129
Final Report Expert’s Report for An Board Pleanála on Environmental Impact Statement for Dart Underground, Dublin Assessment of the Environmental Impacts in Relation to Ground Vibrations and Groundborne Noise, Geotechnical, Hydrogeological and Construction-related Issues August 2011 By K. Rainer Massarsch Ferievägen 25, SE 168 41 BROMMA, Sweden

NA0005 - Assessment of Groundbourne Noise, Vibration ...€¦ · Assessment of the Environmental Impacts in ... 1.6.2 Environmental Risk Management and Enforcement ... 7.2.6 Groundwater

  • Upload
    lycong

  • View
    217

  • Download
    2

Embed Size (px)

Citation preview

Final Report

Expert’s Report for An Board Pleanála on Environmental Impact Statement for Dart Underground, Dublin

Assessment of the Environmental Impacts in

Relation to Ground Vibrations and Groundborne

Noise, Geotechnical, Hydrogeological and

Construction-related Issues

August 2011

By K. Rainer Massarsch

Ferievägen 25, SE 168 41 BROMMA, Sweden

2

Contents

1 Executive Summary ..................................................................................................... 7

1.1 Background ................................................................................................................ 7

1.2 Available Information ................................................................................................ 7

1.3 DART Underground Scheme .................................................................................... 7

1.4 Community Liaison ................................................................................................... 8

1.5 Review Process .......................................................................................................... 8

1.6 Environmental Impacts .............................................................................................. 8

1.6.1 Environmental Impact Statement ....................................................................... 8

1.6.2 Environmental Risk Management and Enforcement .......................................... 9

1.6.3 Building Damage Classification ......................................................................... 9

1.6.4 Property Protection Scheme ............................................................................. 10

1.6.5 Construction Aspects ........................................................................................ 10

1.6.6 Soils and Geology ............................................................................................. 10

1.6.7 Hydrogeology ................................................................................................... 10

1.6.8 Geotechnical Impact ......................................................................................... 11

1.6.9 Vibration and Groundborne Noise ................................................................... 11

1.7 Conclusions and Recommendations ........................................................................ 12

1.8 Summary of Comments and Recommendation ....................................................... 12

2 Introduction ............................................................................................................... 19

2.1 Background .............................................................................................................. 19

2.2 Brief for the Consultant ........................................................................................... 19

2.3 Acceptance of Appointment .................................................................................... 19

2.4 Definition of Subject Areas ..................................................................................... 20

2.5 Oral Hearing ............................................................................................................ 21

2.6 Availability of Information ...................................................................................... 22

2.6.1 Environmental Impact Statement ..................................................................... 22

2.6.2 Submissions by Observers prior to Oral Hearing ............................................. 22

2.6.3 Evidence and Submissions during Oral Hearing .............................................. 23

2.6.4 Questioning During Oral Hearing .................................................................... 23

2.7 Objective and Scope of Report ................................................................................ 23

2.8 Hierarchy of Documents .......................................................................................... 24

2.9 Description of the Scheme ....................................................................................... 25

2.10 Design Considerations ............................................................................................. 25

2.11 Structure of the Report ............................................................................................. 27

3

3 Environmental Impact Statement (EIS) .................................................................. 29

3.1 General ..................................................................................................................... 29

3.2 Structure and Contents of EIS ................................................................................. 29

3.3 Comments and Recommendation on Structure of EIS ............................................ 30

4 Environmental Risk Management ........................................................................... 31

4.1 Methodology ............................................................................................................ 31

4.2 Environmental Risk Assessment ............................................................................. 31

4.3 Commitment by Applicant on Risk Management ................................................... 32

4.4 Limiting values ........................................................................................................ 33

4.5 Monitoring ............................................................................................................... 35

4.5.1 Applicant’s Evidence on Monitoring ............................................................... 35

4.5.2 Compliance Control .......................................................................................... 37

4.6 Applicant’s Commitments to ERA .......................................................................... 38

4.6.1 Risk Management (M. Conroy, Evidence OH-No. 5): ..................................... 39

4.6.2 Construction Strategy, Scheduling & Programming (K. McManus, Evidence

OH-No.18) ........................................................................................................ 39

4.6.3 Oral Hearing Closing Statement (P. Muldoon, Evidence OH-No. 249) .......... 39

4.7 Comments and Recommendation – Environmental Risk Management .................. 40

5 Building Damage Classification ............................................................................... 42

5.1 General Considerations ............................................................................................ 42

5.2 Description of Building Damage ............................................................................. 42

5.3 Condition Survey ..................................................................................................... 43

5.4 Comments and Recommendation – Building Damage Classification ..................... 44

6 Property Protection Scheme ..................................................................................... 46

6.1 Objective .................................................................................................................. 46

6.2 Clarification regarding Property Protection Scheme ............................................... 46

6.3 Comments and Recommendation – Property Protection Scheme ........................... 47

7 Construction Aspects ................................................................................................. 49

7.1 Construction Strategy .............................................................................................. 49

7.1.1 Programme of Works and Phasing ................................................................... 49

7.1.2 Construction Risks and Maximum Working Area ........................................... 50

7.1.3 Comments on Construction Strategy ................................................................ 51

7.2 Main Construction Methods .................................................................................... 52

7.2.1 Cut and Cover Sub-surface Works ................................................................... 52

7.2.2 Wall Construction ............................................................................................. 52

7.2.3 Soil Excavation ................................................................................................. 53

4

7.2.4 Ground Anchors................................................................................................ 54

7.2.5 Ground Treatment ............................................................................................. 54

7.2.6 Groundwater and Dewatering ........................................................................... 55

7.2.7 Running Tunnel Construction .......................................................................... 56

7.2.8 Rock Excavation ............................................................................................... 57

7.3 Comments and Recommendation – Construction Aspects ...................................... 58

8 Soils and Geology ....................................................................................................... 60

8.1 General ..................................................................................................................... 60

8.2 Description of Project Area ..................................................................................... 60

8.2.1 Geological Conditions ...................................................................................... 60

8.2.2 Engineering Properties of Rock ........................................................................ 61

8.2.3 Seismicity ......................................................................................................... 62

8.2.4 Geotechnical Aspects........................................................................................ 62

8.2.5 Radon ................................................................................................................ 63

8.2.6 Contaminated Ground and Aggressive Soil and Groundwater......................... 63

8.3 Impact Assessment .................................................................................................. 64

8.3.1 General .............................................................................................................. 64

8.3.2 Significance Rating ........................................................................................... 64

8.3.3 Construction Impact and General Mitigation Measures ................................... 65

8.3.4 Operational Impact and General Mitigation Measures ..................................... 66

8.4 Comments and Recommendation – Soils and Geology .......................................... 66

9 Hydrogeological Conditions ..................................................................................... 68

9.1 General ..................................................................................................................... 68

9.2 Hydrogeology of Project Area ................................................................................. 68

9.2.1 Groundwater ..................................................................................................... 68

9.2.2 Engineering Geology ........................................................................................ 69

9.2.3 Hydrochemistry ................................................................................................ 69

9.2.4 Site Investigation and Monitoring .................................................................... 70

9.3 Impact Assessment Methodology ............................................................................ 71

9.4 Impact Assessment .................................................................................................. 72

9.4.1 General Impact.................................................................................................. 72

9.4.2 Running Tunnels ............................................................................................... 72

9.4.3 Stations and Shafts ............................................................................................ 72

9.4.4 Enabling Works ................................................................................................ 72

9.5 Mitigation Measures ................................................................................................ 73

9.5.1 General Mitigation Measures ........................................................................... 73

5

9.5.2 Construction of Tunnels and Cross Passages ................................................... 73

9.5.3 Construction of Retaining Walls ...................................................................... 73

9.5.4 Temporary Dewatering ..................................................................................... 73

9.5.5 Groundwater Abstractions ................................................................................ 74

9.5.6 Hydrochemistry ................................................................................................ 74

9.6 Site-specific Construction Impact and Mitigation ................................................... 74

9.6.1 Inchicore Cut and Cover, Inchicore Station and Inchicore Intervention Shaft. 75

9.6.2 Inchicore to Heuston Station ............................................................................ 75

9.6.3 Heuston Station to Christchurch Station........................................................... 75

9.6.4 Christchurch Station to St. Stephen’s Green Station ........................................ 76

9.6.5 St. Stephen’s Green Station to Pearse Station .................................................. 76

9.6.6 Pearse Station to Docklands Station ................................................................. 77

9.6.7 Eastern Portal and Cut and Cover Section ........................................................ 77

9.7 Operational Impact .................................................................................................. 77

9.8 Comments and Recommendation - Hydrogeology .................................................. 78

10 Geotechnical Conditions ........................................................................................... 79

10.1 General ..................................................................................................................... 79

10.1.1 Field Tests ......................................................................................................... 80

10.1.2 Laboratory tests: ............................................................................................... 80

10.2 Geophysical Testing ................................................................................................ 80

10.3 Ground Conditions ................................................................................................... 80

10.4 Extent of Ground Investigations .............................................................................. 84

10.5 Reliability of Geotechnical Properties ..................................................................... 84

10.6 Dynamic Soil Parameters ........................................................................................ 87

10.7 Geotechnical Hazards .............................................................................................. 89

10.7.1 General .............................................................................................................. 89

10.7.2 Geotechnical and Geological Hazards .............................................................. 90

10.7.3 Construction-related Hazards ........................................................................... 91

10.7.4 Stability of Structures ....................................................................................... 92

10.7.5 Settlement and Ground Movement ................................................................... 92

10.8 Site-specific Construction Impact and Mitigation ................................................... 96

10.8.1 Inchicore Cut and Cover, Inchicore Station and Inchicore Intervention Shaft. 96

10.8.2 Inchicore to Heuston Station ............................................................................ 97

10.8.3 Heuston Station to Christchurch Station........................................................... 99

10.8.4 Christchurch Station to St. Stephen’s Green Station ...................................... 101

10.8.5 St. Stephen’s Green Station to Pearse Station ................................................ 102

10.8.6 Pearse Station to Docklands Station ............................................................... 104

6

10.8.7 Eastern Portal and Cut and Cover Section ...................................................... 107

10.9 Comments and Recommendations – Geotechnical Impact ................................... 109

11 Vibration and Groundborne Noise ........................................................................ 111

11.1 General ................................................................................................................... 111

11.2 Dynamic Soil Properties of Soil and Rock ............................................................ 111

11.3 Vibration Hazards .................................................................................................. 112

11.3.1 Enabling Works .............................................................................................. 112

11.3.2 Construction Phase ......................................................................................... 112

11.3.3 Operational Phase ........................................................................................... 112

11.4 Assessment of Ground Vibration ........................................................................... 113

11.4.1 Construction Phase ......................................................................................... 113

11.4.2 Operational Phase ........................................................................................... 115

11.5 Impact Criteria ....................................................................................................... 116

11.5.1 General ............................................................................................................ 116

11.5.2 Human Response ............................................................................................ 117

11.5.3 Utilities ........................................................................................................... 125

11.5.4 Vibration-sensitive Equipment and Processes ................................................ 125

11.5.5 Building Damage ............................................................................................ 126

11.6 Proposed Mitigation Measures in EIS ................................................................... 126

11.7 Comments and Recommendation – Vibration and Groundborne Noise ............... 128

7

1 Executive Summary This report presents the results of my evaluation of the Environmental Impact Statement

submitted to An Bord Pleanála and information gathered during the Oral Hearing for the

proposed construction of the DART Underground Scheme.

1.1 Background

Córas Iompair Éireanne (CIÉ), called the Applicant, has applied to An Bord Pleanála

(ABP) for a Railway Order of a high capacity DART Underground line running

underground through Dublin City centre.

ABP has appointed an in-house Inspector to examine and report on this Railway Order

application. According to instructions by ABP, I have assisted the Inspector in a specialist

capacity, covering the subject areas: geotechnical engineering (e.g. issues related to

settlement, tunnelling and excavation etc.), hydrogeology (groundwater flow, groundwater

lowering, groundwater contamination etc.) and ground vibration (including groundborne

noise).

1.2 Available Information

The Environmental Impact Statement (EIS) was submitted to ABP as part of the

application for a Railway Order to construct the DART Underground. In addition to

reviewing the EIS and attending the Oral Hearing I have also assessed evidence and other

information submitted by the Applicant, by Prescribed Bodies and Observers in relation to

the above matters, prior to and during the Oral Hearing.

The Oral Hearing has been thorough and matches the ambitions of the Applicant to realize

a world-class railway project that will cause minimal residual impacts on the environment.

The evidence provided by the Applicant was generally of high standard and presented

clearly and exhaustively. Response to questions was comprehensive.

Observers were given the opportunity to present their observations and to express their

concerns related to the construction and operation of the DART Underground. The

commitment and thoroughness of observations (submission and evidence provided by their

experts) presented by residents living along the DART Underground is acknowledged.

This information provided a valuable background when preparing this report.

This report is based on the body of information as it was available at the end of the Oral

Hearing in April 2011.

1.3 DART Underground Scheme

DART Underground is an important project to further enhance the transport infrastructure

of Dublin City which will generate an integrated public transportation network. The

Scheme is similar in concept and design to several projects carried out successfully in

major European cities. DART Underground will be the first major tunnelling project to be

constructed in the centre of Dublin.

Although there is general support for the DART Underground Scheme, objections have

been made to certain aspects of the project. It is not possible to eliminate completely

during construction nuisance and negative impact on the city, to its population and

businesses. Due to the envisaged long duration and complexity of the project it is

8

important that genuine concerns by Observers are taken seriously. However, if properly

planned, constructed, operated and maintained, the residual environmental impacts will be

kept to a minimum.

Impacts can be minimised by implementation of efficient mitigation measures and rigorous

supervision and independent monitoring. By applying modern environmental risk

management concepts it can be assured that construction and operation of the scheme is

carried out according to the requirements and conditions set out in the Railway Order.

1.4 Community Liaison

Community liaison and interaction between the Applicant, the Contractor and the public

shall be an essential element of the mitigation process throughout the project.

Transparency with regard to the impact of planned construction activities, extensive

monitoring and communication with the public are of importance. The Applicant is

committed to establishing efficient community liaison procedures.

The Applicant has confirmed that all complaints or issues received and relating to

compliance with the Railway Order or construction/operational nuisances will be relayed

to the Contractor, an Independent Environmental and Archaeological Monitor and the CIÉ

management team. All such complaints or issues raised will be actively processed until

closure.

1.5 Review Process

The Oral Hearing is an important part of the Environmental Impact Assessment process. It

lasted for 62 days and was very thorough. During Module 1 of the Oral Hearing the

Applicant summarised the contents of the EIS and provided clarification to questions

raised by the Board (Note 1 of the Order of Proceedings). During the following Modules

the submissions and evidence by Observers and their experts were presented. The

Applicant was questioned extensively and responded to all queries by ABP Experts and

questions raised by Observers.

In submissions received prior to and during the Oral Hearing, Observers presented well-

documented information and statements of their concerns. The clarifications obtained

during extensive questioning of the Applicant are an important source of information in

preparation of this report.

1.6 Environmental Impacts

This report contains my recommendations regarding the application by the Applicant for

the Railway Order. The report is divided into chapters according to the scope of my brief.

Comments and recommendations are given at the end of each chapter. Important

background information is contained in five Appendices. Of particular importance is

Appendix 4 which documents in detail the submissions made by Observers, response by the

Applicant and review comments.

The following comments are a summary of statements provided in more detail in the main

report.

1.6.1 Environmental Impact Statement

The EIS submitted to ABP was comprehensive and addresses the main concerns of

environmental impact. The EIS is considered adequate for application for a Railway Order.

9

However, in some aspects it is very brief and background information difficult to access.

The structure and presentation of information in the EIS is satisfactory. However, some

deficiencies have been noted. For instance, limiting criteria of environmental impact must

be stated unambiguously as these otherwise would be difficult to enforce.

Evidence provided by the Applicant during the Oral Hearing added important clarifications

and valuable factual information.

1.6.2 Environmental Risk Management and Enforcement

The Applicant confirmed the commitment to the implementation of a comprehensive risk

management framework which shall ensure that all works for DART Underground will be

in compliance with the requirements of a Railway Order. At all times during construction

and operation, the Applicant will retain all obligations imposed by the Railway Order.

Verifiable limiting values with respect to environmental impact shall be closely monitored

and reviewed by an Independent Environmental and Archaeological Monitor (E&AM) to

verify that the Contractor and the Applicant comply with requirements set out in the

Railway Order. In addition to information given in the EIS the Applicant described in

evidence given during the Oral Hearing a rigorous risk management framework which will

extend from project inception through the life of the project. This firm commitment further

enhances the quality of environmental impact control and minimise negative consequences

to the environment.

Environmental Risk Management, for both constructional and operational stages, shall be

as indicated by the applicant in the ‘Brief of Evidence – Risk Management Concept’

submitted to the Oral Hearing into the Railway Order application on the 1st day of

December 2010, ‘Brief of Evidence – Monitoring’ submitted to the Oral Hearing on the

14th

day of January 2011 and ‘Oral Hearing Closing Statement’ submitted to the Oral

Hearing on the 8th

day of April 2011.

1.6.3 Building Damage Classification

The building damage classification system proposed in the EIS is widely accepted and

suitable for the project.

A panel of independent chartered building surveying companies shall be established and

instructed by the Applicant regarding requirements and responsibilities when evaluating

building damage.

Building damage exceeding Category 2 shall be avoided wherever possible. Trigger levels

of the monitoring scheme shall be set not to exceed damage Category 2 and Category 1 for

historic buildings identified on the Record of Protected Structures, respectively. The

contractor shall be informed immediately and be required to modify or adjust the

construction process to avoid further damage. Changes of working method shall be

approved by the Applicant and/or the E&AM.

When building damage corresponding to or exceeding Category 2 is noted an interim

survey shall be carried out without delay. Repair work shall be implemented without undue

delay.

Assurances were given by the Applicant that particular attention will be paid to the

protection and monitoring of historic buildings with ornate plaster ceilings.

10

1.6.4 Property Protection Scheme

As an added assurance to owners of properties along the DART Underground the

Applicant has introduced a Property Protection Scheme (PPS). It is aimed at simplifying

the rectification and repair of minor damage which can arise due to construction work. The

Property Protection Scheme and in particular the limit to repair cost of € 30,000 has caused

extensive discussions and objection from some property owners. However, the PPS must

be seen in the context of unlimited liability of the Applicant and the Contractor for any

damage caused due to the construction work.

It is important that the Applicant retains full responsibility for setting up and implementing

the Property Protection Scheme throughout the construction of the DART Underground

Scheme.

1.6.5 Construction Aspects

The proposed methods off tunnel construction and deep excavation have been used

successfully in similar geological settings and geotechnical conditions elsewhere. I endorse

the proposed construction of two running tunnels by tunnel boring machines (TBMs) with

a launch portal at East Wall and a reception chamber at Inchicore. Tunnel shall be

constructed about 25m below the city centre, which is not expected to cause significant

settlement and vibration impact, provided that the proposed mitigation measures are

implemented.

Construction of stations and shafts by the top down method is the preferred alternative in

the city centre as this reduces negative environmental impact to short periods during

excavation.

Difficulties can be encountered when the tunnels are constructed in mixed face conditions.

Evidence obtained during the Oral Hearing suggests that soil properties and rockhead level

can vary more than anticipated. This aspect needs to be taken into account when selecting

construction and tunnelling methods. The proposed earth pressure balance (EPB) machine

is in my view suitable to carry out tunnelling work under such ground conditions.

1.6.6 Soils and Geology

The description of the general geological situation along the DART Underground route is

comprehensive and sufficient for assessing environmental impacts of the Scheme.

However, impact of geotechnical and geological conditions on construction work is only

addressed briefly in the EIS.

The geological and geotechnical conditions are in general favourable for the construction

of running tunnels as well as stations and shafts. However, in some locations the properties

of soil and rock can vary more than anticipated.

A significantly more detailed assessment of the geotechnical and geological conditions

within the tunnel sections and at locations of deep excavations (shafts and stations) will be

required prior to the Detailed Design and start of major construction work.

1.6.7 Hydrogeology

The hydrogeological situation along the running tunnels does not give rise to concerns.

However, supplementary geological and hydrogeological investigations are required in

some areas, also considering ground water and soil contamination.

Dewatering shall be planned and monitored carefully to avoid soil erosion and/or

consolidation settlements.

11

Where deep excavations are to be carried out, a high degree of quality control of

construction work is needed to assure that design specifications with regard to the water-

tightness of walls are actually achieved.

Flooding can have significant impact on the hydrogeological situation in the project area.

This aspect has in my view not been addressed in sufficient detail.

1.6.8 Geotechnical Impact

Geotechnical impact from construction activities was not covered in great detail in the EIS.

Prediction of settlement and assessment of risk areas follows well-accepted concepts and

additional evidence was provided by the Applicant during the Oral Hearing.

However, the EIS lacks an interpretative geotechnical report, describing geotechnical and

rock properties. Some of this information is contained in appendices to the EIS.

Geotechnical investigations cover the project alignment and are adequate for a basic

assessment of ground conditions. However, in areas with difficult ground conditions, more

detailed investigations and suitable investigation method shall be used. Also, additional

detailed geotechnical investigations are needed where deep excavations have to be

constructed in the vicinity of sensitive structures.

Geotechnical design, testing and investigation shall follow requirements stated in European

Standard, Eurocode EN 1997. All foundation work and construction work below ground

shall be carried out in compliance with European standards CEN “Execution of Special

Geotechnical Works”.

1.6.9 Vibration and Groundborne Noise

The assessment of environmental impact from vibration and groundborne noise in the EIS

is comprehensive. However, the accuracy of vibration predictions can be indicative only

and must be verified by field monitoring and full-scale tests during the construction phase

and operation.

In advance of critical activities the contractor shall work out specific method statement and

prepare a vibration mitigation program including field trials.

Prediction models of vibration and groundborne noise are preliminary and must be updated

and calibrated against field measurements.

Limiting values stated for vibration and groundborne noise shall be based - without

modification - on relevant British Standards, where applicable. The application of “change

base criteria” in areas already affected by vibration as proposed in the EIS is not

recommended.

Impact Criteria - Construction Phase

VDV levels proposed in the EIS are acceptable in principle as upper limits for the

construction phase. During night-time work or supply train operation an effort shall be

made not to exceed vibration levels having low probability of adverse comment according

to British Standard: 0.2 m.s

-1.75. Higher VDV values shall be accepted only for short

duration.

Effort shall be made by field trials and modification of the TBM construction process to

limit groundborne noise to levels not exceeding 45 dB LAmax,S during night time. When

measured vibration levels exceed 49 dB LAmax,S during night time, occupants of buildings

shall be offered without delay alternative accommodation or other form of compensation.

12

Impact Criteria - Operational Phase

Groundborne noise night-time in residential areas shall not exceed 35 dBA. Vibration

levels shall not exceed the category of low probability of adverse comments: 0.2 to 0.4 m.s-

1.75 (day-time) and 0.1 to 0.2 m.s

-1.75 (night-time), respectively.

Limits of vibrations and of groundborne noise proposed in the EIS for theatres are

acceptable. The EIS criterion of 25 dB LAmax,S shall be imposed as an absolute and upper

limit according to the frequency distribution given by the Applicant.

Limiting values shall be monitored and enforced rigorously.

1.7 Conclusions and Recommendations

The body of information provided in the EIS, clarifications and evidence presented during

the Oral Hearing have been extensive and meet high standards of environmental risk

assessment.

Concerns expressed by Observers have been taken into consideration in preparation of this

report. The proposed impact criteria are rigorous and based on relevant standards and

international best practice applied at similar projects elsewhere.

The geological and geotechnical conditions are in general favourable for construction of

two running tunnels, stations and shafts along the proposed alignment.

Well-established construction methods are proposed to be employed. TBMs equipped with

earth pressure balance shields is suitable to work under varying hydrogeological,

geological and geotechnical conditions.

The Property Protection Scheme shall be set up and operated by the Applicant throughout

the lifetime of the project. It is an added benefit to owners of property along the alignment.

All buildings affected by the proposed scheme, independent of participation in the Property

Protection Scheme, shall be surveyed and monitored.

A rigorous environmental risk management framework shall be implemented throughout

the project. This includes extensive instrumentation and monitoring of buildings in risk

area. Especially sensitive receptors such as historic buildings shall be protected by special

mitigation efforts and extensive monitoring.

In conclusion I can recommend to the Board that a Railway Order is given, considering the

comments and recommendations in this report.

1.8 Summary of Comments and Recommendation

This section lists the most important comments and recommendations given in the

respective chapters of this report.

Structure of EIS

1. The structure of the EIS is logical and addresses environmental issues which can arise in connection with a major infrastructure project. However, information regarding environmental risk management, and how risk management concepts were implemented during its preparation, are missing.

2. Limiting values or thresholds shall be strictly adhered to and not “in so far as is reasonably practicable” as stated in the EIS.

13

3. Factual information included in the EIS (e.g. results of site investigations) was reported without interpretation and analysis.

4. Although it is recognised that some aspects of environmental risk assessment can be commercially or contractually sensitive, this does in my view not justify that the description of fundamental aspects of environmental risk assessment was omitted.

5. Evidence provided by the Applicant during the Oral Hearing confirmed that strict environmental risk management procedures will be applied.

Environmental Risk Management

1. In response to the request for clarification in Note 1 of the Order of Proceedings and questions during the Oral Hearing, the Applicant has presented comprehensive evidence on risk management.

2. Rigorous risk management shall be applied during construction and operation of the DART Underground. Construction work which can cause environmental impacts shall be monitored carefully.

3. The Observational method as outlined in EN 1997 (Eurocode 7: Geotechnical design) shall be applied in the Detailed Design and mitigation measures implemented without delay should unforeseen conditions be encountered.

4. Evidence on field instrumentation and monitoring was extensive and of high standard. The Applicant has stated the commitment that extensive field monitoring will be implemented to assure compliance with environmental impact criteria.

5. Monitoring of buildings and other structures or installations shall be carried out on a regular basis, results shall be viewed by experts with competence to evaluate and interpret the type of measurement. These interpreted results shall be made available to the public on a weekly basis.

6. Annual compliance monitoring shall be carried out during the operational phase to assure that the DART Underground Scheme is properly maintained.

Building Damage Classification

1. The proposed building damage classification system is widely accepted and suitable for the project. Building damage exceeding Damage Category 2 shall be avoided. Trigger levels of the monitoring scheme shall be set not to exceed damage Category 2, and Category 1 for historic buildings identified on the Record of Protected Structures, respectively.

2. A panel of independent chartered building surveying companies shall be established. Panel members shall be instructed by the Applicant about the requirements of building surveying.

3. Condition surveys shall be carried out for buildings within the risk zone of settlement and vibration (subject to consent of the property owner), these surveys shall be carried out prior to, during and after completion of the Dart Underground.

4. Trigger levels of the monitoring scheme for building damage shall be set not to exceed Category 1 for buildings/structures on the Record of Protected Structures and Category 2 for all other buildings. Should building damage corresponding to Category 1 for buildings/structures on the Record of Protected Structures or Category 2 for all other buildings occur an interim survey shall be carried out without delay. The contractor shall be required to modify or adjust the construction process to avoid any further damage.

14

Changes to the working method shall be agreed with applicant and/or the Independent Environmental & Archaeological Monitor.

5. The contractor shall be required to engage the services of suitably qualified persons in the field of architectural heritage protection in relation to the carrying out of surveys, installation of monitoring instrumentation, interpreting monitoring data and determining appropriate repairs of any damage caused for buildings/structures on the Record of Protected Structures. The Independent Environmental & Archaeological Monitor shall also include persons suitably qualified in architectural heritage protection.

Property Protection Scheme

1. The structure and content of the Property Protection Scheme shall be as indicated in ‘Property Protection Scheme – DART Underground Oral Hearing’ submitted by the applicant to the Oral Hearing on the 19th day of January 2011. The applicant shall retain overall responsibility for the implementation and operation of the Property Protection Scheme throughout the lifetime of the DART Underground (construction and operation).

2. The limit of € 30,000 stated in the EIS shall correspond to construction cost excluding VAT and, and shall be adjusted annually and shall be adjusted annually to reflect cost of working in the construction industry.

Construction Aspects

1. The construction strategy proposed by the Applicant is based on one tunnel portal at East Wall (Eastern Portal), constructing the running tunnels by two TBMs with EPB shields. From a geotechnical and hydrogeological viewpoint, this strategy has advantages with respect to environmental impact, compared to four TBMs (requiring two portals and two reception pits in the city centre). These are:

Only one launch pit for the two TBMs will be required. The proposed site is located within the CIÉ North Wall Depot and suitable for construction of the launch pit from a geotechnical and site-specific viewpoint, compared to alternative sites.

Tunnel boring using only two TBMs may take longer than using four TBMs but the overall construction process will be simplified.

An added benefit for the contractor of using two TBMs is the extended learning process and experience which will result in adaptation of a safe and efficient construction process.

Spoil from TBM excavation can be transported by conveyor belts in the tunnels below the city to the Eastern Portal where it can be transported by rail or truck.

2. Tunnel boring can be complicated when unexpected ground conditions and mixed face boring are encountered. Mixed face tunnelling requires extra care in measuring operational parameters. Prior to the appointment of the selected contractor for the Tunnel Boring Machine (TBM) works, the contractor shall have demonstrated to the applicant sufficient experience in TBM work in ground conditions similar to those expected to be encountered in the construction of the DART Underground tunnels (i.e. mixed face, boulder clay). The required experience shall be verified by the applicant prior to the contractor’s appointment.

3. The proposed construction methods are well-established and extensive practical experience exists in Dublin from similar projects (wall construction, excavation etc.). Construction of running tunnels will be carried out at relatively large depth (20 to 25m) mainly in limestone and stiff, glacial till. This material is suitable for the proposed tunnelling process. For wall construction of Docklands station the secant pile wall method

15

was selected in the EIS. An inspection of existing basement walls in the Docklands area indicates potential problems with water-tightness. The diaphragm wall method has advantages with respect to water-tightness.

4. A final determination on the construction method to be employed in the construction of the Docklands Station (i.e. secant pile walls or diaphragm walls) shall be made based on further ground investigations and monitoring required for the Detailed Design stage, the construction method chosen shall provide for the optimal level of water-tightness.

5. A review of the EIS and evidence obtained during the Oral Hearing suggests that soil properties and rockhead level can vary more than anticipated. This aspect needs to be taken into account when selecting construction and tunnelling methods. The problem of potentially loose, water-saturated soils was identified. Variable ground conditions are not limited to layers of loose sand and gravel but are also important for problems associated with tunnelling across the rock-soil interface. In some locations this is gives rise to a potentially problematic situation for TBM operation. Tunnelling protective measures are often cost-effective in order to reduce excessive ground loss. Therefore, it is recommended that extensive field monitoring procedures are applied during the initial phase of tunnelling work in critical areas to gain experience.

6. The scheme shown on the Alignment and Structures Details drawings is enveloped by a wider maximum working area, and it is this wider area that is indicated on the Property Details drawings. However, as Detailed Design has not yet been carried out, there is some uncertainty as to the actually required land-take (vertical and horizontal), for instance with regard to extended ground treatment and underpinning work.

7. All sub-surface construction works shall be planned, carried out and monitored in compliance with Eurocodes Execution Standards: ‘Execution of Special Geotechnical Works’

Soils and Geology

1. The EIS provides a description of the general geological situation along the alignment. The information is sufficient for assessing environmental impacts of construction activities on soil and rock formations. However, impact of geotechnical and geological conditions on construction of the DART Underground is only addressed in the chapter on Settlement.

2. Information provided as evidence during the Oral Hearing indicates that soil and rock conditions can vary more rapidly over short distances than anticipated.

3. Presently available information on soil and rock is insufficient for Detailed Design and a significantly more detailed assessment of the geotechnical and geological conditions within the tunnel sections and at locations of deep excavations (shafts and stations) is needed.

4. Occurrence of faults, zones of weakness and weathering in rock needs to be determined more reliably, in particular in locations of deep excavations and mixed face tunnelling conditions. An important task is to establish the rockhead level and rockhead conditions along and perpendicular to the DART Underground alignment.

5. The extent of contaminated ground shall be determined by detailed investigations of all areas where excavations are proposed, these investigations shall be conducted prior to the commencement of excavation works as indicated by the applicant in ‘Brief of Evidence – Waste Management’ submitted to the Oral Hearing into the Railway Order application on the 17th day of December, 2010.

16

6. Potential obstructions and hazards including, inter alia, foundations, services, river walls and ordnances relating to the North Strand WWII bombing event shall be identified and addressed in the Detailed Design stage.

Hydrogeology

The Detailed Design stage, to be carried out in compliance with EN 1997 (Eurocode 7: Geotechnical design), shall include, inter alia, the following:

1. A determination of permissible limits (threshold and limiting values) for permanent or temporary groundwater level drawdown

2. Identification of areas and depths of potential contamination of groundwater and soil deposits.

3. A high degree of quality control during deep excavations relating to water-tightness of walls/structures

4. Mitigation proposals to protect groundwater quality and the hydrogeological regime in the event of a flooding occurrence during the construction phase.

Geotechnical Impact

The Detailed Design stage, to be carried out in compliance with EN 1997 (Eurocode 7: Geotechnical design) shall include, inter alia, the following:

1. (i) The inclusion of the following geotechnical and geological hazards in the geotechnical risk assessment and management scheme:

variable and unexpected ground conditions (made ground and fill)

presence of soft, instable and compressive glacio-marine deposits

sand veins (interbedded as sandy laminations in boulder clay) causing dewatering problems

gravel bed resulting in problematic groundwater inflows into excavation

contamination of ground and groundwater

high levels of methane

artesian or sub-artesian water pressure within glacial gravels

instability of shallow excavations in loose and soft ground (especially silty soils)

settlement of structures and installations in the ground (e.g. utilities) due to tunnel construction

settlement of structures and installations in the ground due to permanent lowering of groundwater

ground movements (vertical and horizontal) of structures due to construction of deep excavations

instability of excavations in soil due to fissuring and/or shearing of glacial clays

instability of excavations in rock due to discontinuities, fissuring rock and weathered rock

variability of rockhead level or unexpected deviations from design assumptions

bedded limestone with interbedded shale resulting in stability problems

dip of limestone bedding

voids in rock formation (potential of karstic features)

high groundwater pressure at tunnel level

running sands in boulder clay

difficulties during tunnel boring in mixed face conditions

settlement of loose, granular soil layers induced by blasting vibrations

obstructions to excavations (made ground, boulders etc.)

17

inflow of water into excavations due to granular horizons

unexpected ground conditions

unexploded ordnance within soft or loose superficial deposits

consequences of archaeological excavations

contamination of groundwater.

2. Consideration of the following construction-related hazards:

Construction of water-tight wall elements due to construction deviations and/or obstructions

Seating of wall elements on blocks or fractured rock layers

Instability of excavations in rock due to unfavourable bedding planes

Leakage of groundwater in soil and fractured rock into deep excavations

TBM work in weathered rock and rock formations with potential faults

TBM work in mixed face conditions (soil-rock interface)

TBM work in deposits with layers and lenses of water-bearing sands

Wear on equipment (tunnelling and excavation) due to presence of abrasive ground

Obstructions in made ground encountered during wall construction (affecting verticality of piles/panels and influencing water tightness)

Chiselling required to penetrate boulders and other obstructions

Draw-down of groundwater adjacent to excavation, due excessive pumping in excavations (leakage through or below secant pile or diaphragm wall)

Difficulties with installation and/or retraction of ground anchors in hard rock

Implementation of ground treatment adjacent to tunnels and/or excavations.

3. Geotechnical investigations to include:

Rotary open hole and core investigations

Cone penetration testing (CPT) and in very soft soils with pore water pressure measurements (CPTU)

Laboratory testing to determine strength and stiffness of soil layers

Piezometer installation

Down-hole Geophysical testing including MASW and/or seismic refraction method logging

Contamination screening.

Vibration and Groundborne Noise

I. General Recommendations

1. Limiting values stated for vibration and groundborne noise shall be based - without modification - on relevant British Standards, where applicable. The application of “change base criteria” shall not apply.

2. As part of the Noise and Vibration Monitoring (NMV) program, the contractor shall be required to work out specific method statements for construction work which can give rise to significant ground vibrations. Field trials and tests shall be carried out by the contractor in advance of critical activities. Vibration levels shall be predicted and compared with measured values.

3. Vibration measurements shall be carried out on the ground and inside of vibration-sensitive buildings. A detailed field measurement program shall be worked out by experienced specialists. All tests shall be carried out in cooperation with, or under supervisions by, the engineering team of the Applicant and independent experts.

18

II. Impact Criteria - Construction Phase

1. Vibration impact on humans is based on BS 6472-1:2008 Table 1. VDV levels proposed in the EIS are acceptable in principle as upper limits for the construction phase. During night-time, VDV levels shall not exceed: < 0.2 m.s-1.75 having low probability of adverse comment. (This can be accomplished in many cases by field trials and modification of working methods with potential of causing disturbance.) Higher VDV values shall be accepted only for a short duration (less than 10 minutes) when unexpectedly difficult ground conditions are encountered.

2. When measured vibration levels from TBM works exceed 49 dB LAmax,S during night time, occupants of buildings shall be offered without delay alternative accommodation (or, if agreeable to the contractor and affected party, other form of mitigation). The threshold level of vibration monitoring during TBM operation night-time shall be 45 dB LAmax,S S. When groundborne noise is predicted to exceed 45 dB dB LAmax,S S during night time the contractor shall in cooperation with the Applicant work out an action plan to minimize ground vibrations. An attempt shall be made to modify the construction processes and phasing of work with the aim of reducing groundborne noise to values below 45 dB LAmax,S S.

III. Impact Criteria - Operational Phase

1. Groundborne noise during night-time in residential areas shall not exceed 35 dBA.

2. Vibration levels shall not exceed VDV belonging to the category of low probability of adverse comments: 0.2 to 0.4 m.s-1.75 (day-time) and 0.1 to 0.2 m.s -1.75 (night-time).

3. For Theatres and Marconi House: limits of vibrations and of groundborne noise proposed in the EIS shall be modified according to the evidence given by the Applicant during the Oral Hearing. The EIS criterion of 25 dB LAmax,S shall be imposed as an absolute and upper limit according to the frequency distribution defined by the Applicant. The 25 dB LAmax,S criterion applies to 100% of trains. Field trials shall be carried out after construction of the tunnels to verify vibration propagation to sensitive receptors. An effort should be made by the Contractor to design the railway track to achieve a lower value than 25 dB LAmax,S.

19

2 Introduction

2.1 Background

Córas Iompair Éireanne (CIÉ), called the Applicant, has applied to An Bord Pleanála

(ABP) for a Railway Order of a high capacity DART Underground line running

underground through Dublin City centre. The Railway Order, if granted, will authorise the

Applicant to construct, maintain, improve and operate an electrified heavy railway, and the

railway works specified in the Railway Order or any part thereof.

2.2 Brief for the Consultant

ABP has appointed an in-house Inspector to examine and report on this Railway Order

application. By ABP decision PL.29S.NA0005 dated 15th

September 2010, I have been

asked to provide consulting services in relation to evaluation of the proposed construction,

operation and maintenance of the DART Underground Scheme. In particular, I have been

requested to:

(i) carry out such inspections as are considered necessary in relation to the said

application,

(ii) attend the oral hearing related to the application,

(iii) make a written report (including recommendation) to the Board on certain

aspects of the application, and

(iv) be an authorized person for the purpose of section 252 of the Planning and

Development Act, 2000.

According to instructions by ABP, I assisted the Inspector in a specialist capacity, covering

the subject areas: geotechnical engineering (e.g. issues related to settlement, tunnelling and

excavation etc.), hydrogeology (groundwater flow, groundwater lowering, groundwater

contamination etc.) and ground vibration (including groundborne noise). I have been asked

to address the following issues:

The impact assessment on the existing soils and geological environment.

Below ground noise and vibration for both the constructional and operational

phases for all aspects of the DART Underground i.e. the twin bore tunnels, the 5

underground stations, the two portals (one of which includes a station in an open

cut) and the ventilation/intervention shafts.

Hydrogeological matters relating to, inter alia, impacts on the groundwater regime,

proposals in relation to dewatering, flood impact assessment and impact on

underground rivers/water courses in the area of the proposed development).

Potential impact of settlement on permanent structures and utilities as a result of

works associated with the proposed development.

In addition to reviewing the Environmental Impact Statement (EIS) and attending the Oral

Hearing I have also been asked to assess evidence and other information submitted by the

Applicant, by Prescribed Bodies and Observers in relation to the above matters, prior to

and during the Oral Hearing.

2.3 Acceptance of Appointment

I have accepted the appointment by ABP to advise the Inspector on this project, based on

the following grounds:

20

I have more than forty years of experience in geotechnical engineering, soil dynamics and

earthquake engineering. Having worked in different parts of the world in a variety of

capacities, such as an academic and researcher, consultant and specialist foundation

contractor, I became involved in large infrastructure construction projects. I have been

retained on major projects as consultant and expert advisor to governmental organizations

and planning authorities. I have been chairman of committees responsible for preparing

European standards on execution of foundation work.

In particular, I have worked on tunnelling and foundation projects in regions with similar

geological, hydrogeological and geotechnical conditions as exist in Dublin, for instance in

southern Sweden, Denmark, Austria and Germany. I have also been responsible for setting

up risk management systems with tunnelling projects. As external examiner for a doctoral

thesis at Trinity College, Dublin, I have also had the opportunity to review geotechnical

and vibration aspects associated with the construction of the Dublin Port Tunnel. I have

also advised ABP on the Application for the Railway Order of the Metro North light

railway. I feel therefore competent to assist the Board of ABP on the DART Underground

Scheme.

As independent expert for this challenging project, I am aware of my responsibilities and

the requirement for balanced and constructive assessment of the EIS and consideration of

observations made by those affected by the DART Underground Scheme.

High international standards with regard to environmental impact should be applied for

such an important and complex project, to be constructed and operated in a metropolitan

area with many sensitive receptors.

This report presents the results of my evaluation of the Environmental Impact Statement

(EIS) submitted to An Bord Pleanála and of information made available by Observers and

the Applicant during the Oral Hearing.

2.4 Definition of Subject Areas

The subject areas covered in my report have been divided into the following main

categories:

Construction Aspects: methods required to construct the running tunnels and deep

excavations for construction of stations and shafts.

Environmental Risk Assessment: concepts used to assess environmental risks related to

tunnelling projects, with reference to settlement, ground vibration and groundborne noise

as well as geotechnical, groundwater and flooding conditions.

Soils and Geology: evaluation of geological and soil conditions along the alignment and

how these are affected by construction and operation of the Scheme.

Geotechnical engineering: ground movement (heave or settlement, lateral displacement)

caused by construction activities (earthworks, tunnelling, ground treatment, retaining

structures) and their effects on buildings and installations on and below the ground.

Geotechnical problems can be influenced by other related subject areas such engineering

geology, rock mechanics and hydrogeology, which also need to be considered.

Hydrogeology: settlements due to change of groundwater conditions, flow of groundwater,

lowering (or rise) of groundwater level and consequences on the environment, including

groundwater contamination.

21

Vibrations: ground vibrations and groundborne noise caused by construction activities, on

and below the ground such as tunnel boring and drilling, mining of tunnels, soil and rock

excavation as well as traffic-induced vibrations during construction and the operational

phase.

2.5 Oral Hearing

The inquiry held as part of the Oral Hearing has been very thorough and corresponds to the

ambitions of the Applicant to realize a world-class railway project that will not cause

residual impacts on the environment. The evidence provided by the Applicant was

generally of high standard and presented clearly and exhaustively. Response to questions

was comprehensive.

Observers were given the opportunity to present their observations regarding the EIS and

to express their concerns related to the construction and operation of the DART

Underground. The high level of commitment and thoroughness of observations

(submission and evidence provided by their experts) presented by residents living along the

DART Underground is acknowledged.

The Oral Hearing started on 22 November, 2010 and lasted until 8 April, 2011 comprising

62 days. The Order of Proceedings was divided into the following 12 Modules, cf.

Appendix 1:

Module 1: Applicant’s Submission.

Module 2: Local Authority’s Submission.

At the end of the Local Authority submission the Applicant was afforded an opportunity to respond to the submission. The Local Authority was then afforded an opportunity to question the Applicant, and the Applicant was then afforded the opportunity to question the Local Authority.

Module 3: Submissions from Prescribed Bodies.

At the end of each Prescribed Body submission the Applicant was afforded an opportunity to respond to that submission. The Prescribed Body was afforded an opportunity to question the Applicant, and the Applicant was then afforded the opportunity to question the Prescribed Body.

Module 4: Submissions from Public Representatives.

At the end of each Observer submission the Applicant was afforded an opportunity to respond to that submission. The Observer was then afforded an opportunity to question the Applicant, and the Applicant was then afforded the opportunity to question the observer.

Module 5: General Observer Submissions (not area/site specific).

Module 6: Observer Submissions from the East Wall (North of Sherrif Street).

Module 7: Observer Submissions from the Docklands Area.

Module 8: Observer Submission from the Pearse Station Area (incl. Grand Canal Dock &

Merrion Sq.).

Module 9: Observer Submissions from the St. Stephen's Green Area

Module 10: Observer Submissions from the Christchurch Area (incl. Temple Bar, Cook

St., Island St. and Heuston Station areas)

Module 11: Observer Submissions from the Inchicore & War Memorial Park Areas.

22

At the end of submissions by an Observer or group of Observers the Applicant was afforded an opportunity to respond to those submissions. The Observer was then afforded an opportunity to question the Applicant, and the Applicant was then afforded the opportunity to question the Observer.

Groundborne noise issues related to Grand Canal Theatre and results of a Listening Test

were addressed as part of Module 11 and 12, respectively.

Legal Submissions were addressed prior to and during Module 12.

Module 12: Closing Statements, presented in the following order:

Observers

Prescribed Bodies

Local Authority

The Applicant.

To the Order of Proceedings issued 27 October, 2010, the Inspector added Notes of which

Note 1 is of relevance for the subject area addressed in the present report, cf. Appendix 1:

Note 1: To expedite the proceedings, and in the interests of clarity, the applicant will be

expected to address, inter alia, the following in Module 1 as explanation of the assessment

and forecasting methodologies used to reach conclusions referred to in the Environmental

Impact Statement:

Details of the environmental risk assessment concepts utilised to identify the

environmental impact of vibrations, groundbourne [sic] noise, settlement and

groundwater lowering etc. i.e. the forecasting methods used to assess the effects on the

environment in relation to Risk Assessment.

The prediction methods and calculations used to assess effects on buildings,

equipment and inhabitants in relation to vibration from above ground works.

Calculation of groundbourne [sic] noise caused by tunnel construction and train

operation in relation to below ground noise and vibration.

Geotechnical interpretation of the results of field and laboratory tests, and a

geohydrological [sic] interpretation of the results of geotechnical and

geohydrological [sic] investigations, in relation to soil and geology.

2.6 Availability of Information

2.6.1 Environmental Impact Statement

The EIS was made available to me in September 2010 in printed and electronic format

(CD). I started my review of the EIS in October 2010. Typing errors and clerical errors

were detected. The typing errors were obvious and did not affect the technical content and

conclusions presented in the EIS. Where of significance, typing errors or mistakes in

drawings (e.g. erroneous technical units etc.) where pointed out to the Applicant during

Module 1. The Applicant checked the documents and, where appropriate, provided

corrigenda and updated drawing which are listed in Appendix 2.

2.6.2 Submissions by Observers prior to Oral Hearing

Written submissions by Observers were received by ABP prior to the Oral Hearing. A list

of submissions which were of relevance for this report is given in Appendix 2.

23

2.6.3 Evidence and Submissions during Oral Hearing

In Module 1 the Applicant presented the main elements of the EIS and provided

clarifications where requested, cf. Note 1 of Order of Proceedings. This evidence was

detailed and helped to clarify issues which were not addressed in sufficient detail in the

EIS. However, in my view this evidence did not alter the contents and main conclusions

presented in the EIS. Evidence presented by the Applicant during the Oral Hearing was

submitted in printed format and was also made available to the public on the Applicants

web site.

Submissions and evidence presented by Observers during the Oral Hearing were received

in printed format and in some cases also in electronic format.

A list of submissions presented during the Oral Hearing, identified by date and number, is

given in Appendix 2. This information is based on documentation received by ABP but

was slightly modified and updated where considered necessary. Reference is made in this

report to the submissions according to numbering used in Appendix 2.

2.6.4 Questioning During Oral Hearing

During the Oral Hearing, Observers had the opportunity to ask the Applicant questions

regarding the EIS, evidence presented in Module 1 and questions related to the

submissions during the respective modules. The Applicant responded to all questions and

provided in many cases also written evidence.

In addition to notes taken by myself I had also access to stenographic transcripts provided

by ABP. These transcripts were available only to the Inspector and ABP Experts as the

contents of the transcripts was unedited and text not verified.

2.7 Objective and Scope of Report

As required in the Brief, the objective of this report is to advise the Board on issues related

to geotechnical, hydrogeological and vibration aspects of environmental impact due to the

construction of the proposed Scheme.

Background information for justification of recommendations given in this report on

critical issues (risks, vibrations and groundborne noise) is based on submissions made

during the Oral Hearing and response given by the Applicant. My detailed review of

relevant submissions is presented in Appendix 4.

General project information regarding the EIS, administrative matters and procedural

issues will be addressed in the Inspector’s report and are not dealt with in this report unless

of direct relevance for specific issues.

I have reviewed written submissions made by Observers prior to the Oral Hearing from:

Local authority (Dublin City Council)

Prescribed Bodies

Dublin Chamber of Commerce and

Public observations by residents and businesses (or their representatives).

In addition to the information contained in the EIS, this report takes into consideration the

evidence and supporting documents provided by the Applicant during the Oral Hearing in

response to the Notes and questions by the Inspector and by ABP experts.

24

New or modified submissions were presented by Observers in the form of oral and written

statements. The Applicant responded to such evidence and questions during or at the end

of the respective module.

In order to verify the relevance of statements, claims and propositions made in the EIS and

during the Oral Hearing, I have also reviewed information from similar tunnelling projects

and compared the environmental requirements with those set out in the EIS. The

experience gained during the review of the application for the Metro North Light Railway

system was valuable as several similarities exist between these two projects. I have also

taken account of the decisions made by ABP with regard to the planning application by

RPA for the Railway Order of the Metro North.

This report is based on the body of information as it was available at the end of the Oral

Hearing in April 2011.

It is important to emphasise that this report addresses only issues related to the subject

areas given in my brief. I have restricted my evaluation and comments to the scope of the

application for a Railway Order. Environmental impacts from other sources, such as the

existing DART lines and the LUAS were only addressed when evaluating their cumulative

impact.

My examination of environmental impacts from the DART Underground and

determination of acceptable levels is based on best practice as required in the most recent

European standards (with Irish National Annexes to European EN standards, where

available), international standards as well as guidance documents issued by recognized

European or other professional organisations. Also environmental requirements from

similar infrastructure projects in Europe and elsewhere have been taken into consideration.

2.8 Hierarchy of Documents

The EIS refers in different chapters to references and documents which have been

considered relevant and applied when determining acceptable environmental impacts.

However, the list of references was not complete and it was difficult for the reader to

determine the status and hierarchy of different documents.

Upon request by ABP the Applicant has compiled a comprehensive list of Design

document s and standards which were used in the EIS (cf. Appendix 2: Submission OH-No.

218A – Definition of Hierarchy of Design Standard - CIE). The following hierarchy among

references to documents is proposed in descending order of importance:

1. EN Standards with Irish National Annexes

2. EN Standards where no Irish National Annex exists

3. Irish National Standards transposing EU, EC, ECC Standards and/or directives

4. EU, EC, ECC Standards and/or Directives

5. Technical reference documents established by European Standardisation bodies

6. Guidance documents developed by recognized European or international

professional organisations (CIRIA, CIBSE, TA Luft, TRL, TRRL, ASTM, ASCE

etc.)

7. Irish National Standards

8. International Standards

9. EIS Chapter References.

It is noted that the list of references is not complete and needs to be updated. This body of

documents is of importance for the design and construction phase of the project.

25

2.9 Description of the Scheme

A detailed description of the DART Underground Scheme is given in the EIS, Chapter 3.

Only key features and aspects of relevance for this report are summarised below.

The proposed DART Underground is approximately 8.6 km in length and comprises

approximately 7.6 km of twin bore running tunnels, cross passages, intervention and

ventilation shafts, a sub-surface station with platforms in open cut at Inchicore and five

underground stations within the city at:

Heuston.

Christchurch.

St. Stephen’s Green.

Pearse.

Docklands.

The twin bored tunnels extend from a portal at the CIÉ Railway Works, (Western Portal) to

a portal at North Wall Yard, (Eastern Portal). From Inchicore Station, the alignment

extends through a section of retained cut of approximately 200 m and section of cut and

cover tunnel of approximately 140 m prior to entering the bored tunnel.

At the Eastern Portal, the alignment ties in with the existing northern line at East Wall and

passes then through a retained cut, for a distance of approximately 250 m before changing

to a cut and cover tunnel for a distance of approximately 420 m.

Ventilation shafts, comprising passive draught relief and forced ventilation, are provided at

either end of each underground station.

Intervention shafts, typically comprising fire fighting stairs and lobby, a fire fighting lift,

emergency escape stairs, and equipment rooms, are also provided in the following

locations:

Inchicore playing field (intervention with future provision for ventilation).

Memorial Park (combined intervention/ventilation).

Island Street (intervention only).

North Wall Yard (intervention only).

Operational facilities comprise an Operational Control Centre (OCC) and Management

Suite at West Road, a Maintenance Facility at North Wall Yard, two ESB substations and

four traction substations.

A summary of the proposed alignment from Inchicore Station to the East Wall Tie-in is

provided in the EIS, Chapter 3, Table 3.1 as shown below.

2.10 Design Considerations

The DART Underground Scheme is a Public Private Partnership (PPP) which will be

carried out on the basis of a design, build, finance and maintain contract. In addition to

planning and construction, the project also includes operation and maintenance of the

Scheme. The environmental impact assessment of the Scheme can be divided into the

following phases:

Phase 1: Concept design by Parsons Brinkerhoff Ireland Ltd.

Phase 2: Preliminary design by Mott MacDonald Pettit Ireland.

Phase 3: Reference Design by Arup Halcrow Joint Venture (AHJV).

26

Phase 4: Detailed Design to be carried out by Contractor (PPPCo) to be appointed.

The EIS submitted as part of the application for the Railway Order is based on the

Reference design in Phase 3 as well as on supporting documents such as reports and

factual information (for instance records of measurements and investigations) from earlier

phases of the project. The Reference design is tentative as not all technical information

(construction processes and equipment to be employed) and environmental facts

(geological, geotechnical, hydrogeological and other information) are yet available. It is

therefore important that conservative assumptions are made in the EIS when selecting

input-values, interpreting results of investigations and proposing mitigation measures. The

Reference Design must be robust and sufficiently detailed, making it possible to identify

all significant environmental risks that may arise during construction and operation of the

DART Underground Scheme.

27

In Phase 4, the Detailed Design shall be based on additional, extensive investigations

applying more sophisticated methods of analyses. The Detailed Design will be carried out

by the PPP Contractor or Design and Build Contractor (Contractor), with the Applicant

overseeing and auditing the design with respect to environmental risks. Modification of the

DART Underground Scheme during the Detailed Design and construction work are not

permitted to exceed the environmental requirements, restrictions and limitations stated in

the Railway Order.

The Detailed Design will be influenced by details not yet available at the time of the Oral

Hearing, such as specific construction methods and equipment to be chosen by the

Contractor. Also, design will be more robust as detailed information from further

geotechnical and geological investigations will become available. Therefore, it is necessary

that the environmental impact is constantly reviewed and updated as new information

becomes available.

The adherence of the Contractor to, and the enforcement of, environmental impact limits

will ultimately be the responsibility of the Applicant.

2.11 Structure of the Report

This report is divided into the following chapters. Headings and numbering do not follow

the order of chapters in the EIS:

Chapter 4: Environmental Impact Statement

Chapter 5: Environmental Risk Management

Chapter 6: Building Damage Classification

Chapter 7: Property Protection Scheme

Chapter 8: Construction Aspects

Chapter 9: Soils and Geology

Chapter 10: Hydrogeological Conditions

Chapter 11: Geotechnical Conditions

Chapter 12: Vibration and Groundborne Noise.

Each chapter starts with an introduction containing general information. Thereafter, the

specific environmental issues are presented, including factual information from the EIS

and results of investigations in supporting documents or evidence provided during the Oral

Hearing. At the end of each chapter, comments and recommendations are given with

respect to environmental impact for consideration by the Board.

The report includes also five Appendices:

Appendix 1: Order of Proceedings of the Oral Hearing

Appendix 2: Submissions and Evidence received prior to and during the Oral

Hearing

Appendix 3: Considerations Regarding Management of Environmental Risks

Appendix 4: Review of Submissions and Evidence to Oral Hearing.

Appendix 5: Inventory of Vibration and Groundborne Noise Guidelines and

Standards for Railway Tunnels.

28

The content of the appendices has been taken into consideration when evaluating the EIS

as well as the information presented during the Oral Hearing. Of particular relevance is

Appendix 4 where all submissions made prior to and/or during the Oral Hearing are briefly

summarised (with reference to Appendix 2) and review comments are given.

29

3 Environmental Impact Statement (EIS)

3.1 General

The EIS which accompanied the application for a Railway Order describes the potential

impacts on the environment which may result from the proposed construction, operation

and maintenance of the DART Underground. The objective of the EIS is to:

identify the likely significant environmental impacts of DART Underground during

the construction and operational phases giving regard to the characteristics of the

local environment,

evaluate the magnitude and significance of likely impacts and to propose

appropriate measures to mitigate potential adverse impacts.

3.2 Structure and Contents of EIS

The EIS was issued in June 2010 and comprises the following documents:

Volume 1: Non-Technical Summary

Volume 2: Main text of the EIS (comprised of 4 Books)

Volume 3: Figures (comprised of 4 books)

Volume 4: Appendices.

In Volume 2, each aspect of the environmental impact is described in a separate chapter

under the following headings:

Introduction

Assessment Methodology

Baseline Environment

Predicted Impacts

Mitigation Measures

Residual Impacts.

The below chapters of Volume 2, respective figures (Volume 3) and Appendices (Volume

4) were of particular relevance for the preparation of this report:

Chapter 5 – Construction Strategy

Chapter 8 – Noise and Vibration: Above Ground

Chapter 9 – Noise and Vibration: Below Ground

Chapter 13 – Soils and Geology

Chapter 14 – Hydrogeology

Chapter 15 – Hydrology

Chapter 16 – Settlement of Permanent Structures and Utilities

Chapter 20 – Architectural Heritage

Chapter 23 – Human Health

Chapter 24 – Cumulative Impacts and Interaction of Effects.

30

3.3 Comments and Recommendation on Structure of EIS

1. The structure of the EIS is logical and addresses environmental issues which can arise in connection with a major infrastructure project. However, information regarding environmental risk management, and how risk management concepts were implemented during its preparation, are missing.

2. Vague statements such as “in so far as is reasonably practicable” shall be avoided when stating impact criteria.

3. Factual information included in the EIS (e.g. results of site investigations) was reported without interpretation.

4. Although it is recognised that some aspects of environmental risk assessment can be commercially or contractually sensitive, this does in my view not justify that the description of fundamental aspects of environmental risk assessment was omitted.

5. Evidence provided by the Applicant during the Oral Hearing confirmed that strict environmental risk management procedures will be applied.

31

4 Environmental Risk Management

4.1 Methodology

At this stage of the DART Underground project, not all information about different aspects

of the proposed Scheme is known. Risk management can be described as: “the art of

making judgements in the absence of complete information”, a situation which is typical

for many major construction projects. Environmental considerations are becoming

increasingly important when evaluating the benefits and negative consequences of major

infrastructure projects and more stringent environmental requirements have been adopted

on recent projects in many countries. The DART Underground Scheme is intended to meet

high international standards and therefore, modern and strict environmental risk

management concepts, which are used on similar projects elsewhere, should also be

applied in the planning, design, execution and operation of this project. A brief discussion

of environmental risk management is presented in Appendix 3.

The process of environmental risk management can be divided into the following steps:

1. Risk Assessment: identify environmental hazards which have the potential to

cause negative impact from project activities (during construction and/or operation

phase). Assess risks by combining likelihood (probability) and consequences of

hazards for various project scenarios (managed by risk register). Risks shall be

expressed in quantitative terms and shall be based on conservative assumptions,

also considering unlikely events with significant consequences. Method statements

shall be prepared for all activities which have the potential of environmental

hazards.

2. Limiting Values: state quantifiable limiting values based on internationally

accepted criteria from best practice. Where such information does not exist, use

observational method in combination with local experience to establish limiting

values.

3. Monitoring: develop, implement and maintain field measurement systems to

monitor threshold (trigger) and limiting values. Inspect structures and survey

buildings to monitor construction impact. The Property Protection Scheme is an

example of prescribing limiting values based on damage criteria. Full-scale testing

and monitoring of construction activities provide a basis for establishing limiting

values (e.g. settlement, groundborne noise or damage to structures).

4. Compliance Control: by Independent Environmental and Archaeological Monitor

(E&AM) to verify that the Contractor and the Applicant comply with requirements

set out in the Railway Order and as documented in a “live” risk register. The

Applicant shall be ultimately responsible for implementation of Environmental

Risk Assessment throughout the lifetime of the project. The Contractor shall

prepare an action plan including measures to modify construction methods and

apply mitigation when trigger values and/or limiting values are exceeded, cf.

Appendix 3, Observational method.

4.2 Environmental Risk Assessment

In order to assure that the environmental goals set out in a Railway Order are actually

achieved during the different phases of the project, it is crucial that a mechanism is put in

place which on a continuous basis verifies that environmental requirements are actually

32

met. Environmental Risk Assessment (ERA) is a systematic and transparent approach of

identifying environmental hazards and potential impacts and how these can be mitigated.

ERA provides a mechanism which encompasses the entire project from planning to design,

construction and operation until the termination of the project. It comprises different

phases, such as the preparation of the EIS by the Applicant, the Oral Hearing with

presentation of evidence and clarifications (in response to questions and submissions by

Observers) and the decision by ABP by granting a Railway Order.

A properly managed ERA provides all parties involved in the project (Applicant, planner,

designer, contractor, authorities but also the public) with information about the potential

risks from critical activities and outlines mitigation measures to avoid negative

environmental consequences of any action. Thus, ERA is an efficient tool to assure

compliance with environmental requirements set out in the Granting of a Railway Order.

However, it is equally important that the conditions are monitored, requirements are

enforced and action is taken when limits are exceeded. For each of the identified

environmental impacts and associated risks, the following steps need to be executed:

Predict quantitative impact by analyses and/or empirical methods (experience)

Set limiting values for each impact.

Prepare mitigation measures to reduce impact to acceptable level.

Monitoring by field measurements (including baseline survey prior to start of

construction/action within zone of influence).

Enforce criteria and assign responsibility for enforcement (site management).

4.3 Commitment by Applicant on Risk Management

The evidence presented by the Applicant during the Oral Hearing on risk management is

comprehensive and convincing. The following statements, which were not included in the

EIS, are reiterated as these should become conditions in a Railway Order (Appendix 1:

Document OH-No. 21, R. Bourke: Risk Management Concept):

Risk management Code of Practice: The International Tunnelling Insurance Group Code of Practice for Risk Management of Tunnel Works (the ITIG Code of Practice1) is intended as a tool to promote best practice in risk management and reduce the occurrence of accidents.

EIS and Environmental Risk Management

In summary therefore, the interrelationship between the EIS and the Environmental Risk Management can be set out as follows:

1) The EIS is a ‘snap shot’ at the stage where the scheme has a robust design. With the associated mitigation and ‘limits’ committed to in the EIS any significant environmental effects of the scheme are either removed or reduced such the residual effects are ‘acceptable’.

2) The EIS provides predictions which adopt conservative parameters to account for unlikely events and divergence from assumptions and thereby presents robust and achievable limits and thresholds.

3) Environmental Risk Management is overseen by IE (the Applicant) and runs for the whole life of the project.

4) Environmental Risk Management will be used to ensure that the project is delivered such that its significant environmental effects are no worse than the residual effects reported in the EIS, whilst accommodating unlikely events, future refinement of the design or construction methodology, introduction of new SI data etc.

The below figure illustrates how this interrelationship evolves during the project phases.

33

4.4 Limiting values

The determination of quantifiable limiting values is essential for implementation of an

EIA. One major deficiency of the EIS is that it lacks in several sections definite and

verifiable limiting values of environmental impacts. In several chapters, the following

ambiguous phrase or similar expressions are used: “in so far as is reasonably practicable”.

The following are examples of statements in the EIS which are not acceptable for

environmental monitoring and control1:

8.6 Mitigation Measures - Above Ground Noise & Vibration

The Noise and Vibration Control Plans which will be based on and include method statements for each area of the works, the associated specific measures (to be at least those from the NVMP) to minimise noise and vibration in so far as is reasonably practicable for the specific works covered by each plan and a detailed appraisal of the resultant construction noise and vibration generated.

9.5 Mitigation Measures - Groundborne Vibrations The design development of the base scheme and its alignment has included the need to reduce environmental impact in so far as is reasonably practicable.

9.5.1. Construction - General

Prior to the commencement of any works on site, the Contractor will implement a mitigation strategy (at source – for all DART Underground noise and vibration sources - or receptor) at Marconi House, Gaiety Theatre and Grand Canal Theatre in order to reduce or remove, in so far as is reasonably practicable, the adverse groundborne noise effects from DART Underground works during critical operational times (e.g. performance, broadcast and critical rehearsal times).

9.5.1.2. TBMs

The Contractor will be obliged to implement a mitigation strategy (at either source or receptor) for the significant adverse effect on residential properties at Inchicore; Marconi House; Gaiety Theatre; and Grand Canal Theatre, in order to reduce or remove, in so far as is reasonably practicable, the adverse groundborne noise effect at night time for residential properties and during critical operational times (e.g. performance broadcast and critical rehearsal times) for non-residential property.

9.5.1.3.9. TBM Supply Trains

1 Numbering in accordance with EIS; emphasis of underlined quotes added.

34

Where necessary and where reasonably practicable, the Contractor will ensure that groundborne noise from the jointed track which the supply trains operate upon will be mitigated.

9.5.1.4 Blasting

The Contractor will be obliged to implement a mitigation strategy (at either source or receptor) for Marconi House, Gaiety Theatre and Grand Canal Theatre in order to reduce or remove, in so far as is reasonably practicable, the adverse groundborne noise effect during critical operational times (e.g. performance broadcast and critical rehearsal times).

The vague definition of limiting values creates uncertainty regarding the willingness of the

Applicant to enforce strict limits. This has been the reason for major concern expressed by

Observers during the Oral Hearing. In evidence presented during the Oral Hearing

(Appendix 2: Document OH-No. 70A) the Applicant confirmed that the term “in so far as

is reasonably practicable” will be replaced by strict and enforceable limiting values. The

Applicant has given the following definition of limits for monitoring:

Limiting Value or Threshold – the maximum, worst case or not to be exceeded value for any particular criterion and the value used to determine the associated impact in the EIS. Limiting Values or Thresholds are either stated in this evidence or reference has been made to their presentation in the EIS.

Predicted Value – the value for any particular criterion that is most likely to occur during construction when adopting best practice construction means and methods.

The below figure which is reproduced from Evidence OH-No. 70A illustrates the

application of limiting values established as part of the Reference Design for enforcement

of environmental limits and predicted (trigger) values for monitoring as determined in the

Detailed Design.

35

4.5 Monitoring

Monitoring has a central role in environmental risk management. The following definition

of Monitoring is given in the Glossary of the EIS:

Monitoring: The repetitive and continues observation, measurement and evaluation of environmental data to follow changes over a period of time to assess the efficiency of control measures.

However, the EIS does not discuss the role of monitoring as part of the environmental

impact assessment process. Due to lack of information on monitoring, the Applicant was

requested to provide detailed evidence with description of how to implement

environmental impact monitoring throughout the project and in particular the overall

strategy for monitoring during construction of the DART Underground.

4.5.1 Applicant’s Evidence on Monitoring

In response to the questions by the Inspector and ABP experts, extensive evidence was

presented by the Applicant on field monitoring. The following section summarises the key

issues which were addressed in the evidence by the Applicant (OH-No. 70A):

This evidence summarises the project’s instrumentation and monitoring obligations relating to the verification of design, construction process control, environmental monitoring and third party asset protection.

Instrumentation and Monitoring Strategy describes why monitoring is an essential element of the risk management strategy for construction of DART Underground and also confirms the monitoring provision.

Instrumentation and Monitoring Methods describe the instrumentation and methods to be deployed to capture the field data during construction relating to the various elements of DART Underground.

Instrumentation and Monitoring Framework sets out the manner in which monitoring data will be processed and made readily available to those who need access to be in a position to respond to that data if required.

Action and Response to Observations outlines the protocol of trigger values set against the Limiting Values identified in the EIS.

The Applicant confirmed the instrumentation and monitoring strategy and monitoring

requirements previously presented in the evidence dealing with the following aspects:

Construction Strategy

Risk Management Concepts

Geotechnics, Soils and Geology

Settlement of Permanent Structures and Utilities

Property Protection Scheme

Hydrogeology

Below Ground Noise and Vibration

Above Ground Noise and Vibration

Air Quality

Hydrology

Traffic.

The evidence describes methods of instrumentation and monitoring to verify the predicted

impacts. Reference is made to Appendix 2: Document OH-No. 70A.

The Contractor will be required to undertake monitoring as follows:

36

Construction Phase Monitoring

Noise and Vibration monitoring for above and below ground works

Ground settlement monitoring

Condition monitoring for buildings (during blasting etc.)

Dust deposition monitoring

Occupational monitoring programme the tunnel

Groundwater level and quality monitoring (also to take account of features dependent on groundwater abstractions and archaeological features)

Surface water quality monitoring

Archaeological monitoring

Monitoring of waste and materials leaving DU sites (as part of waste audit)

Traffic monitoring as part of Construction Traffic Management Plan

Monitoring of Resident car parking

The proposed Environmental and Architectural Monitor (E&AM) will validate all monitoring and undertake check monitoring as required independent of the Contractor.

Operational Phase Monitoring

Vehicle and pedestrian monitoring (in the vicinity of stations)

Cycle parking utilisation

Surface and groundwater monitoring (specified for 3 and 24 months post-construction, respectively)

Monitoring of Resident car parking around Inchicore and Pearse

The Applicant summarised the obligations regarding monitoring as follows:

This evidence has summarised the project’s instrumentation and monitoring obligations relating verification of design, construction process control, environmental monitoring and third party asset protection. The monitoring strategy and framework will provide an effective instrumentation and monitoring regime by ensuring that:

Baselines are established against which measurements can be compared.

There are unambiguous responsibilities to ensure that all data gets captured and interrogated as planned.

There is a framework in place to allow for efficient reading, recording, processing and communication of data so that the people who need the data to make decisions regarding construction activities have the necessary data available in a format that can be readily interpreted and understood.

Risks of exceedance [sic] are minimised by early warning of emerging trends.

There is clarity of definition of Trigger and Limiting Values and clear responsibility for action if Trigger Values are exceeded.

Reliability of data, such that those using the data have confidence in its accuracy. This requires the ability to verify the data if necessary e.g. primary and secondary monitoring

The evidence has presented instrumentation and monitoring strategy that will be delivered within a robust management framework to ensure that the principal aims of monitoring are achieved for DART Underground as follows:

Design verification and construction process control

Environmental monitoring

Third party asset protection

37

In conclusion, for the overall monitoring strategy to be effective it must not involve any decisions based on subjectivity and it has to focus on the impacts of construction that can be easily measured and communicated to, and therefore readily understood by, the site teams. Most importantly the impact must be easy to define and measure.

The clarification obtained during the Oral Hearing by the Applicant on field

instrumentation and monitoring was important and complies with high standards. If

implemented as described, field monitoring will assure compliance with environmental

impact mitigation measures. Thus, many justified concerns of Observers expressed in

submissions can be alleviated.

4.5.2 Compliance Control

According to the EIS, compliance with the requirements will be assured by construction

site management as outlined in the EIS, Chapter 5 (Construction Strategy):

5.22. Construction Health and Safety 5.22.3.1. Construction Site Management

There will be a Contractor management team on site for the duration of the construction phase. The team will supervise the construction of the Works including monitoring the Contractors performance to ensure that the proposed construction phase mitigation measures are implemented and that construction impacts and nuisance are minimised.

However, this commitment in the EIS does not describe in sufficient detail how

independent compliance control is assured during construction and operation of the DART

Underground. Therefore, the Applicant was requested to present clarification and evidence

regarding the obligations for compliance control.

The Applicant presented the management framework with obligations to assure

compliance and enforcement of environmental requirements (OH-No. 70A):

Management Framework

As set out previously in Mr. Mark Conroy’s evidence, CIÉ/IÉ will retain all obligations, including the Environmental & Archaeological obligations, imposed on them by the Railway Order (including the EIS) during the construction and operational phases of the DART Underground Project.

Environmental Management Plan & Monitoring

In order to manage and control the overall Environmental and Archaeological risk exposure to the Project, CIÉ/IÉ is proposing that the Contractor develop an Environmental Management Plan in accordance with the EIS. CIÉ/IÉ is committed to assuring compliance with the Railway Order (including the EIS) and therefore:

1. An independent Environmental & Archaeological Monitor (E&AM) will be appointed jointly by CIÉ/IÉ and the Contractor. The proposed E&AM will report on the compliance of the Contractor with the commitments in the Environmental Management Plan its daughter plans (e.g. Noise & Vibration Management Plan and Noise & Vibration Control Plans) and Railway Order.

2. CIÉ/IÉ will engage a team of engineers and environmental scientists and a project archaeologist to review data submitted by the Contractor, liaise with authorities and interested parties, and monitor the performance (technically and environmentally) of the Contractor.

3. An Independent Certifier (IC) will be appointed jointly by CIÉ/IÉ and the Contractor. The proposed IC will independently monitor and report on all the design, procedures and construction etc. either carried out or implemented by the Contractor.

Non-compliance Issues and Breaches

The Contractor will establish and implement environmental monitoring throughout the project. The methodology will be sanctioned by the E&AM and the CIÉ/IÉ team of engineers and environmental scientists. The Contractor’s monitoring results will be issued to both CIÉ/IÉ and the E&AM for assessment. CIÉ/IÉ and the E&AM will also undertake sample monitoring to verify the Contractor’s process and monitoring results. As set out previously in Mr. Mark Conroy’s evidence, all validated

38

monitoring data will be made available to any interested parties in a manner and format that is easily accessible.

The Contractor will be contractually compelled to immediately inform CIÉ/IÉ and the E&AM of any circumstances which may give rise to non-compliance and breaches of the imposed conditions and obligations set out under the Railway Order and the PPP Contract.

The Contractor will be responsible for promptly implementing whatever action is required to remedy the issue that has arisen. CIÉ/IÉ, the E&AM and the IC will have the right to access the site and carry out audits of the systems and the works at any time during the construction of the project.

If an act or default of the Contractor or a related party has caused, or is likely to cause, CIÉ/IÉ to be in breach of their obligations under the Railway Order then CIÉ/IÉ will have the right under the PPP Contract to suspend the whole or part of the works. The suspensions will be issued by CIÉ/IÉ or their appointed representatives and last until an effective remedy has been approved and put into place by the Contractor.

Action and Emergency Response Plans

The I&M Plans will be developed into the following documents:

Action Plans will be prepared by the Contractor to develop the actions to be taken in response to monitoring data and breaches of trigger values. Action Plans will be required to address the planned response to breaches of all three trigger levels (green, amber and red).

Emergency Response Plans will be developed in conjunction with Asset Owners and will detail the planned response to Back Trigger values.

The Contractor shall ensure that resources necessary to take the defined actions are available so that Action Plans and Emergency Response Plans can be implemented promptly. In addition, emergency drills should be identified and undertaken.

The monitoring data related to each element of the Works shall be reviewed on each shift by the Shift Review Group (SRG) for each construction site and tunnel drive. The SRG, outlined in red on this slide of the Project Management Framework, will typically comprise:

Contractor: Senior Engineer/Environmental Manager for work being undertaken, Senior Monitoring Engineer.

Contractor’s Designer: Senior Design Engineer

Independent Environmental and Archaeological Monitor (E&AM): Senior Field Engineer

CIE Works Review Team: Senior Engineer.

4.6 Applicant’s Commitments to ERA

Note 1 of the Agenda for the Oral Hearing requested clarification how environmental risk

assessment concepts are being applied to DART Underground. Specific environmental risk

assessment concepts used were addressed by the relevant technical experts in their

respective briefs:

• Below ground noise and vibration, R. Greer

• Above ground noise and vibration, J. Harmon

• Soils and geology, S. Mason

• Settlement, S. Fricker

• Hydrogeology, K. Cullen, and

• Construction strategy, K. McManus.

During Module 1, the Applicant confirmed his commitment to the implementation of

environmental risk management:

39

4.6.1 Risk Management (M. Conroy, Evidence OH-No. 5):

There has been significant interaction between design engineers and environmental specialists contributing to the EIS; and also between the multi-disciplinary consultants and CIÉ/Iarnród Éireann. This interaction led to design iteration and refinement that culminates in the DART Underground design presented in the Railway Order Application. The environmental assessments undertaken for the EIS and the environmental risk management of the DART Underground design are parallel and supporting processes.

The environmental assessments undertaken for the EIS and the environmental risk management of the DART Underground design are parallel and supporting processes.

Subject to approval of the Railway Order, CIÉ/Iarnród Éireann commits to continued use of the risk management concepts throughout the life of the project. This will include auditing and enforcing risk management for the duration of the project. As the project proceeds, CIÉ/Iarnród Éireann will appoint a Risk Manager as part of the CIÉ/Iarnród Éireann team for the Detailed Design Stage and Construction Design Stage to manage the auditing and enforcement of the risk management programme.

CIÉ/Iarnród Éireann will employ a team of engineers and scientists to manage the risk management programme, to review all data from the detailed design and construction stages, to liaise with authorities and interested parties and to audit the performance of the works.

4.6.2 Construction Strategy, Scheduling & Programming (K. McManus, Evidence OH-No.18)

With regard to risk management in relation to construction strategy, the following assurances were given:

The concepts utilised to identify the environmental risk of construction are generally those outlined in ‘A Code of Practice for Risk Management of Tunnel Works’ prepared by the International Tunnelling Insurance Group 2006.

Multidisciplinary design iterations and reviews have been conducted throughout the project development stage, resulting in the refinement of design and construction direction described by Mr. C. Lavery and the Risk Management process to be described by Mr. Roland Bourke.

Furthermore, the hazards identified, the risks assessed at specific locations along the project and the mitigation or contingency measures identified by the various discipline specialists have been assimilated in conjunction with the design engineers into the development of construction methodologies, particularly those below ground. As part of this process, the feasibility of a regime of contingent methodologies has been established to cater for the spectrum of hazards identified through site and ground investigation and also across the range of likelihoods of the related risks coming to pass.

The EIS, which forms in large part the submission currently before the Board, has been prepared using concepts founded in risk management and propounded by authoritative international bodies, with the objective of mitigating the impacts of construction of DART Underground to those as low as reasonably practicable.

4.6.3 Oral Hearing Closing Statement (P. Muldoon, Evidence OH-No. 249)

Risk Management for DART Underground is being undertaken within a Risk Management Framework which will extend from project inception through the life of the project.

The approach adopted by DART Underground is consistent with international best practice including the ‘Code of Practice for Risk Management of Tunnel Works’ prepared by the International Tunnelling Insurance Group (ITIG) in 2006.

The development of the EIS and Environmental Risk Management are parallel and supporting processes. The EIS preparation, as I said earlier, is an iterative process, which links into both design development and the first stage of the ongoing environmental risk management process. Moreover, the Environmental Impact Assessment culminates in the granting of a Railway Order, whilst the Environmental Risk Management process continues for the life of the project.

During the construction phase, information will be obtained that will inform further iterations of the

40

environmental risk assessment, including noise and vibration monitoring for above and below ground works; ground settlement monitoring; condition monitoring for buildings and groundwater level monitoring. The monitoring results will be continually reviewed against both the limits set out in the EIS and any updated predictions. On this basis the ongoing assessment of risk will always be based on current information.

4.7 Comments and Recommendation – Environmental Risk Management

The EIS contained insufficient information on how environmental risks associated with the

DART Underground Scheme shall be managed during design, construction and operation.

In response to the request for clarification in Note 1 and to questions during the Oral

Hearing, the Applicant has presented comprehensive and convincing evidence on risk

management.

Mr. Bourke presented a detailed description of the Risk Management Concept (Evidence

OH-No. 2, Risk Management Concept, Roland Bourke, Property Controls Manager) on

which the EIS is based. It was confirmed that, although this aspect was not emphasised in

in the EIS, close interaction and discussion of environmental issues took place between

different technical disciplines.

Mr. Fricker presented a comprehensive document describing field monitoring (Evidence

OH-No. 70A) and clarifications regarding limiting values, field monitoring and compliance

control. This document describes in great detail how monitoring issues will be applied.

In his closing statement (Evidence OH-No. 249, Oral Hearing Closing Statement P.

Muldoon) Mr. Muldoon confirmed the commitment of the Applicant to the implementation

of a comprehensive risk management framework. This in my view satisfies high

international requirements of risk management. The assurances given by the Applicant will

have great significance for the safe implementation of the DART Underground Scheme

and shall help to alleviate the concerns expressed by many Observers.

In summary, Environmental Risk Management, for both constructional and operational

stages, shall be as indicated by the applicant in the ‘Brief of Evidence – Risk Management

Concept’ submitted to the Oral Hearing into the Railway Order application on the 1st day

of December 2010, ‘Brief of Evidence – Monitoring’ submitted to the Oral Hearing on the

14th

day of January 2011 and ‘Oral Hearing Closing Statement’ submitted to the Oral

Hearing on the 8th

day of April 2011.

The following comments and recommendations are made:

1. In response to the request for clarification in Note 1 of the Order of Proceedings and questions during the Oral Hearing, the Applicant has presented comprehensive evidence on risk management.

2. Rigorous risk management shall be applied during construction and operation of the DART Underground. Construction work which can cause environmental impacts shall be monitored carefully.

3. Monitoring of buildings and other structures or installations shall be carried out on a regular basis, results shall be viewed by experts with competence to evaluate and interpret the type of measurement. These interpreted results shall be made available to the public on a weekly basis.

4. Evidence on field instrumentation and monitoring was extensive and of high standard. The Applicant has stated the commitment that extensive field monitoring will be implemented to assure compliance with environmental impact criteria.

41

5. Monitoring of buildings shall be carried out on a regular basis. Results shall be reviewed by experts with competence to evaluate and interpret the type of measurement. These interpreted results shall be made available to the public, preferably on a weekly basis.

6. Annual compliance monitoring shall be carried out during the operational phase to assure that the DART Underground Scheme is properly maintained.

42

5 Building Damage Classification

5.1 General Considerations

Construction of infrastructure projects such as the DART Underground in and below an

urbanised area with sensitive receptors has the potential of causing inconvenience to

humans and damage to buildings, structures and installation and below the ground as well

as utilities and infrastructure. While it is impossible to avoid inconvenience during limited

periods of construction, efforts must be made to avoid or at least to keep damage to

buildings and other structures to a minimum. Environmental risk management is the most

efficient approach of avoiding potential risks to buildings. Identification of a risk zone

along the alignment and extensive monitoring are essential elements. The consequences of

construction work leading to building damage are of major concern to the public and this

issue was raised by many Observers during the Oral Hearing.

The city centre of Dublin is the home of important architectural and cultural heritage. Such

buildings are particularly sensitive to environmental impact and can suffer from

construction activities, if not properly planned, designed and executed.

5.2 Description of Building Damage

The EIS addresses building damage in Chapter 16, Settlement of permanent structures and

utilities. Chapter 16.2.4.1 presents in Table 16.1 a method of characterising building

damage based on ease of repair. It should be noted that this classification system is not

limited to damage from settlement but also to other impacts such as vibrations, variations

of groundwater, temperature changes etc.

The basic concept of “ease of repair” is widely accepted among engineers and has been

applied on many infrastructure projects. However, this concept is often misunderstood by

the public as it is interpreted as an interpretation of the significance of damage to

occupants of buildings. The proposed damage classification system is related to the cost of

repair and does not address the subjective experience that a property owner may have when

detecting cracks in a wall.

It is important to note that this table shall not be applied without careful consideration of

specific requirements to buildings of architectural heritage where even minor cracks can

require significant repair work.

For conventional buildings an important dividing line is between damage Category 2 (Very

slight) and Category 3 (Slight). If damage exceeds Category 2, this is usually associated

with significant ground movement and the causal relationship between construction

activity and observed damage becomes easier to identify.

The objective of ERA and of the proposed monitoring scheme is to avoid that building

damage exceeds Damage Category 2. This can be achieved by keeping the Contractor(s)

informed should any cracks corresponding to Damage Category 2 develop in buildings.

When monitoring and inspection of buildings indicates that damage has been sustained

corresponding to Building Category 2, the Contractor shall be informed immediately. The

method statement for construction work in the vicinity of affected buildings shall be

reviewed in cooperation with the Applicant’s team and the E&AM. The Contractor shall be

required to take immediate action in order to avoid further damage to occur.

43

It is important to keep in mind that all buildings deteriorate to some degree with time.

Cracks can develop due to the unavoidable aging process. Various factors can induce

cracks and aggravate exiting damage, such as temperature changes within a building or as

a result of seasonal temperature and humidity variations. Also other factors, such as type of

building material, activities in buildings and maintenance can influence damage patterns in

buildings. Construction work or other activities inside or near an affected building –

unrelated to the DART Underground – must also be taken into consideration.

5.3 Condition Survey

The Applicant has confirmed that condition surveys shall be undertaken by chartered

building surveyors and chartered structural engineers with expertise from architectural

heritage as required depending on the type of structure.

Condition surveys (the “Dilapidation Protocol”) will be prepared for all buildings within

the risk zone of settlement and vibration provided that permission is obtained by the

44

property owner. Conditions surveys will also be supplemented by installation of different

types of monitoring equipment, where possible and permitted by the property owner.

Condition surveys shall be carried out in the presence of the property owner. The

dilapidation protocol shall be counter-signed by the property owner and any disputes shall

be referred to an arbitrator according to the procedures outlined in the manual prepared for

the implementation of the Property Protection Scheme.

The condition survey will cover each room in a building, examine each wall, each ceiling,

and each floor, with the aim to record any defects. Cracks and other defects will be

recorded on drawings; photographs will be taken and any cracks will be given a category

number, given a category number in accordance with the Building Research Establishment

Digest 251. That digest contains a table which is similar to the Building Damage

Categories. The condition survey will also contain a number of photographs associated

with each defect that is visible. The information on building survey contained in the

following reports should also be considered: BRE Digest 343, Simple measuring and

monitoring of movement in low-rise buildings – Part 1: cracks, (1989) and BRE Digest

344, Simple measuring and monitoring of movement in low-rise buildings - Part 2:

settlement, heave and out-of-plumb, (1995).

With respect to damage due to vibrations and shocks, the following standard should be

used as minimum requirement: British Standards (BS) 7385-2; Evaluation and

measurement for vibration in buildings - Part 2: Guide to damage levels from

groundborne vibration, (1993); Annex A, B and C.

It should be noted that in special cases (historic buildings, sensitive structures, installations

in the ground etc.), the extent and type of the condition survey must be adapted to the

specific requirements. For instance, utilities shall be inspected carefully at critical

(vulnerable) sections, combined with surveying and monitoring.

5.4 Comments and Recommendation – Building Damage Classification

1. The proposed building damage classification system is widely accepted and suitable for the project. Building damage exceeding Damage Category 2 shall be avoided. Trigger levels of the monitoring scheme shall be set not to exceed damage Category 2, and Category 1 for historic buildings identified on the Record of Protected Structures, respectively.

2. A panel of independent chartered building surveying companies shall be established. Panel members shall be instructed by the Applicant about the requirements of building surveying.

3. Condition surveys shall be carried out for buildings within the risk zone of settlement and vibration (subject to consent of the property owner), these surveys shall be carried out prior to, during and after completion of the Dart Underground.

4. Trigger levels of the monitoring scheme for building damage shall be set not to exceed Category 1 for buildings/structures on the Record of Protected Structures and Category 2 for all other buildings. Should building damage corresponding to Category 1 for buildings/structures on the Record of Protected Structures or Category 2 for all other buildings occur an interim survey shall be carried out without delay. The contractor shall be required to modify or adjust the construction process to avoid any further damage. Changes to the working method shall be agreed with applicant and/or the Independent Environmental & Archaeological Monitor.

45

5. The contractor shall be required to engage the services of suitably qualified persons in the field of architectural heritage protection in relation to the carrying out of surveys, installation of monitoring instrumentation, interpreting monitoring data and determining appropriate repairs of any damage caused for buildings/structures on the Record of Protected Structures. The Independent Environmental & Archaeological Monitor shall also include persons suitably qualified in architectural heritage protection.

46

6 Property Protection Scheme

6.1 Objective

In order to assure owners of property located above or adjacent to the DART Underground

alignment protection against damage, the Applicant has set up Property Protection Scheme

(PPS). The PPS is described in Chapter 16.7 of the EIS and in a separate brochure issued

by the Applicant. During Module 1 of the Oral Hearing, the Applicant presented details of

the PPS (OH-No. 27; Mark Conroy: Property Protection Scheme).

Owners of property within a risk zone above or adjacent to the tunnel(s), shafts and

excavations (as defined by the predicted 1 mm settlement contour or 30m from the tunnel

centreline and 50m from shafts, whichever is the greater) are entitled to join the PPS.

Participation in the PPS does not infringe on any legal or other rights of the property

owner. The Applicant proposes that the Contractor assumes responsibility for the PPS. It

will remain in place for 12 months after completion of the underground works or longer in

the case settlement does continue.

The Applicant will establish a panel of three independent firms of building surveyors.

These firms will carry out an initial condition survey report (Dilapidation Protocol). After

construction, a final condition survey will be carried out and a second survey report will be

prepared.

If damage exceeding Category 2 is noted during construction of the DART Underground,

an assessment will be carried out by the building surveyor, resulting in an interim survey

report. If the interim survey and report recommends repairs to rectify the damage caused

by the DART Underground works, and those repairs cost up to € 30,000, the

recommendations will be implemented. In EIS, Chapter 16.2.2 (Basis of Assessment

Methodology) the following conditions are stated for historic buildings (protected

structures):

Any cosmetic impacts, such as minor cracking that may occur within buildings associated with a damage category of slight for general buildings and very slight for buildings that are on the Record of Protected Structures, will be repaired under the Property Protection Scheme.

It can be assumed that cost of repair of damage falling within Category 1 and 2 will be

below a limit of € 30,000. In the event of a dispute, the case will be referred to an

independent expert, selected from a panel established by the Institution of Engineers of

Ireland.

6.2 Clarification regarding Property Protection Scheme

During the Oral Hearing, the Applicant responded to questions from the Inspector, ABP

Experts and Observers. The Applicant was requested by the Inspector to prepare and

present a written document summarising evidence given at different occasions during the

Oral Hearing. The Applicant presented a detailed description of the PPS (OH – No. 73

Detail of the Dart Underground Property Protection scheme). The evidence is

comprehensive and helped to clarify many question raised during the Oral Hearing. The

Applicant confirmed the following key issues regarding the PPS:

1. The PPP Contractor or Design and Build Contractor will be required by its contract to implement the Property Protection Scheme.

2. Upon appointment, the PPP Company will undertake a detailed assessment of ground

47

movement/building settlement and vibration.

3. Nothing in the Property Protection Scheme detracts from, or dilutes, the legal rights of owners to claim for building damages against the DART Underground PPP Company.

4. The PPP Company must have insurance for their legal liabilities for building damage in excess of €30,000.

5. All building damage attributable to DART Underground works will be addressed, regardless of costs.

6. Building damage relates to direct damage to the structure of the building as a result of potential ground movement/settlement and from vibration and also damage to buildings as a result of damage to private utility spurs from local authority services.

7. The Property Protection Scheme will remain valid for:

12 months following completion of construction works; or, in the unlikely event that settlement has not stabilised within this period,

such longer time as is required to demonstrate that settlement has stabilised.

8. CIE/Iarnród Éireann will establish a panel of independent chartered building surveying companies or consulting civil/structural engineering firms. The pre-approval and formation of this panel will ensure a consistency in approach when conducting surveys under the Property Protection Scheme.

9. The Independent Expert will be selected from Engineers Ireland Panel of Conciliators. The decision of the Independent Expert is binding on the PPP Company.

10. The preliminary condition survey report will be issued to the property owner, the PPP Company, and CIE/Iarnród Éireann upon completion.

11. During the construction works, property owners may request an interim survey, should their building develop signs of deterioration.

12. As required and appropriate, based on heritage value or building sensitivities, a conservation architect will provide supplemental advice and input to the condition surveys.

13. Prior to commencement of construction and for the duration of construction, monitoring of Ground Movement/Building Settlement and Vibration will be conducted by the PPP Company. All monitoring will be reviewed, audited and validated by an Independent Environmental and Archaeological Monitor and a team of engineers/scientist employed directly by CIE/Iarnród Éireann.

14. The findings of any issues arising from interim condition surveys will feed into the monitoring data review process. This will provide an interaction between findings of the building condition surveys and the construction monitoring as DART Underground construction is proceeding.

15. The property owner may refer the matter to an Independent Expert, in the event that:

i. the findings of the surveyor are disputed; or

ii. the PPP Company's opinion is disputed in relation to cause of damage; or

iii. the PPP Company's opinion is disputed in relation to the valuation of rectification works; or

iv. the property owner disputes the fact that the damage has been rectified.

16. If the PPP Company fails to rectify damage attributed to DART Underground works, CIE/Iarnród Éireann has the right to intervene and have any matter arising addressed.

6.3 Comments and Recommendation – Property Protection Scheme

The EIS and the evidence given by the Applicant - in response to extensive questioning by

Observers and ABP Experts – have clarified the objectives, scope and limitation of the

PPS. The proposed PPS is an important step of taking into account the concerns of

48

property owners which potentially could be affected by construction of the DART

Underground. Therefore, the above evidence provided by the Applicant shall be made a

condition of the Railway Order.

Property Protection Scheme

1. The structure and content of the Property Protection Scheme shall be as indicated in ‘Property Protection Scheme – DART Underground Oral Hearing’ submitted by the applicant to the Oral Hearing on the 19th day of January 2011. The applicant shall retain overall responsibility for the implementation and operation of the Property Protection Scheme throughout the lifetime of the DART Underground (construction and operation).

2. The limit of € 30,000 stated in the EIS shall correspond to construction cost excluding VAT and, and shall be adjusted annually and shall be adjusted annually to reflect cost of working in the construction industry.

49

7 Construction Aspects This section addresses the construction methods and processes proposed for the DART

Underground Scheme.

7.1 Construction Strategy

A variety of construction activities will occur simultaneously at a number of different

locations along the DART Underground route. Shallow structures founded in the softer

ground will be open cut, with structures formed using diaphragm wall or secant pile

techniques. Since these structures lie outside the city centre and are extensive in nature,

they will be constructed “bottom up” and using bulk excavation. Central stations and shafts

will be founded deeper in the underlying rock. These must be mined. The initial openings

near the surface will be supported using secant piled walls. Thereafter, excavation will

proceed level by level in what is known as “top down” construction. The walls will be

supported by anchors or props. Rock is most likely to be broken in place using drill and

blast technology.

The core structures of the horizontal element of the project are the running tunnels. These

will traverse both hard and soft ground. Due to their length and uniformity, the tunnels will

be bored and lined using tunnel boring machines (TMBs). As a result of the mixed ground

conditions and the need to minimise settlement, Earth Pressure Balance Machines (EPMs)

have been selected as the most appropriate technology.

The running tunnels are to be constructed from the East Portal using two machines, one for

each bore. This method has been assessed as having least impact on the environment.

Cross-passages will be constructed using soil and rock excavation methods.

7.1.1 Programme of Works and Phasing

During the first 3 months of the DART Underground project main construction works have

been set aside for establishment of an initial design for the final works and the final design

procedures and acquisition of detailed local consents across the route. Exceptions to this

are the continuity of operations at Christchurch, following completion of the archaeology

excavation and the early start to construction at the East Portal and Docklands Station. This

is required to ensure that the structures are sufficiently advanced to accept passage of the

TBMs.

The next ten months of construction will see this pattern extend across much of the project,

with a phased start-up of piling and excavation at Pearse, St Stephen’s Green,

Christchurch, Island Street and Heuston. Site Preparation works will also start at the TBM

reception chambers in the CIE lands at Inchicore. The West Road bridge realignment will

be underway during this period.

Following launch of the first TBM, the second will start around 2 months later. By this

time too, excavation will be underway at Pearse, St Stephen’s Green, Christchurch and the

east shaft for Heuston. The TBMs will drive for around 22 months, which will also be the

most intense period of the project for excavation, with activity at locations along the route,

although at Inchicore station this will primarily be installation of piled retaining walls.

The fourth year of the project will see completion of all station and shaft excavation and

activity will become concentrated underground with the start of the platform enlargements,

serviced through the now completed running tunnels.

50

Thereafter, construction will concentrate on fitting out the new railway, the stations and

shafts, work which will be similar to that associated with any other urban development.

This construction will be completed in a further 22 months, following which there will be a

period of 8 months for System Testing, Commissioning and Trial Running, prior to

opening of the new railway for public service.

The estimated duration of construction activities can be summarised as follows:

Duration Activities

12 months Railway Reconfiguration. Archaeology at Christchurch.

3 months Immediate start of Piling at East Portal and Docklands. Design and

approvals.

10 months Piling and initial excavation at all sites except West Portal. West Road

Bridge.

22 months Driving TBMs. Excavation at all sites. Piling at West Portal.

12 months Platform Enlargements and station passageways. Station Excavation at

Inchicore.

22 months Track laying and railway systems. Station Builders Work and fit out; OCC

& Maintenance.

8 months System Testing, Commissioning and Trial Running.

7.1.2 Construction Risks and Maximum Working Area

Construction activities which could have negative environmental impact have been

assessed in terms of a combination of likelihood, duration, magnitude and intensity.

Fundamental to the process of assessment, evaluation and the overall management of risk

or impact, employed during the project development stage, has been the concept of a

hierarchy of mitigation with the objective of minimising residual impacts and risks to a

negligible or acceptable level.

The concepts utilised to identify environmental risk of construction are generally those

outlined in ‘A Code of Practice for Risk Management of Tunnel Works’ prepared by the

International Tunnelling Insurance Group (2006).

At the core of the process described in the ‘Code’ are the actions of “identifying hazards

and evaluating their consequence and probability of occurrence together with strategies as

appropriate for preventative and contingent actions.”

The EIS was unclear about the required maximum working area/space for the DART

Underground Scheme. In evidence given by the Applicant (OH-No. 12; G. O’Donnell:

Description of Railway Order drawings) the following clarification was given:

The proposed land acquisition includes all lands required for the purposes of the Railway Order. The extent of lands referenced accommodates the maximum working area as defined in Article 6 of the Draft Railway Order (Maximum Working Area) and included as Note 5 on each of the Property Details drawings. This definition is quoted here for clarity:

"In constructing, maintaining and improving any of the Railway Works authorised by this Order, the Railway Undertaking may make modifications to allow for innovations in construction methods or technology but such that the extent of lands referenced to accommodate this Scheme, and any such modifications, has been limited to:"

i. 10 metres horizontally from the central lines of running tunnels;

51

ii. 5 metres vertically upwards, and no limit vertically downwards, from the outside edge of running tunnels;

iii. 15 metres horizontally and 15 metres vertically upwards from the central lines of cross passage tunnels;

iv. metres horizontally and 10 metres vertically upwards from the outside edge of platform tunnels;

v. 20 metres horizontally from the outside edge of underground station boxes and shafts."

Therefore, the scheme shown on the Alignment and Structures Details drawings is enveloped by a wider maximum working area, and it is this wider area that is then shown on the Property Details drawings.

7.1.3 Comments on Construction Strategy

The following comments are made regarding the construction strategy envisaged for the DART Underground.

The proposed construction methods are well-established and extensive practical experience exists in Dublin from similar projects (wall construction, excavation etc.). Top down and bottom up construction of shafts and stations are widely used in the Dublin area and suitable for the DART Underground Scheme. The top down method is more environmentally friendly as excavation can be carried out below ground after the surface cover has been constructed.

The construction strategy proposed by the Applicant is based on working from one tunnel portal at East Wall, constructing the running tunnels by two TBMs. The proposed site is located within the CIÉ North Wall Depot and suitable for construction of the launch pit from a geotechnical and site-specific viewpoint, compared to alternative sites.

Boring of tunnels using only two TBMs may take longer than using four TBMs but the overall construction process will be simplified (one launch pit, linear progress of tunnelling work, gain of experience from tunnel boring in limestone and glacial till). Spoil from TBM excavation can be transported by conveyor belts in the tunnels below the city with little environmental impact to the Eastern Portal from where it can be transported by rail or truck.

From a geotechnical and hydrogeological viewpoint, this strategy has advantages with respect to environmental impact, compared to four TBMs (requiring two portals and two reception pits in the city centre). Only one launch pit for the two TBMs will be required (Eastern Portal).

A submission was made during the Oral Hearing (OH-No. 95 Dargan Project), promoting a mono-tunnel solution, using one but significantly larger TBM. However, this alternative was not evaluated by the Observer with respect to environmental impacts and is not considered a realistic alternative to the prosed scheme.

Construction of running tunnels will be carried out at a relatively large depth (20 to 25m) mainly in limestone and stiff, glacial till. This material is suitable for the proposed tunnelling methods.

All sub-surface construction work shall be carried out according to procedures stated in the Eurocodes, Execution of Special Geotechnical Works. For each construction activity with potential environmental impact, method statements shall be prepared and reviewed and improved by the Applicants engineering team and/or the E&AM.

The Applicant confirmed that alignment of the tunnels and shafts/stations are fixed with exception of construction tolerance (approximately 100mm for TBM construction).

The scheme shown on the Alignment and Structures Details drawings was enveloped by a wider maximum working area, and it is this wider area that is then shown on the Property Details drawings.

52

7.2 Main Construction Methods

Volume 2, Chapter 5 of the EIS describes the construction strategy. Evidence on

construction methods and their implementation was given during the Oral Hearing (OH-

No. 18; K. McManus: Construction Strategy, Scheduling & Programming). The following

sections discuss the main construction methods to be used for the DART Underground

Scheme.

7.2.1 Cut and Cover Sub-surface Works

Cut and cover construction of sub-surface structures starts with the installation of vertical

walls from the ground surface. Walls are constructed of reinforced concrete. Thereafter,

soil is excavated while the retaining walls are supported by anchors or struts/props. The

walls form permanent part of shafts and stations. Ground support can be either temporary

or permanent. Two basic forms of cut-and-cover construction are available: bottom up

method and top down method.

7.2.2 Wall Construction

Two methods have been selected by the Applicant for construction of walls: diaphragm

wall and secant pile method, respectively. As these two methods are well-known and have

been described in the EIS and presented during the Oral Hearing they are only summarised

briefly (OH-No. 18).

Diaphragm Walls The characteristics of diaphragm wall construction can be summarised as follows:

Advantages: flexible and more powerful excavation techniques; extensive monitoring

during construction; reduced water ingress compared to piles (larger panels and fewer

vertical joints); accurate construction at depth.

Impact: Large site required; bentonite plant essential.

Mitigation: Minimise use.

Residual Impact: Bentonite disposal.

Secant Pile Walls The characteristics of secant pile wall construction can be summarised as follows:

Advantages: Flexible construction method; seals groundwater but larger number of vertical

joints; no treatment plant; used on small sites.

Impact: water-tightness can be problematic; plant generated noise; spoil removal &

deliveries.

Mitigation: work within hoarding; site management.

Residual Impact: as normal basement site.

Comments

The Applicant has prescribed specific wall construction methods for each site (secant pile and diaphragm wall method, respectively). Both methods are suitable for the geotechnical conditions and well-established in Dublin, each having advantages and limitations. Their primary purpose is lateral ground support and water-tightness. The walls are constructed prior to the commencement of bulk excavation.

53

When installed into limestone, it is important that wall elements (piles or panels) penetrate sufficiently deep into the rock in order to assure water-tightness and structural stability during excavation, also considering dynamic loads due to rock excavation (blasting). Particular attention should be paid to quality control (overlap and verticality) during installation of secant piles as these have a significantly larger number of joints than diaphragm walls.

Wall construction shall be executed by a specialist foundation contractor with documented experience from work in similar ground conditions. Construction equipment must be suitable for site conditions and sufficiently powerful, being able to penetrate through stiff boulder clay (in order to avoid soil decompression).

The following Eurocodes, Execution of Special Geotechnical Works shall apply:

- EN 1536: Bored Piles (Feb 1999)

- EN 1538: Diaphragm Walls (Jan 2000).

Movement of excavation and construction equipment on site as well as soil and rock excavation can have negative environmental impact, especially when operating in close vicinity of sensitive receptors. Vibration and groundborne noise can be generated when the excavation tool encounters stiff soil formations, boulders or rock.

7.2.3 Soil Excavation

Stations and shafts will be constructed in made ground (fill), Alluvial deposits and boulder

clay. Retaining structures are required to ensure that excavations remain stable. The two

principal methods for deep excavation are known as ‘Bottom up’ and ‘Top down’.

Bottom up Construction The bottom up construction technique comprises the following phases:

Excavation & installation of struts

Construction of base slab

Construction of underground structure

Backfilling and reinstatement.

The ground is excavated between these retaining walls with temporary propping or

anchoring as required. Once the excavation has reached the required depth a reinforced

concrete base slab will be cast, followed by the roof slab. The ground above the roof slab

will then be backfilled and the surface re-instated.

Top down Construction The top down construction technique comprises the following phases:

Excavation & construction of roof slab

Sequential excavation and construction of slabs

Construction of underground structure

Backfilling and reinstatement.

The method most suitable in urbanised areas is top down construction. Rigid retaining

elements walls are installed in the form of secant piles or diaphragm wall panels. A roof

slab is constructed which also provides lateral support. Excavation continues beneath the

roof slab until the next level of structural support is reached where anchors can be

installed. The excavation process progresses downwards until the bottom of the excavation

where the base slab is constructed.

54

Comments

Both construction methods are suitable in the prevailing ground conditions. However, the top down construction method has less environmental impact as bulk excavation can be carried out below the surface slab. Thus, top down construction i more suitable for shafts and stations in urbanized areas.

7.2.4 Ground Anchors

The EIS and evidence given during the Oral Hearing provides only limited information

regarding ground support. Ground anchors are installed to tie back retaining wall elements.

Different types of ground anchors can be used, depending on the geotechnical and site-

specific requirements. Ground anchors can be installed as temporary (retractable) or

permanent construction elements.

The use of anchors enables these walls to be higher and deflect less than walls without

anchors, (i.e. cantilever walls). An anchor is installed using drilling and grouting

procedures consistent with the anchor type and prevailing soil conditions. Each anchor is

tested following its installation.

The Contractor is usually responsible for determining the length/depth of wall elements

and required section necessary to resist loadings due to earth and water forces while

controlling ground movements.

Comments

Only general information is given in the EIS with regard anchor type, installation method and life length (temporary vs. permanent).

Installation of anchors can affect adjacent structures and their foundations. The length of ground and rock anchors and bolts is not yet known. Therefore, the working area has been by rule of thumb and increased to take this uncertainty into consideration.

Ground support measures can have impact on lateral ground movements adjacent to deep excavations and in tunnels. Monitoring is an essential element of ground support, as described in the Observational Method of Eurocode 7. The following Eurocode, Execution of Special Geotechnical Works shall apply:

- EN 1537: Ground Anchors (1999).

7.2.5 Ground Treatment

Only a brief section in the EIS, Chapter 5.9.3. (Ground improvement and dewatering)

addresses ground treatment methods. During the Oral Hearing additional evidence was

given on mitigation measures (including ground treatment) to reduce settlement (OH-No.

22; S. Fricker: Settlement and OH-No. 22A; S. Fricker: Settlement of Permanent

Structures and Utilities – Associated PowerPoint presentation).

During discussion with the Applicant it was stated that a decision regarding the need, type

and extent of ground treatment and underpinning methods will be made as part of the

Detailed Design of the project.

Ground treatment methods and underpinning may be required at several locations along the

DART Underground Scheme. However, this important design aspect, which can impact on

adjacent structures and their foundations, was not assessed extensively. The following

ground treatment methods could be envisaged:

55

Compensation Grouting: grout is injected into the ground to counter the movements

caused by tunnelling. In this slide the central grey zone represents the pressurised “bulb” of

grout that effectively pushes the ground above it upwards.

Structural jacking: an intrusive means of mitigation where hydraulic jacks are installed

under a structure’s foundations to “jack” the structure up in response to ground

movements.

Curtain walls: diaphragm walls or bored piles are installed between the location of the

planned tunnel and the structure. The sub-surface “walls” effectively reduce the amount of

settlement that extends towards the surface and the structure.

Deep underpinning: a technique similar to conventional underpinning in that the

buildings foundations are replaced. However for settlement mitigation the technique uses

deep piles to extend the new foundations below the zone of influence of the tunnels.

Structural strengthening: comprises a number of techniques that make the building or

structure more able to resist ground movements caused by tunnelling including structural

ties, propping and internal bracing.

Comments

The EIS lists mitigation methods to reduce ground movements. Ground improvement methods were described during the Oral Hearing and possible ground treatment solutions were shown for different sites. However, in contrast to the tight specification given for wall and tunnel construction, the Contractor is given the choice to choose among a wide variety of ground treatment methods.

Detailed Design may indicate that ground treatment is required to protect or support structure adjacent to the DART Underground, on or below the ground surface. This lack of detail in the EIS introduces uncertainty in the environmental risk assessment process. However, the Applicant stated repeatedly that the required land will be sufficient to carry out ground treatment, if so required.

7.2.6 Groundwater and Dewatering

The Contractor will, either by means of additional site investigation or local probing, study

likely groundwater inflows that may be expected. If the levels of inflow are greater than

the installed pumping capacity, or those levels which are acceptable to third parties with

authority over its disposal, the Contractor will undertake measures to reduce the overall

water inflow. Such measures include high-pressure grouting or installation of cut-off walls

and/or curtains by which it is possible to control and reduce groundwater flow.

It is important that wall panels and secant piles are installed sufficiently deep into the

bedrock to avoid excessive water flow into excavations.

The Contractor will be obliged to develop a detailed Water Monitoring Plan and also to

compile a Groundwater Action Plan which will state what actions he will take if

monitoring shows that the groundwater levels are moving outside their expected range.

Actions could include halting dewatering operations or recharge (where feasible) etc. as

well as the installation of granular trenches around structures or French drains if the

structure is acting as a barrier to flow and groundwater levels are mounding.

Comments

Dewatering is envisaged in certain areas with high groundwater level and soft soil layers. Dewatering must be monitored carefully in order to avoid excessive water flow (internal erosion)

56

in permeable soil layers (silt). Even temporary lowering of groundwater level can cause settlements in compressible, Alluvial soil deposits (especially soft clay and organic material).

7.2.7 Running Tunnel Construction

The nature of tunnel excavation and construction is a repetitive cyclic process. A single

cycle consists of ground being removed under controlled conditions for a short distance

before structural support is installed to the newly formed opening. Once this is complete

the process can be continued with another cycle. Opening up any excavation results in a

small but inevitable movement of the surrounding ground. When tunnelling under urban

areas it is a requirement that these ground movements are minimised in order to avoid any

significant movement on the surface and damage to buildings or installations. It has been

established, over many years and projects, that the more efficiently and consistently the

tunnel process advances, the better is the control of ground movement.

Tunnel Boring Tunnel Boring Machines (TBMs) can be used to excavate tunnels with a circular cross

section in a broad range of geological materials from hard rock to very soft soils. The

proposed TBMs have approximately 7 meters diameter (running tunnel diameter 6m).

TBMs are suitable for use in heavily urbanized areas where settlement must be kept to a

minimum. The alternative of using one larger TBM instead of the proposed two machines

was evaluated by the Applicant. However, the environmental impact from constructing a

single tunnel with larger diameter would have several negative consequences, such as

higher groundborne noise and vibrations due to higher required boring energy and

considerably larger total and differential ground movements. A site suitable for the launch

of the running tunnels using TBMs has been identified at the former CIÉ North Wall

Depot.

The TBM can install water-tight concrete elements to assure that leakage to the tunnel is

kept to a minimum during construction. Thereafter, the completed tunnel will be water-

tight.

Earth Pressure Balance (EPB) tunnel boring machines have been selected for driving the

running tunnels. EPBMs have the potential of minimising ground movement and

settlement. In poor ground it is important to minimise over-excavation or face loss which

leads to ground movement and in turn can result in damage to buildings and structures.

Increasing face support is achieved by the introduction of positive face control to maintain

soil pressure.

Cross Passages Construction Cross passages connecting the two running tunnels are required at spacings of 250m. These

will be constructed by sequential excavation techniques behind the TBMs, once the

machines have advanced sufficiently to allow both a safe working zone and the probing of

the cross tunnel location to prove the ground on the line of the passage. The sites of the

cross passages will be serviced by dual track sections of the construction railway installed

for the TBM.

Platform Tunnel Enlargement The DART Underground station platforms are considerably wider than the running

tunnels. In stations constructed top down, these platform structures will have to be

enlarged from running tunnel size on completion of running tunnel excavation. This

activity will occur simultaneously at all the platform tunnel locations and will be serviced

from the portal work sites using a series of works trains.

57

Comments

Under the prevailing geological conditions, construction of running tunnels using earth pressure balanced TBMs is an environmentally friendly and safe solution compared to other alternatives. Use of two smaller TBMs is preferable compared to one larger TBM as this alternative has lower environmental impact. A smaller tunnel causes lower groundborne noise during boring and results in reduced settlement at the ground surface, compared to one larger tunnel.

Construction of tunnels by TBMs below densely populate areas should be carried out by a contractor with documented experience from work in similar geological conditions. The design of the bored tunnels requires careful review of the anticipated geology, geotechnical conditions and groundwater regime. This is particularly important when tunnelling beneath sensitive areas such as:

• Major road and rail infrastructure and protected structures;

• The River Liffey and known buried river channels to minimise construction risk;

• Major services (particularly sewers) to minimise settlement and construction risk.

7.2.8 Rock Excavation

In addition to the construction of the running tunnels, also stations, shafts and cross

passages need to be excavated in rock. Different types of rock excavation methods can be

envisaged, such as:

Mechanical breaking and percussive breaking.

Predrilling, rock splitting and induced fracturing.

Energetic materials (propellants).

Blasting using explosives.

Percussive rock breaking is widely used but its efficiency is limited to small areas and

fractured material. The same limitations apply to rock splitting and induced fracturing.

Energetic methods cause relatively low levels of vibration but are slow and thus relatively

expensive.

For excavation of shafts and stations, mainly drill and blast techniques will be used to

break the rock over suitable lengths in the order of 1 to 1.5 m advance per blast. Holes are

first drilled into the rock and then charged with explosives and primed with detonators. By

reducing the length of the borehole/blast the amount of explosive per blast is reduced.

Delayed ignition is used to reduce the combined impact from a series of boreholes.

Rock excavation by the drill and blast method can potentially have detrimental

environmental impact. The amount of explosive to be used depends on several factors

including the depth/length of excavation required per blast, the in-situ strength of the rock,

the structural pattern of the rock mass and environmental constraints at the surface. When

the explosive contained in the borehole is detonated, high pressure gases are formed

expanding in the drill holes and fracturing and shattering the rock. Following the blast the

tunnel or excavation will be ventilated to remove gases produced by the explosives. The

broken rock can then be excavated and removed from the tunnel or work place using

mechanical excavators and dump trucks.

Temporary support in the form of sprayed concrete, and rock bolts will be applied. The

length of rock bolts is typically 2 to 4m. The excavation and support cycle will be repeated

until the excavation is complete.

58

Comments

The most efficient method of excavating larger quantities of rock is by blasting. Many tunnels similar to the DART Underground Scheme have - and are being - constructed by rock blasting. If planned, tested, carried out and monitored by experience personnel, rock blasting is a safe rock excavation method even in vibration-sensitive, urbanized areas.

A method not mentioned in the EIS is rock sawing, which is vibration-free and achieves accurate excavation profiles. However, rock sawing is relatively expensive and limited to excavations in highly vibration-sensitive areas.

7.3 Comments and Recommendation – Construction Aspects

The proposed methods for construction of tunnels and deep excavations for the DART

Underground have been used successfully in similar geological settings and geotechnical

conditions elsewhere. However, it is important that the contractor has documented and

verifiable experience from the use of such methods under similar geotechnical conditions.

1. The construction strategy proposed by the Applicant is based on one tunnel portal at East Wall (Eastern Portal), constructing the running tunnels by two TBMs with EPB shields. From a geotechnical and hydrogeological viewpoint, this strategy has advantages with respect to environmental impact, compared to four TBMs (requiring two portals and two reception pits in the city centre). These are:

Only one launch pit for the two TBMs will be required. The proposed site is located within the CIÉ North Wall Depot and suitable for construction of the launch pit from a geotechnical and site-specific viewpoint, compared to alternative sites.

Tunnel boring using only two TBMs may take longer than using four TBMs but the overall construction process will be simplified.

An added benefit for the contractor of using two TBMs is the extended learning process and experience which will result in adaptation of a safe and efficient construction process.

Spoil from TBM excavation can be transported by conveyor belts in the tunnels below the city to the Eastern Portal where it can be transported by rail or truck.

2. Tunnel boring can be complicated when unexpected ground conditions and mixed face boring are encountered. Mixed face tunnelling requires extra care in measuring operational parameters. Therefore, the contractor shall have demonstrated experience from TBM work in similar ground conditions (mixed face, boulder clay).

3. The proposed construction methods are well-established and extensive practical experience exists in Dublin from similar projects (wall construction, excavation etc.). Construction of running tunnels will be carried out at relatively large depth (20 to 25m) mainly in limestone and stiff, glacial till. This material is suitable for the proposed tunnelling process. For wall construction of Docklands station the secant pile wall method was selected in the EIS. An inspection of existing basement walls in the Docklands area indicates potential problems with water-tightness. The diaphragm wall method has advantages with respect to water-tightness. Therefore, when additional geotechnical information becomes available, the Contractor shall reconsider the optimal wall construction method considering the stringent requirements of water-tightness.

4. A review of the EIS and evidence obtained during the Oral Hearing suggests that soil properties and rockhead level can vary more than anticipated. This aspect needs to be taken into account when selecting construction and tunnelling methods. The problem of

59

potentially loose, water-saturated soils was identified. Variable ground conditions are not limited to layers of loose sand and gravel but are also important for problems associated with tunnelling across the rock-soil interface. In some locations this is gives rise to a potentially problematic situation for TBM operation. Tunnelling protective measures are often cost-effective in order to reduce excessive ground loss. Therefore, it is recommended that extensive field monitoring procedures are applied during the initial phase of tunnelling work in critical areas to gain experience.

5. The scheme shown on the Alignment and Structures Details drawings is enveloped by a wider maximum working area, and it is this wider area that is indicated on the Property Details drawings. However, as Detailed Design has not yet been carried out, there is some uncertainty as to the actually required land-take (vertical and horizontal), for instance with regard to extended ground treatment and underpinning work.

6. All sub-surface construction work must be planned, carried out and monitored according to procedures stated in Eurocodes “Execution of Special Geotechnical Works”.

60

8 Soils and Geology

8.1 General

A description of soils and geology along the DART Underground alignment is given in

Chapter 13 of the EIS. A summary of this information was also presented as evidence

during the Oral Hearing (OH-No. 21 and 20A; S. Mason: Geotechnics, Soils and Geology).

Geotechnical properties and their impact on the design and construction of the DART

Underground are addressed in Chapter 10 of this report.

8.2 Description of Project Area

The city of Dublin is situated on a low lying coastal plain and former flood plain of the

river Liffey, which is bounded to the south by high granite cored hills up to 540 metres

above Ordnance Datum (AOD) and to the north-west by lower limestone cored hills of up

to 230m in height. To the west the elevation of the land increases gradually merging into

the central plain of Ireland, while to the east ground surface levels generally decrease

towards Dublin Bay and the Irish Sea.

8.2.1 Geological Conditions

The majority of the Greater Dublin area is contained within the Dublin Basin underlain by

an argillaceous limestone, known as Calp limestone. The limestone was deposited in a

shallow marine environment. Cyclical changes in the water depth and depositional

conditions led to marked changes in the rock properties and thickness, variations in the

sand and clay content, and the inclusion of shale and mudstone layers, occasionally

weathered to clay.

Weathering and erosion during the tertiary period as well as during glaciations formed an

irregular surface of the bedrock. Sea level variations and/or tectonic activities gave rise to

drainage channels cut into the bedrock. Due to the thick cover of glacial till overlying the

bedrock and the consequential lack of bedrock exposures, very little information is

available on faulting within the bedrock.

The bedrock topography is dominated by a major buried channel, the pre-glacial Liffey,

downstream of Islandbridge. There it turns south of the present river Liffey course to the

west of Heuston Station at Islandbridge, before turning northwards under Diageo at depths

of 20 to 25m bgl and on towards Broadstone. Data from the ground investigation gathered

as part of this study show agreement with this interpretation.

The rockhead elevation along the DART Underground is based upon the existing borehole

information and geophysical testing. Rockhead elevations have been presented in the

geological profiles of the EIS. It should be noted that the available information is

somewhat ambiguous and it is not certain that maximum depth has been correctly

identified at all locations along the alignment.

The course of the existing Liffey, which was formed during late and postglacial times,

extends eastwards towards Dublin Bay. The pre-glacial channel has effectively been filled

with sediments related to both marine and transgressional periods. Conditions during the

period immediately before the ice age led to erosion and alteration of the rocks at rockhead

level which led to the formation of buried rock channels and the removal of calcium

from argillaceous layers, reverting them back to clay. There are almost no records of

61

solution features in the Dublin limestone. Bedding planes generally dip at 5º to 30º, with

typical layer thicknesses of 300mm to 500mm.

The Docklands on the north and south bank of the Liffey land was undeveloped prior to

1700, consisting of low-lying wastelands. The area was gradually drained or reclaimed.

Reclamation began in the 18th

century. Materials used for reclamation included

construction and demolition waste, waste topsoil and municipal, industrial and medical

waste.

8.2.2 Engineering Properties of Rock

River Crossings Excavations in limestone bedrock can be potentially difficult. The permeability of the Calp

limestone may be higher beneath river crossings, including the Liffey and culverted rivers.

The presence of greater weathering beneath the river and the river being coincident with

poorer ground or a fracture zone can pose problems during tunnelling work.

Shale Horizons Shale beds and partings can be encountered within the limestone which is likely to form a

plane of weakness within open excavations. Shale has a low friction angle and is hence

weaker in shear and possesses lower tensile strength. The shale beds are often weathered to

clay. Shale horizons within the limestone may cause bed separation on excavation. Shale

with vertical discontinuities can cause crown instability or significant overbreak in the

shoulders.

Shale weathering could have a particularly detrimental effect on tunnelling if more

extensive than initially envisaged.

Unfavourable Discontinuity Orientation Limestone is faulted and discontinuities (both bedding and joints) are frequently occurring

within the rock structure. Typical modes of failure include slabbing where beds are

horizontal/sub-horizontal, and sliding on shale partings. Block and wedge failure may

occur into excavations or tunnels under gravity. Presence and orientation of faults and

discontinuities need to be considered for the design of temporary and permanent support.

Faults, Fracture Zones and Solution Features Locally, increased permeability may be exhibited where major discontinuities are present,

such as in fault zones.

Highly Weathered Limestone at Rockhead Level Within a depth of one to five metres of the rockhead level the limestone must be expected

to be highly weathered and as a result may be highly variable, exhibiting: close-spaced

fractures, reduced strength and degradation to soil. Such materials are likely to have a

higher permeability and be prone to instability.

Difficulty may be experienced with toe-in of diaphragm walls and piles because of

irregular, weathered limestone.

Extremely Strong Rock Calp limestone can exhibit varying strength and abrasivity which must be considered in

respect to the cutting head design and/or selection of mechanical excavators. Extremely

strong silicified material can be present within the limestone sequence, albeit in small

lenses. The strength of unweathered limestone can be as high as 300 MPa. Siliceous layers

and pockets are noted to be present in places and these may exhibit even higher strength.

62

This aspect needs to be taken into consideration when selecting appropriate construction

and excavation equipment and tools. Also, strong rock formations can impact on

equipment wear and require higher maintenance, resulting in reduced productivity.

In-filled Karstic Features Even minor karstic features are uncommon in Calp limestone. However, such features may

exist, in-filled with soft materials, and can exhibit significant water inflow based upon the

prevailing piezometric level within the limestone. Such features could cause significant

stability problems if encountered.

Variable Rockhead Level Rockhead is an eroded surface which has been cut into during interglacial periods. In

particular steep sided in-filled valleys are likely within the rockhead profile. The rockhead

level is therefore potentially highly variable and its prediction based on borings may not be

entirely reliable. The variability of rockhead level will need to be studied in more detail

during design and execution of excavations and in particular during tunnelling work (TBM

and mined tunnels).

In-filled Limestone Mines or Quarries Calp limestone was mined historically. Records exist of an in-filled former limestone

quarry close to the route alignment at Merrion Square. There is further potential for

undocumented and filled former pits within the clay, giving rise to unexpected ground

conditions.

8.2.3 Seismicity

The seismicity of the Dublin area is low. Ireland, as part of north-west Europe, is contained

within the Eurasian plate in an intra-plate location. Consequently the high levels of

seismicity associated with plate boundaries are not experienced here. The largest recorded

earthquake in the Irish Sea area occurred on 19 July 1984 and measured 5.4 on the Richter

scale; it had its epicentre on the Lleyn Peninsula in Wales. Although relatively large, the

focus of the earthquake was quite deep, about 20 km, and thus structural damage was

minor, and it was only weakly felt in Ireland. Two other recent earthquakes have occurred

in the same area, in 1994 (magnitude 2.9) and 1999 (magnitude 3.2).

8.2.4 Geotechnical Aspects

During the Pleistocene epoch of the Quaternary (the most recent geological time period)

two glaciations covered the Dublin region. The glaciation, which gave rise to the Dublin

boulder clay, was presumably not continuous. Local withdrawal and re-advance of the ice

sheet led to the formation of fluvioglacial sediments (gravel and sand lenses) and

glaciomarine sediments (stiff/firm laminated clays, silts, and sands). The glacial deposits

can exhibit significant lateral and vertical variations in grain size distributions over short

distances.

Upon cessation of the glaciation, rising sea levels, related to the changing climatic

conditions, led to the deposition of raised beach deposits and terrace gravel sediments

around the Liffey estuary. Recent Alluvial sediments were deposited along the rivers and

into the river estuaries. Young estuarine sediments were formed along the old shoreline in

the vicinity of and within the Liffey river estuary.

In more recent times large parts of tidal areas along the natural shoreline and along the

Liffey were reclaimed by man. Waste materials of differing kinds including

construction/demolition wastes were deposited in these areas.

63

8.2.5 Radon

Radon is a radioactive gas which is naturally produced in the ground from the uranium

present in small quantities in all rocks and soils. The Radiological Protection Institute of

Ireland (RPII) has produced a Radon Map of Ireland based on the results of the RPII’s

National Radon Survey where radon measurements were carried out in a number of houses

in each 10km grid square of the National Grid.

The 10km grid of the Greater Dublin area indicates that only 1-5% of the homes surveyed

in this area had radon concentrations above the Reference Level (200 Bq/m3). Grid squares

where this percentage is predicted to be 10% or higher are designated High Radon Areas.

The RPII has issued specific guidelines with respect to underground workplaces entitled

‘Radon in Underground Workplaces – Guidance notes for Employers’ (2007). The RPII

assessment does not consider exposure pathways that may be created as a result of the

tunnelling process which may lead to the mobilisation of Radon gas. In recognition of this

an occupational monitoring programme for radon gas will be implemented in accordance

with Section 13.5.1.

8.2.6 Contaminated Ground and Aggressive Soil and Groundwater

The proposed sites for the Heuston and Inchicore Stations and the Eastern Portal are within

existing CIÉ lands. These are railway and industrial sites where contamination of soil and

groundwater can be expected. Rating of soils with respect to contamination is presented in

the EIS, Table 13.12.

High levels of sulphates, chlorides and low pH (acidic) in the soil or groundwater can

cause deterioration of exposed concrete. Durability must be considered in order to

ascertain the appropriate class of concrete for use in construction.

Groundwater in both bedrock and superficial deposits along the coast of Dublin are known

to be brackish with dissolved solids and high chloride concentrations. This aspect may be

of importance for sections of the route alignment which passes beneath the Liffey.

Drawdown of groundwater associated with construction works may also result in intrusion

of saline waters.

Pyrite may be present within shale of the Calp limestone formation. When pyrite is

oxidised it breaks down to form sulphates which cause acidic ground conditions.

The area of the proposed alignment within the Docklands and East Wall area is considered

to be at high risk for contamination due to industrial activities in the past. Any

64

contamination may have significant effects upon workers involved with construction and

the immediate vicinity of the project. Additionally, the storage and disposal of

contaminated waste materials following excavation may pose problems.

8.3 Impact Assessment

8.3.1 General

The DART Underground will affect soil deposits and geological formation due to different

types of construction activities such as excavation, removal and transport of soil and rock

on and from the site, dewatering, ground treatment and other necessary construction work.

Contaminated soils and groundwater can become health hazard. The risk of contamination

can increase as a result of flooding.

Comment

In this chapter, only the potential environmental impact from the DART Underground project on soils and geology is addressed. However, the geological and geotechnical conditions along the project route can also have environmental impact in connection with the implementation of the project. For instance, construction of stations or tunnelling work, installation of anchors, ground treatment etc. can cause ground movements (settlement or heave, lateral displacements and affect the stability of existing structures, infrastructures and installations on or below the ground). These aspects will be addressed in Chapter 10 and 11 of this report.

8.3.2 Significance Rating

As no significance rating criteria are available in Ireland for assessing the impacts of the

proposed scheme on the ground (soil and rock), significance criteria from the National

Road Administration (NRA) document were used, cf. EIS Chapter 13, Table 13.3. While

the NRA document was developed for road schemes the potential soils and geological

impacts are similar to those that occur on road schemes; thus the use of this document

was deemed to be appropriate.

The rating of potential impacts has been assessed by classifying the importance of the

relevant attributes at key locations as follows:

portals and launch chambers (cut and cover sections),

tunnels (bored and mined sections) and

deep excavations (ventilation/intervention shafts/stations/substations).

65

The likely magnitude of any impact from the above features on the attributes was

then quantified. The rating of potential environmental impacts on the soils and geological

environment are based on the matrix presented in Table 13.3 which takes account of both

the importance of an attribute and the magnitude of the potential environmental impacts on

it. These impact ratings are also in accordance with impact assessment criteria provided in

the EPA publication ’Guidelines on the Information to be Contained in Environmental

Impact Statements’ (2002).

The construction impact will be monitored using environmental risk management

concepts. Comprehensive risk management is also aided by compliance with the Health

and Safety Authority (HSA) requirements for risk management of design and construction

works (for construction stage), and the appropriate standards and codes of practice for

site investigation works (including EN1997-2:2007 Annex B3 Ground Investigation

and Testing, and BS 5930 Code of Practice for Site Investigation Works).

All construction activities and works on site will be carried out according to best practice

guidelines, which are described in European and national standards as well as guidance

documents by professional organisations.

8.3.3 Construction Impact and General Mitigation Measures

In EIS, Chapter 13, construction phase impact and mitigation measures are assessed in

detail and summarised in Table 13.15. Impacts from construction of the DART

Underground and appropriate mitigation measures are discussed as follows.

General Construction

Fill will be used for construction of the Operational Control Centre, Maintenance facility

and ESB substation. Placement of fill will require the importation and deposition of fill or

reuse on site of fill material form within the site, leading to local changes in ground level

and topography.

An excess of soil and rock will result in the necessity for off-site disposal. Deposition of

fill may impact on properties of existing ground and affect groundwater flow.

Seepage may occur at slopes and excavations which can affect hydrogeological properties

of materials. In significant cuts this can lead to erosion and affect stability.

Mitigation Measures: in general, a minimum amount of soil and rock will be excavated.

Suitable surplus material will be used on site or other projects where possible.

Contaminated soils will be assessed, tested stored and managed according to the waste

hierarchy set out in the Landfill Directive (99/31/EC).

Seepage will be mitigated by employing a drainage system with suitable slope angles.

Excavation for diversion of utilities will be excavated using trenches minimizing the

amount of soil being generated.

Running Tunnels

Bored and mined soil and rock will be moved from tunnel to portals. During tunnel

construction there is potential of leakage or spillage of construction material such as raw

and uncured concrete, grout, fuel, lubricants and hydraulic fluids. Bitumen and sealants

used for water proofing of concrete surfaces can potentially impact on soils and

groundwater.

66

Mitigation Measures: excavated limestone must be shown to comply with regulations

regarding pyrites. Material shall be tested by the contractor to assure that material which

shall be used as structural backfill is suitable.

An occupational monitoring program for radon gas shall be implemented during

construction to avoid adverse impacts on humans.

A site investigation program has been carried out to inform contractor of appropriate TBM

and construction methodologies.

Portals and Launch Chambers, Deep Excavations

Cut and cover excavation of soil at both Inchicore and Docklands can encounter potentially

contaminated ground (hotspots).

Retaining structures will be installed in the ground in the form of secant pile walls and

diaphragm panel walls. Diaphragm walls are excavated using the slurry trench method

which requires bentonite suspension. Ground support will be required in the form of

ground anchors which need to be installed in the ground.

Ground treatment may be necessary in areas where excavation is carried out in the close

proximity of structures which are sensitive to settlement and/or lateral ground movement.

Also the placement of material on site, handling of potentially harmful liquids and other

chemical substances can have a negative environmental impact. Leakage and spillage of

materials and substances on site can potentially contaminate subsoil.

Construction of portals and launch chambers, of running tunnels and of deep excavations

can have impact on soils and rock on site.

Mitigation Measures: excavated soil and rock will be managed in accordance with the

waste hierarchy as set out in Chapter 21 of the EIS (Waste Management). Spoil removal

will require specialist disposal (cf. EIS Chapter 21; Waste Management). Excavation

techniques shall comply with statutory bodies regarding workers health and safety.

Temporary retaining wall systems shall be designed to mitigate risk of wall or slope

instability. Ground reinforcement systems such as rock bolts, ground anchors and sprayed

concrete lining shall be used in open excavations.

8.3.4 Operational Impact and General Mitigation Measures

The operational phase will have an overall neutral impact on soils and geology. However,

in case of leakage of the tunnel, stations or shafts, the groundwater level may be affected.

There is also a risk of soil and groundwater contamination from spillage of wastewater,

chemical material and hydrocarbons.

Mitigation Measures: if design measures are implemented and the DART Underground is

operated and maintained as outlined in the EIS, specific mitigation measures are not

required.

8.4 Comments and Recommendation – Soils and Geology

Chapter 13 of the EIS addresses one aspect environmental impacts, i.e. the effect of

construction and operation of the DART Underground on soils and rock. Impacts of soil

and rock conditions on the construction and associated risks are addressed only very

briefly in Chapter 13. The following recommendations are made:

67

1. The EIS provides a description of the general geological situation along the alignment. The information is sufficient for assessing environmental impacts of construction activities on soil and rock formations. However, impact of geotechnical and geological conditions on construction of the DART Underground is only addressed in the chapter on Settlement.

2. Information provided as evidence during the Oral Hearing indicates that soil and rock conditions can vary more rapidly over short distances than anticipated.

3. Presently available information on soil and rock is insufficient for Detailed Design and a significantly more detailed assessment of the geotechnical and geological conditions within the tunnel sections and at locations of deep excavations (shafts and stations) is needed.

4. Occurrence of faults, zones of weakness and weathering in rock needs to be determined more reliably, in particular in locations of deep excavations and mixed face tunnelling conditions. An important task is to establish the rockhead level and rockhead conditions along and perpendicular to the DART Underground alignment.

5. The extent of contaminated ground shall be determined by detailed investigations of all areas where excavations are proposed, these investigations shall be conducted prior to the commencement of excavation works as indicated by the applicant in ‘Brief of Evidence – Waste Management’ submitted to the Oral Hearing into the Railway Order application on the 17th day of December, 2010.

6. Potential obstructions and hazards including, inter alia, foundations, services, river walls and ordnances relating to the North Strand WWII bombing event shall be identified and addressed in the Detailed Design stage.

68

9 Hydrogeological Conditions

9.1 General

DART Underground involves the construction of two main types of permanent

underground structures below ground which can have an impact on the hydrogeology

along the project alignment, namely:

bored tunnels and mined tunnels (cross passages)

cut and cover structures (stations and shafts).

In addition, temporary and enabling works shall be carried out which could have negative

hydrogeological consequence. A potentially negative impact would be lowering of the

water table along the alignment generally or at the stations and shafts. This impact could be

either temporary or permanent in nature and would result from the abstraction of

significant quantities of groundwater from either the bored tunnels or the excavated

stations and shafts. However, the proposed construction methodology is aimed at

minimising the inflow of groundwater into the temporary excavations and the construction

of structures which are effectively water tight. This approach therefore reduces the amount

of dewatering required during construction, the need for significant permanent dewatering

and most importantly will minimise any negative hydrogeological impact.

9.2 Hydrogeology of Project Area

The topography and landscape is dominated by the presence of the Liffey which has

affected the most recent geomorphology of Dublin City and is a prevailing influence on

drainage along the proposed route. The Liffey is considered to be estuarine from

Islandbridge until it enters the Irish Sea via Dublin Bay. Along with the Liffey, there are a

number of surface water bodies along the proposed route including the river Camac and the

river Poddle. These water bodies are culverted in places, the Camac for instance is

culverted for much of its length including beneath Heuston Station to its outfall in to the

Liffey.

The hydrogeological regime and features of importance such as groundwater abstractions,

groundwater dependent ecosystems, archaeology and buildings are described in Chapter 14

of the EIS and were addressed in evidence presented at the Oral Hearing (OH-No. 28; K.

Cullen: Hydrogeology).

9.2.1 Groundwater

The EIS shows that there are two main sources of groundwater along the DART

Underground alignment:

shallow groundwater associated with fluvioglacial and Alluvial /estuarine granular

deposits; and

deeper groundwater associated with the Carboniferous Limestone bedrock.

The Dublin urban groundwater body is underlain by interbedded limestones and shales and

there are also some sandstones present. The bedrock aquifers tend to be dominated by

fissure or fracture flow with very little to no flow in the matrix. The limestone bedrock has

a low groundwater storage capacity in the order of 1 to 2 %.

69

The DART Underground lies in a regional groundwater discharge zone where the

groundwater bearing formations tend to discharge into either the surface waters, or where

this is not possible, into the Irish Sea. Groundwater flows in a general eastward direction

and contributes to the various rivers or discharges directly at the Irish Sea coast at Dublin

Bay. The direction of groundwater flow particularly in the overburden deposits is towards

the Liffey. There is a relatively shallow horizontal gradient in the water table

controlled essentially by the tidal channel of the Liffey with an upward vertical component

of flow reflecting the discharge zone.

9.2.2 Engineering Geology

No major bedrock fault structure is recognised as passing through the project area. The

limestone bedrock that underlies the DART Underground route is a locally important

aquifer. Limestone bedrock underlies the full length of the tunnel alignment.

The bedrock is covered by overburden consisting of inter-bedded glacial boulder clay and

fluvio-glacial silts, sands and gravels. The glacial deposits are in turn overlain in places by

post-glacial Alluvial /estuarine silts, sands and gravels. The natural overburden is

predominantly overlain by recent made ground.

The glacial boulder clay, which has generally a very low permeability in the order of 1-10

m/s or lower, is often embedded between other more permeable formations including the

limestone bedrock. The glacial boulder clay will also act as a confining layer where the

groundwater head in an underlying more permeable formation is above the base of the

boulder clay layer. Lenses/layers of sands and gravels found within the overburden have a

higher permeability than the boulder clay. The overlying glacial and post glacial deposits

have no aquifer classification though they are likely to be capable of supplying usable

supplies of groundwater.

Artesian and/or sub-artesian groundwater conditions have been encountered within the

glacial sands and gravels in some locations.

Engineering geology can provide important information regarding the stratification and

composition of different soil layers and rock formations. A complex interlayering of

glacial gravels and boulder clay deposits can be present within the project area. This

stratification of soil layers affects also groundwater conditions.

Permeable soil layers are likely to be in hydraulic continuity with the Liffey and therefore

have a significant recharge potential. Glaciomarine clays can be composed of a sequence

of coarsening upwards clays, silts and fine sands which are particularly difficult to control

under wet conditions. These deposits are restricted to the port area and can affect the

alignment between East wall, Docklands and Pearse station.

Presence of glacial sands and gravel horizons within the boulder clays could result in

gravity collapse and local instability, groundwater inundation and running sands. Such

layers are difficult to predict. Mixed face conditions are likely to encounter such soil

formations and could cause difficulties during underground excavation.

9.2.3 Hydrochemistry

The hydrochemistry of the groundwater along the route has been impacted by the

proximity of the tidal stretch of the Liffey and by the effects of urban drainage. The

combination of these impacts makes it difficult to provide any generalised signature of the

groundwater found along the route.

70

In general terms, the natural salinity of the groundwater in both the overburden and the

limestone bedrock, as described by the chloride values for example, increases to the east of

Islandbridge. This increase in salinity is to be expected as lower mineralised inland

groundwaters mix with brackish groundwaters associated with the estuarine section of the

Liffey. The background levels of chloride of around 50mg/l, which are elevated above a

more inland background of 20 to 30mg/l, increase eastwards along the south bank of the

Liffey with particularly high values recorded in the Docklands area. This picture is

reversed as the route heads away from the Liffey from Christchurch Station towards St.

Stephen’s Green station with the chloride values falling back to below 50mg/l again.

The salinity of the groundwater in the bedrock is generally higher than that recorded in the

overburden deposits. This suggests that a lens of fresher (i.e. lower salinity) groundwater

exists above the deeper bedrock saline groundwater possibly indicating that there is little

natural mixing of groundwaters along the alignment.

Groundwaters in this part of Dublin City are impacted by urban drainage as evidenced by

the high number of groundwater analyses that returned elevated levels of mineral oils and

hydrocarbons. A background concentration of 0.01mg/l for mineral oil in groundwater is

promoted by the Environmental Protection Agency. Many of the analyses returned levels

of mineral oils above 0.1 mg/l and in a few cases values greater than 1 mg/l were recorded.

Generally the trace elements are below accepted background levels for Irish groundwaters.

In some boreholes, however, the levels of barium, cadmium, nickel and arsenic levels

exceeded the EPA Guideline values for groundwater although no individual borehole had

elevated levels of all three elements. The elevated arsenic levels are concentrated in areas

previously used for industrial activities. Heavy metals, poly-aromatic hydrocarbons,

mineral oil contamination hand high levels of methane have previously been identified in

the Docklands area of the project. Elevated barium levels can be expected in the western

half of the route.

9.2.4 Site Investigation and Monitoring

Extensive site investigations in relation to hydrogeology were carried out which comprised

the following methods:

rotary holes

cable percussive holes

groundwater monitoring installations in bedrock

groundwater monitoring installations in both overburden and bedrock

falling head tests

packer tests

pump test.

Surface geophysic investigations were also undertaken along the route to provide

supplementary information on the rock head profile and the nature of the overburden

between the boreholes and in areas where intrusive investigations were not possible. In the

EIS is stated that the results of the geophysic investigations were calibrated against the site

investigation results where available. However, this assumption needs to be verified. Full

details of the types of geophysical investigations are outlined in Chapter 13, Section 13.2.

A programme of groundwater level monitoring continued for 1 year. In general and

consistent with the estuarine setting, the water table is shallow and within or close to the

base of the made ground deposits. The piezometric level of the groundwater within the

limestone bedrock is generally close to the water table level.

71

9.3 Impact Assessment Methodology

During the construction phase the activities which may potentially have the most impact

are related to the construction and dewatering of the tunnels, cross passages, stations,

shafts and cut and cover sections. The potential impacts which are most likely to arise from

these activities are:

changes to groundwater levels

changes to direction of groundwater flow

adjustment of groundwater flow paths

consolidation settlement.

The range of criteria for assessing the importance of hydrogeological features within

the study area and the range of criteria for quantifying the magnitude of impacts are

outlined in the EIS, Chapter 14. The significance rating of potential environmental impacts

on the hydrogeological environment is based on the matrix presented in Table 14.4. This

takes into account both the importance and the magnitude of the potential

environmental impacts.

The hydrogeological assessment included:

i. review of relevant legislation and technical advice

ii. desk study and the compilation of available data sets

iii. comprehensive programme of site investigations.

The area affected by hydrological impact has been assumed to comprise 500m to either

side of the proposed alignment to which potential impacts of the construction and

operation of the scheme will most likely be restricted to.

The proposed scheme passes over, under and near a number of surface water bodies.

Tunnelled sections of the alignment penetrate the ground and therefore have the potential

to influence the groundwater situation.

Relevant administrative bodies and government bodies have defined policies that aim to

protect the hydrogeological environment and aquatic resources by controlling development

in such areas. These guidelines broadly state that all groundwater resources are important

and should be protected and that adverse impacts on regionally or locally important

aquifers, in particular, need to be avoided because of their potential use as a water supply.

72

There is also justifiable concern in relation to the potential impact of groundwater

drawdown, ingress, settlement and pollution.

9.4 Impact Assessment

9.4.1 General Impact

The principle potential impact on the hydrogeological regime by DART Underground

would be the lowering of the water table (and/or piezometric surface) along the alignment

in general or at the main stations and shafts specifically. This potential impact could be

either temporary or permanent in nature and would result from the abstraction of

significant quantities of groundwater from the bored tunnels and/or the excavated stations

and shafts.

Temporary excavations below the water table usually involve some element of dewatering

to allow for dry working conditions. Also, continuous pumping of groundwater may be

required where permanent structures are not water tight. In these circumstances there may

be either temporary or permanent impacts or both on the water table depending on the

nature of the hydrogeological regime, the permeability of the geological formations present

and the depth, and size of structures.

The design rationale is that all permanent underground structures will be effectively water

tight at completion of construction. However, in order to assure that design specifications

are actually achieved, extensive field monitoring is required.

9.4.2 Running Tunnels

Minimising the dewatering requirement will be achieved in the first case with the use TBM

construction. The tunnels will be continually lined during the tunnelling process. If a large

amount of water is encountered in the ground, pressure at the tunnel faces can be

maintained above natural hydrostatic pressure of the ground through use of an EPBM,

which will minimise groundwater inflow. The continuous lining of the tunnels and

maintenance of high face pressure will prevent significant groundwater ingress into the

tunnel and any significant lowering of the water table during construction.

9.4.3 Stations and Shafts

Stations and shafts will be constructed using secant piles or diaphragm wall panels, which

– if properly constructed – are effectively water tight. These will be excavated down

through the overburden strata and seated in the bedrock, except at Inchicore Station.

The retaining walls will have the effect of ‘cutting off’ groundwater flow into the

excavations from the overburden deposits. The deepening and widening of the station and

shaft openings in bedrock will incorporate grouting of the advancing faces where necessary

and the preferential grouting of encountered significant water bearing bedrock fissures to

minimise groundwater inflows.

9.4.4 Enabling Works

Temporary excavations and draw-down of the groundwater by drainage to the excavation

and/or pumping can affect the groundwater situation.

73

9.5 Mitigation Measures

9.5.1 General Mitigation Measures

Where significant water bearing fractures are encountered, high pressure grouting will be

used to seal these up and prevent water ingress. This will prevent the draining of large

water bearing fractures and further minimise the impacts on the water environment. This

grouting process will also be used during the deepening and widening of stations and mine

shafts between tunnels.

Groundwater level monitoring will be undertaken according to the preliminary Water

Monitoring Plan which is part of the overall construction monitoring scheme. The

Contractor will be obliged to develop a detailed Water Monitoring Plan from the

preliminary Water Monitoring Plan. The Contractor will also compile a Groundwater

Action Plan which will state what actions they will take if monitoring shows that the

groundwater levels are moving outside their expected range. Each part of the plan will be

specific to each particular construction location, the works on-going at any given time and

the construction methods employed.

9.5.2 Construction of Tunnels and Cross Passages

The construction methodology proposed for DART Underground is founded on the

principle of minimising the inflow of groundwater into the temporary excavations and the

construction of structures which are effectively water tight. The continuous lining of the

tunnels and the ability to maintain high face pressures will prevent groundwater

ingress into the tunnel and so will prevent any significant lowering of the water table along

the line of the DART Underground route during construction and operation.

Cross passages will be constructed by the drill and blast method and supported by rock

anchors. Walls of cross passages will be supported and made water-tight by shotcrete.

Thus, cross passages shall become essentially watertight.

Provided that the design requirements are achieved, no permanent impact is expected

during construction and operation of the DART Underground.

9.5.3 Construction of Retaining Walls

Embedded retaining walls which –if properly constructed – are effectively water tight will

be installed at each station and shaft excavation and bored down to low permeability strata

or bedrock. Stations and shafts will extend into bedrock (limestone or shale) which

requires rock excavation by blasting. It is essential that walls penetrate sufficiently deep

into unfractured bedrock to limit inflow of groundwater.

Retaining walls will have the effect of cutting off groundwater flow into the excavation

from shallow permeable horizons such as the estuarine and glacial sand and gravel

deposits. Limiting the inflow into the tunnels and excavations from the bedrock will limit

the potential for any downward migration of groundwater from the overlying overburden

deposits and more importantly of surface waters, especially from the river Liffey.

9.5.4 Temporary Dewatering

Some temporary lowering of the water table and piezometric surface(s) is likely to

occur outside the excavations where temporary dewatering is required. The extent of any

such impact on groundwater levels outside the excavations will primarily depend on the

amount of groundwater abstracted from the excavations. Minimising the quantity of

74

groundwater pumped from the excavations will limit any potential lowering of

groundwater levels away from the construction sites.

9.5.5 Groundwater Abstractions

Potential impacts which may occur during the operational phase are:

reduction in inflows to the wells,

accidental spillage of potentially contaminating liquids.

Two groundwater abstractions have been identified within the project area:

Ushers Quay: a geothermal system consisting of an abstraction and discharge

well operated at the Local Government Management Building on Ushers Quay. Based on

the NRA significance criteria, this well would have a low importance.

There is a potential for the tunnelling and the dewatering at Island Street intervention shaft

to interfere with the groundwater wells associated with the geothermal system at the Local

Government Management Services Building.

Diageo: DCC records show abstraction from a bored well(s) on the St James’s Gate site.

However, Diageo have stated that this abstraction has not been active since early 2007. It is

possible that DART Underground would impact detrimentally on the Diageo well(s) if they

are used again in the future.

The magnitude of the tunnel construction on this system is classified as a ‘large

adverse’ potential impact as the base flow to the well could potentially be disrupted by the

tunnel construction.

In order to mitigate the potentially negative impact from construction of the DART

Underground, a monitoring regime is being I mplemented which will continue

during construction to confirm that there are no alterations to the baseline environment A

review of hydrogeological conditions of the geothermal system at the Local Government

Management Services building will be undertaken by the Contractor immediately before

commencement of construction to determine the operating characteristics of the system at

that time. A similar review of currently disused well at Diageo will also be undertaken by

the Contractor. This will provide a reference of the actual conditions pertaining

immediately before construction commences. In the event that the works associated with

DART Underground are detrimental to the existing active wells, replacement well(s) will

be drilled.

9.5.6 Hydrochemistry

The use of the TBMs and the construction methods planned for the various shafts indicate

that there will be a tendency for groundwater and fines to migrate to the construction area

rather than move to the wider area. In such circumstances any spillage within the

construction site will remain there until appropriate remedial action is taken to remove the

offending liquids and contaminated groundwater.

9.6 Site-specific Construction Impact and Mitigation

For each of the seven section of the DART Underground Scheme, the hydrogeological

conditions are described, as well as the predicted impact and proposed mitigation

measures. Due to the incorporated mitigation measures as outlined in the EIS,

groundwater inflows to tunnels and excavation will be minimised and consequently the

75

impact on groundwater levels will be reduced. Impact and possible mitigation measures

have been addressed in previous sections and to EIS Section 14.4.1.

9.6.1 Inchicore Cut and Cover, Inchicore Station and Inchicore Intervention Shaft

Conditions This area is composed of made ground and boulder clay with low permeability, with the

station being constructed primarily within the boulder clay deposits. There are no surface

water bodies currently running in this area. However, the Creosote Stream and its

tributaries were once located in this area. As part of the utilities survey, this stream was

identified on site where it is culverted. The stream had a history of contamination with

creosote.

Potential Impact Due to the ground conditions in this area, and the construction work to be undertaken,

the magnitude of the potential impact on the hydrogeological regime will be ’negligible’.

The predicted impact on the hydrogeological regime will also be ’negligible’. This

indicates that the significance of the impact will be ‘imperceptible’.

Mitigation Measures Mitigation measures incorporated in the design of the DART Underground Scheme will be

implemented. Monitoring shall be carried out to assure that specified limiting values are

not exceeded.

9.6.2 Inchicore to Heuston Station

Conditions The bored tunnels run mainly through bedrock. However these extend into gravel or

boulder clay in areas where the rock head is shallower. The Memorial Park

Ventilation/Intervention shaft extends through made ground, boulder clay, discrete gravel

lenses and finishes in the limestone bedrock. The Heuston station shafts extend through

made ground, glacial gravel and finish in the limestone bedrock. The Camac river is

culverted beneath Heuston station which limits its connection to the groundwater. The

Liffey is tidal in this area and the lower reaches of the Camac may be tidally influenced

too.

Potential Impact The magnitude of the potential impact in this area will be ‘moderate adverse’ and this

is particularly the case at Heuston where gravels are present above the limestone. The

magnitude of the predicted impact will be ‘small adverse’ and the significance of the

impact will be ‘slight’.

Mitigation Measures Mitigation measures incorporated in the design of the DART Underground Scheme will be

implemented. Monitoring shall be carried out to assure that specified limiting values are

not exceeded.

9.6.3 Heuston Station to Christchurch Station

Conditions The bored tunnels are located mainly in the bedrock. The Island Street Intervention shaft

extends through made ground, gravel deposits and terminates in the limestone bedrock.

76

There is a thin layer of boulder clay material present in places, however this is not

continuous.

Shafts at Cook Street and Christchurch extend through made ground, boulder clay, discrete

gravel lenses and terminate in the limestone bedrock.

Potential Impact Dewatering at the Island Street Intervention shaft and the Christchurch station shafts would

result in the lowering of groundwater levels in the immediate area of the excavations. The

magnitude of the potential impact in this area will be ‘moderate adverse’ and this

is particularly the case at Island Street where gravels are present above the limestone. The

magnitude of the predicted impact will be ‘small adverse’ and the significance of the

impact will be ‘slight’.

Mitigation Measures Mitigation measures incorporated in the design of the DART Underground Scheme will be

implemented. Monitoring shall be carried out to assure that specified limiting values are

not exceeded.

9.6.4 Christchurch Station to St. Stephen’s Green Station

Conditions The works in this area will extend through made ground and Dublin boulder clay (DBC)

and will finish in the limestone bedrock.

Potential Impact The magnitude of the potential impact in this area will be ‘small adverse’ due to

the presence of boulder clay above the limestone. The magnitude of the predicted impact

will be ‘negligible’ and the significance of the impact will be ‘imperceptible’.

Mitigation Measures Mitigation measures incorporated in the design of the DART Underground Scheme will be

implemented. Monitoring shall be carried out to assure that specified limiting values are

not exceeded.

9.6.5 St. Stephen’s Green Station to Pearse Station

Conditions The works in this area extend through made ground, Alluvial sand and gravel deposits,

boulder clay and finish in the limestone bedrock.

Potential Impact The magnitude of the potential impact in this area will be ‘small adverse’ due to

the presence of boulder clay above the limestone. The magnitude of the predicted impact

will be ‘negligible’ and the significance of the impact will be ‘imperceptible’.

Mitigation Measures Mitigation measures incorporated in the design of the DART Underground Scheme will be

implemented. Monitoring shall be carried out to assure that specified limiting values are

not exceeded.

77

9.6.6 Pearse Station to Docklands Station

Conditions The works in this area extend through made ground, gravel deposits and boulder clay

and finish close to the limestone bedrock surface.

Potential Impact Tunnelling along this section has the capacity to act as a drain as it is being constructed

below the water table.

Dewatering at the Docklands station would result in the lowering of groundwater levels in

the immediate area of the excavation.

The magnitude of the potential impact in this area will be ‘moderate adverse’ due to

the presence of gravel above the limestone at the Docklands. The magnitude of the

predicted impact will be ‘small adverse’ and the significance of the impact will be ‘slight’.

Mitigation Measures This area has been highlighted as one where recharge to ground may be

employed successfully as a mitigation measure if necessary but further investigation will

be needed to confirm this during the construction phase. Mitigation measures incorporated

in the design of the DART Underground Scheme will be implemented. Monitoring shall be

carried out to assure that specified limiting values are not exceeded.

9.6.7 Eastern Portal and Cut and Cover Section

Conditions The works in this area extend through made ground and finish in gravel deposits. The

alignment rises from a depth of approximately 16m below ground level at the Eastern

Portal to tie into the existing at grade tracks.

Potential Impact Dewatering at the Eastern Portal and the Docklands cut and cover section would result in

the lowering of groundwater levels in the immediate area of the excavation.

The magnitude of the potential impact in this area will be ‘moderate adverse’ due to

the presence of gravel above the limestone at the Docklands. The magnitude of the

predicted impact will be ’small adverse’ and the significance of the impact will be ’slight’.

Mitigation Measures This area has been highlighted as one where recharge to ground may be

employed successfully as a mitigation measure if necessary but further investigation will

be needed to confirm this during the construction phase. Mitigation measures incorporated

in the design of the DART Underground Scheme will be implemented. Monitoring shall be

carried out to assure that specified limiting values are not exceeded.

9.7 Operational Impact

This impact assessment has identified that DART Underground has the potential to alter

the existing groundwater conditions. However, the manner of its construction and proposed

operational method ensures that DART Underground will not result in any significant

residual impact on the existing groundwater regime. On-going groundwater level

monitoring will be undertaken. Where DART Underground is deemed to have a significant

78

effect on the established groundwater regime appropriate, long term mitigation measures

will be implemented such as the provision of replacement water wells.

Activities or features which may impact the hydrogeological regime and

hydrogeological features during the operational phase of the proposed scheme include:

presence of permanent embedded retaining walls in tunnel portals

station boxes and intervention shafts

presence of the bored tunnels

storage of potentially contaminated materials such as fuel

accidental spillage of contaminated material from drains or foul sewers.

On completion of the construction phase the groundwater levels will rebound to their pre-

construction levels as no permanent dewatering is associated with the operation of

DART Underground. The line of the tunnels will not act as a preferential groundwater flow

or drainage path and so there will be no permanent lowering of the water table along the

line of the route.

Structures located in the more permeable overburden deposits and the bedrock have

the potential to have a greater impact on groundwater flow patterns. However, the

potential impact on groundwater flow patterns even in these formations is considered to

be insignificant.

9.8 Comments and Recommendation - Hydrogeology

The assessment of hydrogeological impacts during the construction and operational phase

of the DART Underground Scheme has been thorough and is based on generally accepted

methods and concepts. During the Oral Hearing evidence was given which clarified some

of the aspects which were not addressed in sufficient detail by the Applicant (OH-No. 28;

K. Cullen: Hydrogeology). The information provided by the Applicant with regard to

identified risks and proposed mitigation measures is satisfactory. Also, the proposed

monitoring program is reassuring.

The Detailed Design stage, to be carried out in compliance with EN 1997 (Eurocode 7:

Geotechnical design), shall include, inter alia, the following:

1. A determination of permissible limits (threshold and limiting values) for permanent or temporary groundwater level drawdown

2. Identification of areas and depths of potential contamination of groundwater and soil deposits.

3. A high degree of quality control during deep excavations relating to water-tightness of walls/structures

4. Mitigation proposals to protect groundwater quality and the hydrogeological regime in the event of a flooding occurrence during the construction phase.

79

10 Geotechnical Conditions

10.1 General

The EIS addresses in Chapter 13 how soils and geology could be affected by the

construction and operation of the DART Underground. Chapter 16 of the EIS considers the

consequences of settlement and ground movement. However, the EIS does not address

extensively the impact of geotechnical conditions on the construction of the DART

Underground and its consequences for the receiving environment. This is unfortunate as

the Preliminary Design report (Phase 2 report by Mott McDonald) has dealt with these

geotechnical issue in a separate chapter of Volume 5 (Geotechnical 231922R6001/C), cf.

EIS Volume 4, Appendices to Chapter 2 – Part 5. However, as the Phase 2 report was

included as Appendix to the EIS, the required information was available, albeit not for the

entire route of the DART Underground alignment (as Inchicore area was not included).

In the present report the geological and soil conditions have been addressed in Chapter 8

and hydrogeological conditions in Chapter 9, respectively. This chapter (10) reviews how

geotechnical aspects affect construction of the DART Underground and their impacts on

the receiving environment.

Geotechnical Investigations

The phased ground investigation programme included the preparation of various

geotechnical reports. The geological and geotechnical investigations comprised:

Phase 1: Development of Alignment Options - Parsons Brinckerhoff (Ireland) Ltd.

(2003).

Phase 2: Preliminary Design – Mott MacDonald Pettit Ltd. (2008).

Phase 3: Reference Design – Geological desk study and ground investigations

including walkover survey of the entire route and adjacent areas, including

rock exposures in the Dublin area.

Phase 1 and 2 studied the conditions along the alignment at that stage of the project and did

not include the section from Heuston to Inchicore. The Phase 2 study by Mott McDonald

highlighted the following two issues:

Rockhead level derived from percussion drillings

Anomalous areas where the rockhead depressions were considerably deeper or

wider than previously predicted.

The Phase 2 report emphasised the need for additional, more detailed assessment to assist

in Detailed Design of the scheme.

During Phase 3 (Reference Design for the EIS), additional information was compiled from

relevant published or pre-existing information, feedback from consultations, relevant

organisations and affected third parties. Also, additional ground investigations were

undertaken between December 2008 and September 2009, comprising 167 boreholes,

ranging in depth from 10.6 to 47.1m bgl. This corresponds to an average spacing of 45 m

between boreholes. The ground investigations covered the entire route from the proposed

Inchicore Station to East Wall.

The following geotechnical field and laboratory tests were carried out during Phase 3 of

the project.

80

10.1.1 Field Tests

The following field testing methods were employed:

able Percussion boreholes including SPT at 1.5m depth intervals during drilling

Rotary core drill holes with recovery of disturbed and undisturbed soil samples and

of rock samples

Trial pits and recovery of bulk soil samples

Window samples

Groundwater monitoring and sampling

Variable head permeability tests

Packer permeability tests

Downhole geophysical surveying

Geophysical surveying

Surveying

Condition survey

Pumping tests.

10.1.2 Laboratory tests:

The following laboratory testing of overburden (soil) and rock samples was conducted:

Routine soil classification tests

Determination of soil strength and compressibility

Frequency and nature of fracturing within bedrock

Permeability of both the overburden (soil) and underlying bedrock

Samples tested under waste acceptance criteria for contaminants.

10.2 Geophysical Testing

Surface geophysic testing was carried out along the route to provide

supplementary information on the rockhead profile and the nature of the overburden

between boreholes and in areas where intrusive investigations were not possible. The

following methods were employed:

Seismic refraction to provide information on the bedrock profile

Multichannel Analysis of Surface Wave (MASW) to provide supplementary

information on the stiffness of the overburden (one-dimensional and two-

dimensional methods)

2D resistivity profiles (supplementary information on overburden and bedrock

profile).

Surface geophysical testing was carried out concurrently with intrusive investigations. The

factual information retrieved from the site investigation (such as rotary and cable

percussive borehole logs) was provided to the geophysicists to be used in the calibration of

the geophysical data acquired. However, it is difficult to verify to what extent this

information was actually used in the interpretation and calibration of seismic testing.

10.3 Ground Conditions

The EIS is based on a Reference Design, which requires the conservative assumption of

realistic geotechnical parameters. However, the EIS does not provide in the main report a

quantitative interpretation of geotechnical parameters, which is unfortunate. A general

81

geotechnical description is presented in tables of Appendix 13 (Soil laboratory data). It is

stated that for contractual reasons the contents of the interpretative geotechnical report

cannot be made available. However, in the Phase 2 report Volume 5: Geotechnical,

properties are summarised in two Tables 7.1 and 7.2. The information given on

geotechnical drawings of Phase 2 investigations emphasise the limited reliability of

identified soil layers:

“Stratigraphy of the superficial deposits should be used with caution as it is generally based on potentially unreliable third-party information at a considerable offset from the tunnel alignment.”

This statement must be taken into consideration when evaluating the EIS and the reliability

of conclusions made in the assessment of geotechnical impact.

Based on geotechnical, geological and geophysical information, inferred geological

sections were developed. The information obtained has been used to describe and evaluate

the likely impacts of construction work on the environment.

Baseline soils identified include boulder clays, sands and gravels, silts and sandy clays

from river deposits and made ground including rubble and waste materials. Bedrock

geology consists predominantly of limestones with shales.

Detailed baseline conditions are not presented in this report and only those aspects, which

are of significance for environmental impacts from geotechnical conditions, are discussed.

The general lithological/geological sequence of the overburden within the Dublin area

comprises the following units:

Fill and Made ground

Reclaimed land of soils with varying properties

Estuarine/Alluvial clays and silts

Estuarine/Alluvial gravels and sands

Fluvio-glacial deposits (glacial sands and gravels)

Glaciomarine clays and silts and sands

Glacial till – Dublin Boulder clay

Glacial gravels and sands

Bedrock (Carboniferous limestone)

Fill and Man-made Ground

Extensive areas of made ground are present along the route. The composition of made

ground varies widely and generally consists of a mixture of waste materials including, for

example, domestic refuse, clinker and demolition rubble. The thickness is generally

between 1m and 6m, but locally deeper. Thicknesses of made ground generally increase

towards the city centre and in the Docklands area.

Reclaimed Land

Fill materials in Dublin occur almost exclusively in the east of the City. The majority of fill

was uncontrolled in both manner of placement and material content. Fills are generally in

the range of 3 to 6 m thick. Hydraulic fill is mainly found in the port area, where fills are

anticipated to be loose to medium dense.

Alluvial Deposits

Alluvial clays and silts occur along the profiles of the various streams and rivers which

intersect the DART Underground route such as the rivers Camac, Poddle and Liffey. These

sediments show high lateral variability over short distances and tend to be inter-layered.

82

Some organic material was also noted within these sediments in isolated locations. Bands

of peat have been encountered locally within the Alluvial deposits in the area of the Liffey.

Estuarine Deposits

Estuarine deposits are present in the vicinity of the Liffey. The glacial sands and gravels

can contain cobbles and occasionally boulders. The glacial sands and gravels generally

occur as layers or lenses within the predominantly clayey glacial till. Estuarine clays and

silts prevail within the Liffey estuary particularly where the route crosses beneath the

Liffey at Sir John Rogerson’s Quay and emerges at North Wall Quay. These sediments are

soft to stiff clays and silts with some shell fragments and occasional interbedded sand

layers. However, in the area of the pre-glacial channel to the north of the Liffey (and also

to a lesser extent between the Liffey and St. Stephen’s Green) significant thicknesses are

present. The geology of the pre-glacial channel area is complex with glacial tills occurring

within glacial gravels and vice-versa and likely reflects the complexity of the variations

and different stages of ice sheet advance and withdrawal. Artesian and/or sub-

artesian groundwater conditions have been encountered within the glacial sands and

gravels in some locations.

Alluvium

Alluvial /estuarine sands and gravels dominate the area around Heuston Station, Diageo

Street, James’s Gate and Docklands. Soft silts and clays are likely to be present in the areas

along the Liffey, Tolka and other smaller streams and former river courses. Bands of peat

were encountered locally within Alluvial deposits in the vicinity of the Liffey. The selected

construction methods need to address the potential of ground instability and excessive

settlement associated with construction over and within these materials. The usually dense

to very dense sub-angular to sub-rounded sandy gravels and gravelly sands are locally

overlain by a thin layer of very recent soft estuary clays and silts.

Glacial Till (Dublin Boulder Clay)

The glacial till consists of a heterogeneous mixture of clay, silt, sand and gravel

with cobbles and boulders. It is locally known as Dublin brown or black boulder clay. The

till contains discrete, and in places extensive, layers, lenses and pockets of sand and gravel.

Dublin boulder clay is a stiff to very stiff glacial till found throughout the route. The till is

a well graded soil with numerous cobbles and boulders (the size of the boulders can

vary from 0.5 m to 3.0 m). The thickness of these deposits has been found to be very

variable across the area and up to 25m of till was noted in the area of the proposed tunnel

portal in Inchicore.

Glacial till is generally considered to be a good material for tunnel construction. However,

lenses and layers of sand and gravel are present within the predominantly clay matrix that

can contain groundwater under high pressure.

The presence of boulders within the glacial till has the potential to disrupt bored tunnelling

construction and also the construction of deep foundations. Previous experience indicates

that boulders with maximum dimensions greater than 0.5m are rarely encountered during

construction works in Dublin.

Glacial Gravels and Sands

Glacial gravels and sands can occur beneath, within and on top of the glacial till. Pockets,

lenses and layers of granular material, of varying extent, exist within the glacial till.

83

Glacial gravels within the boulder clay consist typically of very dense, angular to sub-

angular sandy, slightly silty gravels or very gravely, slightly silty sands.

Saturated gravels with sub-artesian pressures can be expected in some areas. Therefore,

engineering solutions will need to be capable of dealing with the potential risk of

encountering groundwater in localised areas within the till; inflows have the potential to be

sudden and variable, with the volume of inflow being dependent on the volume of granular

material, interconnectivity with other gravel deposits and groundwater pressure. The

presence of sandy or gravelly soils within cut slopes can potentially lead to

rapid dissipation of excavation induced negative pore water pressures and can lead to slope

instability. The presence of such materials can also have adverse effects on deep

foundation and shaft construction.

Glaciomarine Clays, Silts and Sands

Glaciomarine sediments are likely to be encountered in the areas around the Docklands.

They consist of very stiff (to hard) sandy, clayey silts and medium dense to dense silty

sands, locally interstratified with thin laminae of clay. Such deposits were presumably

buried below an advancing glacial ice sheet, leading to the very stiff to hard consistency

and slight overconsolidation of the material.

Bedrock

The bedrock encountered during the various phases of ground investigation defines an

undulating bedrock profile formed where changes in the ordnance level of the top of rock

can change relatively quickly over short distances. The bedrock profile has

been particularly influenced by recent geological history where stress relief and weathering

occurred. In Dublin city centre the bedrock consists of carboniferous limestone

interbedded with mudstone and shale (Calp limestone). Due to the nature of the study area

and the subsequent scarcity of bedrock exposures it is difficult to define all structural

manifestations but the resolution of minor fault gouge and recovery of fault breccia

suggests that these fault zones are singular restricted features rather than dominating over

extensive areas.

Weathered Rock Head

The occurrence of weathered rock head is variable across the route. Where encountered,

the engineering properties tend to be poorer and can potentially cause problems in

achieving an adequate cut-off for retaining walls. Design and construction solutions will

need to consider the impact on foundation construction and make provision to achieve an

adequate cut-off for retaining walls. These fractured zones are commonly limited to the

uppermost 0.5 to 3m of the underlying bedrock, but deposition of silty clay materials along

open fractures and joints can reach to considerable depths within the bedrock. Weathered

rock encountered during the site investigation was generally ≤ 0.5m.

Karst features are not likely to be encountered along the DART Underground route.

Groundwater

Groundwater conditions have been addressed in Chapter 9, Hydrogeology and are only

briefly mentioned here. The groundwater level is typically between 2m and 4m below

ground level in the city centre area but may be deeper where ground levels are more

elevated. Sub-artesian groundwater pressure and/or running sands and gravels have

been encountered in several areas, particularly associated with the pre-glacial

84

buried channel to the north of the Liffey. The hydrogeological aspects are discussed in

Chapter 10.

10.4 Extent of Ground Investigations

Phase 3 comprised 167 boreholes which correspond to an average spacing of 45m, or 90m

if the two tunnel routes are taken into consideration. In addition, results from previous

investigation phases and desk studies were available for preparation of the EIS. However,

the DART Underground includes large construction sites for stations, shafts and tunnel

portals for the design and execution of which detailed geological and geotechnical

information is needed.

The type of geotechnical investigation methods employed in the Phase 3 study is limited to

boring and SPT. Chapter 10 of the Phase 2 by report Mott McDonald proposed additional

ground investigation methods which could provide more detailed and reliable factual

information. These include:

Rotary open hole and core investigations

Cone penetration testing (CPT) and in very soft soils with pore water pressure

measurement (CPTU)

Laboratory testing

Piezometer installation

Down-hole geophysical logging and

Contamination screening.

It has not been possible to verify whether and to which extent the above proposed

investigations have been carried out. For instance, results from cone penetration tests have

not been found in the EIS factual information. In areas with difficult ground conditions

(especially in the eastern part of the DART Underground alignment), cone penetration

testing (CPT) or cone penetration testing with pore water pressure measurement (CPTU)

would have been more suitable than Standard Penetration Testing (SPT) to determine

quantitative properties of the stiffness and strength of soft and loose soils. It is in such

areas with soft deposits and variable fill where the greatest geotechnical hazards can be

expected.

10.5 Reliability of Geotechnical Properties

Factual information from various investigations has been compiled in the EIS, Volume 4,

Appendices 1 – 19. However, as no interpretation or comparison of test data from different

types of investigations is given in the EIS, it was difficult to assess the quality and

reliability of predicted and assumed soil and rock properties. Detailed information

regarding geotechnical properties of soil layers is of particular importance in the case of

deep excavations in the vicinity of sensitive structures.

The uncertainty regarding geotechnical properties of soil and rock is illustrated by the

following example. The geotechnical conditions at the planned station at St. Stephen’s

Green are shown in the below Figure 1 as plan and geological profile (between chainage

15+900 and 16+350). Eight boreholes (BH 42 – BH 49) were carried out as part of the

Phase 3 investigation. In addition, surface seismic investigations (seismic refraction and

MASW) were performed along and perpendicular to the alignment.

85

Results of borings from Phase 3 investigations are presented in the EIS, Appendices in

Volume 4, in the form of borehole records. As an example, the geotechnical core log

record in borehole BH 49 is shown in the below Figure 2. In addition to soil type also the

SPT N-values are shown at depth intervals of 1.5m down to about 10m depth. The soil

layer from the ground surface down to 10 m depth is described as black sandy gravelly

clay (Dublin boulder clay).

Figure 1. Plan of station at St. Stephen’s Green and geological profile based on Phase

2 and Phase 3 investigations, cf. Volume 3, Figure 13-00-29 .

From the data provided in the Appendices it is difficult to interpret and evaluate the results

from different investigations. An important aspect which can be noted, however, is the

variability of soil properties within a relatively limited area and with depth in a soil layer.

To illustrate this point, the diagram shown in Figure 3 was compiled. It shows SPT N-

values versus depth derived from boreholes BH47, BH48 and BH49, cf. above plan.

Comparison of SPT results from three different boreholes located within the station area

indicates the possible variability of the Dublin boulder clay. This important aspect

influencing geotechnical design has not been addressed and considered adequately in the

EIS. The main conclusion must be that soil and rock conditions in some locations can be

more variable than anticipated. Alternatively, the reliability of investigations must be put

into question. This example is to illustrate that the EIS lacks information on the variability

of geotechnical parameters, interpretation and comparison of results from different types of

investigations.

The quality of information regarding geotechnical soil and rock properties reported in the

EIS is basic but not more. For instance, compilation and analysis of geotechnical properties

from investigations during the different phases of the project in an interpretative report

would have been helpful in assessing the construction impact on, for instance, structures

located in the zone of influence of deep excavations.

86

Figure 2. Geotechnical borehole data from borehole BH49 at St. Stephen’s Green.

87

Figure 3. Variation of SPT N-values with depth for three boreholes at St. Stephens

Green station, based on evaluation of factual information in the Appendix of

the EIS.

10.6 Dynamic Soil Parameters

The knowledge of dynamic soil parameters is of importance for assessment and design of

many different types of structures of the DART Underground project. Wave speed

(referred to as “wave velocity” in the EIS) provides important information for the

prediction of dynamic track response and vibration propagation from the railway on or

below the ground to the surroundings. It is also possible to determine from the wave speed

the deformation properties of soil and rock. Wave propagation speed can be correlated to

the small-strain modulus, Gmax from which deformation properties during static loading

can be estimated.

In the EIS Volume 4, Appendix 09 (Surface geophysics) the results of shear wave speed

measurements by the MASW method are presented. MASW is a powerful method of

seismic ground investigations especially as the results of measurements are not affected by

groundwater. The evaluation of seismic measurements and in particular the interpretation

of MASW results is a complex task which requires experience. An important aspect is the

calibration of theoretical models with results of actual borings to verify the reliability of

MASW data.

In response to questions during the Oral Hearing the Applicant presented evidence (OH-

No. 63A; S. Mason: Drawings – Soils and Geology) showing at three locations of the

DART Underground route a comparison of borehole data and results from seismic

investigations. Figure 4 shows a section at St. Stephen’s Green between chainage 16+232

and 16+350. Note that in this section, the above SPT N-values were obtained from the

three boreholes BH47, BH48 and BH49, respectively.

The shear wave speed varies in the boulder clay (brown colour) between 800 and 2300m/s.

The shear wave speed in limestone can be assumed to exceed 2300m/s.

88

Agreement between soil profiles and identified wave speeds is rather poor, but this can

partially be explained by the fact that the borehole locations were not aligned with the

MASW and seismic profiles. However, there are significant variations of shear wave speed

with depth in the Dublin boulder clay. Also the soil-rock interface determined from seismic

tests is not in good agreement with the borehole data.

Figure 4. Extract of diagram presented by Applicant at Oral Hearing, comparing soil

layers from borings with shear wave speed obtained from seismic tests at St.

Stephen’s Green.

It is interesting to note the large variability of shear wave speed in the Boulder clay which

is often assumed to be relatively homogenous. Knowledge of the variable soil conditions

and the variations of the soil-rock interface within relatively short distances is an important

aspect which needs to be taken into consideration in the Reference Design and in particular

for the Final Design.

89

The Applicant presented also profiles showing the variation of the small-strain shear

modulus, Gmax with depth. Three MASW profiles were evaluated and these are one-

dimensional representations (average) of the actually measured profiles. The location of

the three MASW profiles is shown in the above plan of the investigated area.

Figure 4 shows that soil stiffness, expressed as small-strain shear modulus, Gmax can vary

considerably with depth but also laterally across the site. From the small-strain modulus,

the elastic deformation modulus can be determined taking into account the strain-softening

of soils at working load.

Figure 5. Variation of small-strain shear modulus, Gmax with depth as determined from

MASW tests at St. Stephen’s Green.

The results of MASW investigations, when carried out properly and calibrated against

other types of geotechnical investigations such as SPT and/or CPT, can be a valuable

source of information for the designer. However, the presently available data are not

deemed reliable for use in the Detailed Design and need to be re-evaluated.

10.7 Geotechnical Hazards

10.7.1 General

Geotechnical and geological as well as hydrogeological conditions play an important role

in environmental risk assessment. Hazards which need to be considered can be divided

into:

hazards due to geotechnical and geological conditions,

hazards due to construction activities on or below the ground.

In the EIS only hazards and risks associated with settlement (and horizontal ground

movement) have been described explicitly. Other hazards were addressed briefly in

90

chapters Chapter 3 (Scheme Description); 5 (Construction Strategy); 9 (Below Ground

Noise and Vibration); 13 (Soils and Geology) and 14 (Hydrogeology).

Management of environmental risks during construction and operation were addressed

during the Oral Hearing in extensive evidence given by the Applicant and in particular in

evidence OH-No. 22 and 22A¸ S. Fricker: Settlement and E-No-23, S. Fricker: Settlement

of permanent structures & utilities – Clarification for An Bord Pleanála.

10.7.2 Geotechnical and Geological Hazards

Although the ground conditions are generally favourable for the proposed DART

Underground Scheme, geotechnical hazards need to be considered with care during the

Detailed Design. The following geotechnical hazards, some of which have been identified

already during Phase 2 and reported in EIS (Volume 4, Appendices A2.5), were not

considered in sufficient detail in the EIS. Therefore, these need to be included in the

geotechnical risk assessment and management scheme:

variable and unexpected ground conditions (made ground and fill)

presence of soft, instable and compressive glacio-marine deposits

sand veins (interbedded as sandy laminations in boulder clay) causing dewatering

problems

gravel bed resulting in problematic groundwater inflows into excavation

contamination of ground and groundwater

high levels of methane

artesian or sub-artesian water pressure within glacial gravels

instability of shallow excavations in loose and soft ground (especially silty soils)

settlement of structures and installations in the ground (e.g. utilities) due to tunnel

construction

settlement of structures and installations in the ground due to permanent lowering

of groundwater

ground movements (vertical and horizontal) of structures due to construction of

deep excavations

instability of excavations in soil due to fissuring and/or shearing of glacial clays

instability of excavations in rock due to discontinuities, fissuring rock and

weathered rock

variability of rockhead level or unexpected deviations from design assumptions

bedded limestone with interbedded shale resulting in stability problems

dip of limestone bedding

voids in rock formation (potential of karstic features)

high groundwater pressure at tunnel level

running sands in boulder clay

difficulties during tunnel boring in mixed face conditions

settlement of loose, granular soil layers induced by blasting vibrations

obstructions to excavations (made ground, boulders etc.)

inflow of water into excavations due to granular horizons

unexpected ground conditions

unexploded ordnance within soft or loose superficial deposits

consequences of archeological excavations

contamination of groundwater.

91

Although this list of potential hazards due to geotechnical conditions is extensive, it may

not be complete. However, it can serve as a basis for establishing a comprehensive risk

management scheme. Some of the more important hazards are discussed briefly.

Lowering of Groundwater Table Dewatering of the ground and lowering the groundwater table may be required or caused

unintentionally by deep excavations or tunnel construction. This can induce consolidation

settlement in compressible clay or organic layers (occurring in Alluvial /estuarine deposits

and glacio-marine deposits) during construction but also extend into the operational phase.

Areas of concern are located along the Liffey estuary and in areas in proximity to buried

river channels.

High Groundwater Pressure Particularly adjacent to the Liffey the groundwater level is likely to be located close to the

ground surface. Significant heads of water (in excess of 10m) may impact upon a large

portion of the route. Confined water pressures may be present particularly within the

granular horizons of the glacial deposits, where sub-artesian water pressures have been

recorded.

Organic Matter in Fill Decay of organic matter present within fill material and reclaimed land in the east of the

alignment and within Alluvial deposits may result in potentially significant total and

differential settlements. Organic matter may also cause high concentrations of gas

(hydrogen sulphide, methane and carbon dioxide) during excavation, particularly within

confined spaces.

Near-surface Obstructions There is a potential for the presence of current and historical structures in the near

subsurface. Such structures could pose potentially significant problems for excavations

associated with cut-and-cover sections and station access structures.

Loose or Soft Deposits The presence of loose or soft soils within excavations may cause stability problems. As a

result of construction activities and resulting stress changes (pore water pressure and

effective stress), such soils may lose strength and stiffness (decompression). Under

unfavourable conditions, such soils could lead during tunnelling work to blow-

out/breakthrough to the ground surface where they overlie the tunnel.

Sand-filled Channels Encountering sand filled channels or other granular horizons within excavations or in

connection with tunnelling work may result in local instability, running sands or

groundwater inundation. This can lead to over-excavation and excessive face loss during

tunnelling work. Case histories from projects in the Dublin area of excavation within

glacio-marine clays and silts show a number of incidences of the material running into the

excavation or excessive ground movement.

10.7.3 Construction-related Hazards

In addition to geotechnical hazards due to ground conditions, also hazards related to

construction activities on and below the ground need to be taken into consideration. The

following list of problems, some of which were also addressed in different chapters of the

92

EIS and in Appendices (Volume 4 – Part 5: Case histories of the Mott McDonald report),

need to be considered:

Construction of water-tight wall elements due to construction deviations and or

obstructions

Seating of wall elements on blocks or fractured rock layers

Instability of excavations in rock due to unfavourable bedding planes

Leakage of groundwater in soil and fractured rock into deep excavations

TBM work in weathered rock and rock formations with potential faults

TBM work in mixed face conditions (soil-rock interface)

TBM work in deposits with layers and lenses of water-bearing sands

Wear on equipment (tunnelling and excavation) due to presence of abrasive ground

Obstructions in made ground encountered during wall construction (affecting

verticality of piles/panels and influencing water tightness)

Chiseling required to penetrate boulders and other obstructions

Draw-down of groundwater adjacent to excavation, due excessive pumping in

excavations (leakage through or below secant pile or diaphragm wall)

Difficulties with installation and/or retraction of ground anchors in hard rock

Implementation of ground treatment adjacent to tunnels and/or excavations

Potential hazards also exists in relation to the execution of foundation and ground

treatment work: installation and extraction of ground and rock anchors, compensation

grouting next to and below potentially affected structures, structural jacking of buildings or

building elements, curtain walling between tunnel and sensitive structures, underpinning of

existing, sensitive structures (historic buildings or monuments) etc.

10.7.4 Stability of Structures

One of the most important aspects of geotechnical design is to assure the stability of

structures, buildings or embankments during the construction and the operational phase.

The stability of structures with respect to geotechnical impacts can be endangered due to a

variety of effects such as:

Higher static loads than anticipated (vertical and horizontal stresses). An example

of such hazards is the unintended placement of fill material at the top of

excavations or slopes.

Excessive excavation depth, leading lower factor of safety.

Effects of dynamic loading on deep excavations for instance due to blasting.

Lower soil strength than anticipated or degradation of strength due to construction

activities (remoulding of soils).

Increased groundwater pressure due to, for instance infiltration of water from

leaking water mains, changes of water drainage or flooding.

Defects in construction execution, for instance construction methods and use of

materials with insufficient strength.

10.7.5 Settlement and Ground Movement

Ground movement, which comprises vertical settlement and lateral ground movement, can

be caused by one or a combination of different construction activities, such as:

Boring or excavation of trenches or walls in the ground

Excavation of soil and reduction of horizontal stress, leading to ground movement

adjacent to the excavation

93

Tunnelling work in soil and rock, resulting in ground loss and distortion of the

ground above and adjacent to the tunnel

Ground-water lowering caused by pumping or drainage, initiating consolidation

and creep settlement in soft, fine-grained soils (normally consolidated)

Heave at base of excavations in overconsolidated soils (boulder clay) due to stress

relief

Erosion of soil at slopes or unprotected excavations

Blasting-induced vibrations causing densification of granular soils (sand and

gravel).

Ground movement in the vertical and horizontal direction decreases usually with

increasing distance from the origin of disturbance. Also, ground movement is generally

smaller the lower the impact of disturbance (e.g. diameter of tunnel, depth of excavation,

amount of drained groundwater etc.).

More frequently, excessive ground movement and associated settlement in buildings or

structures below the ground is caused due to unforeseen geotechnical conditions and

inappropriate construction methods. The most efficient concept of minimising risks to

buildings due to ground movement is extensive control of the construction process and

monitoring of ground movements and of buildings. This concept is called the

“Observational Method” and described in detail in European standard EN 1997.

Potential settlement induced by the above mentioned construction activities can be

estimated using design recommendations as described in the geotechnical literature. The

assessment of settlement (and lateral ground movement) was carried out in the EIS

according to two widely accepted publications:

CIRIA C580 Report (2003). Embedded retaining walls – guidance for economic

design.

CIRIA Project Report 30 (1996). Prediction and effects of ground movements

caused by tunnelling in soft ground beneath urban areas.

The primary objective of the assessment of settlement of the ground and of structures on

and below the ground is to identify areas (and buildings) which are possibly affected by

construction of the DART Underground. Thus, settlement predictions are not intended -

nor suited - to predict actual building damage (cf. building damage classification). The

assessment methodology is clearly described in EIS Chapter 16.2.2. Important aspects of

this methodology are briefly summarized below as these have been discussed extensively

with the Observers during the Oral Hearing.

Assessment Methodology Phase 1: An empirical and conservative method is employed to estimate the magnitude and extent of unmitigated ground movements induced by tunnelling, tunnel approach structures, shaft construction and station excavations. The estimated ground movements are presented on settlement contour plans. Based on accepted criteria, any buildings, utilities or infrastructure potentially ‘at risk’ of damage are identified for either Phase 2 assessment or Phase 3 assessment.

Phase 2: For the buildings, utilities and infrastructure identified in Phase 1, the potential impact of the predicted ground movements is estimated in terms of the “damage category”. Depending on defined criteria, some buildings, utilities or infrastructure may require a Phase 3 assessment.

Phase 3: A Phase 3 assessment is undertaken on any buildings, utilities or infrastructure that, following either the Phase 1 or 2 assessment, are identified to potentially exceed acceptable levels of damage. Depending on the category of property, foundation configuration and architectural heritage category, some buildings and infrastructure will automatically be designated to undergo a Phase 3 assessment irrespective of the results of a Phase 2 assessment; all structures on the

94

Record of Protected Structures within the settlement zone defined by the 10mm contour will require a Phase 3 assessment, and buildings with piled or mixed foundations that lie within the overall zone of influence defined by the 1mm settlement contour, as identified during Phase 1, will automatically require a Phase 3 assessment.

Phase 3 comprises a detailed assessment in which the conservative assumptions made in the Phase 1 and 2 assessments are re-examined. The assessment is carried out prior to construction once the details of the construction and techniques and equipment to be used have been fully determined. The assessment comprises:

(i) A more detailed settlement assessment, more closely modelling the likely behaviour of the building, utility or infrastructure and the ground.

(ii) Internal and external inspections, surveys and reviews of as-built records to identify more precisely the areas and types of sensitivity and the general structural condition. If unacceptable damage is likely following the Phase 3 assessment then possible mitigation measures are designed and re-modelled in the assessment to bring the potential impact within the acceptable levels (i.e. a building damage category of slight for general buildings and very slight for buildings on the Record of Protected Structures– see Section 16.5.2). These mitigation measures are then implemented as part of the construction to safeguard the buildings, utility or infrastructure from exceeding its acceptable damage category and sustaining structural damage.

As the Phase 3 assessment is dependent on the knowledge of the actual construction techniques to be implemented, it is general practice that this assessment phase is carried out once a contractor has been appointed and hence the details of the construction methods are confirmed. However, consideration beyond Phase 2 has been given to be sure that practical measures can be designed and implemented to mitigate the effects of ground movement caused by construction.

In summary the Phase 3 assessment is used to review buildings, utilities and infrastructure identified by either the Phase 1 or 2 assessment and to finalise the use, where required, of mitigation measures which will bring these within the acceptable levels of impact prior to commencing construction.

Any cosmetic impacts, such as minor cracking that may occur within buildings associated with a damage category of slight for general buildings and very slight for buildings that are on the Record of Protected Structures, will be repaired under the Property Protection Scheme.

In response to questions during the Oral Hearing the Applicant provided evidence which

explains the different phases which are used to carry out settlement analyses, cf. below

Figure 6 (E- No. 23, S. Fricker: Settlement of permanent structures & utilities –

Clarification for An Bord Pleanála). With respect to the question why Phase 3 of the

settlement analysis was not included in Phase 3 (Reference Design) the Applicant quoted a

publication by Mair, Burland and Taylor (1996) “Prediction of ground movements and

assessment of risk of building damage due to bored tunnelling”:

“Detailed evaluation (Phase 3) is undertaken for those buildings classified in the second stage (phase) assessment as being at risk of category 3 damage (moderate) or greater……..The sequence and method of tunnelling should be given detailed consideration and full account taken of the three-dimensional aspects of tunnel layout……..…………”

Analysis of Ground Movement The EIS does not describe in sufficient detail how (vertical and horizontal) ground

movement was calculated, in particular due to installation of walls and subsequent

excavation. Ground movement (heave or settlement and horizontal displacement) can

occur due to the following reasons:

Construction of diaphragm wall panels or drilling of piles (installation-induced

ground movements)

Installation of ground anchors below adjacent structures

Excavation of soil inside retaining structure (station or shaft)

95

Removal of rock by blasting inside excavation

Long-term settlement caused by permanent lowering of groundwater level,

resulting in consolidation settlement of compressible soils.

Figure 6. Phasing of settlement assessment during design and construction of DART

Underground Scheme, from evidence provided during Oral Hearing, OH-No.

23, S. Fricker: Settlement of permanent structures & utilities – Clarification

for An Bord Pleanála.

In addition to ground movement by the construction of deep excavations, also the effect of

tunnel boring and mining of cross passages has been considered.

The Applicant presented during the Oral Hearing convincing evidence that the combined

effect of different construction activities has been included in the Reference Design of

Phase 2 settlement study (OH-No. 22; S. Fricker: Settlement and OH-No. 22A; S. Fricker:

Settlement of Permanent Structures and Utilities – Associated PowerPoint presentation).

In addition to a description of the analytical concepts employed for calculating ground

movements, detailed results of ground movement calculations were presented for the

following sites:

Christ Church station

Inchicore Shaft

Heuston station

St. Stephen’s Green station

Pearse station.

96

10.8 Site-specific Construction Impact and Mitigation

During the Oral Hearing Observers expressed concern regarding the potential negative

impact of the DART Underground on their properties. The following section provides

information on the geotechnical conditions along the DART Underground and can serve as

background to the review comments given in Appendix 4.

For each of the seven section of the DART Underground Scheme, the geotechnical and

geological conditions are described, as well as the predicted impact and proposed

mitigation measures. Due to the incorporated mitigation measures as outlined in the EIS,

negative effects of construction activities can be minimised and consequently their impact

will be acceptable. Note that the description of sites starts from the western end of the

DART Underground alignment, according to the sequence used in the EIS.

10.8.1 Inchicore Cut and Cover, Inchicore Station and Inchicore Intervention Shaft

Construction Activities and Potential Impact This area is composed of made ground and boulder clay with low permeability, with the

station being constructed primarily within the boulder clay. There are no surface water

bodies currently running in this area. However, the Creosote Stream and its tributaries

were once located in this area. As part of the utilities survey, this stream was identified on

site where it is culverted. The stream had a history of contamination with creosote.

The station will be in retained cut through the made ground and boulder clay. At the

Western portal the ground conditions comprise from 2m up to 6m of made ground,

overlying 6 to 22m of boulder clays with potential sand and gravel lenses, underlain by

Calp limestone. The scheme along this section is in retained cut and cut-and-cover tunnel,

through the made ground and boulder clay.

Mitigation Measures Mitigation measures incorporated in the design of the DART Underground Scheme shall

be implemented according to Table 13.15 of the EIS. Additional geotechnical

investigations shall be performed to establish more reliably ground conditions comprising

suitable methods such as penetration tests and laboratory testing of disturbed and

undisturbed soil samples. Inventory of potentially contaminated soil and groundwater shall

be carried out.

97

If the proposed mitigation measures are implemented the residual impact will be

negligible.

Monitoring shall be carried out during the construction phase to assure that specified

limiting values are not exceeded.

10.8.2 Inchicore to Heuston Station

Construction Activities and Potential Impact The bored tunnels run mainly through bedrock. However these extend into gravel or

boulder clay in areas where the rock head is shallower. The Memorial Park

ventilation/intervention shaft extends through made ground, boulder clay, discrete gravel

lenses and finishes in the limestone bedrock. The Heuston Station shafts extend through

made ground, glacial gravel and penetrate into the limestone bedrock. The Camac river is

culverted beneath Heuston Station which limits its connection to the groundwater. The

Liffey is tidal in this area and the lower reaches of the Camac may be tidally influenced

too.

From Inchicore to Memorial Park the ground conditions comprise up to 6m of

made ground, overlying 7.5 to 28m of boulder clays with glacial sand and gravel lenses,

underlain by Calp limestone. The scheme over this section comprises two bored tunnels,

primarily within limestone bedrock, with mixed-face and boulder clay conditions

approaching Inchicore portals.

At Memorial Park ventilation/intervention shaft the ground conditions comprise up to 4m

of made ground, overlying 15 to 20m of boulder clay with glacial sand and gravel lenses,

underlain by Calp limestone. The shaft will be excavated through boulder clays with sand

and gravel lenses, into the limestone bedrock to connect with the tunnels running within

the rock.

From Memorial Park to Heuston station the ground conditions comprise up to 7m of made

ground, overlying Alluvial and glacial soils over Calp limestone. The 1.0 to 3.0m of

Estuarine/Alluvial clays and silts are encountered approaching the Liffey. Similarly the

15m to 25m glacial deposits of mainly boulder clays with sand and gravel lenses, become

more predominantly glacial sands and gravels moving closer to the Liffey. The entire area

is underlain by Calp limestone. The bored tunnels along this section are within limestone

98

bedrock towards Memorial Park shaft and Heuston Station, and in mixed-face conditions

in between.

The magnitude of the potential impact in this area will be ‘moderate adverse’ and this

is particularly the case at Heuston where gravels are present above the limestone. The

magnitude of the predicted impact will be ‘small adverse’ and the significance of the

impact will be ‘slight’.

Mitigation Measures Mitigation measures incorporated in the design of the DART Underground Scheme shall

be implemented according to Table 13.15. Additional geotechnical investigations shall be

performed to establish more reliably ground conditions comprising suitable methods such

as penetration tests and laboratory testing of disturbed and undisturbed soil samples.

Inventory of potentially contaminated soil and groundwater shall be carried out.

If the proposed mitigation measures are implemented the residual impact will be

negligible.

99

Monitoring shall be carried out during the construction phase to assure that specified

limiting values are not exceeded.

10.8.3 Heuston Station to Christchurch Station

Construction Activities and Potential Impact The bored tunnels are located mainly in the bedrock. The Island Street intervention shaft

extends through made ground, gravel deposits and terminates in the limestone bedrock.

There is a thin layer of boulder clay present in places, however this is not continuous.

Shafts at Cook Street and Christchurch extend through made ground, boulder clay, discrete

gravel lenses and terminate in the limestone bedrock.

At Heuston Station the ground consists on average of 1m to 3m of made ground, overlying

Alluvial and glacial soils over Calp limestone. The 2m to 3m of Alluvial sands/gravels and

silts/clays are associated with the local rivers (Liffey and Camac). The underlying 8m to

12m of glacial till are predominantly sands and gravels, underlain by Calp limestone.

The station shafts will be excavated through the made ground, Alluvial and glacial soils,

and into the limestone bedrock to connect with the tunnels. The excavations for station

platforms and concourses are all anticipated to be within limestone bedrock.

Thickness of made ground may be significant in the vicinity of the river walls and land

behind may have been filled in. The presence of thick sand and gravel layers as the station

is located above the northern flank of the pre-glacial/glacial buried channel which is

known to exist beneath the Liffey

100

At the location of the Island Street intervention shaft the ground conditions consist of up to

5m of made ground, overlying 2m to 5m of Alluvial silt/clay and sand/gravels sediments,

over 8m to 10m of glacial sands and gravels. The area is underlain by Calp limestone. The

shaft will be excavated through the above sequence to connect to the tunnels within

the limestone bedrock.

From Heuston to the Island Street area the tunnels run close to the Liffey. The ground

conditions comprise 2m to 6m of made ground, overlying Alluvial sediments, over glacial

gravels and sand, underlain by Calp limestone. The Alluvial soils are mainly silts/clays

from 1m to 5m depth, underlain by 8m to 20m of glacial tills, predominantly glacial

sands and gravels. The bored tunnels over this section pass from limestone bedrock,

through mixed face conditions and back into limestone bedrock.

From Island Street shaft to Christchurch the rockhead level rises. Ground conditions

comprise 2m to 4m (locally 8m) of made ground, overlying zero to 6m of

101

estuarine/Alluvial sediments, over zero to 8m of glacial till, underlain by Calp limestone.

The bored tunnels throughout this section are within the limestone bedrock.

Dewatering at the Island Street intervention shaft and the Christchurch station shafts would

result in the lowering of groundwater levels in the immediate vicinity of the excavations.

The magnitude of the potential impact in this area will be ‘moderate adverse’ and this

is particularly the case at Island Street where gravels are present above the limestone. The

magnitude of the predicted impact will be ‘small adverse’ and the significance of the

impact will be ‘slight’.

Mitigation Measures Mitigation measures incorporated in the design of the DART Underground Scheme shall

be implemented according to Table 13.15. Additional geotechnical investigations shall be

performed to establish more reliably ground conditions comprising suitable methods such

as penetration tests and laboratory testing of disturbed and undisturbed soil samples.

Inventory of potentially contaminated soil and groundwater shall be carried out.

If the proposed mitigation measures are implemented the residual impact will be

negligible.

Monitoring shall be carried out during the construction phase to assure that specified

limiting values are not exceeded.

10.8.4 Christchurch Station to St. Stephen’s Green Station

Construction Activities and Potential Impact The works in this area will extend through made ground and Dublin boulder clay (DBC)

and will finish in the limestone bedrock.

At Christchurch Station the ground conditions comprise 3m up to 5m of made ground,

overlying 1 to 3m of boulder clay, underlain by Calp limestone at relatively shallow depths

of 5m to 8m. The station boxes will be excavated through the made ground, boulder clays

and limestone to tunnel level. All station platforms and concourses will be

excavated entirely within limestone bedrock.

From Christchurch to St. Stephen’s Green the route turns south-easterly and into higher

ground with less Alluvial deposits. The ground conditions comprise 1m up to 7m of made

ground, overlying 2m to 16m of glacial till comprising both boulder clays and sands and

gravels, underlain by Calp limestone. Some shallow Alluvial deposits are also present from

102

old stream/river courses. Throughout this section the bored tunnels are within the

limestone bedrock.

Mitigation Measures Mitigation measures incorporated in the design of the DART Underground Scheme shall

be implemented according to Table 13.15. The magnitude of the potential impact in this

area will be ‘small adverse’ due to the presence of boulder clay above the limestone.

The magnitude of the predicted impact will be ‘negligible’ and the significance of the

impact will be ‘imperceptible’.

Additional geotechnical investigations shall be performed to establish more reliably ground

conditions comprising suitable methods such as penetration tests and laboratory testing of

disturbed and undisturbed soil samples. Inventory of potentially contaminated soil and

groundwater shall be carried out.

If the proposed mitigation measures are implemented the residual impact will be

negligible.

Monitoring shall be carried out during the construction phase to assure that specified

limiting values are not exceeded.

10.8.5 St. Stephen’s Green Station to Pearse Station

Construction Activities and Potential Impact The works in this area extend through made ground, Alluvial sand and gravel deposits,

boulder clay and finish in the limestone bedrock.

At St. Stephen’s Green station the ground conditions comprise 2m to 3.0m of made

ground, overlying 4m to 6m of boulder clay with possible glacial sand/gravel lenses,

underlain by Calp limestone. The station boxes will be excavated through the made

ground, boulder clays and limestone to tunnel level. All station platforms and concourses

will be excavated entirely within limestone bedrock.

103

Marked variations in bedrock level may be encountered and buried channels in rockhead

may be present. The channels may be in-filled with complex sequences of boulder clay and

thick gravels.

From St. Stephen’s Green to Pearse Station the ground conditions continue to comprise 1m

to 4m of made ground, overlying 5m to 15m of boulder clay with Glacial Sand and Gravel

lenses, underlain by Calp limestone. Some shallow Alluvial deposits are also likely from

old stream/river courses. Throughout this section the bored tunnels are within the

limestone bedrock.

Mitigation Measures Mitigation measures incorporated in the design of the DART Underground Scheme shall

be implemented according to Table 13.15. Additional geotechnical investigations shall be

performed to establish more reliably ground conditions comprising suitable methods such

as penetration tests and laboratory testing of disturbed and undisturbed soil samples.

Inventory of potentially contaminated soil and groundwater shall be carried out.

If the proposed mitigation measures are implemented the residual impact will be

negligible.

104

Monitoring shall be carried out during the construction phase to assure that specified

limiting values are not exceeded.

The magnitude of the potential impact in this area will be ‘small adverse’ due to

the presence of boulder clay above the limestone. The magnitude of the predicted impact

will be ‘negligible’ and the significance of the impact will be ‘imperceptible’.

10.8.6 Pearse Station to Docklands Station

Construction Activities and Potential Impact At Pearse station the ground conditions consist of 3m to 5m of made ground, overlying

zero to 6m of Alluvial sediments, over 8m to 14m of boulder clay with glacial sand and

gravel deposits. The area is underlain by Calp limestone. The station shafts will be

excavated through made ground, Alluvial and glacial soils and into rock to connect to the

tunnels. The station platform and concourse excavations are anticipated to be within

limestone bedrock, although the cover is much reduced.

Inter-mixed boulder clay and thick gravel beds may be encountered along the historical

course of tributaries of the Liffey.

The works in this area extend through made ground, gravel deposits and boulder clay

and finish close to the limestone bedrock surface.

At Docklands station variable ground conditions exist which comprise 2m to 5m of made

ground, overlying up to 6m of Estuarine/Alluvial clays, silts, sands and gravel which are

deepest towards the Liffey. These soils are underlain by 8m to 25m of glacial tills,

comprising interbedded boulder clays and glacial sands and gravels deposits, with little

evidence of any glacio-marine clays. The entire area is underlain by Calp limestone. The

station shafts will be excavated through the made ground, Alluvial /estuarine and glacial

soil deposits.

Sand and gravel layer within the boulder clay may hold large quantities of water under a

considerable head or may be in hydraulic continuity with the Liffey and thus be continually

recharged.

105

Extensive ground movements have been observed in response to dewatering of sand layers,

within the boulder clay, on the southern side of the Liffey has previously been observed.

Additional concerns include the confined water pressure within laminated clay strata which

may make the deposit susceptible to wash-out or flows in excavations.

Dewatering at the Docklands station would result in the lowering of groundwater levels in

the immediate vicinity of the excavation.

The running tunnels and station platform/concourse excavations will be predominantly

within glacial soils, with penetration into the limestone bedrock in some areas of the

station/tunnels. From Pearse to South Quays the route is turning back towards the

Liffey and approaching the original Dublin coastline. The ground conditions comprise 2m

to 5m of made ground, overlying 3m to 5m of Alluvial sands and gravels, becoming

Alluvial /estuarine silts/clays close to the Liffey, over 2m to 8m of boulder clays with

glacial sand and gravel lenses, underlain by Calp limestone. Throughout this section the

bored tunnels are within the limestone bedrock.

106

The ground conditions along the Liffey crossing comprise 3.0 to 5.0m

of Estuarine/Alluvial silts/clays, overlying 3m to 6m of boulder clay with lenses of glacial

sands and gravels, underlain by Calp limestone. The bored tunnels are anticipated to pass

through mixed face conditions into limestone bedrock running southwards below the river.

Tunnelling along this section has the capacity to act as a drain as it is being constructed

below the water table.

Mitigation Measures This area has been highlighted as one where groundwater may be employed successfully as

a mitigation measure if necessary but further investigation will be needed to confirm this

during the construction phase.

107

Mitigation measures incorporated in the design of the DART Underground Scheme shall

be implemented according to Table 13.15. Additional geotechnical investigations shall be

performed to establish more reliably ground conditions comprising suitable methods such

as penetration tests and laboratory testing of disturbed and undisturbed soil samples.

Inventory of potentially contaminated soil and groundwater shall be carried out.

If the proposed mitigation measures are implemented the residual impact will be

negligible.

Monitoring shall be carried out during the construction phase to assure that specified

limiting values are not exceeded.

The magnitude of the potential impact in this area will be ‘small adverse’ due to

the presence of boulder clay above the limestone. The magnitude of the predicted impact

will be ‘negligible’ and the significance of the impact will be ‘imperceptible’.

10.8.7 Eastern Portal and Cut and Cover Section

Construction Activities and Potential Impact The works in this area extend through made ground and finish in gravel deposits. The

alignment rises from a depth of approximately 16m below ground level at the Eastern

Portal to tie into the existing at grade tracks.

From the rail connection at East Wall the route descends through retained cut, into cut-and-

cover tunnels and TBM launch chambers and portals from which the bored tunnelling

commences. Variable ground conditions will be encountered in this area comprising 2m to

6m of made ground, overlying up to 14m of Estuarine and Alluvial clays, silts, sands and

gravel. These are underlain by 3m to 25m of glacial till, predominantly glacial sands and

gravels with some boulder clays and possible glaciomarine deposits. The entire area is

underlain by Calp limestone. The scheme is entirely within the soil deposits throughout

this area.

108

Dewatering at the Eastern Portal and the Docklands cut and cover section would result in

the lowering of groundwater levels in the immediate vicinity of the excavation.

In the case of flooding it is important that embankments within the project area can

withstand the increased water pressure. Also, higher groundwater level can reduce the

shear strength of primarily permeable (sandy and silty) soil layers below or adjacent to

embankments.

Mitigation Measures This area has been highlighted as one where recharge to ground may be

employed successfully as a mitigation measure if necessary but further investigation will

be needed to confirm this during the construction phase. Any lowering of the groundwater

level must be monitored with respect to consolidation settlement.

As the area may be affected by flooding it important that (existing and planned)

embankments and other retaining structures are designed and constructed adequately.

Therefore, as part of the mitigation program it is recommended that potentially affected

areas are studied. Such studies should comprise geotechnical field and laboratory

investigations and stability analyses for different loading conditions. The factor of safety

with respect to flooding should be at least 1.2. Where necessary, the stability of

embankment shall be upgraded by supporting berms or other suitable measures.

Mitigation measures incorporated in the design of the DART Underground Scheme shall

be implemented according to Table 13.15. The magnitude of the potential impact in this

area will be ‘moderate adverse’ due to the presence of gravel above the limestone at the

109

Docklands. The magnitude of the predicted impact will be ’small adverse’ and the

significance of the impact will be ’slight’.

Additional geotechnical investigations shall be performed to establish more reliably ground

conditions comprising suitable methods such as penetration tests and laboratory testing of

disturbed and undisturbed soil samples. Inventory of potentially contaminated soil and

groundwater shall be carried out. Monitoring of construction activities is particularly

important due to the extensive, deep excavations necessary in this area.

If the proposed mitigation measures are implemented the residual impact will be

negligible.

Monitoring shall be carried out during the construction phase to assure that specified

limiting values are not exceeded.

10.9 Comments and Recommendations – Geotechnical Impact

The environmental impact due to geotechnical conditions is important and needs to be

considered more thoroughly than in the EIS. Important information is contained in

Appendices to the EIS which should have been part of the main report. The impact due to

geotechnical conditions and construction activities was raised during Module 1 of the Oral

Hearing. The Applicant has responded comprehensively to all questions and provided

extensive information as evidence.

Geotechnical Impact

The Detailed Design stage, to be carried out in compliance with EN 1997 (Eurocode 7: Geotechnical design) shall include, inter alia, the following:

4. (i) The inclusion of the following geotechnical and geological hazards in the geotechnical risk assessment and management scheme:

variable and unexpected ground conditions (made ground and fill)

presence of soft, instable and compressive glacio-marine deposits

sand veins (interbedded as sandy laminations in boulder clay) causing dewatering problems

gravel bed resulting in problematic groundwater inflows into excavation

contamination of ground and groundwater

high levels of methane

artesian or sub-artesian water pressure within glacial gravels

instability of shallow excavations in loose and soft ground (especially silty soils)

settlement of structures and installations in the ground (e.g. utilities) due to tunnel construction

settlement of structures and installations in the ground due to permanent lowering of groundwater

ground movements (vertical and horizontal) of structures due to construction of deep excavations

instability of excavations in soil due to fissuring and/or shearing of glacial clays

instability of excavations in rock due to discontinuities, fissuring rock and weathered rock

variability of rockhead level or unexpected deviations from design assumptions

bedded limestone with interbedded shale resulting in stability problems

dip of limestone bedding

voids in rock formation (potential of karstic features)

high groundwater pressure at tunnel level

110

running sands in boulder clay

difficulties during tunnel boring in mixed face conditions

settlement of loose, granular soil layers induced by blasting vibrations

obstructions to excavations (made ground, boulders etc.)

inflow of water into excavations due to granular horizons

unexpected ground conditions

unexploded ordnance within soft or loose superficial deposits

consequences of archaeological excavations

contamination of groundwater.

5. Consideration of the following construction-related hazards:

Construction of water-tight wall elements due to construction deviations and/or obstructions

Seating of wall elements on blocks or fractured rock layers

Instability of excavations in rock due to unfavourable bedding planes

Leakage of groundwater in soil and fractured rock into deep excavations

TBM work in weathered rock and rock formations with potential faults

TBM work in mixed face conditions (soil-rock interface)

TBM work in deposits with layers and lenses of water-bearing sands

Wear on equipment (tunnelling and excavation) due to presence of abrasive ground

Obstructions in made ground encountered during wall construction (affecting verticality of piles/panels and influencing water tightness)

Chiselling required to penetrate boulders and other obstructions

Draw-down of groundwater adjacent to excavation, due excessive pumping in excavations (leakage through or below secant pile or diaphragm wall)

Difficulties with installation and/or retraction of ground anchors in hard rock

Implementation of ground treatment adjacent to tunnels and/or excavations.

6. Geotechnical investigations to include:

Rotary open hole and core investigations

Cone penetration testing (CPT) and in very soft soils with pore water pressure measurements (CPTU)

Laboratory testing to determine strength and stiffness of soil layers

Piezometer installation

Down-hole Geophysical testing including MASW and/or seismic refraction method logging

Contamination screening.

111

11 Vibration and Groundborne Noise

11.1 General

Vibration and groundborne noise can have potentially major environmental impact during

construction but also operation of the DART Underground. Groundborne noise, which

manifests itself as structural noise, propagates from the ground and into buildings. In the

EIS, vibration problems are discussed in two separate chapters. Chapter 8 deals with Above

Ground Vibrations and Noise and Chapter 9 with Below Ground Noise and Vibration.

However, the effects of vibrations from sources on or below the ground are similar and the

same assessment methods and mitigation measures apply. Therefore, both aspects are

treated in this chapter, which deals with all aspects of ground vibrations and groundborne

(structural) noise from sources on and below the ground surface.

In response to Note 1, attached to the Order of Proceedings of the Oral Hearing, the

Applicant gave a detailed presentation regarding below ground noise and vibration: OH-

No. 35; R. Greer: Below Ground Noise and Vibration and OH-No. 35A: Associated

PowerPoint presentation and evidence given by R. Greer on 15th

December 2010 OH-No. -

[sic]: Methods for predicting groundborne noise and vibration from trains and tunnels.

Different sources of vibration (such as the DART railway lines and the LUAS) exist and

affect buildings and their occupants along the DART Underground alignment. Therefore,

cumulative effects must be considered. However, this report addresses only such issues

which are relevant for the application of a Railway Order for the DART Underground.

11.2 Dynamic Soil Properties of Soil and Rock

Dynamic properties of soil and rock are important information required for the analysis

and prediction of vibrations and groundborne noise. Also the geological and geotechnical

conditions, such as soil layering and groundwater conditions, are of importance for

vibration propagation in the ground. This aspect has been addressed in previous sections of

this report.

The ground investigation programme carried out as part of the EIS involved in addition to

conventional geotechnical investigations also surface geophysical surveys (seismic

refraction and MASW profiling), cf. Chapter 8 and Chapter10. The information provided

in the EIS is valuable but has not been used in the evaluation of ground vibrations and

groundborne noise.

The results of seismic surveys inform about dynamic ground properties (material density,

speed of shear wave and compression wave) and their variation along and perpendicular to

the route. Factual data discussed in Chapter 9 suggest that stratification of soil and rock

layers is significantly more complex along some sections of the tunnel alignment than

assumed in the EIS. This is an important consideration and additional geotechnical

investigations and field trials are needed to calibrate theoretical predictions with field

observations.

112

11.3 Vibration Hazards

11.3.1 Enabling Works

Vibrations can be generated by enabling works, for instance the realignment of railway

tracks. The DART Underground alignment is traversed by railway lines forming part of the

existing freight line network. The existing tracks will have to be realigned in sequence with

the construction of the portal approach structures. Such work has the potential of

generating ground vibration but will, after completion, also reduce vibration levels and

thus improve the environmental conditions.

11.3.2 Construction Phase

Activities which can give rise to ground vibration during the construction phase are

discussed in the EIS in Chapters 8 and 9, respectively. Vibrations can primarily be caused

by excavation of soil and rock and by the movement of construction equipment,

compaction of soil and movement of heavy goods vehicles (HGVs) and supply trains.

If transport of spoils is carried out by rail, this increase of traffic can also lead to higher

ground vibrations.

The most important sources of vibration and groundborne noise during construction are

rock excavation by operation of the TBM and blasting. Each of the two TBMs is expected

to advance at the rate of about 75 to 100m per week, operating 7 days per week. The TBM

will only be experienced above each tunnel for a relatively short period which means that

higher impact thresholds can be applied than during the operational phase of the proposed

scheme. In locations between the two tunnels, this experience will be repeated with a delay

of a few weeks between the two tunnel drives. Because of the finite duration of this effect,

the night-time impact thresholds can be set slightly higher than those for the operation of

the proposed scheme.

Some underground construction within the limestone bedrock, for example the excavation

of cross passages, will be carried out by the use of drill and blast techniques. Other

potentially critical construction activities are chiselling and excavation of rock and

boulders during wall construction (diaphragm panels and bored piles).

11.3.3 Operational Phase

Vibration and groundborne noise can be caused by the operation of railway vehicles.

Groundborne vibration is generated by the dynamic forces at the wheel and rail interface.

The most important parameters are wheel/rail roughness, bogie unsprung mass, suspension

stiffness and speed. The train and track system ‘filters’ these dynamic forces, generally

reducing them, to a degree determined by the track design, causing the tunnel lining to

vibrate and hence causing the surrounding ground to vibrate.

A particular feature of the operation of a newly designed railway is incorporation of

resilient rail support and use of welded rail. By choosing during the design the appropriate

form of track support and provided that an adequate maintenance regime is followed,

significant effects due to vibration and groundborne noise can be avoided.

Vibrations propagate from the source (e.g. the tunnel) through rock and soil formations and

decay with increasing distance. However, soil layering, groundwater conditions and

dynamic properties of rock and soil all affect the direction and intensity of vibration

propagation and attenuation. Depending on the angle of impact and the frequency content

113

of the disturbance, vibrations can also be amplified on the ground surface and/or in

buildings.

Above ground railway traffic and in particular freight trains generate ground vibrations.

As part of the EIS vibration measurements were carried out and it is evident that such

vibrations have occurred historically. This aspect has been taken into account when

considering the cumulative impact.

11.4 Assessment of Ground Vibration

The impact of vibration and groundborne noise was assessed in the EIS based on empirical

evidence (construction phase) as well as on advanced semi-empirical and theoretical

models (operational phase). Both methods have advantages and limitations. Both methods

do not consider sufficiently the importance of dynamic ground properties and how these

affect vibration propagation. Therefore, empirical and theoretical prediction methods need

to be verified and calibrated against measurements and updated based on field trials.

The main sources of vibrations and associated hazards are discussed briefly in the

following sections.

11.4.1 Construction Phase

In Chapter 8 of the EIS, prediction of above ground vibrations from construction activities

is based on experience from vibration measurements reported in British Standard BS5228-

2 (2009) and measurements by consulting company AWN. As noted in Transport Research

Laboratory (TRL) Report 429, ‘Groundborne Vibration from Mechanised Construction

Works’ (2000) conventional construction works will generate substantially lower levels of

noise and vibration than blasting. Hence, they have been assessed qualitatively in the

context of the main underground construction activities.

Surface Construction Activities Excavation of soil by bored (auger) piling does normally generate vibration levels which

are low (soft soils) or medium (stiff soils with boulders). It is difficult to predict levels of

vibrations from pile installation. The most disturbing activities in connection with pile and

wall construction are hammer impact, chiselling, grinding or drilling. Therefore, it is

necessary to monitor ground vibrations during the initial phase of construction and to

develop site-specific correlations for prediction of ground vibrations.

A review of measured vibrations due to piling and vibroflotation/compaction activities has

been compiled from BS5228-2 (2009) and is presented in Volume 3 of the EIS, Table

A8.3.6. However, site-specific vibration predictions were not provided for pile and wall

panel excavation. Instead, prior to construction of piles or diaphragm wall panels close to

vibration-sensitive structures or installations, a detailed method statement including a work

schedule shall be prepared by the Contractor. Prediction of ground vibrations shall be made

in advance and verified by field trials, vibration measurement and by rigorous control

(using threshold and limiting values as outlined in Chapter 5 of this report).

TBM Operation A main sources of concern is tunnel boring and in particular the cutting action of the

shield. The lowest vibrations arise from tunnelling in clays and sands; tunnelling through

boulder clay and weak rock causes an intermediate level of vibration; TBM excavation of

more competent rock generates highest vibration levels. Vibrations are the result of actions

of different tools at the TBM within the ground. The amplitude, frequency and phase of the

114

waves arriving at the ground surface from each tool will be different; thus the peak

vibration is not simply a summation of the peak vibration from each tool.

Reliable assessment of TBM groundborne vibration is essential for developing robust

mitigation strategies. This topic was therefore discussed extensively during the Oral

Hearing where the Applicant provided additional evidence to the information given in the

EIS, explaining methods of analysis and prediction concepts, as described in TRL Report

429 (2000). The methodology is based upon measurements from tunnelling projects with

similar ground conditions. The empirical data include TBMs of a similar size to those

proposed for DART Underground. TRL Report 429 classifies measured vibration data

according to geological conditions (e.g. sands, clays, mixed sand & clays, and rock).

For the DART Underground project, vibration predictions were based on data from TBM

operation in rock assuming worst case conditions (e.g. boulders in boulder clay). This

conservative assumption is reasonable due to the fact that boulders can increase vibration

levels in boulder clay. Such predictions are considered to reflect the upper bound of

groundborne noise and vibration which can be expected.

The Contractor will be required to calibrate vibration predictions by field measurements

obtained for different geological and geotechnical conditions.

In the EIS, vibration predictions in terms of peak particle velocity (PPV) were converted to

Vibration Dose Values (VDVs) to reflect the assessment criteria presented in Chapter 9 of

the EIS. In making the conversion it was assumed that:

the TBM would be excavating for 50% of the day and night-time assessment

periods defined in the EIS (this is a typical worst case assumption for the

proportion of the working day when the TBM could be excavating);

the crest factor (ratio of PPV to the root mean square average vibration magnitude)

for TBM vibration is 4 – this is based on measurements over other TBM drives;

and

the frequency content of the TBM vibration velocity – which needs to be

understood as Vibration Dose Values are calculated from frequency weighted

vibration velocity – was taken form vibration measurements obtained over a

number of TBM drives, whilst the TBM was excavating.

The predicted levels of vibration (peak particle vibration, PPV) and groundborne noise (dB

LAmax,S derived from correlation with PPV ) were implemented using a Geographical

Information System (GIS). The results were applied directly to the alignment shown on the

railway order drawings and the ground model and building information, gathered for the

project as presented in the EIS.

TBM Supply Trains A similar prediction method as for the permanent operation of the DART Underground

Scheme was used, as discussed in a following section (cf. operational phase).

Drilling and Blasting Bulk excavation of cross passages will be by controlled blasting. Drill and blast techniques

may also be used to excavate station platforms, station connecting passages and the

underground elements of station boxes and shafts where these structures are to be

constructed in rock. The primary concern with blasting is to avoid building damage.

The principal source of vibration from blasting is the detonation of explosive charges

underground. Empirical techniques are generally used for predicting the vibration intensity

based on blast data from comparable geological conditions. Such relationships have been

115

developed between instantaneous charge weights and distance from the source. Based on

this information, site-specific correlations can then be developed using vibration

measurements from trial blasting. The intensity of vibration depends also on the location of

the source of vibration in relation to that of affected buildings. Predictions in the EIS are

based on a range of peak particle (PPV) values calculated from equations given in TRRL

Report 53 (1986). These equations were ‘fitted’ to measured vibration data gathered from

similar sites or from trials, a concept which is widely used, cf. British Standard, BS6472-2

(2008): Guide to Evaluation of Human Exposure to Vibration in Buildings, Part 2: Blast

Induced Vibration.

The geological and geotechnical conditions affect ground vibration propagation. Also the

geometry of the project site is important. Blasting directly below a building will generate

different types/frequencies of vibrations than blasting at some lateral distance from the

source. All three components of ground vibrations need to be measured when developing

site-specific attenuation relationships. These factors need to be assessed using blasting

tests.

11.4.2 Operational Phase

The main source of vibration and groundborne noise during the operational phase is trains

passing through tunnels and along railway embankments. Prediction of ground vibration

and groundborne noise is a challenging and complex task which requires competence in a

wide range of technical disciplines. The Applicant has demonstrated during the Oral

Hearing such extensive experience.

Train Traffic Rail systems of all types generate groundborne vibration and/or groundborne noise.

Groundborne vibrations created by train movements propagate through the ground to

surrounding buildings where these can result in vibration of floors, walls and ceilings;

these can also sometimes be heard as low frequency ‘rumbling’ noise (also called

structural-borne noise).

In addition to the DART Underground, existing freight train traffic generates vibrations.

The Applicant endeavours to improve the railway tracks and embankment stiffness of

existing railway lines. It is difficult to predict quantitatively the benefit of such mitigation

measures without vibration measurements. However, this improvement effort will without

doubt have a beneficial effect on the environment.

In the East Wall area, the existing freight line is elevated and the DART line will be inside

that line in a cut. It can be assumed that the predicted ground vibrations from the DART

Underground will be significantly lower in buildings at the ground surface than from

existing freight train operation. This is due to the type of track and the location of the

DART Underground track and the dynamic characteristics of the operating trains.

An assessment of likely ground vibrations and response of structures at different distances

from the source is required to predict environmental impact. This information is missing in

the EIS. There are no national or international standards that set out calculation

methodologies for groundborne noise and vibration from the operation of railways.

However, ISO 14837-1: 2005, provides guidance on the calculation and assessment of

railway groundborne noise and vibration.

Modelling of the likely intensity of vibration and groundborne noise from the operation of

train vehicles has been carried out using robust design and operational parameters for

vehicles. Assessment of vibration and groundborne noise from railway traffic must also

116

include mitigation measures which shall be included in the design and operation (including

maintenance) of the system.

Train Traffic in Tunnels Groundborne noise impact of the proposed DART Underground operation has been

calculated using the semi-empirical methods developed and validated initially for the

design and construction of High Speed 1 (HS1) in the UK, formerly known as Channel

Tunnel Rail Link (CTRL). The used method is primarily empirical but takes account of

many key parameters, including train design, train speed, track design, tunnel design,

tunnel depth, ground conditions, receiving building foundations and receiving building

type. A numerical method is used to calculate the vibration ‘filtering effect’ of the track

system including the rail design. This enables effective design development of the primary

form of groundborne noise mitigation: the track system. The semi-empirical procedures

were validated against extensive measurements of vibrations from high-speed, intercity,

and mass transit railways (in accordance with ISO 14837-1).

It is noted that the present model does not include the effect of wave propagation through

geological formations (soil and rock layers, groundwater). Therefore, it is essential that the

model is calibrated against vibration measurements from different locations along the

DART Underground.

11.5 Impact Criteria

11.5.1 General

In order to be able to assess the environmental impact from different vibration sources on

receptors along the DART Underground route it is necessary to establish limits for

vibrations and groundborne noise.

In the absence of international standards regarding ground vibrations and their impact on

buildings and humans, in the EIS impact criteria (limiting values) have been based on the

following British Standards (BS):

BS 5228-2:2009. “Code of practice for noise and vibration control on construction

and open sites – Part 2: Vibration”. Part 2 informs about vibrations caused by

above ground surface construction works, including rock breaking, piling etc.

BS 6472-1:2008. “Guide to evaluation of human exposure to vibration in buildings

Part 1: Vibration sources other than blasting” gives detailed guidance on human

response to vibration in buildings.

BS 6472-2: 2008. “Guide to evaluation of human exposure to vibration in

buildings Part 2: Blast-induced vibration” gives detailed guidance on human

response to blasting.

BS 7385-1:1990. “Evaluation and measurement for vibration in buildings. Guide

for measurement of vibrations and evaluation of their effects on buildings” covers

the measurement and evaluation of structural vibration.

BS 7385-2: 1993. “Evaluation and measurement for vibration in buildings — Part

2: Guide to damage levels from groundborne vibration”. Part 2 gives guidance on

damage levels from groundborne vibration.

Guidance with regard to assessment of vibration and groundborne noise from railway

traffice can also be found in the ISO standard (ISO 14837-1:2005, IDT): “Mechanical

vibration – Groundborne noise and vibration arising from rail systems – Part 1: General

guidance”. For the evaluation of vibration in buildings with respect to comfort and

117

annoyance, reference is made to ISO 2631-2 Second edition 2003-04-01: Mechanical

vibration and shock — Evaluation of human exposure to wholebody vibration — Part

2: Vibration in buildings (1 Hz to 80 Hz).

These standards provide widely accepted criteria (best practice) for evaluating the effect of

vibrations and groundborne noise and are acceptable for the DART Underground Scheme.

11.5.2 Human Response

Standards For the evaluation of vibration effects in buildings with respect to comfort and annoyance,

overall “weighted values” of vibration are used. The value obtained with the appropriate

frequency weighting characterizes the place or site within the building where people may

be present, by giving an indication of the suitability of that place, cf. ISO 2631-2 Second

(2003). Human response to vibration varies quantitatively according to the direction in

which it is perceived. Generally, vertical vibrations are more perceptible than horizontal

vibrations, although at very low frequencies this tendency is reversed. Vibrations can cause

structure‑borne noise which can be an additional irritant to occupants of buildings.

BS 6472 provides guidance on human response to vibration in buildings and suggests

vibration levels at which minimal adverse comment is likely to be provoked from

occupants. Guidance on measurement of vibration for assessing human disturbance is

given in BS 6472. BS 7385‑1 (1993) covers the measurement and evaluation of structural

vibration.

Vibration Dose Value (VDV) For estimation of vibration effects on humans the British Standard uses the Vibration Dose

Value (VDV). BS 6472-1:2008 offers guidance on the evaluation of vibration with respect

to human response not available in ISO 2631-2:2003 and on how people inside buildings

respond to vibration.

Use of the estimated VDV is not recommended for vibration with sharply time-varying

characteristics or shocks. The VDV can be used to estimate the probability of

adverse comment which might be expected from human beings experiencing vibration in

buildings. Consideration is given to the time of day and use made of occupied space in

buildings, whether residential, office or workshop. When the appropriately weighted

vibration measurements or predictions have been used to derive the VDV for either 16 h

(daytime) or 8 h (night-time) at the relevant places of interest, their significance in terms of

human response for people in those places can be derived from Table 1, BS 6472-1:2008.

118

The VDV value can be used for assessing impact from train traffic in tunnels during

construction and operation. The judgement made is of the probability that the determined

vibration dose might result in adverse comment by those who experience it. The following

table offers guidance with respect to the probability of adverse comment from occupants in

residential buildings.

The EIS proposes a modified impact assessment concept compared to the above Table 1

which takes into consideration the existing level of vibration (“change criteria”).

A comparison of the two tables leads to the following conclusion. The impact classification

category “Slight” in the EIS corresponds to a low probability of adverse comments.

However, impact classiffication category “Moderate” is likely to cause adverse comment

by occupants of buildings. Therefore, an effort shall be made by the Contractor not to

exceed impact classification “Slight” with exception of impacts lasting only short periods.

Considering that areas at Inchicor and East Wall are already exposed to train traffic it is not

recommended to use the “change criteria” proposed in the EIS.

Peak Particle Velocity Human beings are known to be very sensitive to vibration, the threshold of perception

being typically in the PPV range of 0.1mm/s to 0.3mm/s. Vibrations above these values

can disturb, startle, cause annoyance or interfere with work activities. At higher levels they

can be unpleasant or even painful. Whilst the assessment of the response to vibration in BS

6472 is based on the VDV, for construction it is considered more appropriate to provide

guidance in terms of the PPV, since this parameter is likely to be more routinely measured

based upon the more usual concern over potential building damage. Furthermore, since

many of the empirical vibration predictors yield a result in terms of PPV, it is necessary to

understand what the consequences might be of any predicted levels in terms of human

perception and disturbance. Some guidance regarding the effect of PPV in mm/s is given

in BS 5228-2,Table B.1.

119

BS 6472-2 (2008) deals with periodic blasting within range of inhabited buildings: the

guidance is a formalization of established, widely recognized techniques common in

the industry. Blast-induced vibration is highly variable and vibration magnitudes should

not be exceeded by more than 10% of the blasts. No blast should give rise to vibration

magnitudes that exceed the satisfactory level by more than 50%. Ideally the percentages

should be calculated as a “running average” with as large a base of representative data as

is reasonable, which would typically extend over a three month period. Due to data scatter,

working to a 90% confidence limit value means, in practice, that blasts need to be designed

to ensure that the average level of vibration is approximately half of the specified

limit. Maximum levels of acceptable vibrations expressed in PPV are given in the below

Table, cf. BS 6472-2.

120

Column 3 of the above Table 1 details the maximum satisfactory magnitudes for vibration

measured on a firm surface outside buildings with respect to human response. For blast

vibration occurring up to three times per day the generally accepted maximum satisfactory

magnitude for residential premises is a PPV of 6.0 mm/s. A transfer function of up to 1.3

has been found to be sufficient to determine likely indoor values. Hence the equivalent

indoor satisfactory magnitude would be between 8.0 mm/s.

Groundborne Noise Groundborne (or structure-borne) noise should be measured at that location in the room

where its effect is considered to be most disturbing. It might often be masked by ambient

noise from other sources, making its unambiguous determination difficult or impossible.

The levels of vibration generated inside buildings close to rail systems are such that in

some situations they give rise to (in order of magnitude) annoyance, discomfort, activity

disturbance and, at extreme levels, might in rare cases affect health. Current common

practice is to measure groundborne noise using the maximum A-weighted level and “slow”

response. The attenuation of low frequencies imposed by the A-weighting and the

wide tolerance allowed at low frequencies by the A-weighting specification need to be

remembered where this is adopted. Any A-weighted measurement should be

complemented by unweighted one-third octave band spectra extending down to 20 Hz, cf.

ISO 14837-1.

In the USA, typical assessment criteria used for new railway projects are stated in the US

Department of Transportation guidance on vibration impact assessments, (1995). Note that

these are based on the maximum level, LAmax,S rather than the long-term averaged level,

LAeq. The below table summarizes the recommendations with regard to groundborne noise

for different types of land use, to be used for railway projects in the USA; US Department

of Transportation – Federal Transit Administration; Transit Noise and Vibration Impact

Assessment, (1995).

The recommendation is that for residences and buildings where people normally sleep,

groundborne noise should not exceed 35 dB LAmax,S. In theatres and concert halls with high

acoustic requirements, groundborne noise should not exceed 25 dB LAmax,S. As will be

discussed below, the criteria given in the above table are also influenced by the frequency

content of the disturbance.

Appendix 5 of this report “Inventory of Vibration and Groundborne Noise Guidelines and

Standards for Railway Tunnels” is based on data compiled by the author for the application

121

for a Railway Order for the Metro North. It demonstrates that in many countries, vibrations

from operational train traffic affecting residential areas is not permitted to exceed 35 dB

LAmax,S night-time.

Theatres and Concert Halls Noise and vibration impact can occur during the construction as well as the operation of

the DART Underground Scheme. Some buildings, such as concert halls, TV and recording

studios and theatres, can be (but not necessarily are) very sensitive to vibration and noise.

Sensitivity to noise and vibration depends on the structural conditions, the acoustic

properties of the auditorium and the type of performance. Because of the potential

sensitivity of such buildings, they usually warrant special attention.

The enforcement of low noise levels will be critical to the uninterrupted operation of

sensitive receptors such as theatres. During the construction phase, short-term, temporary

significant adverse effects have been identified in the EIS at the following non-residential

receptors:

Marconi House broadcast facilities (approx. 15 days per TBM drive).

The Gaiety Theatre (approx. 20 days per TBM drive).

Grand Canal Theatre (approx. 20 days per TBM drive).

The Grand Canal Theatre (GCT) accommodates world-class performances of drama and

classical music. The current back-ground noise conditions in the auditorium are of high

standard and create a very low noise environment. Also the other two premises are deemed

to be sensitive to groundborne noise. In the EIS, Chapter 9.5.1.2 the Applicant propose

with respect to operation of the TBM the following mitigation measure:

The Contractor will be obliged to implement a mitigation strategy (at either source or receptor) for the significant adverse effect on residential properties at Inchicore; Marconi House; Gaiety Theatre; and Grand Canal Theatre, in order to reduce or remove, in so far as is reasonably practicable

2, the

adverse groundborne noise effect at night time for residential properties and during critical operational times (e.g. performance broadcast and critical rehearsal times) for non-residential property.

In the EIS, Chapter 9.5.1.4 the Applicant proposed with respect to blasting the following

mitigation measure:

The Contractor will be obliged to implement a mitigation strategy (at either source or receptor) for Marconi House, Gaiety Theatre and Grand Canal Theatre in order to reduce or remove, in so far as is reasonably practicable, the adverse groundborne noise effect during critical operational times (e.g. performance broadcast and critical rehearsal times).

In the EIS, Table 9.11 the Applicant summarises temporary residual groundborne noise

impacts and effects on non-residential premises from construction activities.

The Significance Criteria proposed for the two theatres is 25 dB LAmax,S and for Marconi

House 30 dB LAmax,S, respectively.

In the EIS, Table 9.13 the Applicant predicted for the operational phase and sensitive non-

residential receptors groundborne vibration levels and proposed Significance Criteria.

2 Emphasis added by the author of this report.

122

The Significance Criteria proposed for the two theatres is 25 dB LAmax,S and for Marconi

House 30 dB LAmax,S, respectively.

In the EIS, Chapters 8 and 9 the propose mitigation measures were in several instances

qualified by the statement: “in so far as is reasonably practicable”. The contractor would

be given the liberty to decide whether to adhere strictly to limiting values imposed by a

Railway Order. As has been pointed out in previous sections of this report, such a

statement is not acceptable in an EIS where adherence to clearly stated and enforceable

limiting values is required.

It is also noted that for Marconi House, the groundborne noise level proposed in the EIS is

30 dB LAmax,S which is higher than the value recommended by the US Department of

Transportation, which is adhered to otherwise in the EIS. It is recommended that the

Applicant engages in negotiations with the owner/operator of Marconi House to reach an

agreement regarding acceptable levels. If no such agreement can be reached it is proposed

that recommendations by the US Department of Transport are adopted (25 dB LAmax,S).

Observations and Submissions at Oral Hearing Vibration and groundborne noise was discussed extensively by Observers during the Oral

Hearing. Most concerns, which have been addressed in Appendix 4 to this report, can be

123

taken into account by applying the restrictions recommended in this report. Of particular

relevance is the long-term effect of groundborne noise during the operational phase of the

DART Underground.

GCT objected to the method of assessing groundborne noise in the EIS, Chapter 9 and to

the proposed limiting values. Reference was made during the Oral Hearing by GCT to an

acoustic tests carried out at the GCT to assess the significance of the proposed criteria. The

following observations submitted:

OH-No. 175, M. Adamson: Grand Canal Theatre Company.

OH-No. 175A, John Spain Associates: Planning.

OH-No. 175B, Slides

OH-No. 175C, Civil Engineering Aspects, O’Connor Sutton Cronin.

OH-No. 175D, Noise and Vibration, Marshall Day Acoustics.

The main concern of GCT was whether the significance criterion proposed in the EIS (25

dB LAmax,S) was sufficient to prevent interference with certain performances and other

related activities in the GCT. The matter of building acoustics and the definition of limiting

values is complex as such criteria are dependent on the frequency content of the

disturbance. The response of buildings and building elements can be highly sensitive to

excitation at different frequencies. For example, vibrations with different frequency spectra

can meet the same limiting value when expressed as a single dB-value. Thus the frequency

distribution of the disturbance entering the foundation of a building is an important

parameter. This aspect was discussed during the Oral Hearing in great detail between and

with the Applicant and the Observer, in order to clarify the assumptions made in their

evidence and submissions.

In Evidence given by the Applicant (OH-No. 35, R. Greer: Below Ground Noise and

Vibration) the following clarification was given:

To further refine the mitigation commitment in the EIS, for the for the [sic] different noise and vibration sources (e.g. TBMs, TBM supply trains, and controlled blasting) the contractor will be required to:

Confirm with the venue the indicative timing of the below ground works that could cause noise or vibration in the venue at least six months in advance;

Liaise regularly with the venue operators to confirm the look ahead programme of noise / vibration sensitive activities within the venue;

Confirm the likely levels of below ground noise and vibration to be generated by the contractor’s proposals as part of relevant Noise and Vibration Control Plan (NVCP) – refer to section 9.5.1.1 of the EIS – that will demonstrate that the proposed works will comply with the relevant EIS criteria and which will also examine and bring forward any reasonable and practicable means to further minimise the noise and vibration forecast at the venues;

Ensure, by monitoring, that the noise generated by any works undertaken during sensitive activities in the venues is less than the relevant criteria set out in Tables 9.2, 9.3, 9.4 and 9.5 of the EIS during sensitive activities within the venue;

For the theatres, schedule and stop the relevant construction activities during noise / vibration sensitive activities where the above criteria cannot be met and ensure there is no significant increase in settlement arising from stoppage (this would involve scheduling works so that maintenance or low intensity works are completed during the performance period and thereafter normal works would recommence outside of times when sensitive activities within the theatres take place); and

for Marconi House broadcasting facilities enact the contingency plan being developed by the operators during construction activities where the agreed criteria cannot be met (the approach to Marconi House differs from the theatres because the facility includes noise

124

and vibration mitigation within the design of parts of the facility that is likely to protect internal noise levels during the works).

In response to the assessment criteria given in the EIS, GCT and their experts proposed

significantly more restrictive “ideal” criterion that they felt would cause no disturbance, cf.

OH-No. 174B, GCT, represented by Marshall Day Acoustics: Grand Canal Square - Noise

and Vibration. Subsequently, GCT experts offered a “compromise” criterion at which

noise and groundborne noise levels would still be acceptable to GCT. For technical details

reference is made to the submissions by GCT (OH-No. 203, Grand Canal Theatre Noise &

Vibration Test Proposal - Grand Canal Theatre; and OH-No. 203A, Document detailing

Qualifications & Experience of Sound Engineer conducting tests - Listening Tests at GCT).

The Applicant and GCT agreed to carry out at the GCT - for the benefit of ABP Experts - a

series of Listening Tests under controlled conditions. Separate test programs were

elaborated by the Applicant and GCT; for details reference is made to the following

documents:

OH-No. 202, C.I.E.: Grand Canal Theatre: Noise & Vibration Test Proposal.

OH-No. 203, Grand Canal Theatre: Grand Canal Theatre Noise & Vibration Test

Proposal.

The scope, implementation and technical details of the two sets of acoustic tests are not

repeated in this report and reference is made to evidence presented at the Oral Hearing.

It was agreed that both parties were allowed to attend, record and analyse both Listening

Tests. In addition, in order to assure that the requirements with respect to planning,

recording and evaluation of the tests met highest standards, two independent experts

chosen by the Applicant and GCT, respectively, attended, inspected, evaluated and

commented on the test results.

The Listening Test was undertaken on 31th

March 2011 and attended by ABP Experts to

experience different scenarios of the type and intensity of noise (simulated groundborne

noise) which can be expected from the operation of DART Underground. In addition to

representatives of the Applicant and GCT, the Applicant also invited 51 “uninformed”

attendants to experience the (simulated) performance of Shakespeare’s Hamlet. After the

performance, the 51 members were asked to reply to a written questionnaire, assessing

ambience, background and noise during the performance and to remark on any noted

disturbance. The results of the Listening Tests were reported to the Oral Hearing on 7th

April 2011:

Report submitted by Arup on behalf of CIE DART Underground: OH-No. 223;

Demonstration of Train Noise at Grand Canal Theatre - CIE.

Report submitted by Peutz Consulting on behalf of Arup: Grand Canal Theatre:

OH-No. 223A; Peutz Review on the methodology of the Noise Test.

Arup: OH-No. 223B;Figure 16: Comparison of spectral content and

Arup: OH-No.223C; Millward Brown Lansdowne Focus group.

Report submitted by Marshall Day on behalf of Gran Canal Theatre: OH-No. 224;

Marshall Day Acoustics Report Grand Canal Theatre – Listening tests.

OH-No. 224B Memo Marshall Day: Response to questions raised by Fred Walsh.

Report submitted by Engineered Acoustic Design on behalf of Marshall Day: OH-

No.224A; Engineered Acoustic Designs, Report of Witnessed Listening Tests.

For details on the acoustic measurements, analyses and tests evaluation, reference is made

to the above listed documents submitted to ABP by GCT and the Applicant.

125

Based on the listening tests, ABP experts carried out a careful evaluation of the results also

considering the different types of vibration scenario that were experienced during the

Listening Test. It is recommended that the criteria proposed by the Applicant – and

including the clarifications and assurances given during the Oral Hearing, shall be the

upper limit of permissible vibrations and ground-borne noise. Extensive field tests shall be

carried out during the construction of the DART Underground below the GCT to further

investigate vibration amplification and response from realistic sources such as TBM boring

and operation of supply trains. Further, it is recommended to carry out a field trial of the

track design to verify that the predicted levels of ground vibrations and ground-borne noise

are not exceeded.

The Applicant and GCT are commended for their efforts in competent planning and

professional implementation of the Listening Tests. Within very short time, the results of

comprehensive measurements were analysed and evaluated and submitted in written

format prior to their presentation at the Oral Hearing. The Listening Tests contributed

significantly to a better understanding of this problematic technical issue.

11.5.3 Utilities

The following criteria taken from BS52288-2 are proposed and acceptable for utilities:

Intermittent and transient vibrations: PPVmax: 30mm/s

Continuous vibrations: PPVmax: 15mm/s

11.5.4 Vibration-sensitive Equipment and Processes

There are no generally applicable standards for assessing the potential impact of vibration

on sensitive equipment or processes. For each receptor which has been identified within

the area of influence (200m) a specific assessment shall be made, taking into account the

sensitivity of each receptor.

A submission was made by Masterlab’s (OH-No. 96, A. Foley and Masterlabs Ltd) stating

that the planned DART Underground would severely interfere with their recording and

mastering business. The studio comprises an interior structure inside an exterior shell and

contact between the two structures is minimised in order to limit transmission of outside

vibrations. The present activities are already affected by vibrations from the existing

railway traffic and sensitive mastering work must be interrupted when freight trains pass. It

is claimed that the additional DART Underground traffic would have fatal impact on

Masterlab’s business.

The upgrading of existing freight lines with welded rail and improved track conditions

shall reduce the present level of ground vibrations. Traffic from operation of the DART

Underground is not considered to worsen the existing vibration level as the DART will

operate in a cut and at a greater distance than the existing freight lines.

The Trinity Bioscience Institute houses vibration-sensitive equipment as well as animals,

cf. S-No. 144, Trinity College Dublin (Paul Mangan); 2010-08-18, 104-105. Blasting and

other construction work will be carried out which can potentially affect the institute.

The EIS has identified the institute as a potentially vibration-sensitive receptor. The

predicted levels of groundborne noise are, however, low (unmitigated: 25 -29 dB LAmax,S

during construction and 20 - 24 dB LAmax,S ). Due to the importance of the building and the

activities it houses, it is necessary to confirm by vibration tests and monitoring that the

predicted levels will not be exceeded.

126

11.5.5 Building Damage

The risk of vibration-induced damage from the DART Underground is very low but shall

be evaluated taking into account the magnitude, frequency and duration of recorded

vibration together with consideration of the type of building which is exposed. BS 5228-2

establishes limits for transient vibration, above which cosmetic damage could occur. These

are given numerically in below shown Table B.2 in terms of the component PPV. The PPV

values represent the best judgement currently available and may be used for both vertical

and horizontal vibration, provided that they are correctly weighted. In the lower frequency

region where strains associated with a given vibration velocity magnitude are higher, the

guide values for the building types corresponding to line 2 are reduced. Below a frequency

of 4 Hz where high displacement is associated with relatively low component PPV a

maximum displacement of 0.6 mm (zero to peak) should be used.

The guide values in BS 5228-2, Table B.2 relate predominantly to transient vibrations

which do not experience resonant responses in structures, and to low-rise buildings. Where

the dynamic loading caused by continuous vibration is such as to give rise to dynamic

magnification due to resonance, especially at the lower frequencies where lower guide

values apply, then the guide values in Table B.2 need to be reduced by 50%. BS 5228-2

recommends also that important buildings which are difficult to repair might require

special consideration on a case-by-case basis.

The EIS proposes the following values of maximum PPV for two types of structures which

are in agreement with BS 5228-2 and acceptable.

11.6 Proposed Mitigation Measures in EIS

The EIS, Chapters 8.6 (Above Ground Vibration) and Chapter 9.5 (Below Ground Noise

and Vibration) outline the following mitigation measures, respectively:

127

Above Ground Vibration

8.6 Mitigation Measures

The key mitigation measures applied to vibration sources for DART Underground are the range of criteria which have been set in order to prevent any significant impacts. The mitigation measures set out in this section are those recommended in order to achieve these criteria based on the proposed works and operational programme. Should the Contractor construct or operate the proposed scheme using alternative means, identical criteria will have to be met.

8.6.1 General

The proposed scheme has, where possible, designed a construction programme to avoid and reduce environmental impacts as is best practicable. In terms of above ground noise and vibration, the construction methodology proposed at station and shaft constructions sites has an inherent mitigation measure incorporated into the design through partially enclosing excavation and construction works beneath the roof slabs.

Mitigation measures set out in this Section are those additional measures which are deemed necessary to further reduce identified negative impacts. The impact assessment conducted for the construction phase has highlighted the requirement for mitigation to be implemented at the majority of construction sites in order to reduce the noise impact to nearby noise sensitive areas.

The Contractor will compile the following plans:

The Noise and Vibration Management Plan (NVMP) which will deal specifically with management processes and strategic (route wide) mitigation measures to remove or reduce significant noise and vibration effects. As part of the NVMP the Contractor will prepare and agree with the contractor for Dublin Metro North a common management process to ensure that cumulative noise and vibration effects from DART Underground and Dublin Metro North sources do not exceed the construction noise and vibration thresholds. Cumulative noise and vibration effects from different DART Underground sources shall also be addressed as part of the NVMP. The Plan will also define noise and vibration monitoring and reporting this will form part of the Environmental Management Plan. The mitigation measures detailed below will form part of the Noise and Vibration Management Plan.

The Noise and Vibration Control Plans which will be based on and include method statements for each area of the works, the associated specific measures (to be at least those from the NVMP) to minimise noise and vibration in so far as is reasonably practicable for the specific works covered by each plan and a detailed appraisal of the resultant construction noise and vibration generated.

Below Ground Noise and Vibration

Mitigation measures with respect to below ground noise and vibration are described as

follows:

9.5 Mitigation Measures

The design development of the base scheme and its alignment has included the need to reduce environmental impact in so far as is reasonably practicable.

The following sections set out the mitigation proposed to reduce or remove the significant adverse effects identified for the base scheme as reported in Section 9.4.

9.5.1 Construction

9.5.1.1 General

(same as 8.6.1)

…..

Prior to the commencement of any works on site, the Contractor will implement a mitigation strategy (at source – for all DART Underground noise and vibration sources - or receptor) at Marconi House, Gaiety Theatre and Grand Canal Theatre in order to reduce or remove, in so far as is reasonably practicable, the adverse groundborne noise effects from DART Underground works

128

during critical operational times (e.g. performance, broadcast and critical rehearsal times).

9.5.1.2 TBMs

The Contractor will be obliged to implement a mitigation strategy (at either source or receptor) for the significant adverse effect on residential properties at Inchicore; Marconi House; Gaiety Theatre; and Grand Canal Theatre, in order to reduce or remove, in so far as is reasonably practicable , the adverse groundborne noise effect at night time for residential properties and during critical operational times (e.g. performance broadcast and critical rehearsal times) for non-residential property.

As discussed previously, it is not acceptable to limit the obligation and responsibility of the

contractor by introducing the vague phrase “in so far as is reasonably practicable”.

11.7 Comments and Recommendation – Vibration and Groundborne Noise

EIS Chapters 8 and 9 assesses the impact of vibration and groundborne noise arising from

the construction and operation of the proposed scheme. The concepts used to assess ground

vibrations from different vibration source during construction and operation were

discussed extensively during the Oral Hearing. In response to Note 1, attached to An Board

Pleanála’s Oral Hearing – Order of Proceedings, the Applicant’s experts prepared detailed

and convincing presentations on prediction of groundborne noise and vibration. However,

the EIS does not address in detail the need for additional ground investigations during

construction and operation. Also the need of field testing and trials during the construction

phase must be emphasised.

The mitigation measures proposed in the EIS are otherwise considered adequate and shall

be applied with the recommended modifications. The “Noise and Vibration Management

Plan” (NVMP) and the “Noise and Vibration Control Plans” (NVCPs) are essential

elements of the environmental risk assessment program. These will be supplemented by an

extensive monitoring scheme as outlined above. Vibration measurements shall be made

during construction and operation of the DART Underground. In addition, full-scale tests

are required at sensitive receptors to verify that predicted values are not exceeded.

I. General Recommendations

4. Limiting values stated for vibration and groundborne noise shall be based - without modification - on relevant British Standards, where applicable. The application of “change base criteria” shall not apply.

5. As part of the Noise and Vibration Monitoring (NMV) program, the contractor shall be required to work out specific method statements for construction work which can give rise to significant ground vibrations. Field trials and tests shall be carried out by the contractor in advance of critical activities. Vibration levels shall be predicted and compared with measured values.

6. Vibration measurements shall be carried out on the ground and inside of vibration-sensitive buildings. A detailed field measurement program shall be worked out by experienced specialists. All tests shall be carried out in cooperation with, or under supervisions by, the engineering team of the Applicant and independent experts.

II. Impact Criteria - Construction Phase

3. Vibration impact on humans is based on BS 6472-1:2008 Table 1. VDV levels proposed in the EIS are acceptable in principle as upper limits for the construction phase. During night-time, VDV levels shall not exceed: < 0.2 m.s-1.75 having low probability of adverse comment. (This can be accomplished in many cases by field trials and modification of

129

working methods with potential of causing disturbance.) Higher VDV values shall be accepted only for a short duration (less than 10 minutes) when unexpectedly difficult ground conditions are encountered.

4. When measured vibration levels from TBM works exceed 49 dB LAmax,S during night time, occupants of buildings shall be offered without delay alternative accommodation (or, if agreeable to the contractor and affected party, other form of mitigation). The threshold level of vibration monitoring during TBM operation night-time shall be 45 dB LAmax,S S. When groundborne noise is predicted to exceed 45 dB dB LAmax,S S during night time the contractor shall in cooperation with the Applicant work out an action plan to minimize ground vibrations. An attempt shall be made to modify the construction processes and phasing of work with the aim of reducing groundborne noise to values below 45 dB LAmax,S S.

III. Impact Criteria - Operational Phase

4. Groundborne noise during night-time in residential areas shall not exceed 35 dBA.

5. Vibration levels shall not exceed VDV belonging to the category of low probability of adverse comments: 0.2 to 0.4 m.s-1.75 (day-time) and 0.1 to 0.2 m.s -1.75 (night-time).

6. For Theatres and Marconi House: limits of vibrations and of groundborne noise proposed in the EIS shall be modified according to the evidence given by the Applicant during the Oral Hearing. The EIS criterion of 25 dB LAmax,S shall be imposed as an absolute and upper limit according to the frequency distribution defined by the Applicant. The 25 dB LAmax,S criterion applies to 100% of trains. Field trials shall be carried out after construction of the tunnels to verify vibration propagation to sensitive receptors. An effort should be made by the Contractor to design the railway track to achieve a lower value than 25 dB LAmax,S.