50
Nantasket Seawall Stabilization Project DCR/USACE Public Meeting December 15, 2016 7:00pm to 8:30pm Nantasket Beach Resort

Nantasket Seawall Stabilization Project

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Nantasket Seawall Stabilization Project

Nantasket Seawall Stabilization Project

DCR/USACE Public Meeting

December 15, 2016 – 7:00pm to 8:30pm

Nantasket Beach Resort

Page 2: Nantasket Seawall Stabilization Project

Commonwealth of Massachusetts

Governor

Charles D. Baker

Lieutenant Governor

Karyn E. Polito

Energy and Environmental Secretary

Matthew A. Beaton

Department of Conservation and Recreation Commissioner

Leo P. Roy

Page 3: Nantasket Seawall Stabilization Project

DCR Mission Statement

To protect, promote and enhance our

common wealth of natural, cultural

and recreational resources

for the well-being of all.

Page 4: Nantasket Seawall Stabilization Project

Purpose of Meeting

• Project Goals

• Project Partnership – DCR and US Army Corps

of Engineers (USACE)

• USACE Findings Regarding Risk of Wall Failure

• USACE Recommended Plan and Design

• Project Schedule and Next Steps

Page 5: Nantasket Seawall Stabilization Project

Project Goals

Seawall Stabilization

• Enhance Safety

• Protect Public and Private Infrastructure and Future Investment in

DCR Master Plan work

• Set the stage for potential beach nourishment

Page 6: Nantasket Seawall Stabilization Project

Source: 2010 Coastal Engineering and Shore Protection Alternatives

Assessment (Woods Hole Group, Inc. and Louis Berger)

Enhance Safety: Protection Provided by Seawall

These lines represent where the shore line would be. Any wave action from

storms would impact areas landward of these lines.

Page 7: Nantasket Seawall Stabilization Project

Enhance Safety:

Damage Caused by the Lowering Beach

Page 8: Nantasket Seawall Stabilization Project

Protect Future Investment:

DCR Master Plan for Water Street to Bay Street

Page 9: Nantasket Seawall Stabilization Project

Cross Section of DCR Master Plan at

USACE Project Area

Existing 10’ promenade shown with red line

Page 10: Nantasket Seawall Stabilization Project

Set the Stage for Potential Nourishment

Not all Beach Nourishment

Material is the same:

Need to find the right balance

between shore protection…

…and recreation. Having a

stable seawall allows greater

emphasis on recreation.

Page 11: Nantasket Seawall Stabilization Project

Project Partnership-

DCR and the US Army Corps Engineers 1. The USACE has a history of designing coastal

solutions. USACE has been working with DCR at

Nantasket Beach for decades

a) Designed southern seawall stabilization

b) Designed northern seawall replacement and

revetment

2. The Army Corps will pay for two-thirds of this project

Page 12: Nantasket Seawall Stabilization Project

217

217

217

200

200

200

255

255

255

0

0

0

163

163

163

131

132

122

239

65

53

110

135

120

112

92

56

62

102

130

102

56

48

130

120

111

237

237

237

80

119

27

252

174

.59

Prepared By Michael Riccio

December 15, 2016

NANTASKET BEACH

COASTAL STORM DAMAGE REDUCTION PROJECT

HULL, MASSACHUSETTS

12

Page 13: Nantasket Seawall Stabilization Project

13 PROJECT PURPOSE

Prevent failure of seawall and subsequent damages to public infrastructure

• Failure experienced in 1992

• Mode of future failure evident within unprotected section of the beach

Currently Exposed Seawall Footing

Page 14: Nantasket Seawall Stabilization Project

File Name

14

Northern Revetment (2006)

TSF

(2004)

Exposed Seawall

(Study Area)

2,200 Linear Feet

Page 15: Nantasket Seawall Stabilization Project

15

IDENTIFYING THE PROBLEM – RISK OF WALL FAILURE

Conceptual Instability (Coastal Processes)

Seawalls increase scour/erosion

Calculated Instability

Stability Analysis (USACE)

Coastal Modeling (USACE)

Survey Data (DCR, current)

Demonstrated Instability

Currently Exposed Footings

Previous Undermining of Wall

Previous Failure of North Section

Page 16: Nantasket Seawall Stabilization Project

16

CONCEPTUAL INSTABILITY (COASTAL PROCESSES)

In a natural system wave energy dissipates upward

and gradually along the beach berm

Page 17: Nantasket Seawall Stabilization Project

17

CONCEPTUAL INSTABILITY (COASTAL PROCESSES)

When a seawall is in place, such as at Nantasket Beach,

wave energy meets an impasse and can no longer

dissipate gradually…

Page 18: Nantasket Seawall Stabilization Project

18

CONCEPTUAL INSTABILITY (COASTAL PROCESSES)

…instead, that wave energy is reflected violently both

upward and downward

Page 19: Nantasket Seawall Stabilization Project

19

CONCEPTUAL INSTABILITY (COASTAL PROCESSES)

Energy reflected downward, creates a scouring effect

eroding beach material along the face of the seawall.

Page 20: Nantasket Seawall Stabilization Project

20

CONCEPTUAL INSTABILITY (COASTAL PROCESSES)

Erosion continues downward and outward and begins

undermining the toe of the seawall

Page 21: Nantasket Seawall Stabilization Project

File Name

21

CONCEPTUAL INSTABILITY (COASTAL PROCESSES)

Eventually scouring undermines the toe of the seawall

and the seawall collapses.

Page 22: Nantasket Seawall Stabilization Project

22

CONCEPTUAL INSTABILITY (COASTAL PROCESSES)

Conceptual wave energy depicted in real

time at Nantasket Beach.

February

2008

Page 23: Nantasket Seawall Stabilization Project

23

CALCULATED INSTABILITY

Stability Analysis (USACE)

- Concluded that “instability of the seawall is caused by the lack of

passive resistance resulting from the continued loss of sand.”

- Confirmed that the condition of the middle section was “serious and

should be addressed as soon as possible.”

- Concluded that the “sand elevation should be at or above the footing of

the seawall to maintain its stability.”

Coastal Modeling (USACE)

- Modeled performance of the existing beach for 84 different storm events

(using existing data from previous storm events).

- Identified that even 2 year storm events could expose the footing of the

seawall

Surveys Conducted Between 2006 - 2016 (DCR)

- Surveyed sand elevations along the seawall quarterly for the past 10 years.

- Demonstrated steady erosion of the material in front of the seawall.

- Does not show signs of improving conditions.

Page 24: Nantasket Seawall Stabilization Project

24

Top of Seawall Footing

CALCULATED INSTABILITY – (CURRENT SURVEY DATA)

Page 25: Nantasket Seawall Stabilization Project

25

September 2016

Seasonal Variability of Beach Profile

DEMONSTRATED INSTABILITY

Page 26: Nantasket Seawall Stabilization Project

File Name

26

June 2016

Seasonal Variability of Beach Profile

DEMONSTRATED INSTABILITY

Page 27: Nantasket Seawall Stabilization Project

27

2004 CONDITIONS

DEMONSTRATED INSTABILITY

Page 28: Nantasket Seawall Stabilization Project

28

2004 CONDITIONS

DEMONSTRATED INSTABILITY

Page 29: Nantasket Seawall Stabilization Project

29

2004 CONDITIONS

DEMONSTRATED INSTABILITY

Page 30: Nantasket Seawall Stabilization Project

30

Seawall collapse at Nantasket Beach caused

by undermining during 1992 coastal storm

DEMONSTRATED INSTABILITY

Page 31: Nantasket Seawall Stabilization Project

31

POTENTIAL SOLUTIONS

USACE Feasibility Study

Authorized to study, design, and construct small coastal storm

damage reduction projects Section 103 - Continuing Authorities

Program

Must demonstrate a public benefit and positive Cost Benefit Ratio

Cannot be used for the purpose of providing a recreational beach

Requires a 65/35 percent cost share with non-federal sponsor for

implementation

The Federal cost for planning, design, and construction of any one

project CANNOT EXCEED $5,000,000

Page 32: Nantasket Seawall Stabilization Project

File Name

32

POTENTIAL SOLUTIONS - BEACH NOURISHMENT

Beach Nourishment

Process

- Beach Profile is rebuilt and

new material acts as

sacrificial material

protecting the toe of the wall

- Sacrificial material erodes

over time

- Beach continues to function

if re-nourished as needed.

Page 33: Nantasket Seawall Stabilization Project

33

BEACH NOURISHMENT ALTERNATIVES

10 year level of Protection - 50’ wide beach berm at elevation 9.25’

- 246,000 cubic yards of material

- Positive Benefit Cost Ratio

- Total Project Cost w/ maintenance

$55 million

25 year level of Protection - 75’ wide beach berm at elevation 9.25’

- 378,000 cubic yards of material

- Positive Benefit Cost Ratio

- Total Project w/ maintenance

- $50 million

Page 34: Nantasket Seawall Stabilization Project

34

Revetment Process

- Sloped Revetment creates more natural slope allowing

waves to break and run up the revetment, reducing the

downward wave energy that causes scour and erosion.

- Reduced scour reduces risk of the wall undermining and

collapsing.

POTENTIAL SOLUTIONS - STONE REVETMENT

Page 35: Nantasket Seawall Stabilization Project

35

POTENTIAL SOLUTIONS - REVETMENT

Project Area Without Revetment Project Area With Revetment

Page 36: Nantasket Seawall Stabilization Project

36

REVETMENT ALTERNATIVES

10 year level of Protection

25 year level of Protection

Page 37: Nantasket Seawall Stabilization Project

37

Stone Revetment – 10 Year Storm Event Protection Level - 8.25’ Crest

- 20’ Wide Slope

- Built to elevation 10’

- 14’ wide exposed revetment (i.e. 27,000 square feet of ‘lost beach’)

- Initial Construction Cost $5.8 million

RECOMMENDED PLAN

Page 38: Nantasket Seawall Stabilization Project

File Name

38

RECOMMENDED PLAN

Page 39: Nantasket Seawall Stabilization Project

USACE recognizes the

recreational usage of

beach and the concern

with impacting the limited

amount of high tide beach

DESIGN MEASURES

Page 40: Nantasket Seawall Stabilization Project

File Name

40

ORIGINAL DESIGN 40’ wide revetment

≈30’ of revetment exposed

Page 41: Nantasket Seawall Stabilization Project

41

REVISED DESIGN (REDUCED FOOTPRINT)

COULD reduce the slope

(Slope reduced from 3:1 to 2:1)

COULD NOT reduce the profile

(Design criteria requires 10’ thickness)

COULD NOT lower the revetment

(excavating below the footing would

risk failure during construction)

Page 42: Nantasket Seawall Stabilization Project

42

REVISED DESIGN (REDUCED FOOTPRINT)

COULD reduce the slope

(Slope reduced from 3:1 to 2:1)

COULD NOT reduce the profile

(Design criteria requires 10’ thickness)

COULD NOT lower the revetment

(excavating below the footing would

risk failure during construction)

Revetment width of 40’ reduced to 33’

Page 43: Nantasket Seawall Stabilization Project

43

REVISED DESIGN (REDUCED FOOTPRINT)

60’ wide project footprint = 130,000 sf

Page 44: Nantasket Seawall Stabilization Project

44

REVISED DESIGN (REDUCED FOOTPRINT)

≈14’ of revetment exposed

Page 45: Nantasket Seawall Stabilization Project

45

REVISED DESIGN (REDUCED FOOTPRINT)

Remainder backfilled and covered

≈14’ of revetment exposed ≈14’ of revetment exposed

(27,000 sf of beach “lost”)

Page 46: Nantasket Seawall Stabilization Project

46

PROJECT SCHEDULE

95% Design Complete Nov. 2016

Submit Permit Application Dec. 2016

Obtain Permits Mar. 2017

Issue Solicitation (30 Days) Apr. 2017

Open Bids May 2017

Award Contract Jun. 2017

Preconstruction Meeting Aug. 2017

Issue Notice to Proceed Aug. 2017

Mobilize Equipment Begin Work Sept. 2017

Complete Project Mar. 2018

• Begin Construction no sooner than Labor Day 2017

• Finish Construction no later than Memorial Day 2018

Page 47: Nantasket Seawall Stabilization Project

Next Steps: Nantasket Beach Reservation

• USACE Seawall Stabilization

• Scope for design contract: master plan components

• Review options for nourishment

Page 48: Nantasket Seawall Stabilization Project

Q & A

Page 49: Nantasket Seawall Stabilization Project

Q & A

Page 50: Nantasket Seawall Stabilization Project

For more information: http://www.mass.gov/eea/agencies/dcr/public-outreach/public-meetings/

If you have comments or suggestions on this project:

Submit online:

http://www.mass.gov/eea/agencies/dcr/public-outreach/submit-public-comments/

Write: Department of Conservation and Recreation

Office of Public Outreach

251 Causeway Street, Suite 600

Boston, MA 02114

Deadline – Comments accepted by DCR through Thursday, December 29, 2016

Note: Public comments submitted to DCR may be posted on the DCR website in their entirety.

If you wish to subscribe to a DCR general information or project-related

listserv: contact DCR’s Office of Community Relations at 617-626-4973 or

[email protected].

Additional Information