Upload
anonymous-he37so
View
213
Download
0
Embed Size (px)
Citation preview
7/25/2019 MS- Water proofing.doc
http://slidepdf.com/reader/full/ms-water-proofingdoc 1/6
PROJECT
MEYDAN VILLA HEIGHTS
METHOD STATEMENT FOR RECTIFICATION
OF DAMAGED WATER PROOFING MEMBRANE
IN MANHOLE ON STABLE ROAD
0 22.06.2016 AFCONS AFCONS ACE
Rev Date Prepared by Reviewed by Approved by
Page 1 of 6
7/25/2019 MS- Water proofing.doc
http://slidepdf.com/reader/full/ms-water-proofingdoc 2/6
INDEX
1.0 PURPOSE
2.0 SCOPE
3.0 DEFINITION
4.0 REFERENCES
5.0 RESOURCES
6.0 RESPONSIBILITIES
7.0 METHOD OF EXECUTION
8.0 MISCELLANEOUS
9.0 HEALTH AND SAFETY PROVISION
10.0 ATTACHMENT
Page 2 of 6
7/25/2019 MS- Water proofing.doc
http://slidepdf.com/reader/full/ms-water-proofingdoc 3/6
1.0 Purpose:This Method Statement is being generated to provide a documented reference for the execution of
the work and its sequence. Thus providing Technica! "nformation and #nderstanding as per the
work requirements.
$!! information mentioned hereunder are based on Pro%ect Specification $pproved Shop &rawing
$pp!icab!e Standards and 'oca! $uthorities (equirements un!ess otherwise required under the
instruction of the )ngineer but not !imited to whatever purpose it requires.
2.0 Scope of Work:
• $ssessment of &amage of *ater Proofing Membrane.
• (emova! of &amaged *ater Proofing Membrane.
• Surface Preparation for app!+ing new membrane.• $pp!ication of ,ew Membrane.
• Testing and "nspection b+ -onsu!tant.
3.0 Definition:
EMPLOYER : Meydan LLC.
ENGINEER : Aqleh consulting Engineers.
CONTRACTOR : Afcons Construction Mideast LLC.
PQP : Project Quality Plan
MS : Method Statement
ITP : Inspection & Test PlanITL : Independent Testing Laboratory
IR : Inspection Request
MAR : Material Approval Request
MIR : Material Inspection Request
HSE : Health, Safety & Environment
PM : Project Manager
CM : Construction Manager
QAQC : Quality Assurance/Quality Control
IFC : Issued For Construction
4.0 Reference Documents:
1.General Specifications:
2.Approved Shop Drawing, Supplier’s and Material Approval
5.0 RESOURCES:
A.Manpower
1.Project Manager/Construction Manager
2.Safety Engineer / Officer
3.Project / Site Engineer
4.QA/QC Engineer
5.Technical Team
6.Foreman / Site Supervisor
Page of 6
7/25/2019 MS- Water proofing.doc
http://slidepdf.com/reader/full/ms-water-proofingdoc 4/6
7. Applicators, Labors / Helpers
B.Tools, Equipment & Materials1. *ater Proofing Membrane
2. /!ame Torch
. 0as -+!inder
. -utter.
6. ammer
6.0 Responsibilities:
6.1 Project Manager is responsible of planning and programming the project
tasks and objectives; determining the organizational structures of the project
team, its roles and positions; setting team directions, coordinating activities
across different organizational functions, assigning works; defining project
baseline, tracking progress and reporting; implementing quality and safety as
per project requirements.
6.2 Construction Manageris responsible for overall execution of this work;
CM shall coordinate with surveyor, Project Engineer and Site Engineer to
ensure that the necessary resources and equipments are provided to
implement the works in an acceptable manner as per the approved
documents, MS and ITPs and also to ensure all construction staffs comply
with Company’s Quality, Health, Safety and Environmental Management
System requirements. He shall ensure that all works are executed as per
approved IFC drawings. He shall involve in tool box talks given by the QC
Engineer for the site staff prior to start works at site. He is also responsible
for indenting and using only the approved materials for construction purpose
and shall also inform the QC engineer at site prior to commencement of any
new activities at site.
6.3 Project Engineeris responsible for the execution of the activity in
accordance with the Project Specifications, approved quality control
procedures, MS and HSE plan. He is also responsible for raising internal IR to
QC engineer at site for day to day activities. He is also responsible for
attending all the required inspections along with the Engineer’s representative
for approvals. He is also responsible for ensuring that works are not rejected
at site.
6.4 QA/QC Engineerat site is responsible for ensuring all the activities are
carried out as per project specification and approved quality control
procedures, and is also responsible for providing toolbox talks to the
execution team. He is also responsible for raising IR for all the related day to
day activities at site as per the approved ITP. He is also responsible for
attending all the required day to day inspection along with the Engineer’s
representative and project engineers for approvals.
6.5 Site Engineer, Supervisors & Foreman is responsible for ensuring that
the workforce is well aware of the quality control procedures and safety rules
and also responsible for executing the works as per approved IFC drawings.
Page 3 of 6
7/25/2019 MS- Water proofing.doc
http://slidepdf.com/reader/full/ms-water-proofingdoc 5/6
6.6 HSEEngineer is responsible for ensuring the activities are carried out as
per Project Specific Safety Rules and Regulations and all the works shall beexecuted as per approved HSE plan.
6.7 Surveyor is responsible for checking the levels of each and every
structure and shall comply with approved IFC drawings and also responsible
for internal coordination and to Site execution team about day to day survey
activities.
7.0 Method of Execution:
7.1 Surface Preparation:
•
Remove damaged water proofing membrane.• Remove dust, dirt and other contaminants. Surface be rough for better
adhesion.
• Make the Surface Hot with Gas Torch so that Bituminous Membrane sticks
on parent surface. Apply uniform pressure to make sure adhesion is
perfect. .
• IR has to be raised and approved by the Engineer prior to proceed with
the application.
• Refer to Inspection and Test Plan for Hold Points
7.2 Protection:
Application protection layer as per specification for better durability
8.0 Miscellaneous:
8.1 Cleaning:
• Area will be made clean and all the waste material will be removed with the
help of brush or scrapper. Empty bags will be disposed properly to the
designed areas
9.0 Health & Safety Provision:
• The prescribe PPE should be provide to all workers and Site staff.
• Proper housekeeping should be done.
• Work area shall be cleared from all the debris, and excess materials.
During night time sufficient lighting arrangement should be done on site.
• Gloves, masks and safety glasses will be provided only for the spray
team.
• Safety shoes, helmets, coverall and safety jackets will be provided to
all laborers and staff.
10.0 Attachment:
• Risk Analysis Statement.
Page of 6
7/25/2019 MS- Water proofing.doc
http://slidepdf.com/reader/full/ms-water-proofingdoc 6/6
=END=
Page 6 of 6