67
Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175 AD HOC REPORT Consortium of INCDPM MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175 AD HOC REPORT

MONITORING THE ENVIRONMENTAL IMPACT OF … · 3. prof.univ.dr.ing. Iulian Gabriel BÎRSAN ... Marin POPA 91. tehn. ... 100. pescar Marcel TIRIPA 101. pescar Petrică CRISTEA

Embed Size (px)

Citation preview

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM

MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING

THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER

BETWEEN CALARASI AND BRAILA,

KM 375-175

AD HOC REPORT

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 2

CARRIED OUT BY:

1. dr.ing. DEÁK György – CS I

2. mat. Alexandru PETRESCU – CS II

3. prof.univ.dr.ing. Iulian Gabriel BÎRSAN

4. dr.ing. Mihai LESNIC – CS I

5. dr. ing. Dan COCIORVA – CS II

6. dr. ing. George POTERAŞ – CS I

7. dr.ing. Ioan BOSOANCĂ

8. biol. Jozsef SZABO

9. dr.ing. Gina GHIŢĂ – CS II

10. dr. chim. Adriana BORŞ – CS II

11. dr. biol. Adrian IONAŞCU – CS III

12. dr. biol. Florica MARINESCU – CS III

13. dr.ing. Mihaela ILIE – CS III

14. prof. univ. ing. dipl. Helmut HABERSACK

15. dr. Falka Istvan

16. dr. ZAHARIA Tania

17. ecolog AMBRUS Laszlo

18. prof. dr. ing. Gh. Viorel UNGUREANU

19. dr. mat. Theodor GHINDĂ – CS I

20. dr. ing. Cristina MARIA - CS I

21. biochim. Magdalena CHIRIAC – CS I

22. ing. Ileana Mîţiu - CSI

23. ing. Marius RAISCHI – CS III

24. biol. Alina TRENTEA – CS III

25. dr. ing. Lucian LASLO – CS III

26. chim. Petra IONESCU – CS III

27. chim. Monica Violeta RADU – CS III

28. ecolog MIHOLCSA Tamas

29. ing. Bianca PETCULESCU – CS III

30. ing. Ana Maria ANGHEL - CS III

31. ing. Alexandru IVANOV - CS

32. Georgiana TĂNASE - CS

33. Robert CSERGŐ

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 3

34. geogr. Bogdan URITESCU – ACS

35. geogr. Nicu CIOBOTARU - ACS

36. ing. Larisa BODEA – ACS

37. ing. Carmen TOCIU - CS III

38. dr. ing. Alin Marius BÂDILIŢĂ - CS

39. ing. Georgeta TUDOR - CS

40. fiz. Georgiana GRIGORAŞ - CS III

41. programator Cristinel GRIGORAŞ

42. ing. Constantin CÎRSTINOIU - ACS

43. geogr. Nicu Ciobotaru - ACS

44. geogr. Alexandru Paul MANOLIU - ACS

45. chim. Carmen MUNTEANU - CS III

46. ecolog Mariana MINCU - CS III

47. dr. ing. Mihaela MÎŢIU - ACS

48. ing. Simona RAISCHI - ACS

49. biol. Ioana SAVIN – ACS

50. biol. Cristina CIMPOERU - ACS

51. ecolog Ecaterina MARCU – ACS

52. ecolog Cornelia LUNGU – ACS

53. ing. Marius OLTEANU - ACS

54. dr. ing. Andreea Mihaela MONCEA - CS

55. dr. ing. Ana Maria PANAIT - ACS

56. dr. ing. Diana DUMITRU - ACS

57. ing. Mădălin SILION - ACS

58. ing. Liviu IANUŞ - ACS

59. ecolog Tiberius DĂNĂLACHE - ACS

60. ing. Ştefan ZAMFIR - ACS

61. ing. Gabriel BADEA - ACS

62. Alexandru Adrian CHINAN - ACS

63. ing. Alexandru CRISTEA - ACS

64. Decebal Stelian CORLĂU - ACS

65. biol. Cecilia ŞERBAN

66. ing. Luiza FLOREA

67. ing. Irina Elena Ciobotaru - ACS

68. dr. biol. Marian TUDOR

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 4

69. ing. Constantin Theodor CONSTANTINESCU - ACS

70. tehn. Sergiu SĂNDICĂ

71. tehn. Corneliu VASILE

72. tehn. Emil NEAGU

73. tehn. Traian PÂRVULESCU

74. tehn. Stelian NEAGU

75. tehn. Angela GÎDEA

76. tehn. Elena BARBU

77. tehn. Paula CATANĂ

78. tehn. Tina ZANFIR

79. tehn. Georgeta MĂNESCU

80. ing. Tudor IONESCU

81. tehn. Iulian NEAGOE

82. tehn. Marian CHINAN

83. tehn. Andrei Paul EMINOVICI

84. tehn. Justinian NACU

85. tehn. Mihai GABURĂ

86. tehn. Adrian Nicolae FRONESCU

87. tehn. Nicolaie MARIN

88. tehn. Tinel GRIGORE

89. tehn. Marius George VISALON

90. tehn. Marin POPA

91. tehn. Gabriel CORNĂŢEANU

92. pescar Sandu MUNTEANU

93. pescar Marian EFTIMIE

94. pescar George MUNTEANU

95. pescar Marian TURTURICĂ

96. pescar Marian MARIN

97. pescar Silviu GREBLĂ

98. pescar Gheorghe LINTARU

99. pescar Andrei LINTARU

100. pescar Marcel TIRIPA

101. pescar Petrică CRISTEA

102. pescar Ghiţă GHEORGHE

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 2

CONTENT

1. INTRODUCTION ........................................................................................... 3

2. STATUS OF THE ACTIVITIES .............................................................................. 6

3. MONITORING RESULTS FOR BIOTIC AND ABIOTIC PARAMETERS .................................... 9

3.1. Air quality monitoring ............................................................................... 9

3.2. Noise level monitoring ............................................................................... 9

3.3. Soil quality monitoring ............................................................................. 10

3.4. Water quality and sediment monitoring ........................................................ 11

3.5. Aquatic flora and fauna monitoring ............................................................. 13

3.6. Avifauna, terrestrial flora and Natura 2000 sites monitoring .............................. 14

3.6.1. Avifauna .......................................................................................... 14

3.6.2. Terrestrial flora ................................................................................. 16

3.6.3. Natura 2000 Sites ............................................................................... 17

3.7. HYDROMORPHOLOGICAL MONITORING .......................................................... 18

3.8. Ichtyofauna monitoring ............................................................................ 31

4. BUILDING SITE ACTIVITIES MONITORING ............................................................. 45

5. STATE OF THE 3D NUMERICAL MODELING ........................................................... 46

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 3

1. INTRODUCTION

This Ad-Hoc Report is a summary of the monitoring activities of the project "Monitoring

the environmental impact of the works regarding the improving of the navigation conditions on

the Danube River between Calarasi and Braila, km 375 -175" and includes:

status of the monitoring activities for each critical point and analyze the status and

evolution of environmental factors;

numerical modeling stage;

interdisciplinary and integrated analysis of the monitoring program results to

estimate the damage degree of the evaluated ecosystems (correlation between the

biotic and abiotic parameters).

Critical points where monitoring was carried out environmental factors are schematically shown:

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 4

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 5

In this report are presented the results obtained from specific environmental objectives

monitoring activity:

- air

- noise

- soil

- water and sediment

- aquatic flora and fauna

- avifauna, terrestrial flora and Natura 2000

- hydromorphological parameters

- ichthyofauna

- building site activity

Also, in the report is presented the stage of 3D modeling.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 6

2. STATUS OF THE ACTIVITIES

Monitoring activities conducted and presented in this report were carried out in two

phases: the preconstruction phase (April - August 2011) and the construction phase (August 2011

- December 2013).

In preconstruction phase monitoring were carried out specific objectives to characterize

the reference state prior hydrotechnical works starting.

Monitoring frequencies for each critical point in the preconstruction phase are presented

briefly in the following table:

Table 2.1. Preconstruction stage - monitoring objectives – frequencies with differences in Critical Points

MONITORING OBJECTIVES

Main Critical Points

Secondary Critical Points

01 02 10 03A 03B 04A 04B 07

A. AIR 1* 1 1 1 1 1 1 1

B. NOISE M M M M M M M M

C. SOIL 2* 2 2 2 2 2 2 2

D. HIDROMORPHOLOGY

Water level C C C Q Q Q Q Q

Water velocity M M M Q Q Q Q Q

Turbidity C C C Q Q Q Q Q

2D bathymetric elevation Q Q Q Q Q Q Q Q

3D bathymetric elevation Q Q Q Q Q Q Q Q

E. WATER QUALITY M M M S S S S S

SEDIMENTS M M M S S S S S

F.

AQUATIC FLORA 1 1 1 1 1 1 1 1

AQUATIC FAUNA 1 1 1 1 1 1 1 1

F. is STURGEONS AND BARBELL

Two seasons /

year Two seasons / year

(Feb, Mar, Apr, May/Aug, Sep, Oct, Nov, Dec)

(Feb, Mar, Apr, May/Aug, Sep, Oct, Nov, Dec)

F. i OTHER FISH SPECIES

Annually Annually

(Apr, May, July, Aug, Sep)

(Apr, May, July, Aug, Sep)

G. TERRESTRIAL FLORA 1 1 1 1 1 1 1 1

TERRESTRIAL FAUNA 1 1 1 1 1 1 1 1

H. NATURA 2000 SITES C C C C C C C C

I. BUILDING SITE ACTIVITY M M - - - - - -

NOTE: M - monthly, S – semester, Q – quarterly, C-continuously, X* – no. investigation/preconstruction

During the construction phase, conducting the monitoring activities was correlated with

construction site activities, monitoring frequencies of environmental objectives are summarized

in Table 2.2.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 7

Table 2.2 – Construction stage – general presentation of the monitoring objectives – frequencies with

differences in Critical Points

MONITORING OBJECTIVES

CRITICAL POINTS

Main Critical Points Secondary Critical

Points

01 02 10 03A 03B 04A 04B 07

A. AIR M M M Q Q Q Q Q

B. NOISE M M M Q Q Q Q Q

C. SOIL S S S Q Q Q Q Q

D. HIDROMORPHOLOGY

Water level C C Q Q Q Q Q Q

Water velocity CV M M Q Q Q Q Q

Turbidity C C C Q Q Q Q Q

2D bathymetric elevation

M M M Q Q Q Q Q

3D bathymetric elevation

Q Q Q Not the case

E. WATER QUALITY M M M S S S S S

SEDIMENTS M M M S S S S S

F.

AQUATIC FLORA July Q Q Q Q Q

AQUATIC FAUNA S Q Q Q Q Q

F. is STURGEONS AND BARBELL

STURGEON Two seasons / year

(February - May / August - December)

Two seasons / year (February - May / August -

December)

BARBELL One season/year

April- May ( breeding season) One season/year

April- May ( breeding season)

F. i OTHER FISH SPECIES Annually

(April - May, July - September)

Annually (April - May, July - September)

G.

TERRESTRIAL FLORĂ Annually in July Annually in July

TERRESTRIAL FAUNĂ / AVIFAUNĂ Annually

(April - June, September - October, January)

Annually (April - June, September -

October, January)

H. NATURA 2000 SITES

SCI

IHTIOFAUNĂ Annually

(April – May, July - September)

Annually (April – May, July - September)

AQUATIC FLORĂ

July Q Q Q Q Q

AQUATIC FAUNĂ

S Q Q Q Q Q

TERRESTRIAL FLORĂ

Annually in July Annually in July

TERRESTRIAL FAUNĂ

Annually (April - June, September -

Octomber, Ianuary)

Annually (April - June, September -

Octomber, Ianuary)

SPA AVIFAUNĂ Annually

(April - June, September - Octomber, Ianuary)

Annually (April - June, September -

Octomber, Ianuary)

I. BUILDING SITE ACTIVITY M M M Not the case

J. 3D NUMERICAL MODELING M

NOTE: CV – quasi-continuous M- monthly Q– quarterly S – semester C- continuously

In table 2.3 are presented the main parameters for each specific monitoring objective

according to the Specifications.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 8

Table2.3 – Monitoring parameters for each environmental objective

MONITORING OBJECTIVES

PARAMETERS

AIR Suspended particles; nitrogen oxides, lead oxides, carbon oxide and carbon

dioxide.

NOISE Noise level for natural state (with no vessel traffic) and for periods with naval

traffic.

SOIL presence/absence of lumbricides in working area; mineral salts; humic acids;

organic matter; physical and mechanical characteristics (granulometry, porosity, texture).

HYDROMORPHOLOGY

water quantity (flow rate – water level and velocity; sections profiles – bathymetry); water flow dynamics;

riverbed morphology;

suspended transported sediments - turbidity / correlated with gravimetrical determinations, dragged sediments flow rate, sediments granulometry, suspended matter granulometry.

WATER QUALITY

Water – indicators from Order 161/2006 – ecological state, and from Government Decision 1038/2010 (chemical state);

Sediments – metals (As, Cu, Zn, total Cr, Cd, Hg, Ni, Pb); PAH, PCB and organochlorine pesticides.

IHTIOFAUNA

Sturgeons, barbell, other species;

Population characterization (structure on age, size classes) distribution, abundance, habitats preferences; reproductive potential; migration periods for breeding, wintering, feeding; breeding habitats characterization; habitats mapping; monitoring and simulation for migration routes;

Performing transversal profiles through determined habitats;

Water velocity monitoring on profiles;

benthos monitoring

Didson camera tracking in bottom sill area at CP01 - Bala.

AQUATIC FLORA AND FAUNĂ

Flora – phytoplankton: composition, abundance, biomass, saprobe index, Simpson index, multimetric index;

- Macrophytes: composition, abundance, biomass;

Fauna – benthic invertebrates: taxonomic composition, numerical abundance, biomass, Shannon Wiener index, saprobe index

TERRESTRIAL FLORA AND FAUNĂ

Flora – Flora - floristic mapping; list of species, species richness, bushes type, vegetation coverage degree, the average height of vegetation - hydrophytes/macrophytes ratio; number of species, invasive plant.

Avifauna – by night and daytime recordings.

NATURA 2000 SITES biodiversity monitoring: ichtyofauna; aquatic flora and fauna; terrestrial flora

and fauna; avifauna.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 9

3. MONITORING RESULTS FOR BIOTIC AND ABIOTIC PARAMETERS

3.1. Air quality monitoring

From analysis of air quality monitoring results for main and secondary critical points it can

concludes that:

measured values for "NOx" indicator do not exceed the critical level of 30μg/m3, the

maximum value of 7,5 μg /m3 was below the lower assessment threshold;

measured values for "CO" indicator do not exceed the limit of 10mg/m3, the maximum

determined value was 0,45 mg/m3, much below the lower assessment threshold;

measured values for "TSP" indicator do not exceed the limit value of 0,05 mg/m3, the

maximum determined value was 0,03 mg/m3 , in the lower assessment threshold domain

of 0,025 mg/m3;

measured values for "Pb" indicator do not exceed the limit of 0,5 µg /m3 , the maximum

determined value was 2,1 ng/m3, much below the lower assessment threshold of

0,25µg/m3, steady value for all three critical points and within the range of specific

values for natural background;

measured values for "CO2" indicator have values of 0,04% and within the range of specific

values for natural background for air, constant value for all three critical points;

Contaminant concentrations measured value is correlated with the intensity of the

activities from the building site;

there is no significant impact on the environmental factor "air" due to construction

activities.

During the monitoring campaign of air quality indicators were observed both visually and

by determinations with combustion gas analyzer Testo 350XL, emissions above the admissible

limits (especially for CO and TSP) on some equipments working on site (mainly at floating

cranes).

The situation was corrected by manufacturer, replacing this equipment with other similar less

polluting.

3.2. Noise level monitoring

In order to determine the intensity of noise levels have been carried out measurement

campaigns in the main critical points as well as in the secondary critical points.

Equipment used during the works execution, which have been sources of noise during the

measurements in three main critical points are as follows: boats, barges, dredgers, excavators,

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 10

floating platforms, floating cranes, tug-boats, motor boats, other equipment (generators,

chainsaws, geotextile mattresses rewinder).

Analyzing the results obtained during the noise monitoring period, following conclusions

are:

• measured values do not exceed the maximum admissible level of 75(dB);

• measured noise level is correlated with the intensity of activities from the construction site;

in the main critical points CP01, CP02 and CP10 area have been observed significant variations of

noise level depending on the type of machinery which worked in the determination period.

3.3. Soil quality monitoring

In the analyzed period, the monitoring of soil quality in the main critical points was

conducted in 6 campaigns for soil sampling, 2 campaigns during the preconstruction period and 4

campaigns during construction stage. In this period were collected sufficiently large number of

soil samples that have allowed establishing the reference state for soil quality, before works

execution and the evolution of the monitored parameters in execution stage of hydrotechnical

construction.

The results of Physical-chemical analysis properties of collected soil samples revealed the

following:

heavy metals content is below normal value in soils, much below the alert and

intervention thresholds for sensitive utilization types imposed by Order 756/1997;

humus content value ranges from <1% for soils very poor in humus (sandy soils) to values

above 10% characteristic for soils rich in humus (sandy - clayey soils).

Physical-mechanical properties for soil samples

In order to define the texture of the soil were conducted laboratory analysis by which

was determined the percentage quantities of sand, dust, and clay. The results of soil samples

taken from the main and secondary critical points highlighted a soil texture from coarse sandy to

medium coarse sandy-clayey.

Soil quality monitoring during the construction phase reveals that the values of the

analyzed indicators in this stage are comparable to those obtained in the preconstruction phase

and are below the normal values required by Order 756/1997. Environmental impact due to

hydrotechnical construction in the main critical points on the environmental factor "SOIL" is

negligible.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 11

3.4. Water quality and sediment monitoring

From the results analysis of water and sediment quality monitoring for main and secondary

critical points, can conclude the following:

Monitored indicators for water quality assessment evolves specimen, predominantly

between class I and class III, expected result, moreover, in the case of a river with a

large catchment area and characterized by large fluctuations of flow.

There is no correlation of quality indicators change over time periods of hydrotechnical

works due to high heterogeneity of sediment samples analyzed. High heterogeneity is due

to level differences in the Danube River. The evolution of quality indicators is consistent

with the historical data retrieved in TNMN.

Organic indicators, as nutrients and certain metals (iron, manganese), have varied

independently from construction works performed, being influenced by external sources

of monitored sector, precipitation regime, temperature and flow.

The variation of indicators is not due to hydrotechnical constructions, but actual

ecological status of the Danube.

Ecological status, in terms of Physical-chemical elements support for the biological

elements, is between good to moderate, assessment which is in range of historical data.

In order to achieve an integrated analysis of the monitoring results evaluation, INCDPM has

defined two complex parameters, relatively easy to use, in the form of Eco Index for water EIA

and sediment EIS. These Eco Index allow an integrated estimation of chemical pressures on

ecosystems, spatial and temporal evolution observation of these pressures and abiotic and biotic

factors correlation.

An global analysis of integrated environmental indicators (Eco Index) highlights that

hydrotehnical works made during the period under consideration have not constituted a factor of

stress in terms of abiotic impact on ecosystem. Although there were occasional high values of

abiotic stress factors, their short duration of action minimized the potential impact of

ecosystem disturbance, not being identified the exact sources.

Following the assessment of water quality and sediment indicators, can be observed a

pronounced natural dynamics, demonstrating both the complexity of the ecosystem, and the

power of biogenesis adaptation.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 12

Thus, from the integrated analysis of environmental factors water and sediment, correlated

with hydrological conditions and environmental risk, it result that, during the construction

phase, the general situation is characterized by the absence of additional environmental

pressures compared to those from the reference period (pre-construction), for the pollutants

monitored on 375 km Calarasi - 175 km Braila section.

Regarding the comparative statistical analysis of water quality and sediment data collected

during the construction phase, can conclude the following:

Monitored quality indicators presented a variability mainly dependent on sampling

moment (season / off season) and less on the sampling location (RB, CN, LB).

The values of statistical parameters calculated for data sets (e.g. minimum value,

average value, maximum value, standard deviation, and so on) shows that the data are

uniformly distributed on the variation domain (min-max) and there is no systematic

errors or outliers values that exceed the control and alert limits values (upper and lower)

of the monitored indicators.

About 75% of monitored water quality indicators are continuously ranges under the

specific conditions for quality class I (e.g. orthophosphate, filterable residue dried at

1050C, sulfates, total chromium, copper, zinc, arsenic, selenium, cadmium, nickel and

detergents) and about 70% of monitored quality indicators for sediment ranges in quality

standards stipulated by the current legislation (e.g. arsenic, cadmium, total chromium,

lead and sum of PAH).

Less than 5% of the monitored quality indicators for water and about 10% of those

monitored for sediment records frequent exceeding of quality standards, that are

systematically higher with 2 from the mean value (e.g. COD-Cr, dissolved oxygen,

nitrites, total iron, magnesium, total phenols for water and nickel for sediments).

About 22% of monitored water quality indicators and about 20% of those monitored for

sediments records accidentally exceeding of quality standards, as confirmed by test 3

that indicates with a 99% probability that these exceeding are accidentally (e.g. BOD5,

COD-Mn, ammonia, nitrate, total nitrogen, total phosphorus, chlorophyll-a, chloride,

calcium, sodium, barium, mercury, cobalt, lead, total manganese, AOX for water,

copper, mercury, zinc and sum-PCB for sediments).

Most indicators for which was registered frequent exceeding of quality standards are

specific for municipal wastewater inadequately treated and originate most likely from

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 13

punctual and/or diffuse pollution upstream from the investigated section (km 375 - km

175).

3.5. Aquatic flora and fauna monitoring

Phytoplancton

In the monitored critical points, the analysis of the multimetric index values for

phytoplankton (as HG 80/2011) showed that during the construction phase, the ecological status

of the Danube water was between very good and good, the general situation being characterized

by the absence of anthropogenic pressures in addition to the preconstruction phase. Quality

indicators of the phytoplankton varied mainly depending on the time of sampling, following the

seasonal dynamics of the development of the main groups of algae.

Macrophytes

During the monitoring period macrophytes were poorly represented. On the banks of the

Danube river, in all critical points were identified four species of macrophytes belonging to two

classes: Liliopsida and Magnoliopsida. In sampling sections where macrophytes were present,

the total biomass varied between 9.40 g/m2 - CP 01 (right bank) up to 90.60 g/m2 - CP 02 (left

bank). There were no significant differences in the values of the total biomass of the

macrophytes in the construction phase comparing preconstruction phase.

Aquatic macroinvertebrates

The mean values of the Shannon-Wiener index, diversity indicator of macroinvertebrates

species, obtained during the construction period were slightly higher or close to the values

obtained in the preconstruction phase, species of macroinvertebrates unaffected. Local and

temporary, related with hydraulic works, it can record an impairment of the ecological status:

substrate disturbance, increased turbidity, loss of biodiversity by the physical removal of

specimens.

Based on saprobic index values of the benthic macroinvertebrates for assess the ecological

status of water bodies (as HG 80/2011), it can be appreciated that during construction phase, in

the investigated critical points the ecological status of the Danube water was good, the general

situation being characterized by the absence of additional sources of pollution with organic

substances.

The multiple correlations of the biotic parameters (phytoplankton) and the abiotic

factors were performed using a statistical method for multi-dimensional regression. All observed

variables considered (total biomass of phytoplankton, diversity Simpson index and multimetric

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 14

index) depend systematic and significant on the abiotic parameters (temperature, turbidity,

water velocity and BOD5).

Correlations conducted revealed some specimen and cumulative effects of biotic and abiotic

parameters, such as:

proportional dependence of the indices of phytoplankton growth (total biomass and

chlorophyll "a");

positive influence that temperature has on all biotic parameters analyzed (total biomass

of phytoplankton, diversity Simpson index and multimetric index);

negative influence that turbidity has of all biotic parameters analyzed (total biomass,

diversity Simpson index and multimetric index);

negative influence that water velocity has on phytoplankton biomass;

positive influence that organic load (BOD5) has of the total biomass of phytoplankton and

multimetric index and the negative impact that they have on the organic loading and

diversity Simpson index.

3.6. Avifauna, terrestrial flora and Natura 2000 sites monitoring

3.6.1. Avifauna

During the monitoring period, determinations were carried out on the critical points in

different habitats. Based on these results, birds density was calculated on three dominant

habitats: Danubian forests of white willow (Salix alba) with Rubus caesius; poplar plantations;

open habitats (including meadows, razor cuts, very young plantations).

Preconstruction phase overlapped spring migration season and nesting birds. The frequency of

bird species identified in the field (April-August 2011) was represented as follows: the total

number of bird species identified- 58% were rare (less than 10 exemplary), 32% frequently

encountered and 10% common (over 100 exemplary).

The highest diversity was recorded in CP04 due to the shape of habitat, formed of poplar

plantation and strips of white willow Danubian communities.

The habitat is not fragmented with anthropic communities. The CP01, CP02, CP07 corresponding

to Danubian white willow forest habitats, Pontic Danubian forests and poplar plantations,

reported values less diverse compared to CP04, because, from the analysis carried out on the

ground, less vegetation was observed and the presence of anthropic communities. The lowest

values of Shannon diversity index were recorded in critical points CP03 and CP10, having as

habitat type poplar plantations and Danubian forests of white willow, but they are not over the

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 15

entire surface of the critical point, due to anthropic communities and sandy areas temporarily

flooded and with no vegetation.

Bird species listed are not affected by hydrotehnical works, because they do not nest and

feed in areas where the works take place, their areas being much larger. The impact of short-

term construction work can only be local and insignificant.

The frequency of bird species identified in the field (April-August 2011) was the

following: of the total number bird species identified, 58% were rarely met (below 10

exemplary), frequently encountered 32% and 10% common (over 100 exemplary).

Negative changes in the number and effectives of ring species/ observed are not caused

by the work done, because in the autumn 2012 the low number of birds was an immediate result

of the drought phenomena.

Spring Migration:

- the area between CP01 and CP10 is an important area of spring migration and seabirds

nesting;

- CP02 is the area with the highest richness of species and with only colony of cormorants

(Epuraşu Island);

- in CP01 are found bank swallow and bee-eaters colonies;

- over 100 species of birds were identified (over 3000 exemplary), including 36 protected

species.

Autumn migration:

- most abundant species are: the great tit (Parus major), blue tit (Parus caeruleus), the

common kingfisher (Alcedo atthis), chaffinch (Fringilla coelebs), willow warbler

(Phylloscopus trochilus) and spotted flycatcher (Muscicapa striata);

- singing species are predominates;

- islets are used as overnight places and arboretum and bushes as resting and feeding

places;

- in 2012 fewer species of birds were identified compared to 2011 due to low water level

and prolonged drought in 2012.

Wintering:

- the predominant species during the winter as number of specimens: great cormorants

(Phalacrocorax carbo) - 1664 specimens; wild ducks (Anas platyrhynchos) – 7763

specimens; rooks (Corvus frugilegus) – 9150 specimens ; the jackdaw (Corvus monedula) –

2000 specimens;

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 16

- the area between CP01 and CP10 is an important wintering area for seabirds: dalmatian

Pelican (Pelecanus crispus), ducks (Anas sp.), pygmy cormorants (Phalacrocorax

pygmaeus); it can be noticed the low number of diving ducks (Aythia sp., Bucephala sp.).

3.6.2. Terrestrial flora

The terrestrial fauna assessment performed in the preconstruction phase indicated the

environmental state, unaffected by the planned works. In future years the changes of

biodiversity in the area potentially affected will be compared with these conditions.

In the studied areas of the Danube predominates are the Canadian poplar plantations and

semi-natural habitats (floodplain forests predominate white willow and poplar), limited to

narrow strips in riparian zones, temporarily flooded and which are in advanced state of

degradation, with invasive alohtone species.

Because of the relatively small occupied area and abundance of invasive species, these

seminatural habitats present a low conservation value.

Among the critical points, CP02 – Epuraşu island represents the most important one, in

terms of biodiversity. Danubian floodplain forests of willow and poplar are presented in

relatively good state of preservation. It can also be notice the existence of a temporary lake

inside the island, which is a potential habitat for a number of hydrophilic plant species (their

absence could be explained because of the summer drought). Monitoring results in the main

critical points are centralized in the following table:

Tabel 3.1 – Habitat types in the main critical points

Critical point

Habitats Location

CP01

Danubian forests of white willow (Salix alba) and white poplar (Populus alba)

shore

Canadian poplar plantations inland

Anthropogenic vegetation shore

Sandy areas devoid of vegetation, partially flooded shore

CP02

Danubian white poplar forests (Populus alba) with Rubus caesius Island Epuraşu shore Danubian forests of white willow (Salix alba) with Rubus caesius

Sandy areas with very poor vegetation (Xanthium sp) shore

CP10

Canadian poplar plantations white willow inland, shore

Danubian forests of white willow (Salix alba) with Rubus caesius shore

Anthropogenic vegetation interleaved

The diversity decreased in 2013 compared to 2012, especially among herbaceous plants

and trees or shrubs. Also, there were some new invasive species, unidentified in 2012. The

changes are primarily due to fluctuating water in the areas analyzed and frequent flooding.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 17

Considering the fact that the works take place on the water and on the banks, we can say

that they do not negatively affect the terrestrial flora. Vegetation may be disturbed only on

certain segments of the riparian zone and adjacent areas. Because of the degraded condition of

habitats, namely strong anthropogenic impact in the area potentially affected, planned works

will not affect the conservation status of habitats with high conservation value of protected

areas. Danubian floodplain forests of willow and poplar (Populus alba and Salix galleries alba)

are not found in workstations, where there are construction works.

3.6.3. Natura 2000 Sites

Critical points in the project area are included in the following sites of the European

ecological network Natura 2000:

Sites of Community Importance SCI):

o ROSCI0006 Natural Park „Balta Mică a Brăilei” – include the critical point CP10

o ROSCI0022 „Canaralele Dunării” – including the critical points CP01, CP02, CP03,

CP04 and the adjacent CP07.

Special Protection Areas (SPA):

o ROSPA0005 „Balta Mică a Brăilei” - including the critical point CP10

o ROSPA0039 „Dunăre Ostroave” - including the critical points CP01, CP02, CP03,

CP04.

During the monitoring period were observed following significant aspects:

In the interest area, there were not identified protected species of terrestrial flora.

Terrestrial flora is composed by forest (especially Danube alluvial forests of willow and

white poplar white, groves - Natura 2000 habitat: 92A0 Salix alba and Populus alba

galleries - Canadian poplar plantations) and meadows often in advanced stages of

degradation, due to the high abundance of invasive local species;

Riparian areas are in general sandy areas, flooded temporarily; in some cases, the flooded

areas are covered by willows;

Campaign of spring migration in 2012 for avifauna monitoring in critical points showed

that, compared to the same campaign in 2011, there were identified several species of

birds, but fewer specimens; the most representative of birds have been identified in CP07

and CP02,CP04 are the most complex areas from the point of view of avifauna biodiversity;

18- 27 species of protected birds were identified, reaching over 400 exemplary observed;

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 18

Site ROSPA0005 „Balta Mică a Brăilei” is an important area for some species of nesting

birds (3 species), for ducks and geese (during migration and wintering);

Site ROSPA0039 „Dunăre-Ostroave” is an area for nesting birds (14 species), for migratory

birds (7 species) and for wintering birds (2 species protected);

Among the fish species of community importance, were identified 9 species in ROSCI0006

and 9 species in ROSCI0022 that have low or medium vulnerability to hydro-technical

works.

3.7. HYDROMORPHOLOGICAL MONITORING

The hydrological measurement was mainly concentrated on the measurements of the

following elements:

Water flow;

Water level;

Water flow dynamics (water velocity);

Single-beam and multi-beam bathymetric measurements;

Flow and water level distribution; comparison to the historical data;

Monitoring in the automatic hydrometric stations

Water velocities monitoring activity made within 16 August- 15 December 2011, on the 10 main

transversal sections has led to the following qualitative information:

in section S1 the velocities are very low near the banks, areas where water depth is

slightly lower; in centre of the channel the velocities have values of almost 1 m/s

and doesn’t present a clear trend of vertical variation;

in section S2 at the entry on Bala branch, velocities values near banks are slightly

higher; in centre there are the highest velocities in relation to the others sections

(over 1 m/s in all monitoring campaigns);

in section S3 the highest velocities are near left bank, area where is drawn the

navigable channel; there are not high variations from a campaign to other;

in sections S4, located on Borcea, there are higher velocities in centre of the

riverbed and very low velocities near right bank;

in section S5 the values of velocities near banks don’t differ much compared to the

velocities from centre;

in sections S6, located on Epuraşu branch, there are lowest values of velocities –

below 0.5 m/s in all measurement campaigns;

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 19

in section S7, located after confluence, the values of velocities are very low near

right bank;

in section S18 – Caleia branch – the velocity in centre is higher than 1 m/s;

in section S19 – located on Danube – values of velocities near the 2 banks are

comparable with the values measured in centre of the section;

in section S20, located after confluence Danube-Caleia branch, there are low values

of velocities near the two banks.

Regarding the extreme and monthly average flow on the monitored sections between 16

December 2011 – 30 April 2012, are being emphasised- in relation to medium flows recorded in

the first 4 months of constructions- an increase of 10- 15% in the first month (16 Dec.2011- 15

Jan 2012) followed by monthly increases of flow rates, more significant in February and March,

followed in April by a relative stabilisation.

These changing tendencies of medium flows measured on sections are normal for this

final winter period and spring debut.

Similar conclusions can be noticed as well in the case of extreme levels and monthly

averages monitored within 16 December- 30 April 2012, thing that can be explained through the

already existent correlations between flow and level on a transversal section, materialised

correlations through limnimetrical keys.

The comparisons to the historical data made in the hydrometric stations at the entrance

within the sector of interest- Călăraşi-Chiciu- for flow rates and the exit from the sector of

interest –Brăila- for levels, reveal a deficit of flow and lower levels in January and April 2012

compared to maximum and multiannual average values respectively higher flows and levels in

February and March, compared to maximum and multiannual averages.

The processing of the informational volume (2D and 3D) of the bathymetric

measurements, repeated with a monthly frequency on the 10 stations located in the area of the

main critical points has not noticed major changes for the thalweg - erosion or deposition-

compared to preconstruction phase, respectively to the measurements made in the first 4

months of the construction period. The small differences can be due to ADV method accuracy,

although the ice in January, February and March had an obvious impact on shores

hydromorphology.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 20

Turbidity values distributions measured on the main 10 sections are similar as values and

shapes to the ones measured in the first 4 months of the construction phase.

Regarding the water flow velocities on the 10 main transversal sections near the shores

and on the centre for 3 depths, it can be noted that there are no significant changes compared

to the data presented during 16 August- 15 December 2011.

The differences between the velocity values, measured in the 2 periods of 4 months

each, are due to different flow rates recorded in the 2 time periods. For some of the monitoring

sections, several transversal profiles are presented into the report, differing either by the date

on which have been measured either through the location or geometry slightly different, but

located in the area of the respective sections.

As for the flows on the all sections monitored within 01 May- 31 August 2012 there was a

general tendency with high flows and comparable in the first 2 months (May- June 2012) and an

accentuated decrease of the flows in July and August 2012. The flows from July 2012 are slightly

lower than the ones recorded during the preconstruction (MEP).

Similar conclusions can be noticed for extreme levels and monthly averages, monitored

during 01 May- 31 August 2012, explained by the direct correlations existent between flow and

level on a transversal section, correlations materialised by limnimetrical keys. Therefore, it can

point out a trend of water level increasing in May and June 2012, then a general decreasing

tendency in July and August. Compared to the MEP the levels from July 2012 are slightly lower.

Regarding the variation of relative and absolute level of water these had a maximum

level at the beginning of June 2012, after which registered an almost continuous decreases of

levels, with some parts of constant level. The total deviation within this period was about 5 m.

This variation of water levels during the 4 months monitoring period is common- with minimum

differences- for all automatic monitoring stations.

Regarding the water flow velocities on the 10 main transversal sections near the banks

and on the centre for 3 depths, it can be noted that there are no significant changes to the data

presented during August 2011-April 2012. The differences between the velocity values,

measured in the 3 time periods, 4 months each in construction stage, are due to different flow

rates recorded in the 3 time periods. For some of the monitoring sections more transversal

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 21

profiles are presented into the report, differing either through the data on which have been

measured or through the location or geometry slightly different, but located in the area of the

respective sections.

Regarding the flow and level distribution, from the comparison with the historical data

from the hydrometric stations at the entrance in the sector of interest- sector Călăraşi-Chiciu-

for flows and the exit from the sector of interest- sector Brăila- for levels, it must be notice

that the average flows in the period May 2012 - August 2012 reveal a major deficit (about 1500

m3/s) compared to multiannual averages of the minimum flows for May, July and August, while

for June, the average flow in 2012 is higher with 300 m3/s compared to the average of

multiannual minimum flows. Also, during the months 9-12 of the construction period, in Braila

hydrometric station the monthly minimum relative levels were situated on an inferior level, with

at most 125 cm - in July 2012- compared to the multiannual averages (90 years) of the monthly

minimum levels. It can be concluded that 2012 medium levels are lower than multiannual ones,

excepting June, when these levels become comparable to the multiannual ones.

In months 9-12 of the construction phase 2D and 3D bathymetric measurements have

been carried out, mainly in the sectors in which low water level in the previous months did not

allowed the bathymetric measurements: Caragheroghe sandbank, existent submersed structures

from Bala and Epurasu branches. It can be noted that are not reveal major changes of the

riverbed configuration. There are changes even of several centimetres of thalweg quotas, but

the representation scale does not allow their highlighting.

Regarding the distribution of turbidity values measured in the main 10 section it can be

noticed that the average values on the sections were relatively constant, without variations

higher than 20%; turbidity higher values have been recorded in months 9-10 of the construction

period, period with higher flow rates (May-June 2012). Referring to turbidity variation on each

section, cannot emphasize clear correlations, not near shores nor on the centre of cross

sections, the turbidity values being very similar on the same section. The maximum value for

turbidity- 80 NTU has been recorded early in June; in the rest of time turbidity values had

fluctuations between 5 NTU and 25 NTU.

From the analysis of data regarding dragged sediments it can be concluded:

The coefficient of dragged flow from the suspension mass flows increases with water flow

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 22

The average percentage of dragged sediment flow compared to the corresponding one of

the mass suspension loading ranges between 0,2- 3,23%, with an average of 1,72%, values

that are within those from specialized literature.

Regarding the flow rate for all monitored sections during 01 September – 31 December 2012,

there was a general trend characterized by medium flow and a decrease of flow rates in

September 2012. Flow rates in September 2012 are lower than the flow recorded during the

preconstruction stage (MEP). Flow rates in October, November and December are higher than

those recorded during the preconstruction phase (MEP).

Similar conclusions can be noticed for average monthly absolute levels, explainable through

the direct correlations existent between flow and level, on a transversal section, correlations

materialised through limnimetrical keys. Therefore, it can point out a decreasing tendency of

water level in September 2012 then a general increase tendency in October, November and

December. Compared to MEP the levels from September 2012 are lower.

Taking into account that the construction phase started in September 2011, there has

been the opportunity to compare the hydrological characteristics - flows elapsed during the

period autumn - early winter (September-December) in 2011 and 2012 respectively. Thus, on all

sections of the main critical points, except of September, flows in 2012 were higher than flows

in 2011 in those months.

ADCP measurements of flow velocities made in months 13-16 of construction period in

the main sections of the critical points and secondary points have been processed, resulting in –

from raw data recorded - distributions values of the flow rate on the main component (in the

direction of water flow on the Danube on those cross sections).

For some of the monitoring sections are presented in the report with several transversal

profiles, with the distribution of velocities that differ either by the date they have been

measured, either by location or geometry slightly different, but located in the respective

sections.

In order to determine the typical behaviour of the Danube - required for 3D

hydrodynamic modeling activity - it is necessary to process long series of data on the

distribution of the flow and level at last 30 years. Delft3D model involves flow data series

processing for a hydrometric station located upstream from the modeling sector and the

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 23

processing of data series corresponding to the levels for a hydrometric station located

downstream boundary of the modelled sector.

For that purpose, have been taken into account - hydrometric station in Calarasi-Chiciu

for flows and respectively - hydrometric station in Braila for levels. For these stations were

processed time series available and compared with the records from the period September 2012

- December 2012. Historical flow data were extracted from the paper "Ouvrage of Reference

Hydrologique du Danube 1921-2001", paper published in 2005 by Danube Commission.

As it can be seen from the presented graphs, the average flows in September 2012-

December 2012, which are recorded at Calarasi-Chiciu reveal a deficit (up to approx. 100 m3/s)

compared to the multi-annual average minimum flow for these months, more pronounced deficit

in September.

The long term evolution has been analyzed, compared to the years 1941-2001 and

compared with 2012, the monthly maximum water flow at Calarasi-Chiciu for September-

October-November-December 2012 characteristic for construction period. In this sense, it can

be concluded that the average flows of September to December 2012 are lower than the

multiannual - except for November, when these levels are comparable.

Regarding the relative water level variation - monitored in 10 automatic stations

installed by INCDPM, there is a general increasing trend since the beginning of the period, with

some fluctuations over time. Thus, in the period November 5 to 17 levels has increased by

almost 200 cm. The total difference of levels in four months period was of 3m. These trends of

variation of water levels within the 4 months of monitoring are common - with minimal

differences – to all automatic monitoring stations.

In the period of September to December 2012 multi-beam respectively single-beam 2D

and 3D bathymetric measurements have been conducted, according to the Specifications.

These measures have led to a thickening in areas of interest, namely in areas where

hydrotechical works will be performed in critical main points CP 01, CP 02 and CP 10. All these

measurements were processed and introduced into the bathymetric database, basis of which

hydrodynamic modeling activities is done.

In the construction phase of 13-16 months turbidity measurements were made both on 10

main sections and also in 10 secondary sections. All these measurements were made at depths of

0.5 m near the 2 banks and at 3 depths - 0.5 m, 1 m and 3 m in the centre of the cross section.

Regarding turbidity values distribution measured on the 10 main sections, it was found

that the average values of turbidity were relatively small on sections, without large variations.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 24

Regarding the variation of turbidity on each section can not reveal clear correlations or near the

banks nor in the center of the cross sections, turbidity values are very similar on the same

section. Turbidity values have varied between 2 NTU and 19 NTU. Maximum turbidity value –

about 19 NTU - was recorded at the end of the first decade of December.

Regarding the flow rates on all monitored sections from 1 January to 30 April 2013, there

was a general trend characterized by high flow rates especially in the months of early spring -

March and April 2013. Average monthly flows for the period of January to April 2013 are higher

than the average multiannual monthly flows for the period of 1941-2001. From the hydrological

point of view this time of year 2013 debut shows a typical trend compared to historical flows for

these months, but the values are much higher than the multiannual average recorded for the

period of comparison.

The figure below presents these findings by presenting average monthly flow variation in

Calarasi-Silistra station (border station located upstream of monitored sector) during January to

April for the 3 years since the start of the monitoring in the project.

Variatia debitului mediu lunar la s.h.Calarasi-Silistra

87067293

59305692

5986

7326

9167

12137

2000

3000

4000

5000

6000

7000

8000

9000

10000

11000

12000

13000

ian. feb. mart. apr.

Luna

Debit m

ediu

(m

3/s

)

medie 1941-2001

2011

2012

2013

From the presented data it can be seen that in the first 2 years it is highlight an atypical

behaviour (such as flow chart allure and as values) compared to historical flows.

Similar conclusions can be found regarding average monthly absolute levels, explained

by the direct correlations between flow and level, both in hydrographical station located in the

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 25

monitored area and on the monitored cross sections - correlations evidenced by limnimetric

keys. There is, therefore, highlighted a continuing increase in the water level during this period.

ADCP measurements of flow rates made in months 17-20 of construction period (January

2013 - April 2013) in the main sections of the critical points and secondary points have been

processed, resulting in – from raw data recorded with ADCP - distributions values of the flow

rate on the main component (in the flow direction of the Danube on those cross sections).

For the main monitoring sections are presented within the report several transversal

profiles with the distribution of velocities which highlight velocity variations on section

according to depth and distance from the banks. These representations have intended to

highlight mainly that the use of the maximum velocity indicator on section is completely

irrelevant to compare the rate of flow of the Danube with sturgeon critical velocity that climbs

on the water. In these sections large areas are emphasized, especially near the bottom of the

riverbed, areas where velocities are much lower compared to the maximum velocity on that

section.

In order to determine the typical behaviour of the Danube - required in the 3D

hydrodynamic modeling activity - it is necessary to process long series of data on the

distribution of the flows and levels on 30 years minimum. Delft3D model series involves

processing flow data at an upstream hydrometric station at the entrance of the modeled sector

and processing of data series corresponding to the levels for a hydrometric station located

downstream from the sector boundary.

For this purpose, were considered for flow hydrometric station in Calarasi-Chiciu and for

levels respectively - hydrometric station in Braila. For these stations there were processed

available time series and compared with records from the period January 2012 - April 2013.

Historical flow data were extracted from the paper "Ouvrage de Reference Hydrologique du

Danube 1921-2001", paper published in 2005 by the Danube Commission. Regarding the relative

water level variation - monitored at 10 automatic stations installed by INCDPM, it has had a

general continuous increase trend since the beginning of the period, with some fluctuations over

time.

In the period January - April 2013 there were conducted a multitude of bathymetric 2D

and 3D single beam measurements, accordingly to the provisions of Specifications. These

measurements lead to an update of the bathymetry in areas with high dynamics of the

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 26

deposition/ erosion processes, and on the other hand, thickening the information lacking in the

areas of interest, namely in particular in the areas where hydrotechnical works will be placed at

main critical points CP 01, CP 02 and CP 10. All these measurements were processed and

entered into the bathymetric database, which is used to perform all hydrodynamic modeling

activities.

In months 17-20 of the construction phase turbidity measurements were made both in

the 10 main sections and in the 10 secondary sections. All these measurements were made at

depths of 0.5 m near the 2 banks and 3 sets of depths - 0.5 m, 1 m and 3 m in the center of the

cross sections.

Regarding distributions turbidity values measured on the 10 main sections, it was found

that the average values of turbidity were relatively small in sections without presenting large

fluctuations. Regarding the variation of turbidity on each section can not reveal clear

correlations neither near the banks nor in the center of the cross sections, turbidity values are

very close on the same section. Turbidity values have varied between 2 NTU and 22 NTU. Higher

values of turbidity - over 20 NTU - were recorded during periods of high flows in March-April

2013, without clearly correlated with the works carried out during this period on the riverbed.

Regarding the flow on all sections monitored during 1 May to 31 August 2013, there was a

situation characterized by high flows especially in May, flow rates accentuated decreasing in the

coming months, with very low values in August 2013.

The report presents for the hydrometric station Calarasi-Chiciu a comparison with

historical monthly average flows (1941-2001). The evolution of the flow in the months May -

August 2013 highlights a peculiar state of this time of hydrological year, but with much higher

flow rates compared to multi annual average flows in May and June, a value comparable to the

average flow in July and deficit of flow in August 2013.

Similar conclusion were found in terms of average monthly absolute levels, is explained

by the direct correlations between flow and level, both in hydrotechnical stations located in the

monitored area and the monitored cross-sections - correlations evidenced by the respective

limnimetrical keys. There is, therefore, highlighted a trend of water levels decreasing

throughout this period.

ADCP flow velocity measurements carried out during months 21- 24 of the construction

period on the sections from main and secondary critical points have been processed, result in -

using the raw data recorded with ADCP technique - size distributions of flow velocity vector,

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 27

both the total horizontal and the main component (in the direction of Danube flow in those cross

sections).

For the main monitoring sections in the report are presented characteristic transversal

profiles with distribution velocity which highlight velocity variations on the section with depth

and distance from the shores. Through these representations was intended to highlight mainly

that the use of the maximum velocity indicator on the section is totally irrelevant when it comes

to compare the Danube flow rate with countercurrent swimming capacity/velocity of sturgeon.

Thus on those sections were highlighted extensive areas, especially near the riverbed bottom

areas where velocities are much lower compared to the maximum velocity on that section.

In order to determine the typical behavior of the Danube - required for 3D hydrodynamic

modeling activity - it is necessary to process long series of data on the distribution of flows and

levels on at least 30 years. Delft3D model series involves the processing of flow data series from

an upstream hydrometric station at the entrance to the modeled sector and processing the

corresponding data series for water levels at a hydrometric station located at downstream

boundary of the sector.

For this purpose, were considered hydrometric station in Calarasi-Chiciu for flow and

hydrometric station in Braila for levels. For these stations were processed available time series

and compared with recordings from the period May 2013 - August 2013. Historical data for water

flow rate were extracted from the paper "Ouvrage de Reference Hydrologique du Danube 1921-

2001", paper published in 2005 by Danube Commission.

Regarding the relative water level variation - monitored at 10 monitoring stations

installed by INCDPM, it was a general continuous decreasing tendency from the beginning of the

period, with some minor fluctuations over time.

In the period May - August 2013 were made a multitude of single-beam 2D and 3D

bathymetric measurements in accordance with Specifications. These measurements led to an

update of the bathymetry in highly dynamic areas of deposition/erosion processes, and, on the

other hand, the thickening of lacunars information in areas of interest, in particular in areas

where hydrotechnical works will be carried out in the main critical points CP 01, CP 02 and CP

10. All these measurements were processed and introduced in the bathymetric database, which

is used to perform all the activities of hydrodynamic modeling.

During the period May to August 2013 were made two campaigns multi-beam

bathymetric measurements in the main critical points CP01, CP02 and respectively CP10.

Bathymetric data processing from these measurements allowed on one hand highlighting the

effects and stage of the already started hydrotechnical constructions (CP01) or continued (CP10)

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 28

in the Danube riverbed, on the other hand allowed updating the bathymetric database used in

the 3D hydrodynamic modeling.

On July 1, 2013 began intensive monitoring PC01 Bala critical point, stage ended on 31

August 2013.

Regarding the hydro-morphological activities coordinated from Command Center located

at km 9,5 on Bala branch, consisted of ADCP and bathymetric measurements made 2 times daily

on 7 cross sections and 3 longitudinal sections located in the bottom sill area. All information

obtained from this intensive monitoring campaign will be used to calibrate the 3D hydrodynamic

model locally.

In months May-August 2013 of the construction phase turbidity measurements were made

on both 10 main sections and on secondary 10 sections. All these measurements were made at

depths of 0.5 m near the 2 banks and for 3 depths - 0.5 m, 1 m and 3 m in the centre of the

cross section.

Regarding distributions turbidity values measured on the 10 main sections, it was found

that the average values of turbidity were relatively small on sections, without large variations.

Regarding the variation of turbidity on each section can not reveal clear correlations or near the

banks nor on the center of the cross sections, turbidity values are very similar on the same

section. Turbidity values have varied between 2 NTU and 22 NTU. Higher values of turbidity -

over 20 NTU - were recorded during periods of high flow in May 2013 without clearly correlated

with the work performed in riverbed during this period.

Regarding the flow rates on the entire sections, monitored within 01 September - 31

December 2013 there has been a general trend characterized by relatively high average monthly

flow rates especially in November 2013.

The report presents for the hydrometric station Calarasi- Chiciu a comparison to the

historical monthly average flows (1941- 2001). The evolution of the flow within September to

December 2013 presents a characteristic situation for this time of hydrological year with flows

rates values close to the multi-annual average flow, except for September, when flows were

slightly deficient.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 29

Similar conclusions were found in terms of the monthly absolute average levels,

explained by the direct correlations between flow and level, both in hydrotechnical stations

located in the monitored area, as well as on the monitored cross-sections - correlations

evidenced by the limnimetrical keys. There is, therefore, highlighted a increasing trend of water

levels in the first three months of the period, followed by a slight decrease in the levels in

December 2013.

ADCP measurements were processed for flow velocities in months 25 - 28 of the

construction period (September-December 2013) on sections of the main critical points and

those of the secondary points to obtain from raw data recorded using ADCP technique - size

distributions of flow velocity vector, both the total horizontal component and the main

component (in the direction of water flow on Danube) for those cross sections.

For the main monitoring sections are presented in the report characteristically

transversal profiles with distribution of velocity, that reveal the velocity variations on the

section according to depth and distance from the banks. Through these representations was

intended to highlight mainly that the use of the indicator maximum velocity on the section is

totally irrelevant when it comes to compare the Danube flow rate with sturgeon critical velocity

that goes up on water. Thus on those sections reveal extensive areas, especially near the bottom

of the riverbed or the banks, areas where velocities are much lower compared to the maximum

velocity on that section.

To determine the typical behaviour of the Danube - required for 3D hydrodynamic

modeling activity - it is necessary to process long series of data on the distribution of the flows

and levels for at least 30 years. Delft3D model involves processing flow data series for upstream

hydrometric station at the entrance to modeled sector and data series processing on water

levels corresponding to a hydrometric station located downstream boundary of the sector.

For this purpose, were considered hydrometric station in Calarasi-Chiciu for flow and

respectively for levels - hydrometric station in Braila. For these stations were processed time

series available and compared with recordings from the period September 2013 – December

2013. Historical flow data were extracted from the paper "Ouvrage de Reference Hydrologique

du Danube 1921-2001", paper published in 2005 by the Danube Commission.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 30

Regarding the relative water level variation - monitored at 10 monitoring stations

installed by INCDPM, it had a general increasing in September – November, followed by a

decrease in levels in December 2013.

In the period September - December 2013 were made a multitude of single-beam

bathymetric measurements 2D and 3D in accordance with the Specifications. These

measurements led to an update of the bathymetry in areas with highly dynamic

deposition/erosion processes, and, on the other hand, the thickening of lacunars information in

areas of interest, namely, in particular in areas where hydrotechnical works will be carried out

at main critical points CP 01, CP 02 and CP 10. All these measurements were processed and

introduced into the bathymetric database, which is used to perform all activities for

hydrodynamic modeling.

In the period September - December 2013 were made two campaigns for multi-beam

bathymetric measurements in the main critical points CP01, CP02 and CP10 areas. The

bathymetric data obtained from these measurements allowed on one side to evidence the

effects of that phase and of the effects of hydrotechnical structures started (CP01) or continued

(CP10) in the Danube riverbed, on the other hand has allowed updating the bathymetric

database used in the 3D hydrodynamic modeling. On July 1, 2013 began an intensive monitoring

CP01 Bala critical point, phase ended on August 31, 2013.

In months 25 - 28 of construction phase were performed turbidity measurements both on

10 main sections and on 10 secondary sections. All these measurements were made at depths of

0.5 m near the 2 banks and for 3 sets of depth – 0.5 m, 1 m and 3 m in the centre of the cross

sections.

Regarding the distributions of turbidity values measured on the 10 main sections, it was

found that the average values of turbidity were relatively small, without high fluctuations.

Regarding the variation of turbidity on each section cannot reveal clear correlations near the

banks or in the centre of the cross sections turbidity, values being very similar on the same

section. Turbidity values have varied between 1 NTU and 27 NTU. Higher turbidity values -

above 20 NTU - were recorded during the periods with high flows in October 2013 without a

clear correlation with the works carried out on the riverbed.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 31

3.8. Ichtyofauna monitoring

Regarding the state of conducting activities related with sturgeon and barbell catching

and marking within 16.08.2011- 15.12.2011 were organised three capture points on each of

lateral branches in CP01 Bala, CP02 Epuraşu and CP10 Caleia, sturgeon specimens have been

captured in the following locations: downstream of CP 01 Bala, on Borcea branch between km:

28-30, 33-35, 35-37, 37-39, 40-42 45-48, 55-57 and on Caleia branch, respective Danube at 196

km. Regarding the capturing and marking of the barbell during this period of 4 months of

construction phase we mention that no exemplary was captured and marked for reasons

independent of INCDPM.

Ichtyofauna monitoring in December 2011- April 2012 consisted in the capture of 13

sterlet (Acipenser sp), weighting 9,5 kg, and 6 beluga specimens (Huso huso) that weighted 486

kg. No barbell (Barbus barbus) has been caught.

For the studied period, the sturgeons monitoring indicator - medium weight of the

capture/species (GMsp)- has the following values:

for sterlet GMsp- 0,73 kg

for beluga GMsp- 81 kg.

After analyzing the data from submersible reception automatic stations VR2W

during December 2011-April 2012 was observed the behavior of ten specimens of beluga (Huso

huso). Four of them have been marked in the analyzed period December 2011 - April 2012 and

the remaining six specimens were marked during the period August - December 2011.

Recordings for the main critical points CP 01, CP 02 and CP 10 and on the sections

between them showed that during December 2011 - April 2012, part of sturgeon specimens

remained in the cold season on the monitoring sector Calarasi km 375 - km 175 Braila and others

probably have descended below km 180 on the Danube. For remaining specimens, Bala branch

presented interest. Three specimens of beluga were recorded successively from December 2011

to April 2012, for which were determined the descending average velocities (medium descending

swimming velocity between 2.5 km / h ÷ 4.2 km / h).

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 32

Figure 3.1 – Released specimen after tagging (Borcea branch km 45-48, 31.03.2012)

Based on the integrated analysis in can be noticed that the minimum migration depth for

sturgeons ranges from 4.4 m to 9.6 m during December 2011- April 2012, related to the

construction phase for months 5 - 8, compared to the period August 2011-December 2011 of the

construction phase(1-4 months) when the minimum migration depth for sturgeon was 1.36 m to

9.6 m.

Ichtyofauna monitoring during period May-August 2012 consisted in the capture of 46

sturgeons: 35 starry sturgeon (Acipenser stellatus), weighting 168.8 kg, 7 starlets (Acipenser

ruthenus)- 13.8 kg and 4 specimens of beluga (Huso huso) - 437 kg. The total weight was of

619.6 kg. Also, in this period 12 barbell specimens (Barbus barbus) have been captured and

marked, with a total weight of 34 kg.

From data integrated analysis it is observed that the minimum depth of migration for

sturgeons varies from 0.44 m to 4.24 m in May-August 2012, towards December 2011- April 2012,

when the minimum depth varied between 4.4 m and 9.6 m. The maximum depth for sturgeon

migration ranged between 10.46 m and 26.38 m. In CP10 has been recorded the lowest depth

(0.44 m) and the highest (26.38 m).

Beluga specimens 2S33 and 3S2 are the only sturgeons tagged and detected that chose to

return on the Old Danube, on Cernavoda - Harsova route, instead of the main return route,

which is Borcea branch.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 33

Figure 3.2- Beluga 2S33 migration route

From the total sturgeons tagged in the period December 2011 - April 2012 in PC01, PC02 and

PC10, a single beluga specimen, with code number 3S2 has been recorded during the

construction period for the period May-August 2012. The marking of this sturgeon took place on

27.03.2012 and was released in Borcea branch area, km 65. It has been recorded by the

receiving station from km 252 on the Old Danube (Harsova area) on 31.05.2012. Water

temperature was of 18.65 0C and the swimming depth varied between 6.52 m and 12.28 m

(figure 3.2). On 01.06.2012 the beluga went down to km 187, on Danube. Thus, the distance

covered was 65 km.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 34

Fig. 3.3. Sturgeon 3S2 swimming route

Regarding the migration of sturgeons, from the total tagged sturgeons 19 have been recorded

by the VR2W reception stations, placed on CP 01, 02, 03 (2 beluga specimens and 17 specimens

of starry sturgeons). In comparison with starry sturgeons, which were recorded at water

temperatures of 19.4- 26.36 0C, the temperature at which beluga were recorded downstream

from CP10, at km 187 Danube, varied between 18.20C and 19.930C. They were in the process of

descending towards the sea.

Regarding the barbell migration in the months 9-12 of the construction period, the reception

stations VR2W placed on the critical points CP 01, 02 and 10 area did not recorded any single

barbell specimen, although 10 specimens had been labelled with ultrasound marks. It is possible

that their movements have been punctual and no specimen moved enough to be detected by the

stationary receivers.

Fig. 3.4 – Barbell (Barbus barbus)

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 35

Other fish species monitoring activity from May to August 2012 comprised 2 catching

campaigns of Alosa species (Danube mackerel and shad), a capturing campaign for mackerel

larvae and biometric measurements analysis.

In the 2 expeditions 82 adult specimens of Alosa immaculate (Danube mackerel) and 46

of Alosa tanaica (shad) have been caught, in all 8 targeted critical points.

The fish fauna is well represented as species number, in all sampled locations. Among

these species, many of them are protected (IUCN red list, Natura 2000, national protection) fact

that certifies the significant conservation value of this sector on Danube.

It can be noticed the presence of shad species and larvae on the entire area of interest,

including lateral branches, with a well presence of shad larvae, fact that certifies a successful

reproduction. These aspects prove the importance of the area as important sector for

reproduction and larvae growth for 2 shad species (Alosa immaculata and Alosa tanaica). The

analysis of data leads to the fact that Calarasi- Braila sector is the most important segment for

reproduction of those 2 Alosa species. The fishing campaigns for other fish species included the

benthic and shore fishing, in daytime and nighttime conditions.

The analysis of benthic and shore samples certifies significant differences between the

fish communities from the 2 habitats categories, indicating that the shore area presents a higher

habitat variability, compared to benthic areas from the main channel.

In the benthic area 28 species have been identified with about 100 detected specimens. Gobies,

coming from Ponto-caspian area dominated in abundance the benthonic habitats. The following

species have a high frequency in the studied areas: the monkey goby (Neogobius fluviatilis), the

round goby (Neogobius melanostomus), the racer goby (Neogobius gymnotrachelus), the bighead

goby (Neogobius kessleri), spined loach (Sabanejewia balcanica). White-finned gudgeon (Gobio

albipinnatus), common bleak (Alburnus alburnus) and streber (Zingel streber) were less

abundant, but frequently appeared in the sampling locations, being important species,

characteristic to Danube. The extremely high percentage of gobies species of ponto-caspian

origin, which are in continuous colonization process of Danube waters (invasive species), has

been determined by the accentuated decline of economical value species (carp, catfish and

zander), fact that allowed the debut of this colonisation process.

In the shore area 32 species and more than 1000 specimens have been identified and

measured during shore area sampling, in 2012. The most abundant species were the common

bleak, the monkey goby, the round goby and the racer goby (more than 95%). Less abundant, yet

wide spread was the pike (Esox lucius), zander (Sander lucioperca), the cobitis (Cobitis

elongatoides) and bream (Abramis bjoerkna).

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 36

According to the samples, the fish communities are well represented by species

characteristic to Danube, on this river section, but their abundance is low, comparative to goby

species. Species such as asp (Aspius aspius), carp (Cyprinus carpio), pike (Esox lucius), silver

carp (Hypophthalmichtys molitrix), sunfish (Lepomis gibbosus), perch (Perca fluviatilis),

topmouth gudgeon (Pseudorasbora parva) and catfish (Silurus glanis) have been detected only

through electrical fishing method near the shore.

The particular case of Epurasu branch can be considered significant for the fish

communities from the lateral Danube’s branches. There was reported habitats with a slow flow,

shallow water and even lentic habitats (stagnant water). The analysis of the fish communities on

this branch reveals a large number of species and individuals. The species cover a wide

spectrum, from some rheophile (common nase, streber, round goby) and up to limnophile

species, such as bitterling and tubenose goby, certifying a great variety of habitats.

It draws attention high abundance of juvenile specimens, including the larger species,

which shows that these branches are used primarily as spawning areas for juveniles, especially

after these species have lost most of the reproduction places due to drainage most of the

Danube floodplain in the twentieth century. Analysing the results it can be concluded that

characteristic species for Danube appear in all 3 types of habitats (benthic, coastal and lateral

branches habitats, with damming works, but in general their relative and absolute abundances

are very low, if compared to the very frequent general species, such as goby and bleak. The

biological explanation of gobies species high abundance may be due their territorial and

aggressive behaviour and Danube colonisation phenomenon with these species in the last

decades.

Within the months 13-16 (1 September to 31 December 2012) a total of 3 specimens of

beluga have been caught, which amounted up to a total weight of 260 kg and one specimen of

starry sturgeon which had a weight of 5.25 kg. Two specimens of sturgeon have been caught on

the Danube at km 200 and other two specimens have been caught on Borcea at km 5

respectively Km 7. Of the total number of sturgeon tagged during the analyzed construction

phase were detected by automatic receiving stations 3 of the 4 specimens marked.

In the period of the construction phase (September – December 2012) have been

monitored a number of 7 wintering habitats, three on the Bala branch at km 6, 7 and 8 and one

on Borcea, at km 49, and two in the area of CP 10. The positions of wintering habitats in area

CP01 and CP10 are shown in the following figure.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 37

Figure 3.5 – Graphic representation of the wintering habitat from CP01 to CP 10

Regarding the captured sturgeons, beluga and starry sturgeon, the analysis of the

recordings at fixed stations on the route reveals downstream travel behaviour. This behaviour

has been highlighted also in the autumn of last year. Their swim velocity over short distances

varies between 10 to 20 km/h, while for long distances (tens of kilometers) of the swimming

velocity is reduced to less than 1km/h, which leads to the conclusion that the existence of

swimming periods associated with stationary periods in certain areas of the route.

Differences in behaviour between beluga and starry sturgeon were limited only to the

depth at which they travel downstream. In beluga depth ranged between 3 and 13 m, while the

starry sturgeon specimen fluctuated between 0.8 and 2.7 m.

The fishing activity was 36 days in CP 10 and nine days in CP 01 and CP 02 area. As

sturgeon autumn migration began earlier in 2012, at the beginning of September, the

authorizations delay caused the missing of migration peak and capture of only four specimens (3

beluga and one starry sturgeon) in area CP 10, at the end of migration season.

The station checking in the main critical points CP 01, CP 02 and CP 10 as well as on

sections between them showed that 3 sturgeon specimens, similar to other specimens tagged

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 38

and monitored during autumn migration in the previous year, have chosen to descent, leaving

the area of interest for the project. It is not known if they chose to spend the winter in the

lower Danube, downstream from Braila, or returned to the sea. In the descent migration they

chose the Old Danube branch to the detriment of Caleia branch. The routes of tagged and

registered sturgeons 4S2, 4S4 and 4S1 are shown on the maps in the following figures.

Fig. 3.6 – Sturgeon 4S2 route in the area of interest

Thus beluga male 4S2 marked on 10.11.2012 in the Danube, km 200, was recorded first time by

Danube station km 186, then by Danube station km 182, both records were made on 13.11.2012.

The distance between the two stations was covered at a velocity of 20 km/h, at a water

temperature of 11.92 °C.

Beluga male 4S4, marked and released at 1600 on 30.11.2012, at km 7 on Borcea branch has been

recorded later at station on Danube km 186, and then by one at km 182, both registrations dated

in 04.12.2012. The distance of about 4 km of the two stations was covered at an average

velocity of 10 km/h, while the distance of 69 km was run with an average velocity of 0.81 km/h.

Water temperature registered by the two stations was of 8.94 °C.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 39

Fig. 3.7 – Sturgeon 4S4 route in the area of interest

Starry sturgeon 4S1 marked and released on 03.11.2012 in the Danube branch km 200,

was recorded on the same day at km 182. Downstream travelled distance was 18 km, with an

average velocity of 13.5 km/h, at a water temperature of 13.96 °C.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 40

Fig. 3.8 – Sturgeon 4S1 route in the area of interest

In December, have been made according to the Specifications, weekly recordings of

water velocity in areas of interest (wintering areas identified in the previous year). We mention

that it was renounced the wintering area monitoring at km 43, because it has not been

confirmed.

Also in November were made Didson camera shooting, in the bottom sill area of Bala

branch without identification of any sturgeon in migration.

As a general conclusion, it highlights the importance of Bala branch and of the Borcea

branch sector between km 40 and 69 as an important breeding and wintering area for migratory

sturgeons of the Danube. It also highlights the Borcea branch between km 0 and 40 as important

breeding area for starry sturgeon.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 41

Months 13-16 of construction phase (September-December 2012) have not included the

monitoring of barbell and other fish species.

Ichtyofauna monitoring during January - April 2013 took into account the following

activities:

catching, marking and monitoring of the sturgeons;

monitoring sturgeon habitats of interest (wintering and breeding);

monitoring of benthic fauna from sturgeon habitats of interest (wintering and breeding);

measurement of water velocities in sturgeons habitats of interest (breeding habitats);

analysis, mapping and description of the habitats of interest (reproduction) previously

identified;

Identification and description of areas of interest and analysis of barbell population

migration in areas of interest in the project.

Carrying out of these activities as well as information gathered after five seasons of

migration and tagging allows some general conclusions to be further verified:

Fishing and marking activity for sturgeons were seriously disrupted as a result of

amending the legislation, which restricts through the annual order of prohibition, the

validity of the scientifically fishing authorization sturgeon in the period 20 March to 10 May,

respectively 1 October to 30 November. It is noticed the strong anthropic pressure of

poaching on these valuable species, many of the marked specimens no longer been detected

or being detected with a linear movement at the water surface, which certifies their

capture and abandonment of the transmitter (case of female sturgeon 2S4, of the female

sturgeon 4S5 and the male beluga). That determines sustain efforts to achieve the

maximum rate of captured and marked fish, so that we can obtain conclusive data, even

under these circumstances of permanent pressure;

• It can been noted, as a general rule that the belugas use the Bala branch and Borcea

branch area at km 64 to the intersection with Bala branch as a wintering area for autumn

migratory specimens. This is consistent with our research that localised wintering areas on

Bala branch and Borcea branch upstream of km 60;

• After wintering period, the fish choose to breed on Borcea or Bala branch (beluga 2S6) or

continue the movement on the Old Danube probably just upstream of km 350 (beluga 2 S20),

for breeding places, higher up on the river. The fish with spring migration follow the same

pattern of behaviour;

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 42

• After the reproduction period, the fish are returning downstream using preponderantly

Borcea branch, but there are cases when they return to the sea using the Old Danube. The

lack of data from stations located on the Old Danube prevents a clear conclusion on the

possibility of those specimens reproducing on the Old Danube between villages Izvoarele and

Hârşova (there is a new spawning area detected at km 310, in the village Rasova area)

• There are examples of fish (2S22, 2S31, 2S37) that have swim upstream on the Danube in

autumn, and after marking they descended leaving the monitored area to return in the

spring again. Data are insufficient to highlight if it is a normal behaviour pattern;

• As a general conclusion it can be highlighted the importance of area of Bala branch and

the sector of Borcea branch between km 40 and km 69 as breeding and wintering important

areas for migratory sturgeons of the Danube. Also, it can highlight the area of Borcea branch

between km 0 and km 40 as important breeding area for starry sturgeon.

• The accumulated data enables us to conclude that there is no limiting factor of sturgeon

migration in future on right branch Bala threshold.

• Activity of the barbell telemetry in the area of interest had provided results less

conclusive, meaning that the number of fixed stations identifying barbell route was low and

has not shown any specimen on several stations, in order to highlight the migration

behaviour over greater distances.

During the monitoring period of 1 May – 31 august 2013 were captured and marked a

number of 18 starry sturgeons on the Borcea Branch between 0-7 km and 20 km, and a total of 5

specimens on the Danube Branch km 217-219.

On the Borcea Branch there were recorded 8 starry sturgeons migrating upstream from

km 3.4 for spawning, and 4 of them were detected at km 182 on the Danube Branch, returning

to specific habitats in the Black Sea. Other 8 marked starry sturgeons on the Danube and

Borceam branch were detected only at km 182, before leaving the studied section.

VR2W receiving stations did not show starry sturgeons on the Bala Branch or the Danube

Branch upstream of km 240.

Detections obtained from VR2W receiving stations from km 182 of the Danube Branch

showed that swimming depth of starry sturgeons varied between 2.4 m and 28.3 m. The

recording carried out in April with the Didson camera did not show any presence of sturgeons in

the two thresholds of Bala Branch and Caleia Branch.

Scientific juvenile sturgeon fishing has resulted with the capture of specimens of starlet

and beluga sturgeon species and Borcea, Danube and Caleia Branches.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 43

The analyzed samples of benthic fauna from the habitats of interest indicated the

presence of a large number of taxons representing food for the development of juvenile

sturgeon, and for the adults who migrate for reproduction.

At common barbell species, because the distance is relatively large between the main

critical points there were mounted VR2W receiving stations, not being able to confirm the

migration routes during reproduction.

The results show some anthropogenic pressures exerted by intensive commercial fishing

and poaching, on the common barbell populations in general and particularly on the marked

specimens of the research team, which leads to the conclusion that many of them were

captured and slaughtered.

Regarding the monitoring of other species of fish during the period of 1 May to 31

August 2013, the analysis of fish communities in the study area leads to several important

conclusions:

The fish fauna is well represented as number of species in all sampled locations. Among

these many species, a big part of them are protected (IUCN red list, Natura 2000, national

protection) which shows significant conservation value in this sector of the Danube.

It is noticed the presence of shads species and larvae on the whole area of interest,

including side branches, with a good presence of shad larvae, which indicates successful

reproduction, even if is delayed, compared to previous years. This shows the importance of the

study area as an important sector for reproduction and larvae growth of the two species of shad

(Alosa Immaculata and AlosaTana).

It is noticed a very high proportion of gobies species with Ponto-Caspian origin that are

in continuous process of colonization in the Danube for more than two decades.

Size histogram analysis reveals an imbalance between fished species to species of

economic value, the larger mature specimens are very rare, which shows continuous

anthropogenic pressure due to excessive industrial fishing (including poaching) and unrestricted

angling, which search and extract the mainly large specimens.

The particular case of the Epuraşu Branch shows a different pattern regarding fishing

communities compared to the situation on the other side branches of the Danube. One can

notice the high degree of natural silting of this branch, with very low depths (most surfaces

under 1m ), whose causes are not known precisely, the possible influence of hydraulic works

started but not finished in the 80s of last the century. It is noted during the year a cyclic

evolution of fish communities, in connection with the development of water flow and current

velocity. The analysis of the fish communities on the branch revealed a large number of species

and specimens, both limnophyles and reophyles species. The ones in the first category are the

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 44

strongly dominated ones; the reophyles species entering the branch only when the flow

conditions and velocity ensures their conditions. The high abundance of juvenile specimens

draws attention, including the larger species, fact that reveals the fact that this branch is used

primarily as a place for spawning and rearing of juveniles, especially after these species have

lost most of the spawning locations because of the draining of the majority of the Danube

floodplains, in the decade of the last century.

Given that, the hydraulic works in progress shall ensure a minimum flow of water in the

channel, necessary to follow the fish communities’ evolution and follow the warping process and

its impact on these communities.

The monitoring activity of the fish fauna in the months September to December 2013

and the information accumulated after six seasons of migration and tagging allow some general

conclusions to be checked out below:

• It is noted that the poaching activity represents a strong anthropogenic pressure on

these valuable species; many marked specimens are subsequently no longer detected, or

detected moving linearly on the water surface, which certifies their capture and the disposal of

the transmitter in the water. This determines stepping up efforts to achieve the maximum rate

of fish captured and marked, so that we can obtain conclusive data, even under the this

pressure circumstances;

• As a general rule the beluga use of area Bala and Borcea branches in km 64 to the

intersection with Bala Branch as a wintering area for migrating fall specimens stands out. This is

consistent with our research that wintering areas located on Bala and Borcea branches upstream

of km 60;

• After the wintering period, the fish choose to spawn on the Borcea or Bala branches

(beluga 2S6) or to keep moving on the Old Danube probably just upstream of km 350 (beluga 2

S20), for spawning places higher up the river. Also, spring migrating fish follow the same

behaviour pattern;

• After the spawning period the fish return downstream using mostly on Borcea branch,

but there are cases when they return to the sea using the Old Danube. The lack of data from

stations located on the Old Danube prevents a clear conclusion on the possibility of these

specimens spawn even in the Old Danube between villages Izvoarele and Hârşova (there is a new

reproduction area detected at km 310, in Rasova area);

• There are examples of sturgeons (2S22, 2S31, 2S37, 4S1, 4S2, 4S4, 6S12, 6S14, 6S21,

6S22) which moved upstream on the Danube in autumn, and after marking they moved

downstream leaving the monitored area to return then again in the spring. Some of these

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 45

sturgeons have been highlighted returning into the sea, by the Chilia branch. Data are

insufficient to highlight if it is a normal behaviour pattern;

• As a general conclusion it can be highlighted the importance of Bala and Borcea

branches sector between km 40 and 69 as an important spawning and wintering areas for

migratory sturgeons of the Danube. Borcea Branch also represents between km 0 and 40 an

important spawning area for the starry sturgeon.

• The accumulated data allows us to conclude that at present we see no limiting factor

for the sturgeon migration right through the threshold under the construction on the Bala

Branch.

4. BUILDING SITE ACTIVITIES MONITORING

Within the preconstruction period, in the CP01, 02, 10 the organisation phase and works

accomplishment have been followed for the activities starting after 15 August 2011.

Within April-August 2011 the activities carried out by the constructor have been limited

to the building site organisation in CP01, located at km 346, on Danube’s right bank, in the area

of CP01 Izvoarele.

Wastes collecting, stocking, evacuation have been followed, as well as construction

materials deposit and oil products, air quality, noise level determination, the evolution of

personnel number within the building site, waste waters collecting and evacuation, the situation

of devices park, state of constructions and utilities.

This action has been made though direct observations, video recording and photos,

discussions with the existent personnel.

Within the construction period, hydrotechnical constructions have been made, both on

shores and riverbed, without overflows of a pollution indicator caused by the activities carried

out.

From the evaluation of noise level measurements and air quality indicators it can be

noticed that in the building site area there are no overflows of the Lzeq maximum level and of

maximum concentrations admitted by CMA, in relation to the air quality.

Analysing the results obtained one can notice a increase of the noise level and aerial pollutants

direct proportional to the volume of the works executed, tendencies that did not exceed normal

values.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 46

5. STATE OF THE 3D NUMERICAL MODELING

The objectives of the preconstruction phase regarding the numerical modeling have been

totally reached:

Analysis of the informational volume initially existent referring to Danube 3D

modeling on the project sector of interest

Accomplishment of the bathymetric measurements campaign through the 2

complementary techniques- 2D (single-beam) and 3D (multi-beam)

Accomplishment of repeating hydrometric measurements, at different Danube’s

quotas regarding water flow and velocity, through measurements using 3D ADCP technique

(Acoustic Doppler Current Profiler) in transversal section, having a resolution of 300- 500 m, the

entire Danube sector monitored and 50- 100- in the lines belonging to the critical points.

Data take over- necessary for the 3D modeling- from the historical databases, the

critical analysis and their processing, data delivery to the Consortium partners, in the formats

necessary to their introduction on the 3D modeling programs.

Preliminary analysis and the construction of discretization network for a sector of

12 km located in the CP01 area. Networks of finite elements have been obtained, using the 3D

hydrodynamic modeling software - Delft3D - the conformation characteristics of the

discretization networks to the shores’ topology from the studied area have been analysed.

Over the network of finite elements bathymetric information have been covered obtained from

the single and multi-beam measurements campaigns.

Regarding the state of 3D modeling within 16 August- 31 December 2013 we mention that

in Figure 4.1 is presented a 3D measurement processing in order to exemplify the complexity of

developing of 3D and quasi 3D numeric simulations resulted from processing of bathymetric and

topographic information.

Figure 4.1 – Example of the processing result for 3D bathymetric measurements

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 47

In the 5-8 months of the construction period (16 December 2011- 30 April 2012) the main

activity regarding the 3D modeling consisted in the preliminary analysis of the model

discretization topology of the area to be modelled.

Therefore, using the model division in various subfields characteristic to Danube

branches, many subfields/sections have been monthly processed.

All these subfields are analysed to be included in a general model in which the other

information regarding the bathymetry, asperity, water quality, velocities and flowing directions.

Overall, within these months about 1300 km of shores have been digitised at a resolution

of about 25 m, horizontally oriented. All X, Y, Z coordinates can be found in STEREO’70

coordinates system.

An operation that needed a high analysis volume, as well as complicated computations

has been the overlapping of bathymetry data on the finite elements’ network cells.

Below figures present particular construction elements of the computation network.

Dunărea, secţiune

amonte de punctul 10 Braţul Vâlciu, secţiune

amonte de punctul 10

Braţul Caleia, secţiune transversală

pe parcurs, în zona punctului 10

Dunărea, secţiune transversală

pe parcurs, în zona punctului 10

Dunărea, secţiune

aval de punctul 10

Figure 4.2 - Particular construction elements of the computation network in CP10 area

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 48

Figure 4.3 – Network orthogonality, estimations during the construction of the

computation network in CP10

The models of Danube’s minor riverbed in the CP 01 and 02 have been connected

so that the passing from a section to another be continuous. Thus has been made a

model of Danube riverbed for CP 01 and 02.

Figure 4.4 – Model of Danube riverbed in CP 01 and 02

During the months 9-12 of the construction phase (01 May- 31 August 2012) the main activity

regarding the 3D modeling consisted in the analysis of 3D representation of branches topology

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 49

on Calarasi- Braila, analysis of some important areas from the main critical points and modeling

tests, measurements to complete the bathymetric and hydrological data, necessary for the 3D

modeling.

Moreover, the following activities have been carried out: operations to construct computation

networks for 3D models, based on the analysis of Delft3D model possibilities in various conditions

on the studied sector, analysis of the data referring to branches in order to apply the Delft3D

model in the studied sector and a detailed analysis of an area from the intersection of Old

Danube branch to Bala branch.

Referring to the analysis of branches’ topology representation in the 3D model, have

been made a partial construction operations of a computation network that take into account

the banks and the islands.

The analysis of these situations proved that it is necessary that the model computation network

have a high number of elements to represent the islands areas and branches on which water

flow is distributed. It needs to be represented at least the local larger branches and the ones

that change over time.

Test computations have been made with a regular network, the modeling of water and fine

sediment movement in the area of Bala branch, were performed with different values of the

levels in the downstream sections, in low flow condition, in order to test and observe the model

behaviour.

The results prove the fact that the model has a good sensitivity at the local conditions of Danube

riverbed and at the branches general conditions. The test computations point out on riverbed

depths and width that must be well represented in the model, on the transversal section,

because these influence the velocities distribution.

Figura 5.4 – Nivele calculate ale apei în CP01

Figure 4.5 – Water computed levels on CP01

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 50

Regarding the fine sediment transport in local conditions of Bala branch, the test computations

have been carried out starting from regular values of fine sediment transport in upstream

section, in low flow conditions. The results present that the test model has the capacity to

simulate fine sediment transport in Bala area, from upstream section on the Danube to the

ramification and on the 2 branches. Therefore, the model will simulate fine sediment transport

in transitory conditions (variable alluvial loading with in Danube waters).

Figure 4.6 – Distribution of fine sediment concentrations, transported from upstream in CP 01

For the purpose of water flow numerical modeling in the CP02 tests have been made in

the construction of discretization networks and the analysis of their properties, following the

obtaining of a basic framework that includes the configuration of the islands upstream and

downstream from CP02.

The grid model has been used of Delft software package. Then, operations to take over

the bathymetry data over the network of finite elements have been carried out.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 51

Figure 4.7 – Particular elements of the basic frame, tests to construct the computation network

upstream and downstream from CP 02

Starting from values of the flow entered from the Old Danube into the upstream section of the

CP02 and Old Danube’s level in the downstream section of the CP02 tests have been made for

water flow computation, using Delft 3D model.

Computed values of the velocities have resulted, in the points of the 3D network. The

flow velocities are higher on the left side, in the deeper sector. In the right part of the section

the velocities are lower. The velocities distribution, computed on the Old Danube, upstream the

first island (left side) from the CP02 show the water flow on the middle and right sides.

Upstream the confluence of Epurasu branch to the Old Danube the highest velocities are the

ones from the middle part. The possibilities of Delft3D model to simulate the movement of

water in the Danube, in the area of CP10 were analyzed using specific bathymetric and

hydrological data.

The tests computations have shown that it is very important the representation into the

model of the width and the depth of the riverbed, on cross section, because these influence

the distribution of velocities.

Old Danube, downstream

section from CP2

Old Danube, upstream

section from CP2

Old Danube, cross-section

upstream from the first island,

in Critical Point 2

Old Danube, cross-section

upstream from Epuraşu brach

confluence

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 52

Figure 4.8 – Computed water levels at CP10

Also, test computations were performed regarding fine sediment transport in the local

conditions from CP10 area. The results show that the model is able to simulate fine sediment

transport in critical point CP10 area, on the Danube and on Caleia branch, in changeable

conditions (of variable sediments loading in Danube water).

Figure 4.9 – Fine sediments concentration distribution, transported from upstream, in CP10

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 53

The works carried out in this period (01 September- 31 December 2012) were focused on

the following areas: examination ways of representing the geometry of irregular proportions or

local branches of the riverbed in a 3D model, functionality and behaviour analysis of quasi 3D

numerical model using Delft3D software in special situations in riverbed (submerged dam -

Epuraşu). Also, measurements were made to complete bathymetric and hydrological data

required 3D modeling.

Experts from BOKU analyzed in detail the areas from the main critical points CP 01, CP

02, CP10. Also they presented and discussed some aspects of the modeling for these areas.

Experts from the Deltares have analyzed the data on river branches to implement quasi 3D

numerical model using Delft3D software with experts INCDPM. Were also discussed some

possibilities of using the interface Delft3D for modeling.

During this period, representation tests in a network computing main elements in some

complex areas of the Danube riverbed were continued, taking account of the specific conditions.

Using Delft3D software interface provided by operations were examined ways of representing

situations with many local islands and branches in a certain area of investigation so that support

can be obtained for calculation and representation of water currents structure. Starting from

the basic configurations can be prepared fine network computing with several transverse profiles

to include situations that may occur over very short distances in some areas, due to work.

Other tests representation riverbed irregularities were conducted for Epuraşu branch. Given that

some start-up items based on measured data lines, built a network of irregular computation,

targeted so that they can better incorporate specific configuration water movement on Epuraşu

branch. Quasi 3D numerical model developed using Delft3D software is used for the whole area

which includes a section of the Old Danube branch downstream of Bala and Epuraşu branch and

allowed to obtain preliminary results from running.

When using a detailed representation of the riverbed, quasi 3D numerical model is able

to simulate the fine variations of velocity and water surface flow orientation toward one side or

the other.

For situations with constructions in riverbed, models were prepared that include details

of the dam in the entrance area to Epuraşu branch and test calculations were carried out in

different ways. Dam effects on water flow were highlighted by plotting the calculated velocity

distributions.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 54

Figure 4.10. – Distribution of northern component size for the velocities computed in the dam area

Further simulation was performed for an analysis of how to achieve computing network

for local construction more complicated situations in riverbed (dam and cross section through

him) and analysis functionality and quasi 3D numerical model results in such cases.

The need to represent on the computation network of some more constructive details

relatively small or with local positions and directions revealed the limits of the initial

computation network designed for simulation on greater distances. Study of very different

situations or different variants construction is done preparing and using for calculations of

several Delft3D type models (one model for each distinct situation of construction).

In Figures obtained from Delft3D software interface, the velocities calculated results are

presented for low water flow conditions and for approximately double (average water flow

range). Results show that numerical model quasi 3D simulates adequately continuous changes of

direction of the current along the outer side of dam.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 55

Figure 4.11 – Distribution of computed velocities sizes in the conditions of a cross section

nearer to Epurasu island

As can be seen in the graphic representations of the results, the model is capable of

simulating the complex structure of the currents from the area between the dam and the

entrance on Epurasu branch. Therefore, in a complicated situation with small but very important

details of the constructions, the Delft3D model type allows the adequate representation of the

situation, having a good functionality.

Delft3D model behaviour has been also analysed for situations with transversal passages

through dam, placed in other portions. The results point out the currents that are formed

towards left and right, around the island and towards the entrance on Epurasu branch. If the

transversal passage is nearer the right bank, the currents behind the dam are oriented towards

Epurasu branch.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 56

Figure 4.12. – Distribution of computed velocities sizes in the conditions of a cross section in the right of the island behind the dam

Figure 4.13 – Distribution of computed velocities sizes in the conditions of a cross section closer to the right bank

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 57

The 3D modeling activities have continued during January- April 2013, with following

activities performed by Deltares, BOKU and INCDPM experts:

▪ Establish of the computation networks and preparation of RSim- 3D hydrodynamic

model for the areas studied in the CP01 and CP02

▪ construction of computation networks for the Delft3D model that covers the areas

of the main critical points CP01 and 02

▪ analysis of the specific conditions and preparation of Delft3D computation

networks for some of Danube’s main sections

▪ completions with new hydrological and bathymetric data, from measurements in

high flows conditions and analysis of the data sets to optimize the representation of

riverbed geometry

▪ establishing of a detailed computation network and preparation of the Delft3D

model for water flow in the CP10 and tests on Delft3D model components that can offer

estimations of sediment transport in riverbed.

BOKU experts have continued the analysis of data sets received from INCDPM and the

preparation of computation networks and RSim-3D model for water flow for area within CP01-

022. The results have been presented at the 2013 February meeting.

BOKU experts analysed the details regarding the parameters of water flow in the area of

CP01 and CP02 based on the INCDPM data, in order to improve the representation in the model

of bathymetric and hydraulic variability conditions.

The preparation activities for the RSim3D model comprised the preparation of

parameters and computation options necessary to run. Parameters adjusting were performed

based on the calibration operation with measured data.

The RSim-3D model for the critical points 01 and 02 provided velocity distributions at

Bala bifurcation and in transversal sections and distributions of water levels in situations with

different flow rates. Based on the elements presented, some aspects regarding the boundary

conditions for computation and implementation of RSim-3D model have also been discussed. The

preparation of Delft3D models continued for main critical points and for some big sections of

Danube. To prepare the computation networks, the Calarasi- Braila sector has been divided in

some big domains.

Deltares experts have built Delft3D grids for some Danube’s longer sections, following the

representation of their specific configuration, based on the data offered by INCDPM. Moreover,

the examination and the preparation of INCDPM data for water flow modeling in the area which

comprises the critical points 01 and 02, have continued.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 58

The analysis of the specific conditions and the preparation of some Delft3D grids versions

have been made for the following areas:

sector from the confluence of Borcea with Old Danube

Inferior Borcea branch downstream the confluence to Bala branch.

Sector within Vadu Oii and Braila

Grids resolution is similar, being built to be formed from elements of comparative

elements.

These grids are going to be connected in order to allow the water flow modeling on the

entire sector.

Using the Delft3D interface, a detailed computation network has been made for the

critical points 01 and 02 as well as a detailed network for the critical point 10 and then prepared

the necessary files for Delft3D model.

Within the 2013 February meeting the previous results of the water currents structure

has been presented, for the CP02, in the entrance area towards Epurasu, in different situations.

Regarding the 3D numerical modeling stage during the 01 May – 31 August 2013 period,

the activities of developing and improving hydrodinamic modeling for studies of flow parameters

and effects of the works on the Danube, at critical points 01, 02 and 10, were continuated.

Some of the activities and preliminary results from this period were presented at the workshop

on 1-2 July 2013.

The activities of BOKU specialists were oriented to hydrodynamic modeling at 01 and 02

critical points. The RSim3D model results, without the constructions influences, were compared

with previous measured data before the bottom sill execution in phase III. The situations

approached to study the effects of construction on hydraulic parameters are those with flow

rates of 7150 m3/s, 5530 m3/s, 3840 m3/s, 1940 m3/s on the Old Danube upstream of Bala

(referring to the total Danube flow of 8000 m3/s, 6000 m3/s, 4000 m3/s, 2000 m3/s).

The types of results presented of the RSim3D model include: water calculated levels,

velocities calculated in different layers, generated efforts of water currents in the riverbed and

other values. Surface and bottom velocities, for the bottom sill situation in phase III, were

presented as distributions of values in the bottom sill area, specifying some maximum calculated

values. The model results show some increases of calculated water levels on the Old Danube

because of the phase III construction stage of the bottom sill. The water currents generated

efforts at the bottom level were analyzed in the bottom sill area. Data from monitoring

activities are considered essential for the evaluation of model results.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 59

Figure 4.14 - Results of the simulation flow of 5530 m3 / s (with bottom sill in phase III),

bottom velocities

For habitat modeling were performed representations on velocity distributions based on

simulation results at different flow rates.

In addition to IIIrd stage of bottom sill, RSim3D model was run also for a subsequent

configuration of the bottom sill, meaning that the water current situation far from the one

without the construction for which the model has been calibrated.

After the results until early July 2013, from calculation with the RSim3D model for the

bottom sill in stage III situation, it is taken into consideration the use of new measurement data

to improve the model, before proceeding to analyze its application to other situations.

Specialists from INCDPM continued the accomplishent of modeling activities in

collaboration with partners and worked with experts from Deltares Delft3D hydrodynamic

models to improve the critical points 01, 02 and 10. Measurements were taken to fill data for

modeling with the existing conditions on the Danube during this period to cover the range of

requirements. It was established a systematic monitoring system in the bottom sill of Bala

Branch to get high frequency ranges of values.

The Danube riverbed configuration in the Bala area is a very complicated one, reason for

which Delft3D model versions were prepared by experts from Deltares and INCDPM, for a more

complete study.

There have been analyzed a number of ways for vertical discretization and computation

options within the models of this type.

Delft3D model for critical points 01 and 02 includes sections on the Old Danube, Borcea

and Bala Branch and Epuraşu Branch entirely. Delft3D model results without the influence of

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 60

construction were compared with data measured in the calibration state, before the stage III of

the bottom sill execution: flows on the branches, water levels, velocity distributions in cross

sections.

Delft3D model results, the effects on Bala Branch after bottom sill phase III construction

activities show distributions of velocities, levels, differences in the distribution of flows on the

branches, obtained with different modeling options.

Figure 4.15 - Results of the model Delft3D showing flow increases on the Old Danube downstream of Bala, under the effect of the bottom sill in phase III and of other constructions

The model provides results related to the velocity in layers on the surface of the water,

at the bottom of the riverbed and profile values in different vertical layers. Were obtained

calculated water levels and estimates of efforts generated by water currents at riverbed level in

the bottom sill area.

For the critical point 10 Delft3D model has prepared taking into account the position of

the bottom sill on Caleia Branch. Without influence of the bottom sill model results were

compared with the data from the measurements. Have been used different modeling options on

vertical discretization and characterization of riverbed roughness effect. Besides the usual

Delft3D model was developed a model of Z type, with horizontal layers, which allowed a local

option non-hydrostatic model. The results showed some differences from the hydrostatic

pressure and the fact that under the influence of pressure differences may result some changes

in velocities direction.

Delft3D model calculations provides estimations of the flow percentage from upstream

that passes on Danube section near Caleia branch. Were taken into account dredging variants.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 61

Figure 4.16 – The model Delft3D simulating bottom sill effect on the flow rate on the section

of the Danube in the right Caleia Branch

Using the model, results have been obtained that estimates velocity values in layers from

water surface to the middle depth current over the sill and bottom.

The modeling results are going to be improved through new data sets measured under the

specific conditions on the Danube.

Because the configuration of the Danube riverbed in the Bala area and bottom sill

generates local effects that can be seen only by measurements in those areas, experts from

INCDPM have established a system for obtaining data in certain sections of the bottom sill.

Cross-sections were fixed in the upstream of the sill, on the sill, and downstream the sill.

However, longitudinal sections were established crossing the bottom sill. There were also

established measurement sections at the critical point 10, for bottom sill area of Caleia Branch

and the Danube.

Morphological data in those sections also highlight values and local details that can be

useful for analyzing modeling results.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 62

Figure 4.17 - Upstream and downstream control sections bottom sill Branch Bala

Regarding the 3D numerical modeling on the stage of period 1 September to 31

December 2013, using the results available in the early period of specialists at BOKU and INCDPM

+ Deltares, modeling results have been prepared on the critical 01, 02 and 10, for a summary

report, requested by the customer. Assessments have been shown to critical hydraulic

parameters specified in special situations, to initial conditions. Were highlighted construction

influences the flow and the velocity of water flow in certain situations.

Further, experts from Boku prepared sets of results from the RSim 3D hydrodynamic

model for the critical points 0 1 and 02 to situations before the execution of construction and

building respectively, obtained by simulations on a domain that contains the riverbed and areas

eventually covered by higher flow rates. CP01 critical point in the discretization construction

areas included a section on the Old Danube upstream and downstream of Bala and Bala Branch

partial section. CP02 critical point in the discretization is included with the submerged

breakwater and partial extensions on the branches. Updated results and completed that were

included in the presentation to the meeting on October 10, 2013 3D modeling shows particular

estimates in the bifurcation of the critical point CP01 and threshold Bala bottom Branch.

Using the results of simulations with the model RSim 3D the specialists from Boku

estimated growth of about 1-3 % in the proportion of flow on the Old Danube, from medium flow

to large, when the bottom sill in phase III compared to the situation before construction

execution. The results of habitat modeling representations consist of the areas with intervals of

values of flow rate at the bottom of the bed or surface, based on simulations with the model 3D

hydrodynamic RSim.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 63

Delft3D model for the CP01 and CP02 critical points has been used by specialists from

INCDPM and Deltares to simulate the influence of the application of variants of dredging on the

Old Danube for flow distribution at the critical point CP01 . Bala Branch bottom sill phase III

situations were analyzed, bathymetric data in different stages with dredging the ENR -3m on the

Old Danube . Simulations carried out for the reference flow of 2000 m3/s, 4000 m3/s, 6000 m3/s,

8000 m3/s, revealed increases in the proportion of flow on the Old Danube , upstream against

the flow in different situations. Continued measurements allow Danube completing basic data

and update these preliminary results. Due to changes due to trends of deepening the riverbed

of Bala Branch in the modeling activities, preparatory analyzes were performed on possible

options for correcting the flow distribution in the Danube Branches Bala . Using a small Delft3D

model the problem of variations in water surface slope in Bala Branch bottom sill was analyzed .

Regarding the critical point CP10 simulation results Delft3D were analyzed the branches

flows in baseline total flow rates on the Danube 2000 m3/s , 4000 m3/s, 6000 m3/s, 8000 m3/s

Then dredging influences at CP10 critical point were simulated in versions up to ENR - 2, 5 m or

ENR - 3, 5 m, the flow of Branches and velocity distributions . Velocity values decrease for the

bottom sil areal in the dredging variants due to increased flow downstream Danube Branch

Gropeni and corresponding loss path. Further calculations on hydraulic parameters in the critical

point CP10 were updated based on bathymetric data in October. Then, Delft3D model of water

flow at high flow rates on the Danube , at the critical point CP10 was ready. In reference flow

of 10000 m3/s flow rates calculated on the left (which includes Caleia Branch) and right side (

the section that borders the Danube Island ) are comparable and 12000 m3/s flow is passing on

the Danube high. The results show ,the water flow rates on the island , are much lower than the

rates for the two Branches .

Throughout the period, further data sets measurements were undertaken by INCDPM

for the current situation to achieve hydraulic structures. Flow and velocity distribution were

measured in sections of the Danube hydrological conditions in the period. Processing of data

from measurements continued to allow modeling to be updated and provide results as close to

the developments as the works at the critical points generates effects on the hydraulic

parameters.

Project: MONITORING THE ENVIRONMENTAL IMPACT OF THE WORKS REGARDING THE IMPROVING OF THE NAVIGATION CONDITIONS ON THE DANUBE RIVER BETWEEN CALARASI AND BRAILA, KM 375-175

AD HOC REPORT

Consortium of INCDPM 5

103. pescar Marian Cristinel DUMITRACHE

104. pescar Alexandru LINTARU

105. pescar Nicolae DIA

106. pescar Vasile POPOACĂ

107. pescar Petrică MUNTEANU

108. pescar Dorian CĂLINESCU

109. pescar Vasile CALOTESCU

110. pescar Marcel LUNGU

111. pescar Tudorel CIOCHINA

112. pescar Daniel Georgian ABĂSEACĂ

113. pescar Costel DASCĂLU

114. pescar Ghiţă VASILE

115. pescar Ion MITREANU

116. pescar Gabriel George MURGU

117. pescar Valentin NEAGU

118. pescar Ştefan Dumitru DIA

119. pescar Daniel Constantin ŞTEFAN