to road blasting
Aide Memoire, UT1 -9- August 19, 2015
and earthworks. In areas where downhill damaged vegetation belongs to community forest user
groups, this should also be dealt with in accordance with the Land Acquisition and Resettlement Plan.
4. Critical path: Environmental and Social Management Systems:
a. NWEDC staffing and management: NWEDC’s cash-flow limitations prior to financial closure make
it impractical to implement their full staffing plan for E&S management until financing is secured.
Nonetheless, the mission stressed the need to bring on board additional community liaison officers as
per the agreed staffing plan on an expedited time frame. In addition, stronger evidence is needed of
attention to E&S issues as the management level, including mechanisms for fluid flow of information
and decisions between technical and E&S staff within the company. Lack of such systems undermines
effective and timely incorporation of environmental and social considerations of detailed design and
construction planning processes, and also raises risks that information being shared with stakeholders
may be incomplete or inaccurate.
b. Contractor and subcontractor management: NWEDC was requested to urgently develop systems to
monitor and verify that subcontractors to the EPC contractors (who constitute the bulk of the project’s
labor force) also follow the same labor and EHS plans and standards that are required of the EPC
contractors, in accordance with NWEDC’s company policies and agreed management plans. This
should include mechanisms to make sure that subcontractors actually source workers from the
workforce training programs for local communities and fulfill local hiring targets set by NWEDC.
5. Critical path: Stakeholder engagement: NWEDC was commended for solid progress in strengthening
engagement and communications with local communities, including establishing a grievance mechanism
just a few weeks prior to the mission. Nonetheless, redoubled and sustained efforts were requested to
ensure and demonstrate that:(a) communities understand the full scope of the project and its potential
impacts; (b) concerns of local communities related to the project – including notably about potential risks
and impacts of blasting and road construction works, and issues associated with worker influx – are being
effectively heard and addressed by the company, and all stakeholders are aware of the grievance
mechanism for ongoing issues and concerns; (c) systems for community engagement and communications
encompass ALL community members, not just official and/or self-proclaimed representatives; (d)
unrealistic expectations about what the project can and will provide for local communities are being
managed; and (e) Free, Prior and Informed Consent (FPIC) and Broad Community Support (BCS) can be
achieved and clearly documented. Relatedly, NWEDC was requested to clarify and broadly communicate
its strategy for providing workforce training and employment opportunities to local communities.
6. Critical path aspects of environmental flow management: NWEDC was requested to ensure
coordination between environmental, technical and financial teams so that environmental flow
management aspects are appropriately factored into key related design and financial decisions of the
project. . Specifically:
a. Fish pass: Final results of additional fish baseline data collection efforts were not expected
for another year, yet detailed designs of the weir were already advancing. Therefore, as a
precaution, the mission requested that the detailed design for the weir should explicitly allow
for accommodation of a future fish pass if required. A preliminary conceptual design for a
potential fish pass was also recommended to be developed so that a placeholder cost estimate
could be reflected in the overall project cost.
Aide Memoire, UT1 -10- August 19, 2015
b. Environmental flow financial sensitivity analysis: A sensitivity analysis to determine the
maximum dry-season environmental flow release volumes to which NWEDC can commit was
flagged as a requirement for WBG Board consideration of the project. This analysis is
necessary to underpin the compliance approach to IFC PS 6 (Biodiversity Conservation and
Sustainable Management of Living Natural Resources), as the WBG cannot support a
project that results in net loss of natural habitat (e.g., the aquatic habitat of the diversion
reach) unless it has been robustly documented that this is unfeasible for the project.
7. Critical path: Power transmission approach: Pending final decisions on whether the project’s
transmission line would share the towers of a planned NEA transmission line running through the project
area or be constructed separately by NEA, corresponding E&S assessments and management plans will
need to be put in place in conformance applicable lender E&S standards. In either case, the transmission
line will be considered an associated facility from the perspective of lender E&S standards, and will
therefore needs to be developed in line with lender standards. If the project ties into the NEA-constructed
transmission line towers, the World Bank may furthermore require that Bank Safeguard Policies be upheld
by NEA for the project-associated stretch of this publicly developed project. In that case, corresponding
safeguards instruments (likely to be an Environmental and Social Management Framework – ESMF)
would need to developed and disclosed at least 60 days before approval of the IDA Guarantee, in
conformance with the Bank’s Safeguard Policies. NWEDC was requested to reach clarity on the approach
for power transmission so that a final determination can be made on critical path E&S documentation
requirements for the IDA Guarantee, and related actions could get underway.
8. Additional priority issues::
a. Development of a comprehensive biodiversity management plan, encompassing both activities inside
Lantang National Park as well as in community forests on the right bank, will be needed to ensure no
net loss of natural habitat and biodiversity as a result of the project. This plan would also address the
project’s contribution to cumulative impacts at a watershed scale stemming from development of
multiple hydroelectric projects and the GoN’s planned joining of the project access road with the
national highway to China further upstream within 3-4 years.
b. NWEDC was requested to clarify with the Government of Nepal regarding GoN expectations on
project access road construction standards, if any, given its future intended use as a national highway.
The timelines for such highway development should also be clarified in order to assess implications
for the project, if any in terms of maintaining controlled or priority access during the project
construction period.
c. NWEDC was requested to finalize and adopt the draft land acquisition, resettlement and livelihood
restoration plans that had been completed just before the mission. Post-earthquake, these plans will
now likely need to be updated and reworked before adoption.
d. NWEDC still needed to finalize all detailed construction management plans, including spoils and
waste management, explosives / controlled blasting; management of construction labor camps and
associated influx, etc. This is still applicable as construction on the project resumes.
Aide Memoire, UT1 -11- August 19, 2015
Annex 4: Technical Specification of UT1
1. The Upper Trishuli-1 HEP is located on the Trishuli River, the Project will divert up to 76 m3/sec of
flow from Trishuli River over a distance of about 12 kilometers to the powerhouse located at Mailung, utilizing
the available head of 345 m for electricity production. The proposed installed capacity is 216 MW consisting
of three Francis units to produce 1,533.1 GWh (Contract energy is 1456.4GWh) of energy per year on average.
Firm energy is calculated as 853.7 GWh and secondary energy as 679.4 GWh. The Trishuli River originates
in China and is a trans-boundary river and one of the major tributaries of the Narayani River (which flows into
the Ganges in India) basin in central Nepal. OP on international waterways is triggered and notices have been
served to the neighboring countries on February 27, 2015.
2. The headworks consist of a concrete dam about 60 m high from the foundation. All the structures are
founded on alluvium which will be excavated to a suitable depth to firm foundation. The headworks create a
normal pool level of El. 1,255 m and divert water to a river intake. Water is diverted by means of the river
intake to three settling basins connected to the intake tunnel and headrace tunnel. After passing through the
de-sanding basins, water is fed into the headrace tunnel. Under normal operating conditions, the water surface
behind the headworks is maintained at El. 1,255 m. All water, less the environmental release, is diverted to
the powerhouse. River flow in excess of the amount for power generation is passed through the spillway gates.
3. Water utilized for power production is withdrawn from the de-sanding basin through the intake and
transported through a 10 km of headrace tunnel and penstock to an underground powerhouse located on the
right bank of Trishuli River and approximately 348 m below the ground. As for geological characteristics, two
rock types of schist unit and gneiss unit appear. Investigations showed that schist was distributed in the area
covering about 26 % of tunnel length, and gneiss about 74 %, respectively. Gneiss has higher strength than
schist. Currently shotcrete lining is planned for rock type I, II, III and concrete lining is planned for rock type
IIIb, IV, V grades.
4. Nepal being in an active seismic risk zone, probabilistic seismic hazard analysis and Peak Ground
acceleration (PGA) was performed for Rasuwa site.
5. The powerhouse is proposed as 18.7 m wide, 83.0 m long and 43.9 m high. The powerhouse substation
will be located at the right side of Trishuli River. It will include three power transformers, five 220-kV circuit
breakers, a takeoff structure, eleven disconnect switches, surge arresters, a power line carrier
transmitter/receiver, and all associated substation hardware. Approximately 10 km of new 220-kV, single
circuit transmission line will be constructed between the Project and the Trishuli 3B Substation. The revenue
metering equipment will be located at the receiving end of the transmission line and will consist of main and
check meters, which will be used to measure and record the amount of electrical output delivered at the 220-
kV voltage level.