35
MURRAY-DARLING BASIN AUTHORITY River Murray System Annual Operating Plan (Public Summary) End February 2011 Review 2010-11 Water Year 1 June 2010 – 31 May 2011

MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

MURRAY-DARLING BASIN AUTHORITY

River Murray SystemAnnual Operating Plan (Public Summary) End February 2011 Review

2010-11 Water Year 1 June 2010 – 31 May 2011

Page 2: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)i

MURRAY-DARLING BASIN AUTHORITY

River Murray SystemAnnual Operating Plan (Public Summary) End February 2011 Review

2010-11 Water Year 1 June 2010 – 31 May 2011

Page 3: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Published by Murray-Darling Basin Authority

Postal Address GPO Box 1801, Canberra ACT 2601

Office location Level 4, 51 Allara Street, Canberra City

Australian Capital Territory

Telephone (02) 6279 0100 international + 61 2 6279 0100

Facsimile (02) 6248 8053 international + 61 2 6248 8053

E-Mail [email protected]

Internet http://www.mdba.gov.au

For further information contact the Murray-Darling Basin Authority office on

(02) 6279 0100

This report may be cited as: River Murray System Annual Operating Plan 2011-12 (Public Summary)

February Review

MDBA Publication No. 146/11

ISBN 978-1-921914-09-6

© Copyright Murray-Darling Basin Authority (MDBA), on behalf of the Commonwealth of Australia 2009.

This work is copyright. With the exception of photographs, any logo or emblem, and any trademarks,

the work may be stored, retrieved and reproduced in whole or in part, provided that it is not sold

or used in any way for commercial benefit, and that the source and author of any material used is

acknowledged.

Apart from any use permitted under the Copyright Act 1968 or above, no part of this work may be

reproduced by any process without prior written permission from the Commonwealth. Requests

and inquiries concerning reproduction and rights should be addressed to the Commonwealth

Copyright Administration, Attorney General’s Department, National Circuit, Barton ACT 2600 or

posted at http://www.ag.gov.au/cca.

The views, opinions and conclusions expressed by the authors in this publication are not necessarily

those of the MDBA or the Commonwealth. To the extent permitted by law, the MDBA and the

Commonwealth excludes all liability to any person for any consequences, including but not limited to

all losses, damages, costs, expenses and any other compensation, arising directly or indirectly from

using this report (in part or in whole) and any information or material contained within it.

Australian Government Departments and Agencies are required by the Disability Discrimination Act

1992 (Cth) to ensure that information and services can be accessed by people with disabilities. If you

encounter accessibility difficulties or the information you require is in a format that you cannot access,

please contact us.

Front cover image: Photographer: David Kleinert - Flooded Murray River, Barmah, 2010

Page 4: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)iii

Contents

1 IntroduCtIon 1

2 systemstatuson28February2011 2

3 summaryofwatersharingandsignificantoperations 6

3.1 River Murray System scenarios for 2010-11 6

3.2 Comparison with River Murray System scenarios for 2010-11 9

4 detailedriverMurraysystemoperationsfor2010-11 16

4.1 River and storage losses 16

4.2 Changes to minimum flow rates 17

4.3 Weir pool level manipulation 17

4.4 Delivering environmental water 18

4.5 Actions to minimise impacts of Blackwater 19

4.6 Dartmouth Reservoir 20

4.7 Hume Reservoir and flows at Doctors Point 22

4.8 Lake Mulwala and the Barmah Choke 24

4.9 Lake Victoria 25

4.10 Menindee Lakes 26

4.11 Flow to South Australia 28

4.12 Lower Lakes and Barrage operation in South Australia 29

Page 5: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)iv

LIstoFFIgures

Figure 1 Rainfall Deciles – 9 months 1 June 2010 to 28 February 2011 2

Figure 2 River Murray System inflows (excluding inflows to Menindee and Snowy Mountains Scheme) - recent years and long-term averages 3

Figure 3 Inflows to Menindee Lakes in recent years and long-term averages 4

Figure 4 MDBA active storage June 2000 to Jan 2011 5

Figure 5 Ranked Historical System Inflows showing years similar to Scenarios 7

Figure 6 River Murray System conveyance losses upstream of the SA border 16

Figure 7 River Murray System storage evaporative losses 17

Figure 8 Impact of environmental flow releases on flow rates at Yarrawonga Weir 18

Figure 9 Dartmouth Reservoir storage outlook 21

Figure 10 Dartmouth Reservoir release outlook 21

Figure 11 Hume Reservoir storage outlook 23

Figure 12 Hume Reservoir release outlook – flows at Doctors Point 23

Figure 13 Yarrawonga Weir release outlook 24

Figure 14 Lake Victoria storage outlook 25

Figure 15 Forecast Menindee Inflows 27

Figure 16 Menindee Lakes outlook assuming no further inflows after July 2010 27

Figure 17 Forecast flows to SA 28

Figure 18 Lower Lake forecast levels 29

LIstoFtabLes

Table 1 Storage in MDBA major reservoirs on 28 February 2011 4

Table 2 Details of each scenario in 2010-11 Operating Plan (GL) 8

Table 3 Summary of Water Availability under each scenario 10

Table 4 Summary of significant river operations under each scenario 12

Table 5 Summary of significant environmental operations under scenarios 14

Page 6: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)1

1 IntroduCtIon

The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was released in June 2010 and provided context and descriptions of how the River Murray System (the System) may have been operated under a number of assumed scenarios.

This document provides a review of the Operating Plan given that not only has 2010-11 been a very wet year, it has provided the highest summer inflows on record. These record inflows have resulted in storage levels and river flow rates that in some instances are outside the range of the scenarios that were presented in the Operating Plan.

The review compares actual river operations up to 28 February 2011 with the six scenarios that were presented in the Operations Plan. The review also describes the very wet conditions to date and their impact on river operations. Variations to the Operations Plan are provided as are descriptions of river operations that may be undertaken during the remainder of 2010-11 that were not documented in the Operating Plan.

There are four significant operations that have, or may be carried out, that were not documented in the Operating Plan: a temporary drawdown of Lake Mulwala to assist in controlling the water weed Egeria densa (section 4.3), operations aimed at reducing the impacts of blackwater (section 4.5), Hume Dam pre-releases (section 4.7) and Menindee Lakes flood operations (section 4.10).

Page 7: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)2

2 systeMstatuson28February2011

Rainfall across the entire Basin between 1 June 2010 and 28 February 2011 was very much above average, with the highest rainfall on record occurring in parts of western Victoria, western NSW and south-east Queensland (Figure 1). Rainfall in the upper Murray catchment, where the majority of the system inflows are usually generated, has also been very much above average. This rainfall has dramatically reversed the extreme dry conditions of recent years, with floods occurring multiple times during 2010-11 along parts of the Murray, Barwon-Darling, Murrumbidgee, Goulburn, Ovens, Campaspe, Loddon and many other rivers in the Basin.

In the south of the Basin, River Murray System inflows (excluding Snowy releases and Menindee inflows) totalled 15,100 GL between 1 June 2010 and 28 February 2011, which has and Annual Exceedance Probability (AEP) of 10%, compared with the annual long-term average of 8,000 GL (Figure 2). High inflows are forecast to continue into March 2011 and it is likely that this year will end up having higher inflows than in the ‘very wet’ scenario that was presented in the Operating Plan.

Although the total inflow is within the range experienced over the past 118 years, the inflow pattern has been very unusual. Inflows in the winter/spring (up to end November) were modest with an AEP of about 35%, however the inflow over summer (December 2010 to February 2011) was about 6,700 GL, which was more than double the previous highest of about 2,980 GL recorded in the summer of 1992-93.

Figure 1 rainfall Deciles – 9 months 1 June 2010 to 28 February 2011

Page 8: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)3

Figure 2 river Murray System inflows (excluding inflows to Menindee and Snowy Mountains Scheme) - recent years and long-term averages

In the north of the Basin, there have also been multiple food events in the catchments of the Darling River. As a consequence the Menindee Lakes commenced pre-release/flood operation on 6 December 2010 and at the end of February 2011 they were still effectively full and spilling. Releases are providing much needed water to floodplains along the Lower Darling and Great Darling Anabranch as well as the River Murray in South Australia. During flood operations, day to day management of Menindee Lakes is coordinated by the NSW Government.

Total inflows to Menindee Lakes between 1 June 2010 and 28 February 2011 were about 3,660 GL, which has an AEP of 8%. The long-term average is about 1,330 GL (Figure 3). Further significant inflows into Menindee are forecast during autumn.

System reserves have improved significantly in the last 9 months. The total MDBA active storage on 28 February 2011 was 6,750 GL (Table 1 and Figure 4), including about 1,621 GL in Menindee Lakes. The active storage at the end of February was above the long-term average for the first time since November 2001. On 28 February 2011, there was also about 390 GL of water available to the Murray in 2010-11 held in storages in the Murrumbidgee and Goulburn Valleys as a result of earlier trade into the Murray.

Long Term Average

2006/07 2007/08 2008/09 2009/10

Actuals 2010/2011Average last 10 years

Tota

l Mon

thly

Infl

ow (G

L)

3500

3000

2500

2000

1500

1000

500

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

0

Page 9: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)4

Figure 3 inflows to Menindee Lakes in recent years and long-term averages

TabLe 1 Storage in MDba major reservoirs on 28 February 2011

Major storage

Total capacity (GL)

active capacity (GL)

Total water in storage on 31st May 2010 (GL)

Percentage of total capacity

active water in storage on 31st May 2010 (GL)

active MDba water in storage on 28th Feb 2011 (GL)

Total water in storage on 28th Feb 2011 (GL)

Percentage of total capacity

Dartmouth Reservoir

3,856 3,785 1,241 32% 1,170 2282 2353 61%

Hume Reservoir

3,005 2,982 622 21% 599 2947 2970 98%

Lake Victoria 677 577 383 57% 283 380 480 71%

Menindee Lakes

1,731 1,251 1,409 81% 929 1141 1621 94%

river Murray System Total

9,352 3,655 39% 2,981 6750 7424 79%

Long Term Average

2006/07 2007/08 2008/09 2009/10

Actuals 2010/2011Average last 10 years

Tota

l Mon

thly

Infl

ow (G

L) 700

600

500

1000

900

800

400

300

200

100

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

0

Page 10: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)5

Figure 4 MDba active storage June 2000 to Jan 2011

Actual Storage Long Term Average Storage modelled to April 2009

Maximum Actual Storage

End

of M

onth

Sto

rage

(GL)

June

10000

9000

8000

7000

6000

5000

4000

3000

2000

1000

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

0

Page 11: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)6

3 suMMaryoFwatersharIngand sIgnIFICantoperatIons

3.1 riverMurraysystemscenariosfor2010-11

Since the inflows to the River Murray System cannot be known in advance, the Operational Plan addressed the operations that may have been undertaken under six different scenarios that covered a range of conditions that may have been experienced.

Each scenario had in-built assumptions regarding inflows from the Snowy scheme, unregulated inflows into Hume Reservoir, inflows into Dartmouth Reservoir and inflows from the tributaries, including the Kiewa, Ovens, Goulburn, Murrumbidgee, and Darling Rivers, conveyance “losses”, storage losses and usage patterns.

Generally, it is only the volume of water available under the ‘worst case scenario’ (and updates thereof) that is progressively allocated by the States to their water users. The other scenarios are used to provide indicative quantities of water availability to the States to assist yearly planning for water managers and customers should those wetter scenarios eventuate.

The relative difference between inflows of each of the six scenarios can be compared in Figure 5. The details of the six scenarios are provided in Table 2 and they are labelled according to the assumed River Murray System inflow as follows:

• the ‘worst case scenario’, assumed 772 GL of River Murray System inflows, which is 198 GL less than the historic minimum inflows of 970 GL that occurred in 2006-07;

• the ‘very dry’ scenario, assumed River Murray System Inflows of about 1,800 GL, which is comparable to inflows in 2008-09;

• the ‘dry’ scenario, assumed River Murray System Inflows of about 2,700 GL which is comparable to inflows in 1997-98;

• the ‘moderate’ scenario, assumed River Murray System Inflows of about 4,000 GL which is comparable to inflows in 1994-95;

• the ‘near average’ scenario, assumed River Murray System Inflows of about 6,000 GL which is comparable to inflows in 2005-06; and

• the ‘very wet’ scenario, assumed River Murray System Inflows of about 16,000 GL which is comparable to inflows in 1992-93.

Page 12: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)7

Figure 5 ranked Historical System inflows showing years similar to Scenarios

0

5000

10000

15000

20000

25000

30000

35000

Syst

em in

flow

s (G

L/yr

) exc

ludi

ng S

now

y an

d D

arlin

g

119 years (ranked from lowest to highest inflows)

very

dry

≈180

0 G

L

“worst case”assumes less than 2006-071

1992

-93

near average

2005

-06

dry

≈270

0 G

L

2006

-07

very wet ≈ 16,000 GL≈6000 GL

2008

-09

moderate ≈4000 GL

2007

-08 20

04-0

5

2009

-10

Forecast for 2010-11 as at 28 Feb 2011

“worst case”• carryover available but minimal State allocations

very dry• small State allocations

dry • State allocations improving• no overbank flows in Barmah-Millewa

• no unregulated flows

moderate

• still no overbank flows through Barmah-Millewa

• potential for small unregulated flows

• Full entitlement for South Australia

near average• overbank flows through Barmah-Millewa

Forest• NSW and Victorian allocations sufficient to

trigger release of Barmah-Millewa EWA• significant unregulated flows• no Hume spill

very wet• major overbank flooding along length over

River Murray System • Dartmouth not filled

Page 13: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)8

Ite

m

wo

rst

case

*ve

ry d

ry

dry

mo

de

rate

ne

ar

ave

rag

eve

ry w

et

Act

ive

MD

BA

sto

rag

e o

n 31

Ma

y 20

1029

6529

6529

6529

6529

6529

65

Sto

rag

e in

Va

lley

Acc

oun

ts o

n 31

Ma

y 20

1014

314

314

314

314

314

3

Wa

ter i

n tra

nsit

on

31 M

ay

2010

2727

2727

2727

June

201

0 to

Ma

y 20

11 i

nflo

ws

from

Up

stre

am

of A

lbur

y 82

816

3425

1234

6545

0179

74

June

201

0 to

Ma

y 20

11 i

nflo

ws

from

Up

stre

am

of M

eni

nde

e17

017

017

017

017

017

0

June

201

0 to

Ma

y 20

11 i

nflo

ws

from

Vic

toria

n tri

but

arie

s 19

048

972

212

2019

6764

20

June

201

0 to

Ma

y 20

11 i

nflo

ws

from

NS

W tr

ibut

arie

s 93

9312

222

047

629

70

Up

pe

r Sta

te u

sag

e a

nd S

A n

on

dilu

tion

Ent

itle

me

nt to

end

Ma

y 20

110

00

00

0

Ne

t tra

de

into

Up

pe

r Sta

tes

this

se

aso

n0

00

00

0

Re

ma

inin

g c

om

mitm

ent

s b

etw

ee

n 1

June

201

0 a

nd 3

1 M

ay

2011

Co

nve

yanc

e lo

sse

s a

long

Mur

ray

upst

rea

m o

f SA

Bo

rde

r -8

00-8

00-8

00-8

30-1

250

-250

5

Co

nve

yanc

e lo

sse

s a

long

Lo

we

r Da

rling

-1

45-1

45-1

45-1

45-1

25-3

5

Sto

rag

e lo

sse

s up

stre

am

of t

he S

A B

ord

er

-547

-552

-563

-590

-740

-915

Sup

ply

of S

out

h A

ustra

lian

Dilu

tion

and

Lo

ss E

ntitl

em

ent

-696

-696

-696

-696

-696

-696

Sup

ply

of t

rans

fer (

trad

e) w

ate

r to

So

uth

Aus

tralia

-52

-52

-52

-52

-52

-52

Sup

ply

of u

nde

live

red

So

uth

Aus

tralia

n E

ntitl

me

nt fr

om

200

9-10

-7

2-7

2-7

2-7

2-7

2-7

2

Sup

ply

of A

dd

itio

nal D

ilutio

n F

low

dui

rng

201

0-11

-90

-90

-139

-151

-250

-380

Sup

ply

of U

nre

gul

ate

d F

low

to S

out

h A

ustra

lia d

urin

g 2

010-

110

00

0-1

00-5

950

To

tal M

urr

ay

allo

cata

ble

wa

ter

(Tie

r 1

)2

01

43

11

44

19

35

67

46

96

41

00

64

52

52

52

52

52

52

To

tal a

vaila

ble

wa

ter

for

use

20

67

31

66

42

45

57

26

70

16

10

11

6

* wor

st c

ase

scen

ario

as

at 2

0 Ju

ne 2

010.

Inc

lude

s a

rece

ssio

n to

wor

st c

ase

by 1

Jul

y 20

10 fo

llowi

ng ra

in in

mid

Jun

e 20

10.

Ad

diti

ona

l ava

ilab

le w

ate

r to

Mur

ray

due

to w

ate

r ta

nsfe

rs

(exc

lud

ing

intr

a s

tate

ent

itle

me

nt tr

anf

ers

)

Tab

Le 2

D

etai

ls o

f eac

h sc

enar

io in

201

0-11

Ope

rati

ng P

lan

(gL)

Page 14: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)9

3.2 ComparisonwithriverMurraysystemscenariosfor2010-11

A comparison of the information provided for the six scenarios in the initial Operating Plan with the actual observations to end February 2011 (last column) are provided for water availability (Table 3), significant river operations (Table 4) and significant environmental operations (Table 5).

The inflow patterns, system losses and usage observed in any particular year are unique and unlikely to be consistent with any single planning scenario. In the case of this water year the actual outcomes are most similar to the Very Wet scenario, but in other instances are more similar to the Near Average, or between the Very Wet and Near Average scenarios. Information is marked in RED where the actual events are significantly different to any of the scenarios.

The following acronyms are used in the last column of Tables 3, 4 and 5.

R - similar to one of the scenarios VW – very wet scenario Na – near average scenario Mod – moderate scenario Dry – dry scenario VD – very dry scenario WC – worst case scenario

Page 15: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)10

TabLe 3 Summary of Water availability under each scenario

WaTer aVaiLabiLiTY ‘worst case’ Very dry Dry Moderate Near average

Very Wet ‘worst case’ outlook at end February 2011

Sharing rules at end of May 2010

Tier 1 Tier 1 Tier 1 Tier 1 Tier 1 Tier 1 Tier 1 R VW

indicative State water entitlements at end May 2011 NSW ViC Sa

680 GL 770 GL 564 GL

940 GL 1340 GL 844 GL

1250 GL 1810 GL 1134 GL

1690 GL 2530 GL 1154 GL*

2480 GL 2940 GL 1154 GL

3560 GL 4510 GL 1154 GL

3420 GL R VW 4250 GL R VW 1154 GL R VW **

Sa Dilution & Loss 696 GL 696 GL 696 GL 696 GL 696 GL 696 GL 696 GL R VW **

Carryover trade delivery to Sa

52 GL 52 GL 52 GL 52 GL 52 GL 52 GL 52 GL R VW

Forecast Minimum Reserve at end May 2011

0 GL 0 GL 0 GL 300 GL* 835 GL 835 GL 835 GL R VW

Special accounting 3 States commencing August

3 States commencing August

3 States commencing August

3 States commencing August

3 States commence in August. Victoria exits special accounting during 2010-11

3 States commence in August. Victoria and NSW exit special accounting during 2010-11

Victoria and NSW no longer in special accounting with South Australia. R VW

internal spill at Lake Victoria (Vic to NSW)

0 GL 0 GL <10 GL # 100 GL # 390 GL # 0 GL 639 GL internal spill from Victoria to NSW – significantly higher than NA and VW scenarios due to inflows in spring primarily coming from Victorian tributaries

Lindsay River Allowance

Normal Lindsay River Allowance from 1 July 2010 unless other arrangements agreed

Normal Lindsay River Allowance from 1 July 2010

Normal Lindsay River Allowance from 1 July 2010

Normal Lindsay River Allowance from 1 July 2010

Normal Lindsay River Allowance from 1 July 2010 R VW

additional Dilution Flow

≈ 90 GL # ≈ 90 GL # ≈ 139 GL # ≈ 151 GL # ≈ 240 GL # ≈ 360 GL # 909 gL – Higher than VW scenario due to persistent high inflows from Darling and high storage levels of Hume, Dartmouth and Menindee.

* If SA takes less than full entitlement in months from August 2010 the full 1,154 GL will not be reached. Instead, any reduced take of entitlement would be added to the Minimum Reserve.

** 1154 GL plus 696 GL Dilution and Loss equals the full entitlement flow of 1850 GL

# Highly dependent on the timing of improvements in water availability and usage patterns

Page 16: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)11

WaTer aVaiLabiLiTY ‘worst case’ Very dry Dry Moderate Near average

Very Wet ‘worst case’ outlook at end February 2011

unregulated Flows at Sa border

0 GL 0 GL 0 GL <10 GL # About 100 GL #

About 7800 GL

9500 GL R VW

assumed usage

NSW ViC Sa ent. Delivered

#

420 GL 520 GL 1010 GL

#

660 GL 890 GL 1270 GL

#

890 GL 1280 GL 1530 GL

#

1300 GL 1630 GL 1850 GL

#

1910 GL 1840 GL 1850 GL

#

2060 GL 1790 GL 1850 GL

#

1000 GL R Dry 900 GL R VD 1850 GL R VW

NSW and Victorian usage very low due to record summer rain

end of season active storage

760 GL # 910 GL # 1080 GL # 1610 GL # 2400 GL # 5100 GL # Approx 6330 GL.

Higher than in VW scenario due to a record wet summer and low usage

# Highly dependent on the timing of improvements in water availability and usage patterns

Page 17: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)12

TabLe 4 Summary of significant river operations under each scenario

riVer OPeraTiONS ‘worst case’ Very dry Dry Moderate Near average

Very Wet ‘worst case’ outlook at end February 2011

expected Dartmouth release above minimum

~ 700 GL, commencing Oct/Nov up to 5,000 ML/day.

500 - 700 GL, commencing Oct/Nov, up to 5,000 ML/day.

400 - 600 GL, commencing Oct/Nov, up to 5,000 ML/day.

200 - 500 GL, commencing Nov/Dec, up to 4,000 ML/day.

<200 GL, only require if Snowy Creek flow is very low

0 GL 0 GL R VW

Dartmouth Storage end May

~680 GL (600 GL active)

~850 GL (770 GL active)

~1080 GL (1000 GL active)

~1430 GL (1350 active)

~ 1900 GL (1820 GL active)

~ 2450 GL (2380 GL active)

2380 GL R VW

Hume storage very low levels (<5% capacity), over summer/autumn, increased chance of algal bloom

very low levels (~10% capacity), over summer/autumn, increased chance of algal bloom

very low levels (~10-capacity), over summer/autumn, increased chance of algal bloom

low levels (~10-20% capacity) in autumn increased chance of algal bloom

No spill but may reach 60% of capacity and ~10-20% capacity through summer/autumn

Spilling from September to December and close to half full at end of year

Spilled from Oct to Dec. approx. 1300 gL, but with more recent rain in February Hume is expected to be >75% full at end of May 2011

Operation of Weir pools

Lake Mulwala lowered at end of year. Large variations at other weir pools may be implemented to conserve water in upper storage BOC: Restrictions

Normal regulated weir pool variability

Normal regulated weir pool variability

Normal regulated weir pool variability.

Normal regulated weir pool variability, with some flood operations

Normal weir pool variability, including major flood operations

Normal weir pool variability, including major flood operations at most weirs. R VW

Potential for temporary lowering of euston Weir to remove debris during reinstatement after flooding

Potential for temporary lowering of Lake Mulwala in winter to assist in control of the waterweed Egeria densa.

Lake Victoria level No internal or actual spills but very low in summer <200 GL MDBA: Balance risks of higher losses / potential restrictions during peak demands

No internal or actual spills but very low in summer <200 GL MDBA: Balance risks of higher losses / potential restrictions during peak demands

Possible small internal spill from Victoria to NSW (<10 GL) depending on timing of Ovens inflows. No actual spill.

Possible internal spill from Victoria to NSW (100 GL). Possibility of inlet capacity causing unregulated flows.

Internal spill from Victoria to NSW (200-400 GL). Spilling for 2-3 months

Spilling for 5-6 months

Spilled from Oct 2010 to February 2011 and now expected to be spilling to end of May (8 months) due to summer flooding

Page 18: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)13

riVer OPeraTiONS ‘worst case’ Very dry Dry Moderate Near average

Very Wet ‘worst case’ outlook at end February 2011

Lake Victoria Operating strategy and Cultural Heritage

Exposure of zones containing large numbers of burials for long periods and potentially prolonged drying of low lying regenerated vegetation.

Exposure of zones containing large numbers of burials for long periods and potentially prolonged drying of low lying regenerated vegetation.

Potential exposure of zones containing large numbers of burials and drying out of low lying regenerated vegetation.

Lake Victoria may not fill but inflows should be sufficient to water regenerated vegetation at higher elevations.

Operations will need to minimise the length of time the Lake Victoria level is high and be consistent with the LVOS.

Operations will need to minimise the length of time the Lake Victoria level is high and be consistent with the LVOS.

Operations have minimised the length of time that Lake Victoria level has been high consistent with the LVOS R VW

Lake Victoria 250 gL reserve at end May 2011.

Not required to be met as minimum reserve is zero.

May require additional release from upper storages. MDBA to advise BOC early in 2011 MC: 103 (4)

Able to be met

Able to be met

Able to be met

Able to met R VW

Page 19: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)14

TabLe 5 Summary of significant environmental operations under scenarios

eNVirONMeNTaL OPeraTiONS

‘worst case’ Very dry Dry Moderate Near average

Very Wet ‘worst case’ outlook at end February 2011

Assumed Environmental flow release from Hume

0 0 150 300 600 900 410 GL R Mod-Na

Less than expected due to very wet summer

barmah-Millewa environmental Water allocation

312 GL in EWA. 302 GL borrowed and not available. Victoria has 10 GL available

About 340 GL in EWA. ~330 GL borrowed and not available. Victoria has 10 GL available

About 380 GL in EWA. ~370 GL borrowed and not available. Victoria has 10 GL available

412 GL in EWA. NSW share borrowed (231 GL) but Victorian share (181 GL) available

412 GL in EWA. Both NSW and Victorian shares available and triggers for release met.

EWA may not be used, partial spill from Hume and up to 400 GL carried over for following year.

200 GL of EWA released. 212 GL expected to be carried over, of which some may spill in 2011-12. R VW

euston Lakes refilling

Dry Lake is filled and Lake Benanee will continue to fill using part of the 800 GL set aside for conveyance for evaporative losses.

Dry Lake and Lake Benanee filled. R VW

below minimum flow/height levels

Required at some locations MDBA: 98(2) & 98(1)

May be required at some stage MDBA: 98(2) & 98(1)

May be required at some stage MDBA: 98(2) & 98(1)

Not required Not required Not required Not required R VW

Lake alexandrina at end May 2011

-0.8 m AHD -0.7 m AHD -0.4 m AHD 0.0 m AHD 0.55 m AHD and likely flow over barrages during spring

FSL >4,000 GL over barrages.

Lower Lakes are full. Over 5,000 GL past the barrages to end February 2011 R VW

Lake albert at end May 2011

-0.4 m AHD -0.4 m AHD -0.4 m AHD 0.0 m AHD

goolwa Channel at end May 2011

0.0 m AHD 0.0 m AHD 0.0 m AHD 0.0 m AHD

Wakool System (NSW Decision)

40 GL replenishment

Normal operations

Normal operations

Normal operations

Normal operations

Normal operations

Normal operations R VW except for extra releases via MiL escapes and Waddy Cutting to assist blackwater dilution

Salinity Potentially high salinities along the River Murray System in South Australia.

Potentially high salinities along the River Murray System in South Australia.

Potentially high salinities along the River Murray System in South Australia.

Normal salinity levels expected

Normal salinity levels expected

Potential for high salinity levels following extensive flooding of the Lower Murray

Slight rises in salinity observed in mid Murray as the peak flows have passed, yet to observe impacts of recession R VW.

Flooding In channel flows

In channel flows

Small chance of small flood into Barmah-Millewa Forest, otherwise in channel.

Increased chance of small flood into Barmah-Millewa Forest and central Murray area.

Flooding into Barmah-Millewa Forest and central Murray area.

Extensive and prolonged flooding along entire River Murray System

Extensive and prolonged flooding along entire River Murray System R VW.

Page 20: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)15

eNVirONMeNTaL OPeraTiONS

‘worst case’ Very dry Dry Moderate Near average

Very Wet ‘worst case’ outlook at end February 2011

Chance of blue-green algal blooms along river

There is always a chance of blue-green algal blooms forming somewhere along the River Murray System. Algal blooms generally form during the summer and persist into autumn and have been observed to form in both high flow and low flow years, however the more extensive blooms have been observed more often during dry years. MDBA may be able to assist in dispersing algal blooms in weir pools with ‘pulsed’ flows on some occasions. However, this is not always feasible, particularly when water is scarce.

Moderate BGA alert at Hume Dam during December R VW.

Page 21: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)16

4 detaILedrIverMurraysysteM operatIonsFor2010-11

4.1 riverandstoragelosses

Conveyancewater(riverlosses)

River losses in September, December, January and February (when the most significant flooding occurred) were higher than assumed in the Very Wet scenario (Figure 6). River losses to the end of February 2011 totalled around 3,390 GL, compared to the 2,320 GL total that was assumed in the very wet scenario. The very high river losses are understood to be a function of the magnitude of the flooding, dryness of the floodplain preceding the floods and persistence of widespread inundation through summer.

storagelosses

Storage losses have been around -100 GL, meaning that in total the storages gained around 100 GL of water. This is due to relatively cool conditions and rainfall landing directly on or around storages, counteracting water lost to evaporation. This is very different to all scenarios forecast, with the lowest forecast evaporative losses being around 550 GL in the worst case scenario (Figure 7). It should be noted that rainfall at Menindee Lakes and Lake Victoria, where the evaporation losses are usually greatest, has been the highest, or close to the highest on record (Figure 1).

Figure 6 river Murray System conveyance losses upstream of the Sa border

Very wet Scenario

Dry Scenario Very dry Scenario Worst case Scenario Actuals 2010/11

Moderate ScenarioNear average Scenario

Loss

es (G

L/m

onth

)

700

600

500

900

800

400

300

200

100

Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11

0

Month

Page 22: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)17

Figure 7 river Murray System storage evaporative losses

4.2 Changestominimumflowrates

As 2010/11 has been extremely wet, no temporary departures from standard procedures have been required during the 2010/11 water year.

4.3 weirpoollevelmanipulation

No weir pool manipulations outside of the normal operating ranges, other than those occurring due to floods or identified in the Operating Plan, have been necessary so far during the 2010/11 water year.

Lake Mulwala has been managed within its normal operating range (124.6 to 124.9 m AHD), except during periods of flooding. However, MDBA is examining the potential to begin a partial drawdown of Lake Mulwala this winter (potentially commencing in May 2011) to assist in controlling the water weed Egeria densa.

At Lock and Weir 11 (Mildura), the planned trestle replacement with a new prototype trestle with mechanised gates was undertaken in mid July 2010. The trestle replacement required a temporary drawdown of the Mildura Weir pool (to about 3.6 m below full supply level). The construction of the ‘Denil’ fishway at Mildura has been delayed due to flooding and cannot proceed until flows are less than 15,000 ML/day. The Mulcra Island works to assist delivering environmental water were almost complete when flooding inundated the site. Some damage has been observed, which will be repaired after the flooding recedes. The planned raising of Lock 8 to provide environmental water to Mulcra Island was not required because the works have not been completed and the area has had a significant flood as a result of high flows.

Very wet Scenario

Dry Scenario Very dry Scenario Worst case Scenario Actuals 2010/11

Moderate ScenarioNear average Scenario

Loss

es (G

L/m

onth

)

200

150

100

50

0

Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11

-50

Month

Page 23: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)18

There were minor variations, within normal operating ranges, in the Torrumbarry, Mildura, Wentworth, Lock 9, Lock 8 and Lock 7 weir pools to protect downstream works during the initial high flow period. However, once it was obvious that flow rates were such that they could not be contained and the work sites had been ‘cleared’, then the weir pools were returned to near their full supply levels.

4.4 deliveringenvironmentalwater

About 410 GL of Environmental Water (from the Barmah-Millewa Environmental Water Account and entitlements held by the NSW government and The Living Murray) was released from Hume Reservoir, between late September 2010 and early February 2011. This ‘environmental flow’ was identified in the Operating Plan and was agreed by the Basin Official’s Committee.

The majority of the environmental water (325 GL) was released from Hume Reservoir between 30 December 2010 and 9 February 2011 at an average flow rate of approximately 8,000 ML/day, which was about 50% of the total release form Hume. The peak environmental flow release was about 14,000 ML/day.

The primary aim of these environmental water releases was to maintain water levels in key colonial water bird breeding areas and other wetlands in the Barmah-Millewa Forest during periods of lower flow rates in between the flood peaks that have originated from the upper Murray, Ovens and Kiewa Rivers. The target environmental flow rates also took into account the blackwater that was draining

Figure 8 impact of environmental flow releases on flow rates at Yarrawonga Weir

0

20,000

40,000

60,000

80,000

100,000

120,000

1 A

UG

15 A

UG

29 A

UG

12 S

EP

26 S

EP

10 O

CT

24 O

CT

7 N

OV

21 N

OV

5 D

EC

19 D

EC

2 JA

N

16 J

AN

30 J

AN

13 F

EB

27 F

EB

13 M

AR

Actual release from Yarrawonga Weir

Channel capacity through barmah Choke

Release from Yarrawonga without EWA

Approximate f low at Yarrawonga under natural conditions

Flow

Dow

nstr

eam

of Y

arra

won

ga (M

L/da

y)

Actual flow in River Murray downstream of Yarrawonga vs probable flow without environmental release

Page 24: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)19

During the release of environmental water from Hume Reservoir the flow at Doctors Point (near Albury/Wodonga) was maintained at less than the 25,000 ML/day maximum regulated flow (within channel capacity), which is well below the minor flood level at Albury (which is equivalent to about 45,000 ML/day at Doctors Point).

The environmental releases targeted flow rates downstream of Yarrawonga Weir of about 16,000 to 22,000 ML/day. However, following some rain events, high inflows from the Ovens and Kiewa Rivers increased the flow downstream of Yarrawonga to about 40,000 ML/day. This is well below the minor flood level downstream of Yarrawonga Weir of 81,500 ML/day and also well below the peak flow downstream of Yarrawonga Weir of in excess of 100,000 ML/day that occurred twice earlier in the year (September and December) as a result of a combination of high inflows from Kiewa and Ovens River and ‘spill’ from Hume. On those two occasions there was no environmental water released.

4.5 actionstominimiseimpactsofblackwater

The extensive flooding that has occurred this year after many years of drought has resulted in large areas of the river system being affected by blackwater. Fish deaths have been reported in several rivers and large numbers of Murray crays were observed on river banks avoiding the blackwater.

There were several actions that were implemented jointly by State agencies and MDBA with the aim of diluting blackwater along sections of the River Murray System and associated streams. These actions took place as a cooperative response between the Victorian, SA, and NSW agencies, and MDBA.

The first area to be affected by blackwater was the mid and lower parts of the Wakool River. This was as a result of water flowing out of the Koondrook-Perricoota Forest after the September 2010 flood events in the Goulburn, Campaspe, Ovens and Kiewa Rivers.

The first sign of fish deaths in the Wakool River was reported to MDBA on 6 October 2010. There was very little ability to respond immediately as at the time there was very little excess water in transit between Hume Reservoir and Deniliquin in the Murray and Edward Rivers. However, over the following week several actions were implemented by MDBA and/or NSW State Water in an effort to provide additional water along the Edward-Wakool System to dilute the blackwater.

On 8 October 2010 NSW State Water began increasing the flow into Yallakool Creek and on 11 October began raising the Stevens Weir pool to further increase the flow into Yallakool Creek. In addition, MDBA requested NSW State Water to increase the outflow from the Edward Escape (8 October 2010) and Wakool and Yallakool Escapes (both 11 October 2010) to the maximum rates. It was agreed that MDBA would cover the agreed monetary costs and the 10% seepage and evaporation loss associated with the use of these Escapes, which are owned by Murray Irrigation Limited (MIL). As at 28 February 2011, the MDBA order for water from the MIL escapes was still in place but was expected to be gradually reduced during autumn 2011 as the flooding subsided and water quality improved.

Monitoring of the blackwater indicated that the use of the MIL escapes improved water quality in some sections of the Edward-Wakool Systems. However, there was insufficient dilution in the mid and lower reaches of the Wakool River to offset the significant impact of the very poor water quality from the subsequent large-scale flooding of the Koondrook-Perricoota Forest in December, January and February.

Page 25: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)20

Following discussions with MDBA in late December 2010, NSW State Water partially opened the Waddy Cutting regulator for the purposes of passing freshwater into Merran Creek and the Wakool River to dilute blackwater in these streams. In early January 2011 the Waddy Cutting regulator was opened further, which led to erosion of the banks and some damage to the regulator, which was closed soon after this was observed.

Additional environmental water was released along the Goulburn River between high flow events to assist in minimising the blackwater event in the lower Goulburn River and the River Murray near Echuca. Also, the environmental water that was being released from Hume (see Section 4.4) also targeted flow rates that took into account the blackwater that was draining from the Barmah-Millewa Forest since mid November 2010.

Trial manipulation of regulators within the Barmah-Millewa Forest was carried out in an effort to maximise the volume of water staying within the river channel to provide dilution of the blackwater. The outcomes of these trials were inconclusive.

Environmental water was also released along the Murrumbidgee River during the flood recession to dilute blackwater that was returning to the river from the lower Murrumbidgee floodplain.

At Lake Victoria, SA Water undertook a trial in which blackwater with low dissolved oxygen was diverted into the lake via the inlet regulator and, in the process, the blackwater was partially oxygenated. It was found that an inflow rate to the lake of about 3,000 ML/day provided the greatest aeration. At the same time the outflow from the Lake, which contained higher oxygenated water, was increased to about 2,500 ML/day. This operation had no detectable detrimental impact on dissolved oxygen levels in Lake Victoria and due to the very high flows passing along the River Murray at the time (80,000-90,000 ML/day) had no detectable positive impact on dissolved oxygen levels the river. However, it was a successful trial and would be a valuable operation in the future if there were blackwater events at lower flow rates.

4.6 dartmouthreservoir

Storage in Dartmouth Reservoir has increased from 32% to 61% capacity between June 2010 and February 2011. The storage volume had been tracking slightly less than that forecast in the Very Wet scenario but is now expected to exceed the Very Wet scenario by the end of May 2011 (Figure 9). An updated capacity table was implemented for Dartmouth Reservoir on 1 October 2010.

Wet conditions have meant that demands downstream of Dartmouth Reservoir have been able to be met by downstream storages and tributaries. As such MDBA releases from Dartmouth have been held at minimums (200 ML/day) except during February 2011 when AGL Hydro utilised entitlement releases for power generation (Figure 10). There may be further entitlement releases by AGL Hydro over the remainder of 2010-11.

Initial planning for 2011-12 shows an increased chance of spill at Dartmouth Reservoir in spring 2011 due to the preceding wet conditions.

Page 26: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)21

Figure 9 Dartmouth reservoir storage outlook

Figure 10 Dartmouth reservoir release outlook

Last Season Revised likely upper releaseRevised Likely lower release

Very wet Scenario

Dry Scenario Very dry Scenario Worst case Scenario

Actuals 2010/11Moderate ScenarioNear average Scenario

Rel

ease

(GL/

Mon

th)

140

120

40

20

100

80

60

Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11

0

Month

INDICATIVE FORECAST ONLY: SUBJECT TO REVISION AS CONDITIONS CHANGE

Last Season Nominal Generation Limit (432 m)

Revised likely upper levelRevised Likely lower level

Very wet Scenario

Dry Scenario Very dry Scenario Worst case Scenario Capacity = 3856 GL

Actuals 2010/11Moderate ScenarioNear average Scenario

Stor

age

(GL)

4000

3500

1500

1000

500

3000

2500

2000

Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11

0

Month

INDICATIVE FORECAST ONLY: SUBJECT TO REVISION AS CONDITIONS CHANGE

Page 27: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)22

4.7 humereservoirandflowsatdoctorspoint

An updated capacity table, as identified in the Operating Plan, was implemented for Hume Reservoir on 1 October 2010.

The high inflows from downstream tributaries and rainfall across the irrigation areas has meant that releases from Hume Reservoir, to meet downstream diversion requirements, have been relatively low. This, coupled with high inflows over the year, resulted in Hume Reservoir spilling in October, November and December of 2010 and then again in February 2011 (Figure 11).

Prior to February 2011, the increase in Hume storage followed a similar pattern to that in the Very Wet scenario, but with a delay due to the relative lateness of the rain events. Hume storage reached full supply level in October as compared with September in the Very Wet scenario.

Total release from Hume Reservoir to the end of February 2011 was about 2,710 GL, which was much less than in the Very Wet scenario forecast of 3,745 GL. This is primarily due to Hume inflows to the end of February 2011 being much less than in the Very wet Scenario.

When Hume releases were combined with inflows from the Kiewa River, the flow at Doctors Point (near Albury/Wodonga) during the December 2010 flood was above channel capacity (>25,000 ML/day) for seven days and averaged about 29,000 ML/day for the month (Figure 12). However, the volume of water that actually flowed past Doctors Point during the month of December 2010 was less than that forecast for October in the Very Wet scenario. Therefore, although the timing of the peak flow was different due lateness of the rain events, the peak flow was within the range of the six scenarios.

The maximum release from Hume Reservoir was 40,000 ML/day (11-13 December 2011), which contributed to a Moderate Flood level on the Albury gauge for a short period.

Environmental and irrigation releases in January 2011 resulted in Hume Reservoir being drawn down to 86% by early February 2011, however further rain resulted in Hume Reservoir again filling and spilling in late February. Since 1956, the previous highest storage volume in Hume Reservoir at the end of February was about 95% in 1993.

Hume storage is now expected to be >75% capacity at the end of May, which is above that described in the Very Wet scenario. There is a good chance that the storage will be near full for the remainder of 2010-11. As such pre-releases are expected to commence in March 2011 to provide airspace in the storage to assist in mitigating larger flood events.

Pre-releases may continue over the autumn and winter months depending on rainfall. Pre-releases generally do not occur until winter which is when storage levels normally rise towards full supply level. However, pre-releases were made in March 1993 due to the very wet conditions in that year. As this is a relatively rare situation, MDBA will initially target about 200 GL of airspace during March and the volume of airspace will be reviewed frequently and adjusted as new information arises. The regular review will take into account a number of factors including past practice (such as in 1993), short and longer term BoM rainfall and streamflow outlooks, potential impacts on water availability, environmental outcomes and in accordance with any advice or determinations provided by Basin Officials Committee.

Page 28: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)23

Figure 11 Hume reservoir storage outlook

Figure 12 Hume reservoir release outlook – flows at Doctors Point (albury)

Last Season Revised likely upper FlowRevised Likely lower Flow

Very wet Scenario

Dry Scenario Very dry Scenario Worst case Scenario Channel Capacity = 25 000 ML/day

Actuals 2010/11Moderate ScenarioNear average Scenario

Ave

rage

dai

ly fl

ow fo

r m

onth

(ML/

day)

35000

15000

10000

5000

30000

25000

20000

Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11

0

Month

INDICATIVE FORECAST ONLY: SUBJECT TO REVISION AS CONDITIONS CHANGE

Last Season Revised likely upper levelRevised Likely lower level

Very wet Scenario

Dry Scenario Very dry Scenario Worst case Scenario Capacity = 3038 GL

Actuals 2010/11Moderate ScenarioNear average Scenario

Stor

age

(GL)

3500

1500

1000

500

3000

2500

2000

Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11

0

Month

INDICATIVE FORECAST ONLY: SUBJECT TO REVISION AS CONDITIONS CHANGE

Page 29: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)24

4.8 LakeMulwalaandthebarmahChoke

The release from Yarrawonga Weir has been different to that forecast in all scenarios (Figure 13). The release has peaked later in the year due to late season flooding. The size of the peak flow in December was also greater than that forecast in the Very Wet scenario. A peak release downstream of Yarrawonga Weir of just over 110,000 ML/day occurred twice (September and December) as a result of a combination of high unregulated inflows from Kiewa and Ovens River and as a result of ‘spill’ from Hume.

Inflows from the Kiewa and Ovens Rivers have been very high and flow rates downstream of Yarrawonga Weir have been well above the channel capacity of the River Murray through Barmah-Millewa Forest since late August 2010. Significant inflow events from the Ovens and Kiewa Rivers have necessitated releases from Lake Mulwala to be managed in accordance with flood procedures.

Figure 13 Yarrawonga Weir release outlook

During 2010-11 the Barmah Choke has not been a major constraint on operations. The rule preventing trade of allocations from above to the below the Choke has been relaxed since September 2007. The MDBA has been undertaking fortnightly reviews of the relaxation, with the result that it has continued uninterrupted.

Last Season Revised likely upper FlowRevised Likely lower Flow

Very wet Scenario

Dry Scenario Very dry Scenario Worst case Scenario Channel Capacity = 10 400 ML/day

Actuals 2010/11Moderate ScenarioNear average Scenario

Ave

rage

dai

ly fl

ow fo

r m

onth

(M

L/da

y)

50000

30000

25000

20000

15000

10000

5000

45000

40000

35000

Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11

0

Month

INDICATIVE FORECAST ONLY: SUBJECT TO REVISION AS CONDITIONS CHANGE

Above channel capacity flows only due to delivery of environmental water

Page 30: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)25

4.9 Lakevictoria

Lake Victoria, at the end of February 2011 was at 71% capacity. Lake Victoria storage has followed a similar pattern, albeit with a delay, to that in the near average scenario (Figure 14). The lake was temporarily raised to 100% full (27.0 m AHD) in mid October 2010 (Figure 14 shows only the end of month volumes) and was then drawn down to 614 GL (26.48 m AHD, 90% by the end of October 2011). It was also temporarily filled to 650 GL (26.79 m AHD, 96% in mid November 2011). After this second peak, projected flood inflows permitted the lake level to be drawn down further, in accordance with the Lake Victoria Operating Strategy (LVOS) to minimise the time spent at high lake levels, in anticipation that it would be refilled to 100% capacity at the end of the flood event. However, given the prolonged period of flooding, Lake Victoria will not now be refilled this season because by the time the flood event ends (April-May), the lake level will again need to be kept low to meet the LVOS targets.

It is expected that storage in Lake Victoria at the end of May 2011 will exceed 350 GL. As such, the first 250 GL of minimum reserve will be held in Lake Victoria in accordance with Clause 103 of the Agreement.

MDBA continues to fulfil the intent of both the LVOS and the Lake Victoria Cultural Landscape Plan of Management (revised 2007) which were developed under the Section 90 consent and Section 87 Permit provided by the, then, NSW Department of Environment, Climate Change and Water.

There was a presentation error in the Lake Victoria storage graph in the original Operating Plan. It showed the lake level being above the LVOS levels in the Very Wet Scenario, whereas the text indicated that the storage management would be consistent with the LVOS in all scenarios. This presentation error has been rectified in this review.

Figure 14 Lake Victoria storage outlook

Last Season Revised likely upper LevelRevised Likely lower Level

Very wet Scenario

Dry Scenario Very dry Scenario Worst case Scenario Capacity

LVOS maximum levels

Actuals 2010/11Moderate ScenarioNear average Scenario

Stor

age

(GL)

700

300

200

100

600

500

400

Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11

0

27m

23m

22m

21m

26m

25m

24m

Month

INDICATIVE FORECAST ONLY: SUBJECT TO REVISION AS CONDITIONS CHANGE

Page 31: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)26

4.10 MenindeeLakes

Total inflows to Menindee Lakes between June 2010 and February 2011 were about 3,660 GL, which has an AEP of 8% (Figure 15). The long-term average for this period is about 1,330 GL. Further significant inflows into Menindee Lakes are forecast during the autumn, arising from water in transit due to summer rainfall.

In all six planning scenarios, it was assumed that the Darling River system would not provide further significant inflows into the Murray after July 2010. This assumption is traditional practice for planning purposes as the hydrology of the Darling River system is difficult to predict and reliable estimates of available water cannot be made for several weeks after rain. Also, there is very little correlation between inflows from the south of the Basin with inflows from the north of the Basin (i.e. a wet year in the south does not necessarily mean a wet year in the north). To include the Darling River in a meaningful manner would require several additional scenarios to be provided and graphed. Instead, this information was provided in a qualitative manner in the Operating Plan, which noted that any additional inflows would be stored preferentially in Lakes Wetherell and Pamamaroo (up to their surcharge level) then in Lakes Menindee and Cawndilla. These aspects of the Operating Plan were implemented.

It was also noted in the Operating Plan that further inflows to Menindee Lakes would be shared according to the Murray-Darling Basin Agreement or by any other agreement made by Basin Officials Committee or Ministerial Council at that time. So far, the inflows have been shared according to the Murray-Darling Basin Agreement. The initial inflows to Menindee Lakes triggered an internal spill of water from Victoria to New South Wales. When the Lakes were filled to surcharge level in spring (Figure 16), the NSW and Victorian shares were equalised. The surcharge volume was released prior to 31 December 2010 in accordance with surcharge rules. Since that time there have been further significant inflows to Menindee Lakes, which have triggered flood operations.

The initiation of flood operations has meant that MDBA has not needed to call on water from Menindee Lakes (due to forced releases) and, consistent with past practice, the NSW Office of Water has overseen the daily flood operations at the lakes. The normal minimum release (200 ML/day in winter) was targeted from June to September. Since October, the release has increased to pass floodwater and in late February 2011 reached as high as 34,000 ML/day.

The current management strategy by NSW Office of Water is to gradually fill the lakes so that they approach the maximum storage of about 2,050 GL (surcharged to 118 per cent of capacity) in April 2011. Consistent with past practise, there will be gradual reductions in the release along the Lower Darling River in April and May to minimise the potential for riverbank damage. Depending on further inflows, this gradual reduction is expected result in the release of some water held in surcharge. However it is expected that the lakes will be above Full Supply Level at the end of May 2011.

Page 32: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)27

Figure 15 Forecast Menindee inflows

Figure 16 Menindee Lakes outlook assuming no further inflows after July 2010.

Last Season Revised likely upper InflowRevised Likely lower Inflow

Very wet Scenario

Dry Scenario Very dry Scenario Worst case Scenario

Actuals 2010/11Moderate ScenarioNear average Scenario

Flow

(GL/

mon

th)

1600

800

600

400

200

1400

1200

1000

Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11

0

Month

INDICATIVE FORECAST ONLY: SUBJECT TO REVISION AS CONDITIONS CHANGE

Last Year Revised likely upper LevelRevised Likely lower Level

Very wet Scenario

Dry Scenario Very dry Scenario Worst case Scenario

Actuals 2010/11Moderate ScenarioNear average Scenario

Stor

age

(GL)

2500

500

2000

1500

1000

Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11

0

Month

INDICATIVE FORECAST ONLY: SUBJECT TO REVISION AS CONDITIONS CHANGE

Nominal Capacity 480 GL

NSW ML Reserve

Page 33: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)28

4.11 Flowtosouthaustralia

During both June and July 2010 the flow to South Australia was above the normal entitlement flow of 3,000 ML/day and 3,500 ML/day (Figure 17). This was to deliver 72 GL that was not delivered during 2009-10 as a result of the implementation of a new rating table for the gauging site immediately downstream of the junction of the Murray and Rufus Rivers.

Additional Dilution Flow (ADF) has been delivered to South Australia since 1 August 2010 as both the total volume of Hume and Dartmouth exceeded 2,000 GL and the volume of Menindee Lakes exceeded the monthly trigger volumes. ADF is expected to continue throughout the remainder of 2010-11, which is longer than indicated in the Very Wet scenario, due to the high inflows in the Darling persisting throughout summer.

Unregulated flows to South Australia began in September 2010 and are also likely to continue throughout the remainder of 2010-11, which is again longer than indicated in the Very Wet scenario.

The pattern of flow to South Australia has been very different to the six scenarios (Figure 17). The significant difference in volume and flow pattern is due to the relative lateness of the floods in the Murray and significant inflows from the Darling.

Figure 17 Forecast flows to Sa

Last Season Revised likely upper FlowRevised Likely lower Flow

Very wet Scenario

Dry Scenario Very dry Scenario Worst case Scenario

Actuals 2010/11Moderate ScenarioNear average Scenario

Flow

(GL/

mon

th)

2500

500

2000

1500

1000

Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11

0

Month

INDICATIVE FORECAST ONLY: SUBJECT TO REVISION AS CONDITIONS CHANGE

Entitlement

Page 34: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was

Murray–Darling Basin Authority

RMS Annual Operating Plan 2010-11 (Public Summary)29

4.12 LowerLakesandbarrageoperationinsouthaustralia

The level of the Lower Lakes increased to the Full Supply Level of 0.75m more rapidly than in the Very Wet scenario (Figure 18). Lake Albert was reconnected with Lake Alexandrina with the partial removal of the Narrung Bund in mid-September 2010. The Goolwa channel was then reconnected to the rest of Lake Alexandrina with the partial removal of the Clayton embankment in late September 2010.

There have been managed variations to the release of water through the barrages in such a way as to vary the level of the Lower Lakes between 0.65 and 0.85 m AHD since January 2011. This action has aimed to try and improve salinity levels in Lake Albert and the Coorong however it has been very difficult to implement large variations in water level due to high water levels in the Coorong as a result of extremely high tides and the relative size of the Murray Mouth compared to the flow through the Barrages. It is aimed to repeat this action several times over the coming months but the water levels in the Lower Lakes will be managed within their normal historical range.

Figure 18 Lower Lake forecast levels

Last Season Revised likely upper LevelRevised Likely lower Level

Very wet Scenario

Dry Scenario Very dry Scenario Worst case Scenario

Actuals 2010/11Moderate ScenarioNear average Scenario

Wat

er le

vel (

m A

HD

)

1.00

0.80

0.60

0.40

0.20

0.00

-0.20

-0.40

-0.60

-0.80

-1.00

Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11

-1.20

Month

INDICATIVE FORECAST ONLY: SUBJECT TO REVISION AS CONDITIONS CHANGE

Page 35: MURRAY-DARLING BASIN AUTHORITY River Murray System … · The River Murray System Annual Operating Plan for the 2010-11 (Operating Plan) water year (1 June 2010 to 31 May 2011) was