Upload
others
View
10
Download
0
Embed Size (px)
Citation preview
1
NATIONAL CYCLONE RISK MITIGATION PROJECT
PROCUREMENT PLAN (REVISION 0)
I. General
1. Project information:
• Project Name: NATIONAL CYCLONE RISK MITIGATION PROJECT • Country: INDIA • Project Code:
2. Bank’s approval Date of the procurement Plan : February 26, 2010
3. Date of General Procurement Notice: December 9, 2009 4. Period covered by this procurement plan: 18 months (From January 01, 2010 to June 30, 2011)
II. Goods and Works and non-consulting services. 1 a) Procurement Methods and Thresholds
Category Method of Procurement Threshold (US$ Equivalent)
Works ICB Works estimated to cost more than US$ 5,000,000
NCB Works estimated to cost more than US$ 30,000 and up to US$ 5,000,000
Shopping Goods estimated to cost up to US$ 30,000
Goods
(also applicable for non-intellectual services and the services contracted on the basis of performance of measurable physical outputs)
ICB Goods estimated to cost more than US$ 500,000
LIB Goods estimated to cost more than US$ 500,000
NCB Goods estimated to cost more than US$ 30,000 and up to US$ 500,000
Shopping Goods estimated to cost up to US$ 30,000
Direct Contracting Proprietary items
of lesser value
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
wb350881Typewritten Text54908
2
1 b) Prior Review Threshold
Works : USD 5,000,000 Force account- Prior review only Goods: ICB/LIB- USD 500,000 NCB- USD 200,000 Direct Contracting- Prior Review only Services: USD 100,000 (other than consultancy)
The Procurement under NCB may be done only after satisfying the following NCB conditions : Invitations to bid shall be advertised in at least one widely circulated national daily newspaper, at
least 30 days prior to the deadline for the submission of bids; No special preference will be accorded to any bidder either for price or for other terms and
conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State;
Except in exceptional circumstances, there will be no negotiations of price with bidders, even with the lowest evaluated bidder.
Extension of bid validity: (a) for the first request for extension if it is longer than four weeks; and (b) for all subsequent requests for extension irrespective of the period (such concurrence will be considered only in cases of Force Majeure and circumstances beyond the control of the purchaser or employer) will require prior approval by bank.
Re-bidding: the system of rejecting bids outside a pre-determined margin or ‘bracket ‘of prices shall not be used.
The two-or-three envelope system will not be used. Rate contracts entered into with DGS & D are not acceptable as substitute for NCB procedures.
This may be used in lieu of shopping.
2. Pre-qualification.
3. Reference to (if any) Project Operational/Procurement Manual: Refer section 5.1 of the Procurement manual of the Project
4. Any Other Special Procurement Arrangements: None
5. Procurement Packages with Methods and Time Schedule – Refer attached consolidated Procurement plan
III. Selection of Consultants 1 a) Selection Methods and Thresholds
Method of Procurement Threshold (US$ Equivalent)
Quality and Cost Based selection (‘QCBS’)
USD 200,000
Least Cost Selection- (‘LCS’) Based on the specifications of the assignment.
3
Method of Procurement Threshold (US$ Equivalent)
(Procurement meeting requirements of Clause 3.6 of the Bank’s guidelines) Contract value less than US $ 200,000.
Fixed Budget System – (‘FBS’)
Based on the specifications of Assignment. (Procurement meeting requirements of Clause 3.5 of the Bank’s guidelines) Contract value less than US $ 200,000
Selection based on Consultants Qualification (‘CQS’)
Based on the specifications of Assignment. (Procurement meeting requirements of Clause 3.7 and 3.8 of the Bank’s guidelines) Contract value less than US $ 200,000
Single Source Selection(‘SSS’)
Based on the specifications of Assignment (if meets requisite criteria) (Selection meeting requirements of Clause 3.9- 3.13 of the Bank’s guidelines)
Individual Consultants Based on the specifications of Assignment (if meets requisite criteria)
1 b) Prior Review Threshold
Consultancy Services: > US$ 100,000 for firms; and > US$ 50,000 equivalent for individuals
All Single Source Selections (SSS) should be prior cleared with Bank.
2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.
3. Any Other Special Selection Arrangements: .None 4. Reference to (if any) Project Operational/Procurement Manual – Refer section 5.2 of the
Procurement manual of the Project
5. Consultancy Assignments with Selection Methods and Time Schedule – Refer attached consolidated Procurement plan
Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT
1 of 15
Procurement Plan for Component B Country: IndiaReceipentProject: (Values in Millions)
Sno Package No. Description Method of Procurement
Schedule/ Slice
Procurement Authority Quantity (Number)
Total Estimated Cost (Million local currency)
Estimated Cost (Million USD)
Stage Initiate preparation of Specification and Bid Document
Preparation of IFB and submission to the Bank
Preparation of the Bid Document
Approval of IFB and Bid documents by the World Bank
Publication of IFB in Newspapers and UNDB
Beginning of Sale of Bid document
Opening of Bids
Submission of BER to Bank for approval/ Preparation of BER
Approval of BER
Signing of the contract
Issue of contract award notice
50% work complete
100% work complete
Completion of contractual obligations
Orissa
622.80 12.84
1 7.98 0.16 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual
2 17.03 0.35 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual
2 17.87 0.37 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual
2 17.18 0.35 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 27-May-11 23-Nov-11 21-Feb-12RevisedActual
2 14.11 0.29 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual
2 16.52 0.34 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual
2 17.07 0.35 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual
2 16.00 0.33 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual
2 17.40 0.36 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
2 15.85 0.33 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
1 8.68 0.18 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
2 15.42 0.32 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual
1 5.88 0.12 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
2 15.75 0.32 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 28-Jan-12 27-Apr-12RevisedActual
1 8.07 0.17 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
1 7.80 0.16 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual
2 17.15 0.35 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
2 16.35 0.34 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
1 8.47 0.17 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12
Government of India, Ministry of Home Affairs
Dist: Balasore
1 NCRMP/OR/BLS/CS/01
2 NCRMP/OR/BLS/CS/02
Kuruda and Kochiakoili of Bahanaga Block, Balasore District
7
Rural Development Department,Govt of
OrissaBajana and Gandhiana of Bahanaga Block, Balasore District
NCB
Bishnupur of Bahanaga Block, Balasore District
NCB
Rural Development Department,Govt of
Orissa
5 NCRMP/OR/BLS/CS/05Ikadapal and Bishnupur of Baliapal Block, Balasore District
NCB
4 NCRMP/OR/BLS/CS/04
Odasala and Nuapu of Bahanaga Block, Balasore District
NCB
3 NCRMP/OR/BLS/CS/03
Rural Development Department,Govt of
Orissa
12 NCRMP/OR/BLS/CS/12
Maharajpur and Mahamadabad of Remuna Block, Balasore District
NCB
11 NCRMP/OR/BLS/CS/11Jalapahi (Bhogarai) of Bhogarai Block, Balasore District
NCB
Badakia and Jayadevkasba of Balasore Sadar District, Balasore District
NCB
Gopinathpur and Parakhi of Balasore Sadar Block, Balasore District
NCB
Rural Development Department,Govt of
Orissa
Binjha of Balasore Sadar Block, Balasore District
NCB
Rural Development Department,Govt of
OrissaRural Development Department,Govt of
Orissa
Panchupada and Alumeda of Balasore Sadar Block, Balasore District
NCB
Sarthabindha of Balasore Sadar Block, Balasore District
NCB
Rural Development Department,Govt of
Orissa
18 NCRMP/OR/BLS/CS/18
NCRMP/OR/BL
National Cyclone Risk Mitigation
Orissa- Cyclone shelters-Orissa- Cyclone Shelters- Total
Rural Development Department,Govt of
Orissa
Aunladiha and Dagara of Baliapal Block, Balasore District
NCB
Rural Development Department,Govt of
Orissa
Bisikadeipur and Govindapur of Baliapal Block, Balasore District
NCB
NCB
NCRMP/OR/BLS/CS/099
NCRMP/OR/BLS/CS/07
8
Rural Development Department,Govt of
Orissa
6 NCRMP/OR/BLS/CS/06Pakmundi and Surahida of Baliapal Block, Balasore District
NCB
Rural Development Department,Govt of
Orissa
Rural Development Department,Govt of
Orissa
Rural Development Department,Govt of
Orissa
Deula and Kunduli of Baliapal Block, Balasore District
NCB
10 NCRMP/OR/BLS/CS/10
Rural Development Department,Govt of
Orissa
Gotadiha and Kainagiri of Basta Block, Balasore District
NCB
NCRMP/OR/BLS/CS/08
Rural Development Department,Govt of
Orissa
13 NCRMP/OR/BLS/CS/13Mandagaon of Remuna Block, Balasore District
NCBRural Development Department,Govt of
Orissa
Rural Development Department,Govt of
Orissa
15 NCRMP/OR/BLS/CS/15
14 NCRMP/OR/BLS/CS/14
17 NCRMP/OR/BLS/CS/17
Rural Development Department,Govt of
Orissa
16 NCRMP/OR/BLS/CS/16
Rural Development
Hidigaon of Balasore Sadar
NCB
Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT
2 of 15
Sno Package No. Description Method of Procurement
Schedule/ Slice
Procurement Authority Quantity (Number)
Total Estimated Cost (Million local currency)
Estimated Cost (Million USD)
Stage Initiate preparation of Specification and Bid Document
Preparation of IFB and submission to the Bank
Preparation of the Bid Document
Approval of IFB and Bid documents by the World Bank
Publication of IFB in Newspapers and UNDB
Beginning of Sale of Bid document
Opening of Bids
Submission of BER to Bank for approval/ Preparation of BER
Approval of BER
Signing of the contract
Issue of contract award notice
50% work complete
100% work complete
Completion of contractual obligations
RevisedActual
2 16.97 0.35 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
1 8.27 0.17 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual
2 14.50 0.30 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-Jul-10 8-Jul-10 9-Aug-10 8-Sep-10 6-Oct-10 7-Oct-10 4-Jun-11 31-Dec-11 30-Mar-12RevisedActual
1 7.60 0.16 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual
2 14.41 0.30 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual
1 7.22 0.15 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
2 16.87 0.35 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
2 15.44 0.32 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-Jul-10 8-Jul-10 9-Aug-10 8-Sep-10 6-Oct-10 7-Oct-10 4-Jun-11 31-Dec-11 30-Mar-12RevisedActual
1 7.45 0.15 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-Jul-10 8-Jul-10 9-Aug-10 8-Sep-10 6-Oct-10 7-Oct-10 4-Jun-11 31-Dec-11 30-Mar-12RevisedActual
1 7.00 0.14 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual
1 8.33 0.17 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
2 14.56 0.30 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
1 8.23 0.17 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual
2 15.46 0.32 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-Jul-10 8-Jul-10 9-Aug-10 8-Sep-10 6-Oct-10 7-Oct-10 4-Jun-11 31-Dec-11 30-Mar-12RevisedActual
1 9.29 0.19 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
1 8.56 0.18 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
2 16.44 0.34 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual
2 12.60 0.26 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual
1 8.47 0.17 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
2 16.13 0.33 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 28-Jan-12 27-Apr-12RevisedActual
3 24.74 0.51 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 28-Jan-12 27-Apr-12RevisedActual
3 22.71 0.47 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-Jul-10 8-Jul-10 9-Aug-10 8-Sep-10 6-Oct-10 7-Oct-10 4-Jun-11 30-Mar-12 28-Jun-12
19 NCRMP/OR/BLS/CS/19
Artung of Basudevpur Block, Bhadrak District
NCB
Rural Development Department,Govt of
Orissa
NCB27 NCRMP/OR/BHK/CS/07
24
Sunaripokhari of Chandbali Block, Bhadrak District
NCB
Ankapada and Biriadia of Chandbali Block, Bhadrak District
NCB26
NCB
NCBNCRMP/OR/GJM/CS/01
Lunguri of Ganjam Block, Ganjam District
NCRMP/OR/BHK/CS/06
Nachhipur and Utarasahi of Chandbali Block, Bhadrak District
Rural Development Department,Govt of
Orissa
NCB
Rural Development Department,Govt of
Orissa
Rural Development Department,Govt of
Orissa
Rural Development Department,Govt of
Orissa
Rural Development Department,Govt of
Orissa
Rural Development Department,Govt of
Orissa
Dist: Kendrapara
30 NCRMP/OR/GJM/CS/02
Dist: Jagatsinghpur
31 NCRMP/OR/JSP/CS/01
32 NCRMP/OR/JSP/CS/02
Pokharia of Rajnagar Block, Kendrapara District
NCB
Gaudasahi (Bhuan), Badatara and Bangara of Gop Block, Puri District
NCB
Madhupur and Sahana of Astaranga Block, Puri District
NCB
NCBKendrapati and Bantilo of Astaranga Block, Puri District
NCB
35 NCRMP/OR/KPD/CS/03
38 NCRMP/OR/PUR/CS/03
Dist: Puri
36 NCRMP/OR/PUR/CS/01
37
NCRMP/OR/BHK/CS/04
25 NCRMP/OR/BHK/CS/05
NCB
NCRMP/OR/BHK/CS/01
Dist: Bhadrak
23 NCRMP/OR/BHK/CS/03Kaduanasi of Chandbali Block, Bhadrak District
21
Department,Govt of
Orissa
20 NCRMP/OR/BLS/CS/20Pakhar and Tentei of Soro Block, Balasore District
NCBRural Development Department,Govt of
Orissa
Hidigaon of Balasore Sadar Block, Balasore District
NCB
22 NCRMP/OR/BHK/CS/02Balarampur and Khedualpur of Basudevpur, Bhadrak District
NCB
Rural Development Department,Govt of
OrissaRural Development Department,Govt of
Orissa
Barakolha and Jantuali of Chandbali Block, Bhadrak District.
Rural Development Department,Govt of
Orissa
NCB
Rural Development Department,Govt of
Orissa
Kankan of Erasama Block, Jagatsinghpur District
NCB
28
Rural Development Department,Govt of
Orissa
Samantarapur and Kusupur of Balikuda Block, Jagatsinghpur District
NCB
Dist: Ganjam
29
Rajapur of Ganjam Block, Ganjam District
Baliarpur of Chandbali Bloc, Bhadrak District
NCRMP/OR/BHK/CS/08
Kajalabandha and Bilikana of Patamundai Block, Kendrapara District
NCB
34 NCRMP/OR/KPD/CS/02Satakuria of Patamundai Block, Kendrapara District
NCB
33 NCRMP/OR/KPD/CS/01
Rural Development Department,Govt of
Orissa
Rural Development Department,Govt of
OrissaRural Development Department,Govt of
OrissaRural Development Department,Govt of
Orissa
Rural Development Department,Govt of
Orissa
NCRMP/OR/PUR/CS/02
Rural Development Department,Govt of
Orissa
39 NCRMP/OR/PUR/CS/04Palanka and Chapamanik of Brahmagiri Block, Puri District
NCBRural Development Department,Govt of
Orissa
Kahalapada of Brahmagiri Block, Puri District
Rural Development Department,Govt of
Orissa
NCRMP/OR/PU Kanthijhadi, Kundish and
NCBRural Development
40 NCRMP/OR/PUR/CS/05
Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT
3 of 15
Sno Package No. Description Method of Procurement
Schedule/ Slice
Procurement Authority Quantity (Number)
Total Estimated Cost (Million local currency)
Estimated Cost (Million USD)
Stage Initiate preparation of Specification and Bid Document
Preparation of IFB and submission to the Bank
Preparation of the Bid Document
Approval of IFB and Bid documents by the World Bank
Publication of IFB in Newspapers and UNDB
Beginning of Sale of Bid document
Opening of Bids
Submission of BER to Bank for approval/ Preparation of BER
Approval of BER
Signing of the contract
Issue of contract award notice
50% work complete
100% work complete
Completion of contractual obligations
RevisedActual
3 20.83 0.43 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-Jul-10 8-Jul-10 9-Aug-10 8-Sep-10 6-Oct-10 7-Oct-10 4-Jun-11 30-Mar-12 28-Jun-12RevisedActual
2 17.09 0.35 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-Jul-10 8-Jul-10 9-Aug-10 8-Sep-10 6-Oct-10 7-Oct-10 4-Jun-11 31-Dec-11 30-Mar-12RevisedActual
2 16.60 0.34 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
1 8.84 0.18 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
2 17.61 0.36 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual
78 622.80 12.84
Total cost 545.42 11.25
3 14.85 0.31 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual
1 25.42 0.52 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual
2 27.24 0.56 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual
2 46.80 0.96 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual
5 40.60 0.84 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual
1 23.62 0.49 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual
4 45.57 0.94 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual
3 15.86 0.33 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual
3 6.45 0.13 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual
6 10.91 0.22 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual
1 24.64 0.51 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual
1 38.22 0.79 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual
2 28.50 0.59 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual
2 24.79 0.51 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual
6 5.3980 0.11 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual
1 25.24 0.52 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12Revised
42 NCRMP/OR/PUR/CS/07
Dhanitri, Runkei and Sukapokhari-Jaleswarpada of Kakatpur Block, Puri District
NCBRural Development Department,Govt of
Orissa
Rural Development Department,Govt of
Orissa
Rural Development Department,Govt of
Orissa
Rural Development Department,Govt of
Orissa43 NCRMP/OR/PUR/CS/08
Orissa- CS- Total
Orissa- Approach Roads- TotalDist: Balasore
45 NCRMP/OR/PUR/CS/10
44 NCRMP/OR/PUR/CS/09
1 NCRMP/OR/BLS/AR/01
Bishnupur, Gandhiana and Odasala of Bahanaga Block, Balasore District
NCB
2 NCRMP/OR/BLS/AR/02Pakhar of Soro Block, Balasore District
NCB
Rural Development Department,Govt of
Orissa11 Kaduanasi of Chandbali Block, Bhadrak District
NCBNCRMP/OR/BHK/AR/02
Rural Development Department,Govt of
Orissa
15 NCRMP/OR/BHK/AR/06
Dosinga & Kaithakola of Chandbali Block and Nuagaon, Bachhada, Padhuan &
NCBRural Development Department,Govt of
Orissa
NCRMP/OR/BHK/AR/05
Khedualpur and Balarampur of Basudevpur Block, Bhadrak District
Rural Development Department,Govt of
Rajapur of Ganjam Block, Ganjam District
NCB
41 NCRMP/OR/PUR/CS/06
Sarada of Gop Block, Puri District
NCB
Department,Govt of Orissa
Gomundia and Jenapur of Krushnaprasad Block, Puri District
NCBRural Development Department,Govt of
Orissa
Bajrakote and Budhibara of Krushnaprasad Block, Puri District
NCB
Rural Development Department,Govt of
Orissa
46 NCRMP/OR/PUR/CS/11
Rural Development Department,Govt of
Orissa
Jamarsuan of Puri Sadar Block, Puri District
NCB
Kantasil and Rendua of Puri Sadar Block, Puri District
NCB
NCRMP/OR/BLS/AR/055
4 NCRMP/OR/BLS/AR/04Binjha and Alumeda of Balasore Sadar Block, Balasore District
Panchapada, Parakhi & Gopinathpurof Balasore Sadar Block and Gotadiha & Kainagiri
NCB
3 NCRMP/OR/BLS/AR/03Ikadapal and Bishnupur of Baliapal block, Balasore District
NCBRural Development Department,Govt of
OrissaRural Development Department,Govt of
OrissaRural Development Department,Govt of
Orissa
NCB
NCBRural Development Department,Govt of
Orissa
Rural Development Department,Govt of
Orissa
NCRMP/OR/BLS/AR/07
6 NCRMP/OR/BLS/AR/06Sarthabindha of Balasore Sadar Block, Balasore District
NCB
8 NCRMP/OR/BLS/AR/08NCB
Dist: Bhadrak
10 NCRMP/OR/BHK/AR/01
Ankapada, Biriadia, Sunaripokhari, Barakhola & Jantuali of Chandbali Block and
NCB
7
Chaumukh of Baliapal Block and Krushnanagar & Bichitrapur of Bhogarai Block, Balasore
NCB9 NCRMP/OR/BLS/AR/09
Jayadevkasba of Balasore Sadar Block and Mahamadabad, Maharajpur &
Rural Development Department,Govt of
Orissa
Rural Development Department,Govt of
Orissa
Talapada of Remuna Block and Maharudrapur & Barajdeuli of Bahanaga Block, Balasore
Rural Development Department,Govt of
Orissa
Rural Development Department,Govt of
Orissa
13 NCRMP/OR/BHK/AR/04
Nachhipur and Utarasahi of Chandbali Block, Bhadrak District
NCBRural Development Department,Govt of
Orissa
12 NCRMP/OR/BHK/AR/03
NCB
Dist: Ganjam
14
Baliarpur of Chandbali Block, Bhadrak District
NCB
16 NCRMP/OR/GJM/AR/01
Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT
4 of 15
Sno Package No. Description Method of Procurement
Schedule/ Slice
Procurement Authority Quantity (Number)
Total Estimated Cost (Million local currency)
Estimated Cost (Million USD)
Stage Initiate preparation of Specification and Bid Document
Preparation of IFB and submission to the Bank
Preparation of the Bid Document
Approval of IFB and Bid documents by the World Bank
Publication of IFB in Newspapers and UNDB
Beginning of Sale of Bid document
Opening of Bids
Submission of BER to Bank for approval/ Preparation of BER
Approval of BER
Signing of the contract
Issue of contract award notice
50% work complete
100% work complete
Completion of contractual obligations
Actual
3 40.73 0.84 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual
4 2.48 0.05 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual
2 38.79 0.80 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual
3 3.71 0.08 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual
2 17.00 0.35 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual
2 13.59 0.28 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual
1 12.09 0.25 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual
2 6.83 0.14 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual
3 6.11 0.13 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual
65 545.42 11.25Orissa Total 1168.22 24.09
Andhra PradeshAndhra Pradesh- Cyclone shelters
455.70 9.40
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
8 63.10 1.30
Appraisal 1-Oct-09 11-Oct-09 30-Nov-09 15-Dec-09 5-Mar-10 6-Mar-10 6-Apr-10 6-May-10 3-Jun-10 4-Jun-10 15-Apr-11 24-Feb-12 24-May-12 Revised
Actual
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
5 40.65 0.84
Appraisal 1-Oct-09 11-Oct-09 30-Nov-09 15-Dec-09 5-Mar-10 6-Mar-10 6-Apr-10 6-May-10 3-Jun-10 4-Jun-10 1-Dec-10 30-May-11 28-Aug-11 Revised
Actual
Construction of D type cyclone shelter in Idduvanipelam, Srikakulam district
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 9.59 0.20
Appraisal 2-Oct-09 12-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of C type cyclone shelter in Gollavooru, Srikakulam district
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 10.08 0.21
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of four cyclone shelters in Vajrapukothuru mandal, Srikakulam district
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
4 33.82 0.70
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Madhupur of Astaranga, Puri District
NCB
25 NCRMP/OR/PUR/AR/05
Gopinathpur, Malud and Nuapada of Krushnaprasad Block, Puri District
3
4
5
1Construction of eight cyclone shelters in Kavali mandal, Nellore District
NCRMP/B-W/AP/MPCS/PRED/09/Kavali/
003
NCRMP/B-W/AP/MPCS/PRED/01/Kaviti/0
01
NCRMP/B-W/AP/MPCS/PRED/01/V.Koth
uru/004
NCRMP/B-W/AP/MPCS/PRED/01/Sompet
a/002
2
NCRMP/B-W/AP/MPCS/PRED/01/V.Koth
uru/003
Construction of five cyclone shelters in Vajrapukothuru mandal, Srikakulam District
Andhra Pradesh- Cyclone
Orissa
Ganjam District
Rural Development Department,Govt of
Orissa
NCB
Kankana of Erasama Block and Samantarapur & Kusupur of Balikuda Block, Jagatsinghpur
NCB
Dist: Jagatsinghpur
M/AR/01
Rural Development Department,Govt of
Orissa
17 NCRMP/OR/JSP/AR/01
18 NCRMP/OR/JSP/AR/02
Nuagarh, Fatepur & Nimidihi of Kujanga Block and Naradia of Erasama Block, Jagatsinghpur
NCB
Dist: Kendrapara
19 NCRMP/OR/KPD/AR/01
Satakudia of Patamundai Block and Pokharia of Rajnagar Block, Kendrapara District
Rural Development Department,Govt of
Orissa
20 NCRMP/OR/KPD/AR/02
Sana Rahama of Mahakalapada Block and Nuagaon & Badanaukana of Rajnagar
NCBRural Development Department,Govt of
Orissa
NCB
Dist: Puri
21 NCRMP/OR/PUR/AR/01
Gomundia and Jenapur of Krushnaprasad Block, Puri District
Orissa- Roads- Total
NCRMP/OR/PUR/AR/02
Kahalapada and Chapamanik of Brahmagiri Block, Puri District
Rural Development Department,Govt of
Orissa
24 NCRMP/OR/PUR/AR/04Kanthijhadi and Badatara of Gop Block, Puri District
NCB
Rural Development Department,Govt of
Orissa
Rural Development Department,Govt of
Orissa
23 NCRMP/OR/PUR/AR/03
Rural Development Department,Govt of
Orissa
NCBRural Development Department,Govt of
Orissa
22 NCB
Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT
5 of 15
Sno Package No. Description Method of Procurement
Schedule/ Slice
Procurement Authority Quantity (Number)
Total Estimated Cost (Million local currency)
Estimated Cost (Million USD)
Stage Initiate preparation of Specification and Bid Document
Preparation of IFB and submission to the Bank
Preparation of the Bid Document
Approval of IFB and Bid documents by the World Bank
Publication of IFB in Newspapers and UNDB
Beginning of Sale of Bid document
Opening of Bids
Submission of BER to Bank for approval/ Preparation of BER
Approval of BER
Signing of the contract
Issue of contract award notice
50% work complete
100% work complete
Completion of contractual obligations
Construction of two cyclone shelters in Santhabommali mandal, Srikakulam district
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
2 20.96 0.43
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of three cyclone shelters in Gara mandal, Srikakulam district
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
3 26.64 0.55
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of A type cyclone shelter in Ragupalem, Srikakulam district
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 7.24 0.15
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of A type cyclone shelter in Kommaravanipeta, Srikakulam district
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 7.02 0.14
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of three cyclone shelters in Ranasthalam mandal, Srikakulam district
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
3 23.81 0.49
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of A type cyclone shelter in Moosavanipeta, Srikakulam district
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 7.43 0.15
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of two cyclone shelters in Pusapatirega, Vizianagaram district
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
2 14.70 0.30
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of A type cyclone shelters in Thotapalli, Vizianagaram district
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 7.02 0.14
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of C type cyclone shelter in Tikkavanipalem, Vishakhapatnam district
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 10.02 0.21
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of three cyclone shelters in Nakkapalli mandal, Vishakhapatnam district
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
3 27.07 0.56
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of two cyclone shelters in Payakaraopeta mandal, Vishakhapatnam district
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
2 14.83 0.31
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of B type cyclone shelter in Venkayyapalem, Vishakhapatnam district
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 7.70 0.16
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11Revised
11
12
13
14
15
16
6
7
8
9
10
17
NCRMP/B-W/AP/MPCS/PRED/01/Etcherl
a/010
NNCRMP/B-W/AP/MPCS/PRED/01/Ranast
halam/008
NCRMP/B-W/AP/MPCS/PRED/01/Gara/0
06
NCRMP/B-W/AP/MPCS/PRED/01/Ranast
halam/009
NCRMP/B-W/AP/MPCS/PRED/01/Santha
bommali/005
NCRMP/B-W/AP/MPCS/PRED/01/Laveru/
007
NCRMP/B-W/AP/MPCS/PRED/02/Bhogap
uram/002
NCRMP/B-W/AP/MPCS/PRED/03/Parava
da/001
NCRMP/B-W/AP/MPCS/PRED/02/Pusapa
tirega/001
NCRMP/B-W/AP/MPCS/PRED/03/Nakkap
alli/002
NCRMP/B-W/AP/MPCS/PRED/03/Rambill
i/004
NCRMP/B-W/AP/MPCS/PRED/03/Payaka
raopeta/003
Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT
6 of 15
Sno Package No. Description Method of Procurement
Schedule/ Slice
Procurement Authority Quantity (Number)
Total Estimated Cost (Million local currency)
Estimated Cost (Million USD)
Stage Initiate preparation of Specification and Bid Document
Preparation of IFB and submission to the Bank
Preparation of the Bid Document
Approval of IFB and Bid documents by the World Bank
Publication of IFB in Newspapers and UNDB
Beginning of Sale of Bid document
Opening of Bids
Submission of BER to Bank for approval/ Preparation of BER
Approval of BER
Signing of the contract
Issue of contract award notice
50% work complete
100% work complete
Completion of contractual obligations
Actual
Construction of two cyclone shelters in Thondangi mandal, East Godavari District
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
2 14.59 0.30
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of C type cyclone shelter in Pedaraghavulupeta, East Godavari District
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 10.09 0.21
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of two cyclone shelters in Nizampatnam mandal, Guntur District
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
2 17.48 0.36
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of B type cyclone shelter in Mollagunta, Guntur District
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 7.41 0.15
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of D type cyclone shelter in Chakicherla, Prakasam District
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 9.97 0.21
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of B type cyclone shelter in Pakala Main, Prakasam District
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 7.19 0.15
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
NCB AppraisalRevisedActual
Construction of B type cyclone shelter in Thopupalem Kanuparthy, Prakasam District
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 7.19 0.15
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of B type cyclone shelters in Epuru Pattapupalem, Nellore District
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 7.84 0.16
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of three cyclone shelters in Bogole mandal, Nellore District
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
3 28.25 0.58
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of two cyclone shelters in Vidavalur mandal, Nellore District
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
2 14.03 0.29
Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Andhra Pradesh- Cyclone shelters- Total 55 455.70 9.40
Andhra Pradesh- Roads1036.52 21.37
21
22
23
24
NCRMP/B-W/AP/MPCS/PRED/09/Vidaval
ur/004
19
20
18
27
NCRMP/B-W/AP/MPCS/PRED/04/Uppala
guptha/002
NCRMP/B-W/AP/MPCS/PRED/09/Bogole/
002
NCRMP/B-W/AP/MPCS/PRED/09/Muthuk
ur/001
NCRMP/B-W/AP/MPCS/PRED/08/Ulavap
adu/001
NCRMP/B-W/AP/MPCS/PRED/04/Thonda
ngi/001
NCRMP/B-W/AP/MPCS/PRED/07/Nizamp
atnam/001
Andhra Pradesh- Roads-
NCRMP/B-W/AP/MPCS/PRED/07/Repalle
/002
NCRMP/B-W/AP/MPCS/P
RED/08/S. Konda/002
NCRMP/B-W/AP/MPCS/PRED/08/N.G.
Padu/003
25
26
Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT
7 of 15
Sno Package No. Description Method of Procurement
Schedule/ Slice
Procurement Authority Quantity (Number)
Total Estimated Cost (Million local currency)
Estimated Cost (Million USD)
Stage Initiate preparation of Specification and Bid Document
Preparation of IFB and submission to the Bank
Preparation of the Bid Document
Approval of IFB and Bid documents by the World Bank
Publication of IFB in Newspapers and UNDB
Beginning of Sale of Bid document
Opening of Bids
Submission of BER to Bank for approval/ Preparation of BER
Approval of BER
Signing of the contract
Issue of contract award notice
50% work complete
100% work complete
Completion of contractual obligations
Construction of road to habitation from Gumpam to Puligeddapalem (via) Palanki, Vizianagaram District
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 25.89 0.53
Appraisal
3-Oct-09 13-Oct-09 30-Nov-09 15-Dec-09 5-Mar-10 6-Mar-10 6-Apr-10 6-May-10 3-Jun-10 4-Jun-10 1-Dec-10 28-Aug-11 26-Nov-11RevisedActual
Construction of roads to habitations in Talasamudram mandal, Srikakulam District
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
3 22.86 0.47
Appraisal
3-Oct-09 13-Oct-09 30-Nov-09 15-Dec-09 5-Mar-10 6-Mar-10 6-Apr-10 6-May-10 3-Jun-10 4-Jun-10 1-Dec-10 28-Aug-11 26-Nov-11RevisedActual
Construction of roads to cyclone shelters in Srikakulam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
4 13.46 0.28
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Srikakulam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
4 16.60 0.34
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Srikakulam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
5 12.80 0.26
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Srikakulam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 5.66 0.12
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Srikakulam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
5 16.94 0.35
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Vizianagaram
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
6 11.43 0.24
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Vishakhapatnam
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
2 5.38 0.11
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Vishakhapatnam
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
4 20.65 0.43
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Vishakhapatnam
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
2 9.69 0.20
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in East Godavari
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 6.52 0.13
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11Revised
3
NCRMP/B-W/AP/RHB/PRED/01/Polaki/00
6
NCRMP/B-W/AP/RHB/PRED/02/Pusapati
rega/001
NCRMP/B-W/AP/RCS/PRED/01/V.Kottur
u/002
NCRMP/B-W/AP/RCS/PRED/01/Santhab
ommali/003
NCRMP/B-W/AP/RCS/PRED/01/V.Kottur
u/001
1
5
4
2
NCRMP/B-W/AP/RCS/PRED/03/Nakkapal
li/003
NCRMP/B-W/AP/RCS/PRED/01/Polaki/00
4
NCRMP/B-W/AP/RCS/PRED/01/Etcherla/
005
NCRMP/B-W/AP/RCS/PRED/02/Bhogapu
ram/001
NCRMP/B-W/AP/RCS/PRED/03/Anandap
uram/001
NCRMP/B-W/AP/RCS/PRED/03/Rambilli/
002
NCRMP/B-W/AP/RCS/PRED/04/Karapa/0
01
6
7
8
9
10
11
12
Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT
8 of 15
Sno Package No. Description Method of Procurement
Schedule/ Slice
Procurement Authority Quantity (Number)
Total Estimated Cost (Million local currency)
Estimated Cost (Million USD)
Stage Initiate preparation of Specification and Bid Document
Preparation of IFB and submission to the Bank
Preparation of the Bid Document
Approval of IFB and Bid documents by the World Bank
Publication of IFB in Newspapers and UNDB
Beginning of Sale of Bid document
Opening of Bids
Submission of BER to Bank for approval/ Preparation of BER
Approval of BER
Signing of the contract
Issue of contract award notice
50% work complete
100% work complete
Completion of contractual obligations
Actual
Construction of roads to cyclone shelters in East Godavari
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
2 5.53 0.11
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in East Godavari
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
1 1.36 0.03
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in East Godavari
NCBPanchayati Raj
Engineering Department (NABARD), Govt of AP
6 14.59 0.30
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Krishna NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
4 15.49 0.32
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Srikakulam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
6 19.79 0.41
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Srikakulam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
4 17.04 0.35
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Srikakulam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
3 16.37 0.34
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Srikakulam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 9.94 0.20
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Srikakulam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 7.29 0.15
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Vizianagaram NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 10.27 0.21
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Vizianagaram NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 8.64 0.18
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Vishakhapatnam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 16.25 0.33
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11
23
24
NCRMP/B-W/AP/RHB/PRED/01/Santhab
ommali/001
NCRMP/B-W/AP/RCS/PR
ED/04/U. Kothapalli/002
NCRMP/B-W/AP/RCS/PRED/04/Uppalag
uptham/003
NCRMP/B-W/AP/RHB/PRED/02/Bhogapu
ram/003
NCRMP/B-W/AP/RHB/PRED/01/Santhab
ommali/002
NCRMP/B-W/AP/RHB/PRED/01/Santhab
ommali/003
NCRMP/B-W/AP/RHB/PRED/02/Pusapati
rega/002
NCRMP/B-W/AP/RHB/PRED/01/Kavity/00
4
NCRMP/B-W/AP/RCS/PRED/04/Thondan
gi/004
NCRMP/B-W/AP/RCS/PRED/06/Machilipa
tnam/001
NCRMP/B-W/AP/RHB/PRED/01/Polaki/00
5
NCRMP/B-W/AP/RHB/PRED/03/Nakkapal
li/001
14
15
16
13
22
17
18
19
20
21
Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT
9 of 15
Sno Package No. Description Method of Procurement
Schedule/ Slice
Procurement Authority Quantity (Number)
Total Estimated Cost (Million local currency)
Estimated Cost (Million USD)
Stage Initiate preparation of Specification and Bid Document
Preparation of IFB and submission to the Bank
Preparation of the Bid Document
Approval of IFB and Bid documents by the World Bank
Publication of IFB in Newspapers and UNDB
Beginning of Sale of Bid document
Opening of Bids
Submission of BER to Bank for approval/ Preparation of BER
Approval of BER
Signing of the contract
Issue of contract award notice
50% work complete
100% work complete
Completion of contractual obligations
RevisedActual
Construction of roads to habitations in Vishakhapatnam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 7.81 0.16
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Vishakhapatnam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 5.30 0.11
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Vishakhapatnam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 9.05 0.19
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Vishakhapatnam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
3 13.18 0.27
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Vishakhapatnam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 11.18 0.23
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Vishakhapatnam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 7.55 0.16
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in East Godavari NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 6.23 0.13
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in East Godavari NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 4.46 0.09
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in East Godavari NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 10.68 0.22
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in East Godavari NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
4 19.58 0.40
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in West Godavari NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
5 21.48 0.44
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
32
33
27
28
29
NCRMP/B-W/AP/RHB/PRED/03/Rambilli/
006
li/001
NCRMP/B-W/AP/RHB/PRED/03/Nakkapal
li/002
NCRMP/B-W/AP/RHB/PRED/03/Anandap
uram/003
NCRMP/B-W/AP/RHB/PRED/03/Paravada
/004
NCRMP/B-W/AP/RHB/PRED/03/Payakara
opeta/005
NCRMP/B-W/AP/RHB/PRED/04/Tallarevu
/002
NCRMP/B-W/AP/RHB/PRED/04/Katreni
kona/003
NCRMP/B-W/AP/RHB/PRED/03/Atchutap
uram/007
NCRMP/B-W/AP/RHB/PRED/04/Karapa/0
01
NCRMP/B-W/AP/RHB/PR
ED/04/U. Kothapalli/004
NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/
001
25
26
30
34
35
31
Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT
10 of 15
Sno Package No. Description Method of Procurement
Schedule/ Slice
Procurement Authority Quantity (Number)
Total Estimated Cost (Million local currency)
Estimated Cost (Million USD)
Stage Initiate preparation of Specification and Bid Document
Preparation of IFB and submission to the Bank
Preparation of the Bid Document
Approval of IFB and Bid documents by the World Bank
Publication of IFB in Newspapers and UNDB
Beginning of Sale of Bid document
Opening of Bids
Submission of BER to Bank for approval/ Preparation of BER
Approval of BER
Signing of the contract
Issue of contract award notice
50% work complete
100% work complete
Completion of contractual obligations
Construction of roads to habitations in West Godavari NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
3 15.71 0.32
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in West Godavari NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 11.46 0.24
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Krishna NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 15.46 0.32
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Krishna NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
3 9.07 0.19
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Krishna NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 5.79 0.12
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Guntur NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
3 13.48 0.28
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Guntur NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
5 16.73 0.34
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Guntur NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
3 8.41 0.17
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Guntur NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
3 5.82 0.12
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Prakasam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
5 14.79 0.30
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Prakasam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 5.88 0.12
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Prakasam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 8.55 0.18
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11Revised
NCRMP/B-W/AP/RCS/PR
ED/07/PV Palem/001
NCRMP/B-W/AP/RHB/PRED/05/Narsapur
/002
NCRMP/B-W/AP/RHB/PRED/05/Kalla/003
NCRMP/B-W/AP/RHB/PRED/06/Kruthive
nnu/003
NCRMP/B-W/AP/RHB/PRED/06/Machipat
nam/002
NCRMP/B-W/AP/RHB/PRED/06/Machipat
nam/001
NCRMP/B-W/AP/RCS/PRED/07/Karlapale
m/002
NCRMP/B-W/AP/RCS/PRED/07/Nizampat
nam/003
NCRMP/B-W/AP/RCS/PRED/08/Tangutur
/003
NCRMP/B-W/AP/RCS/PRED/07/Bapatla/0
04
NCRMP/B-W/AP/RCS/PRED/08/Vetapale
m/001
NCRMP/B-W/AP/RCS/PRED/08/Chirala/0
02
39
40
36
37
38
41
42
43
44
45
46
47
Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT
11 of 15
Sno Package No. Description Method of Procurement
Schedule/ Slice
Procurement Authority Quantity (Number)
Total Estimated Cost (Million local currency)
Estimated Cost (Million USD)
Stage Initiate preparation of Specification and Bid Document
Preparation of IFB and submission to the Bank
Preparation of the Bid Document
Approval of IFB and Bid documents by the World Bank
Publication of IFB in Newspapers and UNDB
Beginning of Sale of Bid document
Opening of Bids
Submission of BER to Bank for approval/ Preparation of BER
Approval of BER
Signing of the contract
Issue of contract award notice
50% work complete
100% work complete
Completion of contractual obligations
Actual
Construction of roads to cyclone shelters in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 5.94 0.12
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 11.86 0.24
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 13.22 0.27
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 20.07 0.41
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 6.69 0.14
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 14.44 0.30
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 15.16 0.31
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 12.44 0.26
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to cyclone shelters in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 11.37 0.23
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Guntur NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 11.79 0.24
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Guntur NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 10.41 0.21
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Prakasam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
3 13.83 0.29
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11
NCRMP/B-W/AP/RCS/PRED/09/Muthuku
r/002
NCRMP/B-W/AP/RCS/PRED/09/T.P.Gud
ur/005
NCRMP/B-W/AP/RCS/PRED/09/Bogole/0
03
NCRMP/B-W/AP/RCS/PRED/09/Kota/001
NCRMP/B-W/AP/RCS/PRED/09/Kavali/00
6
NCRMP/B-W/AP/RCS/PRED/09/Chillakur/
004
NCRMP/B-W/AP/RHB/PRED/07/Karlapale
m/001
NCRMP/B-W/AP/RCS/PRED/09/DV.Satra
m/008
NCRMP/B-W/AP/RCS/PRED/09/Tada/009
NCRMP/B-W/AP/RCS/PRED/09/Kavali/00
7
NCRMP/B-W/AP/RHB/PRED/07/Nagaram
/002
NCRMP/B-W/AP/RHB/PRED/08/S.Konda/
001
51
52
48
49
50
53
54
55
56
57
58
59
Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT
12 of 15
Sno Package No. Description Method of Procurement
Schedule/ Slice
Procurement Authority Quantity (Number)
Total Estimated Cost (Million local currency)
Estimated Cost (Million USD)
Stage Initiate preparation of Specification and Bid Document
Preparation of IFB and submission to the Bank
Preparation of the Bid Document
Approval of IFB and Bid documents by the World Bank
Publication of IFB in Newspapers and UNDB
Beginning of Sale of Bid document
Opening of Bids
Submission of BER to Bank for approval/ Preparation of BER
Approval of BER
Signing of the contract
Issue of contract award notice
50% work complete
100% work complete
Completion of contractual obligations
RevisedActual
Construction of roads to habitations in Prakasam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
4 14.40 0.30
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Prakasam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 10.45 0.22
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Prakasam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 18.53 0.38
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Prakasam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
3 12.43 0.26
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Prakasam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 14.21 0.29
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Prakasam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 13.68 0.28
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Prakasam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 15.89 0.33
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Prakasam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 18.24 0.38
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Prakasam NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 12.26 0.25
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 19.00 0.39
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 20.60 0.42
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
NCRMP/B-W/AP/RHB/PRED/08/S.Konda/
002
001
NCRMP/B-W/AP/RHB/PRED/08/Tangutur
/10
NCRMP/B-W/AP/RHB/PRED/08/Kothapat
nam/003
NCRMP/B-W/AP/RHB/PRED/08/Kothapat
nam/004
NCRMP/B-W/AP/RHB/PRED/08/Ongole/0
06
NCRMP/B-W/AP/RHB/PRED/09/Bogole/0
02
NCRMP/B-W/AP/RHB/PRED/08/Ulavapad
u/07
NCRMP/B-W/AP/RHB/PRED/08/Tangutur
/09
NCRMP/B-W/AP/RHB/PRED/08/Chinaga
njam/005
NCRMP/B-W/AP/RHB/PRED/09/Bogole/0
01
NCRMP/B-W/AP/RHB/PRED/08/Ulavapad
u/08
63
64
69
70
60
61
62
65
66
67
68
Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT
13 of 15
Sno Package No. Description Method of Procurement
Schedule/ Slice
Procurement Authority Quantity (Number)
Total Estimated Cost (Million local currency)
Estimated Cost (Million USD)
Stage Initiate preparation of Specification and Bid Document
Preparation of IFB and submission to the Bank
Preparation of the Bid Document
Approval of IFB and Bid documents by the World Bank
Publication of IFB in Newspapers and UNDB
Beginning of Sale of Bid document
Opening of Bids
Submission of BER to Bank for approval/ Preparation of BER
Approval of BER
Signing of the contract
Issue of contract award notice
50% work complete
100% work complete
Completion of contractual obligations
Construction of roads to habitations in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 19.04 0.39
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
3 17.52 0.36
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 20.38 0.42
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 14.09 0.29
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 11.52 0.24
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 15.75 0.32
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 20.32 0.42
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 22.52 0.46
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
1 11.35 0.23
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Construction of roads to habitations in Nellore NCB
Panchayati Raj Engineering Department (NABARD), Govt of AP
2 9.01 0.19
Appraisal
2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual
Improvements to Nowpada - Venkatapuram road from Km 0/0 to 15/0 in Srikakulam District
NCBRoads and Bridges
Department, Government of AP
1 41.05 0.85
Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 15-Dec-09 6-Mar-10 8-Mar-10 8-Apr-10 8-May-10 5-Jun-10 7-Jun-10 3-Jan-11 2-Jun-11 31-Aug-11RevisedActual
Improvements to NH5 to Patnavanipeta road (via) Tamada connecting Sundarampalem from Km 9/6 to 12/6 in Srikakulam District
NCBRoads and Bridges
Department, Government of AP
1 19.22 0.40
Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 6-Mar-10 8-Mar-10 8-Apr-10 8-May-10 5-Jun-10 7-Jun-10 3-Apr-11 31-Aug-11 29-Nov-11
81
NCRMP/B-W/AP/RD/R&B/
01/ Nowpada/006
82
78
79
77
NCRMP/B-W/AP/RD/R&B/
01/ Patnavanipeta/0
NCRMP/B-W/AP/RHB/PRED/09/T.P.Gud
ur/012
NCRMP/B-W/AP/RHB/PRED/09/V.Chala
m/007
NCRMP/B-W/AP/RHB/PRED/09/Allur/008
NCRMP/B-W/AP/RHB/PRED/09/Allur/009
NCRMP/B-W/AP/RHB/PRED/09/Indukuru
pet/011
NCRMP/B-W/AP/RHB/PRED/09/Muthuku
r/006
NCRMP/B-W/AP/RHB/PRED/09/Chittamu
r/003
NCRMP/B-W/AP/RHB/PRED/09/Allur/010
NCRMP/B-W/AP/RHB/PRED/09/Vidavalur
/005
NCRMP/B-W/AP/RHB/PRED/09/Kavali/00
4
75
76
71
72
73
74
80
Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT
14 of 15
Sno Package No. Description Method of Procurement
Schedule/ Slice
Procurement Authority Quantity (Number)
Total Estimated Cost (Million local currency)
Estimated Cost (Million USD)
Stage Initiate preparation of Specification and Bid Document
Preparation of IFB and submission to the Bank
Preparation of the Bid Document
Approval of IFB and Bid documents by the World Bank
Publication of IFB in Newspapers and UNDB
Beginning of Sale of Bid document
Opening of Bids
Submission of BER to Bank for approval/ Preparation of BER
Approval of BER
Signing of the contract
Issue of contract award notice
50% work complete
100% work complete
Completion of contractual obligations
RevisedActual
Improvements to Konada-Ramatheertham road to Konathalapalem road (via) Pasupam, Yerukonda, Kollayavalasa from km.12/0 to 16/5 (km.0/0 to 4/0 i.e. upto NH5 crossing) in Vizianagaram District
NCBRoads and Bridges
Department, Government of AP
1 15.86 0.33
Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 11-Jun-11 8-Dec-11 7-Mar-12RevisedActual
Andhra Pradesh- Roads- Total 186 1112.65 22.94
Andhra Pradesh- Bridges208.95
NCBRoads and Bridges
Department, Government of AP
1 46.20 0.95Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 20-Mar-10 22-Mar-10 22-Apr-10 22-May-10 19-Jun-10 21-Jun-10 21-Jun-11 18-Dec-11 17-Mar-12
RevisedActual
NCBRoads and Bridges
Department, Government of AP
1 33.37 0.69Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 15-Dec-09 20-Mar-10 22-Mar-10 22-Apr-10 22-May-10 19-Jun-10 21-Jun-10 21-Jun-11 18-Dec-11 17-Mar-12RevisedActual
Construction of Minor Bridge at Km 7/2 near Puligadda of Konada – Ramatheertham R&B road to Konatalapalem via Yerukonda, Pasupam
NCBRoads and Bridges
Department, Government of AP
1 34.39 0.71
Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 7-Jan-11 6-Jun-11 5-Sep-11RevisedActual
NCRMP/B-W/AP/Br/R&B/07/ Bapatla/010
Reconstruction of HLB at km 5/2 of Bapatla-Suryalanka road in Guntur District.
NCBRoads and Bridges
Department, Government of AP
1 35.83 0.74Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 20-Mar-10 22-Mar-10 22-Apr-10 22-May-10 19-Jun-10 21-Jun-10 17-Jan-11 16-Jun-11 14-Sep-11RevisedActual
Construction of Bridge at Km 11/6-8 of NH5 to Patnavanipeta connecting Sundarapalem in Srikakulam District
NCBRoads and Bridges
Department, Government of AP
1 25.85 0.53
Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 6-Mar-10 8-Mar-10 8-Apr-10 8-May-10 5-Jun-10 7-Jun-10 3-Apr-11 31-Aug-11 29-Nov-11RevisedActual
Construction of Minor Bridge across Uppugada at Km 7/6 of Srikakulam limits to Pukkalapeta via Killipalem in Srikakulam District
NCBRoads and Bridges
Department, Government of AP
1 9.50 0.20
Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 11-Jun-11 8-Dec-11 7-Mar-12RevisedActual
Construction of Minor bridge at Km 12/2-4 of NH5 to Surampeta road via Naruva, Menthada in Srikakulam District
NCBRoads and Bridges
Department, Government of AP
1 3.33 0.07
Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 11-Jun-11 8-Dec-11 7-Mar-12RevisedActual
Construction of Minor Bridge at Km 15/2 near Chakaligadda of Konada Ramatheertham R&B road to Konatalapalem via Yrukonda Pasupem, Kollayavalasa (ZP Road) in Vizianagaram District
NCBRoads and Bridges
Department, Government of AP
1 6.34 0.13
Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 11-Jun-11 8-Dec-11 7-Mar-12RevisedActual
5
1
6
7
83
8
4
3
NCRMP/B-W/AP/Br/R&B/0
7/ Perali/011
NCRMP/B-W/AP/Br/R&B/
02/ Puligadda/007
NCRMP/B-W/AP/Br/R&B/0
1/ Bendigadda/004
Construction of High level Bridge (HLB) across Bendigadda at Km 4/10 of Pundi - Parlakimindi road in Srikakulam District
05
NCRMP/B-W/AP/RD/R&B/ 02/ Konada/009
Andhra Pradesh- Bridges-
2
Reconstruction of High Level Bridge (HLB) at km 2/4 of Bapatla-Pandurangapuram across Perali Drain in Guntur District
NCRMP/B-W/AP/Br/R&B/0
2/ Chakaligadda/0
08
NCRMP/B-W/AP/Br/R&B/0
1/ Surampeta/003
NCRMP/B-W/AP/Br/R&B/0
1/ Patnavanipeta/0
01
NCRMP/B-W/AP/Br/R&B/0
1/ Uppugada/ 002
Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT
15 of 15
Sno Package No. Description Method of Procurement
Schedule/ Slice
Procurement Authority Quantity (Number)
Total Estimated Cost (Million local currency)
Estimated Cost (Million USD)
Stage Initiate preparation of Specification and Bid Document
Preparation of IFB and submission to the Bank
Preparation of the Bid Document
Approval of IFB and Bid documents by the World Bank
Publication of IFB in Newspapers and UNDB
Beginning of Sale of Bid document
Opening of Bids
Submission of BER to Bank for approval/ Preparation of BER
Approval of BER
Signin