MOM Report

Galina Vankova

RAL, 1. 09. 2011

MICE Video Conference

Page 2: MOM Report Galina Vankova RAL, 1. 09. 2011 MICE Video Conference

MICE Hall current activities 16.08 - 31.08, 2011

Installation of Step IV and Preparation of the fall MICE run

Decay solenoid and cryogenic system - PSU - DL Group to replace selected components; order of pumping rigs - in progress ; Focus is on quench detector replacement

Liquid Hydrogen system - Heater/chiller pipe work making good progress- Building of vacuum system - mezzanine supports and gate valve/cross installation, various PPS activities - in progress

Vacuum installation on roof - vacuum control panel has been installed and roof handrails have been completed

Gas bottle rack outside the MICE Hall - has almost completed

Page 3: MOM Report Galina Vankova RAL, 1. 09. 2011 MICE Video Conference

Detector preparations - EMR - removed to offline position, awaiting electronics removal and shipment to UNIGE- Report of LK/TOF/EMR survey received from DLS- Both BPMs have been removed- The missing spanner (wrench) for the mechanical beamstop frame has been replaced

Online Reconstruction tests - DAQ system modified to run without the EMR , miceraid2 problem needs to be solved - experts involved ,DAQ - ready - as soon as possible

Target & upstream beam line - T1 removed - Phase II controller installed - Re-build scheduled for 12. 09. , re-installation on 14. 09 - three bobbins has been ordered and cooper for cooling jacket has been provided; T2.8 upgraded, tested and installed

Tracker integration in Lab 7 has been completed - efficient operational condition

Electrical Infrastructure - cable over main door is installed, earth testing in Hall has to be performed