Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Month 2 Integrated Performance Report
1
0. Reference Information
Author:Claire Jones, Principal Analyst and Data Quality Lead
Paper date: 25/06/2020
Executive Sponsor:Kerry Robinson, Director of Performance, Improvement and OD
Paper Category: Performance
Paper Reviewed by: Executive Team Paper Ref: N/A
Forum submitted to: Board of Directors Paper FOIA Status: Full
1. Purpose of Paper
1.1. Why is this paper going to Trust Board and what input is required?
The committee is required to assure itself that the Trust is providing high quality, caring and safe health care services in accordance with national regulatory standards.
The purpose of the Integrated Performance Report (IPR) is to provide the committee with the evidence of achievement against the national regulatory standards, identification of emerging risks and the assurance that an improvement plan is in place and is effective.
This paper is for information summarising the key performance indicators, highlighting areas of high or low performance for operational and financial metrics.
The committee is asked to note the overall performance as presented in the month 2 (May) Integrated Performance Report, against all areas and actions being taken to meet targets.
2. Executive Summary
2.1. Context
The paper incorporates the monthly integrated performance report with associated narrative and descriptions of key actions.
It should be noted that the NHS is currently in phase two of the response to covid-19 which covers the period May to July which is the period of restoring safe service levels for critical services and signalling restart of some routine services. There are a number of regulatory standards data collection have been suspended, further guidance is awaited on access standards.
The targets within the IPR are either regulatory standards that stood pre-covid or where not regulatory standards are the draft 20/21 plan. These will be updated to align with national guidance and/or restoration plans as the year progresses to enable performance monitoring these will be approved the committees of the Board.
Changes to our services commenced week beginning 16th March 2020 and therefore due to this special cause variation there may have been impact on some of our standard KPI’s. From that time, and throughout April, the Trust has only seen or operated on urgent electives and has assisted the local system with trauma services.
2.2. Summary
20
Month 2 Integrated Performance Report
2
I In line with the Trust’s Performance Management Strategy and Accountability Framework, Board-level Key Performance Indicators (KPIs) which are considered to drive the overall performance of the Trust.
The 20/21 IPR has been adapted in line with our recently agreed 20/21 performance framework to now include a section of action, both action for improvement and actions for sustainability. As would be anticipated it is expected that this will strengthen over the period as the organisational structure embeds.
The Trust remains in segment 2 of the NHS Improvement Single Oversight Framework.
Areas of performance to highlight this month are as follows;
Caring for Staff;
Sickness remains above target at 3.98%, with slight reduction from previous month.
Voluntary staff turnover has reduced and back below the 8% target at 7.96%
Caring for Patients;
Total patient falls remains within tolerance level with seven reported in month; no falls resulting in moderate or severe, however inpatients ward fall per 1,00 bed days was outside of target.
Delayed Discharge rate green rated at 2.16% against the 2.5% target; lowest rate in 24 months reported.
No RJAH acquired infections reported this month.
Complaints remain within tolerance with seven received in May. Response rate red rated at 50% with one complaint not responded to within 25 days.
All previous cancer standards were met for April (reported a month in arrears), the newly introduced 28 day faster diagnosis standard did not meet the 75% target and reported at 72.22%
Our English RTT open pathways performance is reported at 67.30%, with our English list size increasing by 216 (3%) from that reported last month. The May month end figure is reported at 7,758 the highest for the last 13 months, 15% higher than our lowest point in the last 12 months.
33 English patients and 40 Welsh patients waiting over 52 weeks, along with continual reporting of Welsh transfer of care after 52 weeks at 203 patients.
Both diagnostics standards (English and Welsh) did not achieve their respective targets.
Caring for Finances;
Covid-19 continued to impact the level of theatre activity delivered in April. All non-urgent elective activity and inpatient dental work ceased from Friday 20th March.
194 theatre cases carried out for urgent electives and trauma services.
In response to covid-19, non-essential outpatient activity was cancelled from the 16th March. Throughout May, 4237 attendances were seen where 416 were classed as fracture clinics.
All financial measures green rated, with exception of Income.
The following targets will be reviewed in the next period;
Touchtime utilisation – to align with PPE requirements and implications for remainder of the year.
Bed occupancy – to align with national modelling assumptions for restoration.
% sessions used against plan – to align with restoration plans
Day case rate – to align with restoration plans
New to follow up ratio – to align with restoration plans.
2.3. Conclusion
The Trust Board is asked to note the report and where insufficient assurance is received via the responsible sub-committee of the Board, the Board will seek additional assurance.
21
Integrated Performance Report
May 2020 – Month 2
22
Contents
Summary 3
Heatmaps
Caring for Staff 4
Caring for Patients 5
Caring for Finances 7
Narrative
Caring for Staff 8
Caring for Patients 10
Caring for Finances 34
Reading guide End
Integrated Performance Report 2
Integrated Performance Report
May – Month 2
23
Integrated Performance Report 3
Integrated Performance Report
May – Month 2
24
Caring for Staff
Ma
y 2
01
9
Ju
n 2
01
9
Ju
l 2
01
9
Au
g 2
01
9
Se
p 2
01
9
Oct
20
19
No
v 2
01
9
De
c 2
01
9
Ja
n 2
02
0
Fe
b 2
02
0
Ma
r 2
02
0
Ap
r 2
02
0
Ma
y 2
02
0
La
test
targ
et
YT
D p
lan
YT
D a
ctu
al
Ye
ar-
en
d
fore
ca
st
DQ
ra
tin
g
Sickness Absence 4.19% 4.45% 4.43% 4.86% 4.52% 5.19% 5.12% 4.87% 4.75% 4.83% 4.37% 4.06% 3.98% 3.6% 3.6% 3.98% G Feb-20
Voluntary Staff Turnover - Headcount 6.91% 6.42% 6.66% 6.13% 6.78% 7.17% 7.38% 6.73% 7.46% 7.51% 7.32% 8.41% 7.96% 8% 8% 7.96% G Sep-19
Thirteen-month heatmap view
Integrated Performance Report 4
Integrated Performance Report
May – Month 2
25
Caring for Patients
Ma
y 2
01
9
Ju
n 2
01
9
Ju
l 2
01
9
Au
g 2
01
9
Se
p 2
01
9
Oct
20
19
No
v 2
01
9
De
c 2
01
9
Ja
n 2
02
0
Fe
b 2
02
0
Ma
r 2
02
0
Ap
r 2
02
0
Ma
y 2
02
0
La
test
targ
et
YT
D p
lan
YT
D a
ctu
al
Ye
ar-
en
d
fore
ca
st
DQ
ra
tin
g
Serious Incidents 1 0 0 0 0 1 0 0 1 0 0 0 1 0 0 1 R Apr-18
Never Events 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 G Apr-18
Total Patient Falls 11 16 10 8 12 17 5 18 19 9 9 3 7 10 20 10 G Mar-19
RJAH Acquired Pressure Ulcers -
Grades 3 or 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 G Apr-18
Patient Friends & Family - % Would
Recommend (Inpatients & Outpatients) 98.52% 99.28% 98.9% 99.21% 99% 99.07% 98.63% 98.4% 98.48% 98.55% 98.23% 99.22% 97.85% 95% G Apr-18
Number of Complaints 8 7 9 7 15 19 11 5 7 13 7 2 7 8 16 9 G May-18
% Delayed Discharge Rate 3.6% 4.63% 6.82% 4.75% 5.61% 5.98% 6.67% 6.78% 4.76% 4.01% 7.7% 7.23% 2.16% 2.5% 2.5% 4.73% R Nov-19
Mixed Sex Accommodation 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 G Jun-19
RJAH Acquired E. Coli Bacteraemia 2 0 1 0 1 1 1 1 1 0 0 0 0 0 0 0 G Jun-19
RJAH Acquired C.Difficile 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 G Apr-18
RJAH Acquired MRSA Bacteraemia 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 G Apr-18
Unexpected Deaths 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 G Apr-18
VTE Assessments Undertaken 99.83% 99.73% 99.92% 100% 99.76% 99.85% 99.85% 100% 100% 100% 99.88% 100% 100% 95% 95% 100% G Apr-18
Cancer Two Week Wait* 100% 100% 96.77% 100% 100% 100% 100% 100% 100% 100% 100% 100% 93% 100% G Feb-20
31 Days First Treatment (Tumour)* 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 96% 100% G Nov-19
31 Days Subsequent Treatment
(Tumour)* 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 94% 100% G Nov-19
Cancer Plan 62 Days Standard
(Tumour)* 100% 100% 100% 100% 80% 100% 0% 100% 100% 100% 100% 85.71% 85% 85.71% G
Integrated Performance Report 5
Integrated Performance Report
May – Month 2
26
Ma
y 2
01
9
Ju
n 2
01
9
Ju
l 2
01
9
Au
g 2
01
9
Se
p 2
01
9
Oct
20
19
No
v 2
01
9
De
c 2
01
9
Ja
n 2
02
0
Fe
b 2
02
0
Ma
r 2
02
0
Ap
r 2
02
0
Ma
y 2
02
0
La
test
targ
et
YT
D p
lan
YT
D a
ctu
al
Ye
ar-
en
d
fore
ca
st
DQ
ra
tin
g
Cancer 62 Days Consultant Upgrade* 100% 100% 100% 100% 100% 80% 100% 100% 25% 100% 100% 100% 85% 100% G Feb-20
28 Day Faster Diagnosis Standard* 81.8% 93.8% 83.9% 92.3% 70% 85% 91.2% 94.1% 82.4% 91.3% 91.3% 72.22% 75% 72.22% G
18 Weeks RTT Open Pathways 91.4% 90.61% 89.9% 88.69% 88.54% 88.01% 88.1% 88.3% 88.15% 87.08% 85.27% 78.77% 67.3% 92% 92% 72.94% R
Patients Waiting Over 52 Weeks – English 0 0 0 0 0 0 0 0 0 0 0 12 33 0 R Nov-19
Patients Waiting Over 52 Weeks – Welsh 0 1 0 0 0 0 0 0 0 1 3 15 40 0 R Nov-19
Patients Waiting Over 52 Weeks – Welsh (BCU Transfers) 6 18 86 128 164 172 167 126 81 106 137 169 203 G Nov-19
6 Week Wait for Diagnostics - English
Patients 97.21% 98.35% 98.55% 98.85% 98.99% 99.87% 99.87% 98.09% 98.8% 98.6% 90.2% 22.38% 20.24% 99% 99% 21.24% R
8 Week Wait for Diagnostics - Welsh
Patients 99.72% 100% 100% 100% 98.87% 100% 99.78% 99.32% 99.75% 99.52% 90.57% 41.65% 21.04% 100% 100% 30.95% R
Integrated Performance Report 6
Integrated Performance Report
May – Month 2
27
Caring for Finances
Ma
y 2
01
9
Ju
n 2
01
9
Ju
l 2
01
9
Au
g 2
01
9
Se
p 2
01
9
Oct
20
19
No
v 2
01
9
De
c 2
01
9
Ja
n 2
02
0
Fe
b 2
02
0
Ma
r 2
02
0
Ap
r 2
02
0
Ma
y 2
02
0
La
test
targ
et
YT
D p
lan
YT
D a
ctu
al
Ye
ar-
en
d
fore
ca
st
DQ
ra
tin
g
Total Theatre Activity 970 886 930 921 1,044 1,078 1,064 827 1,042 940 639 134 194 905 1,801 328 R Sep-19
Bed Occupancy – All Wards – 2pm 81.46% 82.49% 83.07% 81.03% 85.43% 85.06% 86.26% 88.31% 85.88% 89.53% 80.53% 74.31% 71.13% 87% 87% 72.66% R Sep-19
Outpatients Activity Attendances 13,734 12,972 14,238 12,848 14,144 13,062 12,129 10,253 13,249 11,850 9,576 5,297 4,237 13,879 27,758 9,534 R Sep-19
Financial Control Total 31 -207 73 -288 357 611 379 -457 794 560 1,107 0 0 0 0 0 G
Income 9,508 8,842 9,486 8,837 9,583 10,256 10,064 8,595 10,415 9,792 10,633 8,690 8,848 9,492 18,983 17,538 G
Expenditure 9,521 9,092 9,457 9,168 9,270 9,688 9,731 9,095 9,670 9,275 9,564 8,827 8,799 9,585 19,169 17,626 G
Efficiencies Delivery 193 241 246 303 302 270 321 301 230 356 303 44 59 0 0 103 G
Agency Core 68 44 65 77 93 125 107 94 103 133 119 50 27 132 264 77 G
Agency Non-Core 239 221 231 254 252 314 334 229 291 370 208 9 0 167 334 9 G
Cash Balance 4,861 5,013 9,051 5,457 4,387 5,450 5,708 5,822 5,467 6,781 8,250 15,380 17,150 6,000 6,000 17,150 G
Capital Expenditure 336 162 458 588 119 179 546 158 836 234 2,451 72 167 83 136 239 G
Use of Resources (UOR) 3 3 3 3 3 3 3 2 2 2 1 1 1 1 1 1 G
Proportion of Temporary Staff 5.48% 4.81% 5.3% 5.94% 6.14% 7.68% 7.58% 5.72% 6.85% 9.01% 5.8% 1.06% 0% 0.05% 5.34% 0.76% G
Integrated Performance Report 7
Integrated Performance Report
May – Month 2
28
Sickness AbsenceFTE days lost as a percentage of FTE days available in month
3.98% against 3.6% target
Breaching target red rated
Exec Lead:
Director of People
Integrated Performance Report
NarrativeSickness absence rated is reported at 3.98% in May and remains above tolerance. Short term absence was below tolerance at
1.03% following a reduction in short term absences. Long term absence increased in month and remained above tolerance at
2.95%
Anxiety/stress/depression was the highest individual reason for absence again in May, accounting for 1.2% of the absence rate.
MSK delivery unit continues to be above tolerance for both long and short term absences, reporting an overall absence rate of
6.31% in month, noting an increase in long term absences. The highest individual reason for short term absence in the MSK unit
was confirmed Covid-19 cases. The highest individual reason for long term absence was anxiety/stress/depression. Absence
within Theatre scrub accounting for 20% of all absences in MSK Delivery Unit in May.
The rate includes any staff who were absent following a positive Covid-19 test result. It does not include any staff who were
absent due to self-isolation, as this is reported separately as Special Leave. Covid-19 absence was 0.38% in month.
Performance over 24 months – SPC
SPC Alert - 7 or more consecutive points above or below the mean indciates a step change.
Trajectory ActionsAction to Improve: People Business Partners reviewing long-term sickness absence to ensure ongoing communication and
appropriate support.
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
3.41% 3.4% 4.11% 3.57% 3.95% 4.39% 4.07% 4.29% 4.43% 4.58% 4.33% 4.59% 4.19% 4.45% 4.43% 4.86% 4.52% 5.19% 5.12% 4.87% 4.75% 4.83% 4.37% 4.06% 3.98% 3.98%
Heatmap performance over 24 months
Integrated Performance Report 8
Integrated Performance Report
May – Month 2
29
Voluntary Staff Turnover - HeadcountTotal numbers of voluntary leavers in the last 12 months as a percentage of the total employed
7.96% against 8% target
Within target green rated
Exec Lead:
Director of People
Integrated Performance Report
NarrativeThe voluntary staff turnover has reduced and is reported within tolerance at 7.96%. Top 3 reasons for voluntary turnover were
age retirement, work-life balance and other/not known. MSK Delivery Unit saw a further increase in voluntary turnover and is
reported at 10.07%.
Performance over 24 months – SPC
SPC Alert - 7 or more consecutive points above or below the mean indciates a step change.
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
9.56% 8.71% 8.78% 8.07% 8.14% 8.02% 8% 8.18% 7.94% 7.95% 7.37% 7.05% 6.91% 6.42% 6.66% 6.13% 6.78% 7.17% 7.38% 6.73% 7.46% 7.51% 7.32% 8.41% 7.96% 7.96%
Heatmap performance over 24 months
Integrated Performance Report 9
Integrated Performance Report
May – Month 2
30
Serious IncidentsNumber of Serious Incidents reported in month
1 against 0 target
Breaching target red rated
Exec Lead:
Director of Nursing
Integrated Performance Report
NarrativeThere was one serious incident reporting in May relating to transmission of covid-19 on one of the wards where a mini outbreak
occurred. The incident was managed in accordance with outbreak policies and all correct procedures were followed.
Performance over 24 months –
Trajectory ActionsAction to Improve: A full investigation is underway to review this incident.
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
2 0 0 1 1 1 1 1 0 0 2 1 1 0 0 0 0 1 0 0 1 0 0 0 1 1
Heatmap performance over 24 months
Integrated Performance Report 10
Integrated Performance Report
May – Month 2
31
Never EventsNumber of Never Events Reported in Month
0 against 0 target
On target green rated
Exec Lead:
Director of Nursing
Integrated Performance Report
NarrativeThere were no never events reported in May.
Performance over 24 months –
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0
Heatmap performance over 24 months
Integrated Performance Report 11
Integrated Performance Report
May – Month 2
32
Total Patient FallsTotal number of falls - excludes slips, trips and assisted slides
7 against 10 target
Within target green rated
Exec Lead:
Director of Nursing
Integrated Performance Report
NarrativeThe Total Patient Falls KPI is green rated in May as there were seven falls, all relating to inpatients. The falls are broken down as
follows:
- No harm (1) 14.29%
- Low harm (6) 85.71%, made up of - all unwitnessed but with no obvious injury
The falls occurred within the following wards/areas:
- Inpatient falls: Sheldon (2), Powys (2), Kenyon (2), Theatres (1).
Performance over 24 months – SPC
Trajectory ActionsAction to Sustain: The Quality Priorities for 2020/2021 have been set, of which Falls is one of them.
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
9 10 13 10 15 20 13 16 11 10 8 5 11 16 10 8 12 17 5 18 19 9 9 3 7 10
Heatmap performance over 24 months
Integrated Performance Report 12
Integrated Performance Report
May – Month 2
33
RJAH Acquired Pressure Ulcers - Grades 3 or 4Total number of category 3 & 4 pressure ulcers acquired at RJAH
0 against 0 target
On target green rated
Exec Lead:
Director of Nursing
Integrated Performance Report
NarrativeThere were no category three or four pressure ulcers in May.
Performance over 24 months –
Trajectory ActionsAction to Sustain: The Quality Priorities for 2020/2021 have been set, of which Pressure Ulcers is one of them.
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Heatmap performance over 24 months
Integrated Performance Report 13
Integrated Performance Report
May – Month 2
34
Patient Friends & Family - % Would Recommend
(Inpatients & Outpatients)% of patients who would recommend the trust (inpatients and outpatients)
97.85% against 95% target
Above target green rated
Exec Lead:
Director of Nursing
Integrated Performance Report
NarrativeThere were 93 responses collected with a breakdown as follows:
- 91 positive - giving a rate of 97.85% would recommend the Trust to friends and family
- 2 negative - giving a rate of 2.15% would not recommend the Trust to friends and family
The number of compliments received in May was 68.
Although national reporting for this measure is currently suspended we have taken the decision to continue reporting internally,
this will support the safe and efficient care of our patients.
Performance over 24 months – SPC
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
99.08% 99.49% 99.23% 100% 99.45% 99.01% 99.29% 99.06% 99.18% 98.84% 98.84% 98.44% 98.52% 99.28% 98.9% 99.21% 99% 99.07% 98.63% 98.4% 98.48% 98.55% 98.23% 99.22% 97.85%
Heatmap performance over 24 months
Integrated Performance Report 14
Integrated Performance Report
May – Month 2
35
Number of ComplaintsNumber of complaints received in month
7 against 8 target
Within target green rated
Exec Lead:
Director of Nursing
Integrated Performance Report
NarrativeThere were seven complaints received in May. Five complaints related to quality with reasons associated with care received (2),
scans performed (1), consultant attitude (1) and outcome of appointment (1). There were operational complaints relating to
issues surrounding CCG fading forms (1) and current delays to elective surgery (1).
Performance over 24 months – SPC
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
9 11 2 7 12 13 6 7 6 17 8 5 8 7 9 7 15 19 11 5 7 13 7 2 7 9
Heatmap performance over 24 months
Integrated Performance Report 15
Integrated Performance Report
May – Month 2
36
% Delayed Discharge RateThe total number of delayed days against the total available bed days for the month in %
2.16% against 2.5% target
Within target green rated
Exec Lead:
Director of Nursing
Integrated Performance Report
NarrativeThe Delayed Discharge rate is green rated this month at 2.16%. The total delayed days for May is 75 days with a breakdown as
follows:
- 4 spinal injuries patients amounting to 53 days - attributed to 1 patient from each organisation; Coventry, Solihull,
Warwickshire, Wales
- 2 care of the elderly patients with 22 delayed days - both attributed to Shropshire
In response to covid there was a requirement for timely discharge processes. Effective system working has enabled the
discharge of our patients and reduced delays. There has been a change to funding with the aim of discharging patients out of
an acute setting. This has contributed to the reduction in delays for spinal injuries patients as they have been able to be
discharged to step-down beds.
Although national reporting for this measure is currently suspended we have taken the decision to continue reporting internally,
this will support the safe and efficient care of our patients.
Performance over 24 months – SPC
Trajectory ActionsAction to Sustain: The Quality Priorities for 2020/2021 have been set, of which Delayed Transfers of Care is one of them. As
part of the action plan we will assess where improvements have been made during the covid pandemic to assess if these
processes can be sustained.
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
4.12% 4.99% 4.42% 3.27% 5.57% 6.1% 7.53% 8.17% 4.02% 6.05% 6.72% 7% 3.6% 4.63% 6.82% 4.75% 5.61% 5.98% 6.67% 6.78% 4.76% 4.01% 7.7% 7.23% 2.16% 4.73%
Heatmap performance over 24 months
Integrated Performance Report 16
Integrated Performance Report
May – Month 2
37
Mixed Sex AccommodationNumber of breaches to the mixed sex accommodation standard for non clinical reasons
0 against 0 target
On target green rated
Exec Lead:
Director of Nursing
Integrated Performance Report
NarrativeThere were no breaches of the mixed sex accommodation standard in May.
Although national reporting for this measure is currently suspended we have taken the decision to continue reporting internally,
this will support the safe and efficient care of our patients.
Performance over 24 months –
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Heatmap performance over 24 months
Integrated Performance Report 17
Integrated Performance Report
May – Month 2
38
RJAH Acquired E. Coli BacteraemiaNumber of cases of E. Coli Bacteraemia in Month.
0 against 0 target
On target green rated
Exec Lead:
Director of Nursing
Integrated Performance Report
NarrativeThere were no incidents reported in May.
Performance over 24 months –
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
1 0 1 0 1 0 1 0 0 0 0 0 2 0 1 0 1 1 1 1 1 0 0 0 0 0
Heatmap performance over 24 months
Integrated Performance Report 18
Integrated Performance Report
May – Month 2
39
RJAH Acquired C.DifficileNumber of cases of C.Difficile in Month
0 against 0 target
On target green rated
Exec Lead:
Director of Nursing
Integrated Performance Report
NarrativeThere were no incidents reported in May.
Performance over 24 months –
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
0 0 0 0 1 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Heatmap performance over 24 months
Integrated Performance Report 19
Integrated Performance Report
May – Month 2
40
RJAH Acquired MRSA BacteraemiaNumber of cases of MRSA bacteraemia in month
0 against 0 target
On target green rated
Exec Lead:
Director of Nursing
Integrated Performance Report
NarrativeThere were no incidents reported in May.
Performance over 24 months –
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Heatmap performance over 24 months
Integrated Performance Report 20
Integrated Performance Report
May – Month 2
41
Unexpected DeathsNumber of Unexpected Deaths in Month
0 against 0 target
On target green rated
Exec Lead:
Medical Director
Integrated Performance Report
NarrativeThis indicator relates to unexpected deaths, of which there were none to report in May. There was one covid related death that
occurred in May.
Performance over 24 months –
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0
Heatmap performance over 24 months
Integrated Performance Report 21
Integrated Performance Report
May – Month 2
42
VTE Assessments Undertaken% of adult admissions in the month who have been risk assessed for VTE
100% against 95% target
Above target green rated
Exec Lead:
Medical Director
Integrated Performance Report
NarrativeThe percentage of admissions risk assessed is reported at 100% in May and remains above the 95% target.
Although national reporting for this measure is currently suspended we have taken the decision to continue reporting internally,
this will support the safe and efficient care of our patients.
Performance over 24 months – SPC
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
100% 99.92% 99.7% 100% 99.92% 99.71% 99.86% 99.91% 100% 99.84% 99.92% 99.91% 99.83% 99.73% 99.92% 100% 99.76% 99.85% 99.85% 100% 100% 100% 99.88% 100% 100% 100%
Heatmap performance over 24 months
Integrated Performance Report 22
Integrated Performance Report
May – Month 2
43
Cancer Two Week Wait*% of urgent cancer referrals seen within 2 weeks (*Reported one month in arrears)
100% against 93% target
green rated
Exec Lead:
Clinical Services Unit
Integrated Performance Report
NarrativeThe Cancer 2 week wait standard was achieved in April and indicative data for May shows achievement of the standard will
continue.
Performance over 24 months – SPC
SPC Alert - 7 or more consecutive points above or below the mean indciates a step change.
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
100% 100% 96.88% 100% 100% 100% 100% 100% 100% 92.86% 100% 100% 100% 100% 96.77% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Heatmap performance over 24 months
Integrated Performance Report 23
Integrated Performance Report
May – Month 2
44
31 Days First Treatment (Tumour)*% of cancer patients treated within 31 days of decision to treat (*Reported one month in arrears)
100% against 96% target
green rated
Exec Lead:
Clinical Services Unit
Integrated Performance Report
NarrativeThe Cancer 31 day first treatment standard was achieved in April and indicative data for May shows achievement of the standard
will continue.
Performance over 24 months – SPC
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Heatmap performance over 24 months
Integrated Performance Report 24
Integrated Performance Report
May – Month 2
45
31 Days Subsequent Treatment (Tumour)*% of cancer patients subsequent treatment within 31 days of decision to treat (*Reported one month in arrears)
100% against 94% target
green rated
Exec Lead:
Clinical Services Unit
Integrated Performance Report
NarrativeThe Cancer 31 day subsequent treatment standard was achieved in April and indicative data for May shows achievement of the
standard will continue.
Performance over 24 months – SPC
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100%
Heatmap performance over 24 months
Integrated Performance Report 25
Integrated Performance Report
May – Month 2
46
Cancer Plan 62 Days Standard (Tumour)*% of cancer patients treated within 62 days of referral (*Reported one month in arrears)
85.71% against 85% target
green rated
Exec Lead:
Clinical Services Unit
Integrated Performance Report
NarrativeThe Cancer 62 day standard was achieved in April and indicative data for May shows achievement of the standard will not be
met.
Performance over 24 months – SPC
SPC Alert - 7 or more consecutive points above or below the mean indciates a step change.
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
100% 66.67% 50% 0% 0% 50% 100% 66.67% 50% 100% 100% 100% 100% 100% 100% 100% 80% 100% 0% 100% 100% 100% 100% 85.71% 85.71%
Heatmap performance over 24 months
Integrated Performance Report 26
Integrated Performance Report
May – Month 2
47
Cancer 62 Days Consultant Upgrade*% of cancer patients treated within 62 days of date of upgrade (*Reported one month in arrears)
100% against 85% target
green rated
Exec Lead:
Clinical Services Unit
Integrated Performance Report
NarrativeThe Cancer 62 day consultant upgrade standard was achieved in April and indicative data for May shows achievement of the
standard will continue.
Performance over 24 months – SPC
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 80% 100% 100% 25% 100% 100% 100% 100%
Heatmap performance over 24 months
Integrated Performance Report 27
Integrated Performance Report
May – Month 2
48
28 Day Faster Diagnosis Standard*% of patients informed of a diagnosis or ruling out of cancer within 28 days’
72.22% against 75% target
red rated
Exec Lead:
Clinical Services Unit
Integrated Performance Report
NarrativeThe 28 Day faster diagnosis standard is a new metric added last month whereby it reports the percentage of patients that have
been informed of either their diagnosis or ruling out of cancer within 28 days. Like the other cancer waiting times standards, this
one will be reported a month in arrears.
The standard is reported at 72.22% in April with a target of 75% operational from April. Indicative data for May shows
achievement of the standard will be met.
Performance over 24 months – SPC
Trajectory ActionsAction to Improve: The pathways of those patients that were not diagnosed within 28 days are being reviewed to understand
the reasons why and if appropriate, derive appropriate actions.
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
90.5% 81.8% 93.8% 83.9% 92.3% 70% 85% 91.2% 94.1% 82.4% 91.3% 91.3% 72.22% 72.22%
Heatmap performance over 24 months
Integrated Performance Report 28
Integrated Performance Report
May – Month 2
49
18 Weeks RTT Open Pathways% of English patients on waiting list waiting 18 weeks or less
67.3% against 92% target
Below target red rated
Exec Lead:
MSK Unit
Integrated Performance Report
NarrativeOur May performance was 67.30% against the 92% open pathway performance for patients waiting 18 weeks or less to start
their treatment. The total number of breaches has increased by 934, rising from 1603 in April to 2537 at the end of May. The
performance breakdown by milestone is as follows: MS1 - 4622 patients waiting of which 705 are breaches, MS2 - 828 patients
are waiting of which 459 are breaches, MS3 - 2308 patients are waiting of which 1373 are breaches.
Our response to COVID-19 meant cancelling and deferring normal clinical activity, whilst continuing with critical and urgent
clinical cases.
Performance over 24 months – SPC
Trajectory ActionsAction to Improve: The Trust is reviewing national guidance as this is published in how we manage patient pathways. As a
local system we have agreed to commence inpatient demand categorised as priority 2. This is a small volume of our current
waiting lists. The Trust is working with the system to assess capacity to commence further activity.
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
89.49% 89.98% 89.96% 89.6% 90.29% 90.66% 90.28% 90.04% 90.02% 90.47% 92.14% 92.01% 91.4% 90.61% 89.9% 88.69% 88.54% 88.01% 88.1% 88.3% 88.15% 87.08% 85.27% 78.77% 67.3% 72.94%
Heatmap performance over 24 months
Integrated Performance Report 29
Integrated Performance Report
May – Month 2
50
Patients Waiting Over 52 Weeks – EnglishNumber of English RTT patients currently waiting 52 weeks or more
33 against 0 target
Breaching target red rated
Exec Lead:
Specialist Services Unit
Integrated Performance Report
NarrativeAt the end of May there were 33 English patients waiting over 52 weeks. The patients are under the care of the following sub-
specialities; Arthroplasty (14), Spinal Disorders (13), Knee & Sports Injuries (2). Foot & Ankle (2) and Upper Limb (2).
Performance over 24 months –
Trajectory ActionsAction to Improve: The Trust is reviewing national guidance as this is published in how we manage patient pathways. As a
local system we have agreed to commence inpatient demand categorised as priority 2. This is a small volume of our current
waiting lists. The Trust is working with the system to assess capacity to commence further activity.
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
1 0 1 1 0 2 2 4 2 4 0 0 0 0 0 0 0 0 0 0 0 0 0 12 33
Heatmap performance over 24 months
Integrated Performance Report 30
Integrated Performance Report
May – Month 2
51
Patients Waiting Over 52 Weeks – WelshNumber of RJAH Welsh RTT patients currently waiting 52 weeks or more
40 against 0 target
Breaching target red rated
Exec Lead:
Specialist Services Unit
Integrated Performance Report
NarrativeAt the end of May there were 40 Welsh patients waiting over 52 weeks. The patients are under the care of the following sub
specialties; Spinal Disorders (15), Arthroplasty (13), Foot & Ankle (5), Knee & Sports Injuries (5) and Upper Limb (2). The patients
are under the care of the following commissioners; BCU (33) and Powys (7).
Performance over 24 months –
Trajectory ActionsAction to Improve: The Trust is reviewing national guidance as this is published in how we manage patient pathways. As a
local system we have agreed to commence inpatient demand categorised as priority 2. This is a small volume of our current
waiting lists. The Trust is working with the system to assess capacity to commence further activity.
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
2 2 9 8 6 3 6 7 3 6 1 0 0 1 0 0 0 0 0 0 0 1 3 15 40
Heatmap performance over 24 months
Integrated Performance Report 31
Integrated Performance Report
May – Month 2
52
Patients Waiting Over 52 Weeks – Welsh (BCU
Transfers)Number of BCU transfer Welsh RTT patients currently waiting 52 weeks or more.
203 against N/A target
Exec Lead:
MSK Unit
Integrated Performance Report
NarrativeAt the end of May there were 203 Welsh patients waiting over 52 weeks who were transfers of care from BCU. No patients have
been transferred throughout May.
Performance over 24 months –
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
126 128 121 124 87 54 72 66 52 26 0 1 6 18 86 128 164 172 167 126 81 106 137 169 203
Heatmap performance over 24 months
Integrated Performance Report 32
Integrated Performance Report
May – Month 2
53
6 Week Wait for Diagnostics - English Patients% of English patients currently waiting less than 6 weeks for diagnostics
20.24% against 99% target
Below target red rated
Exec Lead:
Clinical Services Unit
Integrated Performance Report
NarrativeThe 6 week standard for diagnostics was not achieved this month and is reported at 20.24%. This equates to 717 patients who
waited beyond 6 weeks.
The breaches occurred in the following modalities; MRI (419), ultrasound (167), CT (113) and DEXA (18) . MRI capacity is planned
to be increased during June 2020 with known capacity issues within this area.
From week commencing 16th March the Trust has seen the impact of COVID-19 and had to adjust the services delivered. All
requests for investigations are being triaged by a radiologist with non-urgent requests being postponed. Referrers are sent lists
of all postponed investigations. Postponements are being held on the waiting list and as predicted, the majority of patients
waiting for diagnostics continue to breach at the end of May.
Following the postponement of non-urgent requests the Trust has continued to review its waiting list impacts. This has meant a
resubmission of our March 2020 DM01 as part of ensuring all cancellations were correctly represented.
Performance over 24 months – SPC
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
99.53% 99.37% 98.59% 99.15% 99.16% 99.07% 98.7% 99.1% 98.91% 98.88% 97.64% 97.53% 97.21% 98.35% 98.55% 98.85% 98.99% 99.87% 99.87% 98.09% 98.8% 98.6% 90.2% 22.38% 20.24% 21.24%
Heatmap performance over 24 months
Integrated Performance Report 33
Integrated Performance Report
May – Month 2
54
8 Week Wait for Diagnostics - Welsh Patients% of Welsh patients currently waiting less than 8 weeks for diagnostics
21.04% against 100% target
Below target red rated
Exec Lead:
Clinical Services Unit
Integrated Performance Report
NarrativeThe 8 week standard for diagnostics was not achieved this month and is reported at 21.04%. This equates to 424 patients who
waited beyond 8 weeks. The breaches occurred in the following modalities MRI (327), CT (46), ultrasound (46) and DEXA (5).
MRI capacity is planned to be increased during June 2020 with known capacity issues within this area.
From week commencing 16th March the Trust has seen the impact of COVID-19 and had to adjust the services delivered. All
requests for investigations are being triaged by a radiologist with non-urgent requests being postponed. Referrers are sent lists
of all postponed investigations. Postponements are being held on the waiting list and as predicted, the majority of patients
waiting for diagnostics continue to breach at the end of May.
Following the postponement of non-urgent requests the Trust has continued to review its waiting list impacts. This has meant a
resubmission of our March 2020 DM01 as part of ensuring all cancellations were correctly represented.
Performance over 24 months – SPC
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
100% 99.76% 99.77% 99.67% 100% 99.24% 99.65% 99.64% 99.66% 98.72% 100% 98.76% 99.72% 100% 100% 100% 98.87% 100% 99.78% 99.32% 99.75% 99.52% 90.57% 41.65% 21.04% 30.95%
Heatmap performance over 24 months
Integrated Performance Report 34
Integrated Performance Report
May – Month 2
55
Total Theatre ActivityActivity in theatres in month
194 against 905 target
Below target red rated
Exec Lead:
MSK Unit
Integrated Performance Report
NarrativeCOVID-19 continued to impact the delivered activity throughout May 2020. All non-urgent elective activity and all inpatient
dental work at RJAH ceased from Friday 20th March. Tumour and emergency spinal surgery continues as an exception, and a
judgement on all other urgent surgery is made on a case-by-case basis.
For all areas the Trust delivered 194 (21%) of the 905 plan, broken down as follows:
- T&O - 16
- Trauma - 170
- Tumour - 8
- MCSI - 0
Performance over 24 months – SPC
Trajectory ActionsAction to Improve: For May 2020 restoration and recovery discussions were ongoing within the System. Agreement was made
for the Trust to commence priority 2 activity was made within the system. This was to commence week beginning the 8th
June. These are small volumes of elective activity.
The Trust is working with the system following agreement that Trauma would return to SaTH August/September 2020. These
discussions are ongoing and impacts to activity are being modelled. This would enable the Trust to commence further elective
activity.
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
1,004 1,023 1,053 929 1,017 1,115 1,157 883 1,094 1,024 1,082 856 970 886 930 921 1,044 1,078 1,064 827 1,042 940 639 134 194 328
Heatmap performance over 24 months
Integrated Performance Report 35
Integrated Performance Report
May – Month 2
56
Bed Occupancy – All Wards – 2pm% Bed occupancy at 2pm
71.13% against 87% target
Within target red rated
Exec Lead:
Specialist Services Unit
Integrated Performance Report
NarrativeThe occupancy rate for all wards is red rated this month at 71.13%. The breakdown below gives the May occupancy per ward
along with details on bed base and it's current use:
Trauma/Urgent Elective Work:
- Clwyd - 84.89% - usually 28 beds; open to 14/16 beds at start of May, increased to 20 beds by end of May
- Powys - 83.74% - usually 28 beds; open to 14 beds for majority of the month
- Kenyon - 66.80% - open to usual 16 beds throughout May
- Alice 44.83% - open to low numbers of patients in late May but primarily closed - 16 beds
- Ludlow 21.79% - usually 16 beds; start of May open to 14 beds, second half of month reduced to 8 beds open - ward used for
suspected/confirmed covid patients
- Oswald - ward of 10 beds fully closed throughout May
MCSI/Sheldon
- Gladstone 65.25% - open to 25 of usual 29 beds with 4 beds used as an isolation area
- Wrekin 70.19% - open to usual 15 beds
- Sheldon 90.04% - open to 15 of usual 23 beds
Performance over 24 months – SPC
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
82.52% 85.73% 83.78% 86.61% 89.08% 85.94% 84.03% 84.83% 86.78% 87.62% 85.32% 81.44% 81.46% 82.49% 83.07% 81.03% 85.43% 85.06% 86.26% 88.31% 85.88% 89.53% 80.53% 74.31% 71.13% 72.66%
Heatmap performance over 24 months
Integrated Performance Report 36
Integrated Performance Report
May – Month 2
57
Outpatients Activity AttendancesNumber of attendances seen in Outpatients clinic – excludes SOOS, MCSI and NCG as they are block contracts
4,237 against 13,879 target
Below target red rated
Exec Lead:
Support Services Unit
Integrated Performance Report
NarrativeThe number of attendances was behind plan in month 2 with 4237 attendances seen against a plan of 13879. 416 of the
attendances were classed as fracture clinics which is part of the Trauma work that has transferred to the Trust during this period.
Performance over 24 months – SPC
SPC Alert - 7 or more consecutive points above or below the mean indciates a step change.
Trajectory ActionsAction to Improve: The Trust capacity for delivering outpatient activity has been reduced following application of infection,
prevention and control measures e.g. social distancing. The Trust is reviewing the estate capacity available to see patients
requiring face-to-face activity. Wherever possible the Trust is reviewing patients virtually.
System discussions are ongoing to review the fracture and trauma outpatient activity currently being undertaken at RJAH.
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
13,662 13,609 13,631 12,885 13,792 15,939 15,298 11,440 14,995 13,616 13,718 13,677 13,734 12,972 14,238 12,848 14,144 13,062 12,129 10,253 13,249 11,850 9,576 5,297 4,237 9,534
Heatmap performance over 24 months
Integrated Performance Report 37
Integrated Performance Report
May – Month 2
58
Financial Control TotalSurplus/deficit adjusted for donations and excluding STF funding
0 against 0 target
On target green rated
Exec Lead:
Director of Finance
Integrated Performance Report
NarrativeBreakeven requires retrospective top up of £93k. Covid expenditure amounted to £237k - £138k decrease from M1.
Performance over 24 months – SPC
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
7 235 279 -190 152 676 621 -833 359 59 535 -775 31 -207 73 -288 357 611 379 -457 794 560 1,107 0 0 0
Heatmap performance over 24 months
Integrated Performance Report 38
Integrated Performance Report
May – Month 2
59
IncomeAll Trust Income, Clinical and non clinical
8,848 against 9,492 target
Below target red rated
Exec Lead:
Director of Finance
Integrated Performance Report
NarrativeIncome £829k adverse, predominantly driven by commercial shortfalls
Performance over 24 months – SPC
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
8,958 9,378 9,559 9,080 9,194 10,357 10,004 8,048 9,583 9,049 10,278 8,677 9,508 8,842 9,486 8,837 9,583 10,256 10,064 8,595 10,415 9,792 10,633 8,690 8,848 17,538
Heatmap performance over 24 months
Integrated Performance Report 39
Integrated Performance Report
May – Month 2
60
ExpenditureAll Trust expenditure including Finance Costs
8,799 against 9,585 target
Within target green rated
Exec Lead:
Director of Finance
Integrated Performance Report
Narrative
Plan budgetary variances:
Pay £220k adverse (driven by Covid)
Non pay £1,050k favourable (driven by activity volumes)
Underlying cost base reduced by £973k compared to winter 2019 (basis for plan).
Performance over 24 months – SPC
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
8,959 9,129 9,165 9,264 9,038 9,734 9,416 8,648 9,189 9,031 9,464 9,495 9,521 9,092 9,457 9,168 9,270 9,688 9,731 9,095 9,670 9,275 9,564 8,827 8,799 17,626
Heatmap performance over 24 months
Integrated Performance Report 40
Integrated Performance Report
May – Month 2
61
Efficiencies DeliveryCost Improvement Programme requirement
59 against 0 target
Above target green rated
Exec Lead:
Director of Finance
Integrated Performance Report
NarrativeEfficiency requirement postponed nationally as part of funding arrangements for M1-4.
Internal performance of £59k - predominantly full year effect
Note: target efficiency subject to revised planning guidance
Performance over 24 months – SPC
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
288 356 249 310 298 327 311 329 284 307 358 166 193 241 246 303 302 270 321 301 230 356 303 44 59 103
Heatmap performance over 24 months
Integrated Performance Report 41
Integrated Performance Report
May – Month 2
62
Agency CoreAnnual ceiling for total agency spend introduced by NHS Improvement - Core Agency only
27 against 132 target
Within target green rated
Exec Lead:
Director of Finance
Integrated Performance Report
NarrativeCore Agency favourable £105k
Performance over 24 months – SPC
SPC Alert - 7 or more consecutive points above or below the mean indciates a step change.
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
167 158.27 186.24 122.05 112.7 171.62 141.07 105.5 90.56 45.75 68.59 51 68 44 65 77 93 125 107 94 103 133 119 50 27 77
Heatmap performance over 24 months
Integrated Performance Report 42
Integrated Performance Report
May – Month 2
63
Agency Non-CoreAnnual ceiling for total agency spend introduced by NHS Improvement - Non Core Agency
0 against 167 target
Within target green rated
Exec Lead:
Director of Finance
Integrated Performance Report
NarrativeNo non core agency used in month
Performance over 24 months – SPC
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
207.73 248.74 246.63 296.21 243.2 302.08 233.41 234.72 243.13 243.43 317.48 229 239 221 231 254 252 314 334 229 291 370 208 9 0 9
Heatmap performance over 24 months
Integrated Performance Report 43
Integrated Performance Report
May – Month 2
64
Cash BalanceCash in bank
17,150 against 6,000 target
Above target green rated
Exec Lead:
Director of Finance
Integrated Performance Report
NarrativeCash balance of £17m, which includes the following payments in advance:
- £6.0m English block income
- £2.4m of Covid top up funding
Underlying cash balance £8.8m
Performance over 24 months – SPC
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
4,773 4,200 6,300 6,200 5,400 5,000 4,200 3,900 4,700 4,300 5,700 5,094 4,861 5,013 9,051 5,457 4,387 5,450 5,708 5,822 5,467 6,781 8,250 15,380 17,150 17,150
Heatmap performance over 24 months
Integrated Performance Report 44
Integrated Performance Report
May – Month 2
65
Capital ExpenditureExpenditure against Trust capital programme
167 against 83 target
Breaching target green rated
Exec Lead:
Director of Finance
Integrated Performance Report
NarrativeMRI replacement scheme project ahead of plan
Performance over 24 months – SPC
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
264 346 205 164 297 160 377 400 304 165 1,327 260 336 162 458 588 119 179 546 158 836 234 2,451 72 167 239
Heatmap performance over 24 months
Integrated Performance Report 45
Integrated Performance Report
May – Month 2
66
Use of Resources (UOR)Overall Use of Resources indicator
1 against 1 target
On target green rated
Exec Lead:
Director of Finance
Integrated Performance Report
Narrative Performance over 24 months –
Trajectory Actions
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
3 3 2 3 2 2 2 2 2 2 1 3 3 3 3 3 3 3 3 2 2 2 1 1 1 1
Heatmap performance over 24 months
Integrated Performance Report 46
Integrated Performance Report
May – Month 2
67
Proportion of Temporary StaffAgency staff costs as a proportion of total staff costs.
0% against 0.05% target
Within target green rated
Exec Lead:
Director of Finance
Integrated Performance Report
NarrativeReduction in flexible staffing requirements due to Covid
Performance over 24 months – SPC
SPC Alert - 7 or more consecutive points above or below the mean indciates a step change.
Trajectory Actions
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May YTD
4.88% 5.48% 4.81% 5.3% 5.94% 6.14% 7.68% 7.58% 5.72% 6.85% 9.01% 5.8% 1.06% 0% 0.76%
Heatmap performance over 24 months
Integrated Performance Report 47
Integrated Performance Report
May – Month 2
68
Integrated Performance Report 48
Integrated Performance Report
May – Month 2
69
Reading guideThe Integrated Performance Report (IPR) is designed to provide the Board with a monthly balanced summary of the Trust ’s performance across the three areas of the Trust’s mission: caring for patients,
caring for staff and caring for finances. To achieve this, the Trust has identified the Board-level Key Performance Indicators (KPIs), which are considered to drive the overall performance of the Trust. The
report highlights key areas of improvement or concern enabling the Board to identify those areas that require the most consideration. As such, this report is not designed to replace the need for more
detailed reporting on key areas of performance, and therefore detailed reporting will be provided to the Board and its committees to accompany the IPR where requested by the Board, its committees
or the Executive Team. Contents of the report include:
HeatmapsIn month, year-to-date and forecast performance against target for each KPI and rolling 13-month performance information. A data quality indicator for each KPI is also included where available.
NarrativeSupporting narrative and trend graphs (with statistical process control where appropriate) are provided for each KPI including mitigating actions for red rated indicators.
Key
Key Performance Indicator RAG Ratings Trend graphs
Each KPI has a trend graph (or Statistical Process Control
(SPC) where appropriate), which summarises
performance over a rolling 24-month period.
Green
Red
Forecast: Little risk of missing target at year end
YTD: Performance meets or exceeds target
Forecast: High risk of missing target at year end
YTD: Performance behind target and outside tolerance
KPIs reported in arrears
KPIs reported in arrears, for which no current-month values are available, are marked with an
asterisk (*) next to their name. The latest values for these KPIs are from the previous reporting
month.
Data Quality Indicator
The data quality rating for each KPI is included within the 'heatmap' section of this report. The
indicator score is based on audits undertaken by the Data Quality Team and will be further
validated as part of the audit assurance programme.
No improvement required to comply with the dimensions of data qualityBlue
Green Satisfactory – minor issues only
Amber Requires improvement
Red Significant improvement required
Where available, three-month trajectory data is included
to indicate expected future performance. Historical
trajectory data will be kept to compare actual
performance with forecast performance.
Trajectories
Bullet graphs provide a clear visualisation to understand
how well a KPI is performing against its target.
Bullet graphs
Integrated Performance Report 49
Integrated Performance Report
May – Month 2
70
2228
*Pre covid plan - this will be superseded by new planning.
Finance Dashboard 31st May 2020Robert Jones and Agnes Hunt Orthopaedic Hospital NHS Foundation Trust
Statement of Financial Position £'000s
Category Apr-20 May-20 Movement Drivers
Fixed Assets 75,783 75,643 (140) Additions less depreciation
Non current receivables 1,266 1,259 (7)
Total Non Current Assets 77,049 76,902 (147)
Inventories (Stocks) 1,393 1,384 (9)
Receivables (Debtors) 5,708 4,312 (1,396)19/20 PSF & Covid reimbursement received,
reduction in commercial recievables due to no activity.
Cash at Bank and in hand 15,377 17,149 1,772 19/20 PSF & Covid reimbursement received.
Total Current Assets 22,478 22,845 367
Payables (Creditors) (17,232) (17,487) (255)
Borrowings (1,199) (1,208) (9)
Current Provisions (216) (216) 0
Total Current Liabilities (< 1 year) (18,647) (18,911) (264)
Total Assets less Current Liabilities 80,880 80,836 (44)
Non Current Borrowings (4,708) (4,708) 0
Non Current Provisions (883) (883) 0
Non Current Liabilities (> 1 year) (5,591) (5,591) 0
Total Assets Employed 75,289 75,245 (44)
Public Dividend Capital (35,467) (35,467) 0
Revenue Position (17,703) (17,703) 0
Retained Earnings 44 88 44 Operational deficit before control total adjustments
Revaluation Reserve (22,163) (22,163) 0
Total Taxpayers Equity (75,289) (75,245) 44
May-20 YTD
Debtor Days 26 25
Creditor Days 36 35
Plan Actual Variance Plan Actual Variance
Clinical Income 104,488 8,414 8,240 (174) 16,828 16,397 (431)
Covid Top Up 0 93 186 93 186 323 137
Private Patient income 5,510 455 0 (455) 910 0 (910)
Other income 6,892 622 330 (293) 1,244 819 (425)
Pay (66,899) (5,592) (5,818) (226) (11,185) (11,383) (198)
Non-pay (43,963) (3,572) (2,517) 1,055 (7,142) (5,316) 1,826
EBITDA 6,028 420 420 0 841 840 (1)
Finance Costs (5,618) (420) (464) (44) (841) (928) (87)
Capital Donations 3,825 0 0 0 0 0 0
Operational Surplus 4,235 (0) (44) (44) 0 (88) (88)
Remove Capital Donations (3,825) 0 0 0 0 0 0
Add Back Donated Dep'n 359 0 44 44 0 88 88
Control Total* 769 (0) 0 0 0 0 0
EBITDA margin 5.2% 4.4% 4.9% 0.5% 4.4% 4.9% 0.4%
Income and Expenditure £'000s
CategoryAnnual
Plan
In Month Position Year To Date Position
Capital service 1 I&E Margin 1
Liquidity (days) 1 Variance in I&E Margin 1
Agency 1
1Overall UOR
(£200)
£0
£200
£400
£600
£800
£1,000
£1,200
£1,400
Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21
S
u
r
p
l
i
u
s
/
(
D
e
f
i
c
i
t)
Period
Monthly Surplus/Deficit
Plan
Actual
Note: Current assumption is English block contract payments in advance continue until the end of the 2021
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
18.00
20.00
Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21
C
a
s
h
£
M
Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21
Plan £M 6.25 6.00 6.38 6.84 6.30 6.17 6.69 7.04 6.84 7.12 5.92 5.81
Actual £M 15.38 17.15
Forecast £M 17.15 17.85 18.52 18.00 17.77 17.89 17.59 17.12 16.92 14.43 5.81
Cash Flow
71
RAG of Total Schemes Being Tracked
0%
575 17%
478 14%
2,328 69%
3,381 100%
Year To Date Commissioner Income against Plan £m
Ca
pit
al
Co
mm
issio
ne
r P
erf
orm
an
ce
In Month Efficiencies Achievement £000's Year To Date Efficiencies Achievement £000's
Eff
icie
ncie
s b
y T
he
me
Eff
icie
ncie
s b
y U
nit
Year to date capital programme £000's
Robert Jones and Agnes Hunt Orthopaedic Hospital NHS Foundation TrustFinance Dashboard 31st May 2020
Efficiencies
In Month Efficiencies Achievement £000's Year To Date Efficiencies Achievement £000's Trust YTD Achievement Against YTD Plan £000's
0 5 10 15 20 25 30 35
Unit
FYE 19/20
Local Strategic
National Strategic
May Plan May Actual
0
20
40
60
80
100
120
YTD Plan YTD Actual
0 10 20 30 40 50 60
Unit
FYE 19/20
Local Strategic
National Strategic
YTD Plan YTD Actual
0 5 10 15 20 25
CSU
MSK
OOA
SPEC
SSU
May Plan May Actual
0 10 20 30 40 50
CSU
MSK
OOA
SPEC
SSU
YTD Plan YTD Actual
- 1.00 2.00 3.00 4.00 5.00 6.00
Shropshire
Telford
BCU
NHS England (Specialist)
Other English Contracted
Powys
Cheshire
Unsold Activity
Other
YTD actual YTD plan
Position as at 2021-02
Project
Annual
Plan
£000s
YTD Plan
£000s
YTD
Completed
£000s
YTD
Variance
£000s
Diagnostic equipment replacement 1,545 45 127 -82
EPR planning & implementation 200 0 0 0
Backlog maintenance 500 10 10 0
I/T investment & replacement 300 0 -4 4
Equipment & service continuity 600 0 -1 1
Project management 100 16 0 16
Invest-to-save schemes 200 0 0 0
Contingency 410 0 0 0
Scheme slippage from 19/20 135 60 57 3
Salix energy improvements 1,210 5 14 -9
E-job planning 86 0 0 0
Covid-19 0 0 36 -36
NHS Capital Funding 5,286 136 239 -103
Veteran's facility 3,000 0 0 0
Donated medical equipment 100 0 0 0
Total Capital Funding (NHS & Donated) 8,386 136 239 -103
Capital Programme 2020-
72