National Cranberry Cooperative Revised 3 Arrivals Wet berries 16,400 *.8 = 13,120 Dry berries 16,400 * .2 = 3,280 Per hour 13,120/12 = 1093.3 per hour 3,280/12 = 273.3 7 am start with no changes Receiving backup wet berries (1093-675)*12 -3200 in bins = 1820 Time to unload trucks 1820/675 = 2.7 hours Total Time per worker (7am to 7pm = 12 hours + 2.7=14.7)*20 days = 294 hours Regular Time for 20 days 4 weeks * 40 hours per week = 160 hours Overtime 294-160 = 134*15 workers = 2010 Overtime cost 2010*$15.75 = $31, 658 Processing Time per worker 13,120 wet berries per day/675 berries per hour = 19.4*20 days = 388 Regular Time for 20 days 160 * 2 shifts = 320 Overtime 388-320 = 68*17 workers = 1169 Overtime cost 1169*$15.75 = $18,405 Total Overtime cost $31,658 + 18,405 = $50,063 Dry Destoners DryTrucks 4500b/h 273.3/hr 4000 Dechafer 1500 Separators W et/Dry 1200b/h 2000 Dryers Dechaffers 675b/h 3000b/h W et W etTrucks 1200 1093.3/hr Dum pers 3000b/h

National Cranberry Cooperative Solutions

  • Upload
    jrgimp

  • View
    843

  • Download
    7

Embed Size (px)

DESCRIPTION

National Cranberry Cooperative Case for MBA

Citation preview

National Cranberry Cooperative Revised 3

Arrivals

Wet berries16,400 *.8 = 13,120Dry berries16,400 * .2 = 3,280Per hour 13,120/12 = 1093.3per hour3,280/12 = 273.3

7 am start with no changes

Receiving backup wet berries (1093-675)*12 -3200 in bins = 1820Time to unload trucks1820/675 = 2.7 hoursTotal Time per worker(7am to 7pm = 12 hours + 2.7=14.7)*20 days = 294 hoursRegular Time for 20 days4 weeks * 40 hours per week = 160 hoursOvertime294-160 = 134*15 workers = 2010Overtime cost2010*$15.75 = $31, 658

Processing Time per worker13,120 wet berries per day/675 berries per hour = 19.4*20 days = 388Regular Timefor 20 days160 * 2 shifts = 320Overtime388-320 = 68*17 workers = 1169Overtime cost1169*$15.75 = $18,405

Total Overtime cost$31,658 + 18,405 = $50,063

7 am start with 1 new dryer

Receiving backup wet berries(1093-900)*12 -3200 bin capacity = 0 (no new bins needed)Total Time per worker(7am to 7pm = 12 hours)*20 days = 240 hoursRegular Time for 20 days4 weeks * 40 hours per week = 160 hoursOvertime240-160 = 80*15 workers = 1200Overtime cost1200*$15.75 = $18,900

Processing Time per worker13,120 wet berries per day/900 berries per hour = 14.6*20 days = 292Regular Timefor 20 days160 * 2 shifts = 320Overtime292-320 = 0 (no overtime)Overtime cost$0

Total Overtime cost$18,900Savings with 1 new dryer$50,063 - $18,900 = $31,163Cost of 1 new dryer$60,000/$31,163 = 2 years. A great investment.Pay Back Period

7am start with 2 new dryers

Receiving stays same

Processing time wet berries13120/1125 = 11.7 hoursBut separator becomes bottleneckProcessing time separator16400/1200 = 13.7 hours

Processing Time per worker13.67*20 = 273Regular Time for 20 days320Overtime 273-320 = 0No SavingsPayback periodInfinite, a very bad investment

Recommendations

1. Buy one new dryer2. No not convert any bins