Upload
yoppy-soleman
View
225
Download
0
Embed Size (px)
Citation preview
8/10/2019 Monthly Project Progress Report - Augustus - September - October 2014 (Section 1)
1/9
10
Gambar 10.a-d. Pekerjaan Beton Bertulang: Segmen atas Kolom Teras, dimensi 50x50 cm,
Pekerjaan Beton Bertulang Pelat Atap (Dak), t = 10 cm.
8/10/2019 Monthly Project Progress Report - Augustus - September - October 2014 (Section 1)
2/9
11
Gambar 11.a-e. Pekerjaan Beton Bertulang Kolom Struktural Lantai II, dimensi 40x40 cm,
Mutu beton K250 (kg/cm2)
8/10/2019 Monthly Project Progress Report - Augustus - September - October 2014 (Section 1)
3/9
12
]
Gambar 12.a-h. Pekerjaan Beton Bertulang Balok Struktural Lt. II, Dim. 25x40 cm dengan L=7.0
m, Balok Struktural Lt.II, Dim. 20x30 cm L=4.0 5.0 m, dan Ringbalk (Blk Tepi)
8/10/2019 Monthly Project Progress Report - Augustus - September - October 2014 (Section 1)
4/9
13
Gambar 13.a-h. Pek. Bekisting & Pembesian/Penulangan Pelat Talang Beton Bertulang Lantai 2
8/10/2019 Monthly Project Progress Report - Augustus - September - October 2014 (Section 1)
5/9
14
Gambar 14.a-e. Detail Konfigurasi Tulangan Pelat (Kantilever) Talang Beton Bertulang, t = 10
cm. Tulangan tarik (negatif) =10 15 cm, tulangan bagi10 15 cm.
8/10/2019 Monthly Project Progress Report - Augustus - September - October 2014 (Section 1)
6/9
15
Gambar 15.a-e. Pekerjaan Susunan Dinding Bata Batu Campuran 1:3 (Traasram) dan Cam-
puran 1 semen : 5 pasir.
8/10/2019 Monthly Project Progress Report - Augustus - September - October 2014 (Section 1)
7/9
16
Gambar 16.a-f. Pekerjaan Plesteran Dinding Bata Batu Campuran 1 semen: 3 pasir
(traasram) dan Campuran 1 semen : 5 pasir (plesteran biasa)
8/10/2019 Monthly Project Progress Report - Augustus - September - October 2014 (Section 1)
8/9
17
Gambar 17.a-h. Pekerjaan Pemasangan Rangka Kuda-kuda dan Reng Baja Ringan dan Peker-
jaan Lapis Penutup Atap Genteng Metal
8/10/2019 Monthly Project Progress Report - Augustus - September - October 2014 (Section 1)
9/9
18