Municip For Procurement of Civil/Mech Name of Work: Operation and including vario circular sewer, of 30 MLD ST etc and all oth Name of Agency : …… …… Agreement No. : …………… -Sd- Signature of Office Assistant pal Corporation Gurgaon TENDER and CONTRACT DOCUMENT hanical/Electrical Works under Local Com Procedure. d maintenance of sewerage system o ous disposal works, S.W. pipe / R.C.C , open, piped & box drain and Operat TP E&M installation , Switch Yard , v her works contingent there to for five y ………………………………………………………… ………………………………………………………… ……………………………………………………....... Tender Notice No..…… mpetitive Bidding old Gurgaon Town C. Pipe sewer, brick tion & Maintenance valves , Horticulture years”. …….......... …….......... .... …………

Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

  • Upload
    hacong

  • View
    220

  • Download
    2

Embed Size (px)

Citation preview

Page 1: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

Municipal Corporation Gurgaon

TENDER

and

CONTRACT DOCUMENT

For Procurement of Civil/Mechanical/Electrical Works under Local Competitive Bidding

Procedure.

Name of Work: Operation and maintenance of sewerage system old Gurgaon Townincluding various disposal works, S.W. pipe / R.C.C. Pipe sewer, brickcircular sewer, open, piped & box drain and Operation & Maintenanceof 30 MLD STP E&M installation , Switch Yard , valves , Horticultureetc and all other works contingent there to for five years”.

Name of Agency : ………………………………………………………………..........

………………………………………………………………..........Agreement No. : ………………………………………………………………..........

-Sd-

Signature of Office Assistant Tender Notice No..……………

Municipal Corporation Gurgaon

TENDER

and

CONTRACT DOCUMENT

For Procurement of Civil/Mechanical/Electrical Works under Local Competitive Bidding

Procedure.

Name of Work: Operation and maintenance of sewerage system old Gurgaon Townincluding various disposal works, S.W. pipe / R.C.C. Pipe sewer, brickcircular sewer, open, piped & box drain and Operation & Maintenanceof 30 MLD STP E&M installation , Switch Yard , valves , Horticultureetc and all other works contingent there to for five years”.

Name of Agency : ………………………………………………………………..........

………………………………………………………………..........Agreement No. : ………………………………………………………………..........

-Sd-

Signature of Office Assistant Tender Notice No..……………

Municipal Corporation Gurgaon

TENDER

and

CONTRACT DOCUMENT

For Procurement of Civil/Mechanical/Electrical Works under Local Competitive Bidding

Procedure.

Name of Work: Operation and maintenance of sewerage system old Gurgaon Townincluding various disposal works, S.W. pipe / R.C.C. Pipe sewer, brickcircular sewer, open, piped & box drain and Operation & Maintenanceof 30 MLD STP E&M installation , Switch Yard , valves , Horticultureetc and all other works contingent there to for five years”.

Name of Agency : ………………………………………………………………..........

………………………………………………………………..........Agreement No. : ………………………………………………………………..........

-Sd-

Signature of Office Assistant Tender Notice No..……………

Page 2: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

MUNICIPAL CORPORATION GURGAON, HARYANA

BID ISSUE DATE :

LAST DATE OF BID SUBMISSION :

DATE OF TECHNICAL BID OPENING :

Operation and maintenance of sewerage system oldGurgaon Town including various disposal works, S.W.pipe / R.C.C. Pipe sewer, brick circular sewer, open,piped & box drain and Operation & Maintenance of30 MLD STP E&M installation , Switch Yard , valves ,Horticulture etc and all other works contingent thereto for five years”

Page 3: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

LIST OF CONTENT

Sr. No Description Page NumberSECTION 1 Notice Inviting Tender

SECTION 2 Description of Site

SECTION 3 General Conditions of Contract

SECTION 4 Eligibility Criteria

SECTION 5 Instruction to Bidders

SECTION 6 Scope OF Work1. Name of the Contract2. Boundaries of Contract3.Contract Structure & Objectives4. Contract time frame5. Scope of Services During Contract Period6. Handling Over

SECTION 7 Special Conditions of Contract

SECTION 8 General Operation & MaintenanceProcedures

SECTION 9 PRICE BID

SECTION 10 Special Term and Conditions

Page 4: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

SECTION 1

MUNICIPAL CORPORATION GURGAON

NOTICE INVITING TENDER

Online bids are hereby invited on behalf of Commissioner MCG for the following work asmentioned below:-

Name of Work: Operation and maintenance of sewerage system old Gurgaon Townincluding various disposal works, S.W. pipe / R.C.C. Pipe sewer, brick circular sewer,open, piped & box drain and Operation & Maintenance of 30 MLD STP E&Minstallation , Switch Yard , valves , Horticulture etc and all other works contingent thereto for five years”

ASr. No. of

workEstimated

CostRs. in Lacs

EarnestMoney

Rs.

TenderDocument

Feein Rs.

During date & Time

Downloading ofTender Document &Payment of TenderDocument fees

Online Bidpreparation and hashsubmission

1 - 2500000/- 25000/- Up to 15-06-2013at 17:00 PM

Up to 16-06-2013at 17:00 PM

1. Tender documents can be seen on website: http://mcg.gov.in anddownloaded online from the Portal: http://mcg.etenders.in by the Firms /Individual registered on the Portal.

2. As the Bids are to be submitted online and are required to be encrypted anddigitally signed, the Bidders are advised to obtain Digital Signature Certificate (DSC)at the earliest. For obtaining Digital Certificate, the Bidders should follow point No. 3under "Annexure-A - Conditions of e-tendering".

Page 5: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

3. Key Dates

Sr.No.

MCG State Contractor Stage Start Date andTime

Expiry Date andTime

1 Release of Tenderdocument

21-05-2013 09:00Hrs.

23-05-2013 19:00Hrs.

2

-

Downloading ofTender Documentsalongwith Tender

fees

23-05-2013 19:01Hrs.

15-06-2013 17:00Hrs.

Prebid meeting 05-06-2013 at 15.00 Hrs.Addendum if any

3-

Online BidPreparation & Hash

Submission

23-05-2013 19:01Hrs.

16-06-2013 17:00Hrs.

4 Technical & FinancialLock - 17-06-2013 09:00

Hrs.17-06-2013 17:00Hrs.

5 - Re-Encryption ofOnline Bids

17-06-2013 17:01Hrs.

19-06-2013 17:00Hrs.

6

-

Manual Submissionof EMD &AdditionalDocuments

18-06-2013 09:01Hrs.

19-06-2013 17:00Hrs.

7 Open EMD &Technical/PQ Bid - 20-06-2013 09:00

Hrs21-06-2013 17:00Hrs.

8 Eligibility criteriaevaluation - 20-06-2013 09:00

Hrs21-06-2013 17:00Hrs.

9 Open Financial/Price-Bid - 24-06-2013 09:00Hrs

24-06-2013 17:00Hrs.

1. The Bidders can download the tender documents from the Portal:http://mcg.etenders.in. Tender Documents Fees has to be paid online throughpayment gateway during the "Downloading of Tender Document & Payment ofTender Document fees" stage and Earnest Money Deposit has to be submitted throughDemand Draft in the name of Commissioner, Municipal Corporation Gurgaon.

a) Name of a/c holder from whose a/c payment for earnest money has been made bythe agencyb) A/C No.c) Name of the Bankd) Transaction IDe) Date of time of transactionf) Mode of payment is through RTGS, Demand Draft, Net banking, Credit card etc.g) Amount of Payment

Page 6: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

Willing Contractors shall have to pay the Tender Document Fees through paymentgateway during the "Downloading of Tender Document & Payment of Tender Documentfees" stage. However, as the details of the EMD are required to be filled at the time of BidPreparation and Hash Submission stage, the Bidders are required to keep the EMD detailsready beforehand.

5. The tender shall be submitted by the bidder in the following three separate envelopsonline:

1. Earnest Money and all the documentsin support of eligibility criteria - Envelope 'ED'

2. N.I.T. and Technical Bid - Envelope 'T I'3. Price Bid - Envelope 'C I'

Note:- Online Bidders shall submit the EMD or through RTGS/Net Banking/Credit card. Documents in support of eligibility criteria shall also be submitted inEnvelope 'ED'. Price Bids are to be submitted mandatory online and shall not beaccepted in any physical form.

Reference of the EMD is to be mentioned online.

The envelopes 'ED' & 'TI' shall be kept in a big outer envelop, which shall also be sealed. Inthe first instance, the Envelop - 'ED' of all the Bidders containing the Earnest Money anddocuments supporting eligibility criteria shall be opened online. If the Earnest Money andeligibility of bidder is found proper, the Envelop 'TI' containing Technical Bid shall beopened in the presence of such bidders who either themselves or through theirrepresentatives choose to be present. The Technical and Financial bid shall be opened onlyif the bidders meet the eligibility criteria as per the Bid document.

The bidder will submit the necessary documents as under.

Envelope 'ED' - Earnest Money Deposit and eligibility criteria Envelop

Online EMD Envelope-Reference details of the Earnest Money Deposit instrument andscanned copy of documents supporting eligibility criteria.

Envelope 'TI' - Technical Bid Envelope

Page 7: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

Online Technical Envelope - All the information and scanned copies of the Documents /Certificates as required to be submitted as per the Tender. Also, all such documents, if any,that cannot be submitted online i.e. all the Information and Documents / Certificates asrequired to be submitted in physical technical envelope as per the Tender.

Envelope 'CI' - Price Bid Envelope

To be submitted mandatory online- "Information related to Price Bid of the Tender". TheEnvelopes "ED" & "TI" shall be placed in another envelop of bigger size clearly marking thename of agency & name of work. In case, the Bidders have submitted all the informationand documents/ certificates required as a part of Technical Bid online, physical Envelope"TI" shall be submitted clearly marking "Blank".

The bidder can submit their tender documents as per the dates mentioned in the scheduleabove.

Terms & Conditions:A. The detail tender notice can be seen on website: http://mcg.gov.inB. Possession of Digital Signature Certificate (DSC) and registration of the contractors

on the portal i.e. http://mcg.etenders.in is a prerequisite for e-tendering. Kindlycontact o/o Nextenders (India) Pvt. Ltd., O/O Old Municipal Corporation,Faridabad, Near Neelam Bata Chowk, Faridabad Contact persons: Sh. Sanjay Kumar– 8743042801.

C. For any other queries, please contact Executive Engineer, Div. No. 2, MunicipalCorporation Gurgaon Tel.(O) 0124-2380492 Tel (M) 9717932333 Address:- NearHUDA Community Centre, Sector 39, Gurgaon. For further details and e-tenderingschedule, visit website http://mcg.etenders.in

D. All bids must be accompanied with Bid Security of the amount specified for the workas mentioned above in favour of Commissioner, Municipal Corporation Gurgaon.

E. It is a fixed priced contract. No Price variation Clause is applicable except change instatutory Laws, Govt levies/ Taxes through contract period, which shall beaccounted for and recovered/ paid by the department as the case may be.

F. Commissioner, Municipal Corporation of Gurgaon reserves the right to reject anytender without assigning any reason before award of contract and no conditionaltender will be accepted.

Technical Criteria1. Agencies/ firms/companies which have worked in area of operation &

maintenance, cleaning of sewer lines by machenical device of minimum value of

Page 8: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

Rs. 1.00 Crore during last 5 years in any State/ central Govt. Deptt., Semi-Govt.Deptt. or ULBs.

ii. For operation and maintenance of Sewerage Treatment Plant (STP), the biddershould have self experience in construction or maintenance of 5 MLD (STP) duringlast 5 years from State/Cenetral Govt. / Semi-Govt./ ULB’s.

OrShould submit a MOU for backup for contract period of the tender with theorganization/ agency which have the above experience. If backup agency is out ofthis tender at any stage, the MCG reserve the right to debar/ blacklist bidder &bachup agency.

iii. The bidder should have completed similar works: -

i. Single work of value not less than Rs. 7.0 Crores in the last five years.or

ii. 2 works of value not less than Rs. 4.0 Crores each in the last five yearsor

iii. 3 works of value not less than Rs. 3 Crores each in the last five year.

iv The bidder shall submit an undertaking on a Rs. 100 non-Judicial Stamp Paperthat agency is not black Listed from any State Govt./central, semi-Govt./ ULB onthe date of submission of tender.

For the purpose of this tender, 'similar works' means the work of operation &maintenance of sewerage system with machinacial devices or laying of sewerage networkor maintenance/ construction of STP.

For and On Behalf of Commissioner MCG

-Sd-

Executive EngineerEndorsement No. Dated

A copy of above is forwarded to the following for information and widepublicity:

1. Mayor, Municipal Corporation, Gurgaon2. Commissioner, Municipal Corporation Gurgaon.3. Deputy Commissioner, Gurgaon.4. Chief Engineer, Municipal Corporation Gurgaon.5. Superintending Engineer, Municipal Corporation Gurgaon.

Page 9: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

6. Superintending Engineer, P.W.D. (B&R) Circle, Gurgaon.7. Superintending Engineer, Public Health Engineering Circle, Gurgaon.8. Superintending Engineer, Circle No. 1 & 2, HUDA, Gurgaon.9. GM, BSNL Gurgaon for taking necessary steps during execution of works.10. Chief Account Officer, Municipal Corporation Gurgaon.11. Executive Engineer III/ IV/ V/ VI, Municipal Corporation Gurgaon.12. Executive Engineer, Marketing Board, Gurgaon.13. Executive Engineer, Public Health Engineering Division, Gurgaon.14. Executive Engineer, PWD B&R Prov. Division No. 1 & 2, Gurgaon.15. Assistant Engineer- 3, 4, 8, Horiculture Municipal Corporation Gurgaon.16. Dy. Director (Audit), Municipal Corporation Gurgaon.17. Assistant Register, Cooperative Societies, Gurgaon.18. Manager, Gurgaon Distt. Co-op. L/C Federation Ltd. 209/3 Gopal Nagar,Gurgaon.19. Notice Board, Municipal Corporation Gurgaon.20. CFC, Municipal Corporation Gurgaon for publication on net.21. Various Contractors.

For and On Behalf of Commissioner MCG

Page 10: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

SECTION 2

DESCRIPTION OF GURGAON TOWN

The Municipal Corporation, Gurgaon was declared a corporation on June 2, 2008. It isskillfully Shouldering the responsibility of providing infrastructure to the residents ofGurgaon, along with other civic governing bodies. For the purpose of election of membersof its Corporation, the Gurgaon Municipal Corporation is divided into 35 wards. TheMunicipal boundary was later extended on March 20, 2010.

Now, the Municipal Corporation of Gurgaon (CORPORATION) intends to hand overApproximately 500 kms of Sewerage System (area shown on the plan) includingdistribution sewer / trunk sewers, outfall sewers, Pump houses, disposal works includingDG set machinery installed on it, Open, pipes and box type storm water drain including 30MLD UASB based STP on ‘as is where is basis’.

The sewerage infrastructure includes all type of sewer of diameter ranging from 200 mm to1800 mm and two pumping Stations at Surya Vihar, Dhanwapur STP and intermediatetemporary pumping stations at Kadipur, Mata Massani road near sector 12, VillageGurgaon near sector 5.

The Storm water system includes the open, covered drains of all sizes in the townincluding storm water pumping station at Public Health Campus.

STP:The sewage Treatment Plant to be maintained is situated near village Dhanwapur which isabout 2 Km from Gurgaon railway station.

The scheme has been executed by Haryana PHED under YAP-I, which has been partiallyfunded by the NRCD, GOI a soft loan form JBIC Japan.

The area provided for construction of 30 MLD, STP is 36 Acres. The STP has beenconstructed about 9.00 Km away from NH - 8 Road just near the Abadi of villageDhanwapur. The MPS is also located near the STP across the railway line & IPS is locatedwithin the premises of STP & shall receive the sewage through sewer by gravity.

The total discharge is expected to be about 30 MLD. The characteristic of influent sewageare expected to be as given below:-

Page 11: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

Sr.No. Particulars

1. BOD 180 mg/1

2. COD 450 mg/l

3. TSS 300 mg/l

4. PH 8.04

5. Temperature 250 C

6. Alkalinity 1200mg/l as CACO3

7. Sulphates 75 mg/l

8. Chlorides 145 mg/l

9. Calcium 153 mg/l

10. Magnesium 35 mg/l

11. HN3 - N 64 mg/l

UASB STP of 30 MLD has been constructed so that the effluent sewage has the followingcharacteristics.

BOD not more than 30 mg/1

TSS not more than 50 mg/1

Brief Description about the UASB System

The up flow Anaerobic Sludge Blanket (UASB) process is an Anaerobic Treatment Systemwherein the organic matter is digested, absorbed and metabolized into bacterial cell massand biogas. The domestic wastewater treated in a UASB reactor is suitable for discharge inriver water or for irrigation after polishing in high rate pond. The Biogas generated can beutilized for generating electricity. Sludge cakes after dewatering and drying on sludgedrying beds will be suitable to be used in fields as manure. The UASB system also does notrequire any external energy and mechanical equipment. It also has a modular constructionand occupies less space. The maintenance requirements are less as compared to theconventional systems.

Page 12: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

The UASB process is a combination of physical and biological processes. The main featureof physical process is separation of solids and gases from the 1iquid and that of biologicalprocess is degradation of decomposable organic matter under anaerobic conditions.

In the UASB treatment concept, the treatment tank consists of an up flow reactor with afeed inlet distribution system at the bottom of the reactor and a three-phase gas-liquid-solids separator (GLSS) at the top. The waste water is evenly distributed over the reactorbottom through feed inlet pipes and flows upward through a bed of anaerobic sludge inthe lower part of the record called the digestion compartment. During passage through thesludge bed particular matter is entrapped and the degradable matter is completely orpartially digested. Dissolved organic matter is removed from the solution by the anaerobicbacteria and converted into biogas and a small fraction into new bacterial biomass. Thebiogas phase Gas-Liquid-Solid Separator (GLSS) is installed. The biogas product iscollected in a gas collector gas (Gas Hood) from where it is withdrawn. The remainingwater-sludge mixture enters a setting compartment where the sludge can settle and flowback into the digestion compartment. After setting the water is collected effluent guttersand discharged out of the reactor to the final polishing unit (FPU) to meet dischargestandards.

Detail of various structures/components of STP/MPS/IPS is enclosed as Appendix “A”

APPENDIX - A

E DETAIL OF CIVIL STRUCTURES, E&M ITEMS (App. Quantity)

a) Civil Structures

Area of S.T.P. site 14.78Hect.(36.50 acres)

Length of 1.8 M. High Boundary Wall 2000M.

Main gate 3.66 m wide 1 No.

Wicket Gate 0.90 M wide 1 No.

Check post 1 No.

Road (width 3.66 M.) Length 1038 M

Path (width 1.20 m) Length 540 M.

Inlet Chamber 1.85 x 2.69 x 2.17 m

(vol. 10.80 cum)

Screen Chamber 6 x 1.85 x 1.30 ,

Page 13: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

Grit Chamber 15.32X1.5X1.47 M

Cross sectional area = 3.06 Sqm.

Division box 2 nos.(2.5 x 3.15m)

Distribution Box 5 mld. 6 nos.(3.15m x 2.50M)

UASB Reactor10 mld 3 No.

Sludge Sump 2 M. dia = 1 No.

Drain Sump 2.50 M. dia =1No.

Sludge Drying beds 22 Nos.

Area of one SDB 256 sqm.

Final polishing unit volume 30250.00 cum

Surface area 24240sqm.

Gas Holder Capacity 350 cum.

Final effluent channel length 550 M.

Width 2.00 M.

Combined channel to pond Length 150 M.

Width 2.00 M.

Common Effluent channel Length 35 M.

Display board 3 No.

Staff Qrs. 34.20 sqm. 2 No.

45.60 sqm. 4 Nos.

62.70 sqm. 1 No.

Generator Room 9 x 6 M.

Office and Lab building Area GFL 146.31

FFl 106.23252.54 sqm

Main Pumping Station

Inlet & screen channel 7.20 x 3 x 9.83 M.

Capacity of Main Sump 305.25 cum

Size 10.80x 13.20x 7.59m

Valve chamber 14.26 x 5.23 x 3.00 M

Page 14: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

D.G. set Room 3.31 x 9.03 M

MEP Room 9.03 x 5.42 M

Operation Room 9.03 x 3.31 M

Transformer Yard 14.92 x 4.23M

b) E & M Items

STP 1 No.

STP MEP 1 No.

APP Capacitor Panel 2 Nos. Discharge

Drain Pump with panel 25 cum/hour Head 9M

Sludge Pump with panel 2 Nos. Discharge50 cum/hour Head 7.50M

Mechanical screen with panel 2 Nos.

Manual Screen 1 No.

Duel Fuel engine (50 KVA) 1 Nos.

HT VCB Panel

Mechanical screen 1 No.

Manual Screen 2 No.

C.I. Gate 2 no.

Sewerage Submersible Pumps 6 Nos. discharge625cum/Head 16.60 M.

Pump Motor/HP/RPM 90 BHP

Sluice Valve 6 no. (450 mm i/d)

Non return valve 6 no. (450 mm i/d)

OTHERS

Water supply pipe line 80 mm i/d

Sluice Valve size 80 mm i/d

Fire hydrant 80mm i/d

Sewer line 200 mm i/d 350 M.

Main Holes 4 Nos.

Page 15: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

Horticultural Area 6.00 Hect.

Rising Main 700 mm i/d 135 M.

Specials –

C.I. Band 700 x 900

C.I. Collar 700 mm

C.I. Tail piece 700 mm

C.I. D/F Sluice Valve 700 mm

C.I. Duck Tee 700 x 700 x 700 mm

Intermediate Pumping station

Inlet & Screen Chamber 363.15 cum

Capacity of main sump

Valve chamber

D.G. Set Room 7.50x5.00

M.E.P. Room 10x 7.50

Operation room 4.75x 4.75

Transformer Yard 5x 5m

Manual Screen 2 Nos.

C.I Gate 2 Nos.

Sewerage Submersible Pumps 6 No. head 18 M

Pump Motor HP 2 No- 15 BHP, 2 No. -20

BHP, 2 No. 25 BHP

Sluice valve

Non return Valve 6 No. (250 mm i/d)

Rising main 600 mm i/d 550 M

Specials:-

C.I Enlarger 200x300mm

C.I Bend 600x 90

C.I Collar 600 mm

C.I Tail piece 600 mm

C.I D/F Sluice valve 600 mm

C.I D/F pipe 60 mm

Page 16: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The
Page 17: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

SECTION 3

GENERAL CONDITIONS OF CONTRACT

3.1. DEFINITIONS AND INTERPRETATION

3.1.1. Definitions

In the Contract (as hereinafter defined) the following words and expressions shall have themeanings hereby assigned to them, except where the context otherwise requires:

a)i. “Corporation or MCG” shall mean the Municipal Corporation of Gurgaon andits successor if any.

ii. “Government” shall mean the Government of Haryanaiii. “Commissioner” means Municipal Commissioner, Corporation.iv. “Engineer-In-Charge” means Chief Engineer / Executive Engineer, Corporation.

v. “Contractor” means the person whose tender has been accepted by theCorporation and the legal successors in title to such person but not (except with theconsent of the Corporation) any assignee of such person.vi. “Contractor’s Representative” means the person (if any) named as such in theContract or other person appointed from time to time by the Contractor.vii. “Subcontractor” means any person named in the Contract as Subcontractor fora part of the Works or any person to whom a part of the Works has beensubcontracted with the consent of the Engineer or MCG and the legal successors intitle to such person, but not any assignee of such person.viii. “Engineer’s Representative” means a person appointed from time to time bythe Engineer-in-Charge. Without limiting the generality of the foregoing, theEngineers Representative shall include the authorized representatives of: (I)Executive Engineer Division, Municipal Corporation, Gurgaon. (ii) ExecutiveEngineer, PWD, Water Supply and Sewerage, PHE, Government of Haryana.b)i. “Contract” means these Notice Inviting Tender, Scope of Work, Special

Conditions of Contract, General Conditions of Contract, Eligibility Criteria,Instruction to Bidder, the Bid, the Bidder’s proposal, the Schedules, the Letter of!cceptance, the Contract !greement (if completed).

ii “Corporation’s Requirements” means the description of the scope, specialconditions, standards, specifications (standard and particular), and programme of

Page 18: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

work, as included in the Contract, and any alterations and modifications thereto inaccordance with the Contract.iii. “Specification” means the specifications of the Works included in the Contractand any Modification thereof or addition thereto made by the Engineer or submittedby the Contractor and approved by the Engineer.iv. “Drawings” means all drawings provided by the Engineer to the Contractorunder the Contract and all drawings, calculations, samples, patterns, models,operation and maintenance manuals and other technical information of a like nature submitted bythe Contractor and approved by the Engineer.v. “Schedules” means the information and data submitted with the Tender, as included in theContract.

vi “Tender” means the Contractor’s priced offer to the Corporation for the execution andcompletion of the Works in accordance with the provisions of the Contract, as acceptedby the Letter of !cceptance/ The word ‘Tender’ is synonymous with ‘Bid’ and the word ‘TenderDocuments’ with ‘Bidding Documents’/

vii. “Letter of !cceptance” means the formal acceptance by the Corporation of the Tender.viii. “Contract !greement” means the contract agreement (if any) referred to in Sub-Clauseix. “Appendix to Tender” means the completed appendix comprised in the form of Tender

annexed to these Conditions/ The words “!ppendix to Tender” are synonymous with the words“!ppendix to Technical Proposal” and “!ppendix to Price Proposal”/

x. “Schedule of Payments’ means the Schedule designated as such,xi. “Effective Date” means the date on which the Contract entered into legal force and effect.

c)i. “Commencement Date” means the date specified in the notice to commence issued by the Engineer-In-Charge to the Contractor.

ii. “Contract Period” means the period from the Commencement date to the date 5 years after the dateduring which all responsibility for works, as specified in the contract shall be with the contractor.

d)i. “Contract Price” means the sum stated in the Letter of !cceptance as payable to the

Contractor for the Works in accordance with the provisions of the Contract.ii. “Interim Payment Certificate” means any payment certificate issued by the Engineer

under Sub-Clause 24.6, other than the Final Payment Certificate.iii. ”Final Payment Certificate” means the payment certificate issued by the Engineer under Sub-Clause 24.12.

iv. “Final Statement” means the agreed statement defined in Sub-Clause 24.12.

e)i. “Works” means the Permanent Works and the Temporary Works or either of them as

appropriate.ii. “Permanent Works” means the permanent Works to be executed (including pipes, earthwork,

pumping plant) in accordance with the Contract.iii. “Temporary Works” means all temporary Works of every kind (other than Contractor’s

Equipment) required in or about the completion of the Works in accordance with the contract.iv. “Variation” means any alteration and/or modification to the Corporation’s Requirements, which is

instructed by the Engineer-in-charge or approved as a variation by the Engineer- in-charge.

Contract and all drawings,calculations, samples, patterns,models, operation and

Page 19: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

v. “Materials” mean things of all kinds which are to be supplied by the Contractor as specified in theContract.vi. “Contractor’s Equipment” means all appliances and things of whatsoever nature (other

than Temporary Works) required for the completion of the Works, in accordance with the contract’, butdoes not include materials or other things intended to form or forming part of the Permanent Works.vii. “Site” means the places provided by the corporation where the Works are to be executed.f)

i. “Cost” means all expenditures properly incurred or to be incurred, whether on or off the Site,including overhead and other charges properly allocable thereto but does not include any allowance forprofit.

ii. “Day” means calendar day and “year” means 365 days.iii. “Writing” means any hand written, type written, or printed communication, including telex, cable,and facsimile transmission.

iv. “Utility” means the service provided by a companyv ‘System” means computer.iv. “Software” means written programs or procedures pertaining to the operation of a

computer system and that are stored in read/write memory.vii. ‘Integration” means combining hardware or software components or both into an overall

system.viii. “!pplication software” means subclass of computer software that employs the capabilities of acomputer directly to a task that the user wishes to perform.ix. “Database” means a set of related files that is created and managed by a database

management system.x. “Computerised Record” means a set of information being stored in the computer in MS Word/MS Excel

3.1.2. Headings and Marginal Notes

The headings and marginal notes in these Conditions shall not be deemed part thereof or be taken intoconsideration in the interpretation or construction thereof or of the Contract.

3.1.3. Interpretation

Words importing persons or parties shall include firms and corporations and any legal entity and anyorganization having legal capacity.

3.1.4. Singular and Plural

Words importing the singular only also include the plural and vice versa where the context requires.

3.1.5. Notices, Consents, Approvals, Certificates and DeterminationsWherever in the Contract provision is made for the giving or issue of any notice, consent, approval, certificateor determination by any person, unless otherwise specified such notice, consent, approval, certificate ordetermination shall be in writing and the words “notify”, “certify” or “determine” shall be construedaccordingly/ !ny such consent, or determination shall not unreasonably be withheld or delayed.

Page 20: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

3.2. Engineer-In-Charge and Engineer –in-Charge’s Representative

3.2.1. Duties and Authority(a) The Engineer-In-Charge shall carry out the duties specified in the Contract.

(b) The Engineer may exercise the authority specified in or necessarily to be implied from the Contract,Provided further that any requisite approval shall be deemed to have been given by the MCG for any suchauthority by the Engineer-In-Charge.(c) Except as expressly stated in the Contract, the Engineer-In-Charge shall have no authority to relieve theContractor of any of his obligations under the Contract.

3.2.2. Engineer –in-Charge’s Representative

The Engineer –in-Charge’s shall be appointed by and be responsible to the Engineer-In-Charge and shall carryout such duties and exercise such authority as may be delegated to him by the Engineer-In-Charge

3.2.3. Engineer –in-Charge’s Authority to Delegate

The Engineer-In-Charge may from time to time delegate to the Engineer-In-Charge’s Representative any of theduties and authorities vested in the Engineer-In-Charge and he may at any time revoke such delegation. Anysuch delegation or revocation shall be in writing with prior consent of the employee and shall not take effectuntil a copy thereof has been delivered to the Corporation and the Contractor. Any communication given by theEngineer-In-Charge’s Representative to the Contractor in accordance with such delegation shall have the sameeffect as though it had been given by the Engineer. Provided that:

(a) any failure of the Engineer-In-Charge’s Representative to disapprove any work, materials or Plantshall not prejudice the authority of the Engineer to disapprove such work, materials or Plant and to giveinstructions for the rectification thereof;(b) if the Contractor questions any communication of the Engineer-In-Charge’s Representative he mayrefer the matter to the Engineer who shall confirm, reverse or vary the contents of such communication.

3.2.4. Appointment of Assistants

The Engineer or the Engineer’s Representative may appoint any number of persons to assist the Engineer’sRepresentative in the carrying out of his duties. He shall notify to the Contractor the name, duties and scope ofauthority of such persons. Such assistants shall have no authority to issue any instructions to the Contractor savein so far as such instructions may be necessary to enable them to carry out their duties and to secure theiracceptance of materials, Plant or workmanship as being in accordance with the Contract, and any instructionsgiven by any of them for those purposes shall be deemed to have been given by the Engineer’s Representative.

3.2.5. Instructions in Writing

Instructions given by the Engineer-In-Charge shall be in writing, provided that if for any reasonthe Engineer considers it necessary to give any such instruction orally, the Contractor shall comply with suchinstruction. Confirmation in writing of such oral instruction given by the Engineer, whether before or after thecarrying out of the instruction, shall be deemed to be an instruction within the meaning of this Sub-Clause.Provided further that if the Contractor, within 7 days, confirms in writing to the Engineer any oral instruction ofthe Engineer and such confirmation is not contradicted in writing within 7 days by the Engineer, it shall bedeemed to be an instruction of the Engineer. Unless it is legally or physically impossible the Contractor shallcomply with instructions given by the Engineer in accordance with the Contract.

The provisions of this Sub-Clause shall equally apply to instructions given by the Engineer-In-Charge’srepresentative and any assistants of the Engineer-in-Charge.

3.2.6. Engineer to Act Impartially

Page 21: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 1 -Wherever, under the Contract, the Engineer-In-Charge is required to exercise his discretion by: a. givinghis decision, opinion or consent, or

b. expressing his satisfaction or approval, orc. determining value, Cost or extension of time, or

d. Otherwise taking action which may affect the rights and obligations of the MCG or the Contractor, heshall consult with the Contractor in an endeavor to reach agreement and shall exercise such discretionimpartially within the terms of the Contract and having regard to all the circumstances. Any suchdecision, opinion, consent, expression of satisfaction, or approval, determination of value or action maybe opened up, reviewed or revised.

3.2.7. Direction and control of Engineer-In-charge

All work to be executed under the contract shall be executed under the direction and subject to theapproval in all respects of the Engineer-In-Charge for the time being, who shall be entitled to direct atwhat point or points and in what manner they are to be commenced, and from time to time carried on.The Engineer-In-Charge is authorized to engage any third party agency for conducting the relevant testsfor different activities of the works. The charges will be paid in accordance with Payment Terms.

3.3. Assignment and Subcontracting

3.3.1 Assignment of contract

The Contractor shall not, without the prior consent of the Corporation (which consent notwithstandingthe provisions Contract shall be at the sole discretion of the MCG), assign the Contract or any partthereof, or any benefit or interest therein or thereunder, otherwise than by:(a) a charge in favor of the Contractor’s bankers of any moneys due or to become due under the contract,or(b) Assignment to the Contractor’s insurers (in cases where the insurers have discharged the Contractor’sloss or liability) of the Contractor’s right to obtain relief against any other

3.3.2 Subcontracting

The contractor shall not sub-contract the whole of the work or any part of the workswithout the prior consent of the Engineer, except where otherwise provided by the Contract. Any such consentshall not relieve the Contractor from any liability or obligation under the Contract and he shall be responsible forthe acts, defaults and neglects of any Subcontractor, his agents, servants or workmen as fully as if they were theacts, defaults or neglects of the Contractor, his agents, servants or workmen.Provided that the Contractor shall not be required to obtain such consent for:(a) the provision of labour, or(b) the purchase of materials which are in accordance with the standards specified in the Contract, or

(c) the subcontracting of any part of the Works for which the Subcontractor is named in the Contract.In the event of a Subcontractor having undertaken towards the Contractor in respect of the work executed, or

the goods, materials, Plant or services supplied by such Subcontractor, any continuing obligation extending for aperiod exceeding that of the Defects Liability Period under the Contract, the Contractor shall at any time, afterthe expiration of such Period, assign to the MCG, at the MCG’s request and cost, the benefit of such obligationfor the un-expired duration thereof.

3.4 Contract Documents

3.4.1 Language of Law

(a) The English or Hindi language shall be used in the contract documents

Page 22: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 2 -and all official correspondence

(b) The law which shall apply to the Contract and according to which the Contract shall beconstrued is that in force in India.

3.4.2 Priority of Contract DocumentsThe several documents forming the contract are to taken as mutually explanatory ofanother, but in case of ambiguities or discrepancies the same shall be explained andadjusted by the Engineer who shall thereupon issue to the Contractor instructions thereonand in such event, unless otherwise provided in the Contract, the priority of the documentsforming the Contract shall be as follows:

i. Signed Form of Agreementii. Letter of Acceptanceiii. Contractor’s bid, !ppendix to bid and the Schedulesiv. Abstract of Tenderv. Special Conditions of Contractvi. Scope of Servicesvii. General Conditions of Contractviii. Price Bid

3.5 Contractor’s General Responsibility

The Works as completed by the Contractor shall be wholly in accordance with the Contractand fit for the purposes for which they are intended, as defined in the Contract. The Worksshall include any work which is necessary to satisfy the Corporation’s Requirements,Contractor’s Proposal and Schedules, or is implied by the Contract, or arises from anyobligation of the Contractor, and all works not mentioned in the Contract but which may beinferred to be necessary for stability or completion or the safe, reliable and efficientoperation of the Works. Before commencing design, the Contractor shall satisfy himselfregarding the Corporation’s Requirements and actual site conditions. The Contractor shallgive notice to the Engineer-In- Charge of any error, fault or other defect in the CorporationsRequirements in contract document.

3.6. Site Operations and Methods of Operation and Maintenance

The contractor shall be fully responsible for adequacy, stability and safety of all siteoperations, of all methods of operation and maintenance and of all the Works under thecontract. Compliance with this clause only, shall not relieve the Contractor of his duties,obligations or responsibilities under the Contract.

3.7. Performance Security

The Contractor shall provide security for his proper performance of the Contract to theCorporation within 14 (Fourteen) days after the receipt of the Letter of Acceptance. Theperformance security shall be total 5% of the Contract Price in the form of an irrevocableand Unconditional Bank Guarantee from the contractor / Firms issued by any NationalizedBanks / from all Banking Companies Registered under Company’s !ct 1956/ The Bankguarantee shall be provided shall be valid until completion of the Contract Period. The

Page 23: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 3 -forms of performance security provided, with the tender document shall be used. Theinstitution providing such guarantee shall be subject to the approval of the MCG. The costof complying with the requirements of this Clause shall be borne by the Contractor. Nointerest will be payable on the performance security.

3.7.1. Claim Under Performance Security

Prior to including a claim under the Performance Security the MCG shall, in every case,notify the Contractor stating the nature of the default in respect of which the claim is to bemade

3.8. Inspection of SiteThe Corporation shall have made available to the Contractor, before the submission by the Contractor of theTender, such data on hydrological and sub-surface conditions as have been obtained by or on behalf of theCorporation from investigations undertaken relevant to the Works; but the Contractor is advised forcollection of actual site data, through its own resources, for carrying out any additional surveys and tests, andfor his own interpretation thereof.The Contractor shall be deemed to have inspected and examined the Site and its surroundings andinformation available in connection therewith and to have satisfied himself so far as is practicable beforesubmitting his Tender, as to:

i. the form and nature thereof, including the sub-surface conditions,ii. the hydrological and climatic conditions,iii. the condition of sewer network laidiv. the condition of all civil, mechanical, electrical, instrumentation systems

v. the extent and nature of work and materials necessary for the execution and completion of theWorks, andvi. the means of access to the Site and the accommodation he may require and, in general, shall bedeemed to have obtained all necessary information, subject as abovsmentioned, as to risk, contingencies and all other circumstances which may influenceor affect his Tender.

3.9 Sufficiency of Tender

The contractor shall be deemed to have satisfied himself as to the correctness and ofthe contract Price. Unless otherwise stated in the contract, the contract Price shall cover allhis obligation under the contract (including those under Provisional sums, if any) And allthingsnecessary for the proper execution of the work, in accordance with the contract clauses

3.10. Adverse Physical Obstruction or Contract.

If, however , during the execution of the contractor encounter physical obstructions orphysical conditions, including climatic condition on the site, which obstruction or condition,were in his opinion, not foreseeable by contractor, Nothing shall be payable extra on thisaccount.

3.11. Programme to be submitted

Page 24: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 4 -The contractor shall submit a programme to the Engineer, for information and gotapproved,Within 14 days of award of the work to his favor. The programme shall include thefollowing:

a. Status of Existing Sewer network based on reconnaissance survey.b. Order in which the contractor proposes to carry out the workc. The preventive maintenance schedulesd. All major events and activities involvede. Reporting formats and reporting schedule

The Contractor shall, whenever required by the Engineer-In-Charge, provide in writing, for information, ageneral description of the arrangements and methods which the Contractor proposes to adopt for the executionof the Works. No alteration to the programme, or to such arrangements and methods, shall be made withoutinforming the Engineer-In-Charge.

3.11.1. Contractor Not Relieved of Duties or Responsibilities

The submission to and consent by the Engineer of such Programmes/ Documents shall not relieve theContractor of any of his duties or responsibilities under the Contract.

3.12. Reports to be Submitted

The Contractor shall maintain a daily log of the labour, equipment and materials supplied to and used at the site.Bi-Monthly progress reports shall be prepared by the Contractor and submitted to the Engineer as per conditionsindicated in special conditions of contract. Each report shall include:

a. photographs and detailed descriptions of progress,b. charts showing the status of works,c. records of personnel and Contractor’s Equipment on Site-d. safety statistics, including details of any hazardous incidents and activities relating to environmental aspects

and public relations; ande. Comparisons of actual and planned progress, with details of any aspects which may jeopardize the completionin accordance with the Contract and the measures being (or to be) adopted to overcome such aspects.

3.13. Contractor’s Representative

Unless the Contractor’s Representative is named in the Contract, the Contractor shall, within 14 days of theEffective Date, submit to the Engineer for consent the name and particulars of the person the Contractorsproposes to appoint, in the capacity of Project Manager.

The Contractor's Representative is named in the Contract, the Contractor shall, within 14and execution of the Works and as long thereafter as the Engineer may consider necessary for the properfulfilling of the Contractor’s obligations under the Contract/ The Contractor’s Representative shall give hiswhole time to the superintendence of the Works. Such authorized representative shall receive, on behalf of theContractor, instructions from the Engineer or, subject to the provisions of special conditions of contract. TheContractor shall not revoke the appointment of the Contractor’s Representative without the prior consent of theEngineer.

If approval of the Representative is withdrawn by the Engineer, the Contractor shall, as soon as is practicable,having regard to the requirement of replacing him as hereinafter mentioned, after receiving notice of suchwithdrawal, remove the Representative from the Works and shall not thereafter employ him again on the Worksin any capacity and shall replace him by another Representative approved by the Engineer.

Page 25: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 5 -

3.14. Contractor’s Employees

The Contractor shall provide on the Site in connection with design, execution and completion of the Works andthe remedying of any defects therein:

only such technical assistants as are skilled and experienced in their respective callings and suchforemen and leading hands as are competent to give proper superintendence of the Works; and such skilled, semi-skilled and unskilled labour as are necessary for the proper and timelyfulfilling of the Contractor’s obligations under the Contract

3.15. Engineer at Liberty to Object

The Engineer shall be at liberty to object to and require the Contractor to remove forthwith from the Works anyperson provided by the Contractor who, in the opinion of the Engineer, misconduct’s himself, or is incompetentor negligent in the performance of his duties, or whosepresence on Site is otherwise considered by the Engineer to be undesirable, and such person shall not be againallowed upon the Works without the consent of the Engineer. Any person so removed from the Works shall bereplaced immediately. Severe penalty, shall be imposed if any contractor worker/ personnel is found inintoxicated state during official working hours.

3.16. Safety, Security and Protection of the Environment

The Contractor shall comply with all applicable safety and environmental regulations in his design, accessarrangements and operations on the Site. Unless otherwise stated in special conditions of contract; the Contractorshall, throughout the completion of the Works, in accordance with tender:

a. be responsible for keeping unauthorized persons off the Site;b. limit authorized persons to the employees of the Contractor, employees of his Subcontractors and persons

authorized by the corporation or the Engineer;c. have full regard for the safety of all persons entitled to be upon the Site and keep the Site (so far as the same isunder his control) and the Works (so far as the same are not completed or occupied by the corporation) in anorderly state appropriate to the avoidance of danger to such persons;d. provide and maintain at his own cost all lights, guards, fencing, warning signs, watching, when and wherenecessary or required by the Engineer or by any duly constituted authority, for the protection of the Works or forthe safety and convenience of the public or others;e. take all reasonable steps to protect the environment on and off the Site and to avoid damage or nuisance topersons or to property of the public or others resulting from pollution, noise or other causes arising as aconsequence of his methods of operation;f. screen all lights provided by the Contractor so as to not to interfere with any signal light on the railways or

with any traffic or signal lights of any local or other authority; andg. Ensure that air emissions, surface discharges and effluent from the Site during the Contract Period shall not

exceed the values prescribed by law.

3.17. Electricity, Water and Diesel

The Contractor shall be entitled to use for the purposes of the Works such supplies of electricity, water, gas andother services as may be available. Water at source shall be made available; the contractor shall be liable to makesuitable arrangements for transportation of this water to site of works.Record of Electricity and fuel consumed shall be maintained by the contractor, along with original bills, as proof.

The corporation shall reimburse the expenditure made on fuel and electricity used for running the pumpingplants shall be paid to DHBVNL by CORPORATION but the electric bills shall be arranged by the contractorfrom DHBVNL office well in time. The penalty/ surcharge imposed on account of delay payment shall berecovered from theContractorHowever, the cost of fuel consumed for running of machines, vehicles and equipment’s for sewer and storm

Page 26: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 6 -water cleaning shall not be reimbursed.

3.18. Responsibility to Rectify Loss or Damage

incorporation therein, during the period for which the Contractor is responsible for the care thereof, due tonegligence on part of Contractor/ Contractor’s representative, the Contractor shall, at his own cost, rectify suchloss or damage so that the Works conform in every respect with the provisions of the Contract to the satisfactionof the Engineer-in-Charge. The Contractor shall also be liable for any loss or damage to the Works occasioned byhim in the course of any operations carried out by him for the purpose of complying with his obligations.

The risks are:a. in so far as they directly affect the Works in the country where the Works are executed:

war and hostilities (whether war be declared or not), invasion, act of foreign enemies; rebellion, revolution, insurrection, or military or usurped power, or civil war;

ionising radiation, or contamination by radioactivity from any nuclear fuel, or from any nuclear waste fromthe combustion of nuclear fuel, radioactive toxic explosive or other hazardous properties of any explosivenuclear assembly or nuclear component thereof; pressure waves caused by aircraft or other aerial devices travelling at sonic or supersonic speeds; riot, strike, commotion or disorder, unless solely restricted to the employees of the Contractor or of hisSubcontractors and arising from the conduct of the Works; death of or injury to any person, or loss of or damage to any property (other thanthe Works), Which may arise out of or in consequence of theexecution and completion of the Works and the remedying of any defects therein, and against all claims,proceedings, damages, costs, charges and expenses whatsoever in respect thereof or in relation thereto, loss ofor damage to any property (other than the Works), Which may arise out of or in consequence of the executionand completion of the Works and the remedying of any defects therein, and against all claims, proceedings,damages, costs, charges and expenses whatsoever in respect thereof or in relation thereto,

3.19. Insurance to Be Taken Out by the Contractor:-

The Contractor shall take out and, during the period of effectiveness of this Contract, appropriate insurancecoverage, which coverage shall include such insurance as may be required by the law of the country ofincorporation of the Contractor and, in addition, the minimum coverage described in the Works contract for theWorks.

3.20. Establishment of Office: -

The bidder shall establish its office within the limits of Municipal Corporation Gurgaon

3.2. Contractor’s Obligations

3.2.1. Compliance with Statutes, Regulations

The Contractor shall conform in all respects, including by the giving of all notices andthe paying of all fees, with the provisions of:

a. any National or State Statute, Ordinance, or other Law, or any regulation,or bye law of any local or other duly constituted authority in relation to theexecution and completion of the Works and the remedying of any defectstherein, and

Page 27: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 7 -b. the rules and regulations of all public bodies and companies whoseproperty or rights are affected or may be affected in any way by the Works,

and the Contractor shall keep the Corporation indemnified against all penalties andliability of every kind for breach of any such provision. Provided always that theCorporation shall be responsible for obtaining any planning, zoning or other similarpermission required for the Works to proceed and shall indemnify the Contractor inaccordance with Sub- Clause 1.23.

3.2.2. Contractor’s Operations on Site

The Contractor shall confine his operations to the Project Area, and to any additionalareas which may be provided by the Contractor and agreed by the Engineer asworking areas. The Contractor shall take all necessary precautions to keep hispersonnel and equipment within the Site and such additional areas, and to keep andprohibit them from encroaching on adjacent land.

3.2.3. Equipment purchased for the services.

All equipment and materials provided by the Contractor as part of the Works remainsthe property of the Contractor on the successful completion of project.

3.3. Fossils

All fossils, coins, articles of value or antiquity and structures and other remains orthings of geological or archaeological interest discovered on the Site shall, as betweenthe Corporation and the Contractor, be deemed to be the absolute property of theCorporation. The Contractor shall take reasonable precautions to prevent hisworkmen or any other persons from removing or damaging any such article or thingand shall, immediately upon discovery thereof and before removal, acquaint theEngineer of such discovery and carry out the Engineer’s instructions for dealing withthe same.

3.4. Interference with Traffic and Adjoining Properties

All operations necessary for execution of the Works, in accordance with the tenderdocument, so far as compliance with the requirements of the Contract permits, becarried on so as not to interfere unnecessarily or improperly with:

a. the convenience of the public, orb. the access to, use and occupation of public or private roads, railways,footpaths and any other right of way to or of properties whether in thepossession of the corporation or of any other person.

The Contractor shall save harmless and indemnify the corporation in respect of allclaims, proceedings, damages, costs, charges and expenses whatsoever arising out of,or in relation to, any such matters insofar as the Contractor is responsible therefor.

Page 28: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 8 -3.5. Opportunities for Other Contractors

The Contractor shall, in accordance with the requirements of the Engineer, afford allreasonable opportunities for carrying out their work to:

a. any other contractors employed by the Corporation and their workmen,b. the workmen of the Corporation, andc. the workmen of any duly constituted authorities who may be employedin the execution on or near the Site of any work not included in the Contract orof any contract which the Corporation may enter into in connection with orancillary to the Works.d. The right to appoint or entrust any part of the work neither repair nornew nature of works to the same Contractor or any other Contractor forsatisfactory completion of the system shall be rest with the Corporation. Thesuccessful Bidder shall bound to co-ordinate for smooth completion of theworks by the other Contractor. This activity shall be controlled and monitoredby the Engineer-in-charge.

3.6. Contractor to Keep Site Clear

During the execution of the Works the Contractor shall keep the Site free from allunnecessary obstruction and shall store or dispose of any Contractor’s Equipmentand surplus materials and clear away and remove from the Site any wreckage,rubbish or Temporary Works no longer required.

3.7. Epidemics

In the event of any outbreak of illness of an epidemic nature, the Contractor shallcomply with such regulations and carry out such orders as are issued by theGovernment or Local Authority.

3.8. LABOUR

3.8.1. Engagement of Staff and Labour

The Contractor shall make his own arrangements for the engagement of all staff andlabour, local or other, and for their payment, housing, feeding, water and transport.

3.8.2. Compliance With Labour Regulations

The Contractor and his Sub-contractors shall abide by the local laws and regulationsgoverning labour as detailed in Annexure A and Annexure A- I.

3.8.3. Returns of Labour and Contractor’s Equipment

The Contractor shall, if required by the Engineer, deliver to the Engineer a return indetail, in such form and at such intervals as the Engineer may prescribe, showing thestaff and the numbers of the several classes of labour from time to time employed by

Page 29: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 9 -the Contractor on the Site and such information in respect of Contractor’s Equipmentas the Engineer may require.

3.8.4. Persons in the Service of Others

The Contractor shall not recruit, or attempt to recruit, his staff and labour fromamongst persons in the service of the Corporation or the Engineer-In-Charge.

3.8.5. Disorderly Conduct

The Contractor shall at all times take all reasonable precaution to prevent anyunlawful, riotous or disorderly conduct by or amongst his staff and labour, and topreserve peace and protection of persons and property in the neighborhood of theWorks against such conduct. No person shall be found in intoxicated state duringofficial duty hours.

3.9. Materials, Plant and Workmanship

3.9.1. Delivery to Site

The Contractor shall be responsible for procurement, transport, receiving, unloadingand safe keeping of all Plant, Materials, Contractor’s Equipment and other thingsrequired for the completion of the Works.

3.9.2. Ownership of Plant and Materials

Each item of Plant and Materials brought by the Contractor for the purpose of worksshall remain the property of the Contractor.

3.9.3. Quality of Materials, Plant and Workmanship

All Plant and Materials to be supplied shall be manufactured, and all work to be doneshall be executed, in the manner set out in the Contract. Where the manner ofmanufacture and the execution is not set out in the Contract, the work shall beexecuted in a proper, workmanship like and careful manner, with properly equippedfacilities and non-hazardous materials and in accordance with recognized goodpractice.

All materials, Plant and workmanship shall be:a. of the respective kinds described in the Contract and in accordance withthe Engineer’s instructions, and

The Contractor shall provide all documents and other information necessary fortesting and such assistance, labour, electricity, fuels, stores, apparatus andinstruments as are normally required for examining, measuring and testing anymaterials or Plant and shall supply samples of materials, before incorporation in theWorks, for testing as may be selected and required by the Engineer.

Page 30: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 10 -

The Contractor is encouraged, to the extent practicable and reasonable, to use plantand materials from sources within India.

3.9.4. Cost of Tests

The cost of making any test shall be borne by the Contractor if such tests are intendedto satisfy the Corporations Requirements and the Contractor’s responsibilities underthe Contract.

3.9.5. Inspection of Operations

The Engineer, and any person authorized by him, shall at all reasonable times haveaccess to the Site of operations. The Contractor shall afford every facility for andevery assistance in obtaining the right to such access.

3.9.6. Inspection and Testing

The Engineer shall be entitled, during manufacture, fabrication or preparation toinspect and test the materials and Plant to be supplied under the Contract. If materialsor Plant are being manufactured, fabricated or prepared in workshops or places otherthan those of the Contractor, the Contractor shall obtain permission for the Engineerto carry out such inspection and testing in those workshops or places. Such inspectionor testing shall not release the Contractor from any obligation under the Contract.

3.9.7. Dates for Inspection and Testing

The Contractor shall agree with the Engineer on the time and place for inspection ortesting of any materials or Plant as provided in the Contract. The Engineer shall givethe Contractor not less than 24 hours’ notice of his intention to carry out theinspection or to attend the tests. If the Engineer, or his duly authorized representative,does not attend on the date agreed, the Contractor may, unless otherwise instructedby the Engineer, proceed with the tests, which shall be deemed to have been made inthe presence of the Engineer. The Contractor shall forthwith forward to the Engineerduly certified copies of the test readings. If the Engineer has not attended the tests, heshall accept the said readings as accurate.

3.9.8. Removal of Improper Work, Materials or Plant

The Engineer shall have authority to issue instructions from time to time, for:a. the removal from the Site, within such time or times as may be specified in the instruction, of any materialsor Plant which, in the opinion of the Engineer, are not in accordance with the Contract,b. the substitution of proper and suitable materials or Plant, and

c. the removal and proper re-execution, notwithstanding any previous test thereofor interim payment therefore, of any work which, in respect of

ii. materials, Plant or workmanship, oriii. is not, in the opinion of the Engineer, in accordance with the

Contract.

Page 31: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 11 -

3.9.9. Default of Contractor in Compliance

In case of default on the part of the Contractor in carrying out such instruction withinthe time specified therein or, if none, within a reasonable time, the CORPORATIONshall be entitled to employ and pay other persons to carry out the same and all costsconsequent thereon or incidental thereto shall, after due consultation with theCORPORATION and the Contractor, be determined by the Engineer and shall berecoverable from the Contractor by the CORPORATION, and may be deducted by theCORPORATION from any monies due or to become due to the Contractor and theEngineer shall notify the Contractor accordingly, with a copy to the CORPORATION.

3.10. Commencement and Delays

3.10.1. Commencement of Works

The Contractor shall commence the work within 14 days of the issue of the letter of award.

3.10.2. Possession of Site and Access Thereto

Save insofar as the Contract may prescribe:a. the extent of portions of the Site of which the Contractor is to be givenpossession from time to time, andb. the order in which such portions shall be made available to the Contractor andsubject to any requirement in the Contract as to order in which the Works shall beexecuted, the CORPORATION will, with the Engineer’s notice to commence theWorks, give to the Contractor possession ofc. so much of the Site, andd. such access as, in accordance with the Contract, is to be provided by theCORPORATIONas may be required to enable the Contractor to commence and proceed with theexecution of the Works. The CORPORATION will, from time to time as the Worksproceed, give to the Contractor possession of such further portions of the Site as maybe required to enable the Contractor to proceed with the execution of the Works withdue dispatch in accordance with the agreed programme or proposals, as the case maybe.

3.10.3. Failure to Give Possession

If the Contractor suffers delay and/or incurs costs from failure on the part of thecorporation to give possession in accordance with the terms, the Engineer shall, afterdue consultation with the corporation and the Contractor, determine anycompensation to be provided to Contractor.

3.10.4. Access Route

The Contractor shall be deemed to have satisfied himself as to the suitability andavailability of the access routes he chooses to use. The Contractor shall (as between

Page 32: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 12 -the parties) be responsible for the maintenance of access routes. The Contractor shallprovide any signs or directions which he may consider necessary for the guidance ofhis staff, labour and others. The Contractor shall obtain any permission that may berequired from the relevant authorities for the use of such routes, signs and directions.

The CORPORATION will not be responsible for any claims which may arise from theuse or otherwise of any access route. The CORPORATION does not guarantee thesuitability or availability of any particular access route, and will not entertain anyclaim for any non-suitability or non-availability for continuous use duringconstruction of any such route.

3.10.5. Wayleaves and Facilities

The Contractor shall bear all costs and charges for special or temporary wayleavesrequired by him in connection with access to the Site. The Contractor shall alsoprovide at his own cost any additional facilities outside the Site required by him forthe purposes of the Works.

3.10.6. Contractor to Provide Notification and Detailed Particulars

Provided that the Engineer is not bound to make any determination unless theContractor has:

a. within 28 days after such event has first arisen notified the Engineer witha copy to the CORPORATION, andb. within 28 days, or such other reasonable time as may be agreed by theEngineer, after such notification submitted to the Engineer detailed particularsof any extension of time to which he may consider himself entitled in order thatsuch submission may be investigated at the time

3.11. Penalty

Penalties shall be imposed on the contractor for non-compliance. This clause shall beread in conjunction with “penalty, receivable and payments clause of the price bidformat.”

3.12. Suspension

3.12.1. Suspension of WorkThe Contractor shall, on the instructions of the Engineer, suspend the progress ofthe Works or any part thereof for such time and in such manner as the Engineer mayconsider necessary and shall, during such suspension, properly protect and secure theWorks or such part thereof so far as is necessary in the opinion of the Engineer.

Unless such suspension is:(a) otherwise provided for in the contract, or(b) necessary by reason of some default of or breach of Contract by theContractor or for which he is responsible, or(c) necessary by reason of climatic conditions on the site, or

Page 33: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 13 -(d) necessary for the proper execution of the Works or for the safety ofthe Works or any part thereof.

3.12.2. Resumption of Work

After receipt of permission or of an instruction to proceed, the Contractor andtogether with the Engineer examine the Works and the Plant and Materials affectedby the suspension. The Contractor shall make good any deterioration or defect in orloss of the Works or Plant or Materials which has occurred during the suspension.

3.13. Dispute Resolution3.13.1. Amicable Settlement

The Parties shall use their best efforts to settle amicably all Disputes arising out of orin connection with the Contract or its interpretation. If dispute persist, thenCommissioner, Municipal Corporation Gurgaon shall appoint a arbitrator anddecision of which shall be binding on both parties.

3.14. AmendmentsNo modification or amendment to this Contract and no waiver of any of the terms orconditions hereof shall be valid or binding unless made in writing and duly executedby the CORPORATION.

3.15. Jurisdiction

(a) The courts at Gurgaon shall have jurisdiction over all disputes, controversy orclaims between the Parties under this Contract.

Page 34: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 14 -ARBITRATION CLAUSE

1) If any dispute or difference of any kind whatsoever shall arise betweenCommissioner Municipal Corporation Gurgaon /his authorised agents and thecontractor in connection with or arising out of the contract of the executing of thework that is (i) whether before its commencent of during the progress of the work orafter its completion (ii) and whether before or after the termination embedmentBranch of the contract it shall in the first instance be referred to for being settled bythe Executive Engineer in charge the work at the time and he shall with in a period ofsixty days after being requested in writing by the contractor to do so convey hisdecision to the contractor and subject to arbitration as here in after provide suchdecision in respect of every matter so refereed shall be final binding upon thecontractor. In case the work is already in progress, the contractor will proceed withthe execution of the work on receipt of the decision by the Executive Engineer incharge as aforesaid with all dues diligence whether he or Commissioner MunicipalCorporation Gurgaon / his authorised agent required arbitration as herein afterprovided or not if the Executive Engineer in charge of the work has conveyed hisdecision to the contractor and no claim to arbitration has been filled with in by thecontractor with a period of sixty days from the receipt of letter communicating thedecision the said decision shall be final and binding upon the contractor and will notbe subject matter of arbitration at all. If the Executive Engineer in charge of the workfails to convey his decision within a period of sixty days after being requestedaforesaid the contractor may within further sixty days of the expiry of first sixty dayfrom the date on which request has been made to the Executive Engineer in chargerequest Engineer-in-chief that the matter in dispute be referred to arbitration as hereinafter provided.

2) All disputes or differences in respect of which the decision is not final andconclusive shall at the request in writing of either party, made in communication sentthrough registered A.D Post be referred to the sole arbitration of any servingSuperintending Engineer or Chief Engineer MCG to be nominated by designation. Itwill be no objection to any such appointment that the arbitrator so appointed is aGovt. servant or that he had to deal with the matters to which the contract related andthat in the course of his duties as a Government servant he had expressed his viewson all or any of the matters in dispute. The arbitrator to whom the matter is originallyreferred being transferred or vacating his office his successor in office as such shall beentitled to proceed with the reference from that stage at which it was left by hispredecessor. In case the arbitrator nominated by Commissioner MCG unable orunwilling to act as such for any reasons what so ever the Commissioner MCG shall becompetent to appoint and nominate any other Superintending Engineer or ChiefEngineer as the case may be entitled to proceed with the reference.

3. It is also a term of this arbitration agreement that no person other than personappointed by the Commissioner, MCG shall act as arbitrator and if for any reason thatis not possible the matter shall not referred to arbitration at all. In all cases where theagreement amount awarded exceeds Rs. 25,000/- (Rs. Twenty five thousand only) the

Page 35: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 15 -arbitrator must invariably give reasons for his award in respect or each claim andcounter claim separately.

4. The arbitrator shall award separately giving his award against each claim anddespite by the either party including any contractor claim and that any lump sumaward shall not be early chargeable.

5. The following matters shall not be within the purview of arbitration.

a) Any dispute relating to the levy of compensation as liquidated damages, whichhas already been referred to the Superintending Engineer and is being heard or/andhas been finally decided by the Superintending Engineer in charge of the work.

b) Any dispute in respect of substituted, altered additional work committedwork/defective work referred by contractor for the decision of the SuperintendingEngineer in charge of the work if it is being heard or has already been decided by thesaid Superintending Engineer.

c) Any dispute regarding the scope of the work or its execution of suspension ofabandonment that has been referred by the contractor for the decision of the MCG/Govt. of Haryana and has been so decided finally by MCG/ the HaryanaGovernment.

6. The Independent claim of the party other than the own getting the arbitratorappointed, as also counter claims of any party will be entertained by the arbitrator notwith standing that the arbitrator has been appointed at the instance of the other party.

7. It is also a term of this arbitration agreement that where the party invokingarbitration is the contractor, no reference for arbitration shall be maintainable unlessthe contractor furnish to the satisfaction of the Executive Engineer in charge of thework a security deposit of a sum determined according to details given below and thesum so deposited shall on the termination of the arbitration proceedings be adjustedagainst the cost if any awarded by the arbitrator against the claimant party and thebalance remaining after such adjustment in the absence of any such cost beingawarded the whole of the sum will be refunded to him with in one month from thedate of the award.

Amount of claim Rate of security deposit

i) For claims below Rs. 10,000 2% of amount claimed.

ii) For claims of Rs. 10,000 and above 5% of amount claimed and below Rs-100000/-

iii) For claims of Rs. 100000/- and 7.5% of amount claimed above.

Page 36: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 16 -

The Stamp fee due on the award shall be payable by the party as desired by thearbitrator and in the event of such party's default stamp fee shall be recoverable fromany other sum due to such party under this or any other contract.

8. The value of the arbitration shall be such place or place as may be fixed by thearbitrator his sole discretion.

The work under the contract shall continue during the arbitration proceeding.

9. Neither party shall be entitled to bring a claim for arbitration if the appointmentof such arbitration has not been applied with in 6 months.

a) Of the date of completing of work as certified by the Executive Engineer incharge.

b) Of the date of abandonment of the work or

c) Of its non-commencement within six months from the date of abandonment orwritten orders to commence the work as applicable.

d) Of the completion of the work through any alternative agency or means afterwithdrawal of the work from the contractor in whole or in part and or its recession or.

e) Of received an intimation from the Executive Engineer in charge of the workthat final payment due to or recovery from the contractor had been determined whichhe may acknowledge and/or receive.

Which ever of (a) to (c) above is the test.

If they matter is not referred to arbitration with in the period prescribed above all therights and claim of any party under the contract shall be deemed to have beenforfeited and absolutely barred by time vain for civil litigation not with in standing.

10. It is also a term of this arbitration agreement that no question relating to thiscontract shall be brought before any civil court without first involving and completingthe arbitration proceeding as above if the scope of arbitration specified hereinconverse issue that can be brought before the arbitration i.e. any matter that can bereferred to arbitration not be brought before civil court.

The pendency of arbitration shall not distrantitle Government to terminate thecontract and make alternative arrangement for the completion of the work.

11. The arbitrator shall be deemed to have entered on the reference on the may beissued notices to the parties fixing the first date of hearing. The arbitrator way from

Page 37: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 17 -time to time with the consent of the parties enlarge the initial time for making andpublishing the award.

12. If is also anteroom of arbitration agreement that subject to the stipulation herein mentioned the arbitration proceeding shall be conducted in accordance with theprovision of the arbitration Act. 1996 or any other law enforce for the time being.

Page 38: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 18 -Extracts of Contract Labour (Regulation and Abolition) Act 1970

ANNEXURE - A(Reference Clause 1.35)

The Contractor shall, at all times during the continuance of the Contract, comply fully withall existing Acts, regulations and byelaws including all statutory amendments and re-enactment of State or Central Government and other local authorities and any otherenactments, notifications and acts that may be passed in future either by the State or theCentral Government or local authority, including Indian Workmen's Compensation Act,Contract Labour (Regulation and Abolition) Act 1970 and Equal Remuneration Act 1976,Factories Act, Minimum Wages Act, Provident Fund Regulations, Employees ProvidentFund Act, schemes made under the same Act and also Labour Regulations mentioned inAnnexure A to Section IV, Health and Sanitary Arrangement for Workmen, Insurance andother benefits and shall keep CORPORATION indemnified in case any action iscommenced by competent authorities for contravention by the Contractor. If theCORPORATION is caused to pay or reimburse, such amounts as may be necessary to causeor observe, or for non-observance of the provisions stipulated henceforth on the part of theContractor, the Engineer shall have the right to deduct from any moneys due to theContractor, his amount of performance security or recover from the Contractor personallyany sum required or estimated to be required for making good the loss or damage sufferedby the CORPORATION, responsibility in connection with the employees of the Contractor,who shall, in no case, be treated as the employees of the CORPORATION at any point oftime.

Fair Wages

The Contractor shall pay the labourers engaged by him on the work not less than fair wagewhich expression shall mean, whether for time or piecework, the respective rates of wagesfixed by the Public Works Department as fair wages for the area payable to the differentcategories of labourers or those notified under the Minimum Wages Act for correspondingemployees of the CORPORATION, whichever may be higher.

The Contractor shall, notwithstanding the provisions of a contract to the contrary, cause tobe paid a fair wage to labourers indirectly engaged on the Works, including any labourengaged by sub/contractors in connection with the sand works as if the labourer had beendirectly employed by him.

NOTICES

The Contractor shall, before he commences the work, display, and correctly maintain, in aclean and legible condition at a conspicuous place on the Site, notices in English and in alanguage spoken by the majority of the workers, stating therein the rate of wages whichhave been fixed as fair wages and the hours of work for which such wages are earned andsend a copy of such notices to the Engineer.

Page 39: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 19 -Wages Records

The contractor shall maintain records of wages and other remuneration paid to hisemployees in such form as may be convenient and as per the requirements of theCORPORATION/Engineer and the Conciliation Officer (Central), Ministry of Labour,Government of India, or such other authorised person appointed by the Central or StateGovernment and the same shall include the following particulars of each worker:

Name, worker's number and grade;Rate of daily or monthly wage;Nature of work on which employed;Total number of days worked during each wage period;Total, amount payable for the work during each wage period;All deduction made from the wage with details in each case of the ground for which thededuction is made;

Wage actually paid for each wage period.

The Contractor shall provide a Wage Slip for each worker employed on a the Works.The Wage records and Wage Slips shall be preserved for a least 12 months after last entry;

Inspection of Wage Records

The Contractor shall allow inspection of the aforesaid Wage Records and Wage Slips to theEngineer and to any of his workers or to his agent at a convenient time and place after duenotice is received or to the CORPORATION or any other person authorised by him on hisbehalf.The CORPORATION, the Engineer or any other person authorised by them on their behalfshall have power to make enquiries with a view to ascertaining and enforcing due andproper observance of the Fair Wages Clause. He shall also have the Power to investigateinto any complaint regarding any default made by the Contractor or sub-contractor inregard to such provision.The CORPORATION shall have the right to deduct from the money's due to the Contractorany sum required or estimated to be required for making good the loss suffered by aworker or workers by reason of non-payment of the aforesaid fair wage, except on accountof any deductions that may be permissible under any law for the time being in force.(i) A workman shall be entitled to be represented in any investigation or enquiry

under this Clause by:

An officer of a registered Trade Union of which he is a member.An officer of a federation of Trade Unions to which the Trade Union referred to in previoussub-clause is affiliated.Where the worker is not a member of any registered Trade Union, by an officer of aregistered Trade Union connected with or by any other workmen employed in the industryin which the worker is employed.

Page 40: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 20 -(ii) The Contractor or sub-contractor shall be entitled to be represented in any investigationor inquiry under this Clause by an office of an Association of CORPORATIONs of whichhe is member.

(iii) No party shall be represented by a legal practitioner in any investigation orinquiry under this Clause, unless all parties agree otherwise.

Safety ProvisionsThe Contractor shall comply with all the precautions as required for the safety of theworkmen by the I.L.O. Convention No.62 as far as they are applicable to the contract.

The Contractor shall provide all necessary safety appliances, gears like goggles, helmets,masks, etc., to the workmen and the staff.

Suitable scaffolds shall be provided for workmen for all work that cannot safely be donefrom the ground, or from solid construction except for such short period work as can bedone safely from ladders, When a ladder is used, an extra labour shall be engaged forholding the ladder and if the ladder is used for carrying materials as well, suitable foot-holds and hand-holds shall be provided on the ladder, which shall be given an inclinationnot steeper than 1/4 to (1/4) horizontal in 1 vertical).Scaffolding or staging more than 3.25 metres above he ground or floor, swing or suspendedfrom an overhead support or erected with stationary support shall have guard rail properlyattached bolted, braced and otherwise secured 1 metres high above the floor or platform ofsuch scaffolding or staging and extending along the entire length may be necessary for thedelivery of materials. Such scaffolding or staging shall be so fastened as to prevent it fromswaying from the support for structure.Working platform, gangways, and stairways shall be so constructed that they do not sagunduly or unequally and if a height of a platform or gangway or stairway is more 3.25metres above ground level or floor level, it shall have closely spaced boards, have adequatewidth and be suitably provided with guard rails as described in (ii) above.Every opening in floor of a structure or in a working platform shall be provided withsuitable means to prevent fall of persons or materials by providing suitable fencing orrailing with a minimum height of one metre.Safe means of access shall be provided to all working platforms and other working places.Every ladder shall be securely fixed. No portable single ladder shall be over 9 metres inlength. Width between side rails in a rung ladder shall in no case be less than 30 cm forladders upto and including 3 metres in length. For longer ladders the width shall beincreased at least 6mm for each additional 30cm of length. Spacing of steps shall be uniformand shall not exceed 30cm.Adequate precautions shall be taken to prevent danger from electrical equipment. Nomaterials on any of the sites shall be so stacked or placed as to cause danger orinconvenience to any person or the public. The Contractor shall provide all necessaryfencing and lights to protect public from accidents and shall be bound to bear expenses ofdefending every suit, action or other proceedings at law that may be brought by any personfor injury sustained owing to neglect of the above precautions and to pay any damages andcost which may be awarded in any such suit, action or proceeding to any such person or

Page 41: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 21 -which may with the consent of the Contractor be paid to compromise any claim by any suchperson.Excavation and Trenching: All trenches, 1.5 metres or more in depth, shall at all times besupplied with at least one ladder for each 20 metres in length or fraction thereof. Laddershall be extended from bottom of trench to at least 1 metres above surface of the ground.Sides of trench which is 1.5 metres or more in depth shall be stepped back to give suitableslope or securely held by timber bracing, so as to avoid the danger of collapsing of sides.Excavated material shall not be placed within 1.5 metres of edge of trench or half the depthof trench, whichever is more. Cutting shall be done from top to bottom. Under nocircumstances, undermining or undercutting shall be done.Demolition: Before any demolition work is commenced and also during the process of thework:A. All roads and open areas adjacent to the work site shall either be closed orsuitably protected.B. No electric cable or apparatus which is liable to be a source of danger over a cable orapparatus used by Contractor shall remain electrically charged.C. All practical steps shall be taken to prevent danger to persons employed by theCORPORATION, from risk of fire or explosion, or flooding. No floor, roof or other part of abuilding shall be so overloaded with debris or materials as to render it unsafe.All necessary personal safety equipment as considered adequate by the Engineer shall beavailable for use of persons employed on the Site and maintained in a condition suitable forimmediate use and the Contractor shall take adequate steps to ensure proper use of theequipment by those concerned.A. Workers employed on mixing asphaltic materials, cement, lime mortars/concreteshall be provided with protective footwear and protective goggles.B. Those engaged in handling any material which is injurious to eyes shall be providedwith protective goggles.C. Those engaged in welding works shall be provided with welder's protective eye-shield.D. Stone breakers shall be provided with protective goggles and protective clothing andseated at sufficiently safe intervals.E. When workers are employed in sewers and manholes, which is in use, the Contractorshall ensure that manhole covers are open and manholes are ventilated at least for an hourbefore workers are allowed to get into them. Manholes so open shall be cordoned off withsuitable railing and provide warning signals or boards to prevent accident to public.The Contractor shall not employ men below the age of 18 years and women on the work ofpainting with products containing lead in any form. Whenever men above the age of 18years are employed on the work of lead painting, the following precautions shall be taken.No paint containing lead or lead products shall be used except in the form of paste or readymade paint.Suitable face masks shall be supplied for use by workers when paint is applied in the formof spray or a surface having lead paint dry rubbed and scrapped.Overalls shall be supplied by the Contractor to workmen and adequate facilities shall beprovided to enable workers to wash during and on close of day's work.When work is done near any place where there is risk of drowning all necessary equipmentshall be provided and kept ready for use and all necessary steps taken for prompt rescue of

Page 42: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 22 -any person in danger and adequate provision made for prompt first aid treatment of allinjuries likely to be sustained during the course of the work.Use of hoisting machines and tackle including their attachments, anchorage and supportsshall conform to the following:(A) (i) These shall be of good mechanical construction, sound material and adequatestrength and free from patent defects and shall be kept in good adequate strength and freefrom patent defects and shall be kept in good working order and properly maintained.

(ii) Every rope used in hoisting or lowering materials or as a means of suspensionshall be of durable quality and adequate strength, and free from defects.(B) Every crane driver or hoisting appliance Contractor shall be properly qualified and noperson under the age of 21 shall be in charge of any hoisting machine including scaffold orof signals to Contractor.(C) In case of every hoisting machine and of every chain hook, shackle swivel and pulleyblock used in hoisting, lowering or as means of suspension, safe working load shall beascertained by adequate means. Every hoisting machine and all gear referred to above shallbe plainly marked with safe working load. In case of a hoisting machine or a variable safeworking load each safe working load and conditions under which it is applicable shall beclearly indicated. No part of any machine or any gear referred to above in the paragraphshall be loaded beyond safe working load except for the purpose of testing.(D) In case of the CORPORATION's machine, safe working load shall be notified by theEngineer or his representative. As regards Contractor's machines, the Contractor shallnotify safe working load of each machine to Engineer or his representative whenever hebrings it to site of work and get it verified by him.Motors, gearing, transmission, electric wiring and other dangerous parts of hoistingappliance shall be provided with efficient safeguards hoisting appliances shall be providedwith such means as will reduce the risk of accident during descent of load to the minimum.Adequate precautions shall be taken to reduce to the minimum risk of any part of asuspended load becoming accidentally displaced. When workers are employed on electricalinstallations which are already energised, insulating mats, working apparel such as gloves,sleeves and boots, as may be necessary, shall be provided, workers shall not wear any rings,watches and carry keys or other material which are good conductors of electricity.All scaffolds, ladders and other safety devices mentioned or described herein shall bemaintained in safe condition and no scaffold, ladder or equipment shall be altered orremoved while it is in use. Adequate washing facilities shall be provided at or near places ofwork.These safety provisions shall be brought to the notice of all concerned by display on a noticeboard at a prominent place at the workspot. Persons responsible for ensuring compliancewith the safety code shall be named therein by the Contractor.To ensure effective enforcement of the rules and regulations relating to safety precautions,arrangements made by the Contractor shall be open to inspection by the Engineer or hisrepresentative and the Inspecting Officer as defined in the Contractor's Labour Regulationmentioned in thereafter these Documents as Annexure A of Section IV.Notwithstanding anything contained in conditions (i) to (xiv) above, the Contractor shallremain liable to comply with the provisions of all Acts, rules, regulations and byelaws forthe time being in force in India and applicable in this matter.

Page 43: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 23 -The Contractor shall be responsible for observance, by his sub/contractors, of the forgoingprovisions.For work carried out in the vicinity of any wharf or quay, the Contractor shall abide by allthe provisions of the Dock Workers (Safety, Health and Welfare) Scheme, 1961.FootwearThe contractor shall at his own expense provide footwear for all labour engaged on concretemixing work and other types of work involving the use of tar, cement, etc., to thesatisfaction of the Engineer or his Representative, and on his failure to do so, theCORPORATION shall be entitled to provide the same and recover the cost from theContractor.Local LabourThe Contractor is encouraged as far as possible to employ, in the execution of the Contract,qualified Indian citizens as workmen. Employment of expatriate personnel is subject to theIndian Laws and Regulations. In case the contractor wishes to employ expatriate personnelin any particular trade or skill required to execute the contract, the CORPORATION willassist the Contractor in obtaining permission for which the Contractor shall submit requisitedata.Model Rules for Labour Welfare

(i) Definitions:(A) Workplace means a place at which, on an average, twenty or more workers areemployed.(B) Large workplace means a site at which, on an average, 250 or more workers areemployed.

(ii) First Aid:At every workplace, there shall be maintained in a readily accessible place first aid

appliances including an adequate supply of sterilized dressings and sterilized cotton woolas prescribed in the Factory Rules of the State in which the work is carried on. Theappliances shall be kept in good order and, in large workplaces, they shall be placed underthe charge of a responsible person who shall be readily available during working hours.

At large workplaces, where hospital facilities are not available within easy distance ofthe Works, First Aid Posts shall be established and be run by a trained compounder.

Where large workplaces are remotely situated and far away from regular hospitals,an indoor ward shall be provided with one bed for every 250 employees.

Where large workplace are situated in cities, towns or in their suburbs and no bedsare considered necessary owing to proximity of city or town hospitals, suitable transportshall be provided to facilitate removal of urgent cases to these hospitals. At otherworkplaces, some conveyance facilities shall be kept readily available to take injured personon persons suddenly taken seriously ill, to the nearest hospital.

At large workplaces, there shall be provided and maintained an ambulance roomcontaining the prescribed equipment and in the charge of such medical and nursing staff asmay be prescribed. For this purpose, the relevant provisions of the Factory Rules of theState government of the area where the work is carried on, may be taken as the prescribedstandard.

(iii) Accommodation for Labour:

Page 44: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 24 -The Contractor shall during the progress of the Work provide, erect and maintain

necessary temporary living accommodation and ancillary for labour at his own expenses tothe standards and scales as approved by the Engineer.

(iv) Drinking Water:In every workplace, there shall be provided and maintained at suitable places, easily

accessible to labour, a sufficient supply of cold water fit for drinking.Where drinking water is obtained from an intermittent public water supply, each

workplace shall be provided with storage of cold water fit for drinking.Ever water supply storage shall be at a distance of not less than 15 metres from any

latrine, drain or other source of pollution. Where water has to be drawn from an existingwell, which is within such proximity of latrine, drain or any other source of pollution, wellshall be properly chlorinated before water is drawn from it for drinking. All such wells shallbe entirely closed in and be provided with a trap door which shall be dust-proof and water-proof.

A reliable pump shall be fitted to each covered well. The trap door shall be keptlocked and opened only for cleaning or inspection which shall be done at least once amonth.(v) Washing and Bathing Places :

Adequate washing and bathing places shall be provided separately for men andwomen. Such places shall be kept in clean and drained condition.

(vi) Scale of Accommodation in Latrines and Urinals:There shall be provided within the precincts of every workplace, latrines and urinals

in an accessible place, and the accommodation, separately for each of these, shall not be lessthan at the following scale:-

No. of SeatsWhere number of persons does notexceed 50

2

Where number persons exceed 50 butdoes not exceed 100

3

For additional persons per 100 or partthereof

3

In particular cases, the Engineer shall have the power to increase the requirement, wherevernecessary.Latrines and Urinals:Except in workplaces provided with water/flushed latrines connected with a water bornesewage system, all latrines shall be provided with receptacles on dry-earth system whichshall be cleaned at least four times daily and at least twice during working hours and keptin a strictly sanitary condition. Receptacles shall be tarred inside and outside at least once ayear.

If women are employed, separate latrine and urinals, screened from those for men andmarked in the vernacular in conspicuous letters. "For Women Only" shall be provided onthe scale laid down in rule (vi). Those for men shall be similarly marked "For Men Only". Aposter showing the figures of a man and a woman shall also be exhibited at the entrance tolatrines for each sex. There shall be adequate supply of water, close to latrines and urinals.

Page 45: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 25 -

Construction of Latrines:

Inside walls shall be constructed of masonry or other non-absorbent material and shall becement washed inside and outside at least once a year. The dates of cement washing shallbe noted in a register maintained for the purpose and kept available for inspection. Latrinesshall have at least thatched roof.

Disposal of Excreta:Unless otherwise arranged for by the local sanitary authority, arrangement for properdisposal of excreta by incineration at the workplace shall be made by means of suitableincinerator approved by the local medical, health and municipal or cantonment authorities.Alternatively, excreta may be disposed off by putting a layer or night soils at the bottom ofa pucca tank prepared for that purpose and covering it with a 15 cm layer of waste or refuseand then covering it with a layer of earth for a fortnight (when it will turn into manure).

The Contractor shall, at his own expense, carry out all instructions issued to him by theEngineer to effect proper disposal of soil and other conservancy work in respect ofContractor's work-purpose or employees on the site. The Contractor shall be responsible forpayment of any charges which may be levied by municipal or cantonment authority forexecution of such work on his behalf.

Provisions of shelters during rest:At every workplace, there shall be provided, free of cost, four suitable sheds, two for mealsand two others for rest, separately for use of men and women labour. Height of each sheltershall not be less than 3 metres from floor-level to lowest part of roof. Sheds shall be keptclean and the space provided shall be on the basis of at least 0.5 sqm per head.(xi) Creches:At a place at which 20 or more women are ordinarily employed, there shall be provided atleast one hut for use of children under the age of 6 years belonging to such women. Hutsshall not be constructed to a standard lower than that of thatched roof, mud floor and wallwith wooden planks spread over mud floor and covered with matting.

Huts shall be provided with suitable and sufficient openings, for light and ventilation.There shall be adequate provision of sweepers to keep the places clean. There shall be twomaid-servants in attendance. Sanitary utensils shall be provided to the satisfaction of localmedical, health and municipal or cantonment authorities. Use of huts shall be restricted tochildren, their attendants and mothers of children.

Where the number of women workers is more than 25 but less than 50, the Contractor shallprovide at least one hut and one maid-servant to look after children of women workers.

Size of creche(s) shall vary according to the number of women workers employed.Creche(s) shall be properly maintained and necessary equipment like toys, etc., provided.(xii) Canteen:

Page 46: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 26 -A cooked food canteen on a moderate scale shall be provided for the benefit of

workers wherever it is considered necessary.(xiii) Planning, setting and erection of the above mentioned structures shall be approved bythe Engineer or his representative and the whole of such temporary accommodation shall atall times during the progress of the work be kept tidy and in a clean and sanitary conditionto the satisfaction of the Engineer or his representative and at the Contractor's expense. TheContractor shall conform generally to sanitary requirements of local medical, health andmunicipal or cantonment authorities and at all times adopt such precautions as may benecessary to prevent soil pollution of the site.

On completion of the Works, the whole of such temporary structures shall be clearedaway, all rubbish burnt, excreta or other disposal pits or trenches filled in and effectivelysealed off and the whole of site left clean and tidy at the contractor's expense to the entiresatisfaction of the Engineer.

(xiv) Anti-malarial precautions:The Contractor shall, at his own expense, conform to all anti-malarial instructions

given to him by the Engineer, including filling up any borrow pits which may have beendug by him.

(xv) Enforcement:Inspecting Officer mentioned in the Contractor's Labour Regulations or any other

Officer nominated on his behalf by the Engineer shall report to the Engineer all cases offailure on the part of the Contractor and/or his sub-contractor to comply with theprovisions of these Rules either wholly or in part and the Engineer shall impose such finesand other penalties as are prescribed in the conditions of contract.

(xvi) Interpretations, etc.:On any question as to the application, interpretation or effect of these Rules, the

decision of the Chief Labour Commissioner or Deputy Chief Labour Commissioner(Central) shall be final and binding.

(xvii) Amendments:The CORPORATION may, from time to time, add to, or amend these Rules and issue suchdirections as it may be considered necessary for the proper implementation of these Rulesor for the purpose of removing any difficulty which may arise in the administration thereof.

Page 47: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 27 -Extracts of Contract Labour (Regulation and Abolition) Act 1970

ANNEXURE - A - 1CONTRACTOR’S LABOUR REGULATIONS

Regulation 1 - Definition

In these regulations, unless otherwise expressed or indicated, the following words andexpression shall have the meaning hereby assigned to them :

“Labour” means workers employed by a contractor directly, or indirectly, through a sub-contractor, or by an agent on his behalf on a payment not exceeding Rs. 1.600/- per month.

“Wages” means wages, which shall include wages for weekly day of rest and otherallowance, whether for time or piece work, after taking into consideration prevailing marketrates for similar employments in the neighborhood but shall not be less than the minimumrates of wages fixed under the Payment of minimum Wages Act.

“Contractor” for the purpose of these regulations shall include an agent or sub-contractoremploying labour on the work taken on contract.

“Inspecting Officer” means any Labour Enforcement Officer, or Assistant LabourCommissioner of the chief labour Commissioner’s Organisation.

“Form” means a form appended to these Regulations.

Regulation 2 - Notice of Commencement

The Contractor shall within SEVEN days of commencement of the Work, furnish in writingto the Inspecting Officer of the area concerned the following information :

Name and situation of the workContractor’s name and addressParticular of the Department for which the work is undertakenName and address of sub-contractors as and when they are appointedCommencement and probable duration of the workNumber of workers employed and likely to be employedFair wages for different categories of workers

Regulations 3 - Hours of Work and Weekly Day of Rest

Number of hours of work which shall constitute normal working day :- The number ofhours which shall constitute a normal working day for an adult shall be NINE hours. Theworking day of an adult worker shall be so arranged that, inclusive of intervals, if any, forrest, it shall not spread over more than Twelve hours on a day. When an adult worker ismade to work for more than nine hours on any day or for more than FORTY EIGHT hours

Page 48: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 28 -in a week, he shall in respect of overtime work, be paid wages at double the ordinary rate ofwages.

Weekly day of Rest: - Every worker shall be given a weekly day of rest which shall be fixedand notified at least TEN days in advance. A worker shall not be required or allowed towork on the weekly rest day unless he has or will have a substituted rest day, one of thefive days immediately before or after the rest day. Provided no substitution shall be madewhich will result in the worker working for more than ten days consecutively without a restday for a whole day.

Where in accordance with the foregoing provisions, a worker works on the rest day and hasbeen given a substituted rest day, he shall be paid wages for the work done on the weeklyrest day at the overtime rate of wages.

NOTE : The expression “ordinary rate of wages” means the fair wage the worker is entitledto.

Regulations 4 - Display of Notice Regarding wages, Weekly day of Rest, etc.,

The Contractor shall before he commences his work on contract, display and correctlymaintain and continue to display and correctly maintain in a clean and legible condition inconspicuous places on the works, notice in English and in the local language spoken bymajority of workers, giving the rate of fair wages, the hours of work for which such wagesare payable, the weekly rest days workers are entitled to and name and address of theInspecting Officer. The Contractor shall send a copy of each of such notice to the InspectingOfficer.

Regulation 5 - Fixation of Wage periods

The Contractor shall fix wage periods in respects of which wages shall be payable. No wageperiod shall normally exceed one week.

Regulation 6 - Payment of wages

Wages due to every worker shall be paid to him direct. All wages should be paid in currentcoins or currency or in both.

Wages of every worker employed on the Contract shall be paid where the wage period isone week, within THREE days from the end of the wage period ; and in any other casebefore the expiry of the 7th day or 10th day from the end of the wage period according asthe number of workers does not exceed 1,000 or exceeds 1,000.

When employment of any worker is terminated by or on behalf of the Contractor, the wagesearned by him shall be paid before expiry of the day succeeding the one on which hisemployment is terminated.

Page 49: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 29 -Payment of wages shall be made at the Work Site on a working day except when the workis completed before expiry of the wage period in which case final payment shall be made atthe Work Site within 48 hours of the last working day and during normal time.

Note : The term “Working Day” means a day on which the work on which the labour isemployed is in progress.

Regulation 7 - Register of Workmen

A register of workmen shall be maintained in the Form appended to the regulations andkept at the work site or as near to it as possible and relevant particulars of every workmanshall be entered therein within THREE days of his employment.

Regulation 8 - Employment Card

The Contractor shall issue an Employment card in the Form appended to these regulationsto each worker on the day of work or entry into his employment. If a worker already hasany such card with him issued by the previous CORPORATION, the Contractor shallmerely endorse that Employment Card with relevant entries. On termination ofemployment, the Employment Card shall again be endorsed by the Contractor and returnedto the worker.

Regulation 9 - Register of Wages etc.

A Register of Wages cum Muster Roll in the Form appended to these regulations shall bemaintained and kept at the Work Site or as near to it as possible.

A wage slip in the form appended to these regulations shall be issued to every workeremployed by the Contractor at least a day prior to disbursement of wages.

Regulation 10 - Fines and Deductions which may be made from Wages

1. Wages of a worker shall be paid to him without any deductions of any kind exceptthe following:

a) Fines

b) Deductions for absence from duty ; i.e. from the place of his employmentwhere he is required to work. The amount of deduction shall be in proportion tothe period for which he was absent;

c) Deduction for damage to or loss of goods expressly entrusted to the employedperson for custody, or for loss of money which is required to be accounted for,where such damage or loss is directly attributable to his neglect or default.

Page 50: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 30 -d) Deductions for recovery of advances or for adjustment of overpayment ofwages, advance granted being entered in a register; and

e) Any other deductions which the CORPORATION may from time to timeallows.

2. No fines shall be imposed on any worker save in respect of such acts and omissionson his part as have been approved by the Chief Labour commissioner.3. No fine shall be imposed on a worker and no deductions for damage or loss shall bemade from his wages until the worker has been given an opportunity of showing causeagainst such fines or deductions.

4. The total amount of fines which may be imposed in any one wage period of a workershall not exceed an amount equal to 0.3% of the wages payable to him in respect of thatwage period.

5. No fine imposed on a worker shall be recovered from him on installments, or afterexpiry of sixty days from the date on which it was imposed. Every fine shall be deemed tohave been imposed on the day of the act or omission in respect of which it was imposed.

6. The Contractor shall maintain both in English and the local language a list, approvedby the Chief Labour Commissioner, clearly stating the acts and omissions for which penaltyor fine may be imposed on a workman and display it in good condition in a conspicuousplace on the Work Site.

7. The Contractor shall maintain a register of fines and the register of deductions fordamage or loss in the forms appended to these regulations which should be kept at theplace of work.

Regulation 11 - Register of Accidents

The Contractor shall maintain a register of accidents in such form as may be convenient atthe work place but the same shall include the following particulars :

a) Full particulars of the labourers who met with accident.b) Rate of wagesc) Sexd) Agee) Nature of accident and cause of accidentf) Time and date of accidentg) Date of Time when admitted to hospitalh) Date of discharge from the hospitali) Percentage of loss of earning capacity and disability as assessed by the medicalOfficer.j) Claim required to be paid under Workmen’s Compensation Act.k) Date of payment of compensation.

Page 51: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 31 -l) Amount paid with details of the person to whom the same was paidm)Authority by whom the compensation was assessedn) Remarks

Regulation 12 - Preservation of Register

The Register of workmen and the Register of wages cum Muster Roll required to bemaintained under these Regulations shall be preserved for 3 years after the date on whichthe last entry is made therein.

Regulation 13 - Enforcement

The Inspecting Officer shall either on his own motion or on a complaint received by himcarry out investigations and send a report to the Engineer specifying the amountsrepresenting Workers Dues and amount of penalty to be imposed on the Contractor forbreach of these regulations, that have to be recovered from the Contractor, indicating fulldetails of the recoveries proposed and the reason therefor. It shall be obligatory on the partof the Engineer on receipt of such a report to deduct such amounts from payments due tothe Contractor.

Regulation 14 - Disposal of Amounts Recovered from the Contractor

The Engineer shall arrange payment to workers concerned within FORTY FIVE days ofreceipt of a report from the Inspecting Officer except in cases where the Contractor hadmade an appeal under Regulation 16 of these regulations. In cases where there is an appeal,payment of workers dues would be arranged by the Engineer wherever such payment arise,within THIRTY days from the date of receipt of the decision of the Regional LabourCommissioner (RLC).

Regulation 15 - Welfare Fund

All moneys that are recovered by the Engineer by way of worker’s dues which could not bedisbursed to workers within the time limit prescribed above, due to reasons such aswhereabouts of workers not being known, death of workers, etc., and also amountsrecovered as penalty, shall be credited to a Fund to be kept under the custody of theCORPORATION for such benefit and welfare of workmen employed by Contractors as theEngineer may deem fit.

Regulation 16 - Appeal against decision of Inspecting Officer

Any person aggrieved by a decision of the Inspecting Officer may appeal, against suchdecision of the Regional Labour Commissioner concerned with THIRTY days from the dateof the decision forwarding simultaneously a copy of this appeal of the Engineer.

The decision of the Regional Labour Commissioner shall be final and binding upon theContractor and the Workmen.

Page 52: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 32 -

Regulation 17 - Representation of Parties

1. Workmen shall be entitled to be represented in any investigation of enquiry underthese Regulations by an officer of a registered trade union of which he is a member or byan officer of a Federation of Trade Unions to which the said trade union is affiliated orwhere the workman is not a member of any registered trade union by an officer of aregistered trade union, connected with, or by any other workmen employed in theindustry in which the worker is employed.

2. A contractor shall be entitled to be represented in any investigation or enquiry underthese Regulations by an officer of an association of Contractors of which he is a memberor by an officer of a Federation of associations of Contractors to which the saidassociation is affiliated or by an officer of association of employees connected with or byany other CORPORATION engaged in the industry in which the Contractor is engaged.

3. No party shall be entitled to be represented by a legal practitioner in any investigationor enquiry under these Regulation

Regulation 18 - Inspecting of Books and Other Documents

The Contractor shall allow inspection of the Registers and other documents prescribedunder these Regulations by Inspecting Officers and the Engineer or his authorizedrepresentative at any time and by the worker or his agent on receipt of due notice at aconvenient time.

Regulation 19 - Interpretation etc.

On any question as to the application, interpretation or effect of these regulations, thedecision of the Chief Labour Commissioner or Deputy Chief Labour Commissioner(Central) as the case may be, shall be final and binding.

Regulation 20 - Amendments

The CORPORATION may, from time to time, add to or amend these Regulations and issuesuch directions as it may consider necessary for the purpose of removing any difficultywhich may arise in the demonstration thereof.

Page 53: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 33 -SECTION 4

ELIGIBILITY CRITERIA

A. Technical Criteria

1. Agencies/ firms/companies which have worked in area of operation & maintenance, cleaning of sewerlines by machenical device of minimum value of Rs. 1.00 Crore during last 5 years in any State/ central Govt.Deptt., Semi-Govt. Deptt. or ULBs.

iv.For operation and maintenance of Sewerage Treatment Plant (STP), the bidder should have selfexperience in construction or maintenance of 5 MLD (STP) during last 5 years from State/CenetralGovt. / Semi-Govt./ ULB’s.

OrShould submit a MOU for backup for contract period of the tender with the organization/ agencywhich have the above experience. If backup agency is out of this tender at any stage, the MCG reservethe right to debar/ blacklist bidder & bachup agency.

v.The bidder should have completed similar works: -

i. Single work of value not less than Rs. 7.0 Crores in the last five years.or

ii. 2 works of value not less than Rs. 4.0 Crores each in the last five yearsor

iii. 3 works of value not less than Rs. 3 Crores each in the last five year.

iv The bidder shall submit an undertaking on a Rs. 100 non-Judicial Stamp Paperthat agency is not blackListed from any State Govt./central, semi-Govt./ ULB on the date ofsubmission of tender.

For the purpose of this tender, 'similar works' means the work of operation & maintenance of sewerage systemwith machinacial devices or laying of sewerage network or maintenance/ construction of STP.

It is a fixed priced contract inclusive of all taxes. No Price variation Clause is applicable except change instatutory Laws. Govt levies/ Taxes through contract period shall be accounted for and recovered/ paid by thedepartment as the case may be.

B. Financial Criteria

i. The bidder shall comply with the following financial eligibilityTURNOVER: Average annual Turnover of the bidder shall be not less thanRs.10.00 Crores in last three financial years. Copy of last three years auditedaccounts duly certified by the Chartered Accountant of company shall have tobe enclosed.

ii. Solvency certificate from anatinalized/scheduled bank be provided forthe value not less than Rs.2.50 Crores. The certificate issued shall not be morethan six months old from the date of tender Submission.

Scanned copy of all the documents mentioned herein for eligibility shall be presentedalong with the bid documents.

Page 54: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 34 -SECTION 5

INSTRUCTIONS TO BIDDER

ANNEXURE-A

CONDITIONS OF E-TENDERING Instructions to Contractors on ElectronicTendering

1. These conditions will over-rule the conditions stated in the tender documents,wherever relevant and applicable.

2. All the Contractors intending to participate in the tenders processed online, arerequired to get registered for the Electronic Tendering System on the Portalhttp://mcg.etenders.in For more details, please see the information in Registration info linkon the home page.

3. Obtaining a Digital Certificate:

3.1 The Bids submitted online should be encrypted and signed electronically with a DigitalCertificate to establish the identity of the bidder bidding online. A digital signaturecertificate has two keys i.e. Public Key and Private Key. Public Key is used to encrypt thedata and Private Key is used to decrypt the data. Encryption means conversion of normaltext into coded language whereas decryption means conversion of coded language intonormal text. These Digital Certificates are issued by an approved certifying authority, by thecontroller of Certifying Authorities, Government of India.

3.2 A Digital Certificate is issued upon receipt of mandatory identity proofs andverification letters attested by the Notary Public / Charted Account / Any Gazatted Officerwhose stamp bears emblem of Ashoka. Only upon the receipt of the required documents, adigital certificate can be issued.

3.3 The contractors may obtain Class II B digital certificate from any Certifying Authorityor Sub-certifying Authority authorized by the Controller of Certifying Authorities on theportal http://cca.gov.in. or may obtain information and application format and documentsrequired for issue of digital certificate from one such certifying authority on given belowwhich is :-

1. TATA Consultancy Services Ltd.11th Floor, Air India Building, Nariman Point, Mumbai-400021 website -www.tcs-ca.tcs.co.in

2. Sify Communications Ltd.III Floor, Tidel Park, 4 Canal Bank Road, Taramani, Chennai-600113. Website -www.safescrypt.com

3. MTNL Trustline CA

Page 55: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 35 -O/o DGM (IT-CA), 5515, 5th Floor, Core-V Mahanagar Doorsanchal Sadan, CGOComples, MTNL, Delhi-125003. Website - www.mtnltrustline.com

4. iTrust CA (IDRBT)Castle Hills, Road No.1, Masab Tank, Hyderabad, Andhra Pardesh -500057. Website -idrbtca.org.in

5. (n) Code solutions301, GNFC Tower, Bodak Dev, Ahmedabad-380054, Gujarat. Website -www.ncodesolutions.com

6. National Informatics Centre Ministry of Communication and Information TechnologyA-Block CGO Complex, Lodhi Road,New Delhi-125003. Website https://nicca.nic.in

7. e-Mudhra CA3i Info-tech Consumer Serivces Ltd3rd Floor, Sai Arcade, Outer Ring Road, Devarabeesanahalli, Bangalore560036,Karnataka Website - http://www.e-Mudhra.com

Contractors may also obtain information and application format and documents requiredfor issue of digital certificate from the following:-

1. Nextenders (India) Pvt. Ltd.O/O Additional Chief Engineer, HUDA, Sector 40, M- Block South City –I, Gurgaon.Contact persons : Sh. Rajit Garg – 09650482332

2. Nextenders (India) Pvt. Ltd.YUCHIT, Juhu Tara Road, Mumbai-400049 [email protected]

3. Nextenders (India) Pvt. Ltd.O/o HSRDC, Bays No.13-14, Sec-2, Panchkula-134151Contact Person: Manmit - 09815034028Rishi – 09878012160

3.4 Bid for a particular tender may be submitted only using the digital certificate,which is used to encrypt the data and sign the hash during the stage of bidpreparation and hash submission. In case, during the process of a particular tender,the user looses his digital certificate (i.e. due to virus attack, hardware problem,operating system problem), he may not be able to submit the bid online. Hence, theusers are advised to have back up of certificate and keep the copies at safe placeunder proper security to be used in case of emergencies.

3.5 In case of online tendering, if the digital certificate issued to the authorized userof a firm is used for signing and submitting a bid, it will be considered equivalent to ano-objection certificate/power of attorney to that User. The firm has to authorize aspecific individual via an authorization certificate signed by all partners to use the

Page 56: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 36 -digital certificate as per Indian Information Technology Act 2000. Unless thecertificates are revoked, it will be assumed to represent adequate authority of the userto bid on behalf of the firm for Municipal Corporation Gurgaon , Haryana tenders asper Information Technology Act 2000. The digital signature of this authorized userwill be binding on the firm. It shall be the responsibility of management / partners ofthe registered firms to inform the certifying authority or Sub Certifying Authority, incase of change of authorized user and applies for a fresh digital certificate and issuesan 'authorization certificate' for the new user. The procedure for application of adigital certificate will remain the same for the new user.

3.6 The same procedure holds true for the authorized users in a private/Publiclimited company. In this case, the authorization certificate will have to be signed bythe directors of the company.

4. Set up of machine

In order to operate on the electronic tender management system, a user's machine isrequired to be set up. A help file on setting up of the system can be obtained fromNexTenders (India) Pvt. Ltd. or downloaded from the home page of the website -http://mcg.etenders.in.>> "Information for new users".

5. Online Viewing of Notice Inviting Tenders:

The contractors can view the N.I.T and the time schedule (Key Dates) for all thepackages floated using the electronic tendering system on the Haryana MCGDwebsite http://mcg.etenders.in. Contractor may refer to NIT in the office ofExecutive Engineer.

6. Opening of an Electronic Payment Account:

6.1 For purchasing the tender documents online, contractors are required to pay thetender documents fees online using the electronic payments gateway service asmentioned at S. No.8.

6.2 For the list of payments using which the online payments can be made, pleaserefer to the Home page of the Portal http://mcg.etenders.in

7. Submission of Earnest Money Deposit:

7.1 The EMD Payment can be made by eligible contractors through ApprovedTraditional Financial Instruments or through RTGS/Net Banking transaction .

7.2 Contractors have to submit the EMD either physically in a sealed physicalenvelope which should reach the office of concerned Executive Engineer asmentioned in the Tender Notice or make EMD payment through RTGS/Net Bankingtransaction.

Page 57: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 37 -

8. Submission of Tender Document Fees:

The Payment can be made by eligible contractors online directly via Credit Card /Internet Banking Account / Cash Card / Debit card. The contractors have to pay forthe tender documents online by making online payment of tender document feesusing the service of the secure electronic payment gateway. The secure electronicpayments gateway is an online interface between contractors and credit card / onlinepayment authorization networks.

9. Purchase of Tender Documents:

Download of Tender Documents: The tender documents can only be downloadedfrom the Electronic Tendering System on the Portal http://mcg.etenders.in

10. Submission of Bid Seal (Hash) of online Bids:

Submission of bids will be preceded by submission of the digitally signed bid seal(Hash) as stated in the tender time schedule (Key Dates) of the Tender. Biddersshould take note of any corrigendum being issued on the website on a regular basis.They should view and note down the tender Hash and ensure that it matches withtheir previous noted Hash before confirming the rates.

11. Generation of Super Hash:After the time of submission of Bid Seal (Hash) by the bidders has lapsed, the bidround will be closed and a digitally signed tender Super Hash will be generated byauthorized Haryana MCG official. This is equivalent to sealing the tender box.

12. Submission (Re-encryption) of actual online bids:Bidders have to submit their encrypted bids online and upload the relevantdocuments for which they generated the hash at the stage of hash generation andsubmission after the generation of Super Hash within the date and time as stated inthe Notice Inviting Tenders (Key Dates). The electronic bids of only those contactorswho have submitted their bid seals (Hashes) within the stipulated time, as per thetender time schedule (Key Dates), will be accepted by the System. A bidder who doesnot submit his bid seal (Hash) within the stipulated time will not be allowed tosubmit his bid.

13. Key Dates:13.1 The bidders are strictly advised to follow dates and time as indicated in theNotice Inviting Tender. The date and time will be binding on all the bidders. Thebidders are required to complete the stage within the stipulated time as per theschedule to continue their participation in the tender. All online activities are timetracked and the system enforces time locks that ensure that no activity or transactioncan take place outside the start and end dates and time of the stage as defined in theNotice Inviting Tender. The bidder should check the status of a particular stage byfollowing the below mentioned procedure:-

Page 58: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 38 -

a. Click on "Main" after login into the portal.b. Select "Tender Search" and click on "Go"

c. Next screen will appear on the screen and click on "Search" buttonto view the list of various tenders.

d. Select the tender whose status is to be viewed by clicking on the tenderno.e. Click on "Action page" button. The status of all the stages

i.e. whether "Pending" or "Completed" can be viewed.

The bidder should ensure that the status of a particular stage should be shown as"Completed" before the expiry date and time of that particular stage and he shouldpossess a copy of receipt of completion of each stage to be performed from his end. Itwill be the sole responsibility of the bidder if the status of a particular stage is"Pending" till the expiry date and time of that stage and he is not able to proceedfurther in the e-tendering process.

Other Information:

1. The intending bidders shall fill the lumpsum rate / item rate / Percentage ratein the online templates of the online tender. The Price Bid has to be submittedmandatory online.

2. Technical Bid Documents except EMD that cannot be submitted online, if anyshould be put in separate sealed envelopes and these sealed envelopes together withthe documents listed below should be sealed in another cover and delivered to thisoffice before the date and time mentioned in the Tender Notice.i. A list of all documents accompanying the sealed envelopes containing thetender documents.

ii. Duly accepted power of Attorney in original along with its two certifiedcopies in the name of bidder or authorized representative to act on behalf of theagency.

iii. Documents in respect of payment of earnest money.

3. Tender must strictly abide by the stipulations set forth in notice inviting tender& while tendering for the work, the bidder shall adopt only the three envelopesystem.

4. The third envelop - Price Bid envelope has to be submitted mandatory onlineand shall not be accepted physically under any circumstances. In case any bidderdoes not comply with procedure given above, it will be presumed that he is notinterested in the work and the work shall not be let out to him. Further he may be de-listed without further notice to him for failing to abide by the strictly approved termsof notice inviting tender for this work.

Page 59: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 39 -5. The tenders which are not accompanied by the earnest money or proof ofearnest money or do not strictly follow the technical requirement, are liable to berejected summarily.

6. Tenders / quotations which are dependent upon the quotations of anotherbidder shall be summarily rejected.7. The tenders of the bidders who does not satisfy the qualification in the biddocuments are liability to be rejected summarily without assigning any reason and noclaim what so ever on their account will be considered.

Note: - Bidders participating in e-tendering shall check his/her validity of DigitalSignature Certificate before bidding in the specific work floated online at e-tendering portal of Municipal Corporation Gurgaon , Haryana on the websitehttp://mcg.etenders.in. Also, the bidder will be held liable solely, in case, whilebidding in particular stage - Date & Time expired as per the key dates available onthe tender document. Key dates are subject to change in case of any amendment inschedule due to any reason stated by concerned Executive Engineer of theDepartment.

1. The Municipal Corporation Gurgaon invites sealed bidsthrough two envelope bid (Technical and Financial bids) systems from reputed andeligible bidders (as defined in Section of the Tender Document).

a) Sealed Envelope No.1 shall contain tender documents and Technical bid whichshall depict clearly on top right hand corner of the sealed cover “Technical”.Technical bid is to be treated as pre-qualification bid and incomplete data maymake bidder liable for rejection. The documents forming part of Technical Bid arelisted in sub clause.

b) Financial Bid shall be unloaded on online in etendering. This shall contain theamount payable for complete job as per Schedule No. 1 of the tender document.No terms and conditions shall be leaded in this offer.

Note: - “Financial Bid” of only those tenderer shall be opened on a notified dateby Executive Engineer, MUNICIPAL CORPORATION GURGAON, who qualify inTechnical bid as specified above.

2. Tender fee shall be online on e-tender web site andcopy the same shall be enclosed, in Sealed Envelope 1, which shall be nonrefundable.The fees shall be paid at the time of purchasing the tender.

3. The full name and addresses of the tenderer and nameof authorized representative delivering the tender shall be written on the bottom lefthand corner of the sealed envelope.

Page 60: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 40 -4. All bids must be accompanied by Bid Security of theamount of Rs. 25.00 Lacs for the Works detailed above payable in favour ofCommissioner, Municipal Corporation GURGAON.

5. Power of attorney or a true copy thereof duly attestedby a Gazetted officer in case an authorized representative has signed the tender asrequired in general.

6. All Bids must be submitted on MUNICIPALCORPORATION GURGAON e-tender website only. No manual tender shall beaccepted.

Page 61: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 41 -

1. Preparation & Submission of Tenders

Tenderer should submit his tender as per procedure for submission of tender in twosealed envelopes for complete scope of work mentioned hereinafter keeping in viewcondition of contract.

The tenderer should fill up the prescribed form for invitation of tender withoutmaking any alternation in the items specified. Tender with any alternation may beliable for rejection.

The Executive Engineer, MUNICIPAL CORPORATION GURGAON (hereinaftercalled the Engineer-in-Charge) will open the properly submitted tenders, in presenceof the Tenderers, who may choose to be present.

2. Refusal of Tender / Black listing

Commissioner, Municipal Corporation Gurgaon, reserves the right to accept thetender in part or reject thereof before the award of the contractor. If the tendererrefuses to carry out the work on the ground that the tender has not been accepted infull, his earnest money deposit will be forfeited and he will be liable for any loss onaccount of such refusal.

The Commissioner, MUNICIPAL CORPORATION GURGAON (Haryana) reservesthe right to reject any or all the tenders, without assigning any reason, what so everbefore award of contract. If the tender is rejected, before award of contract EMD bytenderers shall be refunded, MUNICIPAL CORPORATION Gurgaon shall not beliable for any interest whatsoever.

Notwithstanding the eligibility criteria above, the Employer may debar orblacklist any of the bidder(s) for their misleading or false representations in the formsstatements etc. for the period to be decided by the Employer.

3. One Bid per Bidder

Each bidder shall submit only one bid per contract package either by himself oras a partner in a joint venture. A bidder who submits or participates in more than onebid for a contract package will be disqualified.

4. Cost of Bidding

The bidder shall bear all costs associated with the preparation and submissionof his bid and the Employer will in no case be responsible or liable for those costs.

5. Site visit

Page 62: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 42 -The Tenderer, at the Tenderer’s own responsibility and risk is encouraged to

visit and examine the Site of Works and its surroundings and obtain all informationthat may be necessary for preparing the Tender and entering into a contract formentioned Works. The costs of visiting the Site shall be at the Tenderers own expense.

6. Amendment of Tender Documents

Before the deadline for submission of Tenders, the Employer may modify theTender documents by issuing addenda. Any addendum thus issued shall be part ofthe Tender documents and can be seen/ downloaded from MCG website by thepurchasers of the Tender documents.

To give prospective Tenderers reasonable time in which to take an addenduminto account in preparing their Tenders, the Employer may extend as necessary thedeadline for submission of Tenders.

7. Signing of the Letter Of Tender

Tenderers are requested to sign all pages in the tender schedule and must signLetter of Tender. The attention of the tenderer is drawn to the following declaration,which forms part of the letter of tender to be signed by the tenderer.

“I / we agree that I / we will not withdraw the tender during the period thatwill be required for intimation of acceptance or non-acceptance during such extendedperiod as agreed to by me / us, such period to date from the last date by whichTenders are due to be submitted to the Employer and if I / we do so withdraw, I / weshall forfeit the E.M.D to the Municipality.

Failure to sign the letter of tender is liable for the rejection of the tender.

8. Tender Validity.

Tenders shall remain valid for a period of not less than One hundred eightydays (180 days) after opening of the financial bids. A tender valid for a shorter periodshall be rejected by the Employer as non-responsive. In exceptional circumstances,prior to expiry of the original time limit, the Employer may request that the Tenderersto extend the period of validity for a specified additional period. The request and theTenderers' responses shall be made in writing or by cable. A Tenderer may refuse therequest without forfeiting his Earnest Money Deposit. A Tenderer agreeing to therequest will not be required or permitted to modify his tender.

9. Clarifications

Tenderers are requested to verify the number of pages in the tender schedule,number of items in the work schedule. Any clarification and further informationrequired may be obtained from the Office of the Employer by sending the queries inwriting on or before the pre-bid meet date. The reply will be sent to all the tenderers

Page 63: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 43 -in writing. No communication in this regards shall be entertained after the pre-bidmeet.

10.Conditional Tender.Tenders with conditions are liable for rejection.

11.Preparation and Submission of Tender

The Tenderer shall prepare the Tenders (Technical and Financial) marking them“Technical / Financial”

12.Language of the Tender

All documents relating to the Tender shall be in the English language.

13.Documents comprising the Tender

Note: The tender shall be submitted through e-tendering only.The Tender submitted by the Tenderer shall be in two forms:

1 Technical Bid2 Financial Bid

Technical Bid

It shall include the following, with all documents signed by the person holding powerof attorney.

Earnest Money Deposit in the form of DD/ CDR/FDR/BG from a nationalizedbank

A Power of Attorney duly authorized by a Notary Public indicating that theperson signing the Tender has the authority to sign the Tender and that the Tender isbinding upon the Tenderer during the full period of its validity.

Qualification information and supporting documents as specified in the Sectionof the tender document.

• Experience in similar nature and magnitude executed in the last five years,along proof• List of key and equipment’s and machinery, along with proof• Qualification and Experience of the Technical Personnel proposed to bedeployed for this work.• Detailed Methodology for “Work”• Health & Safety Plan & Procedure to be followed by bidder should be providedalong with the Bid.

Page 64: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 44 -List of Certificates

• Proof of Registration of the Tenderer, place of business and address forcommunication. Company details including last 5 years profit loss account statement,memorandum of understanding, financial soundness information i.e. annual turnoverof proceeding 5 financial years.• Audited Balance Sheet for the last five years, duly authorized by the CharteredAccountant• Sales Tax Registration Certificate and Verification Certificates.

Work experience certificate. Income Tax clearance certificate. Memorandum of understanding with some other supporting companies, if any. T & P details. List of pending disputes i.e. audit objections / court case against the firm.

• Note: In the Technical Tender there shall not any indication of the price/ratequoted.• In case of JV all the above information shall be submitted by the both thepartners.• Duly filled & signed Form 1 to Form 8 as given in the tender document.

Financila Bid”

• It shall be submitted online only.

14.Tender PricesThe contract shall be for the whole works as described in Scope of work and theMandatory Duties of the Contractor as in the Tender Document and based on the pricedBill Quantities submitted by the Tenderer.

The Tenderer shall fill in rates and prices and line item total (both in figures and words)for all items of the Works described in the Bill of Quantities along with total Tender price(both in figures and words). Items for which no rate or price is entered by the Tendererwill not be paid for by the Employer when executed and shall be deemed covered by theother rates and prices in the Bill of Quantities. Corrections, if any, shall be made bycrossing out, initialing, dating and rewriting.

The rate entered in the Bill of Quantities for any class of work shall be for finished workon situ and shall include all contingent expenses whether direct construction expensesinvolved in the work in accordance with the drawings and specifications or whether theybe expenses imposed by outside authority such as local bodies. Such contingent expensesshall not entitle the contractor to claim an extra in respect thereof.

Rates for finished work shall always include the cost of conveyance and all leads, liftsloading unloading, and stacking in the manner and at the places ordered by the officer in

Page 65: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 45 -immediate charge of the work, unless circumstances necessitate provisions for a separateschedule item in which case such will be specified in the Tender schedule.

All duties, taxes, and other levies payable by the contractor under the contract, or for anyother cause shall be included in the rates, prices and total Tender Price submitted by theTenderer.

The rates and prices quoted by the Tenderer shall be fixed for the duration of theContract and shall not be subject to adjustment on any account.

15.Escalation

No escalation of the rates shall be allowed for any reason.

16.Format and Signing of Tender

The Tenderer shall prepare the document as described in these Instructions to Tenderer,bound with the volume containing the Form of Tender.

The Tender shall be typed or written in indelible ink and shall be signed by a person orpersons duly authorized to sign on behalf of the Tenderer. All pages of the Tenderwhere entries or amendments have been made shall be initialed by the person orpersons signing the Tender.

The Tender shall contain no alterations or additions, except those to comply withinstructions issued by the Employer, or as necessary to correct errors made by theTenderer, in which case such corrections shall be initialed by the person or personssigning the Tender.

17.Submission of Tenders

Sealing and Marking of Tenders

The Tenderer shall prepare Technical Bid comprising the various documentsprescribed. Shall then be put in a Cover properly sealed and super-scribed as “Cover1 Technical Tender” to be opened on ………………..

The Cover shall then be put in another Big Cover properly sealed and super scribed:

“Operation and maintenance of sewerage system old Gurgaon Town including variousdisposal works, S.W. pipe / R.C.C. Pipe sewer, brick circular sewer, open, piped & boxdrain and Operation & Maintenance of 30 MLD STP E&M installation , Switch Yard ,valves , Horticulture etc and all other works contingent there to for five years”

All Covers shall be addressed to the Employer at the following address:

Page 66: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 46 -

Municipal Commissioner, Municipal Corporation of Gurgaon and should bear thefollowing information. Tender for Operation and maintenance of sewerage system oldGurgaon Town including various disposal works, S.W. pipe / R.C.C. Pipe sewer, brickcircular sewer, open, piped & box drain and Operation & Maintenance of 30 MLD STPE&M installation , Switch Yard , valves , Horticulture etc and all other works contingentthere to for five years”

o Cover 1 - Technical Tender to be opened on ……………………..

o Financial Tender to be opened on the date of the opening to be announced after thecompletion of evaluation of the Cover- 1 Technical Tender.

o In addition to the identification required as above, the Covers shall indicate thename and address of the Tenderer to enable the Tender to be returned unopened in caseit is declared late.

o If the Cover is not sealed and marked as above, the Employer will assume noresponsibility for the misplacement or premature opening of the Tender.

Tender Opening and Evaluation of Technical Tenders

Opening of the Cover I of all Tenderers and evaluation to determine qualified Tenderers

7. On the notified date of opening of tenders only envelop No. 1 shall be opened.

8. Date of opening of envelop No. 2 shall be communicated only to the bidders,whose The envelope No. 2 only will be opened when all the documents are foundsatisfactory and the contractor is found capable of carrying the scope of work.

9. In case some clarification / modifications are required to keep all the parties atcommon parameters, the same shall be obtained. If a party does not agree to theserequirements its envelope No. 2 shall not be opened and will be returned in original.The contractor shall be allowed to modify rates in view of modifications etc., ifrequired, as per the common parameter finalized.

10. The envelope No. 2 of modified rate shall be opened on a date to be notifiedsubsequently by the Executive Engineer. The tenderer who qualify in their technicalbid but do not submit revised bid, then their original price bid would be opened &shall be treated as revised / Modified price bid for all intent and purposes

The Employer will first open the common Cover containing the Covers 1 & 2 at thetime & date given in the presence of those Tenderers or their authorizedRepresentatives who shall sign a Register as a proof of their attendance. In the eventof the specified date of the Tender opening being declared as a holiday for the

Page 67: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 47 -Employer the Tenders will be opened at the appointed time and venue on the nextworking day.

After opening the common Cover, the Cover 1, “Technical Tender” will then beopened.

Then the Employer will read out the details of Earnest Money Deposit andother such details as he may consider appropriate and the Employer will prepareminutes of the Tender opening.

The Employer will make a preliminary examination of the Technical Tenders todetermine whether they are complete, whether the required Earnest Money Depositfurnished in the form specified, whether the documents are properly signed andwhether the Tenders are generally in order.

Any Tender found to be not meeting the qualification criteria specified (such asrequired Earnest Money Deposit, Power of Attorney, Certificate of Tender validityperiod, Qualification/ Eligibility Criteria etc.) will be rejected by the employer andwill not be included for further evaluation.

The Employer will carry out a detailed evaluation of the Tenders in order todetermine whether the qualification and experience details furnished meet with therequirements set forth in the Tender documents. In order to reach such determinationthe employer will examine the information supplied by the Tenderers pursuant torequirements in the Tender documents.

No correspondence regarding clarification/ information will be sent by theEmployer to the Tenderer to respond. The Employer will scrutinize and evaluate withthe data as submitted with the Tender only. In case relevant documents are found tobe missing the bid shall be termed as non-responsive.

Process to be confidential.

Information relating to the examination, clarification and evaluation of theTechnical Tender shall not be disclosed to any Tenderers or any other persons notofficially concerned with such process until the final decision on the Tender is made.Any effort by a Tenderer to influence the Employers’ processing of Tenders /decisions may result in rejection of Technical Tender of that Tenderer.

On completion of evaluation of the Technical Tender, final decision will becommunicated to the concerned Tenderers and the qualified Tenderers will beinformed of the date, time and venue of the opening of the financial Tender (Cover 2 )by giving notice.

Opening of “Financial Tender”

Page 68: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 48 -

The Employer will open “ Financial Tenders” including modifications made pursuantto Clause 21if allowed of the qualified Tenderers of “Technical Tender” in thepresence of the Tenderers or their authorized representatives who choose to attend atthe time , date and venue of the opening specified in the information and sign aRegister in token of their attendance. In the event of the specified date of Tenderopening being declared a holiday for the Employer, the Tenders will be opened at theappointed time and location on the next working day.

The Employer shall read out the submissions in themodification proposals in appropriate detail.

The Tenderers names, the Tender prices, the total amount of each Tender, anydiscount(s), modification and such other details as the Employer may considerappropriate will be announced by the Employer at the opening. Tender modification/ discount(s) that are not opened and read out at Tender opening will not beconsidered for further evaluation regardless of the circumstances.

The Employer will prepare minutes of the Tender opening including the informationdisclosed to those present.

The Employer will have preliminary examination of “Financial Tenders” to determinewhether (1) they are complete, (2) any computational errors have been made, (3) thedocuments are properly signed and (4) the Tenders are substantially responsive to therequirements of tender documents.

A substantially responsive tender is one which conforms to all the terms, conditionsand specifications of the Tender documents, without material deviation orreservation. A material deviation or reservation is one (a) which affects in anysubstantial way the scope, quality or performance of the works (b) which limits in anysubstantial way, inconsistence with the Tender documents, the Employer’s rights orTenderers obligations under the contract or (c) whose rectification would affectunfairly the competitive position of other tenderers presenting substantiallyresponsive tenders.

If a Tender is not substantially responsive, it will be rejected by the employer andmay not subsequently be made responsive by correction or withdrawal of the non-conforming deviation or reservation.

18.Evaluation and Comparison of Financial Tenders

The Employer will evaluate and compare only the Tenders determined to besubstantially responsive in accordance with tender document.

The Employer reserves the right to accept or reject any variation, deviation, oralternative offer. Variations, deviations, and alternative offers and other factors which

Page 69: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 49 -are in excess of the requirements of the Tender documents or otherwise result inunsolicited benefits for the Employer shall not be taken into account in Tenderevaluation.

19.Confidentiality

Information relating to the examination, clarification, evaluation, and comparison offinancial Tender and recommendations of the award of the contract shall not bedisclosed to tenderers or any other persons not officially concerned with such processuntil the award to the successful Tenderer has been announced. Any effort by aTenderer to influence the Employer’s processing of Tenders or award decisions mayresult in the rejection of his Tender

20.Negotiations

The Tenders determined to be substantially responsive in accordance with Clausesmentioned above will be taken into Consideration and the rates of all the items andthe total Tender value quoted by the Tenderer will be compared with the estimaterates and the total estimate value put to Tender. Where considered necessary theemployer may invite the lowest tenderer for negotiations as outlined below:

The Employer may seek breakdown detail from the lowest responsive Tenderer forthe rates quoted for the unbalanced items and total Tender amount offered by theTenderer within 10 days time. The Tenderer may also be requested to examine thepossibility of reducing the rates of high pitched items quoted thereby to reduce theTender amount to the extent possible.

Then the lowest Tenderer has to furnish the breakdown details as required by theEmployer within the time limit fixed by the Employer. The Tenderer may also reducethe rates of the high-pitched items quoted / high percentage quoted if possible orexpress his inability to reduce the quoted rates/ percentage stating the reasons. Areply shall be furnished within the time limit fixed by the Employer.

If the Employer is satisfied that the details furnished and the reasons stated by the tendererfor his inability to reduce the rates /percentage by the Tenderer is considered to bereasonable then he may take a decision suitably.

If the Employer feels that the reduced offer is reasonable, suitable action shall betaken to award the work and if the reduced rates offered / percentage rate even afternegotiation is considered still to be on the higher side and if the Tenderer refuses toreduce further then the Employer may record the reasons and take suitable action toreject the Tenders received and to go in for fresh Tender

21.Award of Contract

The Employer will award the Contract to the Tenderer whose Tender has been

Page 70: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 50 -determined to be substantially responsive to the Tender documents and who hasoffered the lowest evaluated Tender Price, (after negotiation where appropriate)provided that such Tenderer has been determined to be (a) eligible in accordance withthe provisions of Clause 3 and (b) qualified in accordance with the provisions ofClause 6.

22.Notification of Award and Signing of Agreement

The Tenderer whose Tender has been accepted will be notified of the award by theEmployer prior to expiration of the Tender validity period by cable, telex or facsimileconfirmed by registered letter. This letter (hereinafter and in the Conditions ofContract called the "Letter of Acceptance") will state the sum that the Employer willpay the Contractor in consideration of the execution, completion, and maintenance ofthe Works by the Contractor as prescribed by the Contract (hereinafter and in theContract called the "Contract Price").

The notification of award will constitute the formation of the Contract, subject only tothe furnishing of a Security Deposit in accordance with provisions of clause 31.

The Agreement will incorporate all understandings reached between the employerand the successful Tenderer during negotiations and post Tender correspondences. Itwill be kept ready for signature of the successful Tenderer in the office of employerwithin 14 days following the notification of award along with the Letter ofAcceptance. Within 14 days of receipt, the successful Tenderer will furnish theSecurity Deposit and sign the Agreement kept in the office of the Employer.

Upon signing of the agreement the Employer will promptly notify the otherTenderers that their Tenders have been unsuccessful and release their Earnest MoneyDeposit.

23.Specifications

Whenever detailed specifications for various items of work included in this contractare not found in the tender CORPORATION which is called as Municipal corporationGurgaon or the relevant Indian standard specifications or code of practice or theinstructions and requirements of the Engineering shall apply in that order.

24.Address for communications.

Tenderers should give full postal address of their office in their tender. The deliveryat the above named place or posting in a post box regularly maintained by the postaldepartment or sending by letter registered for acknowledgement of any notice, letteror other communication to the tenderer or contractor shall be deemed sufficientservice thereof upon the tenderer or contractor in writing. The address may bechanged at any time by an instrument executed by the tenderer or contractor anddelivered to the Employer.

Page 71: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 51 -

Note: Nothing contained in the agreement and its contract conditions shall bedeemed to preclude or render inoperative the service of any notice, letter orcommunication upon the contractor personally.

25.Currencies of Bid and Payment

The rates and the prices shall be quoted by the bidder entirely in Indian Rupees

All payments including advances, if any, shall be made in Indian Rupees.

5. Bank Guarantees

A. Performance Security Simultaneously with execution of the Contract, theContractor has delivered to Corporation a performance security ("PerformanceSecurity") of 5% of the agreed Contract Price from a Scheduled Bank located in Indiaas acceptable to the CORPORATION.

B. The Contractor shall keep the Performance Security valid and enforceablethroughout the Term and for a period of 90 days after the Expiry Date. In case thePerformance Security provided by the AC to the CORPORATION is set to expire forany reason whatsoever at any time before expiry of 90 days after the Expiry Date, theAC shall renew and provide to the CORPORATION renewed Performance Security atleast 30 days prior to its date of expiry. Upon any failure on part of the AC to renewthe Performance Security or to keep it valid and enforceable in terms of this Clause,the Performance Security will be en-cashed by the CORPORATION without givingany notice to the AC or to any other Party. This is without prejudice to any otheraction that may be taken by the CORPORATION under the terms and conditions ofthis Contract.

C. The CORPORATION, without prejudice to any of its rights or remedies underthis Contract, is free to en-cash the Performance Security in part or in full, in terms ofClause of this Contract. In the event of the invocation of any amount of thePerformance Security by the CORPORATION under this Contract, the AC shallimmediately take appropriate steps to establish the Performance Security at its fullvalue contemplated under this Contract within 15 days of the date when thePerformance Security is wholly or partially invoked by the CORPORATION.

D. The Performance Security shall be released by CORPORATION on satisfactoryfulfillment of all contractual obligations of the Contractor under this Contract after 90days from the Expiry Date.

Accident & Insurance

1. Staff employed / engaged by the contractor should be medically fit.

Page 72: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 52 -2. Accidents on the works: - The contractors shall be fully responsible for anyaccident that may occur to the labour on his work on duty and report the same to theEngineer-in-Charge and concerned Govt. Department Authority and shall pay allnecessary compensation as per rules falling which it may be paid by Engineer-in-Charge from the amount payable to contractor. Contractor shall also be fullyresponsible for any loss to any individual or public property of MUNICIPALCORPORATION GURGAON occurred due to him or his workers under the scope ofthis contract.3. The contractor shall be solely responsible for any mishap, during the executionof work. He will get his labour insured against injury, partial/permanent disabilityand death for Rs. 2.00 Lacs, or any instructions issued by Labour Deptt. Haryana willsupersede these instructions, each worker before the start of work, for the entireperiod till completion of work. No payment shall be released to the contractors unlessthey produce proof of policy of labourers premium paid to the insurance agency.Contractor shall have to provide following insurance cover to all the employees/staffengaged in the joint name of the Engineer-in-Charge and the contractor. However, ifthe contractor desire to effect insurance with the local office of any insurancecompany that will be recovered directly from the amount payable to the contractoragainst executed contract work which shall be noted by the contractor from the dateof work order for the following events which due to contractor’s risks.

a) Fire insurance policy – Substation, transformers, cables, controls, motors allelectrical and mechanical equipments.b) Workman compensation insurance policy – Personal injury or death due tovehicles of the contractor and or due to any accident that arise at or around the siteto the contractor personnel.c) Policies and certificates for insurance shall be delivered by the contractor to theEngineer in charge for his approval before the date of actual starting of work. Allsuch insurance shall provide for compensation payable in the types of proportionsrequired to rectify the loss or damage incurred.d) If the contractor does not produce any of the policies and certificates asrequired, the Engineer in charge may affect the insurance for which the contractorshould have produced the policies and certificate and recover the premiums it hasbeen paid from payments otherwise due to the contractor, or if no payment is due,the payment of the premium shall be debit due.Alterations to the terms of insurance shall not be made without the approval of theEngineer-in-Charge.

4. The contractor shall be responsible for any labour dispute carrying out thecontract and shall keep the Engineer-in-Charge informed against any judgment,award of degree passed in pursuance to any such dispute or claim made by any of thecontractor, workmen or staff.

SecrecyThe contractor shall during the tenure of the contract and any time thereafter mentionin strict confidence all information relating to the work and shall not unless soauthorized in writing by the competent authority, disclose of grant access to anyinformation about the work to any body and prevent and unauthorized person to

Page 73: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 53 -have information about the work to any body and prevent and unauthorized personto have an access to such an information. The obligation to keep secrecy shall becontinued even after the termination of contract.

Regulating Laws for WorkAll works shall be carried out as per: -

G. Govt. laws and rules such as Indian Electricity Act – 1948, Factory Act –1948, contractor labour (Regulation & Abolition) Act – 1972, WorkmenCompensation Act, Provident Fund Act, and any other relevant act etc. and therules framed under the said acts by the competent authority with all upto dateamendments.H. Laws and rules prevailing during contract and pertaining to the sites.I. Directions and instructions of the Engineer-in-Charge.

Page 74: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 54 -ANNEXURE - 1BIDDING FORMS

Form 1: Letter of Technical BidInvitation for Bid No.: …………………………….. Date: ...........................To:Municipal Commissioner,MUNICIPAL CORPORATION GURGAONCivil Line Road ,Telephone:Facsimile number:Electronic Mail Address:

We, the undersigned, declare that:

(a) We haveexamined and have no reservations to the Bidding Documents, including Addendaissued in accordance with Instructions to Bidders (ITB);

(b) We offer toexecute in conformity with the Bidding Documents the following Works:

(Name of Work …………………………………………………………………………………..)(c) Our Bid consisting of the Technical Bid and the Price Bid shall be valid for aperiod of 180 days from the date of opening of Financial Bid in accordance with theBidding Documents, and it shall remain binding upon us and may be accepted atany time before the expiration of that period;

(d) Our firm, including any subcontractors or suppliers for any part of theContract, have nationalities from [insert the nationality of the Bidder, including thatof all parties that comprise the Bidder if the Bidder is a consortium or association,and the nationality of each Subcontractor and Supplier];

(e) We, including any subcontractors or suppliers for any part of the contract, donot have any conflict of interest to/ with ITB ;

(f) We are not participating, as a Bidder or as a subcontractor, in more than onebid in this bidding process in accordance with ITB , other than alternative offerssubmitted in accordance with ITB;

(g) Our firm, its affiliates or subsidiaries, including any Subcontractors orSuppliers for any part of the contract, has not been declared ineligible by the saidauthorities as mentioned in the ITB under the Employer’s country laws or officialregulations.(h) We are not a government owned entity / We are a government owned entitybut meet the requirements of ITB; *

Page 75: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 55 -Name ....................................................................................................................In the capacity of ................................................................................................Signed ...................................................................................................................Duly authorized to sign the Bid for and on behalf of ...................................Date ......................................................................................................................

Page 76: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 56 -Form 2: Bank GuaranteeBank’s Name, and Address of Issuing Branch or Office

Beneficiary: Municipal Commissioner, Municipal Corporation GurgaonDate: ..........................................................................Bid Security No.: …………………………………….

We have been informed that . . . . . name of the Bidder. . . . . (hereinafter called “theBidder”) has submitted to you its bid dated . . . . . . . . . (hereinafter called “the Bid”) forthe execution of (Name of the Work……………………………………………………………….)under Invitation for Bids No. (Invitation Number )Furthermore, we understand that, according to your conditions, bids must be supported by a bid guarantee.At the request of the Bidder, we . . . . . name of Bank. . . . . hereby irrevocably undertake to pay you any sum or sumsnot exceeding in total an amount of ………………….. (in wordsRupees…………………………………………………………………………………… upon receipt by us of your firstdemand in writing accompanied by a written statement stating that the Bidder is in breach of its obligation(s) under thebid conditions, because the Bidder:

(a) has withdrawn its Bid during the period of bid validity specified by the Bidder in the Form of Bid; or(b) does not accept the correction of errors in accordance with the Instructions to Bidders (hereinafter “the ITB”)of the IFB; or(c) having been notified of the acceptance of its Bid by the Employer during the period of bid validity, (i) fails orrefuses to execute the Contract Agreement, or (ii) fails or refuses to furnish the performance security, inaccordance with the ITB.

This guarantee will expire: (a) if the Bidder is the successful Bidder, upon our receipt of copies of the ContractAgreement signed by the Bidder and the performance security issued to you upon the instruction of the Bidder; and (b)if the Bidder is not the successful Bidder, upon the earlier of (i) our receipt of a copy your notification to the Bidder ofthe name of the successful Bidder; or (ii) forty-five days after the expiration of the Bidder’s bid.Consequently, any demand for payment under this guarantee must be received by us at the office on or before that date.This guarantee is subject to the Uniform Rules for Demand Guarantees, ICC Publication No. 458.. . . . . . . . . . . .Bank’s seal and authorized signature(s) . . . . . . . . . .

Page 77: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 57 -Form 3: Proposed Methodology

a) Bidders shall also submit, with their bid, a detailed note outlining the bidders’proposed methodology of operation backed with their equipment& Manpowerplanning and development, duly supported with broad features and quality controlprocedures proposed to be adopted, in sufficient detail so as to demonstrate theadequacy of the Bidder's proposal to meet the Employer's requirements and completethe work as per milestones specified.

b) Methodology shall specifically include the statement for handling, treatment&safe disposal of sewage silt/ sludge at the sites designated by Employer (Thecarriage may be assumed to be to the STP Site).

Page 78: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 58 -Form 4: Bidder’s Information Sheet

Bidder’s Information

Bidder’s legal name

In case of JV, legal name of- Lead partner

- Other JV partner

- Representative of JV firm

In case of JV,% of the partnership ofLead partner & Other partner

Lead Members country of constitution

Lead Members year of constitution

Lead Members legal address in country ofconstitution

Authorized representative of the Lead Member(name, address, telephone numbers, faxnumbers, e-mail address)

Attached are copies of the following original documents. 1. In case of single entity, articles of incorporation orconstitution of the legal entity named above, in accordance withITB. 2. Authorization to represent the firm or JV named in above,in accordance with ITB. 3. In case of JV, letter of intent to form JV or JV agreement, inaccordance with ITB. 4. In case of a government-owned entity, any additionaldocuments not covered under 1 above required to comply withITB.

Page 79: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 59 -Form 5: Pending Litigation

Each Bidder or member of a JV must fill in this form

Pending Litigation No pending litigation in accordance with Criteria ___ ofSection ___ (Evaluation and Qualification Criteria) Pending litigation in accordance with Criteria ___ ofSection ___ (Evaluation and Qualification Criteria)

Year Matter in Dispute

Value ofPendingClaim inRS. Lacs

Value ofPendingClaim asaPercentage of NetWorth

Page 80: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 60 -Form 6: Financial Situation

Each Bidder or member of a JV must fill in this formFinancial Data for last 5 Years [In Rs. Lacs ]

Information from Balance Sheet1. Total Assets2. TotalLiabilities3. Net Worth =[1-2]4. Current Assets5. CurrentLiabilities6. TotalRevenues7. Profits BeforeTaxes8. Profits AfterTaxes

9. DedicatedRevolving Lineof Credit (as performat)10. AvailableWorkingCapital = [4 - 5]+ [9]

Page 81: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 61 -Form 7: Specific Experience in Similar works

Fill up one form per contract: (Kindly give details of such contracts which qualify forconditions for post qualification. Please enclose the copies of the work order, completioncertificate and the satisfactory work performance certificate for the same from theEmployer)

Contract with Similar Key Activities*Contract No . . . . . . of. . . . . . Contract Identification

Award Date Completion Date

Role in Contract Contractor

ManagementContractor

Subcontractor

Total ContractAmount

INR

If partner in a JV orsubcontractor, specifyparticipation of totalcontract amount

Percent of Total Amount

Employer’s NameAddressTelephone NumberFax NumberE-mailDescription of the key activities in accordance with Section __

Of the above mentioned works; the bidder should have billed at least 40 % of ordervalue;till date. Proof in this regard shall be submitted along with tender document dullysigned and issued by the authority not less than Executive Engineer.

Page 82: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 62 -Form 8: Statement of Compliance with the Bidding Documents

Bidder shall provide a complete statement of any proposed deviations from the Conditionsof Contract that are stipulated in the various Sections , General Requirements, givingreference to the Section Number and Clause Number, along with a description of theproposed deviation and the reason for proposing such deviation.

Section & ClauseNumber

As Mentioned in BidDocument

As Proposed bythe Bidder Reasons for Deviation

The Bidder hereby certifies that the above mentioned deviations are the only deviationsproposed to the various Sections

Page 83: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 63 -

SECTION 6

SCOPE OF WORK

O&M of Sewerage and Storm Water System:

1. Name of ContractOperation and maintenance of sewerage system old Gurgaon Town including variousdisposal works, S.W. pipe / R.C.C. Pipe sewer, brick circular sewer open, piped &box drain etc. and all other works contingent there to for five years”

2. Boundaries of Contract

The boundary of contract shall be all the works covered under scope of work,for the geographical area indicated in the area demarcated in enclosed map. This shallinclude but not be limited to: S.W / R.C.C. (Pipe, Brick ) Branch, Main & Trunk Open, Piped & Box Storm Water CCTV

Sewage Pumping Stations (Components of Sewage Pumping Stations shallinclude civil structures, mechanical, electrical, instrumentation equipment’s, pumps,motors, valves,interconnecting pipes, Diesel generator

Silt Disposal to designated locationat Sewage Treatment Plant Site (STP)Customer Complaint Redressed SystemMaintenance of Records

3. Contract Structure & ObjectivesThe Contract would be performance based Operations and Management Contract.The long term objective(s) of the contract shall be:

Ensure no overflow of sewage, Protect the environment, Improve the community health and the quality of life, Maintain good health and hygiene conditions in Gurgaon. Round the clock service backup to Sewerage System

4. Contract Time Frame

The contract is spread over 5 years from the date of Award of Contract.

5. Scope of Services during the Contract

S.W / R.C.C. (Pipe, Brick) Branch, Main & Trunk

Page 84: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 64 -i) Providing, Maintaining, Operating in good working condition the manpower, machinery,

Equipment’s to ensure smooth running of sewage in sewers.

ii) Desilting & keeping of S.W/ RCC Sewers to be running smoothly. De-silting here,means the removal of accumulated debris in the sewer system with the objective ofmaximizing sewer efficiency by removing grease, fat, silt, bricks/stone and any otherdebris, usually through the use of specialist sewer cleaning equipment.

iii) Operation & Maintenance of sewer lines and removal of silt on regular basis fromsewers and manhole.

iv) Operation, routine work, preventive and breakdown, maintenance and any kind ofrepair work round the clock for its smooth run.v) The plugging of sewerage system for maintenance purposed shall be done with latesttechniques.vi) Desilting of main sewer (pipe dia. from 300 mm and above) immediately after thenotified date of commencement of workvii) Any type of damage (due to any reason such as natural or caused by any person) ofsewer line, manhole, slab etc complete in all respect of sewerage system will beresponsibility of contractual agency and no payment on this account shall be made.

viii) Maintenance of smooth sewage flow in main sewers including carrier channels.ix) Desilting of the sewers as per the priority fixed by the Engineer-in-Charge.

x) Searching and Repair of damaged Manhole, sewer line etc. xi) Supply, Procurement,Putting in place of missing manhole cover and frame.

xii) Dismantling of Road for the purpose to cleaning & repair of sewers & manholes.xiii) Arrangement, operation and maintenance of sewer cleaning machinery andequipment, as defined in the scope, according to requirement and as desired byEngineer-in-Charge to complete the work

xiv) Engagement of sufficient number of super suckers and jetting sewer cleaningmachines to meet the performance parameters.

Open, Piped & Box Storm Water Drain

i) Providing, Maintaining, Operating in good working condition the manpower,machinery,

equipment’s to ensure smooth running of Open, piped & box storm water drains.ii) Desilting & keeping of open drain, piped & box storm water drains in smooth runningcondition.

iii) Operation & Maintenance of open drain piped & box storm water drains and removalof silt on regular basis from sewers and manhole.iv) Operation, routine work, preventive and breakdown, maintenance and any kind ofrepair work round the clock for its smooth run.

v) Desilting of the open drain piped & box storm water drains as per the priority fixed bythe Engineer-in-Charge.vi) Arrangement, operation, maintenance of machinery and equipment, as defined in thescope, according to requirement and as desired by Engineer-in-Charge to complete the

Page 85: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 65 -work vii) Arrangement, operation, maintenance of sufficient number of Mobile electric &diesel engine pumping sets for routine maintenance and during storm water/ rains.viii) All the complaint regarding manhole, sewerage / storm water lines and carrierchannel, open, pipe & box type storm water drains, rising mains etc. will be done by thecontractor on his account.ix) Arrangement, operation and maintenance of temporary machinery (at his own cost)during rainy season in order to pump out the storm water from the area in minimumpossible time, if any area of the town is flooded with the storm/rainy water.

CCTV Survey

i) Development of a planned programme of CCTV works to establish the sewercondition for sewer sizes 300 mm diameter and above.ii) The manpower, machinery, equipment’s for conducting CCTV Surveys shallremain in good working condition in whole contract period.iii)Conducting CCTV surveys of designated sections of the sewer network as perdirection of Engineer-in-Charge.

Sewage Pumping Stations (Components of Sewage Pumping Stations shall include civilstructures, mechanical, electrical, instrumentation equipment’s, pumps, motors, valves,interconnecting pipes, Diesel generator Sets):

i) Responsibility towards upkeep, safety and security of the Sewage PumpingStation and Pumping Mains.ii) Providing Manpower, Equipment and Machinery for routine Operation andMaintenance of Sewage Pumping Station and Pumping Mains.iii)Routine, Preventive, Breakdown maintenance and repair of Sewage PumpingStations, If required, replacement of material and spares for various components &Diesel Generator Sets.iv) Minor maintenance & repair works such as replacement of fuses, glandspacking, oiling, rectification of fault in electrical and electronic circuits, arrestingsparking, water and oil leakage.v) Extending full co-operation to inspections related to electrical, Mechanical &Civil work to be visited by any Statutory Authority visiting the plant.vi) Providing Diesel, petrol, lubricants and Kerosene required for repair &operation of machinery of any type.vii) Ensuring a power factor of above 0.9 and Installation of energy efficientdevices like capacitors etc in order to consume electricity in most economical wayirrespective up-gradation at his own cost.viii) Operation of Diesel Generator sets, immediately, in the event of electricityfailure.ix) Diversion of the traffic and Public movement for making the site clear from theobstructions for smooth operations.x) In case of repairs due to major break down of machine it will be theresponsibility of the Contractor to carry out further works via properarrangements at the premises itself or as per the direction of Engineer-in-Charges.

Page 86: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 66 -xi) Irrespective of day or night to put the machine in working order in shortestpossible time, if required, Contractor will have to increase the staff. No extrapayment will be made by the CORPORATION on this account. During breakdown maintenance staff should not leave the premises without permission ofEngineer-in-Charge.xii) The contractor will have to complete the work within the time frame fixedby Engineer-in-Charge at any cost even by deputing additional staff round theclock.

Silt Disposal to designated location at Sewage Treatment Plant Site

i) Providing Manpower, Equipment and Machinery for collection, transportationof silt/ sludge for disposal.ii) Removal of silt/ sludge, from sewers/ pumping station, on daily basis andtransportation to the Sewage Treatment Plant for final disposal. Ensure Collection/transportation/ dumping/ disposal in a way, so that it does not cause anyhardship to the nearby inhabitations / shopkeepers / traffic movement /movement of Public.iii)Ensure no spillage on the ground. The silt should be sucked by the Super suckermachine and go directly to the sealed Dump Tank and disposed at the designatedsite (Sewage Treatment Plant).iv) The silt removed from the sewer or from any structure will be dumped in a waythat it does not cause any hardship to the nearby inhabitations / shopkeepers /traffic movement / movement of Public.

Executive Engineer

Page 87: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 67 -Detail of Sewer line & Storm Water Drain:

The tentative details of sewer line and storm water drain are as under. The detail given isfor guidance only where as the contractor has to maintain the whole sewer line and stormwater drains (open, covered and piped) of area hatched on the plan attached.

Length of Sewer Line

S.No. Name of Colony Length

1 Bhim Garh Khedi 6680

2 Ashok Vihar 6560

3 Gurgaon Village 25950

4 Dayanand Colony 6780

5 Ashok Puri 5825

6 Tanga Stand to Bheem nagar 1608

7 Indra Puri 5050

8 Jawahar Nagar 5500

9 Jacubpura 10950

10 Subhash Nagar 7650

11 Roshanpura Sadar Bazar 5285

12 Barafkhana 2868

13 Shama Resturnt to old jail chowk 550

14 Civil Lines 3575

15 Jharsa road to Alwar road alongbandh

1485

16 Mahavir Pura 2500

17 Bhim Nagar 3550

Page 88: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 68 -18 New Railway rd to kabir bhawan

chowk1050

19 Subhash Nagar Balmiki Basti 2750

20 Dhanak Basti 1900

21 Sanjay Nagar 1709

22 Miyanwali Colony 4555

23 Lajpat Nagar 2315

24 Gopal Nagar 2400

25 Acharya Puri 5659

26 Friends Colony 3645

27 Housing Board Colony 1900

28 Patel Nagar 9560

29 Police Line 850

30 Mehrauli Gurgaon Road 5656

31 Old Delhi Road 4080

32 Old Najafgarh Road 800

33 Old DLF 4082

34 Prem nagar 6650

35 IDC Sector -14 2650

36 Adarsh Nagar 5240

37 Kirti Nagar 3046

38 Sukhrali Village 12500

39 Mini Sectt. To Old Jail 908

40 Old jail to Sohna chowk 400

41 Sohna Chow – BhuteshwarMandir – Ved Madir - ShamhanGhat – PH office

1650

42 Khandsa Road – DAV School –Rama Hospital – Basai Road

2710

Page 89: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 69 -43 Laxmi Garden – Shakti nagar –

Nirankari Bhawan – Ved matamandir Basai road

2040

44 NH – Raj Nagar – Khadsa Road 1200

45 DAV Scholl – Anaj mandi – MClimited on Khandas Road

1000

46 MC limited on khandas Road 1200

47 Mini sect – Shivaji Nagar –Khandsa road

2000

48 Pataudi road police choki – Hudasewer Pataudi road

1400

49 Gandhi nagar – Hanuman mandir– shivji Park Pataudi road

1400

50 Police chowk – Pataudi chowk –shamshaan ghaat MadanpuriRoad

1100

51 Alwar road – Beriwala bagh –Khandsa road – police chowkiPataudi road – Auto MarketBasari road

4500

52 Auto Market Basai road to tempDisposal Basai road

2250

53 Madanpuri Madhya marg 700

54 Jyoti Park – Gita Bhawan –Krishan Colony

1400

55 Krishna colony – Vivekanandschool

800

56 New Colony Gurudwara – AryaKanya School Sector - 7

1000

57 New Colony Mor – Harish Bakery 800

58 New Colony Mor – P.H. Office 700

59 Basai road – Nai Basti 1000

60 Madanpuri road – Vijay park –Arya samaj mandir Arjun Nagar

800

61 Om Sweet – Madanpuri Road 800

62 Basai road - Feroz Gandhi colony 800

63 Basai road – Baldev Nagar 1400

64 Shiv Puri 3848

Page 90: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 70 -65 Laxman Vihar 24058

66 Rattan Garden 1298

67 New Colony 6085

68 Krishna Colony 6829

69 Jyoti Park 7250

70 Madanpuri 5290

71 Baldev Nagar 5487

72 Feroz Gandhi Colony 4325

73 Manohar Nagar 2365

74 Subhash Nagar (part) 1341

75 Vijay Park 1345

76 Pratap Nagar 2073

77 Nai Basti 4150

78 Ram Nagar 1097

79 Arjun Nagar 4878

80 D Colony 975

81 Model Town 5880

82 Veer Nagar 1097

83 Shakti Nagar 1685

84 Laxmi Garden 3780

85 Hira Nagar 4679

86 Shivaji Nagar 7290

87 Gandhi Nagar 5680

88 Shiv Nagar 8392

89 Shanti Nagar 4650

90 Om Nagar 4885

91 Raj Nagar 2126

Page 91: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 71 -92 Shivji Park 4500

93 Rajendea park area 23560

94 Surat Nagar 6135

95 Amar Colony 3850

96 Jyoti park – F.G. Colony – Basairoad

600

97 Sohna Chowk old railway road –Kabir Bhawan Chowk

600

98 Kabir Bhawan chowk to PHcampus

1000

99 PH office to Vivekanad school,Krishna colony

2000

100 Vivekanad school, Krishna colony- MPS

2000

101 Railway station – chowk of sector4&5

1000

102 Laxman Vihar – Railway road 800

103 Harish Bakery – chowk of sector4&7

2280

104 Chowk of sector 4&5 to MPS 1300

105 Railway phatak surat Nagar -Bajghera Road

900

106 Daulatabad road – IPS 1630

107 Shiv mandir surat Nagar –Daulatabad road

900

108 Vishnu Garden – Bajghera road 400

109 Railway line swaroop Garden –Bajghera road

300

110 Rajiv Gandhi school – Bajgheraroad

300

111 Shersingh colony – Daulatabadroad – Bajghera chowk

2300

112 Sewer line self laid by public 93000

Total501514

Length of storm Water

Page 92: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 72 -S.L Stretch Type Lenght

1. Basai chowk to sethi Hospital alongBasai Road

RCC box typedrain

3030

2. Umang Bhardwaj Chowk to policePost Pataudi road

RCC box typedrain

1815

3. Police post Pataudi road to SDSchool khandsa road

RCC box typedrain

655

4. Khandsa Road sec. 10-A to towardsAnaj Mandi

RCC box typedrain

715

5. Sethi Nursing home to sohnaChowk

RCC box typedrain

598

6. Sohna chowk to jail Road RCC NP3 Pipe 388

7. Jail Road to More chowk RCC NP3 Pipe 423

8. More chowk to DDR Chowk RCC NP3 Pipe 191

9. DDR chowk to Patel Nagar uptoNear P.H. residence

RCC NP3 Pipe 219

10. Pataudi chowk to Public HealthOffice

RCC NP3 Pipe 801

11. Public Health office to subhashnagar

RCC NP3 Pipe 698

12. Shama Pesturant to DDR chowk RCC NP3 Pipe 899

13. Gandhi Nagar to police PolicePataudiChowk

RCC NP3 Pipe 479

14. S.D. school Khandsa road toKhandsa road sagar steel

RCC NP3 Pipe 477

15. Om nagar to Raj Nagar chowk RCC NP3 Pipe 360

16. Raj nagar chowk to Hira Nagar RCC NP3 Pipe 245

17. Road gully to existing storm waterFor above said area.

RCC NP3 Pipe 1643

18. Storm water Drainage system in 4& 8 Marla, Model Town,

RCC box typedrain

1540

19. Petrol pump, New colony toKrishna colony

RCC box typedrain

1600

20. Old Railway road RCC NP3 Pipe 3800

21. New railway road RCC NP3 Pipe 4000

Page 93: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 73 -

Minimum Machinery to be deployed:

Bidder must own at least 2 Nos. High Capacity Super suckers, 4 Nos. silt carrying pay loaders, 2 nos. JettingMachine & 1 no. CCTV Camera for survey.

22. Rajeev chowk to Nehru chowk RCC NP3 Pipe 2400

TOTAL 26976mtrs.

EquipmentName

Model & specific Nos.

High capacitysuperSuckers

Heavy Duty, vacuum Machine Air handlingcapacity of min 4000 Cum/Hr. Capable ofAchieving vacuum of 8000mm Watercolumn (80% vacuum) (ReputedMake)

2 Nos.

Silt carryingPay Loaders

Min 10 Cum silt carrying capacity Equippedwith Hydraulic Rear Door Lift & TippingArrangement.

4 Nos.

Jettingmachines

High Pressure Jetting System operated WithHigh pressure of Dischrge capacity Of 780liter Per Minute & pressure upto 140 Bar

2 Nos.

CCTV Camera 10x optical zoom12x Digital zoomPAN & tilt 2 x 175d

1 Nos.

Page 94: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 74 -

STP/MPS/IPS

The contractor is to maintain Sewage Treatment Plant (STP) and Main Pumping Station (MPS)Intermediate Pumping Station (IPS) on turn Key basis. However basic responsibility is as under:-

1. Operation and Maintenance of MPS/IPS including Civil, Electrical, Mechanical and any otherworks.

2. Operation and Maintenance of Sewerage Treatment Plant (STP) including Civil Electrical,Mechanical FRP, PVC, HDPE & any other works.

3. Sampling & Testing of influent sewage to know its characteristics. This is to be done on daily basisand as per instruction of WPCB in force from time to time.

4. Laboratory will be maintained properly by the agency. Desilting of FPU’s once in the contractperiod but with in 2 years.

5. Proper maintenance of all the other buildings at MPS/IPS & STP site including Brickwork of theareas. This includes proper maintenance of electrical & P.H. installations also.

6. Proper use of sludge, which shall be available from sludge drying beds.

7. Proper use of methane gas, which shall be produced in the UASB reactors.

8. Maintenance of log books of all the machinery separately & collective's both at the MPS/IPS &STP as per Performa provided by the Deptt./DNIT.

9. To take preventive and curative maintenance steps as per instruction given in DNIT/ byDepartment from time to time.

Digital view Angle = 90d(LED Light Enabled)

J.C.B 1 Nos.

Water tanker TATA 2 Nos.

Mixer Machine 2 Nos.

Page 95: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 75 - Log book showing pressure, discharge, rate of flow, total flow, voltage current, levels in

sump/SWR interruption of power if any hourly.

Log book showing power factor and MDI readings.

Log book of switchgear, HT/LT panels showing all relevant details.

Log books of C.R Panels.

Log books of I.C Panels.

History sheets of overhauling/ maintenance/ replacement of all important electrical/mechanicalequipments.

10. Proper Security of the campus shall also be contractor’s responsibility.Executive Engineer

11. Clearing of reactors and other sumps as per requirement. Cleaning of Gas hoods shall be doneevery quarter. Regarding frequency of this cleaning, decision of Engineer-In-Charge shall be final &binding.

12. The records maintained by the contractor shall be produced periodically to the Engineer-in-Chargeof proper monitoring.

The details of Operation and Maintenance unit wise are described as below.

A STPAs prescribed in chapter “General Operation & Maintenance procedure of DNIT.

B PUMP HOUSE

Operation and Maintenance:-

For the purpose of operating pumps as above, it shall be the responsibility of the contractor to properlycontrol, operate, maintain and safely keep all electricity units such as 11 KV switch gear, HT/LT panels,CR panels, IC panels capacitors, transformers etc.

Pumps/motors. cranes/exhaust fans etc. shall be operated and periodically overhauled as per normsprescribed in the latest IS codes and manuals provided by the manufactures.

All electrical installations shall also be operated and maintained periodically, and checked for theirperformance as per codes and manuals provided by the manufactures.

Valves and other appurtenances shall be operated and maintained periodically, and checked for theirperformance as per codes of practice and manuals provided by the manufactures.

All measuring equipments/devices for measuring pressure discharge/levels etc. shall be operated andperiodically maintained.

C GENERAL MAINTENANCE

The pump house and its surrounding shall be kept in clean and dry condition, properly ventilated andilluminated. For the purpose of illumination the maintenance and replacement of fittings/fixtures shall bedone by the contractor.

To keep the pump house in dry conditions, the necessary required drain pumps have been installed whichshall be operated and maintained properly. The electrical panels cranes, pumps and motors, walls of pump

Page 96: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 76 -house/MEP room, stair cases, railing, battery charger room floor at MEP room, DFE room, capacitor roometc. shall be Kept and maintained dust oil/grease free to the satisfaction of the Engineer-in-Charge.

Executive Engineer

All kerb & channels should be painted. All buildings /boundary wall /iron gate should be white washed /distempered/ snowcem / painted every year.

D SWITCH YARD UNIT:-

The switchyard units though are of non operational type, but it shall be the responsibility of the contractorfor proper functioning of installed units.

The maintenance/overhaul etc. shall be the contractor’s responsibility, the periodical filtration oftransformers oil shall be carried out and record shall be maintained.

Any electrical fault in the switchyard unit shall be immediately attended and repaired. The materialrequired for its replacement shall be contractor responsibility and suitable stores shall be maintained tomeet out any sort of contingencies immediately.

As the units installed in the switchyard are of high tension powers carrying 2300 volts. standard safetyprecaution shall have to be observed as per practice adopted by HVPN. Any instructions conveyed byHVPN shall be obeyed and implemented by the agency.

Customer Complaint Redressal System

i) Liaison with the Customer Service Call Center. The Customer Service CallCentre has already been established by CORPORATION.ii) Establishment, operation and maintenance of complaint centre over the town.iii) Arrangement to flash Customer Complaint Redressal Numbers, at 100locations, across the project area.iv) Upon receipt of complaint, the customer shall be provided with a referencenumber and a response time for designated person to reach the site and assess thesituation.v) Maintenance a Complaint Response time (Strictly to be met within 2 hours oflodging a Complaint, failing which Contractor has to face Penalty, as per Clause),to access the nature of complaintvi) Issuance of a ticket, for complaint Redressal, after the nature/ extent ofcomplaint are identified, indicates the timelines for Redressal. (Redressal, Strictlyto be met within the time limits indicated on the ticket hours of lodging aComplaint, failing which Contractor has to face Penalty, as per Clause)

General Scope

ii) Arrangement for diversion of the traffic and Public movement for making thesite clears from the obstructions for smooth operation.iii)Observe all safety measure(s) per the norms of Govt. under various acts andrules.

Page 97: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 77 -iv) Providing adequate safety gear to personnel involved in cleaning of sewers andmanholes.v) Providing and maintaining of proper barricading and night light at the siteswhere work is ongoing.vi) Every installation shall be kept in tip top condition if any improvement isrequired shall be done by agency at his own cost. So bidder/agency shall visit thesite before bidding.vii) The agency will bear the cost of dismantling of road during cleaning andsearching of manholes.viii) If any additional civil work is required to be carried out during operationand maintenance shall be paid at Par to Haryana Schedule of Rates which shall bemaximum to Rs. 10.00 Lacs per year.

Maintenance of Records

ii) Maintenance of log books indicating the consumables used units of electricityconsumed, quantity of diesel consumed, and time of failure of electricity.iii)All abnormal events e/g/ continuous power failure / failure of equipment’setc/ shall be reported to the Engineer-in-Charge promptly in writing only.iv) The actual bills of petrol pumps dealer shall be submitted along with thereimbursement (of diesel) bill raised by the agency.v) In case of failure of power supply from DHBVN, contractor will have to informExecutive Engineer- in-Charge / Assistant Engineer, Superintending Engineerimmediately and approach to DHBVN and will take all necessary steps to restorepower supply immediately. The contractor is also responsible to provide all sort ofhelp and cooperation to DHBVN staff at site for restoring supply, meter readingetc.vi) Shall have to submit specific information other than monthly information onprescribed form to the office of Engineer-in-Charge as per his requirement.vii) Contractor will have to maintain the computerized record of maintenance/ repair works, Preventive as well as break-down work, carried out. Separatehistory sheet should be maintained for every equipment / machine

Responsibility of CORPORATION

i) CORPORATION shall provide free access for the cleaning of sewer line from allencroachments.ii) The agency will bear the cost of dismantling of road during cleaning andsearching of manholes. The same shall be restored to the original position byCORPORATION.iii) The water shall be provided by CORPORATION free of cost at source andtransportation shall be done by the agency at his own cost.iv) The call center has already been setup by CORPORATION and the agency hasto make liaison with it for prompt Redressal of complaints.v) The electric energy for operation of pumping machinery and for operation andmaintenance of treatment plant will be supplied free of cost by theCORPORATION.

SPECIAL CONDITION /RESPONSIBILITY OF SUCCESSFUL AGENCY

Page 98: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 78 -

The agency shall be responsible for the following:-

1. The agency will ensure proper running of the plant, instrument & equipment to give the desiredeffluent standards i.e. BOD less than 30mg/l and TSS less than 50mg/l. The agency will responsible foroverall maintenance of the plant i.e. Civil Electrical and mechanical, including gas utilization and gasflaring system.

2. The plant and equipment’s covered under the above contract shall be totally attended to by thecontractor included any “Trouble Shooting” to ensure smooth and trouble free operation.3. The contractor will monitor the quality of influent and effluent. The contractor shall intimate andtake adequate action to ensure smooth and satisfactory performance/running of the plant on 24hours/round the clock basis.4. The contractor shall prepare and implement an effective plant maintenance programme inconsultation with Engineer-in-Charge. It will be absolutely contractor’s responsibility to look after allsorts or maintenance whether preventive or break down. The agency shall maintain the operation activityrecord as per table No. 5.1 and 5.2 prescribed in Chapter “General Operation & Maintenance procedure”of DNIT.5. The contractor will be responsible for keeping upto date record of documents including Historycard for equipment’s and maintaining every day log book relating to running of machinery and variousanalysis performed. The agency shall record and maintain the operation and maintenance date of atleastfollowing units of STP on prescribed sheets:-

Daily Status record of STP Daily flow record Daily sampling record Record of screen chamber Record of Grit Chamber Performance data of UASB reactor

Performance/evaluation sheet of the UASB STP. Sludge profile data of UASB rector Record of sludge discharge from sludge sump Record of Bio –Gas Producing Record of Bio-Gas Composition.

Operation record of Duel Fuel Engine.

The Sample Proforma of the Data-Sheet is enclosed as Appendix ‘B’

6. The contractor will prepare and submit a daily report of plant performance and will assist thedepartment in preparing the necessary documents for their perusal and record.

7. The contractor will be responsible to carry out day to day as well as periodic maintenance,necessary to ensure smooth and efficient performance/running of all equipments/instruments installed atthe Sewage Treatment Plant and Main Pumping Station. The agency shall hand over the machinery & siteto the department after expiry of the contract period, in the same condition as it was at the time of theaward of the contract.

8. The contractor shall also be responsible for proper upkeep of all the buildings including godown,staff quarter and boundary wall at the Sewage Treatment Plant and Main Pumping Station.

9. He shall be responsible for proper maintenance of all the pumps and allied items including BarScreens, Gates etc.

10. He shall be responsible for maintenance of Street Light, Poles & Light also.

Page 99: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 79 -

11. Land Scaping has been done on the Sewage Treatment Plant. He shall maintain the same and keptit in proper condition.

12. The Estate water supply, sewerage system, street light, roads & paths provided at the SewageTreatment Plant shall also be maintained properly.

13. The sludge available from Sewage Treatment Plant shall be property of the agency and suitablecredit for the same shall be offered by the agency in its price bid.

14. The agency shall also be responsible for proper gas production and shall put it to proper use. DuelFuel Engines have been provided at Sewage Treatment Plant for conversion of gas to electricity. Thiselectricity shall be utilized for lighting the Street Lights and the building at the STP & MPS/IPS includingStaff Quarters and running of machinery at STP and MPS./IPS.

15. For effective maintenance of STP, the agency shall employ sufficient staff with properqualification, for its guidance the pattern and minimum of staff to be engaged is appended in DNIT. Thisincludes the running of different components of STP, which and word of site for 24 hours, mtc. Of estatewater supply and sewerage system, street light, roads, as well as lawns.

16. The maintenance period in the 1st instance shall be 36 months from the date of award.

17. If any electrical/mechanical part is not available at MPS/STP/IPS as per approved originaldrawings the agency shall supply/fire them in this contract.

18. The agency shall ensure that there is no flooding during rainy season.

19. The contractor shall abide by all Central/State Government /Semi Government /Local Bodies rulesregulation pertaining to this contract without any extra cost.

20. The contractor shall inspect the site before submitting the tender & the contractor is bound uptotake over the charge of STP & MPS/IPS in the condition as it exists and if any repair of short at siterequired for maintenance, it is the sole responsibility of the contractor & the cost for such items is alsotaken in the price bid & nothing extra for the same shall be paid to the contractor.

21. The roads and paths at the Sewage Treatment Plant (S.T.P.) shall be maintained properly .

22. The treated effluent shall be used by the agency to the best of his ability and revenue so collectedshall be kept by him as property of the agency and suitable credit for same shall be offered by the agencyin its price bid.

23. The agency shall apply consent and pay required fee u/s 25 & 26 of the water (prevention andcontrol of pollution) Act 1974 to Haryana State Pollution Control Board annual or after every such periodas desired by Haryana State Pollution Control Board and shall be fully responsibility for any legalproceedings initiated by Haryana State Pollution Control Board for failing to comply with any norms,rules, regulations of Haryana State Pollution Control Board.

2. SPECIAL CONDITION OF CONTRACT – I

1. Initially the work shall be awarded for a period of 60 months from the date of award. The agencyshall immediately on award of the Job, mobilise its men & machinery.

2. If the Job is not taken in hand up to 7 days after the due date earnest money deposit shall beforfeited and the Job shall be withdrawn. The agency shall also be blacklisted.

Page 100: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 80 -3. At present, the department has residential quarters for operating staff at the STP site, which shallbe at the disposal of the contractor for use to his staff deployed at the STP. House rent/Electricity bill inrespect of staff quarters allotted to the agency shall be charged at the Government rates. For this purpose,the agency shall install its own submitter and pay the charges accordingly.

4. The department will allow the agency to make use of Laboratory set up at the STP site & undertake the sampling & testing of both influent & treated effluent. The chemicals and reagents will also besupplied by the agency. The agency will employ its own chemist for testing purpose. However thedepartment will be at liberty to get random sampling & Testing done from any reliable agency/StatePollution Control Board.

5. The office building is situated at the STP, which can be used by the contractor as his office for thisJob only.

ELECTRICITY CHARGES

The electricity charges will be paid the department on actual basis as per electricity bill raised by theHVPN Ltd. However, it shall be responsibility of the contractor to maintain power factor as per HVPNrules, so that no extra payment on account of non maintenance of correct power factor is levied by HVPN.In case of non compliance, extra charges levied by HVPN on account of un-proper power factor shall berecovered from the bills of contractor.

SPECIAL CONDITIONS OF CONTRACT-II

1. Servicing of D.G. Set/Dual Fuel Engine shall be responsibility of the contractor. However theelectric charges & diesel for running of the STP & MPS/IPS will be paid by the department.

2. The site will be open for inspection by the designated officers/official of the PHED at all timesduring the contract period.

3. The price bid shall include all repairs/job work of all civil, electricity & mechanical works andmaintenance of FRP, PVC & HDPE items complete in all respects in working order.

4. Epoxy coating shall be done quarterly on manual and mechanical screen & ventilators of MPS/IPS& STP, chequered plates on Division box, sludge sump, drain sump, all M.S. parts in screening cum gritchamber, gate on combined effluent channels. In case of default Rs. 5000/- per MLD of rated capacity ofSTP, shall be deducted per quarter.

5. Test for faecal and E. Coliforms shall be done at least once in 7 days by the contractor, for influentas well as the effluent.

6. The agency will employ required staff for the regular running of different components of the STP& MPS/IPS watch & ward of site for 24 hours, maintenances of roads & paths as well as lawns and willhave to employ minimum staff required for the purpose as may be decided by the PHED.

7. The agency will be free to sell sludge as well as treated effluent produced from the STP to farmersfor use as manure irrigation purposes if suitable credit is given for the same in the O & M bid.

8. White washing / distempering /snowcem / painting shall be done in the every first quarter of 1st

year, 2nd year & 3rd year at all civil structures i.e. staff quarter, boundary wall/iron gate/ godown etc. bythe contractor.9. The transformer oils shall be dehydrated once in a year or earlier as required & cost of the sameshall be included in the price bid.

Page 101: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 81 -10. ACB installed at site shall be serviced twice in a year panels shall be serviced quarterly in a yearregularly & cost of the same is also to be included in the price bid.

11. 25mm thick premix carpeting of roads shall be made by pavers in the first year out of three year &cost of the same shall be included in the price bid.

12. Fire fighting extinguisher provided at site shall be got refilled by the contractor minimum once in ayear or earlier as required.

13. Epoxy coating shall be done on inside & outside of the M.S.Gas dome once in a year.

14. In case of motor/transformer or any other component is burst or damaged, it shall the soleresponsibility of the contractor to replace / repair the same as per site of the equipment / components freeof cost. At least 4 Nos. pumping machinery should be in running condition at every time at MPS.

15. Epoxy / bitumen coating shall be done to the internal concrete portion of UASB Reactor once inthree year & cost of the same shall be included in the price bid. This epoxy / bitumen coating will be gotdone during first year of contract period.

16. The contractor shall be responsible for replacement of 25cm thick top layer of the filter media in allthe sludge drying beds.

Any other works not covered above but required at site to maintain the system and coverscope of work shall be responsibility of the agency without any additional cost.

6. Handing Over

The contractor will hand over the sewer system after completion of Contract Period withrunning smoothly of the entire main / trunk / branch sewers as well the open, pipe & boxtype storm water drains channels and disposals and sewage pumping stations.

Page 102: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 82 -SECTION 7

SPECIAL CONDITIONS OF CONTRACT

These Special Conditions of Contract delete, amend or add to the clauses in the GeneralConditions of Contract. In the event of an inconsistency, these Special Conditions ofContract shall take precedence over the General Conditions of Contract to the extent of thatinconsistency.All conditions mentioned herein and under scope of services shall be fulfilled with noadditional cost implication.Detailed Scope of Services

(1) Immediately, after award of contract, the contractor shall conduct areconnaissance survey of all the sewer lines. During, these surveys allbroken/missing manhole cover and frame, road gully shall be counted and assessed.(2) The contractor shall do all repairs related to Civil, electrical, mechanicalengineering works & replacement of materials and spares required for variousinstallations, disposal works, temporary pumping station, complaint centers,manhole, sewerage / storm water lines and carrier channel, open, pipe & box typestorm water drains, rising mains etc.(3) All the broken/ missing/ damaged manhole covers shall be replaced within 30days from the award of contract. Also, the contractor shall ensure that all manholeshave covers in place, throughout the contract period.(4) The contractor shall do all type of dismantling, assembling, fitting of machines,equipment and their repairs.(5) The contractor will ensure availability of Sewer Cleaning machines as perrequirement and the written directions of the Engineer-in-Charge to complete thework of desilting of sewer lines within stipulated period(6) The desilting of main sewer (dia. ranging from 300 mm and above) along withopen, pipe & box type storm water drains channels will be taken in hand immediatelyafter the notified date of commencement of work and smooth flow of sewage will bemaintained in sewers.(7) The desilting of the sewers will be done as per priority fixed by the Engineer-in-Charge. After this, desilting of branch sewers of smaller size, open, pipe & box typestorm water drains will be taken in hand and smooth flow shall be maintained in allthe branch sewers, smaller drains etc.(8) The contractor will make adequate arrangements for diversion of the traffic andPublic movement for making the site clear from the obstructions for smooth repair,desilting and maintenance operations.

(9) The contractor shall dismantle the roads, if required, during cleaning andsearching of manholes. The same shall be restored to the original position byCORPORATION.

(10) During rainy season, if any area of the town is flooded with the rainy water,the contractor shallbe responsible to provide temporary machinery and required power arrangementon the site to pump out the storm water. The storm water should be pumped out inminimum possible time.

Page 103: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 83 -

(11) Sufficient number of Mobile electric & diesel engine pumping sets shall be arranged,maintained and operated by the contractor for routine maintenance and during storm waterdrainage. He shall maintain & operate these sets fully during contract period. The runningand maintenance cost to operate these sets will be borne by contractor.

(12) The contractor will engage sufficient number of super suckers and jettingsewer cleaning machines to achieve the scope of services and objectives of contract.In case, additional super sucker or jetting machine

(13) The contractor will ensure no spillage, of silt on the ground. The silt sucked bythe Super Sucker Machine shall be transported in sealed Dump Tank to the SewageTreatment Plant Site for disposal.

(14) The contractor shall ensure smooth flowing of sewers and storm water drainsthroughout the contract period.(15) Immediately, after award of contract, the contractor shall conduct areconnaissance survey of all the sewer lines/ During, these surveys all panels, MCB’S,all type of cables from H-Pole to Pump sets, electric fitting, electric installations,mechanical parts and accessories, screens etc. shall be assessed and contractor shallrectify/ repair within 30 days. Also, the contractor shall ensure that all machinery,equipment’s and instrumentation is in working order, throughout the contract period.(16) The Contractor shall be responsible for smooth running of the pumping stationson its rated & installed capacity.(17) On award of contract, the contractor shall submit a preventive maintenanceschedule for all civil, mechanical, electrical and instrumentation (includingreplacement of fuses, glands packing, oiling, rectification of fault in electrical andelectronic circuits, Arresting sparking, water and oil leakage) etc. The contractor shallcarry out the preventive maintenance of the transformers, DG sets, motors, pumpsand all other electrical, mechanical and instrumentation etc. as per schedule,throughout the period of contract.(18) In case of major break down of machine, the contractor shall address thebreakdown and at the same time provide alternate arrangements to ensure smoothoperations.

(19) The Contractor shall carryout all essential and breakdown maintenance/ repairwork on a continuous basis. All the breakdown maintenance shall be completed asper the complaint Redressal timelines.(20) Complaint Redressal shall be completed as per the complaint Redressal timelinesprovided by customer service call center, irrespective of day or night. If required, thecontractor may have to deploy more manpower and machinery, to meet the timelines.(21) During breakdown, maintenance staff shall not be permitted to leave thepremises before completely redressing the complaint. In exceptional circumstances,permission of Engineer-in- Charge may be sought for.

(22) The Contractor shall install energy saving equipment’s like capacitor’s etc for ensuringconsumption of electricity in most economical way.

(23) The contractor shall make all necessary arrangement to maintain power factor of 0.9. Ifany up-

gradation, in equipment’s/ installations is required, it shall be done by the

Page 104: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 84 -contractor/

(24) In the event of electricity failure, the D.G Set shall be put into operationimmediately and shall ensure smooth operations of machinery at pumping stations

(25) The contractor shall maintain the entire plantation, watering of green belt, withinthe pumping station premises.(26) The contractor shall maintain good housekeeping, cleanliness, ventilation andproper illumination during night, within the pumping station premises. Allmanpower, material, machinery, tools and tackles for the purpose shall be provided bythe contractor(27) The contractor will carry out the distemper / white washing / painting once in ayear on the all structure i.e. pump chamber / staff quarters, all machinery, pipes etc.(28) The complete watch and ward of the pumping station premises, on account ofbeing Government Property, shall be the responsibility of the contractor,

(29) The contractor shall depute only trained and efficient manpower foroperations and activities under the contract.

(30) In case of strike by contractor’s employees, contractor will have to makenecessary alternate arrangement for operation and maintenance of the plants but in nocase day to day operation & maintenance work should be stopped. If necessary,contractor can seek police protection/ seek help from home guards. The necessaryletter(s) shall be floated by CORPORATION.

(31) The contractor shall extend full cooperation to DHBVN staff at site for restoringsupply, meter reading etc

Site Assessments, Taking Over, Inspections and Handing Over(32) The brief details of Sewerage System & Storm Water Drainage System ofGurgaon town have been provided in the tender document. However, the contractoris encouraged to conduct site visits, verify the details, make self assessments andconduct due diligence in light of the tender document, before submitting the pricebid.(33) On award of contract, the contractor shall take over all the Sewer Systems, StormWater Drainage System, and Pumping Stations on ‘!s is where is basis’ in the projectarea, for the contract period from CORPORATION.(34) At the time of taking over the said work by the contractor, if some machine /pump sets are found out of order / under maintenance, then all these machines /pump sets will have to put in working conditions, within reasonable time as decidedby Engineer-in-Charge

(35) The CORPORATION, in the capacity of owner, shall be at liberty to conductscheduled and surprise inspections of the project facilities, machinery,instrumentation and control. CORPORATION shall also be at liberty to invite thirdparty for inspections. Contractor shall comply with the suggestions and directionsconveyed to him for the inspection of plants.(36) Contractor shall extend full co-operation to the inspections to Engineer-In-chargeor any Statutory Authority visiting the plant as per rules.(37) The contractor shall Conduct CCTV surveys of designated sections of the sewernetwork for assessment by Engineer-in-charge to ascertain the flow conditions.

Page 105: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 85 -(38) Upon completion of Contract Period, the contractor will hand over the sewersystem in smooth running condition including entire main / trunk / branch sewers aswell the open, pipe & box type storm water drains channels and sewage pumpingstations.

Communications and Maintenance of Records

(39) Upon award of contract, the contractor shall designate a qualified andexperienced person as the Project Manager. The Project Manager should be wellconversant with the job and can guide or pass the instruction to field staff properlyand he should be available round the clock on telephone or at site.(40) The Project Manager will work in close co-ordination with the Engineer-In-Charge for providing updated information and receiving instructions. The projectmanager shall work as the single

point of contact, from contractor’s side.(41) The customer complaint service center has been established by CORPORATION.CORPORATION shall identify two telephone numbers dedicated for complaintsrelated to Sewerage, Storm Water and Sewage Pumping Stations. Upon receipt ofcomplaint, the customer shall be provided with a reference number and a responsetime by customer complaint service center staff for designated person to reach the siteand assess the situation.

(42) The contractor shall have liaison with the customer complaint service center.(43) The contractor shall establish 10 complaint centre all over the town as decided byEngineer-in- charge(44) The contractor shall arrange to flash the ‘Two identified Customer ComplaintRedressal Numbers’ at 100 locations, across the project area.(45) Immediately after award of contract, the contractor shall develop formats forrecording of nature of complaints received from the customer complaint servicecenter, Complaint response time, Redressal for maintenance / repair works. Theformats shall be submitted for approval and the contractor shall maintain this recordthroughout the contract period.(46) The contractor shall maintain computerized record of all preventive maintenancework. This shall also be supplemented with Separate history sheet(s) for everyequipment / machine(47) The contractor shall maintain computerized record of daily consumption ofelectricity and time of failure of electricity in the log book, consumption of diesel,

(48) The detailed record entry of silt clearance indicating area, length of sewer, portionsof manhole will be made in the measurement book which shall be checked 25% byAssistant Engineer in- charge of the work and random checking to the extent ofminimum of 10% will be carried out by the Engineer-in-Charge.(49) The customer Redressal formats, nature of complaint, name of the complainant,location of complaint, date on which complaint received, action taken to tackle thecomplaint and date on which complaint rectified, preventive maintenance formats,record of daily consumption of electricity, sewers being cleaned,. All such records shallbe updated on daily basis and shall be presented to the Engineer-In-Charge twice amonth for information on 15 of the subsequent month.

Page 106: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 86 -(50) In addition, the Engineer-In-Charge shall be at liberty to check the records any timeduring the contract period.(51) Any abnormal event like continuous power failure / failure of equipment’s etc/shall be reported to the Engineer-in-Charge promptly in writing only.

Manpower & Work Force

(52) The contractor shall deploy only trained/ specialized/ experienced personnel forworks related to preventive and breakdown maintenance.(53) Upon award of contract, the contractor shall designate a qualified and experiencedperson as the Project Manager.

(54) Workers to be engaged under contract should possess technical qualification andexperience as below: -

A) Project Manager BE Civil with over 15 years of Experiencein Management of Sewerage NetworksOrDiploma in Civil Engineering with over20 years of Experience in Management ofSewerage Networks

B) Pump Operator (s) Should be at least ITI certificate holderpreferably in such as Electrical,Mechanical

C) Worker carrying out work withelectrical Installation.

Wiremen license with 6 monthsexperience of working with H.T.Installation.

DESCRIPTION OF STAFFING

Details of the various staffing, their levels, functions and responsibilities for the operation and maintenance of a

Sewage Treatment Plant and Main Pumping Station (M.P.S)/IPS is given below in the Table 7.1

Table 7.1 Staffing of UASB STP & MPS /IPS (To be Provided by the agency)

Sr.No

Function Level Number ofPersonnel

Maj. Task of the personnel

1. Chemist M.Sc.Chemistry

1 Daily analysis of samples of the treatmentplant.

2. Lab. Attendant 12 Standard 1 Assistance to Chemist in daily analysis ofsamples.

3. Operator ITI 7 Execution of specific tasks as indicated by theJunior Engineer

4. Electrician ITI 1 Responsible for maintenance of Elect.Equipment.

5. Fitter (Mech.) ITI 1 Responsible for maintenance of Elect.Equipment.

6. Cleaner High School 18 Assistance to operator for cleaning of grit

Page 107: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 87 -(Sewerman) Literatre chamber/chnnels, removal of screening &

opening of HDPE pipes.7. Casual Labour - 5 Miscellaneous task

8. Watchman - 3 To protect the plant from the trespassers,animals. Etc.

9. Gardener - 2 Maintain the garden of the plant.

*To be provided by the Department. ** To be provided by Contractor.

(55) All the workers engaged on the work shall be the employees of the contractor andcontract shall be completely responsible for their regular payment as per minimumwages act. PF, ESIC, insurance and their safety.(56) Appointment / Dismissal and conditions of their services and other liabilitiesregarding workers engaged under the contract shall be the responsibility of thecontractor.(57) Contractor shall maintain the record of attendance, wages paid to the employeesand C.P.F. subscription on site.(58) The contractor shall make payment to his workers on fixed date before 7th day ofevery month. If any complaint is received by the CORPORATION for non-payment ofwages to the workers, the CORPORATION reserved their right to make such paymentto the workers and dues so incurred along with a penalty as deem fit by the Engineer-in-Charge will be recovered/deducted from the amount payable to the contractor.(59) Contractor shall be responsible for the weekly offs and leaves of the workerengaged by him as per factory act, 1948/ Govt. instructions time to time.(60) The contractor shall be responsible to pay the compensation to their employees oftheir legal heir,

as per Workmen’s Compensation !ct and as statutory rule and laws as applicable.(61) The contractor shall submit the list of the employees, along with their qualificationto the Engineer-In-Charge. The employees should possess identity cards duly signedby the contractor. If demanded, contractor shall submit the certificates showing thequalification of the employees.

(62) The contractor will provide uniform and safety gear to workers as and shouldpossess identity cards. All workers must attend their duty in proper uniform.(63) Any decision of any court, tribunal or authority as regards any worker or the staffshall be binding on the contractor.

(64) Employment to the workers engaged by the contractor on the work shall be entirelythe contractor’s responsibility/ In no case contractor’s workers / employees shall haveany right for

employment in CORPORATION. Contractor will have to submit indemnity bond dulyregistered with notary public / registrar. The draft of indemnity bond attached asAnnexure to the Tender Document.(65) The workers engaged by the contractor shall maintain discipline. TheCORPORATION reserves the right to ask the contractor to discontinue any worker formisbehavior / misconduct or negligence on duty.(66) In no case the any workers, official of the contractor should be found in intoxicated

Page 108: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 88 -condition, during the official working hours.(67) The contractor shall ensure, no worker shall be on duty without wearing safetyequipment. All safety equipments shall be arranged by the contractor/agency.(68) All the workers engaged should be medically fit and a medical fitness certificatefrom the competent authority can be asked from the contractor by the Engineer incharge.

Health, Safety and Environment

(69) The contractor shall adhere to all the guidelines and safety code issued by theNational Human Rights Commission, throughout the contract period. All Central andState Government Safety Guidelines shall be adhered to by the contractor.

(70) The contractor shall provide adequate number of necessary safety equipment,tools and tackles required for the work in good working condition. His personnelshould be trained in handling safety equipment’s and the same will have to bedemonstrated at any given time(71) The contractor shall provide adequate number of tools, torch with cells,insulated screw driver set, discharge rod and safety instrument like self breathingapparatus, rubber mats, Spare parts, Material & First Aid etc.

(72) The contractor shall provide adequate quantity of all sundry materials formaintenance and repair, such as cotton waste, gland packing, lubricating oil, greases,brooms, doormat, phenol, washing powder, soap for sweeping etc.

(73) Adequate barricading and night light should be arranged by the contractor.(74) The methodology adopted by contractor for operation and maintenance should beenvironment

friendly and as per the direction of Hon‟ble courts and as per NHRC guidelines.(75) It has been noticed that a number of accident occur, while operation andmaintenance of sewerage is undertaken. The issue has been studied by a Committee theEngineer-in-Chief, Haryana, Public Health Engineering Department; recommendationsare presented in the following paragraphs.

I. It is important that all the towns where the sewer system in operation, areequipped with necessary safety equipment should occasionally be checked for itsefficiency.

II. The main equipment for the above purpose shall be: -i) Safety belt.ii) Safety helmet.iii) Emergency (First Aid Kit)iv) Air Blowerv) Gas Mask Respiratorvi) Airline Respiratorvii) Pure Oxygen Respiratorviii) Air Respiratorix) Portable Lighting Equipment’sx) Two Mirrors and Torch equipment

Page 109: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 89 -III. It must be ensured that the equipment so procured is ISI marked, where available.

IV. The procedure to be adopted for taking the work of cleaning of sewers has beenelaborated and the same must be followed strictly and on each maintenance booth, theimportant points requiring attention of the worker should be put up in the shape of a chartin local languages. The help of sketches / diagrams may also be had so that even illiterateworkers can understand the steps so elaborated there in the chart.V. The preventive and corrective of maintenance also becomes very important for suchinstallations and are requires to be given desired priority.

VI. Proceeding of the meeting held on 06.10.1993 regarding safety measures and safeequipment for operation and maintenance staff employed on sewerage systems isreproduced as under. Relevant sections of the same may be referred for the contract, as perthe directions of the Engineer-In-Charge.

A meeting was held under the Chairmanship of Sh. Gurdip Singh, Engineer-in-Chief,Haryana, PWD, Public Health Branch, Chandigarh on 06.10.1993 in respect of issuesinvolved in the safety measures and safe equipment requirements for operation andmaintenance staff employed on sewerage systems. The list of participants is annexedherewith.

Though there were many issue related to this aspect, since the main theme was the safetymeasures to be adopted by the workman for safe operation maintenance of the seweragesystem particularly cleaning of the choked sewers, it was suggested that therecommendations may presently be concerning the main theme i.e. the safety measures tobe adopted by the workman.

After detailed deliberations the recommendation are grouped as under: -ii) Hazards involved.iii) Precautions to be adopted by the workman.iv) Safety equipment to be provided to such workman and guidelines for safeoperation maintenance.v) Preventive and corrective maintenance of the sewerage system.

The sub head wise details of each item are covered as under: -

i) Hazards involved

“Sewer gas” is a mixture of gases in sewers and manholes containing abnormally highpercentage of carbon dioxide, varying amounts of methane, hydrogen, hydrogen sulphideand low percentage of oxygen caused by septic action through the accumulation of organicmatter inside the sewer. The actual hazard is due to the presence of high levels of methaneform an explosive mixture or the oxygen deficiency or hydrogen sulphide in excess ofpermissible levels. Sometimes trade wastes may also contribute to other gases like chlorine,ammonia, sulphur dioxide etc.

Page 110: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 90 -

ii) Precautions to be adopted by the workman precautions against Gas Hazards.When a sewer or a manhole has to be entered of cleaning clearing an obstruction, it will beadvisable to in for efficient ventilation either natural or forced and get assured that theatmosphere inside the manhole of sewer is from oxygen deficiency and noxious gases orvapors. Where such clearance of the noxious atmosphere by ventilation is not possible ortimeconsuming, the following precautions must take before entering into the manhole or sewer:-a) Traffic warning signs should be erected.b) No smoking or open flames should be allowed and sparks guarded against.c) Only safety, explosion-proof electric lighting equipment or mirrors for reflection of lightshould be used.d) The atmosphere should be tested for noxious gases and oxygen deficiency.e) If the atmosphere is normal, the worker may enter in the manhole or sewer with safetyharness attached with two men available at the top.f) If any noxious gas or oxygen deficiency is found, forced ventilation should resort tousing a portable blower.g) Frequent tests as in item (IV) should be confirm even if the initial tests ate satisfactory, asconditions may change during the period workers are inside the manhole or sewers.h) If forced ventilation is not possible or satisfactory and men have to enter urgently such asin saving a life, a gas mark should worn and extreme care take to avoid all of

ignition if inflammable gas is permissible safety lights (not ordinary fly lights),rubbers or non-sparking shoes and non-sparking tools should be used.i) Only personnel experienced in the line and familiar with the dangers involvedin working in a noxious gas environment and fully equipped with the properprotective safety equipment should be allowed to enter.

ii) Precautions against infections

The personnel working in sewerage maintenance systems are prone to infections and hencethe following precautions should be taken: -

a) Emergency first aid treatment kits shall be provided to take care of all minorinjuries like cuts and burns.b) The workers should be educated about the hazards of waterborne diseases suchas typhoid and cholera through sewage and tetanus through cuts and wounds.c) The importance of personal hygiene should be emphasized and the workersshould be instructed to keep finger nails short and well trimmed, not to brushfingers when they are sore, wash hands with soap and hot water before takingfood and to keep fingers out of nose, mouth and eyes, because the hands carrymost infections.

d) Use of rubber gloves and gum boots should be insisted so that sewage orsludge does not come in direct contract with the hands and feet.

e) In laboratory work, only pipettes with rubber teats should be used to preventcontamination of the mouth. Laboratory glassware should not be used for drinking

Page 111: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 91 -purposes. In no event food should be prepared in the laboratory.

iv) Safety equipment to be provided to such workman and guidelines for safeoperation maintenance

a) Safety Equipment

The various safety equipments that are normally required in sewer maintenance work arebreathing apparatus, portable lighting equipment, non sparking tools, portable airblowers, safety belts and inhalators. The use of particular safety equipment governed by thedetection of various gases and oxygen deficiency.

Knowledge of the type of gases in the atmosphere of the working locationbecomes essential for the selection of the right type of safety equipment. Equipment andsimple tests for detection of various gases and oxygen deficiency are furnished inAppendix-I.

Normally following safety equipment should be available in each Sub Division.Their number will depend upon the size of the town.

a) Safety belt.b) Safety helmet.c) Emergency (First Aid Kit)d) Air blower.e) Gas mask respirator.f) Air line respirator.g) Pure oxygen respirator.h) Air respirator.i) Portable lighting equipments hand lampsj) Two mirrors and torch

v) Procedure for working in a SewerTo ensure proper safety standards the following steps should be followed: -

Step – I Before leaving the stores.a) Collect and check all safety equipment.b) Check working location with supervisor and list all known or potential hazards.

Step – II On arrival at site.Set up at site.

a) Ventilate the system (guarding all openings) on a sewer open up. The working manhole. Next manhole up stream. Next manhole downstream.

This is the minimum requirement. It should preferably be two manholes on upstreamand downstream. Use to be made of blowers if necessary.

Page 112: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 92 -Step – III Entry Procedure

Natural ventilation as described in step Ii (b) above should preferably to for 2 hoursbefore any entry.a) Check for gas (if in doubt stay out).b) Tie safety belt and rope before entering.c) Check ladders, step iron etc. for defect (if in doubt use a rope attached to the safetybelt).d) Keep safety ropes, spare lamp, breathing sets close to working area for immediateuse in ca of emergency.e) With the help of mirrors and torch, the status sewer to be cleared may be checked.In deep sewers the water level in the sewers should be checked before entering.Portable sets should be available while working in deep sewers.

Step – IV Working inside the sewerEvery three minutes the top man calls to the man working in the sewer. Everymessage shall be acknowledged.

Step – V Completion of work

a) Top man informed and ready.b) Danger (Normally last man out) checked that all tools, ropes etc. are out and

that the sewer is clearc) Replace all grids, guard rails, manholes covers.

d) Road signs to be removed and site cleared.e) Supervisor to be informed that work is completed.f) Wash thoroughly before eating or

vi) Guidelines for giving first aid to a gas victimb) Remove him to fresh air as soon as possible.

c) Apply artificial respiration with resuscitator if he is not breathing and if available,otherwise mouth to mouth resuscitation be administered.

d) If the victim does not respond within two minutes, remove him to the nearest hospital.

vii) Preventive and Corrective maintenance of the sewerage system

a) Preventive MaintenanceMany of the causes leading to the clogging of sewers can be prevented by periodic cleaningand removal of silt accumulations in sewer lines including manholes while the system isfunctioning.Each of the sewer maintenance gangs shall be under the supervision of a competent personwell trained in the use of sewer cleaning and safety equipments and qualified to render firstaid service in case of emergencies.

The covers of all manholes immediately upstream and downstream of the particularmanholes into which men are to enter should be removed and kept open for at least half an

Page 113: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 93 -hour for natural ventilation. Sufficient protective barricades shall be erected on the street toregular flow or prevent entry of the traffic in the area.

After the lapse of this period, there should be no noxious gas or vapour or oxygendeficiency as evidenced by the tests described in the relevant manual additional time maybe allowed if the foul atmosphere has not cleared up. Forced ventilation shall be resortedfor purging out the foul atmosphere inside using portable blowers. If the forced ventilationis already provided for in the sewerage system, the evacuation of air will be carried outfrom one end with the manhole covers kept open permitting the entry of outside air into thesewer system. It has to be ensured that the atmosphere inside the manhole is safe before theworkers are directed to enter the manholes.

With the cleaning of the sewer other repairs, if any, to the inside of the manhole, the footsteps the cover etc. should be carried out. In the case of larger conduits through which aman can walk for the work will also include the examination of the inner surface of theconduit and carrying out necessary repairs. If a sewer is damages, it has to be tackledseparately and not by routine maintenance personnel.Based on local needs, a schedule of cleaning of all the sewers in the system has to beprepared and followed. The frequency of cleaning depends on the nature of sewage flowingin a particular section and the velocities obtained in the sewers during the peak flow.

b) Corrective maintenanceCorrective maintenance becomes necessary for removal of obstructions in sewers caused byexcessive silt accumulation or damage leading to the break down of the system with flowsmuch lower than the normal.

The sewer gang for this type of work should consist of specially trained men who are awareof the hazards and capable of coping with situations calling for prompt action. Thesupervision in this case should be entrusted to a responsible person well versed in the useof the special sewer cleaning equipment, safety equipment and in first aid. For locating theexact position of blockages, it is necessary to commence observation from the overflowingmanholes down the line until the first manhole with little or no flow is reached. The sectionbetween this manhole and the one immediately upstream is the one which should becleaned first, after taking the necessary precautions for the safety of the workers. Theaccumulated sewage should be pumped out into the manhole further downstream and themouth of the sewer exposed after allowing for natural ventilation for one hour, by keepingall manholes within a radious of 200 m open, tests shall be conducted to ensure that theconditions are satisfactory for the workmen to enter the manhole, resorting to forcedventilation, if necessary. Air from the bottom of the manhole should be sucked out by anexhaust pump which will enable fresh air being drawn into the manhole. This is helpful toevacuate gases heavier than air such as Carbon Dioxide, Petrol vapour and Hydrogensulphide. Sometimes air may be blown inside the manhole which pushes out the foul gasesfrom the manhole. This is very effective for gases which are lighter than air, such as Carbonmonoxide, Methane, Nitrogen etc. if the sewage flow into the manhole is heavy andpumping has to be carried out continuously to enable men tot get in work. It is preferable toblock the mouth of the sewer on the upstream side and start pumping from the second next

Page 114: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 94 -upstream manhole while the work of clearing the obstruction in the sewer down below isbeing carried out.

In this case of simple blockages, the flexible sewer rod of the bamboo and manila rope typewill be sufficient. A ferret with a fire hose can also be used for breaking and removing sandstoppages. Where a rodding machine with flexible sewer rods is available. It can be usedwith suitable tool attachments to break the blockage.

When the above methods are not successful or damage to the sewer is suspected, thelocation of the blockage can e found by the use of sectional rods from either end of theclocked sewer. Once this is located, the sewer length near the blocks can be exposed by theopen excavation to examine and set right the sewer line. If the damage to the sewer isextensive and is caused by poor foundation then the stretch between the two manholes mayhave to be relaid on a proper foundation.

In case it is not possible to wait for proper evacuation of the foul atmosphere inside amanhole or a tank and men have to enter urgently to save a life, then only men trained towork with safety belts, gas masks and other safety equipment may be allowed to enter themanhole, observing the precautions against gas hazards and under the guidance andsupervision of a competent supervisor. In an emergency the supervisor should promptlyget in touch with the nearest police station, a fire station and a hospital for help.

Where the material of the sewer, especially concrete is damage, the cause must beinvestigated and due rectification carried out. If flows much lower than the designed oneslead to low velocities and consequent septicity resulting in the production of hydrogensulphide, routine chlorination of the sewage may have to be considered.

Force Majeure

(76) Force Majeure shall be read as per standard conditions of CPWD specifications.In addition to this following shall in regards to force majeure; Except followingconditions no other condition will be considered as Force Majeure condition: -

a. Failure of electric supply from DHBVN.b. All electrical break down at H.T / L.T control gear, switch gear, equipments ofsubstation upto a reasonable time as assessed by the Engineer-in-Charge of the work.

Page 115: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 95 -GENERAL OPERATION AND MAINTENANCE PROCEDURES

INTRODUCTION

The objective of the waste water treatment plant are to reduce the pollution load of waste water and to dispose theplant treated effluent and any other by products such as excess sludge and gas. These objectives have to be gainedwithin the resistance imposed by the plant administration fluctuating quantity and quality of the influent andpossible power cuts. A wastewater treatment plant facility is run only with a well-managed smoothly operatingentity.

The three prime activities in the plant control are operation, maintenance and data collection.i) Operation concerns the day to day activities required to maintain the quality of the treatmentprocess.

ii) Maintenance concerns the activities to keep the plant facility in good shape.

iii) Data collection concerns the collection of data on the treatment performance of the plant andrecords on maintenance and daily activity in the plant.

8.1 OPERATIONOperation relates those activities, which required to monitor, guarantine, and sustain the quality of thetreatment process. The daily operation of the plant largely consists of activities required to maintain thequality of the treated effluent.

8.2 MAINTENANCEMaintenance is meant as preventive maintenance, which are, the activities required keeping the plantfunctioning well. Daily maintenance comprises of the day to day cleaning of the plant structures and ofthose activities, which are frequently carried out to keep the plant properly in function. Preventivemaintenance aims at minimizing repairs and maximizing lifetime of the components of the plant. For thesereasons maintenance activities are carried out according to a fixed and well-planned schedule.

8.3 DATA COLLECTIONData collection is carried out under the supervision and instructions of the Junior Engineer and chemist.Samples are collected by the operator and sewer-man. A 24 hour composite sample of influent and effluentis prepared by taking samples every 2 hours and mixing them in direct proportion of the flow. Thesamples, which are being taken every 2 hours, have a volume of 100ml. These samples are collected in 2litre bottles, which are kept in a refrigerator in the laboratory. The operator indicates with a date andsignature when and from where the samples were collected.During routine monitoring, samples of influent, effluent, sludge and bio- gas are analyzed based on theanalysis Schedule given in the following Table No. 8.1 for the parameters.

Executive Engineer

Page 116: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 96 -Table 8.1 Analysis Schedule

Sr.

No.

Parameters Frequency

Mon. Tue. Wed. Thru. Fri. Sat.

Wastewater x X x x x x

Temperature x X x x x x

PH x x

BOD Tot. x x

BOD Fil. x x

COD Tot. x x

COD Fil. x x

TSS X x

VSS X x

VFA X

Alkalinity x

Sulphate x

Sulfide x

Sludge Profile

Total Solids (TS) x

Volatile Solids (VS) x

Ash Content x

Sludge Sump

Total Solids (TS) x X x x x x

Big Gas

Methane

Once a MonthCarbon Di Oxide

Nitrogen

Hydrogen Sulphide

Every week samples for the sludge profile from each reactor is to be taken. The corresponding samples areanalyzed on TS & VS. The samples are taken at different heights i.e. positions of sludge ports of the reactor.

8.4 General Operation and Maintenance of Various units of the treatment plant.

General operation of the various units of plant is provided to properly operate the plant units to achieve thedesired quality of the treated effluent. The general maintenance of the unit is provided to keep theinvestment on the plant intact and keep the units functional and without any trouble.

8.4.1.1 Intel Chamber

A Operation of Inlet Chamber

Page 117: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 97 -1. Check that the inlet is open and operational.

2. The Junior Engineer should daily check the overflow from Inlet Chamber.

3. In case of emergencies or when reactor are not operational by pass the flow from the Main

Pumping Station to the by-pass channel and avoid any treatment of the sewage.

B. Maintenance of the Inlet Chamber1) The level of the overflow weirs should be checked yearly.

2) The concrete works have to be checked and repaired when necessary.

3) The railings stairs should be painted once in a year where as M.S. parts are involved epoxy

painting shall be done quarter.

4) Greasing of valve shall be done on a regular basis in order to ensure smooth operation.

8.4.2 Screen Chamber

A. Operation of Screen Chamber1. The mechanical screen should always be in operation. The raking mechanism is controlled eitherby the differential control system or by a timer.

2. The Operator should check the correct functioning and choking of the screen and smoothmovement of the rake mechanism every 2 hours or at a suitable time interval.

3. Check that the lifting mechanism of the mechanical screen properly lifts and dumps the screeningsinto the belt conveyor.

4. While working on the screens, the sewer-men should wear protection gear & other safety devicesto be provided by the agency.

5. In the morning during his round, the Junior Engineer estimates the quantity of screen waste anddescribes the type of the waste. Data are reported in the daily status record.

6. Junior Engineer orders the disposal of the screened waste at a suitable disposal site daily hauledthrough a truck outside the plant premises.

7. Mesh screen shall be cleaned as and when it gets choked.

8. Screenings shall be dumped into the nearby area within the STP premises as directed by the JuniorEngineer on daily basis before it is hauled outside the premises. As far as possible the material should bedisposed off daily.

B. Maintenance of Manual Screen.

1. Cleaning of screen is done with a rake. Waste has to be removed from the bottom of the screentowards the top. Screening shall be removed from the bar screens and dumped on to the conveyer belt andfinally transferred to the discharge chute. From here, the screening as transferred into the wheel barrowsand finally hauled and dumped in a remote area as directed by the Junior Engineer.

2. Waste has to be put in the wheel barrow as soon as the screen tray is filled. Waste shall be dumpedfrequently in order to avoid are pollution.

C. Maintenance of Mechanical Screen

1. Lubricate all moving parts in the mechanical screen.

Page 118: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 98 -

2. Check its operation at no load condition.

3. Check the operation of rakes and conveyer belt.

4. The Screens and Mesh Screens have to be painted every three months. During painting the Screensand Mash Screens shall be checked for necessary repairs.

5. Repair of the Screen and rake mechanism has to be done immediately when required/fund rusted ordamage.

6. Repair of the Screen and replacement of the bars has to be done when required / or found ordamaged.

8.4.3 GRIT CHAMBER

A Operation of Grit Chamber1. Grit chamber is divided into even number of channels out of which half of the channels act as standby.

2. After 2 days/as per the quality of the incoming wastewater, the Junior Engineer orders to divert theflow of sewage to the stand by Grit Channels. The gate to the respective channel is lowered in order tostop the flow.

Executive Engineer

Page 119: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 99 -3. The used grit channel is first allowed to drain the excess water into the drain pit through verticalgrit removal pipe.

4. The grit channel should be washed, dried and cleaned on the same day.

5. When working in the grit channel the sewer-men should wear gloves and rubber boots in order toprotect them from any injury.

6. After the channel is drained, the sewer-men remove grit from the channels with the help of shovelsand drag the grit into the vertical grit removal pipe and finally the grit is dumped in the wheel barrows.

7. A full wheelbarrow is transported to the dumping site.

8. The operator estimates the amount of grit ready for disposal by counting the nos. of wheelbarrows.

9. The operator reports the amount of grit to Junior Engineer who incorporates the amount of grit inthe daily status report.

10. The cleaned Grit Channel should be left dry until next use.

11. The gloves, rubber shoes etc. shall be arranged by the agency.

B MAINTENANCE OF GRIT CHAMBER.

1. Every two days or depending upon the amount of grit accumulation, the stand by grit channel shallbe put in operation.

2. By instruction of the Junior Engineer the operator shall close the sluice gate of grit channel that ispresently operational and open the gate and divert the flow to the stand by grit channel.

3. The operator shall slowly open the sluice valve of the vertical grit removal pipe of the closed gritchannel in order to drain the extra water.

4. The sewer-man shall remove the settled grit from the closed channel with a shovel towards thevertical grit removal pipe from where the grit will be collected in the wheel barrows and manually taken tothe final dumped site.

5. The sewer-man shall remove the remaining grit from the channel with a water hose.

6. The cleaned grit channel should be left for drying until next use.

7. The sluice valves shall be checked and cleaned every month with the aid of a water hose.

Executive Engineer

8. Every year the concrete shall be checked for corrosion and should be repaired if necessary.

9. Greasing of valves shall be done once in three months or as per manufacturer specifications.

10. Valves shall be painted once a year.

11. Greasing of moving parts of gates and spindle shall be done once in three months or as per theguidelines of the manufacture.

8.4.4 Distribution Box

Page 120: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 100 -A OPERATION OF DISTRIBUTION BOXES.

1. The Operator and sewer-man shall clean the distribution boxes at every shift (3 times / day)

2. Obstructions of distribution box inlet pipes shall be removed with a high- pressure water hose,whenever required or by opening the joints at the bend. After cleaning the obstruction, the pipes shall beproperly joined at flanges, and the joints shall be checked for any kind of leakage.

3. The top of the central compartment of Distribution boxes shall be kept covered with the chequeredplate at all times, except during operation and repair activities.

4. The Junior Engineer shall have a record of the number of clogged feed inlet pipes in the dailystatus record (DSR).

5. The Sewer-man shall clean the weir plate of the obstruction boxes once per shift with a brush.

6. The Junior Engineer shall check the cleanness of weir plate and obstruction to the feed inlet pipes.

7. The Junior Engineer shall have a record of obstructions in the feed inlet pipes in the daily statusrecord.

8. The sewer-man shall introduce the special orifice of the pressure water hose in the obstructed feedinlet pipe and cleans the same or removes obstruction by opening the flanged connections. After removalof obstructions, the flanged connector shall be made leak proof.

9. The pipe shall be flushed the with water until it is fully opened and obstruction removed.

Executive Engineer

Page 121: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 101 -10. If inlet pipe cannot be unplugged in this manner a flexible rod should be inserted to remove theobstruction.

B Maintenance of Distribution Boxes1. Check the levels of the weir plate

2. check for any kind of blockages in the pipe.3. Check the cement works and repair when required.4. Check for leakage blockage of feed inlet pipes especially where they are connected to the feedingboxes/or at their flanged joints.

8.4.5 UASB Reactors

A. GENERAL OPERATION & MAINTENANCE1. Open and remove floating layer inside the FRP gas domes at least once in three months.2. Check the concrete works and repair when necessary.

3. Check FRP Gutters, V-notch weir plates, baffles, feeding boxes and repair when necessary.

4. All metal works, like railing, ladders chequered plates etc. shall be painted quarterly.

5. The level of the overflow weirs shall be checked and adjusted yearly.

6. The FRP structure must be checked yearly and repaired whenever necessary.

7. The floating layer at the top of reactor between the baffles has to be checked daily. When floatinglayer appears, it should be removed.

8. The sewer-man shall remove the floating scum/material at the top water surface of the reactor witha brush/broom once a day. The floating scum/material shall be collected in a bucket and transferred in awheelbarrow to dispose at the dumping site.

B. OPERATION & MAINTENANCE OF FEEDING BOXES.

1. In order to keep the plant functional, check and clean the incoming pipes from the distribution boxdaily.

2. Check that all the pipe in the feeding boxes are carrying the sewage to the bottom withoutoverflow/choking of the feeding pipes.

3. In case down-take pipes choked and feeding boxes are overflowing, record the numbers of overflowing feeding boxes.

4. When the down-take pipes are choked, the obstruction shall be removed manually by the sewer-man by properly “scrubbing” the pipe with help of a bamboo stick attached with a cleaning device at thefar end of the bamboo stick or with the help of high pressure flow water system.

5. When larger number of down take pipes are found choking due to improper screening anddegrading of the sewage the unplugging of those down take pipes shall be done in the following manner.

i) The sever-man shall introduce the special orifice of the pressure water hose in theobstructed down take pipe.ii) The orifice shall close the pipe in such a manner that a high pressure can be built up.iii) The Pipe shall be flushed with water until it is fully opened.iv) If down take pipe cannot be unplugged in this manner, a flexible rod shall be inserted toremove the obstrction.

Page 122: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 102 -6. The weir level of V-notches shall be checked and if needed the level shall be adjusted by adustingscrews to distribute the sewage quality in the reactors.

C OPERATION & MAINTENANCE OF EFFLUENT GUTTERS AND BAFFLE PLATES.1 The obstructions accumulated near the opening of V-notches of the weir plate shall be removed 3times a day.

2 In case sludge is accumulated in the effluent gutter due to improper alignment, it shall be cleanedwith a brush or with a water jet, once a day when require.

3 The levels of the weir plate fixed to the gutters are important for the correct functioning of theplant. Each weir plate shall be horizontally aligned and all gutters in one reactor shall be fixed at the samelevel. Each gutter shall have a small slope declining toward the Common Effluent Channel.

4 The sewer-man shall not step on the gutters strictly, as the gutters will not then remain leveled.

5 The sewer-man shall clean the V-notches of the gutters with a broom or brush, once in every shift(3 times /day)

6 The baffles plates and their fixing fixtures shall be checked for any kind of damage/corrosion everyyear and repaired/replaced if necessary.

D. THREE YEARLY MAINTENANCE OF UASB REACTOR.

1. Alternately each UASB reactor shall be put out of operation in every three years for themaintenance of all the internal components of the reactor and cleaning purposes.

2. In order to empty out the reactor for the above operation, sludge as well as total content of theselected reactor shall be discharged over the sludge drying beds.

3. Provide ventilation through opening of the Gas Domes and part of the PVC sheets of the gascollectors.

4. After cleaning of the reactor, apply new Epoxy/Bitumen coating to the internal concrete surfaces.

5. Check the damaged feed inlet/down – take pipes and replace wherever necessary.

6. Check the fixing of down-take pipes both at the feeding boxes and at the bottom. Replace thecorroded fixing fixtures for the pipes.

7. Check the positioning and alignment of the PVC sheets and trusses and rectify, if necessary.

8. Check the fixing fixtures of the PVC sheets and trusses and replace them, if necessary.

9. Check the quality of the FRP gas hoods, FRP gas pipes, PP valves and their fixing fixtures andreplace/rectify them, if necessary.

10. Check the PVC valves on the gas collection line and replace the same wherever required.

11. Check all the concrete works for damages and repair them, if necessary.

8.4.6 Sludge Discharge System.

A. OPERATION OF SLUDGE DISCHARGE SYSTEM.

Page 123: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 103 -1. Sludge shall be discharged from each reactor on alternate days or as per the instructions of JuniorEngineer based on sludge profile. Determination of the sludge profile shall be done as following.

a) Weekly sludge sample from different ports of the reactor at different heights shall becollected for the analysis.b) Preferably the sludge samples shall be collected between 12.00 and 14.00 hours.c) Sludge samples shall be taken at different heights of 40,80,120 160,240 and 320 cm fromthe bottom of the reactor.d) Sludge samples shall be analysed for TS VS.

2. After getting the sludge profile, Junior Engineer shall determine the quantity of sludge to bedischarged from the reactor.

3. For the operation of sludge discharge, operator shall open the sludge discharge valve in the sludgewill flow to the sludge sump by gravity. Valve shall be closed when the sludge sump is filled to its fullcapacity. Sludge shall be pumped for a specified time to the sludge Drying Beds. The operation shall berepeated for the remaining sludge to be withdrawn from the reactor. The sludge sample from the sludge pitshall be analyzed for TS.

B. MAINTENANCE OF SLUDGE DISCHARGE SYSTEM.

1. Check the operation of sludge discharge valves.

2. Check the operation of valves at sludge sampling ports. Replace the non- functional valve.

3. The spindles of the valves shall be greased every three months.

4. The glands and packing of the valves shall be checked every three months, and replace, ifnecessary.

5. The sludge withdrawal pit shall be cleaned every three months.

6. The valves, checkered – plates, ladders railings, gantry girders and rungs shall be painted everyquarter.

7. The concrete works shall be checked every year and repaired whenever necessary.

8. Electrical connections of the sludge discharge pumps shall be checked every year.

9. Corroded electrical connections shall be repaired every year.

8.4.7 Gas Collection System

A OPERATION & MAINTENANCE OF GAS COLLECTION SYSTEM.

1. Record the rise/level of the MS Gas dome.

2. If Bio-gas production is excessive, divert the gas to the gas flare system.

3. Check that the pulley of the MS Gas dome of the gas holder is freely moving over the rails.

4. Record the quantity of the bio-gas production in the Data collection sheet.

5. Record the temperature of the gas at the time of recording the quantity of gas production.

6. Record the moisture content in the gas at the time of recording the gas production.

Page 124: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 104 -

7. Check the operation of Gas Scrubbing System wherever provided.

8. Check FRP Gas hoods and gas pipes for leakage every three months. Repair the damaged portionsof the gas collection system wherever necessary.

9. Check the water level in the Gas holder daily and add water when required

10. Check the pressure in the Gas holder daily.

11. Around gas collection system following precautionary measures shall be strictly followed.

a. Avoid open fires or sparks near the reactor, gas holder, gas flaring system, DG set room,gas meters and other gas collection system.

b. Take extreme care against fire hazard while replacing/repairing the accessories provided inthe gas collection system.

c. Declare and display the gas collection system area as “NO SMOKING” zone.

d. Follow the fire preventive instructions displayed at different places in the plant.

8.4.8 Sludge Drying Beds.

A OPERATION OF SLUDGE DRYING BEDS

1. Before applying sludge to a drying bed, remove the vegetation and level the sand bed.

2. Check the position of stop log gates and splash trays under the gates.

3. Only open the stop log gate of that sludge drying bed that has to be charged.

4. Allow the sludge to flow into the sludge drying bed until the maximum height of 20cm is achieved.

5. After 6 days of sludge drying the dried sludge cakes shall be picked up by hand and stored at thesludge storage platform.

6. The emptied bed shall be prepared to further receive a new charge of sludge.

7. Sludge drying bed shall never be recharged before removing the dried sludge cakes.

8. In principle the sludge drying beds shall be charged clockwise

B MAINTENANCE OF SLUDGE DRYING BEDS.

1. Before sludge application, the upper surface of the sand layer of sludge drying bed shall be leveled.

2. The sludge feeding channel shall be washed with water after every sludge application.

3. Before every sludge application, the correct position of the splash trays shall be checked.

4. Check the Brick work, plastering and pointing yearly and repair if necessary.

5. Drainage pipes shall be checked for clogging and cleaned if necessary.

8.4.9 Final Polishing Unit

Page 125: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 105 -

A OPERATION AND MAINTENANCE OF FINAL POLISHING UNIT.

1. In order to get a uniform flow, floating material/scums in the common effluent channel andcombined effluent channel shall be frequently cleaned.

2. When flow from the combined effluent channel is entering to the FPU, the sluice gate of the bypasschannel of the STP must be closed and vice versa.

3. Proper functioning of the inlet weir and the outfall weir of the unit shall be checked daily by theoperator.

4. Weed shall be removed from the pond every year, by diverting the flow to bypass channel.

5. The Brick work, plastering and pointing of the unit shall to be checked and if necessary repairsshall be made every year.

6. Every two year (preferably in summer) sludge shall be removed from the bed of the pond. For thispurpose the pond shall be emptied by pumping out the water. The settled sludge in the pond shall beallowed to dry approximately for a week shall be and dried sludge falkes shall be picked up manually.During this period, the flow shall be diverted through the by pass channel of the STP.

8.5 Record of the Operation and Maintenance Activities.

A. OPERATION ACTIVITIES.

Following Performa of the activity records shall be maintained by the Junior Engineer monitor, guarantee, andsustain the quality of the treatment procss. The activities for the operation of the different units of plant shall berecorded daily. The records shall be maintained in such a manner that if a particular activity is performed on aparticular day, it must be marked in the appropriate box in the following record sheet. The frequency of thevarious activities for different units of the plant are mentioned in the record sheet, however if need arises theactivities can be attend to when it is felt necessary.

Table No. 8.2 : Record of Activity Schedule.

Month:

S .No Activity during operation Staff

Responsible

Frequency 1 2 3 4 30 31

A Waste Water supply from Pumping Station.

1 Record power supply in daily status recordDSR.

J.E. Once a day

B Inlet and screen chamber J.E.

1 Check overflow in the inlet chamber J.E. Once a day

2 By pass sewage if reactors are nonoperational

J.E. As reqyured

3 Check positioning of the screen S.W. Once a day

4 Clean the bar screen and mesh screen S.W. As reqyured

5 Check proper alignment and functioning ofthe bar screen and mash screen

OP Once a day

6. Record the quantity of screenings removed OP & SW Once a day

C Grit Chamber

1. Make alternate grit channel operational OP Every 2 days

2. Clean and dry the non operational gritchannel

OP & SW Every 2 days

Page 126: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 106 -3. Record the quantity of grit removed OP & SW Every 2 days

4. Clean the drain channel SW Every 2 days

5 Disposal of grit SW Once a da

6. Record the flow at proportional weir OP Hourly

D Distribution and division Box

1. Check the overflow of the individualcompartment of distribution box

OP & SW Once a day

2 Check the choking of the pipes runningbetween distribution box and feeding box

OP & SW Once a day

E UASB Reactor

Feed INLET Box

1. Clean the V-notches OP & SW Thrice a day

2. De-choke the feed inlet pipes OP & SW Once a day

3. Record the Nos. of choked feed inlet pipes J.E. Once a day

Effluent Gutters

1 Clean the V-Notches SW Thrice a day

2. Removal of floating layers of scum whenthickness exceeds 2 cm

SW As required

3. Clean command combined effluent channel SW Once a month

F Sludge pit. Sludge sump and pump

1. Take sludge profile of a reactor from sludgewithdrawal pits

JE/OP/SW

2. Discharge sludge from each sludgewithdrawal pit of UASB reactor to sludgesump

3. Pump the sludge from sludge sump to SDB

G Gas Collection

1. Record the production of gas in the DSR J.E. Once a day

2. Check the operation of gas flow meter J.E. Once a day

3. Check the leakage in the pipes and valves J.E. Once a day

4. Check the slope and joints of the gas pipes J.E. Once a day

5. Check the free movement of the pulleys asMS gas dome.

J.E. Once a day

6. Check the water level in the gas holder J.E. Once a day

H Sludge Drying Beds.

1. Clean and level drying bed to be put inoperation

OP & SW Weekly

2. Check position of gates and splash trays J.E. Daily

3. Clean the sludge chnnel SW Daily

4. Check free flow of filtrate to drain sump JE Weekly

J Final Polishing Unit

1. Removal of weeds from the FPU SW Qarterly

2. Removal of settled sludge from FPU bed SW Once in 2 yrs.

Legend:

Page 127: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 107 -

JE: Junior EngineerOp: OperatorSW: Sewer Man

Maintenance Activities:

Following proforma of the maintenance records shall be maintained by the Junior Engineer to maintain the properfunctioning of the plant. The activities for the maintenance of the different units of plant shall be recorded weekly.The records shall be maintained in such a manner that if a particular activity is performed on a particular week itmust be marked in the appropriate box in the following record sheet.

Table No. 8.3: Record of Maintenance Schedule.

Year

S .No Maintenance Activities WEEKS

1 2 3 4 5 6 47 48 49 50 51 52

A. Inlet and Screen Chamber

1 Check concrete works for crosion and leakage

and repair, if necessary.

Manual Bar Screen

1 Check the screens and replace the damaged

bars, if necessary

2 Painting of the screen/bars

3 Replace the damaged wheel borrows

Mechanical Bar Screen

1 Lubricate all the moving parts

2 Repair the screen / bars and replace the

damaged parts, if necessary.

3. Check the operation of rakes and conveyor

belt

4 Painting of the bars, screen and rakes.

Mesh Screen

1 Check the damaged mesh and replace if

necessary

2 Paint the Mechanical Parts

Sluice Gate

1 Lubricate all the moving parts

2 Clean the rubber packing of the gates

3. Check the movement of the spindle.

4. Paint the Mechanical Parts.

B Grit Chamber

1. Check the positioning of the proportional

weir

2. Check concrete works for crosion and leakage

and repair, if necessary.

3. Frequent cleaning of the drain channel

4. Painting of railings and ladders

Sluice Gate Valves

1 Lubricate all the moving parts

Page 128: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 108 -2 Clean the rubber packing of the gates

3. Check the movement of the spindle

4. Paint the valves and other mechanical parts.

C Division Box

1. Lubricate the spindle of valves

2. Check the movement of the spindle

3. Paint the valves and other mechanical parts

Distribution Box

1 Check the level and sharpness of the weir

crest

2 Check obstruction in the incoming/outgoing

pipes and remove the obstruction.

3 Check concrete works for erosion and leakage

and repair, if necessary.

4 Painting or railing, ladders and chequered

plates.

D UASB Reactor

Reactor Compartment

1 Open gas hoods, clean the Gas Hoods and

remove floating material and solidified matter

from the gas-hood.

2 Check the gas collector for gas leakage and

repair, if necessary.

3 Check concrete works for erosion and leakage

and repair if necessary

4 Paint all the metal works like railing, ladders

etc.

5 Check the thickness of floating material scum

in the Reactor, Remove these floating

material when thickness exceeds 2cm.

6 Check the down takes pipes for choking &

de-choke the pipes.

7 Remove obstructions from V-notches in the

feeding box.

8 Check the positioning of the V- notches in the

feeding box.

Effluent Gutters/Baffles

1 Clean the obstruction from V-notches.

2 Check and correct the leveling of the gutter &

baffle plate individually & in combination.

3 Check the side baffles of the compartments

and repair if necessary.

4 Check the slope of the effluent gutter and

rectify it if necessary.

5 Fixing fixture of the baffle plate & effluent

gutter should be intact.

Sludge pit/Sludge Sump & Pump

1 Grease the spindles of the valves

2 Check glands and packing of the valves,

replace if necessary.

3 Clean the sludge pits

4 Paint valves and chequred plates

5 Check concrete works for erosion and leakage

and repair, if necessary

6 Check electrical connections & wiring

Page 129: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 109 -remove corrosion.

7 Painting of railings, ladders and chequered

plates

Gas Collection

1 Check the function of gas flow meter, digital

recorder, valves etc.

2 Check gas collector, flexible PVC pipe, FRP

laterals and braided pipes for leakage

3 Check the gas flaring system and gas ignition

system.

E. Sludge Drying Beds

1 Check the thickness of top sand layer, if

10cm is lost, replenish it.

2 Check drain pipes for clogging and clean it if

necessary.

3 Check the Brick works, pointing and

plastering and repair if necessary.

4 Never allow sludge application on semi dried

or dried cakes, check it and duard against.

Drain Sump & Pump

1. Clean the Drain sump.

2. Check concrete works for erosion and leakage

and repair, if necessary.

3. Check electrical connections & wiring

remove corrosion.

4. Painting of railings, ladders, gantry girders

and chequered

9 Data Collection

General

Regular record and reports of the wastewater treatment plant operation can be used for many purposes.The collected data serve the plant management to judge on the performance of the plant and to justifydecisions concerning operation and maintenance, allocation of budget and expansion proposals for the up-gradation of the plants. These data shall be used as guide lines by the operating staff to regulate, adjust andmodify the plant facilities and treatment processes.

9.1 PurposeAn efficient communication between the personnel involved in the operation of the plant is of crucialimportance to achieve and maintain a properly functioning STP with satisfactory treatment results. Thecommunication, though in some cases may be verbal, should be essentially written and documented. Onlywritten reports allow an adequate flow of information amongst plant operation and management staff tokeep tract of the reasons for possible malfunctioning of the STP as well as to look into its performance.The various information streams are compiled into reports and result into an evaluation report which isprepared by the Assistant Plant Manager and submitted to the Plant Manager (Fig. 9.1)

Page 130: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 110 -

Figure 9.1 Reporting Scheme for operation and management

9.2 The Log BookThe log book is kept by the Asstt. Plant Manager and describes all movements in and out of the plant. Itcomprises of attendance records of personnel, the entrance of external personnel and equipment, anddisposal of dried sludge, grit and Screening etc. The Log-book is maintained by the Junior Engineer.

9.3 Data Recording:

Regular recording of the operational and analytical data every important activities in the operation andmaintenance of the running plant. These data are used to generalize the behavior of the various units underthe varying condition of the incoming sewage during various seasonal conditions. Data collection sheetswith the following Titles are described below. These data sheets shall provide the operation andperformance data of various units of the STP.

Daily status record of STP. Daily flow record Daily sampling record Record of Screen Chamber Record of Grit Chamber Performance data of UASB reactor. Performance evaluation sheet of the UASB STP. Sludge evaluation sheet of the UASB reactor. Record of sludge discharge from sludge sump Record of bio-gas production. Record of bio-gas composition. Operational Record of Duel – Fuel Engine.

Executive Engineer

9.3.1 Daily Status Record of STP

The daily status record sheet contains the information on power supply, quantities of screenings, grit collection, pluggeddistribution boxes, production of bio-gas sludge discharge and sludge application. This record is kept by the JuniorEngineer and contains basic data on plant functioning. The Junior Engineer should take the status record during the roundin the plant to note down all measurements indicated on the sheet and any observation on abnormal situations at the plant.In principle all information is collected in the morning at the beginning of the first shift. During the second shift onlyobservations are made.

APPENDIX - BTable No. 9.1 (A) Daily Status Record

Plant Manager

Asstt. Plant ManagerEvaluation Report

Junior Engineer(E&M)

Daily Status Report, Log book

Junior EngineerEvaluation Sheet

ChemistLaboratory Records and

Analysis Reoprt

Page 131: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 111 -DATE POWER SUPPLY (HSEB) POWER SUPPLY (Diesel Gen. Set) Screening

SHIFT - 1 SHIFT - 2 SHIFT - 3 SHIFT - 1 SHIFT - 2 SHIFT - 3

Time Time Time Time Time Time

Started

Hrs.

Closed

Hrs.

Starte

d Hrs.

Closed

Hrs.

Started

Hrs.

Closed

Hrs.

Started

Hrs.

Closed

Hrs.

Started

Hrs.

Closed

Hrs.

Started

Hrs.

Closed

Hrs.

No. of

Trolley

M 3

Day

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

Executive Engineer

Table No. 9. (B) Daily Status Record

Month:

Date Grit Chamber in

Operation

GRIT REMOVAL No. of DISTRIBUTION BOXES PLUGGED

No. of

Wheel

Barrows

Quality

M3/Day

Reactor 1 Reactor 1 Reactor 1 Reactor 1 Reactor 1 Reactor 1

GC1 GC2 GC3 GC4 Shift

1

Shift

2

Shift

3

Shift

1

Shift

1

Shift

1

Shift

1

Shift

1

Shift

1

Shift

1

Shift

1

Shift

1

1

2

3

4

5

6

7

8

Page 132: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 112 -9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

Executive Engineer

Table No. 9. (C) Daily Status Record

Month:

Date BIO GAS PRODUCTION Sludge Discharge from Each

Reactor

SLUDGEDRYING BEDS

Shift Reading 1 Shift Reading 2 Shift Reading 3 Sludge

Loading

Cake Disposal

Time Start End Time Start End Time Start End R 1 R 2 R 3 R 4 Bed

No.

Height Bed

No.

Quantity

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

Page 133: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 113 -16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

Executive Engineer

9.3.2 Daily Flow Record

The daily flow record sheet contains the information on pump operation, hourly flow records and averageflow to the STP. This record is kept by the Junior Engineer and contains basic data on plant functioning.

Daily No. 9.2 Daily Flow RecordDate Pump

OperationNo. of Pumpsin operation

TotaltimeHrs.Start

Hrs.StopHrs.

1 2 3 20 21 22 23 24 Avg. flow(MLD)

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

Page 134: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 114 -23

24

25

26

27

28

29

30

31

Executive Engineer

9.3.3 Daily Sampling Record

The daily sampling record sheet contains the information on the sewage sample collected at inlet and outletof reactor, sludge samples from sludge withdrawal pit for sludge profile and from sludge sump. This record iskept by the junior Engineer and contains basic data on plant functioning.

Table No. 9.3 Daily Sampling Record.

Date Sample Collection of Influent & Effluent Sludge Sample collection from Sludgewithdrawal pit

Sludge Samplecollection from SludgeSump

Inf. R 1 R 2 R 3 R 4 R 1 R 2 R 3 R4

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

Page 135: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 115 -29

30

31

Executive Engineer9.3.4 Record of Screen Chamber

The record sheet of screen chamber contains the information about the duration of operation of manual andmechanical screen and quantity of screenings discharged from the plant. This record is kept by the JuniorEngineer and contains basic data on plant functioning.

Table No.9.4 Record of Screen ChamberMonth:Year:

Date MechanicalScreen

Manual Screen Quantities of Screening Based No. ofWheel Borrows

Officer on dutyPHED

Operations

No. ofOperations per

day

Hours ofOperationalper day

Hours ofOperationalper day

No. of WheelBarrows filled

Quantity ofScreening (M3/d)

9.3.5 Record of Grit Chamber

The record sheet chamber of grit chamber contains the information about the duration of operation ofindividual grit channel, volume of grit collected and removed. This record is kept by the Junior Engineer andcontains basic on plant functioning..

Table No. 9.5 Record of Grit Chamber

Month:

Year:

Date Grit channels in operation Stand – by Channels No. of wheel

barrows filled

Grit

Collection

in M3 d

Officers on

Duty PHED

Operator

Ch-1 Ch-2 Ch-3 Ch-4 Ch-1 Ch-2 Ch-3 Ch-4

Executive Engineer

9.3.6 Performance data of UASB reactor.

Page 136: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 116 -

The performance data sheet of UASB reactor contains the records of the analyticalresults at the inlet and outlet of each reactor for all the parameters. These parameters arePH Alkalinity, Total and Filtered BOD & COD, TSS, VSS, VFA, Sulphates andTemperature. This record is kept by the Junior Engineer and contains basic data onplant functioning.

Table No. 9.6 (a) Performance data of UASB Reactor

Date PH Alkalinity COD Total COD FLL BOD TotalReactor Reactor Reactor Reactor Reactor

Inf

R1 R2 R3 R4 Inf

R1 R2 R3 R4 Inf

R1 R2 R3 R4 Inf

R1 R2 R3 R4 Inf

R1 R2 R3 R4

123456789

10111213141516171819202122232425262728293031

Legend:Inf. = InfluentR1 = Effluent from Reactor 1R2 = Effluent from Reactor 2R3 = Effluent from Reactor 3R4 = Effluent from Reactor 4* All values in mg/I except pH. VFA & Temperature VFA in meq/I & Temp in “C.

Executive Engineer

Table No. 9.6 (b) Performance data of UASB Reactor

Date BOD Fil TSS VSS VFA Sluphates Temperature

Page 137: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 117 -Reactor Reactor Reactor Reactor Reactor Reactor

Inf

R1 R2 R3 R4 Inf

R1 R2 R3 R4 Inf

R1 R2 R3 R4 Inf

R1 R2 R3 R4

R1 R2 R3 R4 Inf

R1 R2 R3 R4

123456789

10111213141516171819202122232425262728293031

Legend:Inf. = InfluentR1 = Effluent from Reactor 1R2 = Effluent from Reactor 2R3 = Effluent from Reactor 3R4 = Effluent from Reactor 4* All values in mg/I except pH. VFA & Temperature VFA in meq/I & Temp in “C.

Executive Engineer

Page 138: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 118 -9.3.7 Performance evaluation sheet of UASB STP

The performance evaluation sheet of UASB reactor contains the records of the data like BOD total, TSS & VSS at intet,outlet of the reactors and pond outlets. This record is kept by the Junior Engineer and contains basic data on plant functioningand performance evaluation of reactor, pond and overall plant.

Table No. 97 (a) Performance Evaluation Sheet of UASB STPMonth:Year:

Date FlowinMLD

COD Tot. BOD Tot. TSS VSS.Location / Efficiency Location / Efficiency Location / Efficiency Location / EfficiencyIn

fRO PO R P Inf RO PO R P Inf RO PO R P Inf RO PO R P

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31Legend:Inf. = Influent to the STPRO = Combined Effluent from Reactors OutletPO = Effluent from Pond OutletR = Efficiency of ReactorP = Overall Efficiency of STP Executive Engineer

9.3.8 Sludge Profile data of UASB reactors.

The Sludge profile data of UASB reactors contains the analytical result for TS,VS and Ash content of the sludgesamples collected at various heights of the reactor. This records is kept by the Junior Engineer and contains basison plant functioning.

Table No. 9.8 (a) Sludge Profile Data of UASB Reactor-1

Page 139: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 119 -

Port A Sampling Portht. From

Bottom (m)

AssumedLayer (m)

TS (g/I) VS (g/I) Ashcontent

(%)

TS –amount

(Kg)

VS-amount

(Kg)0.4 0.60.8 0.41.2 0.4

Date 1.6 0.62.4 0.83.2 0.8

Total

Table No. 9.8 (b) Sludge Profile Data of UASB Reactor-1

Port B Sampling Portht. From

Bottom (m)

AssumedLayer (m)

TS (g/I) VS (g/I) Ashcontent

(%)

TS –amount

(Kg)

VS-amount

(Kg)0.4 0.60.8 0.41.2 0.4

Date 1.6 0.62.4 0.83.2 0.8

Total

Table No. 9.8 (c) Sludge Profile Data of UASB Reactor-2

Port A Sampling Portht. From

Bottom (m)

AssumedLayer (m)

TS (g/I) VS (g/I) Ashcontent

(%)

TS –amount

(Kg)

VS-amount

(Kg)0.4 0.60.8 0.41.2 0.4

Date 1.6 0.62.4 0.83.2 0.8

Total

Executive Engineer

Table No. 9.8 (d) Sludge Profile Data of UASB Reactor-2

Port B Sampling Portht. From

Bottom (m)

AssumedLayer (m)

TS (g/I) VS (g/I) Ashcontent

(%)

TS –amount

(Kg)

VS-amount

(Kg)0.4 0.60.8 0.41.2 0.4

Date 1.6 0.62.4 0.83.2 0.8

Total

Page 140: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 120 -Table No. 9.8 (e) Sludge Profile Data of UASB Reactor-3

Port B Sampling Portht. From

Bottom (m)

AssumedLayer (m)

TS (g/I) VS (g/I) Ashcontent

(%)

TS –amount

(Kg)

VS-amount

(Kg)0.4 0.60.8 0.41.2 0.4

Date 1.6 0.62.4 0.83.2 0.8

Total

Table No. 9.8 (f) Sludge Profile Data of UASB Reactor-3

Port B Sampling Portht. From

Bottom (m)

AssumedLayer (m)

TS (g/I) VS (g/I) Ashcontent

(%)

TS –amount

(Kg)

VS-amount

(Kg)0.4 0.60.8 0.41.2 0.4

Date 1.6 0.62.4 0.83.2 0.8

Total

Executive Engineer

Table No. 9.8 (g) Sludge Profile Data of UASB Reactor-4

Port B Sampling Portht. From

Bottom (m)

AssumedLayer (m)

TS (g/I) VS (g/I) Ashcontent

(%)

TS –amount

(Kg)

VS-amount

(Kg)0.4 0.60.8 0.41.2 0.4

Date 1.6 0.62.4 0.83.2 0.8

Total

Table No. 9.8 (h) Sludge Profile Data of UASB Reactor-4

Port B Sampling Portht. From

Bottom (m)

AssumedLayer (m)

TS (g/I) VS (g/I) Ashcontent

(%)

TS –amount

(Kg)

VS-amount

(Kg)0.4 0.60.8 0.41.2 0.4

Date 1.6 0.62.4 0.8

Page 141: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 121 -3.2 0.8

Total

9.3.9 Records of Sludge Discharge from Sludge Sump

The record of sludge sump and pump contains the duration of pump operation and quantity of sludgedischarged to the sludge drying beds. With this record the sludge drying cycle could be established duringweather conditions. This record is kept by the Junior Engineers and contains basic data on plantfunctioning.

Table No. 9.9 Record of Sludge Discharge from Sludge Sump

Month:

Year :

Date PumpingDurationper day

SludgeDischarge Rate

(cum/hr)

Total Sludgedischarge inM3 per day

TotalSolids(g/1)

SDBNo.used

PHEDofficer on

duty

Operator

9.3.10 Record of Bio-gas productionThe Record of bio-gas production contains the information on total bio-gas produced in the plant daily. Thisrecord is kept by the Junior Engineer and contains basis data on plant functioning.

Table No. 9.10 Record of Bio-gas productionMonth :Year :

Date Bio- Gas Production in M3 / day PHED officeron Duty

Operator.

Initial Reading Final Reading Net Bio-Gas Produced

9.3.11.1 Record of Bio – Gas composition

The Record of Bio-gas composition contains the information on the parameters like methane Carbon –di-oxide, Hydrogen sulphide, Nitrogen present in the bio – gas. This record is kept by the JuniorEngineer and contains basic data on plant functioning.

Table No. 9.11 Record of Bio-Gas composition

Month

Page 142: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 122 -Year:

Parameter % Composition

Methane

Carbon-di-oxide

Hydrogen Sulphide

Nitrogen

9.3.11.2 Operational Record of Duel Fuel Engine

The operational record of duel fuel engine contains the information about the running hours of the DuelFuel Engine, amount of diesel consumed and electricity generated in Kilowatt (KW). This record iskept by the Junior Engineers and contains basic data on plant functioning.

Table No. 9.12 Operational Record of Duel Fuel Engine.

Month: Year:

Date Running

Hours per

day

Diesel

Consume

(Litres/day)

Total Units

generated in

KWH per day

HSEB

Supply in

Hours

PHED

officer on

duty

Operatior

1.1 DAILY MAINTENANCE

Daily maintenance of the biological, processes in the UASB reactor follows logically from the precedingparagraphs. Data should be obtained on the functioning of the plant, and checked. If the waste water flowthe biogas production, and the effluent concentrations are normal no actions should be taken.

Regular maintenance of the UASB reactor hardware should consists of checking of the screening system,the effluent gutter and the gas collectors.

The feeder system of the UASB reactors can become choked over time. Therefore, it is important to keepdata on pimp pressure, for it can Indicative for the amount of food inlet points choked. To maximize theperiods between two sequential required cleaning operations, vigorous screening In four stages must becarried out, continuously requiring day and night operations by sweepers of the screens.

It is required to empty reactor once after the first one year of full operation to check the complete feederand sludge withdrawal systems, especially the valves and the internal pipes for any accumulation of debris,sludge, etc. The routine maintenance requirement of feeder and sludge withdrawal, systems must beestablished on the basis of such as inspection.

The effluent gutters are essential for the removal of the effluent of the reactors. If the gutters are not leveledand the water in the V-notches is not at the same level in all of the notches in one gutter, or in differentgutters, then the flow will not be even. This will lead to more solids washout than necessary. Similarly,blocking of the V-notches of the effluent gutters will lead to an uneven flow over the effluent gutters willlead to an uneven Flow over the effluent gutters. Therefore the effluent gutters has be inspected on aregular basis to remove any material blocking an even out flow over the v-notches in the glitters. The level

Page 143: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 123 -of gutter's has to be inspected on a regular basis and if uneven flow is seen. adjustment of the level of thegutters should be made.

Regular maintenance of the effluent gutter consists of the following activities. Cleaning if done from thetop of the reactor.

1. The sleeper cleans the v-notches of the gutter with broom, once in every shift (3 times/day)2. The sweeper removes sludge from the effluent gutter with a brush or with jet once a day.

A floating layer on top of the surface of the reactors should be removed when required.

1. The sweeper breaks the floating layer with a rake.2. The sweeper removes the material at one- side of the reactor with a rake.3. The material is put in a wheelbarrow and disposed at the dumping site.

The gas collectors should be checked for leakage. Leakage is easily seen, by bubbles in the water and byapplying a soap solution showing bubbles at leaks in piping. This can be done a regular basis. If the gascollectors are leaking, the valve at the end of one bay in the gas link should be first closed and then theyshould be repaired as soon as possible. Regular maintenance includes: -

1. Open watch boxes and remove floating layer inside the gas collections.3. Check gas collectors and pipes for gas leaking and repair when necessary.

Figure 1.1 Scheme for the decision on where to release the sludge.

Start

Sludge Levelbelow 2.5m

No Yes

Bottom sludge bottom sludgeash 70% ash 70%bottom TSS > 12%

Yes No No Yes

bottom valve bottom TSS bottom 50 % Bottom Valveonly conc. > 8% middle 50% only

Yes No

bottom 50% middle valvemiddle 50% only

Initial Setting= 50 mm Volume per day

Set New withdrawal VolumeContinue for 3 days

Page 144: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 124 -

Figure 1.2 scheme for the decision on how much sludge to release

1.1.2 PREVENTIVE MAINTENANCE

Preventive maintenance should be carried out, on a regular basis. It was prevent the reactor formhaving to put them out of operation unnecessarily. Preventive maintenance aims at minimizingrepairs and maximizing lifetime of the components of the Plant. For this reason, maintenanceactivities are carried out according to a fixed schedule.

1.2.1 Distribution system

1. Check screening stages.

2. A first check of the complete system including valves and holes should be made afterone year, or earlier when required. Routine check can be established on the basis of the firstinspection observation.

1.2.2 UASB Reactor

Page 145: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 125 -The UASB reactors themselves require little attention. Every five year the followingmaintenance should be carried out.

1. Alternately each reactor should be put out of operation.

2. Discharge sludge-to-sludge drying beds.

3. Provide ventilation by removing part of the hatch boxes.

4. Remove all grit form the bottom of the reactor through the drainage pit provided.

5. Clean the inside concrete surface.

6. Apply new coating on the concrete surface.

7. Check quality of feed inlet pipes and replace when necessary.

8. Check fixing of the feed inlet pipes, both at the distribution boxes and at the bottom.Change corroded fixing material when necessary.

9. Check position of PVC sheets.

10. Check the fixing material of the PVC sheets and replace when necessary.

11. Check the quality of gas collectors and carry out repair whenever necessary.

Executive Engineer

Page 146: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 126 -1.2.3 Effluent gutters

1. The effluent gutters have to be checked for leveling and alignment once a year. Eachgutter should be horizontally leveled and all gutters in one reactor should be at the same level.

2. Possible settlements should be removed.

1.2.4 Sludge withdrawal system

1. The spindles of the valves have to be greased every three months.

2. The glands and packing of the valves have to be checked every three months, andreplaced if necessary.

3. The cement works have to be checked yearly and repaired when necessary.

4. The sludge filtrate water pumps should be maintained.

5. Electrical wiring has to be checked every year.

6. Corrosion on electrical connections has to be removed every year.

A summary of the maintenance activities is presented in the following pages. Most activities areeither three-monthly or yearly; the three-monthly activities are to be carried out in the months ofJanuary, April, July and October.

The yearly activities are to be carried out in the month of October after the monsoon.

1.5 SHUT-DOWN AND STANDSTILL

At shut down of the plant, the sludge will settle to the bottom of the reactor. The biologicalactivity of the sludge decrease only slowly during stand care should be taken that the sludge isnot exposed to aerobic conditions. This might occur for instance, when the reactor if flushedwith clean water for prolonged period of time.

At shut down of the plant the gas production wil1 decrease. At a prolonged period of plantstandstill, the pressure in the gas collections system can drop and air may enter into system. Inthis situation internal parts of the gas flare, the gas meter and the pressure/vacuum releasevalves that normally are not in contact with the atmospheric air start to corrode. These partshave to be protected, for instance by greasing.

Executive Engineer

Page 147: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 127 -

If the water level in the tank is lowered during shut-down It should be taken into account thecapacity of the vacuum release valves is limited and that imploding of the gas collectors mayoccur at fast withdrawal of the reactor contents. At lowering of the water level in the reactor it isadvised to open the manholes on the top of the gas collectors. Only after re-establishing themaximum water level the manholes can be closed and sealed.

When manholes are opened and in general with every type of work on the gas collectors itshould be taken into account that an explosive mixture of air and methane can develop in oraround the gas collectors. When it is necessary to enter the reactor, while sludge is present, ithas to be realized the methane is being formed continuously. A proper ventilation of the reactoris absolutely necessary. Very Strict rules concerning upon fire, spark emission etc. Should beused when entering the reactor plant person should wear respiration equipment. Measurement ofexplosion risk and hydrogen sulfide con cent ration have to taken frequently when repair worksare carried out.

Executive Engineer

MAINTENANCE

Sr.No.

MaintenanceActivities

Jan Feb Mar Apr May

Jun Jul Aug Sep Oct Nov Dec

Main ValveChamber

Page 148: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 128 -1. Greasing spindle of

the valveX X X X

2. Check the glandsand packing of thevalve replace ifnecessary

X X X X

3. Clean valvechambers

X X X X

4. Paint valve andchecker plants

5. Check cement worksrepair whennecessary

6. Check cement worksrepair whennecessaryFlow Control Box

1. Check weir positioncorrect whennecessary

X X X X

2. Check cement worksrepair whennecessary

X

3. Paint railing & stairs X4. Flow Division Box1. Check weir position

correct whennecessary

X

2. Check cement worksrepair whennecessary

X

3. Paint railing & repairSW

X

Executive Engineer

Page 149: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 129 -1 Check & correct the

leveling of guttersindividually and incombination

2. Check the sidevaffles of thecompartment 2 &repair if necessarySludge DischargeSystem SludgeSampling Pumps

1. Grease moving parts X X X X X X X X X X X X2. Lubricate the

plunger checkpacking, replace ifrequired.

X X X X X X X X X X X X

3. Check washer andback flush leatherreplace if required

X X X X X X X X X X X X

Sludge Pit1. Grease the spindles

of the values.X X

2. Check glands &packing of thevalves, replace ifnecessary.

X X

3. Clean sludge pits X X4. Paints valves and

checker plates5. Check the cement

works repair ifnecessary

6. Check electricalconnections &wiring removecorrosionGas Collection

1. Drain and replacedistilled water in gasmeters.

X X

2. Check system forleakage

X X

Sludge Drying Beds1. Check the thickness

of top sand layer, if10 cm is lost,replenish it.

X X X X X X X X X X X X

2. Check drain pipesfor clogging clean ifnecessary.

X X

3. Check the cementworks & repair ifnecessary

X

Executive Engineer

Sr. Maintenance Jan Feb Mar Apr May

Jun Jul Aug Sep Oct Nov Dec

Page 150: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 130 -No. Activities

Main ValveChamber FlowAdjusting Boxes

1. Greasing spindles ofthe valve

X X X X

2. Check the glandsand packing of thevalve replace ifnecessary

X X X X

3. Clean valve flowadjusting boxes

X X X X

4. Paint valve andchecker plates

X

5. Check cement worksrepair whennecessary

X

Flow MeasuringChamber

1. Check the leveling ofthe V-notches,correct whennecessary

X X X

2. Check the shape andsharp edging of theV-notch

X X X X

3. Zero setting of thefloat and fixing theguide pipe check froleakages in float.

X X X X

4. Check the cementworks and repairs ifnecessary

X X

5. Paint the railingsand other metalpartsSCREENS

1. Check the screen andreplace the bars, ifnecessary.

X X X X

2. Painting of thescreen

X X X X

SIEVES1. Check the sieve and

replace it, ifnecessary

2. Painting of the sieve

Executive Engineer

GRIT Chambers1. Clean the rubber

packing ofaluminum gates

X X X X X X X X X X X X

2. Grease valves X X X X3. Pain valves4. Check the

positioning if theeffluent weir

5. Check the concretework for erosion and

Page 151: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 131 -leakage repair ifnecessary.UASB ReactorReactorCompartments

1. Open hatch boxes,clean removefloating layer insidethe gas collectors

2. Check gas collectorsfor gas leakage,repair if necessary.

3. Check the cementworks and repair ifnecessary

4. Paint all the metalworks like railingstairs, checkerplasters hatch boxes

5. Check the thicknessof floating materialin middlecompartmentremove the floatingmaterial is thicknessexceeds 5 cm.Distribution Boxes

1. Check leveling of thenotches

2. Check the metalparts of boxes forcorrosion replace ifnecessary

3. Check the cementworks repair ifrequired.EFFLUENTGUTTERS

1. Paint effluent gutters X X X X

Executive Engineer

SECTION 7PRICE SCHEDULE

Letter of Financial Bid

Invitation for Bid No.: ……………………. Date:

To:The Commissioner,MUNICIPAL CORPORATION GURGAONCivil Line RoadTelephone ;

Page 152: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 132 -Facsimile number;Electronic Mail Address;

We, the undersigned , declare that :(c) We have examined and have no reservations to the BiddingDocuments, including Addenda issued in accordance with instructions toBidders, Specification, Scope of work , Special and General Conditions of Contract(d) We offer to execute in conformaity with the Bidding Document s thefollowing Works:

( Name of Work……………………………………………………………………………………. )

(e) Our Price is valid for a period of 180 days from the date openingof financial bid as indiaccated in the following schedules:

For Sewerage & Storm Water System:

Sr.No.

DESCRIPTION Amount to be quoted by the Agency(Rs. In Crores per month per year)Unit for

Year1

forYear2

forYear3

forYear4

forYear5

1. Operation and maintenance ofsewerage system of Old GurgaonTown. Including various disposalworks MPS/IPS’s S.W. pipe /R.C.C. pipe sewer, brick circularsewer etc., Storm Water Drainsand all other works contingentthere to as scope of DNIT.”including provision of man,machinery etc.

L.S.

2. Maintenance & operation ofadditional work executed by theCORPORATION to be handedover to the agency during thecontract period.(a) Additional pumping station

(Rate per MLD per pumpingstation per year

(b) Additional sewer line/ stormwater up to 16” pipesewer/storm water ( Rate perKM length or part thereto )

(c) Additional main sewer/stormwater beyond 16” ( Rate perKM length or part there to )

Each

PerKm

PerKm

Page 153: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 133 -per year

3. Raising of manhole cover andframe complete up to road levelup to 2 feet height. (per unit)

Each

4. Lifting/ casting of manhole slab ofany size including manhole cover& frame up to road level includingbrick work, plaster etc complete inall respect. (per unit)

Each

5. Construction of additional newmanhole of size 5’x3’ with averagedepth (per unit)

A) Up to 2 mtr. DepthB) 2 to 3 mtr. Depth

Each

6. Laying of SW Sewer line includingexcavation, lean concrete 1:4:8,laying & jointing of SW pipe,refilling of earth etc up to 3 mtr.Depth complete in all respect asper PWD Specifications (permeter)

a) 200 mm PerKm

b) 250 mm PerKm

c) 300 mm PerKm

Page 154: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 134 -For STP:

Sr.No. Descriptions Qty. Unit Rate

1. Establishment as per DNIT. 36 Months

2. Replacement of filter media as perNIT.

1 Job

3. Cleaning/desilting of final polishingunit as per App. Item

1 Job

4. Cleaning of reactors as per App.DNIT

3 Job

5. Epoxy painting on the componentsstructure as per detail in DNIT

3 Job

6. Premix carpeting of roads in STPpremises as details in DNIT

1 Job

7. Insurance charge for electrical, mech,equipment against theft and fireincluding insurance the workersemployed at site for 03 years.

3 Job

8. Maintenance of laboratory andconduction of tests as per App.DNIT.

36 Months

9. White washing painting on thecomponents / structures as per App.DNIT

3 Job

10. All other works/ Items as per App.DNIT

3 Job

Name ………………………………………………………….In the capacity of ……………………………………………..Signed…………………………………………………………Duly authorized to sign the Bid for and on behalf of ………………………………Date……………………………………………………………

Page 155: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 135 -Special Terms and Conitions

1. The Unit Rates and the Prices shall be quoted by the Contractor in Indian Rupees, asper the price bid format provided in the tender document.

2. Contractor will receive, scrutinize DHBVN energy bill and submit the same toEngineer-in- Charge well in advance i.e. at least 7 days in advance from last date ofpayment.

3. The actual bills of petrol pumps dealer (petrol, diesel) shall be submitted along withthe reimbursement bill raised by the agency.

4. Water if required for operation of hydraulically operated sewer cleaning machine, willbe supplied free of cost at the water works to the contractor by the Deptt. Howevercontractor will make his own arrangement for its transportation from water works tothe site of work where it is required.

5. Ignorance of actual site conditions, lack of understanding of scope of work on anyother reason whatsoever, beyond the conditions mentioned, shall not entailCORPORATION to make any additional payment to the contractor.

6. The contractor will be paid bimonthly as per conditions of award of work a. Thecontractor whose tender has been accepted will submit the bimonthly bill showing theamount payable to him in duplicate to Engineer-in-Charge. b. Contractor will have noany claim for delay in payments.

7. Mandatory duties of the contractor specified in the schedule have to be carried out infull.

8. The tenderer should quote the rates both in words and figures. In cases of discrepancybetween the rates quoted in words and in figures, lower of the two shall be consideredfor evaluation. If there is a discrepancy between the amount quoted for an item andthe line item total resulting from multiplying the unit rate by the quantity, the unit rateas quoted will govern.

9. Payment to the contractor will not be made till he full fill following conditions: -i. Submission of insurance policy to the CORPORATION.

ii. Provide safety measures for the workers engaged as per instruction issued byEngineer-in- Chief, Public Health Engineering Department, Panchkula.

10. The contractors are required to operate and maintain the sewage pumping stationscontinuously during the rainy seasons by providing additional shifts at no extra cost

11. The rate quoted by the bidder is inclusive of provision towards Uniform and Stitchingcharges for two sets of shirt and pants for each employee (full pant for MaintenanceEngineers, operators, sewer superintendents and half pants for field workers), andgingili oil for Sewer workers at one liter per month, soap for all staff at two soaps per

Page 156: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 136 -person per month and Consumables like cotton waste, oil, grease, packing rope, etc.

12. It is the responsibility of the Contractor to make necessary provision towards thewelfare measures as directed by statutory authorities and as prescribed by theapplicable acts and rules for Contract Labourers.

13. The Contractor having ESI, EPF Code Nos. should remit the contributions bythemselves, the payment towards ESI & EPF for the employees, employers’contributions in his/their code numbers and copy of the remittance challans should beproduced. If the contractor fails to remit, he/they should inform wage rates ofemployees to the principal employer and authorize the Municipality to makedeductions from the payment of bills. The contribution / premium / tax etc. to anyother statutory authorities, the contractor has to remit them directly after registeringwith the respective department.

14. Recoveries will be made from the bimonthly/final bills as under: -a. Penalty in full, if levied.b. Income Tax, as applicable.c. Expenditure in full, if any, incurred by the MUNICIPAL CORPORATION

GURGAON contractor’s behalf, in labor and material or any other type.d. Charges in full for the service extended by MUNICIPAL CORPORATION

GURGAON to the contractor, such as residence with water sanitation andpower supply arrangement, if provided.

e. Hire charges in full for any land or building or machinery of MUNICIPALCORPORATION GURGAON given to the contractor for use during theexecution of the work.

f. Any other charges, if levied by CORPORATION.

15. CORPORATION, also reserves the right to extend or reduce the contract period withinaccepted from the date of commencement of the date of written order/ If required‘MUNICIP!L CORPOR!TION GURG!ON’ may extend the contract period up to sixmonths and proportionately additional payment shall be made on the basis of ratesfor last financial year.

16. . If there are any changes in the prevailing tax component, increase in taxes will beborne by the Municipality and any decrease will be deducted from the contractors’payment.

17. White washing/ distempering/ snowcem/ painting shall be done in every firstquarter of every year if agency fail to do so, the work shall be executed at risk andcost of the agency.

18. The transformer oils shall be dehydrated one in a year or earlier as required.

19. ACB shall be serviced twice in a year, panels shall be serviced quarterly.

Page 157: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 137 -20. In case of motor/ transformers or any component is burst or damaged, it shall be sole

responsibility of the contractor to replace/ repair the same as per standard of theequipment/ components free of cost.

21. At least 5 nos. pumping machinery should be in running condition at every time atMPS/IPS as the case may be.

22. The rate quoted by the bidder should be inclusive of ESI as per labour Act 1948,Employee contribution of the wages to be recovered from the staff salary, EPF atmatching contribution of the employee’s wages be payable towards EPF a/c both bythe Employer/Contractor and Employee and Service Tax and all other applicable taxesetc. all at applicable rates as per statutory provisions.

23. No payment shall be made for replacement of broken/damaged manhole cover andframe.

Page 158: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 138 -Penalties & other Receivables

1. Contractor will be liable to work in accordance with the Scope detailed in the biddocument failing which levy of penalty/liquidated damages as envisaged below arelikely to be imposed.

2. Failure to operate the generating set / diesel engine immediately after the disruptionof electricity / power supply, then the recovery @ Rs.1000/- per hour for this durationof failure of electricity will be recovered from the agency.

3. If any sewage pump, panel board goes out of order than the agency will be bound toget the same repaired within 15 days from the date of burning otherwise recovery ofRs. 1000.00 per day per pump set for the delayed period will be made from theagency and after 30 days from the date of burning, the same will be got repaired atthe risk and cost of the agency in addition to above penalty.

4. If it is observed that the contractor has not complied with any act or rules applicable,a penalty of Rs. 5000.00 or as decided by the concerned Executed Engineer may beimposed. In additional to above penalty / liability applicable as per the relevant act /rules for which contractor shall exclusively responsible.

5. Epoxy coating shall be done quarterly on manual and mechanical screen andventilators of MPS/IPS, in case of default a penalty of Rs. 5000.00 per quarter shall beimposed and work shall be executed on the risk and cost of the agency.

6. In case contractor fails to attend machine, instruments, equipment’s in time and failsto put the same in working order within stipulated time, as indicated in the complaintresponse ticket and directed by the Executive Engineer-in-Charge, then Engineer-in-Charge reserve the right to bring the same in working order by deputing anotheragency at the risk and cost of the contractor and same will be recovered from bill ofthe contractor. The amount calculated by Engineer- In – Charge as recoverable fromthe contractor shall be final and binding on the contractor.

7. If contractor dosen’t performs his duty as per instruction and direction give byEngineer-in- Charge then Executive Engineer- in- charge reserves the right to imposepenalty or engage some other agency and losses occurred thereon will be recoveredfrom contractor’s bill.

8. If Engineer-in-Charge observes that the instruments are not maintained properly ornot showing reading properly suitable penalty of Rs. 500.00 per instrument will beimposed on contractor and decision of Engineer-in-Charge will be final and bindingon contractor.

9. If during inspection it is observed that proper upkeep of pumping station premises isnot maintained by the Contractor at the work site a penalty upto @ Rs. 1000.00 pervisit will be imposed and deduction will be made accordingly from contractor’s bill.

Page 159: Municipal Corporation Gurgaon - e Tendersmcg.etenders.in/tpoimages/mcg/tender/Tender1213.pdf · of 30 MLD STP E&M installation , Switch Yard , ... Near Neelam Bata Chowk, ... The

-Sd-Contractor Witness Executive Engineer

- 139 -

10. If contractor fails to redress a complaint, as per the timelines indicated in thecomplaint response ticket, a penalty @ Rs. 500.00 per day for delay in time will beimposed.

11. Contractor will arrange sufficient no. of sewer jetting machines for proper operationof this maintenance contract. The expenditure on all consumables including repairs,lubricants, manpower, transportation, diesel etc for sewerage cleaning machines willbe borne by contractor. In case sewer jetting machines of CORPORATION isdeployed in emergency, recovery shall be made @ Rs. 5000/- per day.

12. Contractor will arrange sufficient no. of super sucker machines for proper operationof this maintenance contract. The expenditure on all consumables including repairs,lubricants, manpower, transportation, diesel etc for sewerage cleaning machines willbe borne by contractor. In case super sucker machines of CORPORATION isdeployed in emergency, recovery shall be made @ Rs. 25000/- per day.

13. In no case the any workers, official of the contractor should be found in intoxicatedcondition, during the official working hours penalty of Rs. 1000.00 shall be imposed.

14. No representation of reduction/ waving off of penalty imposed shall be entertained.