Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Research ArticleModified PCI Multipliers for Time-Dependent Deformation ofPSC Bridges
Joo-Ha Lee 1 Kwang-Mo Lim1 and Chan-Gi Park 2
1Department of Civil and Environmental Engineering e University of Suwon Hwaseong 18323 Republic of Korea2Department of Rural Construction Engineering Kongju National University Yesan 32439 Republic of Korea
Correspondence should be addressed to Chan-Gi Park cgparkkongjuackr
Received 28 February 2018 Revised 14 May 2018 Accepted 23 May 2018 Published 10 July 2018
Academic Editor Constantin Chalioris
Copyright copy 2018 Joo-Ha Lee et al -is is an open access article distributed under the Creative Commons Attribution Licensewhich permits unrestricted use distribution and reproduction in any medium provided the original work is properly cited
Nowadays prestressed concrete (PSC) bridges have become very common but there are still many difficulties in predicting their long-term behavior In order to predict the long-term behavior of PSC bridges it is possible to use very complex formulas developed byvarious researchers or numerical analysis through computer but many engineers are having difficulty in using such methodsMoreover the accuracy of the prediction result is not satisfactory compared to the effort On the contrary the PCI Bridge DesignManual proposes a method that can easily predict the long-term behavior using multipliers However this method does not take intoaccount various construction schedules and has some assumptions that are inadequate for the current situation in various girdersections and topping thicknesses -erefore in this study new long-time factors were developed by modifying the multipliers of thePCI Bridge Design Manual by a rational manner-is allows prediction of long-term behavior of bridges taking into account variousconstruction schedules and the characteristics of modern girder sections -e prediction results of the long-term camber anddeflection of PSC bridges using the proposed multipliers were compared with those using the basic PCI Bridge Design Manual theimproved PCI Bridge Design Manual KR C-08090 (same as ACI 318-14) and numerical analysis As a result the newly proposedmethodmakes possible to predict the long-term behavior at any time after casting and the accuracy of the prediction is also improved
1 Introduction
Recently the application of prestressed concrete (PSC)bridges has been increasing due to the development of high-strength concrete the improvement of strength and quality ofprestressing (PS) steel and the development of structuralanalysis technology using computer program -e long-termbehavior of these PSC bridges is very important because itdirectly affects the serviceability and safety of the bridge Inthe case of high-speed railway for example very small de-flection of the railway caused by the long-term deformation ofthe bridge can cause serious problems on the running abilityand safety of train -erefore it is necessary to accuratelypredict the time-dependent deformation in the design andconstruction stages and even use stage of the bridge Howeverit is very difficult to accurately calculate time-dependentdeformation of PSC bridges -e calculations should takeinto account creep and shrinkage as well as load-induced
deformation which can cause significant deformation overthe years Especially unlike nonprestressed members forprestressed members prestress forces and prestress lossesmust be considered In addition when combined withnonprestressed members the prediction of long-term be-havior becomes more difficult
Korearsquos railway design guidelines and handbooks (KRC-08090) provides a factor λ applied to initial deflection forestimating the additional long-term deflection of non-prestressed reinforced concrete members as shown in thefollowing equation
λ ξ
1 + 50ρprime (1)
where ρprime is the ratio of compressive reinforcement and ξ isthe time-dependent factor for sustained loads to be equal to20 for 5 years or more 14 for 12 months 12 for 6 monthsand 10 for 3 months
HindawiAdvances in Civil EngineeringVolume 2018 Article ID 1391590 13 pageshttpsdoiorg10115520181391590
It should be noted that (1) of KR C-08090 [1] actuallycomes from the equation presented by ACI 318-14 [2] -eACI 318 code [2] is primarily for building applications notfor bridges Moreover both KR C-08090 [1] and ACI 318-14[2] do not provide specific design guideline such as pre-diction equations for long-term behavior of PSC members-e ACI 318-14 [2] merely suggests an abstract guidelinethat additional time-dependent deflections of PSC memberscan be calculated by considering the stresses of concrete andsteel bars under sustained load the creep and shrinkageeffects of concrete and the relaxation of PS steels
Alternatively the long-term deflection of PSC bridgescan be calculated by using the concrete creep coefficient anddrying shrinkage formulas given in various standards [3ndash5]However such formulas are somewhat complicated to use inpractice because they need to take into consideration variousparameters including concrete mix proportion and sur-rounding environment -ey also do not fully account forthe effects and losses of the prestress Moreover eventhrough these complex methods there is no guarantee ofhighly accurate predictions
Until recently many researchers have proposed variousmethods to predict the long-term behavior of PSC bridges[6ndash11] However the reliability of such predictions has not beensufficiently verified and these methods are difficult and com-plicated for designers to understand and use In addition due torecent advances in computer technology many researchers aretrying to predict and evaluate the long-term behavior of PSCbridges by numerical analysis using the finite differencemethodor finite element method [12ndash17] but for designers a simpleand clear prediction method is more preferable
On the contrary the PCI Bridge Design Manual [18]presents multipliers that can be easily used to predict long-term deformation of PSC bridges However in the PCIBridge Design Manual [18] the multipliers can be appliedonly to two points of time erection and final In practice thetiming of the girder construction of PSC bridges can varygreatly depending on the site conditions and the long-term
deflection should be checked out at any important time inaddition to the time of erection and final depending onvarious construction plans and processes Furthermoresince the PCI Bridge Design Manual [18] multipliers arebased on the 1977 Martinrsquos study [19] it is difficult to saythat they properly reflect the characteristics of various crosssections of modern PSC bridges
-erefore in this study modified PCImultipliers for long-term deflection of PSC bridges considering various con-struction schedules and cross sections of modern PSC bridgeswere proposed so that the time-dependent deformation of PSCbridges can be more easily and accurately predicted
2 PCI Bridge Design Manual Basic Multipliers
Table 1 shows the basic multipliers presented in the PCIBridge Design Manual [18] for predicting long-term cam-bers and deflections of PSC members Derivation of thesemultipliers is in [19]
In (1) for the nonprestressed concrete the base factor foradditional long-term deflection μb is 20 in the absence ofcompressive reinforcement For PSC members howeversince the elastic deflection due to member weight at therelease of the prestress not at the standard age of 28 days ismultiplied by the long-time factor the factor should becalculated considering the elastic modulus Eci at the time ofrelease not the elastic modulus Ec at 28 days as follows
μdf Eci
Ecμb (2)
Since Eci is about 85 of Ec and μb is 20 (2) would thenbecome μdf 17 As shown in Table 1 therefore themultiplier for deflection at final is 1 + μdf 27
In the PCI Bridge Design Manual [18] it is assumed thatthe period from casting to erection is about 30ndash60 days andin this period creep and drying shrinkage which are themain factors of the long-term behavior will have reachedabout 40 to 60 of the ultimate value Using the average
Table 1 PCI Bridge Design Manual basic multipliers [18]
Without composite topping With composite toppingAt erection(1) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
185 185
(2) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
180 180
Final(3) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
270 240
(4) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
245 220
(5) Deflection (downward)mdashapply to elasticdeflection due to superimposed dead load only 300 300
(6) Deflection (downward)mdashapply to elasticdeflection caused by the composite topping mdash 230
2 Advances in Civil Engineering
value of 50 therefore the long-term deflection coefficientat erection is presented as the following equation
1 + μde 1 + 05μdf (3)
-e multiplier for deflection at erection would then be1 + 05(17) 185
In deriving the multiplier for the camber in the PCIBridge Design Manual [18] the prestress loss is taken intoaccount -at is the method of obtaining the long-termcamber by multiplying the long-time factor by the elasticcamber at the release of the prestress is the same as (2) butconsidering the prestress loss which is a phenomenon inwhich the prestress as a sustained load decreases over time-e long-term prestress loss is assumed to be 15 of theinitial force -erefore using μdf in (2) factor for final long-time camber can be expressed as follows
μpf μdfP
P0 (4)
-erefore the multiplier used to determine the camberdue to prestress is 1 + μpf 1 + 17(085) 245
-emultiplier for the camber due to prestress at the timeof erection is derived in the same way as (3) is derived -elong-term loss of prestress is governed by long-term be-havior factors such as creep and shrinkage of concrete So ifthese long-term behavior factors occur 50 of ultimate aterection prestress loss will also result in one-half of the long-time total loss 15 Applying this to (4) the multiplier forthe camber caused by the prestress at the time of erection canbe calculated as follows
1 + μpe 1 + μde(1minus 015 times 050) (5)
-erefore the multiplier applied to the initial upwardcamber caused by prestressing force is equal to be1 + μpe 1 + 085(0925) asymp 180
Since the long-term deflection due to the superimposedsustained dead load depends on the creep the multiplier isexpressed by the following equation using the basic factorμb 20
1 + μsdf 1 + 20 30 (6)
In addition the PCI Bridge Design Manual [18] providesmultipliers for composite members by taking into accountthe effect of increased moment of inertia due to topping Asshown in the following equations the effect of topping on
the deflection and camber is taken into account by multi-plying the difference between long-time factors at erectionand final by the ratio of noncomposite to composite mo-ments of inertia IoIc
μdfc μde + μdf minus μde( 1113857Io
Ic1113888 1113889 (7)
μpfc μpe + μpf minus μpe1113872 1113873Io
Ic1113888 1113889 (8)
Here the PCI Bridge Design Manual [18] assumes that thesection becomes composite at about the time of erection -ethickness of the topping is assumed to be 2 inches and the valueof IoIc is assumed to be 065 for commonly used members-erefore if these values are substituted in (7 and 8) themultiplier for deflection and camber of the composite memberwith topping is 240 and 220 respectively as shown in Table 1
3 PCI Bridge Design ManualImproved Multipliers
As shown in Table 2 the PCI Bridge Design Manual 2ndEdition [20] suggested an improved multiplier method pro-posed by Tadros et al [21] -is method is very similar to thebasic multiplier method described in the preceding sectionAccording to the manual however this method provides twoimprovements First it provides more accurate coefficients forcases where the reliable creep coefficient is known or high-performance concrete with a very low creep coefficient is usedSecond the prediction of the deflection caused by the prestressloss can be calculated by considering the amount of prestressloss actually occurred However it is not easy to know thecorrect creep coefficient and the actual prestress loss at thedesign stage Moreover there are many variables that must becalculated separately to derive the multiplier which is some-what inconvenient for designers to use However since theaverage value is presented it can be used effectively It is notedthat the improved multiplier method has been deleted in thecurrent PCI Bridge Design Manual 3rd Edition [18]
4 Development of Proposed Multipliers
41ModificationofPCIMultipliers forPredictionatAnyTimeAs mentioned earlier the PCI Bridge Design Manual [18]provides multipliers only for at the time of erection and final
Table 2 PCI Bridge Design Manual improved multipliers [20]
Load conditionErection time Final time
Formula Average Formula AverageInitial prestress 1 + Ca 196 1 + Cu 288Prestress loss αa(1 + χCa) 100 (1 + χCu) 232Self-weight 1 + Ca 196 1 + Cu 288Dead load on plain beam 100 100 1 + Cuprime 250Dead load on composite beam 100 100 1 + Cuprime 250Cu ultimate creep coefficient for loads applied immediately after transfer and the average value is 188 Cuprime ultimate creep coefficient for loads applied attime of erection and the average value is 150 Ca creep coefficient for loading applied immediately after transfer and strains measured at time of erectionand the average value is 096 αa time-dependent prestress loss at erection divided by total time-dependent prestress loss and the average value is 060χ Bazantrsquos aging coefficient and the average value is 070
Advances in Civil Engineering 3
Moreover it is assumed that the erection time is about 30ndash60days after casting In practice however the time of erection isvery flexible depending on the site conditions-erefore in thisstudy the multipliers applicable at any time including thevarious time of erection were suggested by considering the rateof creep and drying shrinkage It can be useful for field con-struction management and maintenance of structures if thecamber or deflection can be predicted at any time after casting
Equations (3) and (5) were modified using rt the rate ofcreep and drying shrinkage over time
1 + μdt 1 + rt times μdf (9)
1 + μpt 1 + μdt 1minus 015 times rt( 1113857 (10)
where t is the time after casting and μdt and μpt are the factorsfor time-dependent deflection and camber at the time of t
applied to initial deformation caused by member weight andprestressing force respectively μdf is 17 as in the PCI BridgeDesign Manual [18] If the time of the erection is t(e) themultiplier for the deflection and camber at erection can beexpressed by substituting t(e) in (9) and (10) as follows
1 + μdt(e) 1 + rt(e) times μdf
1 + μpt(e) 1 + μdt(e) 1minus 015 times rt(e)1113872 1113873(11)
Also the multiplier for the long-term deflection due tothe superimposed dead load at any time can be expressed bythe following equation
1 + μsdt 1 + r[tminust(s)] times μsdf (12)
where μsdt is the factor for additional long-time deflection attime t applied to initial deflection caused by superimposeddead load and t(s) is the time at which the superimposed
dead load is applied μsdf is 20 as in the PCI Bridge DesignManual [18]
-e creep and drying shrinkage predictions presented inACI 209R-92 [3] were used to calculate the rate of creep andshrinkage over time rt For creep and shrinkage understandard condition the relationship between at any time andat final is given by (13) and (14) respectively
vt t06
10 + t06vu (13)
εsh( 1113857t t
35 + tεsh( 1113857u (14)
where t time in days vt creep coefficient at any timevu ultimate creep coefficient (εsh)t shrinkage strain atany time and (εsh)u ultimate shrinkage strain
Long-term behavior is both affected by creep and dryingshrinkage at the same time -erefore rt the rate of creepand drying shrinkage over time were derived from theaverage of (13) and (14) as shown in (15) Figure 1 shows thegraphs of creep and drying shrinkage rates over time
rt 12
t06
10 + t06 +t
35 + t1113888 1113889 (15)
42 Modification of Multipliers for Composite Member Asmentioned earlier in the PCI Bridge DesignManual [18] forthe composite member the thickness of the topping is as-sumed to be 2 inches and the ratio of noncomposite tocomposite moments of inertia IoIc is 065 for all casesregardless of the shape of cross section However given thevariety of girder geometry and the recent bridge slab deck
0
10
20
30
40
50
60
70
80
90
100
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Tim
e-ra
tio v
alue
s for
cree
p an
d sh
rinka
ge (
)
Elapsed time (day)Creep time ratioShrinkage time ratioAverage time ratio of creep and shrinkage
Figure 1 Rate of creep and drying shrinkage over time
4 Advances in Civil Engineering
thickness the assumptions for composite members in thePCI Bridge Design Manual [18] are not likely to reflectmodern bridge characteristics -erefore in this study themultipliers for the long-term behavior of composite memberwere proposed by analyzing the representative cross sectionsof the recent bridges
Currently girder sections commonly used in single-spanrailway bridges in Korea are I girder box girder and WPC(wide flange prestressed concrete) In general a thickness ofslab placed on the girder is 280mm Figure 2 and Table 3show the details of the cross sections of I girder box girderand WPC which are the representative girder sections ac-tually used in practice Table 4 shows IoIc for all cross
sections of Figure 2 and Table 3 As shown in Table 4 thevalue of IoIc is different from 065 of the PCI Bridge DesignManual [18] IoIc was in the range of 051 to 056 and boxgirder bridges and long span bridges tend to have relativelylarge IoIc For the convenience of design this study pro-posed to use the total average value of 053 for IoIc
-e PCI Bridge Design Manual [18] assumed that thesection becomes composite at about the time of erectionbut it is not always Rather there are many cases wheretopping is not applied when the girder is erected because offield condition and construction schedules -ereforemultipliers have been proposed to enable the prediction ofdeflection and camber of the composite member at anytime t by considering the time t(c) at which the sectionbecomes composite -is can be expressed as follows using(7)ndash(10)
1 + μdtc 1 + μdt(c) + μdt minus μdt(c)1113872 1113873Io
Ic1113888 1113889
1 + μptc 1 + μpt(c) + μpt minus μpt(c)1113872 1113873Io
Ic1113888 1113889
(16)
where IoIc is 053-e factor for long-term deflection by a composite
topping should be also modified by the ratio of IoIc becausethe elastic deflection caused by the placement of the toppingto which the factor is applied is calculated using the non-composite section as follows
1 + μtt 1 + μsdtIo
Ic1113888 1113889 (17)
where μtt is the factor for additional long-term deflectioncaused by topping at any time t
As a result the multipliers of the PCI Bridge DesignManual [18] in Table 1 were revised as shown in Table 5
ed
ifg
h
b c ba
j k jl
(a)i
c b
j
da
cb
kl
m
nopq
o
g
n
he f
(b)
p
cb
m
n
q r
de
f
i j kg
lh g
k j i
o
a
(c)
Figure 2 Typical cross sections of PSC bridges (a) I girder (b) box girder (c) WPC girder
Table 3 Cross section dimension of I box and WPC girders byspan (mm)
Type I girder Box girder WPC girderSpan 25m 30m 35m 30m 35m 40m 30m 35m 40m 1000 1000 1000 1200 1200 1200 3580 3580 2650 400 400 400 220 220 220 150 150 150 200 200 200 50 50 50 100 100 100 80 150 150 660 660 660 982 1135 1514 90 120 120 2000 2400 2600 116 115 86 1520 1550 1950 1900 2300 2500 350 500 450 240 180 180 30 30 30 98 113 151 320 200 200 70 70 70 1181 1150 865 2350 2200 2600 400 350 350 730 730 370 240 350 350 50 50 50 110 110 110 200 200 200 1080 1530 1730 145 175 205 680 900 900 220 220 220 1610 1550 1280 mdash mdash mdash 250 250 250 1700 2000 2300 mdash mdash mdash 30 30 30 1450 1750 2050 mdash mdash mdash 220 220 220 135 135 135 mdash mdash mdash 760 760 760 115 115 115 mdash mdash mdash 1260 1260 1260 480 480 120 mdash mdash mdash mdash mdash mdash 250 250 250
Advances in Civil Engineering 5
5 Verification of Proposed Multipliers
In order to verify the proposed multipliers for actuallyconstructed PSC bridges the predictions of long-termcamber and deflection by the proposed multipliers werecompared with those by the basic PCI multipliers [18] theimproved PCI multipliers [20] and KR C-08090 [1] (same asACI 318-14 [2]) In addition numerical analysis was per-formed and the results were compared with the results fromother prediction methods
51 PSCBridges forVerification PSC bridges A and B whichwere recently constructed on a new line from Wonju toGangneung in Korearsquos high-speed railway were selected toverify the prediction methods Bridge A is a WPC type witha span of 388m and bridge B is constructed with an I-girdertype with a span of 34m -e cross-sectional details of thebridges at midspan are shown in Figure 3 Tables 6 and 7
show the construction history of the bridges and the elasticdeformation due to the applied load respectively
52 Numerical Analysis for Long-Term Behavior of PSCBridges Long-term behavior of the bridges A and B waspredicted using MIDAS Civil a general-purpose finite el-ement analysis program-e validity of theMIDAS Civil hasalready been confirmed through previous researches [22ndash24] In general the prediction of long-term behavior usinga finite element analysis is known to have a higher accuracythan that of the methods using a multiplier such as the PCIBridge Design Manual [18 20] although the design con-venience is poor [25ndash28] -erefore the numerical analysisresults were used to verify the newly proposed multipliers
-ematerial model was selected from the database of theMIDAS Civil program C40 and C27 were selected forthe girder and deck concrete respectively and the strandof SWPC7B empty152mm was selected for PS steel -ese
Table 4 Ratio of noncomposite to composite moments of inertia by girder type and span
Span PCI Bridge Design Manual I girder Box girder WPC girder Average25m
065
051 mdash mdash 05130m 049 054 053 05235m 052 056 050 05340m mdash 057 054 056Average 065 051 056 052 053
Table 5 Proposed multipliers
Without topping With toppingAt erection(1) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
1 + 17rt(e) 1 + 17rt(e)
(2) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
1 + 17rt(e)(1minus 015rt(e)) 1 + 17rt(e)(1minus 015rt(e))
At certain time(3) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
1 + 17rt 1 + 08rt(c) + 09rt
(4) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
1 + 17rt(1minus 015rt) 1 + 08rt(c)(1minus 015rt(c)) + 09rt(1minus 015 times rt)
(5) Deflection (downward)mdashapply to elasticdeflection due to superimposed dead load only 1 + 20r[tminust(s)] 1 + 20r[tminust(s)]
(6) Deflection (downward)mdashapply to elasticdeflection caused by the composite topping mdash 1 + 106r[tminust(c)]
Final(7) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
270 19 + 08rt(c)
(8) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
245 1765 + 08rt(c)(1minus 015rt(c))
(9) Deflection (downward)mdashapply to elasticdeflection due to superimposed dead load only 300 300
(10) Deflection (downward)mdashapply to elasticdeflection caused by the composite topping mdash 206
6 Advances in Civil Engineering
materials are the same as concrete and PS steel actually usedfor bridges A and B -e structural members of the bridgeswere modeled based on structural calculations and designdrawings of bridges A and B According to the designdrawing the strands were arranged by setting the actualcoordinates of the strand on the girder nodes using the 3-Dinput type from tendon profile option of MIDAS Civil -eCEB-FIP MC90 model [5] was used to calculate creep anddrying shrinkage of concrete For the relaxation of thetendon the Magura 45 model was used to consider thetime-dependent loss of the prestress Based on the con-struction history of the bridges A and B in Table 6construction sequence analysis was carried out After thecast of deck composite behavior of the girder and the deckwas simulated through the node connection using the rigidtype of elastic link In the same way common duct which isthe additional superimposed dead load was also simulatedfor composite behavior after its installation At the finalstage the deformation patterns of bridges A and B areshown in Figure 4 As a result the bridges A and B in themidspan showed 324mm and 393mm of camber at girdererection and 297mm and 192mm of camber at finalrespectively
53 Comparison of Predictions of Long-Term DeformationTables 8 and 9 and Figure 5 show the predictions of the long-term deformation of bridges A and B by using the proposedmultipliers the basic PCI multipliers [18] the improved PCImultipliers [20] KR C-08090 [1] and numerical analysisFor the improved PCI multipliers [20] the average values inTable 2 were used because the actual creep coefficient and theamount of the prestress loss can hardly be known
Although the values of predictions by the proposedmultipliers and KR C-08090 [1] were somewhat different
from the prediction by numerical analysis their predictiontrends of the camber over time were generally similar be-cause they provided available multipliers at any time In thecase of the basic PCI multipliers [18] however the long-term behavior after the erection was quite different fromother prediction methods because there are no applicablelong-term factors for the period between the erection andthe final
-e girder of bridge A was erected on the 30th day aftercasting while the girder of bridge B was erected on the 150thday relatively long time after casting -e basic PCI
1025 90 420 90 1025
2650
120
100
110
2670 30
00
150
2250
600
220
95 600150
2190
60600
3000
600
1040 110 695110695
(a)
400 200 4001000
2600
150
120
1950
180
200
2600
200 350350
900
(b)
Figure 3 Cross-sectional details of bridges (a) A and (b) B
Table 6 Construction history of bridges A and B
EventTime from casting (days)Bridge A Bridge B
(1) Release 1 1(2) Erection (t(e)) 30 150(3) Topping (t(c)) 240 157(4) 1st random time (t1) 270 180(5) Superimposed dead load (t(s)) 390 360(6) 2nd random time (t2) 700 1000
(7) Final 5 years ormore
5 years ormore
Table 7 Elastic camber and deflection of bridges A and B
LoadCamber (+) or deflection (minus)Bridge A Bridge B
Self-weight minus223 minus165Prestressing force +461 +353Topping minus80 minus75Superimposed dead load minus25 minus265
Advances in Civil Engineering 7
multiplier method [18] calculated the long-term camberusing the same multiplier for both bridges regardless of thedifferent erection time while the new proposed method useddifferent long-term multipliers for the bridges A and B inorder to consider different creep and shrinkage rates Asa result the predictions at erection by the proposed methodwere smaller for bridge A and larger for bridge B than thoseby the basic PCI multiplier method [18] as shown inFigure 5
In terms of the long-term behavior after erection thecamber predicted by KR C-08090 [1] was generally thelargest among all prediction methods KR C-08090 [1] doesnot take into account prestress loss so it overestimates thecamber by prestress force -e predictions by the proposedmethod were larger than the predictions by numericalanalysis until about 200 days after superimposed dead loadwas applied and thereafter they were smaller than thepredictions by numerical analysis
When comparing the camber at final the predictionswere large in the order of KR C-08090 [1] numericalanalysis proposed method improved PCI multipliers [20]and basic PCI multipliers [18] for both bridges A and BNumerical analysis seems to estimate the effect of creep and
shrinkage on long-term deformation weaker than othermethods In comparison with numerical analysis for de-formation at the final difference rates of the proposedmethod basic PCI multipliers [18] improved PCI multi-pliers [20] and KR C-08090 [1] were 101 259 116and 343 for bridge A respectively and 146 331143 and 350 for bridge B respectively It is interestingto note that the proposed formula and the improved PCImultiplier method [20] show very similar prediction resultsof ultimate deformation at final
Figure 6 shows the long-term behavior predicted by theproposed multipliers for each load type In early agesa relatively large amount of camber was observed due to theprestress but as time went by the rate of increase of camberby prestress decreased sharply because the amount of creepand drying shrinkage converged and the PS steel relaxationincreased -e amount of deflection due to self-weight wassmaller than the camber due to the prestress but the ten-dency of deflection over time was very similar to that ofcamber On the contrary after the girder erection a con-siderable amount of immediate deflection and long-termdeflection due to dead loads such as topping and commonduct partially offset the camber
000000e + 000270033e + 000540066e + 000810100e + 000108013e + 001135017e + 001162020e + 001189023e + 001216027e + 001243030e + 001270033e + 001297037e + 001
MIDASCivilpostndashprocessorDisplacementYZ-direction
(a)
000000e + 000175416e + 000350832e + 000526248e + 000701664e + 001877080e + 001105250e + 001122791e + 001140333e + 001157874e + 001175416e + 001192958e + 001
MIDASCivilpostprocessorDisplacementYZ-direction
(b)
Figure 4 Analysis result of final deformation of bridges (a) A and (b) B
8 Advances in Civil Engineering
Tabl
e8
Predictio
nsby
variou
smetho
dsforbridge
A(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus2
230
176
minus3929
236
minus5265
237
minus5291
241
minus5364
245
minus5453
254minus5
665
Prestress
4610
171
7887
220
10130
221
10171
223
10284
226
10420
233
10734
Topp
ing
minus800
148
minus1180
178
minus1427
192
minus1533
206minus1
648
Superimpo
sed
dead
load
minus250
266
minus664
300minus7
50
Total
2380
3957
4066
3700
3243
2771
2671
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus2
230
185
minus4126
minus4126
minus4126
240minus5
352
Prestress
4610
180
8298
8298
8298
220
10142
Topp
ing
minus800
minus800
230minus1
840
Superimpo
sed
dead
load
minus250
300minus7
50
Total
2380
4173
3373
3123
2200
Improved
PCI
BDM
Self-weigh
tminus2
230
196
minus4371
minus4371
minus4371
288minus6
422
Prestress
4610
196
9036
9036
9036
288
13277
Prestresslossminus6
92
100
minus692
minus692
minus692
232minus1
604
Topp
ing
minus800
minus800
250minus2
000
Superimpo
sed
dead
load
minus250
250minus6
25
Total
2380
3973
3173
2923
2625
KRC-08090
Self-weigh
tminus2
230
150
minus3345
227
minus5062
230
minus5129
245
minus5464
265
minus5910
300minus6
690
Prestress
4610
150
6915
227
10465
230
10603
245
11295
265
12217
300
13830
Topp
ing
minus800
150
minus1200
215
minus1720
250
minus2000
300minus2
400
Superimpo
sed
dead
load
minus250
235
minus588
300minus7
50
Total
2380
3570
4603
4274
3861
3720
3990
Num
erical
analysis
Total
2348
3237
3446
3240
2988
2894
2970
Advances in Civil Engineering 9
Tabl
e9
Predictio
nsby
variou
smetho
dsforbridge
B(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus1
650
226
minus3725
227
minus3744
229
minus3771
236
minus3886
242
minus3994
250minus4
120
Prestress
3530
212
7477
213
7508
214
7553
219
7740
224
7909
230
8102
Topp
ing
minus750
142
minus1065
183
minus1370
196
minus1470
206minus1
545
Superimpo
sed
dead
load
minus265
278
minus736
300minus7
95
Total
1880
3752
3014
2717
2218
1710
1642
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus1
650
185
minus3053
minus3053
minus3053
240minus3
960
Prestress
3530
180
6354
6354
6354
220
7766
Topp
ing
minus750
minus750
230minus1
725
Superimpo
sed
dead
load
minus265
300minus7
95
Total
1880
3302
2552
2287
1286
Improved
PCI
BDM
Self-weigh
tminus1
650
196
minus3234
minus3234
minus3234
288minus4
752
Prestress
3530
196
6919
6919
6919
288
10166
Prestresslossminus5
30
100
minus530
minus530
minus530
232minus1
228
Topp
ing
minus750
minus750
250minus1
875
Superimpo
sed
dead
load
minus265
250minus6
63
Total
1880
3155
2405
2140
1648
KRC-08090
Self-weigh
tminus1
650
210
minus3465
211
minus3482
220
minus3630
240
minus3960
280
minus4620
300minus4
950
Prestress
3530
210
7413
211
7448
220
7766
240
8472
280
9884
300
10590
Topp
ing
minus750
150
minus1125
220
minus1650
275
minus2063
300minus2
250
Superimpo
sed
dead
load
minus265
265
minus702
300minus7
95
Total
1880
3948
3217
3011
2597
2499
2595
Num
erical
analysis
Total
1792
3926
2866
2536
2138
1954
1923
10 Advances in Civil Engineering
Consequently the proposed multipliers method pro-vided not only the closest prediction values but also themost similar long-term behavior trend to the numericalanalysis
6 Conclusions
Since the current PCI Bridge Design Manual [18] providesthe long-term deformation multipliers only at erection andfinal it cannot consider various construction processesFurthermore the multipliers for the composite cross sectionare also required to be modified to reflect the characteristicsof the cross section used in modern PSC bridges -ereforein this study newmodified PCImultipliers were proposed toovercome these problems -e conclusions drawn from thisstudy are as follows
(1) -e new modified PCI multipliers were proposed byusing the rate of creep and shrinkage over timeUnlike the existing PCI Bridge Design Manual [18]method it is possible to reflect the actual girdererection time and predict the long-term deformationfor any construction schedule Moreover throughthe new method camber and deflection of PSCbridges can be predicted at any time including designstage construction stage and use stage
(2) -e ratio of noncomposite to composite moments ofinertia IoIc was 051ndash056 as a result of analyzingrepresentative cross sections used in practice byspan while the PCI Bridge Design Manual [18]suggests 065 of IoIc-erefore it is suggested to usethe average value of 053 for IoIc in order to predictthe long-term behavior of composite members
ndash80
ndash60
ndash40
ndash20
0
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
PS forceSelf-weight
ToppingAdditional DL
(a)
ToppingPS forceSelf-weight Additional DL
0
ndash80
ndash60
ndash40
ndash20
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 6 Predictions by the proposed multipliers for each load type (a) Bridge A (b) Bridge B
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
(a)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 5 Comparison of various predictions for bridges (a) A and (b) B
Advances in Civil Engineering 11
(3) In order to verify the proposed multipliers for ac-tually constructed PSC bridges the predictions oflong-term camber and deflection by the proposedmultipliers were compared with those by the basicPCI multipliers [18] improved PCI multipliers [20]KR C-08090 [1] and numerical analysis As a resultKR C-08090 [1] predictions were significantly higherthan the other predictions and the basic PCI mul-tipliers [18] did not show a reasonable tendency inthe long-term behavior between the erection timeand the final Among all methods except the pro-posed method the improved PCI multipliers [20]showed the most similar predictions to the nu-merical analysis However this improved PCImultiplier method also has limitations in finding thelong-term deflection or camber of the bridge at anytime and there are several variables such as the creepcoefficient that must be known precisely in order touse the multipliers which is inconvenient for de-signers to use However the predictions through thenewly proposed multipliers showed a reasonablelong-term behavior trend and the amount of thefinal camber was also the most similar to the nu-merical analysis result Above all the proposedmethod can make it possible for the designer topredict the long-term behavior of the bridge veryeasily according to any construction schedule
Data Availability
-e data used to support the findings of this study areavailable from the corresponding author upon request
Conflicts of Interest
-e authors declare that they have no conflicts of interest
Acknowledgments
-is research was supported by a grant (17RTRP-B067919-05) from Railroad Technology Research Program funded byMinistry of Land Infrastructure and Transport of Koreangovernment
References
[1] Korea Rail Network Authority Railway Design Guidelines andHandbooks Bridge Concrete Track Ends Usability Review (KRC-08090) in Korean Korea Rail Network Authority DaejeonRepublic of Korea 2014
[2] ACI Committee 318 Building Code Requirements for Struc-tural Concrete (ACI 318-14) and Commentary AmericanConcrete Institute Farmington Hills MI USA 2014
[3] ACI Committe 209 Prediction of Creep Shrinkage andTemperature Effects in Concrete Structure American ConcreteInstitute Farmington Hill MI USA 1992
[4] AASHTO (American Association of State Highway andTransportation Officials) AASHTO LRFD Bridge DesignSpecifications AASHTO Washington DC USA 2007
[5] CEBFIP Model Code Comit Euro-International du BetonTelford Ltd London UK 1990
[6] H-G Kwak and Y-J Seo ldquoLong-term behavior of compositegirder bridgesrdquo Computers and Structures vol 74 no 5pp 583ndash599 2000
[7] H Yang ldquoUncertainty and updating of long-term predictionof prestress forces in PSC box girder bridgesrdquo Computers andStructures vol 83 no 25ndash26 pp 2137ndash2149 2005
[8] S Biswal and A Ramaswamy ldquoUncertainty based modelaveraging for prediction of long-time prestress losses inconcrete structuresrdquo Construction and Building Materialsvol 153 pp 469ndash480 2017
[9] W He and Z Zhang ldquoModeling creep fracture in rock byusing kelvin discretized virtual internal bondrdquo Advances inCivil Engineering vol 2018 Article ID 8042965 8 pages 2018
[10] Y-S Park Y-H Lee and Y Lee ldquoDescription of concretecreep under time-varying stress using parallel creep curverdquoAdvances in Materials Science and Engineering vol 2016Article ID 9370514 13 pages 2016
[11] Z Pan and S Meng ldquo-ree-level experimental approach forcreep and shrinkage of high-strength high-performanceconcreterdquo Engineering Structures vol 120 pp 23ndash36 2016
[12] H-G Kwak and Y-J Seo ldquoNumerical analysis of time-dependent behavior of pre-cast pre-stressed concrete girderbridgesrdquo Construction and Building Materials vol 16 no 1pp 49ndash63 2002
[13] I N Robertson ldquoPrediction of vertical deflections for a long-span prestressed concrete bridge structurerdquo EngineeringStructures vol 27 no 12 pp 1820ndash1827 2005
[14] T Lou S M R Lopes and A V Lopes ldquoA finite elementmodel to simulate long-term behavior of prestressed concretegirdersrdquo Finite Elements in Analysis and Design vol 81pp 48ndash56 2014
[15] P Liu Q Xing DWang andM Oeser ldquoApplication of linearviscoelastic properties in semianalytical finite element methodwith recursive time integration to analyze asphalt pavementstructurerdquo Advances in Civil Engineering vol 2018 Article ID9045820 15 pages 2018
[16] A Sagara and I Pane ldquoA study on effects of creep andshrinkage in high strength concrete bridgesrdquo Procedia En-gineering vol 125 pp 1087ndash1093 2015
[17] H Sousa J Bento and J Figueiras ldquoConstruction assessmentand long-term prediction of prestressed concrete bridgesbased on monitoring datardquo Engineering Structures vol 52pp 26ndash37 2013
[18] PCI Bridge Design Manual Second Release PrecastPrestressed Concrete Institute Chicago IL USA 3rd edi-tion 2014
[19] L D Martin ldquoA rational method for estimating camber anddeflection of precast prestressed membersrdquo PCI Journalvol 22 no 1 pp 100ndash108 1977
[20] PCI Bridge Design Manual PrecastPrestressed ConcreteInstitute Chicago IL USA 2nd edition 2003
[21] M K Tadros A Ghali and A W Meyer ldquoPrestressed lossand deflection of precast concrete membersrdquo PCI Journalvol 30 no 1 pp 114ndash141 1985
[22] Y Zhang ldquoOrthogonal test analysis on influencing factors ofprestressed concrete small box beam camberrdquo Applied Me-chanics and Materials vol 405-408 pp 1527ndash1530 2013
[23] Y Jianjun W Xun and H Xianzheng ldquoEffects of live load onthe deflection of long-span PC continuous rigid-framehighway bridge based on midasrdquo in Proceedings of 20147th International Conference on Intelligent ComputationTechnology and Automation pp 944ndash946 Changsha China2014
12 Advances in Civil Engineering
[24] T Grigorjeva A Juozapaitis and Z Kamaitis ldquoStatic analysisand simplified design of suspension bridges having variousrigidity of cablesrdquo Journal of Civil Engineering and Man-agement vol 16 no 3 pp 363ndash371 2011
[25] ACI Committee 435 Control of Deflection in ConcreteStructures ACI 435R-95 ACI Farmington Hills MI USA2003
[26] F B Angomas ldquoBehavior of prestressed concrete bridgegirdersrdquo All Graduate -eses and Dissertations Utah StateUniversity Logan UT USA 2009
[27] E H Gheitanbaf ldquoImproving the prediction of time-dependent effects on prestressed concrete bridgesrdquo Gradu-ate-eses and Dissertations Iowa State University Ames IAUSA 2015
[28] M K Tadros F Fawzy and K Hanna ldquoPrecast prestressedgirder camber variabilityrdquo PCI Journal vol 56 no 1pp 135ndash154 2011
Advances in Civil Engineering 13
International Journal of
AerospaceEngineeringHindawiwwwhindawicom Volume 2018
RoboticsJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Active and Passive Electronic Components
VLSI Design
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Shock and Vibration
Hindawiwwwhindawicom Volume 2018
Civil EngineeringAdvances in
Acoustics and VibrationAdvances in
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Electrical and Computer Engineering
Journal of
Advances inOptoElectronics
Hindawiwwwhindawicom
Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Control Scienceand Engineering
Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Journal ofEngineeringVolume 2018
SensorsJournal of
Hindawiwwwhindawicom Volume 2018
International Journal of
RotatingMachinery
Hindawiwwwhindawicom Volume 2018
Modelling ampSimulationin EngineeringHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Chemical EngineeringInternational Journal of Antennas and
Propagation
International Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Navigation and Observation
International Journal of
Hindawi
wwwhindawicom Volume 2018
Advances in
Multimedia
Submit your manuscripts atwwwhindawicom
It should be noted that (1) of KR C-08090 [1] actuallycomes from the equation presented by ACI 318-14 [2] -eACI 318 code [2] is primarily for building applications notfor bridges Moreover both KR C-08090 [1] and ACI 318-14[2] do not provide specific design guideline such as pre-diction equations for long-term behavior of PSC members-e ACI 318-14 [2] merely suggests an abstract guidelinethat additional time-dependent deflections of PSC memberscan be calculated by considering the stresses of concrete andsteel bars under sustained load the creep and shrinkageeffects of concrete and the relaxation of PS steels
Alternatively the long-term deflection of PSC bridgescan be calculated by using the concrete creep coefficient anddrying shrinkage formulas given in various standards [3ndash5]However such formulas are somewhat complicated to use inpractice because they need to take into consideration variousparameters including concrete mix proportion and sur-rounding environment -ey also do not fully account forthe effects and losses of the prestress Moreover eventhrough these complex methods there is no guarantee ofhighly accurate predictions
Until recently many researchers have proposed variousmethods to predict the long-term behavior of PSC bridges[6ndash11] However the reliability of such predictions has not beensufficiently verified and these methods are difficult and com-plicated for designers to understand and use In addition due torecent advances in computer technology many researchers aretrying to predict and evaluate the long-term behavior of PSCbridges by numerical analysis using the finite differencemethodor finite element method [12ndash17] but for designers a simpleand clear prediction method is more preferable
On the contrary the PCI Bridge Design Manual [18]presents multipliers that can be easily used to predict long-term deformation of PSC bridges However in the PCIBridge Design Manual [18] the multipliers can be appliedonly to two points of time erection and final In practice thetiming of the girder construction of PSC bridges can varygreatly depending on the site conditions and the long-term
deflection should be checked out at any important time inaddition to the time of erection and final depending onvarious construction plans and processes Furthermoresince the PCI Bridge Design Manual [18] multipliers arebased on the 1977 Martinrsquos study [19] it is difficult to saythat they properly reflect the characteristics of various crosssections of modern PSC bridges
-erefore in this study modified PCImultipliers for long-term deflection of PSC bridges considering various con-struction schedules and cross sections of modern PSC bridgeswere proposed so that the time-dependent deformation of PSCbridges can be more easily and accurately predicted
2 PCI Bridge Design Manual Basic Multipliers
Table 1 shows the basic multipliers presented in the PCIBridge Design Manual [18] for predicting long-term cam-bers and deflections of PSC members Derivation of thesemultipliers is in [19]
In (1) for the nonprestressed concrete the base factor foradditional long-term deflection μb is 20 in the absence ofcompressive reinforcement For PSC members howeversince the elastic deflection due to member weight at therelease of the prestress not at the standard age of 28 days ismultiplied by the long-time factor the factor should becalculated considering the elastic modulus Eci at the time ofrelease not the elastic modulus Ec at 28 days as follows
μdf Eci
Ecμb (2)
Since Eci is about 85 of Ec and μb is 20 (2) would thenbecome μdf 17 As shown in Table 1 therefore themultiplier for deflection at final is 1 + μdf 27
In the PCI Bridge Design Manual [18] it is assumed thatthe period from casting to erection is about 30ndash60 days andin this period creep and drying shrinkage which are themain factors of the long-term behavior will have reachedabout 40 to 60 of the ultimate value Using the average
Table 1 PCI Bridge Design Manual basic multipliers [18]
Without composite topping With composite toppingAt erection(1) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
185 185
(2) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
180 180
Final(3) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
270 240
(4) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
245 220
(5) Deflection (downward)mdashapply to elasticdeflection due to superimposed dead load only 300 300
(6) Deflection (downward)mdashapply to elasticdeflection caused by the composite topping mdash 230
2 Advances in Civil Engineering
value of 50 therefore the long-term deflection coefficientat erection is presented as the following equation
1 + μde 1 + 05μdf (3)
-e multiplier for deflection at erection would then be1 + 05(17) 185
In deriving the multiplier for the camber in the PCIBridge Design Manual [18] the prestress loss is taken intoaccount -at is the method of obtaining the long-termcamber by multiplying the long-time factor by the elasticcamber at the release of the prestress is the same as (2) butconsidering the prestress loss which is a phenomenon inwhich the prestress as a sustained load decreases over time-e long-term prestress loss is assumed to be 15 of theinitial force -erefore using μdf in (2) factor for final long-time camber can be expressed as follows
μpf μdfP
P0 (4)
-erefore the multiplier used to determine the camberdue to prestress is 1 + μpf 1 + 17(085) 245
-emultiplier for the camber due to prestress at the timeof erection is derived in the same way as (3) is derived -elong-term loss of prestress is governed by long-term be-havior factors such as creep and shrinkage of concrete So ifthese long-term behavior factors occur 50 of ultimate aterection prestress loss will also result in one-half of the long-time total loss 15 Applying this to (4) the multiplier forthe camber caused by the prestress at the time of erection canbe calculated as follows
1 + μpe 1 + μde(1minus 015 times 050) (5)
-erefore the multiplier applied to the initial upwardcamber caused by prestressing force is equal to be1 + μpe 1 + 085(0925) asymp 180
Since the long-term deflection due to the superimposedsustained dead load depends on the creep the multiplier isexpressed by the following equation using the basic factorμb 20
1 + μsdf 1 + 20 30 (6)
In addition the PCI Bridge Design Manual [18] providesmultipliers for composite members by taking into accountthe effect of increased moment of inertia due to topping Asshown in the following equations the effect of topping on
the deflection and camber is taken into account by multi-plying the difference between long-time factors at erectionand final by the ratio of noncomposite to composite mo-ments of inertia IoIc
μdfc μde + μdf minus μde( 1113857Io
Ic1113888 1113889 (7)
μpfc μpe + μpf minus μpe1113872 1113873Io
Ic1113888 1113889 (8)
Here the PCI Bridge Design Manual [18] assumes that thesection becomes composite at about the time of erection -ethickness of the topping is assumed to be 2 inches and the valueof IoIc is assumed to be 065 for commonly used members-erefore if these values are substituted in (7 and 8) themultiplier for deflection and camber of the composite memberwith topping is 240 and 220 respectively as shown in Table 1
3 PCI Bridge Design ManualImproved Multipliers
As shown in Table 2 the PCI Bridge Design Manual 2ndEdition [20] suggested an improved multiplier method pro-posed by Tadros et al [21] -is method is very similar to thebasic multiplier method described in the preceding sectionAccording to the manual however this method provides twoimprovements First it provides more accurate coefficients forcases where the reliable creep coefficient is known or high-performance concrete with a very low creep coefficient is usedSecond the prediction of the deflection caused by the prestressloss can be calculated by considering the amount of prestressloss actually occurred However it is not easy to know thecorrect creep coefficient and the actual prestress loss at thedesign stage Moreover there are many variables that must becalculated separately to derive the multiplier which is some-what inconvenient for designers to use However since theaverage value is presented it can be used effectively It is notedthat the improved multiplier method has been deleted in thecurrent PCI Bridge Design Manual 3rd Edition [18]
4 Development of Proposed Multipliers
41ModificationofPCIMultipliers forPredictionatAnyTimeAs mentioned earlier the PCI Bridge Design Manual [18]provides multipliers only for at the time of erection and final
Table 2 PCI Bridge Design Manual improved multipliers [20]
Load conditionErection time Final time
Formula Average Formula AverageInitial prestress 1 + Ca 196 1 + Cu 288Prestress loss αa(1 + χCa) 100 (1 + χCu) 232Self-weight 1 + Ca 196 1 + Cu 288Dead load on plain beam 100 100 1 + Cuprime 250Dead load on composite beam 100 100 1 + Cuprime 250Cu ultimate creep coefficient for loads applied immediately after transfer and the average value is 188 Cuprime ultimate creep coefficient for loads applied attime of erection and the average value is 150 Ca creep coefficient for loading applied immediately after transfer and strains measured at time of erectionand the average value is 096 αa time-dependent prestress loss at erection divided by total time-dependent prestress loss and the average value is 060χ Bazantrsquos aging coefficient and the average value is 070
Advances in Civil Engineering 3
Moreover it is assumed that the erection time is about 30ndash60days after casting In practice however the time of erection isvery flexible depending on the site conditions-erefore in thisstudy the multipliers applicable at any time including thevarious time of erection were suggested by considering the rateof creep and drying shrinkage It can be useful for field con-struction management and maintenance of structures if thecamber or deflection can be predicted at any time after casting
Equations (3) and (5) were modified using rt the rate ofcreep and drying shrinkage over time
1 + μdt 1 + rt times μdf (9)
1 + μpt 1 + μdt 1minus 015 times rt( 1113857 (10)
where t is the time after casting and μdt and μpt are the factorsfor time-dependent deflection and camber at the time of t
applied to initial deformation caused by member weight andprestressing force respectively μdf is 17 as in the PCI BridgeDesign Manual [18] If the time of the erection is t(e) themultiplier for the deflection and camber at erection can beexpressed by substituting t(e) in (9) and (10) as follows
1 + μdt(e) 1 + rt(e) times μdf
1 + μpt(e) 1 + μdt(e) 1minus 015 times rt(e)1113872 1113873(11)
Also the multiplier for the long-term deflection due tothe superimposed dead load at any time can be expressed bythe following equation
1 + μsdt 1 + r[tminust(s)] times μsdf (12)
where μsdt is the factor for additional long-time deflection attime t applied to initial deflection caused by superimposeddead load and t(s) is the time at which the superimposed
dead load is applied μsdf is 20 as in the PCI Bridge DesignManual [18]
-e creep and drying shrinkage predictions presented inACI 209R-92 [3] were used to calculate the rate of creep andshrinkage over time rt For creep and shrinkage understandard condition the relationship between at any time andat final is given by (13) and (14) respectively
vt t06
10 + t06vu (13)
εsh( 1113857t t
35 + tεsh( 1113857u (14)
where t time in days vt creep coefficient at any timevu ultimate creep coefficient (εsh)t shrinkage strain atany time and (εsh)u ultimate shrinkage strain
Long-term behavior is both affected by creep and dryingshrinkage at the same time -erefore rt the rate of creepand drying shrinkage over time were derived from theaverage of (13) and (14) as shown in (15) Figure 1 shows thegraphs of creep and drying shrinkage rates over time
rt 12
t06
10 + t06 +t
35 + t1113888 1113889 (15)
42 Modification of Multipliers for Composite Member Asmentioned earlier in the PCI Bridge DesignManual [18] forthe composite member the thickness of the topping is as-sumed to be 2 inches and the ratio of noncomposite tocomposite moments of inertia IoIc is 065 for all casesregardless of the shape of cross section However given thevariety of girder geometry and the recent bridge slab deck
0
10
20
30
40
50
60
70
80
90
100
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Tim
e-ra
tio v
alue
s for
cree
p an
d sh
rinka
ge (
)
Elapsed time (day)Creep time ratioShrinkage time ratioAverage time ratio of creep and shrinkage
Figure 1 Rate of creep and drying shrinkage over time
4 Advances in Civil Engineering
thickness the assumptions for composite members in thePCI Bridge Design Manual [18] are not likely to reflectmodern bridge characteristics -erefore in this study themultipliers for the long-term behavior of composite memberwere proposed by analyzing the representative cross sectionsof the recent bridges
Currently girder sections commonly used in single-spanrailway bridges in Korea are I girder box girder and WPC(wide flange prestressed concrete) In general a thickness ofslab placed on the girder is 280mm Figure 2 and Table 3show the details of the cross sections of I girder box girderand WPC which are the representative girder sections ac-tually used in practice Table 4 shows IoIc for all cross
sections of Figure 2 and Table 3 As shown in Table 4 thevalue of IoIc is different from 065 of the PCI Bridge DesignManual [18] IoIc was in the range of 051 to 056 and boxgirder bridges and long span bridges tend to have relativelylarge IoIc For the convenience of design this study pro-posed to use the total average value of 053 for IoIc
-e PCI Bridge Design Manual [18] assumed that thesection becomes composite at about the time of erectionbut it is not always Rather there are many cases wheretopping is not applied when the girder is erected because offield condition and construction schedules -ereforemultipliers have been proposed to enable the prediction ofdeflection and camber of the composite member at anytime t by considering the time t(c) at which the sectionbecomes composite -is can be expressed as follows using(7)ndash(10)
1 + μdtc 1 + μdt(c) + μdt minus μdt(c)1113872 1113873Io
Ic1113888 1113889
1 + μptc 1 + μpt(c) + μpt minus μpt(c)1113872 1113873Io
Ic1113888 1113889
(16)
where IoIc is 053-e factor for long-term deflection by a composite
topping should be also modified by the ratio of IoIc becausethe elastic deflection caused by the placement of the toppingto which the factor is applied is calculated using the non-composite section as follows
1 + μtt 1 + μsdtIo
Ic1113888 1113889 (17)
where μtt is the factor for additional long-term deflectioncaused by topping at any time t
As a result the multipliers of the PCI Bridge DesignManual [18] in Table 1 were revised as shown in Table 5
ed
ifg
h
b c ba
j k jl
(a)i
c b
j
da
cb
kl
m
nopq
o
g
n
he f
(b)
p
cb
m
n
q r
de
f
i j kg
lh g
k j i
o
a
(c)
Figure 2 Typical cross sections of PSC bridges (a) I girder (b) box girder (c) WPC girder
Table 3 Cross section dimension of I box and WPC girders byspan (mm)
Type I girder Box girder WPC girderSpan 25m 30m 35m 30m 35m 40m 30m 35m 40m 1000 1000 1000 1200 1200 1200 3580 3580 2650 400 400 400 220 220 220 150 150 150 200 200 200 50 50 50 100 100 100 80 150 150 660 660 660 982 1135 1514 90 120 120 2000 2400 2600 116 115 86 1520 1550 1950 1900 2300 2500 350 500 450 240 180 180 30 30 30 98 113 151 320 200 200 70 70 70 1181 1150 865 2350 2200 2600 400 350 350 730 730 370 240 350 350 50 50 50 110 110 110 200 200 200 1080 1530 1730 145 175 205 680 900 900 220 220 220 1610 1550 1280 mdash mdash mdash 250 250 250 1700 2000 2300 mdash mdash mdash 30 30 30 1450 1750 2050 mdash mdash mdash 220 220 220 135 135 135 mdash mdash mdash 760 760 760 115 115 115 mdash mdash mdash 1260 1260 1260 480 480 120 mdash mdash mdash mdash mdash mdash 250 250 250
Advances in Civil Engineering 5
5 Verification of Proposed Multipliers
In order to verify the proposed multipliers for actuallyconstructed PSC bridges the predictions of long-termcamber and deflection by the proposed multipliers werecompared with those by the basic PCI multipliers [18] theimproved PCI multipliers [20] and KR C-08090 [1] (same asACI 318-14 [2]) In addition numerical analysis was per-formed and the results were compared with the results fromother prediction methods
51 PSCBridges forVerification PSC bridges A and B whichwere recently constructed on a new line from Wonju toGangneung in Korearsquos high-speed railway were selected toverify the prediction methods Bridge A is a WPC type witha span of 388m and bridge B is constructed with an I-girdertype with a span of 34m -e cross-sectional details of thebridges at midspan are shown in Figure 3 Tables 6 and 7
show the construction history of the bridges and the elasticdeformation due to the applied load respectively
52 Numerical Analysis for Long-Term Behavior of PSCBridges Long-term behavior of the bridges A and B waspredicted using MIDAS Civil a general-purpose finite el-ement analysis program-e validity of theMIDAS Civil hasalready been confirmed through previous researches [22ndash24] In general the prediction of long-term behavior usinga finite element analysis is known to have a higher accuracythan that of the methods using a multiplier such as the PCIBridge Design Manual [18 20] although the design con-venience is poor [25ndash28] -erefore the numerical analysisresults were used to verify the newly proposed multipliers
-ematerial model was selected from the database of theMIDAS Civil program C40 and C27 were selected forthe girder and deck concrete respectively and the strandof SWPC7B empty152mm was selected for PS steel -ese
Table 4 Ratio of noncomposite to composite moments of inertia by girder type and span
Span PCI Bridge Design Manual I girder Box girder WPC girder Average25m
065
051 mdash mdash 05130m 049 054 053 05235m 052 056 050 05340m mdash 057 054 056Average 065 051 056 052 053
Table 5 Proposed multipliers
Without topping With toppingAt erection(1) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
1 + 17rt(e) 1 + 17rt(e)
(2) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
1 + 17rt(e)(1minus 015rt(e)) 1 + 17rt(e)(1minus 015rt(e))
At certain time(3) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
1 + 17rt 1 + 08rt(c) + 09rt
(4) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
1 + 17rt(1minus 015rt) 1 + 08rt(c)(1minus 015rt(c)) + 09rt(1minus 015 times rt)
(5) Deflection (downward)mdashapply to elasticdeflection due to superimposed dead load only 1 + 20r[tminust(s)] 1 + 20r[tminust(s)]
(6) Deflection (downward)mdashapply to elasticdeflection caused by the composite topping mdash 1 + 106r[tminust(c)]
Final(7) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
270 19 + 08rt(c)
(8) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
245 1765 + 08rt(c)(1minus 015rt(c))
(9) Deflection (downward)mdashapply to elasticdeflection due to superimposed dead load only 300 300
(10) Deflection (downward)mdashapply to elasticdeflection caused by the composite topping mdash 206
6 Advances in Civil Engineering
materials are the same as concrete and PS steel actually usedfor bridges A and B -e structural members of the bridgeswere modeled based on structural calculations and designdrawings of bridges A and B According to the designdrawing the strands were arranged by setting the actualcoordinates of the strand on the girder nodes using the 3-Dinput type from tendon profile option of MIDAS Civil -eCEB-FIP MC90 model [5] was used to calculate creep anddrying shrinkage of concrete For the relaxation of thetendon the Magura 45 model was used to consider thetime-dependent loss of the prestress Based on the con-struction history of the bridges A and B in Table 6construction sequence analysis was carried out After thecast of deck composite behavior of the girder and the deckwas simulated through the node connection using the rigidtype of elastic link In the same way common duct which isthe additional superimposed dead load was also simulatedfor composite behavior after its installation At the finalstage the deformation patterns of bridges A and B areshown in Figure 4 As a result the bridges A and B in themidspan showed 324mm and 393mm of camber at girdererection and 297mm and 192mm of camber at finalrespectively
53 Comparison of Predictions of Long-Term DeformationTables 8 and 9 and Figure 5 show the predictions of the long-term deformation of bridges A and B by using the proposedmultipliers the basic PCI multipliers [18] the improved PCImultipliers [20] KR C-08090 [1] and numerical analysisFor the improved PCI multipliers [20] the average values inTable 2 were used because the actual creep coefficient and theamount of the prestress loss can hardly be known
Although the values of predictions by the proposedmultipliers and KR C-08090 [1] were somewhat different
from the prediction by numerical analysis their predictiontrends of the camber over time were generally similar be-cause they provided available multipliers at any time In thecase of the basic PCI multipliers [18] however the long-term behavior after the erection was quite different fromother prediction methods because there are no applicablelong-term factors for the period between the erection andthe final
-e girder of bridge A was erected on the 30th day aftercasting while the girder of bridge B was erected on the 150thday relatively long time after casting -e basic PCI
1025 90 420 90 1025
2650
120
100
110
2670 30
00
150
2250
600
220
95 600150
2190
60600
3000
600
1040 110 695110695
(a)
400 200 4001000
2600
150
120
1950
180
200
2600
200 350350
900
(b)
Figure 3 Cross-sectional details of bridges (a) A and (b) B
Table 6 Construction history of bridges A and B
EventTime from casting (days)Bridge A Bridge B
(1) Release 1 1(2) Erection (t(e)) 30 150(3) Topping (t(c)) 240 157(4) 1st random time (t1) 270 180(5) Superimposed dead load (t(s)) 390 360(6) 2nd random time (t2) 700 1000
(7) Final 5 years ormore
5 years ormore
Table 7 Elastic camber and deflection of bridges A and B
LoadCamber (+) or deflection (minus)Bridge A Bridge B
Self-weight minus223 minus165Prestressing force +461 +353Topping minus80 minus75Superimposed dead load minus25 minus265
Advances in Civil Engineering 7
multiplier method [18] calculated the long-term camberusing the same multiplier for both bridges regardless of thedifferent erection time while the new proposed method useddifferent long-term multipliers for the bridges A and B inorder to consider different creep and shrinkage rates Asa result the predictions at erection by the proposed methodwere smaller for bridge A and larger for bridge B than thoseby the basic PCI multiplier method [18] as shown inFigure 5
In terms of the long-term behavior after erection thecamber predicted by KR C-08090 [1] was generally thelargest among all prediction methods KR C-08090 [1] doesnot take into account prestress loss so it overestimates thecamber by prestress force -e predictions by the proposedmethod were larger than the predictions by numericalanalysis until about 200 days after superimposed dead loadwas applied and thereafter they were smaller than thepredictions by numerical analysis
When comparing the camber at final the predictionswere large in the order of KR C-08090 [1] numericalanalysis proposed method improved PCI multipliers [20]and basic PCI multipliers [18] for both bridges A and BNumerical analysis seems to estimate the effect of creep and
shrinkage on long-term deformation weaker than othermethods In comparison with numerical analysis for de-formation at the final difference rates of the proposedmethod basic PCI multipliers [18] improved PCI multi-pliers [20] and KR C-08090 [1] were 101 259 116and 343 for bridge A respectively and 146 331143 and 350 for bridge B respectively It is interestingto note that the proposed formula and the improved PCImultiplier method [20] show very similar prediction resultsof ultimate deformation at final
Figure 6 shows the long-term behavior predicted by theproposed multipliers for each load type In early agesa relatively large amount of camber was observed due to theprestress but as time went by the rate of increase of camberby prestress decreased sharply because the amount of creepand drying shrinkage converged and the PS steel relaxationincreased -e amount of deflection due to self-weight wassmaller than the camber due to the prestress but the ten-dency of deflection over time was very similar to that ofcamber On the contrary after the girder erection a con-siderable amount of immediate deflection and long-termdeflection due to dead loads such as topping and commonduct partially offset the camber
000000e + 000270033e + 000540066e + 000810100e + 000108013e + 001135017e + 001162020e + 001189023e + 001216027e + 001243030e + 001270033e + 001297037e + 001
MIDASCivilpostndashprocessorDisplacementYZ-direction
(a)
000000e + 000175416e + 000350832e + 000526248e + 000701664e + 001877080e + 001105250e + 001122791e + 001140333e + 001157874e + 001175416e + 001192958e + 001
MIDASCivilpostprocessorDisplacementYZ-direction
(b)
Figure 4 Analysis result of final deformation of bridges (a) A and (b) B
8 Advances in Civil Engineering
Tabl
e8
Predictio
nsby
variou
smetho
dsforbridge
A(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus2
230
176
minus3929
236
minus5265
237
minus5291
241
minus5364
245
minus5453
254minus5
665
Prestress
4610
171
7887
220
10130
221
10171
223
10284
226
10420
233
10734
Topp
ing
minus800
148
minus1180
178
minus1427
192
minus1533
206minus1
648
Superimpo
sed
dead
load
minus250
266
minus664
300minus7
50
Total
2380
3957
4066
3700
3243
2771
2671
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus2
230
185
minus4126
minus4126
minus4126
240minus5
352
Prestress
4610
180
8298
8298
8298
220
10142
Topp
ing
minus800
minus800
230minus1
840
Superimpo
sed
dead
load
minus250
300minus7
50
Total
2380
4173
3373
3123
2200
Improved
PCI
BDM
Self-weigh
tminus2
230
196
minus4371
minus4371
minus4371
288minus6
422
Prestress
4610
196
9036
9036
9036
288
13277
Prestresslossminus6
92
100
minus692
minus692
minus692
232minus1
604
Topp
ing
minus800
minus800
250minus2
000
Superimpo
sed
dead
load
minus250
250minus6
25
Total
2380
3973
3173
2923
2625
KRC-08090
Self-weigh
tminus2
230
150
minus3345
227
minus5062
230
minus5129
245
minus5464
265
minus5910
300minus6
690
Prestress
4610
150
6915
227
10465
230
10603
245
11295
265
12217
300
13830
Topp
ing
minus800
150
minus1200
215
minus1720
250
minus2000
300minus2
400
Superimpo
sed
dead
load
minus250
235
minus588
300minus7
50
Total
2380
3570
4603
4274
3861
3720
3990
Num
erical
analysis
Total
2348
3237
3446
3240
2988
2894
2970
Advances in Civil Engineering 9
Tabl
e9
Predictio
nsby
variou
smetho
dsforbridge
B(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus1
650
226
minus3725
227
minus3744
229
minus3771
236
minus3886
242
minus3994
250minus4
120
Prestress
3530
212
7477
213
7508
214
7553
219
7740
224
7909
230
8102
Topp
ing
minus750
142
minus1065
183
minus1370
196
minus1470
206minus1
545
Superimpo
sed
dead
load
minus265
278
minus736
300minus7
95
Total
1880
3752
3014
2717
2218
1710
1642
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus1
650
185
minus3053
minus3053
minus3053
240minus3
960
Prestress
3530
180
6354
6354
6354
220
7766
Topp
ing
minus750
minus750
230minus1
725
Superimpo
sed
dead
load
minus265
300minus7
95
Total
1880
3302
2552
2287
1286
Improved
PCI
BDM
Self-weigh
tminus1
650
196
minus3234
minus3234
minus3234
288minus4
752
Prestress
3530
196
6919
6919
6919
288
10166
Prestresslossminus5
30
100
minus530
minus530
minus530
232minus1
228
Topp
ing
minus750
minus750
250minus1
875
Superimpo
sed
dead
load
minus265
250minus6
63
Total
1880
3155
2405
2140
1648
KRC-08090
Self-weigh
tminus1
650
210
minus3465
211
minus3482
220
minus3630
240
minus3960
280
minus4620
300minus4
950
Prestress
3530
210
7413
211
7448
220
7766
240
8472
280
9884
300
10590
Topp
ing
minus750
150
minus1125
220
minus1650
275
minus2063
300minus2
250
Superimpo
sed
dead
load
minus265
265
minus702
300minus7
95
Total
1880
3948
3217
3011
2597
2499
2595
Num
erical
analysis
Total
1792
3926
2866
2536
2138
1954
1923
10 Advances in Civil Engineering
Consequently the proposed multipliers method pro-vided not only the closest prediction values but also themost similar long-term behavior trend to the numericalanalysis
6 Conclusions
Since the current PCI Bridge Design Manual [18] providesthe long-term deformation multipliers only at erection andfinal it cannot consider various construction processesFurthermore the multipliers for the composite cross sectionare also required to be modified to reflect the characteristicsof the cross section used in modern PSC bridges -ereforein this study newmodified PCImultipliers were proposed toovercome these problems -e conclusions drawn from thisstudy are as follows
(1) -e new modified PCI multipliers were proposed byusing the rate of creep and shrinkage over timeUnlike the existing PCI Bridge Design Manual [18]method it is possible to reflect the actual girdererection time and predict the long-term deformationfor any construction schedule Moreover throughthe new method camber and deflection of PSCbridges can be predicted at any time including designstage construction stage and use stage
(2) -e ratio of noncomposite to composite moments ofinertia IoIc was 051ndash056 as a result of analyzingrepresentative cross sections used in practice byspan while the PCI Bridge Design Manual [18]suggests 065 of IoIc-erefore it is suggested to usethe average value of 053 for IoIc in order to predictthe long-term behavior of composite members
ndash80
ndash60
ndash40
ndash20
0
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
PS forceSelf-weight
ToppingAdditional DL
(a)
ToppingPS forceSelf-weight Additional DL
0
ndash80
ndash60
ndash40
ndash20
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 6 Predictions by the proposed multipliers for each load type (a) Bridge A (b) Bridge B
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
(a)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 5 Comparison of various predictions for bridges (a) A and (b) B
Advances in Civil Engineering 11
(3) In order to verify the proposed multipliers for ac-tually constructed PSC bridges the predictions oflong-term camber and deflection by the proposedmultipliers were compared with those by the basicPCI multipliers [18] improved PCI multipliers [20]KR C-08090 [1] and numerical analysis As a resultKR C-08090 [1] predictions were significantly higherthan the other predictions and the basic PCI mul-tipliers [18] did not show a reasonable tendency inthe long-term behavior between the erection timeand the final Among all methods except the pro-posed method the improved PCI multipliers [20]showed the most similar predictions to the nu-merical analysis However this improved PCImultiplier method also has limitations in finding thelong-term deflection or camber of the bridge at anytime and there are several variables such as the creepcoefficient that must be known precisely in order touse the multipliers which is inconvenient for de-signers to use However the predictions through thenewly proposed multipliers showed a reasonablelong-term behavior trend and the amount of thefinal camber was also the most similar to the nu-merical analysis result Above all the proposedmethod can make it possible for the designer topredict the long-term behavior of the bridge veryeasily according to any construction schedule
Data Availability
-e data used to support the findings of this study areavailable from the corresponding author upon request
Conflicts of Interest
-e authors declare that they have no conflicts of interest
Acknowledgments
-is research was supported by a grant (17RTRP-B067919-05) from Railroad Technology Research Program funded byMinistry of Land Infrastructure and Transport of Koreangovernment
References
[1] Korea Rail Network Authority Railway Design Guidelines andHandbooks Bridge Concrete Track Ends Usability Review (KRC-08090) in Korean Korea Rail Network Authority DaejeonRepublic of Korea 2014
[2] ACI Committee 318 Building Code Requirements for Struc-tural Concrete (ACI 318-14) and Commentary AmericanConcrete Institute Farmington Hills MI USA 2014
[3] ACI Committe 209 Prediction of Creep Shrinkage andTemperature Effects in Concrete Structure American ConcreteInstitute Farmington Hill MI USA 1992
[4] AASHTO (American Association of State Highway andTransportation Officials) AASHTO LRFD Bridge DesignSpecifications AASHTO Washington DC USA 2007
[5] CEBFIP Model Code Comit Euro-International du BetonTelford Ltd London UK 1990
[6] H-G Kwak and Y-J Seo ldquoLong-term behavior of compositegirder bridgesrdquo Computers and Structures vol 74 no 5pp 583ndash599 2000
[7] H Yang ldquoUncertainty and updating of long-term predictionof prestress forces in PSC box girder bridgesrdquo Computers andStructures vol 83 no 25ndash26 pp 2137ndash2149 2005
[8] S Biswal and A Ramaswamy ldquoUncertainty based modelaveraging for prediction of long-time prestress losses inconcrete structuresrdquo Construction and Building Materialsvol 153 pp 469ndash480 2017
[9] W He and Z Zhang ldquoModeling creep fracture in rock byusing kelvin discretized virtual internal bondrdquo Advances inCivil Engineering vol 2018 Article ID 8042965 8 pages 2018
[10] Y-S Park Y-H Lee and Y Lee ldquoDescription of concretecreep under time-varying stress using parallel creep curverdquoAdvances in Materials Science and Engineering vol 2016Article ID 9370514 13 pages 2016
[11] Z Pan and S Meng ldquo-ree-level experimental approach forcreep and shrinkage of high-strength high-performanceconcreterdquo Engineering Structures vol 120 pp 23ndash36 2016
[12] H-G Kwak and Y-J Seo ldquoNumerical analysis of time-dependent behavior of pre-cast pre-stressed concrete girderbridgesrdquo Construction and Building Materials vol 16 no 1pp 49ndash63 2002
[13] I N Robertson ldquoPrediction of vertical deflections for a long-span prestressed concrete bridge structurerdquo EngineeringStructures vol 27 no 12 pp 1820ndash1827 2005
[14] T Lou S M R Lopes and A V Lopes ldquoA finite elementmodel to simulate long-term behavior of prestressed concretegirdersrdquo Finite Elements in Analysis and Design vol 81pp 48ndash56 2014
[15] P Liu Q Xing DWang andM Oeser ldquoApplication of linearviscoelastic properties in semianalytical finite element methodwith recursive time integration to analyze asphalt pavementstructurerdquo Advances in Civil Engineering vol 2018 Article ID9045820 15 pages 2018
[16] A Sagara and I Pane ldquoA study on effects of creep andshrinkage in high strength concrete bridgesrdquo Procedia En-gineering vol 125 pp 1087ndash1093 2015
[17] H Sousa J Bento and J Figueiras ldquoConstruction assessmentand long-term prediction of prestressed concrete bridgesbased on monitoring datardquo Engineering Structures vol 52pp 26ndash37 2013
[18] PCI Bridge Design Manual Second Release PrecastPrestressed Concrete Institute Chicago IL USA 3rd edi-tion 2014
[19] L D Martin ldquoA rational method for estimating camber anddeflection of precast prestressed membersrdquo PCI Journalvol 22 no 1 pp 100ndash108 1977
[20] PCI Bridge Design Manual PrecastPrestressed ConcreteInstitute Chicago IL USA 2nd edition 2003
[21] M K Tadros A Ghali and A W Meyer ldquoPrestressed lossand deflection of precast concrete membersrdquo PCI Journalvol 30 no 1 pp 114ndash141 1985
[22] Y Zhang ldquoOrthogonal test analysis on influencing factors ofprestressed concrete small box beam camberrdquo Applied Me-chanics and Materials vol 405-408 pp 1527ndash1530 2013
[23] Y Jianjun W Xun and H Xianzheng ldquoEffects of live load onthe deflection of long-span PC continuous rigid-framehighway bridge based on midasrdquo in Proceedings of 20147th International Conference on Intelligent ComputationTechnology and Automation pp 944ndash946 Changsha China2014
12 Advances in Civil Engineering
[24] T Grigorjeva A Juozapaitis and Z Kamaitis ldquoStatic analysisand simplified design of suspension bridges having variousrigidity of cablesrdquo Journal of Civil Engineering and Man-agement vol 16 no 3 pp 363ndash371 2011
[25] ACI Committee 435 Control of Deflection in ConcreteStructures ACI 435R-95 ACI Farmington Hills MI USA2003
[26] F B Angomas ldquoBehavior of prestressed concrete bridgegirdersrdquo All Graduate -eses and Dissertations Utah StateUniversity Logan UT USA 2009
[27] E H Gheitanbaf ldquoImproving the prediction of time-dependent effects on prestressed concrete bridgesrdquo Gradu-ate-eses and Dissertations Iowa State University Ames IAUSA 2015
[28] M K Tadros F Fawzy and K Hanna ldquoPrecast prestressedgirder camber variabilityrdquo PCI Journal vol 56 no 1pp 135ndash154 2011
Advances in Civil Engineering 13
International Journal of
AerospaceEngineeringHindawiwwwhindawicom Volume 2018
RoboticsJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Active and Passive Electronic Components
VLSI Design
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Shock and Vibration
Hindawiwwwhindawicom Volume 2018
Civil EngineeringAdvances in
Acoustics and VibrationAdvances in
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Electrical and Computer Engineering
Journal of
Advances inOptoElectronics
Hindawiwwwhindawicom
Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Control Scienceand Engineering
Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Journal ofEngineeringVolume 2018
SensorsJournal of
Hindawiwwwhindawicom Volume 2018
International Journal of
RotatingMachinery
Hindawiwwwhindawicom Volume 2018
Modelling ampSimulationin EngineeringHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Chemical EngineeringInternational Journal of Antennas and
Propagation
International Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Navigation and Observation
International Journal of
Hindawi
wwwhindawicom Volume 2018
Advances in
Multimedia
Submit your manuscripts atwwwhindawicom
value of 50 therefore the long-term deflection coefficientat erection is presented as the following equation
1 + μde 1 + 05μdf (3)
-e multiplier for deflection at erection would then be1 + 05(17) 185
In deriving the multiplier for the camber in the PCIBridge Design Manual [18] the prestress loss is taken intoaccount -at is the method of obtaining the long-termcamber by multiplying the long-time factor by the elasticcamber at the release of the prestress is the same as (2) butconsidering the prestress loss which is a phenomenon inwhich the prestress as a sustained load decreases over time-e long-term prestress loss is assumed to be 15 of theinitial force -erefore using μdf in (2) factor for final long-time camber can be expressed as follows
μpf μdfP
P0 (4)
-erefore the multiplier used to determine the camberdue to prestress is 1 + μpf 1 + 17(085) 245
-emultiplier for the camber due to prestress at the timeof erection is derived in the same way as (3) is derived -elong-term loss of prestress is governed by long-term be-havior factors such as creep and shrinkage of concrete So ifthese long-term behavior factors occur 50 of ultimate aterection prestress loss will also result in one-half of the long-time total loss 15 Applying this to (4) the multiplier forthe camber caused by the prestress at the time of erection canbe calculated as follows
1 + μpe 1 + μde(1minus 015 times 050) (5)
-erefore the multiplier applied to the initial upwardcamber caused by prestressing force is equal to be1 + μpe 1 + 085(0925) asymp 180
Since the long-term deflection due to the superimposedsustained dead load depends on the creep the multiplier isexpressed by the following equation using the basic factorμb 20
1 + μsdf 1 + 20 30 (6)
In addition the PCI Bridge Design Manual [18] providesmultipliers for composite members by taking into accountthe effect of increased moment of inertia due to topping Asshown in the following equations the effect of topping on
the deflection and camber is taken into account by multi-plying the difference between long-time factors at erectionand final by the ratio of noncomposite to composite mo-ments of inertia IoIc
μdfc μde + μdf minus μde( 1113857Io
Ic1113888 1113889 (7)
μpfc μpe + μpf minus μpe1113872 1113873Io
Ic1113888 1113889 (8)
Here the PCI Bridge Design Manual [18] assumes that thesection becomes composite at about the time of erection -ethickness of the topping is assumed to be 2 inches and the valueof IoIc is assumed to be 065 for commonly used members-erefore if these values are substituted in (7 and 8) themultiplier for deflection and camber of the composite memberwith topping is 240 and 220 respectively as shown in Table 1
3 PCI Bridge Design ManualImproved Multipliers
As shown in Table 2 the PCI Bridge Design Manual 2ndEdition [20] suggested an improved multiplier method pro-posed by Tadros et al [21] -is method is very similar to thebasic multiplier method described in the preceding sectionAccording to the manual however this method provides twoimprovements First it provides more accurate coefficients forcases where the reliable creep coefficient is known or high-performance concrete with a very low creep coefficient is usedSecond the prediction of the deflection caused by the prestressloss can be calculated by considering the amount of prestressloss actually occurred However it is not easy to know thecorrect creep coefficient and the actual prestress loss at thedesign stage Moreover there are many variables that must becalculated separately to derive the multiplier which is some-what inconvenient for designers to use However since theaverage value is presented it can be used effectively It is notedthat the improved multiplier method has been deleted in thecurrent PCI Bridge Design Manual 3rd Edition [18]
4 Development of Proposed Multipliers
41ModificationofPCIMultipliers forPredictionatAnyTimeAs mentioned earlier the PCI Bridge Design Manual [18]provides multipliers only for at the time of erection and final
Table 2 PCI Bridge Design Manual improved multipliers [20]
Load conditionErection time Final time
Formula Average Formula AverageInitial prestress 1 + Ca 196 1 + Cu 288Prestress loss αa(1 + χCa) 100 (1 + χCu) 232Self-weight 1 + Ca 196 1 + Cu 288Dead load on plain beam 100 100 1 + Cuprime 250Dead load on composite beam 100 100 1 + Cuprime 250Cu ultimate creep coefficient for loads applied immediately after transfer and the average value is 188 Cuprime ultimate creep coefficient for loads applied attime of erection and the average value is 150 Ca creep coefficient for loading applied immediately after transfer and strains measured at time of erectionand the average value is 096 αa time-dependent prestress loss at erection divided by total time-dependent prestress loss and the average value is 060χ Bazantrsquos aging coefficient and the average value is 070
Advances in Civil Engineering 3
Moreover it is assumed that the erection time is about 30ndash60days after casting In practice however the time of erection isvery flexible depending on the site conditions-erefore in thisstudy the multipliers applicable at any time including thevarious time of erection were suggested by considering the rateof creep and drying shrinkage It can be useful for field con-struction management and maintenance of structures if thecamber or deflection can be predicted at any time after casting
Equations (3) and (5) were modified using rt the rate ofcreep and drying shrinkage over time
1 + μdt 1 + rt times μdf (9)
1 + μpt 1 + μdt 1minus 015 times rt( 1113857 (10)
where t is the time after casting and μdt and μpt are the factorsfor time-dependent deflection and camber at the time of t
applied to initial deformation caused by member weight andprestressing force respectively μdf is 17 as in the PCI BridgeDesign Manual [18] If the time of the erection is t(e) themultiplier for the deflection and camber at erection can beexpressed by substituting t(e) in (9) and (10) as follows
1 + μdt(e) 1 + rt(e) times μdf
1 + μpt(e) 1 + μdt(e) 1minus 015 times rt(e)1113872 1113873(11)
Also the multiplier for the long-term deflection due tothe superimposed dead load at any time can be expressed bythe following equation
1 + μsdt 1 + r[tminust(s)] times μsdf (12)
where μsdt is the factor for additional long-time deflection attime t applied to initial deflection caused by superimposeddead load and t(s) is the time at which the superimposed
dead load is applied μsdf is 20 as in the PCI Bridge DesignManual [18]
-e creep and drying shrinkage predictions presented inACI 209R-92 [3] were used to calculate the rate of creep andshrinkage over time rt For creep and shrinkage understandard condition the relationship between at any time andat final is given by (13) and (14) respectively
vt t06
10 + t06vu (13)
εsh( 1113857t t
35 + tεsh( 1113857u (14)
where t time in days vt creep coefficient at any timevu ultimate creep coefficient (εsh)t shrinkage strain atany time and (εsh)u ultimate shrinkage strain
Long-term behavior is both affected by creep and dryingshrinkage at the same time -erefore rt the rate of creepand drying shrinkage over time were derived from theaverage of (13) and (14) as shown in (15) Figure 1 shows thegraphs of creep and drying shrinkage rates over time
rt 12
t06
10 + t06 +t
35 + t1113888 1113889 (15)
42 Modification of Multipliers for Composite Member Asmentioned earlier in the PCI Bridge DesignManual [18] forthe composite member the thickness of the topping is as-sumed to be 2 inches and the ratio of noncomposite tocomposite moments of inertia IoIc is 065 for all casesregardless of the shape of cross section However given thevariety of girder geometry and the recent bridge slab deck
0
10
20
30
40
50
60
70
80
90
100
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Tim
e-ra
tio v
alue
s for
cree
p an
d sh
rinka
ge (
)
Elapsed time (day)Creep time ratioShrinkage time ratioAverage time ratio of creep and shrinkage
Figure 1 Rate of creep and drying shrinkage over time
4 Advances in Civil Engineering
thickness the assumptions for composite members in thePCI Bridge Design Manual [18] are not likely to reflectmodern bridge characteristics -erefore in this study themultipliers for the long-term behavior of composite memberwere proposed by analyzing the representative cross sectionsof the recent bridges
Currently girder sections commonly used in single-spanrailway bridges in Korea are I girder box girder and WPC(wide flange prestressed concrete) In general a thickness ofslab placed on the girder is 280mm Figure 2 and Table 3show the details of the cross sections of I girder box girderand WPC which are the representative girder sections ac-tually used in practice Table 4 shows IoIc for all cross
sections of Figure 2 and Table 3 As shown in Table 4 thevalue of IoIc is different from 065 of the PCI Bridge DesignManual [18] IoIc was in the range of 051 to 056 and boxgirder bridges and long span bridges tend to have relativelylarge IoIc For the convenience of design this study pro-posed to use the total average value of 053 for IoIc
-e PCI Bridge Design Manual [18] assumed that thesection becomes composite at about the time of erectionbut it is not always Rather there are many cases wheretopping is not applied when the girder is erected because offield condition and construction schedules -ereforemultipliers have been proposed to enable the prediction ofdeflection and camber of the composite member at anytime t by considering the time t(c) at which the sectionbecomes composite -is can be expressed as follows using(7)ndash(10)
1 + μdtc 1 + μdt(c) + μdt minus μdt(c)1113872 1113873Io
Ic1113888 1113889
1 + μptc 1 + μpt(c) + μpt minus μpt(c)1113872 1113873Io
Ic1113888 1113889
(16)
where IoIc is 053-e factor for long-term deflection by a composite
topping should be also modified by the ratio of IoIc becausethe elastic deflection caused by the placement of the toppingto which the factor is applied is calculated using the non-composite section as follows
1 + μtt 1 + μsdtIo
Ic1113888 1113889 (17)
where μtt is the factor for additional long-term deflectioncaused by topping at any time t
As a result the multipliers of the PCI Bridge DesignManual [18] in Table 1 were revised as shown in Table 5
ed
ifg
h
b c ba
j k jl
(a)i
c b
j
da
cb
kl
m
nopq
o
g
n
he f
(b)
p
cb
m
n
q r
de
f
i j kg
lh g
k j i
o
a
(c)
Figure 2 Typical cross sections of PSC bridges (a) I girder (b) box girder (c) WPC girder
Table 3 Cross section dimension of I box and WPC girders byspan (mm)
Type I girder Box girder WPC girderSpan 25m 30m 35m 30m 35m 40m 30m 35m 40m 1000 1000 1000 1200 1200 1200 3580 3580 2650 400 400 400 220 220 220 150 150 150 200 200 200 50 50 50 100 100 100 80 150 150 660 660 660 982 1135 1514 90 120 120 2000 2400 2600 116 115 86 1520 1550 1950 1900 2300 2500 350 500 450 240 180 180 30 30 30 98 113 151 320 200 200 70 70 70 1181 1150 865 2350 2200 2600 400 350 350 730 730 370 240 350 350 50 50 50 110 110 110 200 200 200 1080 1530 1730 145 175 205 680 900 900 220 220 220 1610 1550 1280 mdash mdash mdash 250 250 250 1700 2000 2300 mdash mdash mdash 30 30 30 1450 1750 2050 mdash mdash mdash 220 220 220 135 135 135 mdash mdash mdash 760 760 760 115 115 115 mdash mdash mdash 1260 1260 1260 480 480 120 mdash mdash mdash mdash mdash mdash 250 250 250
Advances in Civil Engineering 5
5 Verification of Proposed Multipliers
In order to verify the proposed multipliers for actuallyconstructed PSC bridges the predictions of long-termcamber and deflection by the proposed multipliers werecompared with those by the basic PCI multipliers [18] theimproved PCI multipliers [20] and KR C-08090 [1] (same asACI 318-14 [2]) In addition numerical analysis was per-formed and the results were compared with the results fromother prediction methods
51 PSCBridges forVerification PSC bridges A and B whichwere recently constructed on a new line from Wonju toGangneung in Korearsquos high-speed railway were selected toverify the prediction methods Bridge A is a WPC type witha span of 388m and bridge B is constructed with an I-girdertype with a span of 34m -e cross-sectional details of thebridges at midspan are shown in Figure 3 Tables 6 and 7
show the construction history of the bridges and the elasticdeformation due to the applied load respectively
52 Numerical Analysis for Long-Term Behavior of PSCBridges Long-term behavior of the bridges A and B waspredicted using MIDAS Civil a general-purpose finite el-ement analysis program-e validity of theMIDAS Civil hasalready been confirmed through previous researches [22ndash24] In general the prediction of long-term behavior usinga finite element analysis is known to have a higher accuracythan that of the methods using a multiplier such as the PCIBridge Design Manual [18 20] although the design con-venience is poor [25ndash28] -erefore the numerical analysisresults were used to verify the newly proposed multipliers
-ematerial model was selected from the database of theMIDAS Civil program C40 and C27 were selected forthe girder and deck concrete respectively and the strandof SWPC7B empty152mm was selected for PS steel -ese
Table 4 Ratio of noncomposite to composite moments of inertia by girder type and span
Span PCI Bridge Design Manual I girder Box girder WPC girder Average25m
065
051 mdash mdash 05130m 049 054 053 05235m 052 056 050 05340m mdash 057 054 056Average 065 051 056 052 053
Table 5 Proposed multipliers
Without topping With toppingAt erection(1) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
1 + 17rt(e) 1 + 17rt(e)
(2) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
1 + 17rt(e)(1minus 015rt(e)) 1 + 17rt(e)(1minus 015rt(e))
At certain time(3) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
1 + 17rt 1 + 08rt(c) + 09rt
(4) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
1 + 17rt(1minus 015rt) 1 + 08rt(c)(1minus 015rt(c)) + 09rt(1minus 015 times rt)
(5) Deflection (downward)mdashapply to elasticdeflection due to superimposed dead load only 1 + 20r[tminust(s)] 1 + 20r[tminust(s)]
(6) Deflection (downward)mdashapply to elasticdeflection caused by the composite topping mdash 1 + 106r[tminust(c)]
Final(7) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
270 19 + 08rt(c)
(8) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
245 1765 + 08rt(c)(1minus 015rt(c))
(9) Deflection (downward)mdashapply to elasticdeflection due to superimposed dead load only 300 300
(10) Deflection (downward)mdashapply to elasticdeflection caused by the composite topping mdash 206
6 Advances in Civil Engineering
materials are the same as concrete and PS steel actually usedfor bridges A and B -e structural members of the bridgeswere modeled based on structural calculations and designdrawings of bridges A and B According to the designdrawing the strands were arranged by setting the actualcoordinates of the strand on the girder nodes using the 3-Dinput type from tendon profile option of MIDAS Civil -eCEB-FIP MC90 model [5] was used to calculate creep anddrying shrinkage of concrete For the relaxation of thetendon the Magura 45 model was used to consider thetime-dependent loss of the prestress Based on the con-struction history of the bridges A and B in Table 6construction sequence analysis was carried out After thecast of deck composite behavior of the girder and the deckwas simulated through the node connection using the rigidtype of elastic link In the same way common duct which isthe additional superimposed dead load was also simulatedfor composite behavior after its installation At the finalstage the deformation patterns of bridges A and B areshown in Figure 4 As a result the bridges A and B in themidspan showed 324mm and 393mm of camber at girdererection and 297mm and 192mm of camber at finalrespectively
53 Comparison of Predictions of Long-Term DeformationTables 8 and 9 and Figure 5 show the predictions of the long-term deformation of bridges A and B by using the proposedmultipliers the basic PCI multipliers [18] the improved PCImultipliers [20] KR C-08090 [1] and numerical analysisFor the improved PCI multipliers [20] the average values inTable 2 were used because the actual creep coefficient and theamount of the prestress loss can hardly be known
Although the values of predictions by the proposedmultipliers and KR C-08090 [1] were somewhat different
from the prediction by numerical analysis their predictiontrends of the camber over time were generally similar be-cause they provided available multipliers at any time In thecase of the basic PCI multipliers [18] however the long-term behavior after the erection was quite different fromother prediction methods because there are no applicablelong-term factors for the period between the erection andthe final
-e girder of bridge A was erected on the 30th day aftercasting while the girder of bridge B was erected on the 150thday relatively long time after casting -e basic PCI
1025 90 420 90 1025
2650
120
100
110
2670 30
00
150
2250
600
220
95 600150
2190
60600
3000
600
1040 110 695110695
(a)
400 200 4001000
2600
150
120
1950
180
200
2600
200 350350
900
(b)
Figure 3 Cross-sectional details of bridges (a) A and (b) B
Table 6 Construction history of bridges A and B
EventTime from casting (days)Bridge A Bridge B
(1) Release 1 1(2) Erection (t(e)) 30 150(3) Topping (t(c)) 240 157(4) 1st random time (t1) 270 180(5) Superimposed dead load (t(s)) 390 360(6) 2nd random time (t2) 700 1000
(7) Final 5 years ormore
5 years ormore
Table 7 Elastic camber and deflection of bridges A and B
LoadCamber (+) or deflection (minus)Bridge A Bridge B
Self-weight minus223 minus165Prestressing force +461 +353Topping minus80 minus75Superimposed dead load minus25 minus265
Advances in Civil Engineering 7
multiplier method [18] calculated the long-term camberusing the same multiplier for both bridges regardless of thedifferent erection time while the new proposed method useddifferent long-term multipliers for the bridges A and B inorder to consider different creep and shrinkage rates Asa result the predictions at erection by the proposed methodwere smaller for bridge A and larger for bridge B than thoseby the basic PCI multiplier method [18] as shown inFigure 5
In terms of the long-term behavior after erection thecamber predicted by KR C-08090 [1] was generally thelargest among all prediction methods KR C-08090 [1] doesnot take into account prestress loss so it overestimates thecamber by prestress force -e predictions by the proposedmethod were larger than the predictions by numericalanalysis until about 200 days after superimposed dead loadwas applied and thereafter they were smaller than thepredictions by numerical analysis
When comparing the camber at final the predictionswere large in the order of KR C-08090 [1] numericalanalysis proposed method improved PCI multipliers [20]and basic PCI multipliers [18] for both bridges A and BNumerical analysis seems to estimate the effect of creep and
shrinkage on long-term deformation weaker than othermethods In comparison with numerical analysis for de-formation at the final difference rates of the proposedmethod basic PCI multipliers [18] improved PCI multi-pliers [20] and KR C-08090 [1] were 101 259 116and 343 for bridge A respectively and 146 331143 and 350 for bridge B respectively It is interestingto note that the proposed formula and the improved PCImultiplier method [20] show very similar prediction resultsof ultimate deformation at final
Figure 6 shows the long-term behavior predicted by theproposed multipliers for each load type In early agesa relatively large amount of camber was observed due to theprestress but as time went by the rate of increase of camberby prestress decreased sharply because the amount of creepand drying shrinkage converged and the PS steel relaxationincreased -e amount of deflection due to self-weight wassmaller than the camber due to the prestress but the ten-dency of deflection over time was very similar to that ofcamber On the contrary after the girder erection a con-siderable amount of immediate deflection and long-termdeflection due to dead loads such as topping and commonduct partially offset the camber
000000e + 000270033e + 000540066e + 000810100e + 000108013e + 001135017e + 001162020e + 001189023e + 001216027e + 001243030e + 001270033e + 001297037e + 001
MIDASCivilpostndashprocessorDisplacementYZ-direction
(a)
000000e + 000175416e + 000350832e + 000526248e + 000701664e + 001877080e + 001105250e + 001122791e + 001140333e + 001157874e + 001175416e + 001192958e + 001
MIDASCivilpostprocessorDisplacementYZ-direction
(b)
Figure 4 Analysis result of final deformation of bridges (a) A and (b) B
8 Advances in Civil Engineering
Tabl
e8
Predictio
nsby
variou
smetho
dsforbridge
A(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus2
230
176
minus3929
236
minus5265
237
minus5291
241
minus5364
245
minus5453
254minus5
665
Prestress
4610
171
7887
220
10130
221
10171
223
10284
226
10420
233
10734
Topp
ing
minus800
148
minus1180
178
minus1427
192
minus1533
206minus1
648
Superimpo
sed
dead
load
minus250
266
minus664
300minus7
50
Total
2380
3957
4066
3700
3243
2771
2671
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus2
230
185
minus4126
minus4126
minus4126
240minus5
352
Prestress
4610
180
8298
8298
8298
220
10142
Topp
ing
minus800
minus800
230minus1
840
Superimpo
sed
dead
load
minus250
300minus7
50
Total
2380
4173
3373
3123
2200
Improved
PCI
BDM
Self-weigh
tminus2
230
196
minus4371
minus4371
minus4371
288minus6
422
Prestress
4610
196
9036
9036
9036
288
13277
Prestresslossminus6
92
100
minus692
minus692
minus692
232minus1
604
Topp
ing
minus800
minus800
250minus2
000
Superimpo
sed
dead
load
minus250
250minus6
25
Total
2380
3973
3173
2923
2625
KRC-08090
Self-weigh
tminus2
230
150
minus3345
227
minus5062
230
minus5129
245
minus5464
265
minus5910
300minus6
690
Prestress
4610
150
6915
227
10465
230
10603
245
11295
265
12217
300
13830
Topp
ing
minus800
150
minus1200
215
minus1720
250
minus2000
300minus2
400
Superimpo
sed
dead
load
minus250
235
minus588
300minus7
50
Total
2380
3570
4603
4274
3861
3720
3990
Num
erical
analysis
Total
2348
3237
3446
3240
2988
2894
2970
Advances in Civil Engineering 9
Tabl
e9
Predictio
nsby
variou
smetho
dsforbridge
B(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus1
650
226
minus3725
227
minus3744
229
minus3771
236
minus3886
242
minus3994
250minus4
120
Prestress
3530
212
7477
213
7508
214
7553
219
7740
224
7909
230
8102
Topp
ing
minus750
142
minus1065
183
minus1370
196
minus1470
206minus1
545
Superimpo
sed
dead
load
minus265
278
minus736
300minus7
95
Total
1880
3752
3014
2717
2218
1710
1642
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus1
650
185
minus3053
minus3053
minus3053
240minus3
960
Prestress
3530
180
6354
6354
6354
220
7766
Topp
ing
minus750
minus750
230minus1
725
Superimpo
sed
dead
load
minus265
300minus7
95
Total
1880
3302
2552
2287
1286
Improved
PCI
BDM
Self-weigh
tminus1
650
196
minus3234
minus3234
minus3234
288minus4
752
Prestress
3530
196
6919
6919
6919
288
10166
Prestresslossminus5
30
100
minus530
minus530
minus530
232minus1
228
Topp
ing
minus750
minus750
250minus1
875
Superimpo
sed
dead
load
minus265
250minus6
63
Total
1880
3155
2405
2140
1648
KRC-08090
Self-weigh
tminus1
650
210
minus3465
211
minus3482
220
minus3630
240
minus3960
280
minus4620
300minus4
950
Prestress
3530
210
7413
211
7448
220
7766
240
8472
280
9884
300
10590
Topp
ing
minus750
150
minus1125
220
minus1650
275
minus2063
300minus2
250
Superimpo
sed
dead
load
minus265
265
minus702
300minus7
95
Total
1880
3948
3217
3011
2597
2499
2595
Num
erical
analysis
Total
1792
3926
2866
2536
2138
1954
1923
10 Advances in Civil Engineering
Consequently the proposed multipliers method pro-vided not only the closest prediction values but also themost similar long-term behavior trend to the numericalanalysis
6 Conclusions
Since the current PCI Bridge Design Manual [18] providesthe long-term deformation multipliers only at erection andfinal it cannot consider various construction processesFurthermore the multipliers for the composite cross sectionare also required to be modified to reflect the characteristicsof the cross section used in modern PSC bridges -ereforein this study newmodified PCImultipliers were proposed toovercome these problems -e conclusions drawn from thisstudy are as follows
(1) -e new modified PCI multipliers were proposed byusing the rate of creep and shrinkage over timeUnlike the existing PCI Bridge Design Manual [18]method it is possible to reflect the actual girdererection time and predict the long-term deformationfor any construction schedule Moreover throughthe new method camber and deflection of PSCbridges can be predicted at any time including designstage construction stage and use stage
(2) -e ratio of noncomposite to composite moments ofinertia IoIc was 051ndash056 as a result of analyzingrepresentative cross sections used in practice byspan while the PCI Bridge Design Manual [18]suggests 065 of IoIc-erefore it is suggested to usethe average value of 053 for IoIc in order to predictthe long-term behavior of composite members
ndash80
ndash60
ndash40
ndash20
0
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
PS forceSelf-weight
ToppingAdditional DL
(a)
ToppingPS forceSelf-weight Additional DL
0
ndash80
ndash60
ndash40
ndash20
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 6 Predictions by the proposed multipliers for each load type (a) Bridge A (b) Bridge B
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
(a)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 5 Comparison of various predictions for bridges (a) A and (b) B
Advances in Civil Engineering 11
(3) In order to verify the proposed multipliers for ac-tually constructed PSC bridges the predictions oflong-term camber and deflection by the proposedmultipliers were compared with those by the basicPCI multipliers [18] improved PCI multipliers [20]KR C-08090 [1] and numerical analysis As a resultKR C-08090 [1] predictions were significantly higherthan the other predictions and the basic PCI mul-tipliers [18] did not show a reasonable tendency inthe long-term behavior between the erection timeand the final Among all methods except the pro-posed method the improved PCI multipliers [20]showed the most similar predictions to the nu-merical analysis However this improved PCImultiplier method also has limitations in finding thelong-term deflection or camber of the bridge at anytime and there are several variables such as the creepcoefficient that must be known precisely in order touse the multipliers which is inconvenient for de-signers to use However the predictions through thenewly proposed multipliers showed a reasonablelong-term behavior trend and the amount of thefinal camber was also the most similar to the nu-merical analysis result Above all the proposedmethod can make it possible for the designer topredict the long-term behavior of the bridge veryeasily according to any construction schedule
Data Availability
-e data used to support the findings of this study areavailable from the corresponding author upon request
Conflicts of Interest
-e authors declare that they have no conflicts of interest
Acknowledgments
-is research was supported by a grant (17RTRP-B067919-05) from Railroad Technology Research Program funded byMinistry of Land Infrastructure and Transport of Koreangovernment
References
[1] Korea Rail Network Authority Railway Design Guidelines andHandbooks Bridge Concrete Track Ends Usability Review (KRC-08090) in Korean Korea Rail Network Authority DaejeonRepublic of Korea 2014
[2] ACI Committee 318 Building Code Requirements for Struc-tural Concrete (ACI 318-14) and Commentary AmericanConcrete Institute Farmington Hills MI USA 2014
[3] ACI Committe 209 Prediction of Creep Shrinkage andTemperature Effects in Concrete Structure American ConcreteInstitute Farmington Hill MI USA 1992
[4] AASHTO (American Association of State Highway andTransportation Officials) AASHTO LRFD Bridge DesignSpecifications AASHTO Washington DC USA 2007
[5] CEBFIP Model Code Comit Euro-International du BetonTelford Ltd London UK 1990
[6] H-G Kwak and Y-J Seo ldquoLong-term behavior of compositegirder bridgesrdquo Computers and Structures vol 74 no 5pp 583ndash599 2000
[7] H Yang ldquoUncertainty and updating of long-term predictionof prestress forces in PSC box girder bridgesrdquo Computers andStructures vol 83 no 25ndash26 pp 2137ndash2149 2005
[8] S Biswal and A Ramaswamy ldquoUncertainty based modelaveraging for prediction of long-time prestress losses inconcrete structuresrdquo Construction and Building Materialsvol 153 pp 469ndash480 2017
[9] W He and Z Zhang ldquoModeling creep fracture in rock byusing kelvin discretized virtual internal bondrdquo Advances inCivil Engineering vol 2018 Article ID 8042965 8 pages 2018
[10] Y-S Park Y-H Lee and Y Lee ldquoDescription of concretecreep under time-varying stress using parallel creep curverdquoAdvances in Materials Science and Engineering vol 2016Article ID 9370514 13 pages 2016
[11] Z Pan and S Meng ldquo-ree-level experimental approach forcreep and shrinkage of high-strength high-performanceconcreterdquo Engineering Structures vol 120 pp 23ndash36 2016
[12] H-G Kwak and Y-J Seo ldquoNumerical analysis of time-dependent behavior of pre-cast pre-stressed concrete girderbridgesrdquo Construction and Building Materials vol 16 no 1pp 49ndash63 2002
[13] I N Robertson ldquoPrediction of vertical deflections for a long-span prestressed concrete bridge structurerdquo EngineeringStructures vol 27 no 12 pp 1820ndash1827 2005
[14] T Lou S M R Lopes and A V Lopes ldquoA finite elementmodel to simulate long-term behavior of prestressed concretegirdersrdquo Finite Elements in Analysis and Design vol 81pp 48ndash56 2014
[15] P Liu Q Xing DWang andM Oeser ldquoApplication of linearviscoelastic properties in semianalytical finite element methodwith recursive time integration to analyze asphalt pavementstructurerdquo Advances in Civil Engineering vol 2018 Article ID9045820 15 pages 2018
[16] A Sagara and I Pane ldquoA study on effects of creep andshrinkage in high strength concrete bridgesrdquo Procedia En-gineering vol 125 pp 1087ndash1093 2015
[17] H Sousa J Bento and J Figueiras ldquoConstruction assessmentand long-term prediction of prestressed concrete bridgesbased on monitoring datardquo Engineering Structures vol 52pp 26ndash37 2013
[18] PCI Bridge Design Manual Second Release PrecastPrestressed Concrete Institute Chicago IL USA 3rd edi-tion 2014
[19] L D Martin ldquoA rational method for estimating camber anddeflection of precast prestressed membersrdquo PCI Journalvol 22 no 1 pp 100ndash108 1977
[20] PCI Bridge Design Manual PrecastPrestressed ConcreteInstitute Chicago IL USA 2nd edition 2003
[21] M K Tadros A Ghali and A W Meyer ldquoPrestressed lossand deflection of precast concrete membersrdquo PCI Journalvol 30 no 1 pp 114ndash141 1985
[22] Y Zhang ldquoOrthogonal test analysis on influencing factors ofprestressed concrete small box beam camberrdquo Applied Me-chanics and Materials vol 405-408 pp 1527ndash1530 2013
[23] Y Jianjun W Xun and H Xianzheng ldquoEffects of live load onthe deflection of long-span PC continuous rigid-framehighway bridge based on midasrdquo in Proceedings of 20147th International Conference on Intelligent ComputationTechnology and Automation pp 944ndash946 Changsha China2014
12 Advances in Civil Engineering
[24] T Grigorjeva A Juozapaitis and Z Kamaitis ldquoStatic analysisand simplified design of suspension bridges having variousrigidity of cablesrdquo Journal of Civil Engineering and Man-agement vol 16 no 3 pp 363ndash371 2011
[25] ACI Committee 435 Control of Deflection in ConcreteStructures ACI 435R-95 ACI Farmington Hills MI USA2003
[26] F B Angomas ldquoBehavior of prestressed concrete bridgegirdersrdquo All Graduate -eses and Dissertations Utah StateUniversity Logan UT USA 2009
[27] E H Gheitanbaf ldquoImproving the prediction of time-dependent effects on prestressed concrete bridgesrdquo Gradu-ate-eses and Dissertations Iowa State University Ames IAUSA 2015
[28] M K Tadros F Fawzy and K Hanna ldquoPrecast prestressedgirder camber variabilityrdquo PCI Journal vol 56 no 1pp 135ndash154 2011
Advances in Civil Engineering 13
International Journal of
AerospaceEngineeringHindawiwwwhindawicom Volume 2018
RoboticsJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Active and Passive Electronic Components
VLSI Design
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Shock and Vibration
Hindawiwwwhindawicom Volume 2018
Civil EngineeringAdvances in
Acoustics and VibrationAdvances in
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Electrical and Computer Engineering
Journal of
Advances inOptoElectronics
Hindawiwwwhindawicom
Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Control Scienceand Engineering
Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Journal ofEngineeringVolume 2018
SensorsJournal of
Hindawiwwwhindawicom Volume 2018
International Journal of
RotatingMachinery
Hindawiwwwhindawicom Volume 2018
Modelling ampSimulationin EngineeringHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Chemical EngineeringInternational Journal of Antennas and
Propagation
International Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Navigation and Observation
International Journal of
Hindawi
wwwhindawicom Volume 2018
Advances in
Multimedia
Submit your manuscripts atwwwhindawicom
Moreover it is assumed that the erection time is about 30ndash60days after casting In practice however the time of erection isvery flexible depending on the site conditions-erefore in thisstudy the multipliers applicable at any time including thevarious time of erection were suggested by considering the rateof creep and drying shrinkage It can be useful for field con-struction management and maintenance of structures if thecamber or deflection can be predicted at any time after casting
Equations (3) and (5) were modified using rt the rate ofcreep and drying shrinkage over time
1 + μdt 1 + rt times μdf (9)
1 + μpt 1 + μdt 1minus 015 times rt( 1113857 (10)
where t is the time after casting and μdt and μpt are the factorsfor time-dependent deflection and camber at the time of t
applied to initial deformation caused by member weight andprestressing force respectively μdf is 17 as in the PCI BridgeDesign Manual [18] If the time of the erection is t(e) themultiplier for the deflection and camber at erection can beexpressed by substituting t(e) in (9) and (10) as follows
1 + μdt(e) 1 + rt(e) times μdf
1 + μpt(e) 1 + μdt(e) 1minus 015 times rt(e)1113872 1113873(11)
Also the multiplier for the long-term deflection due tothe superimposed dead load at any time can be expressed bythe following equation
1 + μsdt 1 + r[tminust(s)] times μsdf (12)
where μsdt is the factor for additional long-time deflection attime t applied to initial deflection caused by superimposeddead load and t(s) is the time at which the superimposed
dead load is applied μsdf is 20 as in the PCI Bridge DesignManual [18]
-e creep and drying shrinkage predictions presented inACI 209R-92 [3] were used to calculate the rate of creep andshrinkage over time rt For creep and shrinkage understandard condition the relationship between at any time andat final is given by (13) and (14) respectively
vt t06
10 + t06vu (13)
εsh( 1113857t t
35 + tεsh( 1113857u (14)
where t time in days vt creep coefficient at any timevu ultimate creep coefficient (εsh)t shrinkage strain atany time and (εsh)u ultimate shrinkage strain
Long-term behavior is both affected by creep and dryingshrinkage at the same time -erefore rt the rate of creepand drying shrinkage over time were derived from theaverage of (13) and (14) as shown in (15) Figure 1 shows thegraphs of creep and drying shrinkage rates over time
rt 12
t06
10 + t06 +t
35 + t1113888 1113889 (15)
42 Modification of Multipliers for Composite Member Asmentioned earlier in the PCI Bridge DesignManual [18] forthe composite member the thickness of the topping is as-sumed to be 2 inches and the ratio of noncomposite tocomposite moments of inertia IoIc is 065 for all casesregardless of the shape of cross section However given thevariety of girder geometry and the recent bridge slab deck
0
10
20
30
40
50
60
70
80
90
100
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Tim
e-ra
tio v
alue
s for
cree
p an
d sh
rinka
ge (
)
Elapsed time (day)Creep time ratioShrinkage time ratioAverage time ratio of creep and shrinkage
Figure 1 Rate of creep and drying shrinkage over time
4 Advances in Civil Engineering
thickness the assumptions for composite members in thePCI Bridge Design Manual [18] are not likely to reflectmodern bridge characteristics -erefore in this study themultipliers for the long-term behavior of composite memberwere proposed by analyzing the representative cross sectionsof the recent bridges
Currently girder sections commonly used in single-spanrailway bridges in Korea are I girder box girder and WPC(wide flange prestressed concrete) In general a thickness ofslab placed on the girder is 280mm Figure 2 and Table 3show the details of the cross sections of I girder box girderand WPC which are the representative girder sections ac-tually used in practice Table 4 shows IoIc for all cross
sections of Figure 2 and Table 3 As shown in Table 4 thevalue of IoIc is different from 065 of the PCI Bridge DesignManual [18] IoIc was in the range of 051 to 056 and boxgirder bridges and long span bridges tend to have relativelylarge IoIc For the convenience of design this study pro-posed to use the total average value of 053 for IoIc
-e PCI Bridge Design Manual [18] assumed that thesection becomes composite at about the time of erectionbut it is not always Rather there are many cases wheretopping is not applied when the girder is erected because offield condition and construction schedules -ereforemultipliers have been proposed to enable the prediction ofdeflection and camber of the composite member at anytime t by considering the time t(c) at which the sectionbecomes composite -is can be expressed as follows using(7)ndash(10)
1 + μdtc 1 + μdt(c) + μdt minus μdt(c)1113872 1113873Io
Ic1113888 1113889
1 + μptc 1 + μpt(c) + μpt minus μpt(c)1113872 1113873Io
Ic1113888 1113889
(16)
where IoIc is 053-e factor for long-term deflection by a composite
topping should be also modified by the ratio of IoIc becausethe elastic deflection caused by the placement of the toppingto which the factor is applied is calculated using the non-composite section as follows
1 + μtt 1 + μsdtIo
Ic1113888 1113889 (17)
where μtt is the factor for additional long-term deflectioncaused by topping at any time t
As a result the multipliers of the PCI Bridge DesignManual [18] in Table 1 were revised as shown in Table 5
ed
ifg
h
b c ba
j k jl
(a)i
c b
j
da
cb
kl
m
nopq
o
g
n
he f
(b)
p
cb
m
n
q r
de
f
i j kg
lh g
k j i
o
a
(c)
Figure 2 Typical cross sections of PSC bridges (a) I girder (b) box girder (c) WPC girder
Table 3 Cross section dimension of I box and WPC girders byspan (mm)
Type I girder Box girder WPC girderSpan 25m 30m 35m 30m 35m 40m 30m 35m 40m 1000 1000 1000 1200 1200 1200 3580 3580 2650 400 400 400 220 220 220 150 150 150 200 200 200 50 50 50 100 100 100 80 150 150 660 660 660 982 1135 1514 90 120 120 2000 2400 2600 116 115 86 1520 1550 1950 1900 2300 2500 350 500 450 240 180 180 30 30 30 98 113 151 320 200 200 70 70 70 1181 1150 865 2350 2200 2600 400 350 350 730 730 370 240 350 350 50 50 50 110 110 110 200 200 200 1080 1530 1730 145 175 205 680 900 900 220 220 220 1610 1550 1280 mdash mdash mdash 250 250 250 1700 2000 2300 mdash mdash mdash 30 30 30 1450 1750 2050 mdash mdash mdash 220 220 220 135 135 135 mdash mdash mdash 760 760 760 115 115 115 mdash mdash mdash 1260 1260 1260 480 480 120 mdash mdash mdash mdash mdash mdash 250 250 250
Advances in Civil Engineering 5
5 Verification of Proposed Multipliers
In order to verify the proposed multipliers for actuallyconstructed PSC bridges the predictions of long-termcamber and deflection by the proposed multipliers werecompared with those by the basic PCI multipliers [18] theimproved PCI multipliers [20] and KR C-08090 [1] (same asACI 318-14 [2]) In addition numerical analysis was per-formed and the results were compared with the results fromother prediction methods
51 PSCBridges forVerification PSC bridges A and B whichwere recently constructed on a new line from Wonju toGangneung in Korearsquos high-speed railway were selected toverify the prediction methods Bridge A is a WPC type witha span of 388m and bridge B is constructed with an I-girdertype with a span of 34m -e cross-sectional details of thebridges at midspan are shown in Figure 3 Tables 6 and 7
show the construction history of the bridges and the elasticdeformation due to the applied load respectively
52 Numerical Analysis for Long-Term Behavior of PSCBridges Long-term behavior of the bridges A and B waspredicted using MIDAS Civil a general-purpose finite el-ement analysis program-e validity of theMIDAS Civil hasalready been confirmed through previous researches [22ndash24] In general the prediction of long-term behavior usinga finite element analysis is known to have a higher accuracythan that of the methods using a multiplier such as the PCIBridge Design Manual [18 20] although the design con-venience is poor [25ndash28] -erefore the numerical analysisresults were used to verify the newly proposed multipliers
-ematerial model was selected from the database of theMIDAS Civil program C40 and C27 were selected forthe girder and deck concrete respectively and the strandof SWPC7B empty152mm was selected for PS steel -ese
Table 4 Ratio of noncomposite to composite moments of inertia by girder type and span
Span PCI Bridge Design Manual I girder Box girder WPC girder Average25m
065
051 mdash mdash 05130m 049 054 053 05235m 052 056 050 05340m mdash 057 054 056Average 065 051 056 052 053
Table 5 Proposed multipliers
Without topping With toppingAt erection(1) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
1 + 17rt(e) 1 + 17rt(e)
(2) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
1 + 17rt(e)(1minus 015rt(e)) 1 + 17rt(e)(1minus 015rt(e))
At certain time(3) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
1 + 17rt 1 + 08rt(c) + 09rt
(4) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
1 + 17rt(1minus 015rt) 1 + 08rt(c)(1minus 015rt(c)) + 09rt(1minus 015 times rt)
(5) Deflection (downward)mdashapply to elasticdeflection due to superimposed dead load only 1 + 20r[tminust(s)] 1 + 20r[tminust(s)]
(6) Deflection (downward)mdashapply to elasticdeflection caused by the composite topping mdash 1 + 106r[tminust(c)]
Final(7) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
270 19 + 08rt(c)
(8) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
245 1765 + 08rt(c)(1minus 015rt(c))
(9) Deflection (downward)mdashapply to elasticdeflection due to superimposed dead load only 300 300
(10) Deflection (downward)mdashapply to elasticdeflection caused by the composite topping mdash 206
6 Advances in Civil Engineering
materials are the same as concrete and PS steel actually usedfor bridges A and B -e structural members of the bridgeswere modeled based on structural calculations and designdrawings of bridges A and B According to the designdrawing the strands were arranged by setting the actualcoordinates of the strand on the girder nodes using the 3-Dinput type from tendon profile option of MIDAS Civil -eCEB-FIP MC90 model [5] was used to calculate creep anddrying shrinkage of concrete For the relaxation of thetendon the Magura 45 model was used to consider thetime-dependent loss of the prestress Based on the con-struction history of the bridges A and B in Table 6construction sequence analysis was carried out After thecast of deck composite behavior of the girder and the deckwas simulated through the node connection using the rigidtype of elastic link In the same way common duct which isthe additional superimposed dead load was also simulatedfor composite behavior after its installation At the finalstage the deformation patterns of bridges A and B areshown in Figure 4 As a result the bridges A and B in themidspan showed 324mm and 393mm of camber at girdererection and 297mm and 192mm of camber at finalrespectively
53 Comparison of Predictions of Long-Term DeformationTables 8 and 9 and Figure 5 show the predictions of the long-term deformation of bridges A and B by using the proposedmultipliers the basic PCI multipliers [18] the improved PCImultipliers [20] KR C-08090 [1] and numerical analysisFor the improved PCI multipliers [20] the average values inTable 2 were used because the actual creep coefficient and theamount of the prestress loss can hardly be known
Although the values of predictions by the proposedmultipliers and KR C-08090 [1] were somewhat different
from the prediction by numerical analysis their predictiontrends of the camber over time were generally similar be-cause they provided available multipliers at any time In thecase of the basic PCI multipliers [18] however the long-term behavior after the erection was quite different fromother prediction methods because there are no applicablelong-term factors for the period between the erection andthe final
-e girder of bridge A was erected on the 30th day aftercasting while the girder of bridge B was erected on the 150thday relatively long time after casting -e basic PCI
1025 90 420 90 1025
2650
120
100
110
2670 30
00
150
2250
600
220
95 600150
2190
60600
3000
600
1040 110 695110695
(a)
400 200 4001000
2600
150
120
1950
180
200
2600
200 350350
900
(b)
Figure 3 Cross-sectional details of bridges (a) A and (b) B
Table 6 Construction history of bridges A and B
EventTime from casting (days)Bridge A Bridge B
(1) Release 1 1(2) Erection (t(e)) 30 150(3) Topping (t(c)) 240 157(4) 1st random time (t1) 270 180(5) Superimposed dead load (t(s)) 390 360(6) 2nd random time (t2) 700 1000
(7) Final 5 years ormore
5 years ormore
Table 7 Elastic camber and deflection of bridges A and B
LoadCamber (+) or deflection (minus)Bridge A Bridge B
Self-weight minus223 minus165Prestressing force +461 +353Topping minus80 minus75Superimposed dead load minus25 minus265
Advances in Civil Engineering 7
multiplier method [18] calculated the long-term camberusing the same multiplier for both bridges regardless of thedifferent erection time while the new proposed method useddifferent long-term multipliers for the bridges A and B inorder to consider different creep and shrinkage rates Asa result the predictions at erection by the proposed methodwere smaller for bridge A and larger for bridge B than thoseby the basic PCI multiplier method [18] as shown inFigure 5
In terms of the long-term behavior after erection thecamber predicted by KR C-08090 [1] was generally thelargest among all prediction methods KR C-08090 [1] doesnot take into account prestress loss so it overestimates thecamber by prestress force -e predictions by the proposedmethod were larger than the predictions by numericalanalysis until about 200 days after superimposed dead loadwas applied and thereafter they were smaller than thepredictions by numerical analysis
When comparing the camber at final the predictionswere large in the order of KR C-08090 [1] numericalanalysis proposed method improved PCI multipliers [20]and basic PCI multipliers [18] for both bridges A and BNumerical analysis seems to estimate the effect of creep and
shrinkage on long-term deformation weaker than othermethods In comparison with numerical analysis for de-formation at the final difference rates of the proposedmethod basic PCI multipliers [18] improved PCI multi-pliers [20] and KR C-08090 [1] were 101 259 116and 343 for bridge A respectively and 146 331143 and 350 for bridge B respectively It is interestingto note that the proposed formula and the improved PCImultiplier method [20] show very similar prediction resultsof ultimate deformation at final
Figure 6 shows the long-term behavior predicted by theproposed multipliers for each load type In early agesa relatively large amount of camber was observed due to theprestress but as time went by the rate of increase of camberby prestress decreased sharply because the amount of creepand drying shrinkage converged and the PS steel relaxationincreased -e amount of deflection due to self-weight wassmaller than the camber due to the prestress but the ten-dency of deflection over time was very similar to that ofcamber On the contrary after the girder erection a con-siderable amount of immediate deflection and long-termdeflection due to dead loads such as topping and commonduct partially offset the camber
000000e + 000270033e + 000540066e + 000810100e + 000108013e + 001135017e + 001162020e + 001189023e + 001216027e + 001243030e + 001270033e + 001297037e + 001
MIDASCivilpostndashprocessorDisplacementYZ-direction
(a)
000000e + 000175416e + 000350832e + 000526248e + 000701664e + 001877080e + 001105250e + 001122791e + 001140333e + 001157874e + 001175416e + 001192958e + 001
MIDASCivilpostprocessorDisplacementYZ-direction
(b)
Figure 4 Analysis result of final deformation of bridges (a) A and (b) B
8 Advances in Civil Engineering
Tabl
e8
Predictio
nsby
variou
smetho
dsforbridge
A(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus2
230
176
minus3929
236
minus5265
237
minus5291
241
minus5364
245
minus5453
254minus5
665
Prestress
4610
171
7887
220
10130
221
10171
223
10284
226
10420
233
10734
Topp
ing
minus800
148
minus1180
178
minus1427
192
minus1533
206minus1
648
Superimpo
sed
dead
load
minus250
266
minus664
300minus7
50
Total
2380
3957
4066
3700
3243
2771
2671
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus2
230
185
minus4126
minus4126
minus4126
240minus5
352
Prestress
4610
180
8298
8298
8298
220
10142
Topp
ing
minus800
minus800
230minus1
840
Superimpo
sed
dead
load
minus250
300minus7
50
Total
2380
4173
3373
3123
2200
Improved
PCI
BDM
Self-weigh
tminus2
230
196
minus4371
minus4371
minus4371
288minus6
422
Prestress
4610
196
9036
9036
9036
288
13277
Prestresslossminus6
92
100
minus692
minus692
minus692
232minus1
604
Topp
ing
minus800
minus800
250minus2
000
Superimpo
sed
dead
load
minus250
250minus6
25
Total
2380
3973
3173
2923
2625
KRC-08090
Self-weigh
tminus2
230
150
minus3345
227
minus5062
230
minus5129
245
minus5464
265
minus5910
300minus6
690
Prestress
4610
150
6915
227
10465
230
10603
245
11295
265
12217
300
13830
Topp
ing
minus800
150
minus1200
215
minus1720
250
minus2000
300minus2
400
Superimpo
sed
dead
load
minus250
235
minus588
300minus7
50
Total
2380
3570
4603
4274
3861
3720
3990
Num
erical
analysis
Total
2348
3237
3446
3240
2988
2894
2970
Advances in Civil Engineering 9
Tabl
e9
Predictio
nsby
variou
smetho
dsforbridge
B(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus1
650
226
minus3725
227
minus3744
229
minus3771
236
minus3886
242
minus3994
250minus4
120
Prestress
3530
212
7477
213
7508
214
7553
219
7740
224
7909
230
8102
Topp
ing
minus750
142
minus1065
183
minus1370
196
minus1470
206minus1
545
Superimpo
sed
dead
load
minus265
278
minus736
300minus7
95
Total
1880
3752
3014
2717
2218
1710
1642
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus1
650
185
minus3053
minus3053
minus3053
240minus3
960
Prestress
3530
180
6354
6354
6354
220
7766
Topp
ing
minus750
minus750
230minus1
725
Superimpo
sed
dead
load
minus265
300minus7
95
Total
1880
3302
2552
2287
1286
Improved
PCI
BDM
Self-weigh
tminus1
650
196
minus3234
minus3234
minus3234
288minus4
752
Prestress
3530
196
6919
6919
6919
288
10166
Prestresslossminus5
30
100
minus530
minus530
minus530
232minus1
228
Topp
ing
minus750
minus750
250minus1
875
Superimpo
sed
dead
load
minus265
250minus6
63
Total
1880
3155
2405
2140
1648
KRC-08090
Self-weigh
tminus1
650
210
minus3465
211
minus3482
220
minus3630
240
minus3960
280
minus4620
300minus4
950
Prestress
3530
210
7413
211
7448
220
7766
240
8472
280
9884
300
10590
Topp
ing
minus750
150
minus1125
220
minus1650
275
minus2063
300minus2
250
Superimpo
sed
dead
load
minus265
265
minus702
300minus7
95
Total
1880
3948
3217
3011
2597
2499
2595
Num
erical
analysis
Total
1792
3926
2866
2536
2138
1954
1923
10 Advances in Civil Engineering
Consequently the proposed multipliers method pro-vided not only the closest prediction values but also themost similar long-term behavior trend to the numericalanalysis
6 Conclusions
Since the current PCI Bridge Design Manual [18] providesthe long-term deformation multipliers only at erection andfinal it cannot consider various construction processesFurthermore the multipliers for the composite cross sectionare also required to be modified to reflect the characteristicsof the cross section used in modern PSC bridges -ereforein this study newmodified PCImultipliers were proposed toovercome these problems -e conclusions drawn from thisstudy are as follows
(1) -e new modified PCI multipliers were proposed byusing the rate of creep and shrinkage over timeUnlike the existing PCI Bridge Design Manual [18]method it is possible to reflect the actual girdererection time and predict the long-term deformationfor any construction schedule Moreover throughthe new method camber and deflection of PSCbridges can be predicted at any time including designstage construction stage and use stage
(2) -e ratio of noncomposite to composite moments ofinertia IoIc was 051ndash056 as a result of analyzingrepresentative cross sections used in practice byspan while the PCI Bridge Design Manual [18]suggests 065 of IoIc-erefore it is suggested to usethe average value of 053 for IoIc in order to predictthe long-term behavior of composite members
ndash80
ndash60
ndash40
ndash20
0
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
PS forceSelf-weight
ToppingAdditional DL
(a)
ToppingPS forceSelf-weight Additional DL
0
ndash80
ndash60
ndash40
ndash20
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 6 Predictions by the proposed multipliers for each load type (a) Bridge A (b) Bridge B
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
(a)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 5 Comparison of various predictions for bridges (a) A and (b) B
Advances in Civil Engineering 11
(3) In order to verify the proposed multipliers for ac-tually constructed PSC bridges the predictions oflong-term camber and deflection by the proposedmultipliers were compared with those by the basicPCI multipliers [18] improved PCI multipliers [20]KR C-08090 [1] and numerical analysis As a resultKR C-08090 [1] predictions were significantly higherthan the other predictions and the basic PCI mul-tipliers [18] did not show a reasonable tendency inthe long-term behavior between the erection timeand the final Among all methods except the pro-posed method the improved PCI multipliers [20]showed the most similar predictions to the nu-merical analysis However this improved PCImultiplier method also has limitations in finding thelong-term deflection or camber of the bridge at anytime and there are several variables such as the creepcoefficient that must be known precisely in order touse the multipliers which is inconvenient for de-signers to use However the predictions through thenewly proposed multipliers showed a reasonablelong-term behavior trend and the amount of thefinal camber was also the most similar to the nu-merical analysis result Above all the proposedmethod can make it possible for the designer topredict the long-term behavior of the bridge veryeasily according to any construction schedule
Data Availability
-e data used to support the findings of this study areavailable from the corresponding author upon request
Conflicts of Interest
-e authors declare that they have no conflicts of interest
Acknowledgments
-is research was supported by a grant (17RTRP-B067919-05) from Railroad Technology Research Program funded byMinistry of Land Infrastructure and Transport of Koreangovernment
References
[1] Korea Rail Network Authority Railway Design Guidelines andHandbooks Bridge Concrete Track Ends Usability Review (KRC-08090) in Korean Korea Rail Network Authority DaejeonRepublic of Korea 2014
[2] ACI Committee 318 Building Code Requirements for Struc-tural Concrete (ACI 318-14) and Commentary AmericanConcrete Institute Farmington Hills MI USA 2014
[3] ACI Committe 209 Prediction of Creep Shrinkage andTemperature Effects in Concrete Structure American ConcreteInstitute Farmington Hill MI USA 1992
[4] AASHTO (American Association of State Highway andTransportation Officials) AASHTO LRFD Bridge DesignSpecifications AASHTO Washington DC USA 2007
[5] CEBFIP Model Code Comit Euro-International du BetonTelford Ltd London UK 1990
[6] H-G Kwak and Y-J Seo ldquoLong-term behavior of compositegirder bridgesrdquo Computers and Structures vol 74 no 5pp 583ndash599 2000
[7] H Yang ldquoUncertainty and updating of long-term predictionof prestress forces in PSC box girder bridgesrdquo Computers andStructures vol 83 no 25ndash26 pp 2137ndash2149 2005
[8] S Biswal and A Ramaswamy ldquoUncertainty based modelaveraging for prediction of long-time prestress losses inconcrete structuresrdquo Construction and Building Materialsvol 153 pp 469ndash480 2017
[9] W He and Z Zhang ldquoModeling creep fracture in rock byusing kelvin discretized virtual internal bondrdquo Advances inCivil Engineering vol 2018 Article ID 8042965 8 pages 2018
[10] Y-S Park Y-H Lee and Y Lee ldquoDescription of concretecreep under time-varying stress using parallel creep curverdquoAdvances in Materials Science and Engineering vol 2016Article ID 9370514 13 pages 2016
[11] Z Pan and S Meng ldquo-ree-level experimental approach forcreep and shrinkage of high-strength high-performanceconcreterdquo Engineering Structures vol 120 pp 23ndash36 2016
[12] H-G Kwak and Y-J Seo ldquoNumerical analysis of time-dependent behavior of pre-cast pre-stressed concrete girderbridgesrdquo Construction and Building Materials vol 16 no 1pp 49ndash63 2002
[13] I N Robertson ldquoPrediction of vertical deflections for a long-span prestressed concrete bridge structurerdquo EngineeringStructures vol 27 no 12 pp 1820ndash1827 2005
[14] T Lou S M R Lopes and A V Lopes ldquoA finite elementmodel to simulate long-term behavior of prestressed concretegirdersrdquo Finite Elements in Analysis and Design vol 81pp 48ndash56 2014
[15] P Liu Q Xing DWang andM Oeser ldquoApplication of linearviscoelastic properties in semianalytical finite element methodwith recursive time integration to analyze asphalt pavementstructurerdquo Advances in Civil Engineering vol 2018 Article ID9045820 15 pages 2018
[16] A Sagara and I Pane ldquoA study on effects of creep andshrinkage in high strength concrete bridgesrdquo Procedia En-gineering vol 125 pp 1087ndash1093 2015
[17] H Sousa J Bento and J Figueiras ldquoConstruction assessmentand long-term prediction of prestressed concrete bridgesbased on monitoring datardquo Engineering Structures vol 52pp 26ndash37 2013
[18] PCI Bridge Design Manual Second Release PrecastPrestressed Concrete Institute Chicago IL USA 3rd edi-tion 2014
[19] L D Martin ldquoA rational method for estimating camber anddeflection of precast prestressed membersrdquo PCI Journalvol 22 no 1 pp 100ndash108 1977
[20] PCI Bridge Design Manual PrecastPrestressed ConcreteInstitute Chicago IL USA 2nd edition 2003
[21] M K Tadros A Ghali and A W Meyer ldquoPrestressed lossand deflection of precast concrete membersrdquo PCI Journalvol 30 no 1 pp 114ndash141 1985
[22] Y Zhang ldquoOrthogonal test analysis on influencing factors ofprestressed concrete small box beam camberrdquo Applied Me-chanics and Materials vol 405-408 pp 1527ndash1530 2013
[23] Y Jianjun W Xun and H Xianzheng ldquoEffects of live load onthe deflection of long-span PC continuous rigid-framehighway bridge based on midasrdquo in Proceedings of 20147th International Conference on Intelligent ComputationTechnology and Automation pp 944ndash946 Changsha China2014
12 Advances in Civil Engineering
[24] T Grigorjeva A Juozapaitis and Z Kamaitis ldquoStatic analysisand simplified design of suspension bridges having variousrigidity of cablesrdquo Journal of Civil Engineering and Man-agement vol 16 no 3 pp 363ndash371 2011
[25] ACI Committee 435 Control of Deflection in ConcreteStructures ACI 435R-95 ACI Farmington Hills MI USA2003
[26] F B Angomas ldquoBehavior of prestressed concrete bridgegirdersrdquo All Graduate -eses and Dissertations Utah StateUniversity Logan UT USA 2009
[27] E H Gheitanbaf ldquoImproving the prediction of time-dependent effects on prestressed concrete bridgesrdquo Gradu-ate-eses and Dissertations Iowa State University Ames IAUSA 2015
[28] M K Tadros F Fawzy and K Hanna ldquoPrecast prestressedgirder camber variabilityrdquo PCI Journal vol 56 no 1pp 135ndash154 2011
Advances in Civil Engineering 13
International Journal of
AerospaceEngineeringHindawiwwwhindawicom Volume 2018
RoboticsJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Active and Passive Electronic Components
VLSI Design
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Shock and Vibration
Hindawiwwwhindawicom Volume 2018
Civil EngineeringAdvances in
Acoustics and VibrationAdvances in
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Electrical and Computer Engineering
Journal of
Advances inOptoElectronics
Hindawiwwwhindawicom
Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Control Scienceand Engineering
Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Journal ofEngineeringVolume 2018
SensorsJournal of
Hindawiwwwhindawicom Volume 2018
International Journal of
RotatingMachinery
Hindawiwwwhindawicom Volume 2018
Modelling ampSimulationin EngineeringHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Chemical EngineeringInternational Journal of Antennas and
Propagation
International Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Navigation and Observation
International Journal of
Hindawi
wwwhindawicom Volume 2018
Advances in
Multimedia
Submit your manuscripts atwwwhindawicom
thickness the assumptions for composite members in thePCI Bridge Design Manual [18] are not likely to reflectmodern bridge characteristics -erefore in this study themultipliers for the long-term behavior of composite memberwere proposed by analyzing the representative cross sectionsof the recent bridges
Currently girder sections commonly used in single-spanrailway bridges in Korea are I girder box girder and WPC(wide flange prestressed concrete) In general a thickness ofslab placed on the girder is 280mm Figure 2 and Table 3show the details of the cross sections of I girder box girderand WPC which are the representative girder sections ac-tually used in practice Table 4 shows IoIc for all cross
sections of Figure 2 and Table 3 As shown in Table 4 thevalue of IoIc is different from 065 of the PCI Bridge DesignManual [18] IoIc was in the range of 051 to 056 and boxgirder bridges and long span bridges tend to have relativelylarge IoIc For the convenience of design this study pro-posed to use the total average value of 053 for IoIc
-e PCI Bridge Design Manual [18] assumed that thesection becomes composite at about the time of erectionbut it is not always Rather there are many cases wheretopping is not applied when the girder is erected because offield condition and construction schedules -ereforemultipliers have been proposed to enable the prediction ofdeflection and camber of the composite member at anytime t by considering the time t(c) at which the sectionbecomes composite -is can be expressed as follows using(7)ndash(10)
1 + μdtc 1 + μdt(c) + μdt minus μdt(c)1113872 1113873Io
Ic1113888 1113889
1 + μptc 1 + μpt(c) + μpt minus μpt(c)1113872 1113873Io
Ic1113888 1113889
(16)
where IoIc is 053-e factor for long-term deflection by a composite
topping should be also modified by the ratio of IoIc becausethe elastic deflection caused by the placement of the toppingto which the factor is applied is calculated using the non-composite section as follows
1 + μtt 1 + μsdtIo
Ic1113888 1113889 (17)
where μtt is the factor for additional long-term deflectioncaused by topping at any time t
As a result the multipliers of the PCI Bridge DesignManual [18] in Table 1 were revised as shown in Table 5
ed
ifg
h
b c ba
j k jl
(a)i
c b
j
da
cb
kl
m
nopq
o
g
n
he f
(b)
p
cb
m
n
q r
de
f
i j kg
lh g
k j i
o
a
(c)
Figure 2 Typical cross sections of PSC bridges (a) I girder (b) box girder (c) WPC girder
Table 3 Cross section dimension of I box and WPC girders byspan (mm)
Type I girder Box girder WPC girderSpan 25m 30m 35m 30m 35m 40m 30m 35m 40m 1000 1000 1000 1200 1200 1200 3580 3580 2650 400 400 400 220 220 220 150 150 150 200 200 200 50 50 50 100 100 100 80 150 150 660 660 660 982 1135 1514 90 120 120 2000 2400 2600 116 115 86 1520 1550 1950 1900 2300 2500 350 500 450 240 180 180 30 30 30 98 113 151 320 200 200 70 70 70 1181 1150 865 2350 2200 2600 400 350 350 730 730 370 240 350 350 50 50 50 110 110 110 200 200 200 1080 1530 1730 145 175 205 680 900 900 220 220 220 1610 1550 1280 mdash mdash mdash 250 250 250 1700 2000 2300 mdash mdash mdash 30 30 30 1450 1750 2050 mdash mdash mdash 220 220 220 135 135 135 mdash mdash mdash 760 760 760 115 115 115 mdash mdash mdash 1260 1260 1260 480 480 120 mdash mdash mdash mdash mdash mdash 250 250 250
Advances in Civil Engineering 5
5 Verification of Proposed Multipliers
In order to verify the proposed multipliers for actuallyconstructed PSC bridges the predictions of long-termcamber and deflection by the proposed multipliers werecompared with those by the basic PCI multipliers [18] theimproved PCI multipliers [20] and KR C-08090 [1] (same asACI 318-14 [2]) In addition numerical analysis was per-formed and the results were compared with the results fromother prediction methods
51 PSCBridges forVerification PSC bridges A and B whichwere recently constructed on a new line from Wonju toGangneung in Korearsquos high-speed railway were selected toverify the prediction methods Bridge A is a WPC type witha span of 388m and bridge B is constructed with an I-girdertype with a span of 34m -e cross-sectional details of thebridges at midspan are shown in Figure 3 Tables 6 and 7
show the construction history of the bridges and the elasticdeformation due to the applied load respectively
52 Numerical Analysis for Long-Term Behavior of PSCBridges Long-term behavior of the bridges A and B waspredicted using MIDAS Civil a general-purpose finite el-ement analysis program-e validity of theMIDAS Civil hasalready been confirmed through previous researches [22ndash24] In general the prediction of long-term behavior usinga finite element analysis is known to have a higher accuracythan that of the methods using a multiplier such as the PCIBridge Design Manual [18 20] although the design con-venience is poor [25ndash28] -erefore the numerical analysisresults were used to verify the newly proposed multipliers
-ematerial model was selected from the database of theMIDAS Civil program C40 and C27 were selected forthe girder and deck concrete respectively and the strandof SWPC7B empty152mm was selected for PS steel -ese
Table 4 Ratio of noncomposite to composite moments of inertia by girder type and span
Span PCI Bridge Design Manual I girder Box girder WPC girder Average25m
065
051 mdash mdash 05130m 049 054 053 05235m 052 056 050 05340m mdash 057 054 056Average 065 051 056 052 053
Table 5 Proposed multipliers
Without topping With toppingAt erection(1) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
1 + 17rt(e) 1 + 17rt(e)
(2) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
1 + 17rt(e)(1minus 015rt(e)) 1 + 17rt(e)(1minus 015rt(e))
At certain time(3) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
1 + 17rt 1 + 08rt(c) + 09rt
(4) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
1 + 17rt(1minus 015rt) 1 + 08rt(c)(1minus 015rt(c)) + 09rt(1minus 015 times rt)
(5) Deflection (downward)mdashapply to elasticdeflection due to superimposed dead load only 1 + 20r[tminust(s)] 1 + 20r[tminust(s)]
(6) Deflection (downward)mdashapply to elasticdeflection caused by the composite topping mdash 1 + 106r[tminust(c)]
Final(7) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
270 19 + 08rt(c)
(8) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
245 1765 + 08rt(c)(1minus 015rt(c))
(9) Deflection (downward)mdashapply to elasticdeflection due to superimposed dead load only 300 300
(10) Deflection (downward)mdashapply to elasticdeflection caused by the composite topping mdash 206
6 Advances in Civil Engineering
materials are the same as concrete and PS steel actually usedfor bridges A and B -e structural members of the bridgeswere modeled based on structural calculations and designdrawings of bridges A and B According to the designdrawing the strands were arranged by setting the actualcoordinates of the strand on the girder nodes using the 3-Dinput type from tendon profile option of MIDAS Civil -eCEB-FIP MC90 model [5] was used to calculate creep anddrying shrinkage of concrete For the relaxation of thetendon the Magura 45 model was used to consider thetime-dependent loss of the prestress Based on the con-struction history of the bridges A and B in Table 6construction sequence analysis was carried out After thecast of deck composite behavior of the girder and the deckwas simulated through the node connection using the rigidtype of elastic link In the same way common duct which isthe additional superimposed dead load was also simulatedfor composite behavior after its installation At the finalstage the deformation patterns of bridges A and B areshown in Figure 4 As a result the bridges A and B in themidspan showed 324mm and 393mm of camber at girdererection and 297mm and 192mm of camber at finalrespectively
53 Comparison of Predictions of Long-Term DeformationTables 8 and 9 and Figure 5 show the predictions of the long-term deformation of bridges A and B by using the proposedmultipliers the basic PCI multipliers [18] the improved PCImultipliers [20] KR C-08090 [1] and numerical analysisFor the improved PCI multipliers [20] the average values inTable 2 were used because the actual creep coefficient and theamount of the prestress loss can hardly be known
Although the values of predictions by the proposedmultipliers and KR C-08090 [1] were somewhat different
from the prediction by numerical analysis their predictiontrends of the camber over time were generally similar be-cause they provided available multipliers at any time In thecase of the basic PCI multipliers [18] however the long-term behavior after the erection was quite different fromother prediction methods because there are no applicablelong-term factors for the period between the erection andthe final
-e girder of bridge A was erected on the 30th day aftercasting while the girder of bridge B was erected on the 150thday relatively long time after casting -e basic PCI
1025 90 420 90 1025
2650
120
100
110
2670 30
00
150
2250
600
220
95 600150
2190
60600
3000
600
1040 110 695110695
(a)
400 200 4001000
2600
150
120
1950
180
200
2600
200 350350
900
(b)
Figure 3 Cross-sectional details of bridges (a) A and (b) B
Table 6 Construction history of bridges A and B
EventTime from casting (days)Bridge A Bridge B
(1) Release 1 1(2) Erection (t(e)) 30 150(3) Topping (t(c)) 240 157(4) 1st random time (t1) 270 180(5) Superimposed dead load (t(s)) 390 360(6) 2nd random time (t2) 700 1000
(7) Final 5 years ormore
5 years ormore
Table 7 Elastic camber and deflection of bridges A and B
LoadCamber (+) or deflection (minus)Bridge A Bridge B
Self-weight minus223 minus165Prestressing force +461 +353Topping minus80 minus75Superimposed dead load minus25 minus265
Advances in Civil Engineering 7
multiplier method [18] calculated the long-term camberusing the same multiplier for both bridges regardless of thedifferent erection time while the new proposed method useddifferent long-term multipliers for the bridges A and B inorder to consider different creep and shrinkage rates Asa result the predictions at erection by the proposed methodwere smaller for bridge A and larger for bridge B than thoseby the basic PCI multiplier method [18] as shown inFigure 5
In terms of the long-term behavior after erection thecamber predicted by KR C-08090 [1] was generally thelargest among all prediction methods KR C-08090 [1] doesnot take into account prestress loss so it overestimates thecamber by prestress force -e predictions by the proposedmethod were larger than the predictions by numericalanalysis until about 200 days after superimposed dead loadwas applied and thereafter they were smaller than thepredictions by numerical analysis
When comparing the camber at final the predictionswere large in the order of KR C-08090 [1] numericalanalysis proposed method improved PCI multipliers [20]and basic PCI multipliers [18] for both bridges A and BNumerical analysis seems to estimate the effect of creep and
shrinkage on long-term deformation weaker than othermethods In comparison with numerical analysis for de-formation at the final difference rates of the proposedmethod basic PCI multipliers [18] improved PCI multi-pliers [20] and KR C-08090 [1] were 101 259 116and 343 for bridge A respectively and 146 331143 and 350 for bridge B respectively It is interestingto note that the proposed formula and the improved PCImultiplier method [20] show very similar prediction resultsof ultimate deformation at final
Figure 6 shows the long-term behavior predicted by theproposed multipliers for each load type In early agesa relatively large amount of camber was observed due to theprestress but as time went by the rate of increase of camberby prestress decreased sharply because the amount of creepand drying shrinkage converged and the PS steel relaxationincreased -e amount of deflection due to self-weight wassmaller than the camber due to the prestress but the ten-dency of deflection over time was very similar to that ofcamber On the contrary after the girder erection a con-siderable amount of immediate deflection and long-termdeflection due to dead loads such as topping and commonduct partially offset the camber
000000e + 000270033e + 000540066e + 000810100e + 000108013e + 001135017e + 001162020e + 001189023e + 001216027e + 001243030e + 001270033e + 001297037e + 001
MIDASCivilpostndashprocessorDisplacementYZ-direction
(a)
000000e + 000175416e + 000350832e + 000526248e + 000701664e + 001877080e + 001105250e + 001122791e + 001140333e + 001157874e + 001175416e + 001192958e + 001
MIDASCivilpostprocessorDisplacementYZ-direction
(b)
Figure 4 Analysis result of final deformation of bridges (a) A and (b) B
8 Advances in Civil Engineering
Tabl
e8
Predictio
nsby
variou
smetho
dsforbridge
A(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus2
230
176
minus3929
236
minus5265
237
minus5291
241
minus5364
245
minus5453
254minus5
665
Prestress
4610
171
7887
220
10130
221
10171
223
10284
226
10420
233
10734
Topp
ing
minus800
148
minus1180
178
minus1427
192
minus1533
206minus1
648
Superimpo
sed
dead
load
minus250
266
minus664
300minus7
50
Total
2380
3957
4066
3700
3243
2771
2671
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus2
230
185
minus4126
minus4126
minus4126
240minus5
352
Prestress
4610
180
8298
8298
8298
220
10142
Topp
ing
minus800
minus800
230minus1
840
Superimpo
sed
dead
load
minus250
300minus7
50
Total
2380
4173
3373
3123
2200
Improved
PCI
BDM
Self-weigh
tminus2
230
196
minus4371
minus4371
minus4371
288minus6
422
Prestress
4610
196
9036
9036
9036
288
13277
Prestresslossminus6
92
100
minus692
minus692
minus692
232minus1
604
Topp
ing
minus800
minus800
250minus2
000
Superimpo
sed
dead
load
minus250
250minus6
25
Total
2380
3973
3173
2923
2625
KRC-08090
Self-weigh
tminus2
230
150
minus3345
227
minus5062
230
minus5129
245
minus5464
265
minus5910
300minus6
690
Prestress
4610
150
6915
227
10465
230
10603
245
11295
265
12217
300
13830
Topp
ing
minus800
150
minus1200
215
minus1720
250
minus2000
300minus2
400
Superimpo
sed
dead
load
minus250
235
minus588
300minus7
50
Total
2380
3570
4603
4274
3861
3720
3990
Num
erical
analysis
Total
2348
3237
3446
3240
2988
2894
2970
Advances in Civil Engineering 9
Tabl
e9
Predictio
nsby
variou
smetho
dsforbridge
B(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus1
650
226
minus3725
227
minus3744
229
minus3771
236
minus3886
242
minus3994
250minus4
120
Prestress
3530
212
7477
213
7508
214
7553
219
7740
224
7909
230
8102
Topp
ing
minus750
142
minus1065
183
minus1370
196
minus1470
206minus1
545
Superimpo
sed
dead
load
minus265
278
minus736
300minus7
95
Total
1880
3752
3014
2717
2218
1710
1642
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus1
650
185
minus3053
minus3053
minus3053
240minus3
960
Prestress
3530
180
6354
6354
6354
220
7766
Topp
ing
minus750
minus750
230minus1
725
Superimpo
sed
dead
load
minus265
300minus7
95
Total
1880
3302
2552
2287
1286
Improved
PCI
BDM
Self-weigh
tminus1
650
196
minus3234
minus3234
minus3234
288minus4
752
Prestress
3530
196
6919
6919
6919
288
10166
Prestresslossminus5
30
100
minus530
minus530
minus530
232minus1
228
Topp
ing
minus750
minus750
250minus1
875
Superimpo
sed
dead
load
minus265
250minus6
63
Total
1880
3155
2405
2140
1648
KRC-08090
Self-weigh
tminus1
650
210
minus3465
211
minus3482
220
minus3630
240
minus3960
280
minus4620
300minus4
950
Prestress
3530
210
7413
211
7448
220
7766
240
8472
280
9884
300
10590
Topp
ing
minus750
150
minus1125
220
minus1650
275
minus2063
300minus2
250
Superimpo
sed
dead
load
minus265
265
minus702
300minus7
95
Total
1880
3948
3217
3011
2597
2499
2595
Num
erical
analysis
Total
1792
3926
2866
2536
2138
1954
1923
10 Advances in Civil Engineering
Consequently the proposed multipliers method pro-vided not only the closest prediction values but also themost similar long-term behavior trend to the numericalanalysis
6 Conclusions
Since the current PCI Bridge Design Manual [18] providesthe long-term deformation multipliers only at erection andfinal it cannot consider various construction processesFurthermore the multipliers for the composite cross sectionare also required to be modified to reflect the characteristicsof the cross section used in modern PSC bridges -ereforein this study newmodified PCImultipliers were proposed toovercome these problems -e conclusions drawn from thisstudy are as follows
(1) -e new modified PCI multipliers were proposed byusing the rate of creep and shrinkage over timeUnlike the existing PCI Bridge Design Manual [18]method it is possible to reflect the actual girdererection time and predict the long-term deformationfor any construction schedule Moreover throughthe new method camber and deflection of PSCbridges can be predicted at any time including designstage construction stage and use stage
(2) -e ratio of noncomposite to composite moments ofinertia IoIc was 051ndash056 as a result of analyzingrepresentative cross sections used in practice byspan while the PCI Bridge Design Manual [18]suggests 065 of IoIc-erefore it is suggested to usethe average value of 053 for IoIc in order to predictthe long-term behavior of composite members
ndash80
ndash60
ndash40
ndash20
0
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
PS forceSelf-weight
ToppingAdditional DL
(a)
ToppingPS forceSelf-weight Additional DL
0
ndash80
ndash60
ndash40
ndash20
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 6 Predictions by the proposed multipliers for each load type (a) Bridge A (b) Bridge B
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
(a)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 5 Comparison of various predictions for bridges (a) A and (b) B
Advances in Civil Engineering 11
(3) In order to verify the proposed multipliers for ac-tually constructed PSC bridges the predictions oflong-term camber and deflection by the proposedmultipliers were compared with those by the basicPCI multipliers [18] improved PCI multipliers [20]KR C-08090 [1] and numerical analysis As a resultKR C-08090 [1] predictions were significantly higherthan the other predictions and the basic PCI mul-tipliers [18] did not show a reasonable tendency inthe long-term behavior between the erection timeand the final Among all methods except the pro-posed method the improved PCI multipliers [20]showed the most similar predictions to the nu-merical analysis However this improved PCImultiplier method also has limitations in finding thelong-term deflection or camber of the bridge at anytime and there are several variables such as the creepcoefficient that must be known precisely in order touse the multipliers which is inconvenient for de-signers to use However the predictions through thenewly proposed multipliers showed a reasonablelong-term behavior trend and the amount of thefinal camber was also the most similar to the nu-merical analysis result Above all the proposedmethod can make it possible for the designer topredict the long-term behavior of the bridge veryeasily according to any construction schedule
Data Availability
-e data used to support the findings of this study areavailable from the corresponding author upon request
Conflicts of Interest
-e authors declare that they have no conflicts of interest
Acknowledgments
-is research was supported by a grant (17RTRP-B067919-05) from Railroad Technology Research Program funded byMinistry of Land Infrastructure and Transport of Koreangovernment
References
[1] Korea Rail Network Authority Railway Design Guidelines andHandbooks Bridge Concrete Track Ends Usability Review (KRC-08090) in Korean Korea Rail Network Authority DaejeonRepublic of Korea 2014
[2] ACI Committee 318 Building Code Requirements for Struc-tural Concrete (ACI 318-14) and Commentary AmericanConcrete Institute Farmington Hills MI USA 2014
[3] ACI Committe 209 Prediction of Creep Shrinkage andTemperature Effects in Concrete Structure American ConcreteInstitute Farmington Hill MI USA 1992
[4] AASHTO (American Association of State Highway andTransportation Officials) AASHTO LRFD Bridge DesignSpecifications AASHTO Washington DC USA 2007
[5] CEBFIP Model Code Comit Euro-International du BetonTelford Ltd London UK 1990
[6] H-G Kwak and Y-J Seo ldquoLong-term behavior of compositegirder bridgesrdquo Computers and Structures vol 74 no 5pp 583ndash599 2000
[7] H Yang ldquoUncertainty and updating of long-term predictionof prestress forces in PSC box girder bridgesrdquo Computers andStructures vol 83 no 25ndash26 pp 2137ndash2149 2005
[8] S Biswal and A Ramaswamy ldquoUncertainty based modelaveraging for prediction of long-time prestress losses inconcrete structuresrdquo Construction and Building Materialsvol 153 pp 469ndash480 2017
[9] W He and Z Zhang ldquoModeling creep fracture in rock byusing kelvin discretized virtual internal bondrdquo Advances inCivil Engineering vol 2018 Article ID 8042965 8 pages 2018
[10] Y-S Park Y-H Lee and Y Lee ldquoDescription of concretecreep under time-varying stress using parallel creep curverdquoAdvances in Materials Science and Engineering vol 2016Article ID 9370514 13 pages 2016
[11] Z Pan and S Meng ldquo-ree-level experimental approach forcreep and shrinkage of high-strength high-performanceconcreterdquo Engineering Structures vol 120 pp 23ndash36 2016
[12] H-G Kwak and Y-J Seo ldquoNumerical analysis of time-dependent behavior of pre-cast pre-stressed concrete girderbridgesrdquo Construction and Building Materials vol 16 no 1pp 49ndash63 2002
[13] I N Robertson ldquoPrediction of vertical deflections for a long-span prestressed concrete bridge structurerdquo EngineeringStructures vol 27 no 12 pp 1820ndash1827 2005
[14] T Lou S M R Lopes and A V Lopes ldquoA finite elementmodel to simulate long-term behavior of prestressed concretegirdersrdquo Finite Elements in Analysis and Design vol 81pp 48ndash56 2014
[15] P Liu Q Xing DWang andM Oeser ldquoApplication of linearviscoelastic properties in semianalytical finite element methodwith recursive time integration to analyze asphalt pavementstructurerdquo Advances in Civil Engineering vol 2018 Article ID9045820 15 pages 2018
[16] A Sagara and I Pane ldquoA study on effects of creep andshrinkage in high strength concrete bridgesrdquo Procedia En-gineering vol 125 pp 1087ndash1093 2015
[17] H Sousa J Bento and J Figueiras ldquoConstruction assessmentand long-term prediction of prestressed concrete bridgesbased on monitoring datardquo Engineering Structures vol 52pp 26ndash37 2013
[18] PCI Bridge Design Manual Second Release PrecastPrestressed Concrete Institute Chicago IL USA 3rd edi-tion 2014
[19] L D Martin ldquoA rational method for estimating camber anddeflection of precast prestressed membersrdquo PCI Journalvol 22 no 1 pp 100ndash108 1977
[20] PCI Bridge Design Manual PrecastPrestressed ConcreteInstitute Chicago IL USA 2nd edition 2003
[21] M K Tadros A Ghali and A W Meyer ldquoPrestressed lossand deflection of precast concrete membersrdquo PCI Journalvol 30 no 1 pp 114ndash141 1985
[22] Y Zhang ldquoOrthogonal test analysis on influencing factors ofprestressed concrete small box beam camberrdquo Applied Me-chanics and Materials vol 405-408 pp 1527ndash1530 2013
[23] Y Jianjun W Xun and H Xianzheng ldquoEffects of live load onthe deflection of long-span PC continuous rigid-framehighway bridge based on midasrdquo in Proceedings of 20147th International Conference on Intelligent ComputationTechnology and Automation pp 944ndash946 Changsha China2014
12 Advances in Civil Engineering
[24] T Grigorjeva A Juozapaitis and Z Kamaitis ldquoStatic analysisand simplified design of suspension bridges having variousrigidity of cablesrdquo Journal of Civil Engineering and Man-agement vol 16 no 3 pp 363ndash371 2011
[25] ACI Committee 435 Control of Deflection in ConcreteStructures ACI 435R-95 ACI Farmington Hills MI USA2003
[26] F B Angomas ldquoBehavior of prestressed concrete bridgegirdersrdquo All Graduate -eses and Dissertations Utah StateUniversity Logan UT USA 2009
[27] E H Gheitanbaf ldquoImproving the prediction of time-dependent effects on prestressed concrete bridgesrdquo Gradu-ate-eses and Dissertations Iowa State University Ames IAUSA 2015
[28] M K Tadros F Fawzy and K Hanna ldquoPrecast prestressedgirder camber variabilityrdquo PCI Journal vol 56 no 1pp 135ndash154 2011
Advances in Civil Engineering 13
International Journal of
AerospaceEngineeringHindawiwwwhindawicom Volume 2018
RoboticsJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Active and Passive Electronic Components
VLSI Design
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Shock and Vibration
Hindawiwwwhindawicom Volume 2018
Civil EngineeringAdvances in
Acoustics and VibrationAdvances in
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Electrical and Computer Engineering
Journal of
Advances inOptoElectronics
Hindawiwwwhindawicom
Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Control Scienceand Engineering
Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Journal ofEngineeringVolume 2018
SensorsJournal of
Hindawiwwwhindawicom Volume 2018
International Journal of
RotatingMachinery
Hindawiwwwhindawicom Volume 2018
Modelling ampSimulationin EngineeringHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Chemical EngineeringInternational Journal of Antennas and
Propagation
International Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Navigation and Observation
International Journal of
Hindawi
wwwhindawicom Volume 2018
Advances in
Multimedia
Submit your manuscripts atwwwhindawicom
5 Verification of Proposed Multipliers
In order to verify the proposed multipliers for actuallyconstructed PSC bridges the predictions of long-termcamber and deflection by the proposed multipliers werecompared with those by the basic PCI multipliers [18] theimproved PCI multipliers [20] and KR C-08090 [1] (same asACI 318-14 [2]) In addition numerical analysis was per-formed and the results were compared with the results fromother prediction methods
51 PSCBridges forVerification PSC bridges A and B whichwere recently constructed on a new line from Wonju toGangneung in Korearsquos high-speed railway were selected toverify the prediction methods Bridge A is a WPC type witha span of 388m and bridge B is constructed with an I-girdertype with a span of 34m -e cross-sectional details of thebridges at midspan are shown in Figure 3 Tables 6 and 7
show the construction history of the bridges and the elasticdeformation due to the applied load respectively
52 Numerical Analysis for Long-Term Behavior of PSCBridges Long-term behavior of the bridges A and B waspredicted using MIDAS Civil a general-purpose finite el-ement analysis program-e validity of theMIDAS Civil hasalready been confirmed through previous researches [22ndash24] In general the prediction of long-term behavior usinga finite element analysis is known to have a higher accuracythan that of the methods using a multiplier such as the PCIBridge Design Manual [18 20] although the design con-venience is poor [25ndash28] -erefore the numerical analysisresults were used to verify the newly proposed multipliers
-ematerial model was selected from the database of theMIDAS Civil program C40 and C27 were selected forthe girder and deck concrete respectively and the strandof SWPC7B empty152mm was selected for PS steel -ese
Table 4 Ratio of noncomposite to composite moments of inertia by girder type and span
Span PCI Bridge Design Manual I girder Box girder WPC girder Average25m
065
051 mdash mdash 05130m 049 054 053 05235m 052 056 050 05340m mdash 057 054 056Average 065 051 056 052 053
Table 5 Proposed multipliers
Without topping With toppingAt erection(1) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
1 + 17rt(e) 1 + 17rt(e)
(2) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
1 + 17rt(e)(1minus 015rt(e)) 1 + 17rt(e)(1minus 015rt(e))
At certain time(3) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
1 + 17rt 1 + 08rt(c) + 09rt
(4) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
1 + 17rt(1minus 015rt) 1 + 08rt(c)(1minus 015rt(c)) + 09rt(1minus 015 times rt)
(5) Deflection (downward)mdashapply to elasticdeflection due to superimposed dead load only 1 + 20r[tminust(s)] 1 + 20r[tminust(s)]
(6) Deflection (downward)mdashapply to elasticdeflection caused by the composite topping mdash 1 + 106r[tminust(c)]
Final(7) Deflection (downward) componentmdashapply to theelastic deflection due to the member weight attransfer of prestress
270 19 + 08rt(c)
(8) Camber (upward) componentmdashapply to theelastic camber due to prestress at the time of transferof prestress
245 1765 + 08rt(c)(1minus 015rt(c))
(9) Deflection (downward)mdashapply to elasticdeflection due to superimposed dead load only 300 300
(10) Deflection (downward)mdashapply to elasticdeflection caused by the composite topping mdash 206
6 Advances in Civil Engineering
materials are the same as concrete and PS steel actually usedfor bridges A and B -e structural members of the bridgeswere modeled based on structural calculations and designdrawings of bridges A and B According to the designdrawing the strands were arranged by setting the actualcoordinates of the strand on the girder nodes using the 3-Dinput type from tendon profile option of MIDAS Civil -eCEB-FIP MC90 model [5] was used to calculate creep anddrying shrinkage of concrete For the relaxation of thetendon the Magura 45 model was used to consider thetime-dependent loss of the prestress Based on the con-struction history of the bridges A and B in Table 6construction sequence analysis was carried out After thecast of deck composite behavior of the girder and the deckwas simulated through the node connection using the rigidtype of elastic link In the same way common duct which isthe additional superimposed dead load was also simulatedfor composite behavior after its installation At the finalstage the deformation patterns of bridges A and B areshown in Figure 4 As a result the bridges A and B in themidspan showed 324mm and 393mm of camber at girdererection and 297mm and 192mm of camber at finalrespectively
53 Comparison of Predictions of Long-Term DeformationTables 8 and 9 and Figure 5 show the predictions of the long-term deformation of bridges A and B by using the proposedmultipliers the basic PCI multipliers [18] the improved PCImultipliers [20] KR C-08090 [1] and numerical analysisFor the improved PCI multipliers [20] the average values inTable 2 were used because the actual creep coefficient and theamount of the prestress loss can hardly be known
Although the values of predictions by the proposedmultipliers and KR C-08090 [1] were somewhat different
from the prediction by numerical analysis their predictiontrends of the camber over time were generally similar be-cause they provided available multipliers at any time In thecase of the basic PCI multipliers [18] however the long-term behavior after the erection was quite different fromother prediction methods because there are no applicablelong-term factors for the period between the erection andthe final
-e girder of bridge A was erected on the 30th day aftercasting while the girder of bridge B was erected on the 150thday relatively long time after casting -e basic PCI
1025 90 420 90 1025
2650
120
100
110
2670 30
00
150
2250
600
220
95 600150
2190
60600
3000
600
1040 110 695110695
(a)
400 200 4001000
2600
150
120
1950
180
200
2600
200 350350
900
(b)
Figure 3 Cross-sectional details of bridges (a) A and (b) B
Table 6 Construction history of bridges A and B
EventTime from casting (days)Bridge A Bridge B
(1) Release 1 1(2) Erection (t(e)) 30 150(3) Topping (t(c)) 240 157(4) 1st random time (t1) 270 180(5) Superimposed dead load (t(s)) 390 360(6) 2nd random time (t2) 700 1000
(7) Final 5 years ormore
5 years ormore
Table 7 Elastic camber and deflection of bridges A and B
LoadCamber (+) or deflection (minus)Bridge A Bridge B
Self-weight minus223 minus165Prestressing force +461 +353Topping minus80 minus75Superimposed dead load minus25 minus265
Advances in Civil Engineering 7
multiplier method [18] calculated the long-term camberusing the same multiplier for both bridges regardless of thedifferent erection time while the new proposed method useddifferent long-term multipliers for the bridges A and B inorder to consider different creep and shrinkage rates Asa result the predictions at erection by the proposed methodwere smaller for bridge A and larger for bridge B than thoseby the basic PCI multiplier method [18] as shown inFigure 5
In terms of the long-term behavior after erection thecamber predicted by KR C-08090 [1] was generally thelargest among all prediction methods KR C-08090 [1] doesnot take into account prestress loss so it overestimates thecamber by prestress force -e predictions by the proposedmethod were larger than the predictions by numericalanalysis until about 200 days after superimposed dead loadwas applied and thereafter they were smaller than thepredictions by numerical analysis
When comparing the camber at final the predictionswere large in the order of KR C-08090 [1] numericalanalysis proposed method improved PCI multipliers [20]and basic PCI multipliers [18] for both bridges A and BNumerical analysis seems to estimate the effect of creep and
shrinkage on long-term deformation weaker than othermethods In comparison with numerical analysis for de-formation at the final difference rates of the proposedmethod basic PCI multipliers [18] improved PCI multi-pliers [20] and KR C-08090 [1] were 101 259 116and 343 for bridge A respectively and 146 331143 and 350 for bridge B respectively It is interestingto note that the proposed formula and the improved PCImultiplier method [20] show very similar prediction resultsof ultimate deformation at final
Figure 6 shows the long-term behavior predicted by theproposed multipliers for each load type In early agesa relatively large amount of camber was observed due to theprestress but as time went by the rate of increase of camberby prestress decreased sharply because the amount of creepand drying shrinkage converged and the PS steel relaxationincreased -e amount of deflection due to self-weight wassmaller than the camber due to the prestress but the ten-dency of deflection over time was very similar to that ofcamber On the contrary after the girder erection a con-siderable amount of immediate deflection and long-termdeflection due to dead loads such as topping and commonduct partially offset the camber
000000e + 000270033e + 000540066e + 000810100e + 000108013e + 001135017e + 001162020e + 001189023e + 001216027e + 001243030e + 001270033e + 001297037e + 001
MIDASCivilpostndashprocessorDisplacementYZ-direction
(a)
000000e + 000175416e + 000350832e + 000526248e + 000701664e + 001877080e + 001105250e + 001122791e + 001140333e + 001157874e + 001175416e + 001192958e + 001
MIDASCivilpostprocessorDisplacementYZ-direction
(b)
Figure 4 Analysis result of final deformation of bridges (a) A and (b) B
8 Advances in Civil Engineering
Tabl
e8
Predictio
nsby
variou
smetho
dsforbridge
A(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus2
230
176
minus3929
236
minus5265
237
minus5291
241
minus5364
245
minus5453
254minus5
665
Prestress
4610
171
7887
220
10130
221
10171
223
10284
226
10420
233
10734
Topp
ing
minus800
148
minus1180
178
minus1427
192
minus1533
206minus1
648
Superimpo
sed
dead
load
minus250
266
minus664
300minus7
50
Total
2380
3957
4066
3700
3243
2771
2671
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus2
230
185
minus4126
minus4126
minus4126
240minus5
352
Prestress
4610
180
8298
8298
8298
220
10142
Topp
ing
minus800
minus800
230minus1
840
Superimpo
sed
dead
load
minus250
300minus7
50
Total
2380
4173
3373
3123
2200
Improved
PCI
BDM
Self-weigh
tminus2
230
196
minus4371
minus4371
minus4371
288minus6
422
Prestress
4610
196
9036
9036
9036
288
13277
Prestresslossminus6
92
100
minus692
minus692
minus692
232minus1
604
Topp
ing
minus800
minus800
250minus2
000
Superimpo
sed
dead
load
minus250
250minus6
25
Total
2380
3973
3173
2923
2625
KRC-08090
Self-weigh
tminus2
230
150
minus3345
227
minus5062
230
minus5129
245
minus5464
265
minus5910
300minus6
690
Prestress
4610
150
6915
227
10465
230
10603
245
11295
265
12217
300
13830
Topp
ing
minus800
150
minus1200
215
minus1720
250
minus2000
300minus2
400
Superimpo
sed
dead
load
minus250
235
minus588
300minus7
50
Total
2380
3570
4603
4274
3861
3720
3990
Num
erical
analysis
Total
2348
3237
3446
3240
2988
2894
2970
Advances in Civil Engineering 9
Tabl
e9
Predictio
nsby
variou
smetho
dsforbridge
B(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus1
650
226
minus3725
227
minus3744
229
minus3771
236
minus3886
242
minus3994
250minus4
120
Prestress
3530
212
7477
213
7508
214
7553
219
7740
224
7909
230
8102
Topp
ing
minus750
142
minus1065
183
minus1370
196
minus1470
206minus1
545
Superimpo
sed
dead
load
minus265
278
minus736
300minus7
95
Total
1880
3752
3014
2717
2218
1710
1642
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus1
650
185
minus3053
minus3053
minus3053
240minus3
960
Prestress
3530
180
6354
6354
6354
220
7766
Topp
ing
minus750
minus750
230minus1
725
Superimpo
sed
dead
load
minus265
300minus7
95
Total
1880
3302
2552
2287
1286
Improved
PCI
BDM
Self-weigh
tminus1
650
196
minus3234
minus3234
minus3234
288minus4
752
Prestress
3530
196
6919
6919
6919
288
10166
Prestresslossminus5
30
100
minus530
minus530
minus530
232minus1
228
Topp
ing
minus750
minus750
250minus1
875
Superimpo
sed
dead
load
minus265
250minus6
63
Total
1880
3155
2405
2140
1648
KRC-08090
Self-weigh
tminus1
650
210
minus3465
211
minus3482
220
minus3630
240
minus3960
280
minus4620
300minus4
950
Prestress
3530
210
7413
211
7448
220
7766
240
8472
280
9884
300
10590
Topp
ing
minus750
150
minus1125
220
minus1650
275
minus2063
300minus2
250
Superimpo
sed
dead
load
minus265
265
minus702
300minus7
95
Total
1880
3948
3217
3011
2597
2499
2595
Num
erical
analysis
Total
1792
3926
2866
2536
2138
1954
1923
10 Advances in Civil Engineering
Consequently the proposed multipliers method pro-vided not only the closest prediction values but also themost similar long-term behavior trend to the numericalanalysis
6 Conclusions
Since the current PCI Bridge Design Manual [18] providesthe long-term deformation multipliers only at erection andfinal it cannot consider various construction processesFurthermore the multipliers for the composite cross sectionare also required to be modified to reflect the characteristicsof the cross section used in modern PSC bridges -ereforein this study newmodified PCImultipliers were proposed toovercome these problems -e conclusions drawn from thisstudy are as follows
(1) -e new modified PCI multipliers were proposed byusing the rate of creep and shrinkage over timeUnlike the existing PCI Bridge Design Manual [18]method it is possible to reflect the actual girdererection time and predict the long-term deformationfor any construction schedule Moreover throughthe new method camber and deflection of PSCbridges can be predicted at any time including designstage construction stage and use stage
(2) -e ratio of noncomposite to composite moments ofinertia IoIc was 051ndash056 as a result of analyzingrepresentative cross sections used in practice byspan while the PCI Bridge Design Manual [18]suggests 065 of IoIc-erefore it is suggested to usethe average value of 053 for IoIc in order to predictthe long-term behavior of composite members
ndash80
ndash60
ndash40
ndash20
0
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
PS forceSelf-weight
ToppingAdditional DL
(a)
ToppingPS forceSelf-weight Additional DL
0
ndash80
ndash60
ndash40
ndash20
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 6 Predictions by the proposed multipliers for each load type (a) Bridge A (b) Bridge B
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
(a)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 5 Comparison of various predictions for bridges (a) A and (b) B
Advances in Civil Engineering 11
(3) In order to verify the proposed multipliers for ac-tually constructed PSC bridges the predictions oflong-term camber and deflection by the proposedmultipliers were compared with those by the basicPCI multipliers [18] improved PCI multipliers [20]KR C-08090 [1] and numerical analysis As a resultKR C-08090 [1] predictions were significantly higherthan the other predictions and the basic PCI mul-tipliers [18] did not show a reasonable tendency inthe long-term behavior between the erection timeand the final Among all methods except the pro-posed method the improved PCI multipliers [20]showed the most similar predictions to the nu-merical analysis However this improved PCImultiplier method also has limitations in finding thelong-term deflection or camber of the bridge at anytime and there are several variables such as the creepcoefficient that must be known precisely in order touse the multipliers which is inconvenient for de-signers to use However the predictions through thenewly proposed multipliers showed a reasonablelong-term behavior trend and the amount of thefinal camber was also the most similar to the nu-merical analysis result Above all the proposedmethod can make it possible for the designer topredict the long-term behavior of the bridge veryeasily according to any construction schedule
Data Availability
-e data used to support the findings of this study areavailable from the corresponding author upon request
Conflicts of Interest
-e authors declare that they have no conflicts of interest
Acknowledgments
-is research was supported by a grant (17RTRP-B067919-05) from Railroad Technology Research Program funded byMinistry of Land Infrastructure and Transport of Koreangovernment
References
[1] Korea Rail Network Authority Railway Design Guidelines andHandbooks Bridge Concrete Track Ends Usability Review (KRC-08090) in Korean Korea Rail Network Authority DaejeonRepublic of Korea 2014
[2] ACI Committee 318 Building Code Requirements for Struc-tural Concrete (ACI 318-14) and Commentary AmericanConcrete Institute Farmington Hills MI USA 2014
[3] ACI Committe 209 Prediction of Creep Shrinkage andTemperature Effects in Concrete Structure American ConcreteInstitute Farmington Hill MI USA 1992
[4] AASHTO (American Association of State Highway andTransportation Officials) AASHTO LRFD Bridge DesignSpecifications AASHTO Washington DC USA 2007
[5] CEBFIP Model Code Comit Euro-International du BetonTelford Ltd London UK 1990
[6] H-G Kwak and Y-J Seo ldquoLong-term behavior of compositegirder bridgesrdquo Computers and Structures vol 74 no 5pp 583ndash599 2000
[7] H Yang ldquoUncertainty and updating of long-term predictionof prestress forces in PSC box girder bridgesrdquo Computers andStructures vol 83 no 25ndash26 pp 2137ndash2149 2005
[8] S Biswal and A Ramaswamy ldquoUncertainty based modelaveraging for prediction of long-time prestress losses inconcrete structuresrdquo Construction and Building Materialsvol 153 pp 469ndash480 2017
[9] W He and Z Zhang ldquoModeling creep fracture in rock byusing kelvin discretized virtual internal bondrdquo Advances inCivil Engineering vol 2018 Article ID 8042965 8 pages 2018
[10] Y-S Park Y-H Lee and Y Lee ldquoDescription of concretecreep under time-varying stress using parallel creep curverdquoAdvances in Materials Science and Engineering vol 2016Article ID 9370514 13 pages 2016
[11] Z Pan and S Meng ldquo-ree-level experimental approach forcreep and shrinkage of high-strength high-performanceconcreterdquo Engineering Structures vol 120 pp 23ndash36 2016
[12] H-G Kwak and Y-J Seo ldquoNumerical analysis of time-dependent behavior of pre-cast pre-stressed concrete girderbridgesrdquo Construction and Building Materials vol 16 no 1pp 49ndash63 2002
[13] I N Robertson ldquoPrediction of vertical deflections for a long-span prestressed concrete bridge structurerdquo EngineeringStructures vol 27 no 12 pp 1820ndash1827 2005
[14] T Lou S M R Lopes and A V Lopes ldquoA finite elementmodel to simulate long-term behavior of prestressed concretegirdersrdquo Finite Elements in Analysis and Design vol 81pp 48ndash56 2014
[15] P Liu Q Xing DWang andM Oeser ldquoApplication of linearviscoelastic properties in semianalytical finite element methodwith recursive time integration to analyze asphalt pavementstructurerdquo Advances in Civil Engineering vol 2018 Article ID9045820 15 pages 2018
[16] A Sagara and I Pane ldquoA study on effects of creep andshrinkage in high strength concrete bridgesrdquo Procedia En-gineering vol 125 pp 1087ndash1093 2015
[17] H Sousa J Bento and J Figueiras ldquoConstruction assessmentand long-term prediction of prestressed concrete bridgesbased on monitoring datardquo Engineering Structures vol 52pp 26ndash37 2013
[18] PCI Bridge Design Manual Second Release PrecastPrestressed Concrete Institute Chicago IL USA 3rd edi-tion 2014
[19] L D Martin ldquoA rational method for estimating camber anddeflection of precast prestressed membersrdquo PCI Journalvol 22 no 1 pp 100ndash108 1977
[20] PCI Bridge Design Manual PrecastPrestressed ConcreteInstitute Chicago IL USA 2nd edition 2003
[21] M K Tadros A Ghali and A W Meyer ldquoPrestressed lossand deflection of precast concrete membersrdquo PCI Journalvol 30 no 1 pp 114ndash141 1985
[22] Y Zhang ldquoOrthogonal test analysis on influencing factors ofprestressed concrete small box beam camberrdquo Applied Me-chanics and Materials vol 405-408 pp 1527ndash1530 2013
[23] Y Jianjun W Xun and H Xianzheng ldquoEffects of live load onthe deflection of long-span PC continuous rigid-framehighway bridge based on midasrdquo in Proceedings of 20147th International Conference on Intelligent ComputationTechnology and Automation pp 944ndash946 Changsha China2014
12 Advances in Civil Engineering
[24] T Grigorjeva A Juozapaitis and Z Kamaitis ldquoStatic analysisand simplified design of suspension bridges having variousrigidity of cablesrdquo Journal of Civil Engineering and Man-agement vol 16 no 3 pp 363ndash371 2011
[25] ACI Committee 435 Control of Deflection in ConcreteStructures ACI 435R-95 ACI Farmington Hills MI USA2003
[26] F B Angomas ldquoBehavior of prestressed concrete bridgegirdersrdquo All Graduate -eses and Dissertations Utah StateUniversity Logan UT USA 2009
[27] E H Gheitanbaf ldquoImproving the prediction of time-dependent effects on prestressed concrete bridgesrdquo Gradu-ate-eses and Dissertations Iowa State University Ames IAUSA 2015
[28] M K Tadros F Fawzy and K Hanna ldquoPrecast prestressedgirder camber variabilityrdquo PCI Journal vol 56 no 1pp 135ndash154 2011
Advances in Civil Engineering 13
International Journal of
AerospaceEngineeringHindawiwwwhindawicom Volume 2018
RoboticsJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Active and Passive Electronic Components
VLSI Design
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Shock and Vibration
Hindawiwwwhindawicom Volume 2018
Civil EngineeringAdvances in
Acoustics and VibrationAdvances in
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Electrical and Computer Engineering
Journal of
Advances inOptoElectronics
Hindawiwwwhindawicom
Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Control Scienceand Engineering
Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Journal ofEngineeringVolume 2018
SensorsJournal of
Hindawiwwwhindawicom Volume 2018
International Journal of
RotatingMachinery
Hindawiwwwhindawicom Volume 2018
Modelling ampSimulationin EngineeringHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Chemical EngineeringInternational Journal of Antennas and
Propagation
International Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Navigation and Observation
International Journal of
Hindawi
wwwhindawicom Volume 2018
Advances in
Multimedia
Submit your manuscripts atwwwhindawicom
materials are the same as concrete and PS steel actually usedfor bridges A and B -e structural members of the bridgeswere modeled based on structural calculations and designdrawings of bridges A and B According to the designdrawing the strands were arranged by setting the actualcoordinates of the strand on the girder nodes using the 3-Dinput type from tendon profile option of MIDAS Civil -eCEB-FIP MC90 model [5] was used to calculate creep anddrying shrinkage of concrete For the relaxation of thetendon the Magura 45 model was used to consider thetime-dependent loss of the prestress Based on the con-struction history of the bridges A and B in Table 6construction sequence analysis was carried out After thecast of deck composite behavior of the girder and the deckwas simulated through the node connection using the rigidtype of elastic link In the same way common duct which isthe additional superimposed dead load was also simulatedfor composite behavior after its installation At the finalstage the deformation patterns of bridges A and B areshown in Figure 4 As a result the bridges A and B in themidspan showed 324mm and 393mm of camber at girdererection and 297mm and 192mm of camber at finalrespectively
53 Comparison of Predictions of Long-Term DeformationTables 8 and 9 and Figure 5 show the predictions of the long-term deformation of bridges A and B by using the proposedmultipliers the basic PCI multipliers [18] the improved PCImultipliers [20] KR C-08090 [1] and numerical analysisFor the improved PCI multipliers [20] the average values inTable 2 were used because the actual creep coefficient and theamount of the prestress loss can hardly be known
Although the values of predictions by the proposedmultipliers and KR C-08090 [1] were somewhat different
from the prediction by numerical analysis their predictiontrends of the camber over time were generally similar be-cause they provided available multipliers at any time In thecase of the basic PCI multipliers [18] however the long-term behavior after the erection was quite different fromother prediction methods because there are no applicablelong-term factors for the period between the erection andthe final
-e girder of bridge A was erected on the 30th day aftercasting while the girder of bridge B was erected on the 150thday relatively long time after casting -e basic PCI
1025 90 420 90 1025
2650
120
100
110
2670 30
00
150
2250
600
220
95 600150
2190
60600
3000
600
1040 110 695110695
(a)
400 200 4001000
2600
150
120
1950
180
200
2600
200 350350
900
(b)
Figure 3 Cross-sectional details of bridges (a) A and (b) B
Table 6 Construction history of bridges A and B
EventTime from casting (days)Bridge A Bridge B
(1) Release 1 1(2) Erection (t(e)) 30 150(3) Topping (t(c)) 240 157(4) 1st random time (t1) 270 180(5) Superimposed dead load (t(s)) 390 360(6) 2nd random time (t2) 700 1000
(7) Final 5 years ormore
5 years ormore
Table 7 Elastic camber and deflection of bridges A and B
LoadCamber (+) or deflection (minus)Bridge A Bridge B
Self-weight minus223 minus165Prestressing force +461 +353Topping minus80 minus75Superimposed dead load minus25 minus265
Advances in Civil Engineering 7
multiplier method [18] calculated the long-term camberusing the same multiplier for both bridges regardless of thedifferent erection time while the new proposed method useddifferent long-term multipliers for the bridges A and B inorder to consider different creep and shrinkage rates Asa result the predictions at erection by the proposed methodwere smaller for bridge A and larger for bridge B than thoseby the basic PCI multiplier method [18] as shown inFigure 5
In terms of the long-term behavior after erection thecamber predicted by KR C-08090 [1] was generally thelargest among all prediction methods KR C-08090 [1] doesnot take into account prestress loss so it overestimates thecamber by prestress force -e predictions by the proposedmethod were larger than the predictions by numericalanalysis until about 200 days after superimposed dead loadwas applied and thereafter they were smaller than thepredictions by numerical analysis
When comparing the camber at final the predictionswere large in the order of KR C-08090 [1] numericalanalysis proposed method improved PCI multipliers [20]and basic PCI multipliers [18] for both bridges A and BNumerical analysis seems to estimate the effect of creep and
shrinkage on long-term deformation weaker than othermethods In comparison with numerical analysis for de-formation at the final difference rates of the proposedmethod basic PCI multipliers [18] improved PCI multi-pliers [20] and KR C-08090 [1] were 101 259 116and 343 for bridge A respectively and 146 331143 and 350 for bridge B respectively It is interestingto note that the proposed formula and the improved PCImultiplier method [20] show very similar prediction resultsof ultimate deformation at final
Figure 6 shows the long-term behavior predicted by theproposed multipliers for each load type In early agesa relatively large amount of camber was observed due to theprestress but as time went by the rate of increase of camberby prestress decreased sharply because the amount of creepand drying shrinkage converged and the PS steel relaxationincreased -e amount of deflection due to self-weight wassmaller than the camber due to the prestress but the ten-dency of deflection over time was very similar to that ofcamber On the contrary after the girder erection a con-siderable amount of immediate deflection and long-termdeflection due to dead loads such as topping and commonduct partially offset the camber
000000e + 000270033e + 000540066e + 000810100e + 000108013e + 001135017e + 001162020e + 001189023e + 001216027e + 001243030e + 001270033e + 001297037e + 001
MIDASCivilpostndashprocessorDisplacementYZ-direction
(a)
000000e + 000175416e + 000350832e + 000526248e + 000701664e + 001877080e + 001105250e + 001122791e + 001140333e + 001157874e + 001175416e + 001192958e + 001
MIDASCivilpostprocessorDisplacementYZ-direction
(b)
Figure 4 Analysis result of final deformation of bridges (a) A and (b) B
8 Advances in Civil Engineering
Tabl
e8
Predictio
nsby
variou
smetho
dsforbridge
A(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus2
230
176
minus3929
236
minus5265
237
minus5291
241
minus5364
245
minus5453
254minus5
665
Prestress
4610
171
7887
220
10130
221
10171
223
10284
226
10420
233
10734
Topp
ing
minus800
148
minus1180
178
minus1427
192
minus1533
206minus1
648
Superimpo
sed
dead
load
minus250
266
minus664
300minus7
50
Total
2380
3957
4066
3700
3243
2771
2671
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus2
230
185
minus4126
minus4126
minus4126
240minus5
352
Prestress
4610
180
8298
8298
8298
220
10142
Topp
ing
minus800
minus800
230minus1
840
Superimpo
sed
dead
load
minus250
300minus7
50
Total
2380
4173
3373
3123
2200
Improved
PCI
BDM
Self-weigh
tminus2
230
196
minus4371
minus4371
minus4371
288minus6
422
Prestress
4610
196
9036
9036
9036
288
13277
Prestresslossminus6
92
100
minus692
minus692
minus692
232minus1
604
Topp
ing
minus800
minus800
250minus2
000
Superimpo
sed
dead
load
minus250
250minus6
25
Total
2380
3973
3173
2923
2625
KRC-08090
Self-weigh
tminus2
230
150
minus3345
227
minus5062
230
minus5129
245
minus5464
265
minus5910
300minus6
690
Prestress
4610
150
6915
227
10465
230
10603
245
11295
265
12217
300
13830
Topp
ing
minus800
150
minus1200
215
minus1720
250
minus2000
300minus2
400
Superimpo
sed
dead
load
minus250
235
minus588
300minus7
50
Total
2380
3570
4603
4274
3861
3720
3990
Num
erical
analysis
Total
2348
3237
3446
3240
2988
2894
2970
Advances in Civil Engineering 9
Tabl
e9
Predictio
nsby
variou
smetho
dsforbridge
B(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus1
650
226
minus3725
227
minus3744
229
minus3771
236
minus3886
242
minus3994
250minus4
120
Prestress
3530
212
7477
213
7508
214
7553
219
7740
224
7909
230
8102
Topp
ing
minus750
142
minus1065
183
minus1370
196
minus1470
206minus1
545
Superimpo
sed
dead
load
minus265
278
minus736
300minus7
95
Total
1880
3752
3014
2717
2218
1710
1642
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus1
650
185
minus3053
minus3053
minus3053
240minus3
960
Prestress
3530
180
6354
6354
6354
220
7766
Topp
ing
minus750
minus750
230minus1
725
Superimpo
sed
dead
load
minus265
300minus7
95
Total
1880
3302
2552
2287
1286
Improved
PCI
BDM
Self-weigh
tminus1
650
196
minus3234
minus3234
minus3234
288minus4
752
Prestress
3530
196
6919
6919
6919
288
10166
Prestresslossminus5
30
100
minus530
minus530
minus530
232minus1
228
Topp
ing
minus750
minus750
250minus1
875
Superimpo
sed
dead
load
minus265
250minus6
63
Total
1880
3155
2405
2140
1648
KRC-08090
Self-weigh
tminus1
650
210
minus3465
211
minus3482
220
minus3630
240
minus3960
280
minus4620
300minus4
950
Prestress
3530
210
7413
211
7448
220
7766
240
8472
280
9884
300
10590
Topp
ing
minus750
150
minus1125
220
minus1650
275
minus2063
300minus2
250
Superimpo
sed
dead
load
minus265
265
minus702
300minus7
95
Total
1880
3948
3217
3011
2597
2499
2595
Num
erical
analysis
Total
1792
3926
2866
2536
2138
1954
1923
10 Advances in Civil Engineering
Consequently the proposed multipliers method pro-vided not only the closest prediction values but also themost similar long-term behavior trend to the numericalanalysis
6 Conclusions
Since the current PCI Bridge Design Manual [18] providesthe long-term deformation multipliers only at erection andfinal it cannot consider various construction processesFurthermore the multipliers for the composite cross sectionare also required to be modified to reflect the characteristicsof the cross section used in modern PSC bridges -ereforein this study newmodified PCImultipliers were proposed toovercome these problems -e conclusions drawn from thisstudy are as follows
(1) -e new modified PCI multipliers were proposed byusing the rate of creep and shrinkage over timeUnlike the existing PCI Bridge Design Manual [18]method it is possible to reflect the actual girdererection time and predict the long-term deformationfor any construction schedule Moreover throughthe new method camber and deflection of PSCbridges can be predicted at any time including designstage construction stage and use stage
(2) -e ratio of noncomposite to composite moments ofinertia IoIc was 051ndash056 as a result of analyzingrepresentative cross sections used in practice byspan while the PCI Bridge Design Manual [18]suggests 065 of IoIc-erefore it is suggested to usethe average value of 053 for IoIc in order to predictthe long-term behavior of composite members
ndash80
ndash60
ndash40
ndash20
0
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
PS forceSelf-weight
ToppingAdditional DL
(a)
ToppingPS forceSelf-weight Additional DL
0
ndash80
ndash60
ndash40
ndash20
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 6 Predictions by the proposed multipliers for each load type (a) Bridge A (b) Bridge B
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
(a)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 5 Comparison of various predictions for bridges (a) A and (b) B
Advances in Civil Engineering 11
(3) In order to verify the proposed multipliers for ac-tually constructed PSC bridges the predictions oflong-term camber and deflection by the proposedmultipliers were compared with those by the basicPCI multipliers [18] improved PCI multipliers [20]KR C-08090 [1] and numerical analysis As a resultKR C-08090 [1] predictions were significantly higherthan the other predictions and the basic PCI mul-tipliers [18] did not show a reasonable tendency inthe long-term behavior between the erection timeand the final Among all methods except the pro-posed method the improved PCI multipliers [20]showed the most similar predictions to the nu-merical analysis However this improved PCImultiplier method also has limitations in finding thelong-term deflection or camber of the bridge at anytime and there are several variables such as the creepcoefficient that must be known precisely in order touse the multipliers which is inconvenient for de-signers to use However the predictions through thenewly proposed multipliers showed a reasonablelong-term behavior trend and the amount of thefinal camber was also the most similar to the nu-merical analysis result Above all the proposedmethod can make it possible for the designer topredict the long-term behavior of the bridge veryeasily according to any construction schedule
Data Availability
-e data used to support the findings of this study areavailable from the corresponding author upon request
Conflicts of Interest
-e authors declare that they have no conflicts of interest
Acknowledgments
-is research was supported by a grant (17RTRP-B067919-05) from Railroad Technology Research Program funded byMinistry of Land Infrastructure and Transport of Koreangovernment
References
[1] Korea Rail Network Authority Railway Design Guidelines andHandbooks Bridge Concrete Track Ends Usability Review (KRC-08090) in Korean Korea Rail Network Authority DaejeonRepublic of Korea 2014
[2] ACI Committee 318 Building Code Requirements for Struc-tural Concrete (ACI 318-14) and Commentary AmericanConcrete Institute Farmington Hills MI USA 2014
[3] ACI Committe 209 Prediction of Creep Shrinkage andTemperature Effects in Concrete Structure American ConcreteInstitute Farmington Hill MI USA 1992
[4] AASHTO (American Association of State Highway andTransportation Officials) AASHTO LRFD Bridge DesignSpecifications AASHTO Washington DC USA 2007
[5] CEBFIP Model Code Comit Euro-International du BetonTelford Ltd London UK 1990
[6] H-G Kwak and Y-J Seo ldquoLong-term behavior of compositegirder bridgesrdquo Computers and Structures vol 74 no 5pp 583ndash599 2000
[7] H Yang ldquoUncertainty and updating of long-term predictionof prestress forces in PSC box girder bridgesrdquo Computers andStructures vol 83 no 25ndash26 pp 2137ndash2149 2005
[8] S Biswal and A Ramaswamy ldquoUncertainty based modelaveraging for prediction of long-time prestress losses inconcrete structuresrdquo Construction and Building Materialsvol 153 pp 469ndash480 2017
[9] W He and Z Zhang ldquoModeling creep fracture in rock byusing kelvin discretized virtual internal bondrdquo Advances inCivil Engineering vol 2018 Article ID 8042965 8 pages 2018
[10] Y-S Park Y-H Lee and Y Lee ldquoDescription of concretecreep under time-varying stress using parallel creep curverdquoAdvances in Materials Science and Engineering vol 2016Article ID 9370514 13 pages 2016
[11] Z Pan and S Meng ldquo-ree-level experimental approach forcreep and shrinkage of high-strength high-performanceconcreterdquo Engineering Structures vol 120 pp 23ndash36 2016
[12] H-G Kwak and Y-J Seo ldquoNumerical analysis of time-dependent behavior of pre-cast pre-stressed concrete girderbridgesrdquo Construction and Building Materials vol 16 no 1pp 49ndash63 2002
[13] I N Robertson ldquoPrediction of vertical deflections for a long-span prestressed concrete bridge structurerdquo EngineeringStructures vol 27 no 12 pp 1820ndash1827 2005
[14] T Lou S M R Lopes and A V Lopes ldquoA finite elementmodel to simulate long-term behavior of prestressed concretegirdersrdquo Finite Elements in Analysis and Design vol 81pp 48ndash56 2014
[15] P Liu Q Xing DWang andM Oeser ldquoApplication of linearviscoelastic properties in semianalytical finite element methodwith recursive time integration to analyze asphalt pavementstructurerdquo Advances in Civil Engineering vol 2018 Article ID9045820 15 pages 2018
[16] A Sagara and I Pane ldquoA study on effects of creep andshrinkage in high strength concrete bridgesrdquo Procedia En-gineering vol 125 pp 1087ndash1093 2015
[17] H Sousa J Bento and J Figueiras ldquoConstruction assessmentand long-term prediction of prestressed concrete bridgesbased on monitoring datardquo Engineering Structures vol 52pp 26ndash37 2013
[18] PCI Bridge Design Manual Second Release PrecastPrestressed Concrete Institute Chicago IL USA 3rd edi-tion 2014
[19] L D Martin ldquoA rational method for estimating camber anddeflection of precast prestressed membersrdquo PCI Journalvol 22 no 1 pp 100ndash108 1977
[20] PCI Bridge Design Manual PrecastPrestressed ConcreteInstitute Chicago IL USA 2nd edition 2003
[21] M K Tadros A Ghali and A W Meyer ldquoPrestressed lossand deflection of precast concrete membersrdquo PCI Journalvol 30 no 1 pp 114ndash141 1985
[22] Y Zhang ldquoOrthogonal test analysis on influencing factors ofprestressed concrete small box beam camberrdquo Applied Me-chanics and Materials vol 405-408 pp 1527ndash1530 2013
[23] Y Jianjun W Xun and H Xianzheng ldquoEffects of live load onthe deflection of long-span PC continuous rigid-framehighway bridge based on midasrdquo in Proceedings of 20147th International Conference on Intelligent ComputationTechnology and Automation pp 944ndash946 Changsha China2014
12 Advances in Civil Engineering
[24] T Grigorjeva A Juozapaitis and Z Kamaitis ldquoStatic analysisand simplified design of suspension bridges having variousrigidity of cablesrdquo Journal of Civil Engineering and Man-agement vol 16 no 3 pp 363ndash371 2011
[25] ACI Committee 435 Control of Deflection in ConcreteStructures ACI 435R-95 ACI Farmington Hills MI USA2003
[26] F B Angomas ldquoBehavior of prestressed concrete bridgegirdersrdquo All Graduate -eses and Dissertations Utah StateUniversity Logan UT USA 2009
[27] E H Gheitanbaf ldquoImproving the prediction of time-dependent effects on prestressed concrete bridgesrdquo Gradu-ate-eses and Dissertations Iowa State University Ames IAUSA 2015
[28] M K Tadros F Fawzy and K Hanna ldquoPrecast prestressedgirder camber variabilityrdquo PCI Journal vol 56 no 1pp 135ndash154 2011
Advances in Civil Engineering 13
International Journal of
AerospaceEngineeringHindawiwwwhindawicom Volume 2018
RoboticsJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Active and Passive Electronic Components
VLSI Design
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Shock and Vibration
Hindawiwwwhindawicom Volume 2018
Civil EngineeringAdvances in
Acoustics and VibrationAdvances in
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Electrical and Computer Engineering
Journal of
Advances inOptoElectronics
Hindawiwwwhindawicom
Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Control Scienceand Engineering
Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Journal ofEngineeringVolume 2018
SensorsJournal of
Hindawiwwwhindawicom Volume 2018
International Journal of
RotatingMachinery
Hindawiwwwhindawicom Volume 2018
Modelling ampSimulationin EngineeringHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Chemical EngineeringInternational Journal of Antennas and
Propagation
International Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Navigation and Observation
International Journal of
Hindawi
wwwhindawicom Volume 2018
Advances in
Multimedia
Submit your manuscripts atwwwhindawicom
multiplier method [18] calculated the long-term camberusing the same multiplier for both bridges regardless of thedifferent erection time while the new proposed method useddifferent long-term multipliers for the bridges A and B inorder to consider different creep and shrinkage rates Asa result the predictions at erection by the proposed methodwere smaller for bridge A and larger for bridge B than thoseby the basic PCI multiplier method [18] as shown inFigure 5
In terms of the long-term behavior after erection thecamber predicted by KR C-08090 [1] was generally thelargest among all prediction methods KR C-08090 [1] doesnot take into account prestress loss so it overestimates thecamber by prestress force -e predictions by the proposedmethod were larger than the predictions by numericalanalysis until about 200 days after superimposed dead loadwas applied and thereafter they were smaller than thepredictions by numerical analysis
When comparing the camber at final the predictionswere large in the order of KR C-08090 [1] numericalanalysis proposed method improved PCI multipliers [20]and basic PCI multipliers [18] for both bridges A and BNumerical analysis seems to estimate the effect of creep and
shrinkage on long-term deformation weaker than othermethods In comparison with numerical analysis for de-formation at the final difference rates of the proposedmethod basic PCI multipliers [18] improved PCI multi-pliers [20] and KR C-08090 [1] were 101 259 116and 343 for bridge A respectively and 146 331143 and 350 for bridge B respectively It is interestingto note that the proposed formula and the improved PCImultiplier method [20] show very similar prediction resultsof ultimate deformation at final
Figure 6 shows the long-term behavior predicted by theproposed multipliers for each load type In early agesa relatively large amount of camber was observed due to theprestress but as time went by the rate of increase of camberby prestress decreased sharply because the amount of creepand drying shrinkage converged and the PS steel relaxationincreased -e amount of deflection due to self-weight wassmaller than the camber due to the prestress but the ten-dency of deflection over time was very similar to that ofcamber On the contrary after the girder erection a con-siderable amount of immediate deflection and long-termdeflection due to dead loads such as topping and commonduct partially offset the camber
000000e + 000270033e + 000540066e + 000810100e + 000108013e + 001135017e + 001162020e + 001189023e + 001216027e + 001243030e + 001270033e + 001297037e + 001
MIDASCivilpostndashprocessorDisplacementYZ-direction
(a)
000000e + 000175416e + 000350832e + 000526248e + 000701664e + 001877080e + 001105250e + 001122791e + 001140333e + 001157874e + 001175416e + 001192958e + 001
MIDASCivilpostprocessorDisplacementYZ-direction
(b)
Figure 4 Analysis result of final deformation of bridges (a) A and (b) B
8 Advances in Civil Engineering
Tabl
e8
Predictio
nsby
variou
smetho
dsforbridge
A(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus2
230
176
minus3929
236
minus5265
237
minus5291
241
minus5364
245
minus5453
254minus5
665
Prestress
4610
171
7887
220
10130
221
10171
223
10284
226
10420
233
10734
Topp
ing
minus800
148
minus1180
178
minus1427
192
minus1533
206minus1
648
Superimpo
sed
dead
load
minus250
266
minus664
300minus7
50
Total
2380
3957
4066
3700
3243
2771
2671
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus2
230
185
minus4126
minus4126
minus4126
240minus5
352
Prestress
4610
180
8298
8298
8298
220
10142
Topp
ing
minus800
minus800
230minus1
840
Superimpo
sed
dead
load
minus250
300minus7
50
Total
2380
4173
3373
3123
2200
Improved
PCI
BDM
Self-weigh
tminus2
230
196
minus4371
minus4371
minus4371
288minus6
422
Prestress
4610
196
9036
9036
9036
288
13277
Prestresslossminus6
92
100
minus692
minus692
minus692
232minus1
604
Topp
ing
minus800
minus800
250minus2
000
Superimpo
sed
dead
load
minus250
250minus6
25
Total
2380
3973
3173
2923
2625
KRC-08090
Self-weigh
tminus2
230
150
minus3345
227
minus5062
230
minus5129
245
minus5464
265
minus5910
300minus6
690
Prestress
4610
150
6915
227
10465
230
10603
245
11295
265
12217
300
13830
Topp
ing
minus800
150
minus1200
215
minus1720
250
minus2000
300minus2
400
Superimpo
sed
dead
load
minus250
235
minus588
300minus7
50
Total
2380
3570
4603
4274
3861
3720
3990
Num
erical
analysis
Total
2348
3237
3446
3240
2988
2894
2970
Advances in Civil Engineering 9
Tabl
e9
Predictio
nsby
variou
smetho
dsforbridge
B(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus1
650
226
minus3725
227
minus3744
229
minus3771
236
minus3886
242
minus3994
250minus4
120
Prestress
3530
212
7477
213
7508
214
7553
219
7740
224
7909
230
8102
Topp
ing
minus750
142
minus1065
183
minus1370
196
minus1470
206minus1
545
Superimpo
sed
dead
load
minus265
278
minus736
300minus7
95
Total
1880
3752
3014
2717
2218
1710
1642
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus1
650
185
minus3053
minus3053
minus3053
240minus3
960
Prestress
3530
180
6354
6354
6354
220
7766
Topp
ing
minus750
minus750
230minus1
725
Superimpo
sed
dead
load
minus265
300minus7
95
Total
1880
3302
2552
2287
1286
Improved
PCI
BDM
Self-weigh
tminus1
650
196
minus3234
minus3234
minus3234
288minus4
752
Prestress
3530
196
6919
6919
6919
288
10166
Prestresslossminus5
30
100
minus530
minus530
minus530
232minus1
228
Topp
ing
minus750
minus750
250minus1
875
Superimpo
sed
dead
load
minus265
250minus6
63
Total
1880
3155
2405
2140
1648
KRC-08090
Self-weigh
tminus1
650
210
minus3465
211
minus3482
220
minus3630
240
minus3960
280
minus4620
300minus4
950
Prestress
3530
210
7413
211
7448
220
7766
240
8472
280
9884
300
10590
Topp
ing
minus750
150
minus1125
220
minus1650
275
minus2063
300minus2
250
Superimpo
sed
dead
load
minus265
265
minus702
300minus7
95
Total
1880
3948
3217
3011
2597
2499
2595
Num
erical
analysis
Total
1792
3926
2866
2536
2138
1954
1923
10 Advances in Civil Engineering
Consequently the proposed multipliers method pro-vided not only the closest prediction values but also themost similar long-term behavior trend to the numericalanalysis
6 Conclusions
Since the current PCI Bridge Design Manual [18] providesthe long-term deformation multipliers only at erection andfinal it cannot consider various construction processesFurthermore the multipliers for the composite cross sectionare also required to be modified to reflect the characteristicsof the cross section used in modern PSC bridges -ereforein this study newmodified PCImultipliers were proposed toovercome these problems -e conclusions drawn from thisstudy are as follows
(1) -e new modified PCI multipliers were proposed byusing the rate of creep and shrinkage over timeUnlike the existing PCI Bridge Design Manual [18]method it is possible to reflect the actual girdererection time and predict the long-term deformationfor any construction schedule Moreover throughthe new method camber and deflection of PSCbridges can be predicted at any time including designstage construction stage and use stage
(2) -e ratio of noncomposite to composite moments ofinertia IoIc was 051ndash056 as a result of analyzingrepresentative cross sections used in practice byspan while the PCI Bridge Design Manual [18]suggests 065 of IoIc-erefore it is suggested to usethe average value of 053 for IoIc in order to predictthe long-term behavior of composite members
ndash80
ndash60
ndash40
ndash20
0
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
PS forceSelf-weight
ToppingAdditional DL
(a)
ToppingPS forceSelf-weight Additional DL
0
ndash80
ndash60
ndash40
ndash20
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 6 Predictions by the proposed multipliers for each load type (a) Bridge A (b) Bridge B
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
(a)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 5 Comparison of various predictions for bridges (a) A and (b) B
Advances in Civil Engineering 11
(3) In order to verify the proposed multipliers for ac-tually constructed PSC bridges the predictions oflong-term camber and deflection by the proposedmultipliers were compared with those by the basicPCI multipliers [18] improved PCI multipliers [20]KR C-08090 [1] and numerical analysis As a resultKR C-08090 [1] predictions were significantly higherthan the other predictions and the basic PCI mul-tipliers [18] did not show a reasonable tendency inthe long-term behavior between the erection timeand the final Among all methods except the pro-posed method the improved PCI multipliers [20]showed the most similar predictions to the nu-merical analysis However this improved PCImultiplier method also has limitations in finding thelong-term deflection or camber of the bridge at anytime and there are several variables such as the creepcoefficient that must be known precisely in order touse the multipliers which is inconvenient for de-signers to use However the predictions through thenewly proposed multipliers showed a reasonablelong-term behavior trend and the amount of thefinal camber was also the most similar to the nu-merical analysis result Above all the proposedmethod can make it possible for the designer topredict the long-term behavior of the bridge veryeasily according to any construction schedule
Data Availability
-e data used to support the findings of this study areavailable from the corresponding author upon request
Conflicts of Interest
-e authors declare that they have no conflicts of interest
Acknowledgments
-is research was supported by a grant (17RTRP-B067919-05) from Railroad Technology Research Program funded byMinistry of Land Infrastructure and Transport of Koreangovernment
References
[1] Korea Rail Network Authority Railway Design Guidelines andHandbooks Bridge Concrete Track Ends Usability Review (KRC-08090) in Korean Korea Rail Network Authority DaejeonRepublic of Korea 2014
[2] ACI Committee 318 Building Code Requirements for Struc-tural Concrete (ACI 318-14) and Commentary AmericanConcrete Institute Farmington Hills MI USA 2014
[3] ACI Committe 209 Prediction of Creep Shrinkage andTemperature Effects in Concrete Structure American ConcreteInstitute Farmington Hill MI USA 1992
[4] AASHTO (American Association of State Highway andTransportation Officials) AASHTO LRFD Bridge DesignSpecifications AASHTO Washington DC USA 2007
[5] CEBFIP Model Code Comit Euro-International du BetonTelford Ltd London UK 1990
[6] H-G Kwak and Y-J Seo ldquoLong-term behavior of compositegirder bridgesrdquo Computers and Structures vol 74 no 5pp 583ndash599 2000
[7] H Yang ldquoUncertainty and updating of long-term predictionof prestress forces in PSC box girder bridgesrdquo Computers andStructures vol 83 no 25ndash26 pp 2137ndash2149 2005
[8] S Biswal and A Ramaswamy ldquoUncertainty based modelaveraging for prediction of long-time prestress losses inconcrete structuresrdquo Construction and Building Materialsvol 153 pp 469ndash480 2017
[9] W He and Z Zhang ldquoModeling creep fracture in rock byusing kelvin discretized virtual internal bondrdquo Advances inCivil Engineering vol 2018 Article ID 8042965 8 pages 2018
[10] Y-S Park Y-H Lee and Y Lee ldquoDescription of concretecreep under time-varying stress using parallel creep curverdquoAdvances in Materials Science and Engineering vol 2016Article ID 9370514 13 pages 2016
[11] Z Pan and S Meng ldquo-ree-level experimental approach forcreep and shrinkage of high-strength high-performanceconcreterdquo Engineering Structures vol 120 pp 23ndash36 2016
[12] H-G Kwak and Y-J Seo ldquoNumerical analysis of time-dependent behavior of pre-cast pre-stressed concrete girderbridgesrdquo Construction and Building Materials vol 16 no 1pp 49ndash63 2002
[13] I N Robertson ldquoPrediction of vertical deflections for a long-span prestressed concrete bridge structurerdquo EngineeringStructures vol 27 no 12 pp 1820ndash1827 2005
[14] T Lou S M R Lopes and A V Lopes ldquoA finite elementmodel to simulate long-term behavior of prestressed concretegirdersrdquo Finite Elements in Analysis and Design vol 81pp 48ndash56 2014
[15] P Liu Q Xing DWang andM Oeser ldquoApplication of linearviscoelastic properties in semianalytical finite element methodwith recursive time integration to analyze asphalt pavementstructurerdquo Advances in Civil Engineering vol 2018 Article ID9045820 15 pages 2018
[16] A Sagara and I Pane ldquoA study on effects of creep andshrinkage in high strength concrete bridgesrdquo Procedia En-gineering vol 125 pp 1087ndash1093 2015
[17] H Sousa J Bento and J Figueiras ldquoConstruction assessmentand long-term prediction of prestressed concrete bridgesbased on monitoring datardquo Engineering Structures vol 52pp 26ndash37 2013
[18] PCI Bridge Design Manual Second Release PrecastPrestressed Concrete Institute Chicago IL USA 3rd edi-tion 2014
[19] L D Martin ldquoA rational method for estimating camber anddeflection of precast prestressed membersrdquo PCI Journalvol 22 no 1 pp 100ndash108 1977
[20] PCI Bridge Design Manual PrecastPrestressed ConcreteInstitute Chicago IL USA 2nd edition 2003
[21] M K Tadros A Ghali and A W Meyer ldquoPrestressed lossand deflection of precast concrete membersrdquo PCI Journalvol 30 no 1 pp 114ndash141 1985
[22] Y Zhang ldquoOrthogonal test analysis on influencing factors ofprestressed concrete small box beam camberrdquo Applied Me-chanics and Materials vol 405-408 pp 1527ndash1530 2013
[23] Y Jianjun W Xun and H Xianzheng ldquoEffects of live load onthe deflection of long-span PC continuous rigid-framehighway bridge based on midasrdquo in Proceedings of 20147th International Conference on Intelligent ComputationTechnology and Automation pp 944ndash946 Changsha China2014
12 Advances in Civil Engineering
[24] T Grigorjeva A Juozapaitis and Z Kamaitis ldquoStatic analysisand simplified design of suspension bridges having variousrigidity of cablesrdquo Journal of Civil Engineering and Man-agement vol 16 no 3 pp 363ndash371 2011
[25] ACI Committee 435 Control of Deflection in ConcreteStructures ACI 435R-95 ACI Farmington Hills MI USA2003
[26] F B Angomas ldquoBehavior of prestressed concrete bridgegirdersrdquo All Graduate -eses and Dissertations Utah StateUniversity Logan UT USA 2009
[27] E H Gheitanbaf ldquoImproving the prediction of time-dependent effects on prestressed concrete bridgesrdquo Gradu-ate-eses and Dissertations Iowa State University Ames IAUSA 2015
[28] M K Tadros F Fawzy and K Hanna ldquoPrecast prestressedgirder camber variabilityrdquo PCI Journal vol 56 no 1pp 135ndash154 2011
Advances in Civil Engineering 13
International Journal of
AerospaceEngineeringHindawiwwwhindawicom Volume 2018
RoboticsJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Active and Passive Electronic Components
VLSI Design
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Shock and Vibration
Hindawiwwwhindawicom Volume 2018
Civil EngineeringAdvances in
Acoustics and VibrationAdvances in
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Electrical and Computer Engineering
Journal of
Advances inOptoElectronics
Hindawiwwwhindawicom
Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Control Scienceand Engineering
Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Journal ofEngineeringVolume 2018
SensorsJournal of
Hindawiwwwhindawicom Volume 2018
International Journal of
RotatingMachinery
Hindawiwwwhindawicom Volume 2018
Modelling ampSimulationin EngineeringHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Chemical EngineeringInternational Journal of Antennas and
Propagation
International Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Navigation and Observation
International Journal of
Hindawi
wwwhindawicom Volume 2018
Advances in
Multimedia
Submit your manuscripts atwwwhindawicom
Tabl
e8
Predictio
nsby
variou
smetho
dsforbridge
A(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus2
230
176
minus3929
236
minus5265
237
minus5291
241
minus5364
245
minus5453
254minus5
665
Prestress
4610
171
7887
220
10130
221
10171
223
10284
226
10420
233
10734
Topp
ing
minus800
148
minus1180
178
minus1427
192
minus1533
206minus1
648
Superimpo
sed
dead
load
minus250
266
minus664
300minus7
50
Total
2380
3957
4066
3700
3243
2771
2671
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus2
230
185
minus4126
minus4126
minus4126
240minus5
352
Prestress
4610
180
8298
8298
8298
220
10142
Topp
ing
minus800
minus800
230minus1
840
Superimpo
sed
dead
load
minus250
300minus7
50
Total
2380
4173
3373
3123
2200
Improved
PCI
BDM
Self-weigh
tminus2
230
196
minus4371
minus4371
minus4371
288minus6
422
Prestress
4610
196
9036
9036
9036
288
13277
Prestresslossminus6
92
100
minus692
minus692
minus692
232minus1
604
Topp
ing
minus800
minus800
250minus2
000
Superimpo
sed
dead
load
minus250
250minus6
25
Total
2380
3973
3173
2923
2625
KRC-08090
Self-weigh
tminus2
230
150
minus3345
227
minus5062
230
minus5129
245
minus5464
265
minus5910
300minus6
690
Prestress
4610
150
6915
227
10465
230
10603
245
11295
265
12217
300
13830
Topp
ing
minus800
150
minus1200
215
minus1720
250
minus2000
300minus2
400
Superimpo
sed
dead
load
minus250
235
minus588
300minus7
50
Total
2380
3570
4603
4274
3861
3720
3990
Num
erical
analysis
Total
2348
3237
3446
3240
2988
2894
2970
Advances in Civil Engineering 9
Tabl
e9
Predictio
nsby
variou
smetho
dsforbridge
B(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus1
650
226
minus3725
227
minus3744
229
minus3771
236
minus3886
242
minus3994
250minus4
120
Prestress
3530
212
7477
213
7508
214
7553
219
7740
224
7909
230
8102
Topp
ing
minus750
142
minus1065
183
minus1370
196
minus1470
206minus1
545
Superimpo
sed
dead
load
minus265
278
minus736
300minus7
95
Total
1880
3752
3014
2717
2218
1710
1642
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus1
650
185
minus3053
minus3053
minus3053
240minus3
960
Prestress
3530
180
6354
6354
6354
220
7766
Topp
ing
minus750
minus750
230minus1
725
Superimpo
sed
dead
load
minus265
300minus7
95
Total
1880
3302
2552
2287
1286
Improved
PCI
BDM
Self-weigh
tminus1
650
196
minus3234
minus3234
minus3234
288minus4
752
Prestress
3530
196
6919
6919
6919
288
10166
Prestresslossminus5
30
100
minus530
minus530
minus530
232minus1
228
Topp
ing
minus750
minus750
250minus1
875
Superimpo
sed
dead
load
minus265
250minus6
63
Total
1880
3155
2405
2140
1648
KRC-08090
Self-weigh
tminus1
650
210
minus3465
211
minus3482
220
minus3630
240
minus3960
280
minus4620
300minus4
950
Prestress
3530
210
7413
211
7448
220
7766
240
8472
280
9884
300
10590
Topp
ing
minus750
150
minus1125
220
minus1650
275
minus2063
300minus2
250
Superimpo
sed
dead
load
minus265
265
minus702
300minus7
95
Total
1880
3948
3217
3011
2597
2499
2595
Num
erical
analysis
Total
1792
3926
2866
2536
2138
1954
1923
10 Advances in Civil Engineering
Consequently the proposed multipliers method pro-vided not only the closest prediction values but also themost similar long-term behavior trend to the numericalanalysis
6 Conclusions
Since the current PCI Bridge Design Manual [18] providesthe long-term deformation multipliers only at erection andfinal it cannot consider various construction processesFurthermore the multipliers for the composite cross sectionare also required to be modified to reflect the characteristicsof the cross section used in modern PSC bridges -ereforein this study newmodified PCImultipliers were proposed toovercome these problems -e conclusions drawn from thisstudy are as follows
(1) -e new modified PCI multipliers were proposed byusing the rate of creep and shrinkage over timeUnlike the existing PCI Bridge Design Manual [18]method it is possible to reflect the actual girdererection time and predict the long-term deformationfor any construction schedule Moreover throughthe new method camber and deflection of PSCbridges can be predicted at any time including designstage construction stage and use stage
(2) -e ratio of noncomposite to composite moments ofinertia IoIc was 051ndash056 as a result of analyzingrepresentative cross sections used in practice byspan while the PCI Bridge Design Manual [18]suggests 065 of IoIc-erefore it is suggested to usethe average value of 053 for IoIc in order to predictthe long-term behavior of composite members
ndash80
ndash60
ndash40
ndash20
0
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
PS forceSelf-weight
ToppingAdditional DL
(a)
ToppingPS forceSelf-weight Additional DL
0
ndash80
ndash60
ndash40
ndash20
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 6 Predictions by the proposed multipliers for each load type (a) Bridge A (b) Bridge B
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
(a)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 5 Comparison of various predictions for bridges (a) A and (b) B
Advances in Civil Engineering 11
(3) In order to verify the proposed multipliers for ac-tually constructed PSC bridges the predictions oflong-term camber and deflection by the proposedmultipliers were compared with those by the basicPCI multipliers [18] improved PCI multipliers [20]KR C-08090 [1] and numerical analysis As a resultKR C-08090 [1] predictions were significantly higherthan the other predictions and the basic PCI mul-tipliers [18] did not show a reasonable tendency inthe long-term behavior between the erection timeand the final Among all methods except the pro-posed method the improved PCI multipliers [20]showed the most similar predictions to the nu-merical analysis However this improved PCImultiplier method also has limitations in finding thelong-term deflection or camber of the bridge at anytime and there are several variables such as the creepcoefficient that must be known precisely in order touse the multipliers which is inconvenient for de-signers to use However the predictions through thenewly proposed multipliers showed a reasonablelong-term behavior trend and the amount of thefinal camber was also the most similar to the nu-merical analysis result Above all the proposedmethod can make it possible for the designer topredict the long-term behavior of the bridge veryeasily according to any construction schedule
Data Availability
-e data used to support the findings of this study areavailable from the corresponding author upon request
Conflicts of Interest
-e authors declare that they have no conflicts of interest
Acknowledgments
-is research was supported by a grant (17RTRP-B067919-05) from Railroad Technology Research Program funded byMinistry of Land Infrastructure and Transport of Koreangovernment
References
[1] Korea Rail Network Authority Railway Design Guidelines andHandbooks Bridge Concrete Track Ends Usability Review (KRC-08090) in Korean Korea Rail Network Authority DaejeonRepublic of Korea 2014
[2] ACI Committee 318 Building Code Requirements for Struc-tural Concrete (ACI 318-14) and Commentary AmericanConcrete Institute Farmington Hills MI USA 2014
[3] ACI Committe 209 Prediction of Creep Shrinkage andTemperature Effects in Concrete Structure American ConcreteInstitute Farmington Hill MI USA 1992
[4] AASHTO (American Association of State Highway andTransportation Officials) AASHTO LRFD Bridge DesignSpecifications AASHTO Washington DC USA 2007
[5] CEBFIP Model Code Comit Euro-International du BetonTelford Ltd London UK 1990
[6] H-G Kwak and Y-J Seo ldquoLong-term behavior of compositegirder bridgesrdquo Computers and Structures vol 74 no 5pp 583ndash599 2000
[7] H Yang ldquoUncertainty and updating of long-term predictionof prestress forces in PSC box girder bridgesrdquo Computers andStructures vol 83 no 25ndash26 pp 2137ndash2149 2005
[8] S Biswal and A Ramaswamy ldquoUncertainty based modelaveraging for prediction of long-time prestress losses inconcrete structuresrdquo Construction and Building Materialsvol 153 pp 469ndash480 2017
[9] W He and Z Zhang ldquoModeling creep fracture in rock byusing kelvin discretized virtual internal bondrdquo Advances inCivil Engineering vol 2018 Article ID 8042965 8 pages 2018
[10] Y-S Park Y-H Lee and Y Lee ldquoDescription of concretecreep under time-varying stress using parallel creep curverdquoAdvances in Materials Science and Engineering vol 2016Article ID 9370514 13 pages 2016
[11] Z Pan and S Meng ldquo-ree-level experimental approach forcreep and shrinkage of high-strength high-performanceconcreterdquo Engineering Structures vol 120 pp 23ndash36 2016
[12] H-G Kwak and Y-J Seo ldquoNumerical analysis of time-dependent behavior of pre-cast pre-stressed concrete girderbridgesrdquo Construction and Building Materials vol 16 no 1pp 49ndash63 2002
[13] I N Robertson ldquoPrediction of vertical deflections for a long-span prestressed concrete bridge structurerdquo EngineeringStructures vol 27 no 12 pp 1820ndash1827 2005
[14] T Lou S M R Lopes and A V Lopes ldquoA finite elementmodel to simulate long-term behavior of prestressed concretegirdersrdquo Finite Elements in Analysis and Design vol 81pp 48ndash56 2014
[15] P Liu Q Xing DWang andM Oeser ldquoApplication of linearviscoelastic properties in semianalytical finite element methodwith recursive time integration to analyze asphalt pavementstructurerdquo Advances in Civil Engineering vol 2018 Article ID9045820 15 pages 2018
[16] A Sagara and I Pane ldquoA study on effects of creep andshrinkage in high strength concrete bridgesrdquo Procedia En-gineering vol 125 pp 1087ndash1093 2015
[17] H Sousa J Bento and J Figueiras ldquoConstruction assessmentand long-term prediction of prestressed concrete bridgesbased on monitoring datardquo Engineering Structures vol 52pp 26ndash37 2013
[18] PCI Bridge Design Manual Second Release PrecastPrestressed Concrete Institute Chicago IL USA 3rd edi-tion 2014
[19] L D Martin ldquoA rational method for estimating camber anddeflection of precast prestressed membersrdquo PCI Journalvol 22 no 1 pp 100ndash108 1977
[20] PCI Bridge Design Manual PrecastPrestressed ConcreteInstitute Chicago IL USA 2nd edition 2003
[21] M K Tadros A Ghali and A W Meyer ldquoPrestressed lossand deflection of precast concrete membersrdquo PCI Journalvol 30 no 1 pp 114ndash141 1985
[22] Y Zhang ldquoOrthogonal test analysis on influencing factors ofprestressed concrete small box beam camberrdquo Applied Me-chanics and Materials vol 405-408 pp 1527ndash1530 2013
[23] Y Jianjun W Xun and H Xianzheng ldquoEffects of live load onthe deflection of long-span PC continuous rigid-framehighway bridge based on midasrdquo in Proceedings of 20147th International Conference on Intelligent ComputationTechnology and Automation pp 944ndash946 Changsha China2014
12 Advances in Civil Engineering
[24] T Grigorjeva A Juozapaitis and Z Kamaitis ldquoStatic analysisand simplified design of suspension bridges having variousrigidity of cablesrdquo Journal of Civil Engineering and Man-agement vol 16 no 3 pp 363ndash371 2011
[25] ACI Committee 435 Control of Deflection in ConcreteStructures ACI 435R-95 ACI Farmington Hills MI USA2003
[26] F B Angomas ldquoBehavior of prestressed concrete bridgegirdersrdquo All Graduate -eses and Dissertations Utah StateUniversity Logan UT USA 2009
[27] E H Gheitanbaf ldquoImproving the prediction of time-dependent effects on prestressed concrete bridgesrdquo Gradu-ate-eses and Dissertations Iowa State University Ames IAUSA 2015
[28] M K Tadros F Fawzy and K Hanna ldquoPrecast prestressedgirder camber variabilityrdquo PCI Journal vol 56 no 1pp 135ndash154 2011
Advances in Civil Engineering 13
International Journal of
AerospaceEngineeringHindawiwwwhindawicom Volume 2018
RoboticsJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Active and Passive Electronic Components
VLSI Design
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Shock and Vibration
Hindawiwwwhindawicom Volume 2018
Civil EngineeringAdvances in
Acoustics and VibrationAdvances in
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Electrical and Computer Engineering
Journal of
Advances inOptoElectronics
Hindawiwwwhindawicom
Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Control Scienceand Engineering
Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Journal ofEngineeringVolume 2018
SensorsJournal of
Hindawiwwwhindawicom Volume 2018
International Journal of
RotatingMachinery
Hindawiwwwhindawicom Volume 2018
Modelling ampSimulationin EngineeringHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Chemical EngineeringInternational Journal of Antennas and
Propagation
International Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Navigation and Observation
International Journal of
Hindawi
wwwhindawicom Volume 2018
Advances in
Multimedia
Submit your manuscripts atwwwhindawicom
Tabl
e9
Predictio
nsby
variou
smetho
dsforbridge
B(unitmm)
Metho
dLo
ad(1)
Release
Multip
lier
(2)
Erectio
nt(e)
Multip
lier
(3)
Topp
ing
(t(c))
Multip
lier
(4)1st
rand
omtim
e(t1)
Multip
lier
(5)
Superimpo
sed
dead
load
(t(s))
Multip
lier
(6)2n
drand
omtim
e(t2)
Multip
lier
(7)
Final
Prop
osed
multip
liers
Self-weigh
tminus1
650
226
minus3725
227
minus3744
229
minus3771
236
minus3886
242
minus3994
250minus4
120
Prestress
3530
212
7477
213
7508
214
7553
219
7740
224
7909
230
8102
Topp
ing
minus750
142
minus1065
183
minus1370
196
minus1470
206minus1
545
Superimpo
sed
dead
load
minus265
278
minus736
300minus7
95
Total
1880
3752
3014
2717
2218
1710
1642
PCIBridge
DesignManual
(BDM)
Self-weigh
tminus1
650
185
minus3053
minus3053
minus3053
240minus3
960
Prestress
3530
180
6354
6354
6354
220
7766
Topp
ing
minus750
minus750
230minus1
725
Superimpo
sed
dead
load
minus265
300minus7
95
Total
1880
3302
2552
2287
1286
Improved
PCI
BDM
Self-weigh
tminus1
650
196
minus3234
minus3234
minus3234
288minus4
752
Prestress
3530
196
6919
6919
6919
288
10166
Prestresslossminus5
30
100
minus530
minus530
minus530
232minus1
228
Topp
ing
minus750
minus750
250minus1
875
Superimpo
sed
dead
load
minus265
250minus6
63
Total
1880
3155
2405
2140
1648
KRC-08090
Self-weigh
tminus1
650
210
minus3465
211
minus3482
220
minus3630
240
minus3960
280
minus4620
300minus4
950
Prestress
3530
210
7413
211
7448
220
7766
240
8472
280
9884
300
10590
Topp
ing
minus750
150
minus1125
220
minus1650
275
minus2063
300minus2
250
Superimpo
sed
dead
load
minus265
265
minus702
300minus7
95
Total
1880
3948
3217
3011
2597
2499
2595
Num
erical
analysis
Total
1792
3926
2866
2536
2138
1954
1923
10 Advances in Civil Engineering
Consequently the proposed multipliers method pro-vided not only the closest prediction values but also themost similar long-term behavior trend to the numericalanalysis
6 Conclusions
Since the current PCI Bridge Design Manual [18] providesthe long-term deformation multipliers only at erection andfinal it cannot consider various construction processesFurthermore the multipliers for the composite cross sectionare also required to be modified to reflect the characteristicsof the cross section used in modern PSC bridges -ereforein this study newmodified PCImultipliers were proposed toovercome these problems -e conclusions drawn from thisstudy are as follows
(1) -e new modified PCI multipliers were proposed byusing the rate of creep and shrinkage over timeUnlike the existing PCI Bridge Design Manual [18]method it is possible to reflect the actual girdererection time and predict the long-term deformationfor any construction schedule Moreover throughthe new method camber and deflection of PSCbridges can be predicted at any time including designstage construction stage and use stage
(2) -e ratio of noncomposite to composite moments ofinertia IoIc was 051ndash056 as a result of analyzingrepresentative cross sections used in practice byspan while the PCI Bridge Design Manual [18]suggests 065 of IoIc-erefore it is suggested to usethe average value of 053 for IoIc in order to predictthe long-term behavior of composite members
ndash80
ndash60
ndash40
ndash20
0
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
PS forceSelf-weight
ToppingAdditional DL
(a)
ToppingPS forceSelf-weight Additional DL
0
ndash80
ndash60
ndash40
ndash20
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 6 Predictions by the proposed multipliers for each load type (a) Bridge A (b) Bridge B
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
(a)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 5 Comparison of various predictions for bridges (a) A and (b) B
Advances in Civil Engineering 11
(3) In order to verify the proposed multipliers for ac-tually constructed PSC bridges the predictions oflong-term camber and deflection by the proposedmultipliers were compared with those by the basicPCI multipliers [18] improved PCI multipliers [20]KR C-08090 [1] and numerical analysis As a resultKR C-08090 [1] predictions were significantly higherthan the other predictions and the basic PCI mul-tipliers [18] did not show a reasonable tendency inthe long-term behavior between the erection timeand the final Among all methods except the pro-posed method the improved PCI multipliers [20]showed the most similar predictions to the nu-merical analysis However this improved PCImultiplier method also has limitations in finding thelong-term deflection or camber of the bridge at anytime and there are several variables such as the creepcoefficient that must be known precisely in order touse the multipliers which is inconvenient for de-signers to use However the predictions through thenewly proposed multipliers showed a reasonablelong-term behavior trend and the amount of thefinal camber was also the most similar to the nu-merical analysis result Above all the proposedmethod can make it possible for the designer topredict the long-term behavior of the bridge veryeasily according to any construction schedule
Data Availability
-e data used to support the findings of this study areavailable from the corresponding author upon request
Conflicts of Interest
-e authors declare that they have no conflicts of interest
Acknowledgments
-is research was supported by a grant (17RTRP-B067919-05) from Railroad Technology Research Program funded byMinistry of Land Infrastructure and Transport of Koreangovernment
References
[1] Korea Rail Network Authority Railway Design Guidelines andHandbooks Bridge Concrete Track Ends Usability Review (KRC-08090) in Korean Korea Rail Network Authority DaejeonRepublic of Korea 2014
[2] ACI Committee 318 Building Code Requirements for Struc-tural Concrete (ACI 318-14) and Commentary AmericanConcrete Institute Farmington Hills MI USA 2014
[3] ACI Committe 209 Prediction of Creep Shrinkage andTemperature Effects in Concrete Structure American ConcreteInstitute Farmington Hill MI USA 1992
[4] AASHTO (American Association of State Highway andTransportation Officials) AASHTO LRFD Bridge DesignSpecifications AASHTO Washington DC USA 2007
[5] CEBFIP Model Code Comit Euro-International du BetonTelford Ltd London UK 1990
[6] H-G Kwak and Y-J Seo ldquoLong-term behavior of compositegirder bridgesrdquo Computers and Structures vol 74 no 5pp 583ndash599 2000
[7] H Yang ldquoUncertainty and updating of long-term predictionof prestress forces in PSC box girder bridgesrdquo Computers andStructures vol 83 no 25ndash26 pp 2137ndash2149 2005
[8] S Biswal and A Ramaswamy ldquoUncertainty based modelaveraging for prediction of long-time prestress losses inconcrete structuresrdquo Construction and Building Materialsvol 153 pp 469ndash480 2017
[9] W He and Z Zhang ldquoModeling creep fracture in rock byusing kelvin discretized virtual internal bondrdquo Advances inCivil Engineering vol 2018 Article ID 8042965 8 pages 2018
[10] Y-S Park Y-H Lee and Y Lee ldquoDescription of concretecreep under time-varying stress using parallel creep curverdquoAdvances in Materials Science and Engineering vol 2016Article ID 9370514 13 pages 2016
[11] Z Pan and S Meng ldquo-ree-level experimental approach forcreep and shrinkage of high-strength high-performanceconcreterdquo Engineering Structures vol 120 pp 23ndash36 2016
[12] H-G Kwak and Y-J Seo ldquoNumerical analysis of time-dependent behavior of pre-cast pre-stressed concrete girderbridgesrdquo Construction and Building Materials vol 16 no 1pp 49ndash63 2002
[13] I N Robertson ldquoPrediction of vertical deflections for a long-span prestressed concrete bridge structurerdquo EngineeringStructures vol 27 no 12 pp 1820ndash1827 2005
[14] T Lou S M R Lopes and A V Lopes ldquoA finite elementmodel to simulate long-term behavior of prestressed concretegirdersrdquo Finite Elements in Analysis and Design vol 81pp 48ndash56 2014
[15] P Liu Q Xing DWang andM Oeser ldquoApplication of linearviscoelastic properties in semianalytical finite element methodwith recursive time integration to analyze asphalt pavementstructurerdquo Advances in Civil Engineering vol 2018 Article ID9045820 15 pages 2018
[16] A Sagara and I Pane ldquoA study on effects of creep andshrinkage in high strength concrete bridgesrdquo Procedia En-gineering vol 125 pp 1087ndash1093 2015
[17] H Sousa J Bento and J Figueiras ldquoConstruction assessmentand long-term prediction of prestressed concrete bridgesbased on monitoring datardquo Engineering Structures vol 52pp 26ndash37 2013
[18] PCI Bridge Design Manual Second Release PrecastPrestressed Concrete Institute Chicago IL USA 3rd edi-tion 2014
[19] L D Martin ldquoA rational method for estimating camber anddeflection of precast prestressed membersrdquo PCI Journalvol 22 no 1 pp 100ndash108 1977
[20] PCI Bridge Design Manual PrecastPrestressed ConcreteInstitute Chicago IL USA 2nd edition 2003
[21] M K Tadros A Ghali and A W Meyer ldquoPrestressed lossand deflection of precast concrete membersrdquo PCI Journalvol 30 no 1 pp 114ndash141 1985
[22] Y Zhang ldquoOrthogonal test analysis on influencing factors ofprestressed concrete small box beam camberrdquo Applied Me-chanics and Materials vol 405-408 pp 1527ndash1530 2013
[23] Y Jianjun W Xun and H Xianzheng ldquoEffects of live load onthe deflection of long-span PC continuous rigid-framehighway bridge based on midasrdquo in Proceedings of 20147th International Conference on Intelligent ComputationTechnology and Automation pp 944ndash946 Changsha China2014
12 Advances in Civil Engineering
[24] T Grigorjeva A Juozapaitis and Z Kamaitis ldquoStatic analysisand simplified design of suspension bridges having variousrigidity of cablesrdquo Journal of Civil Engineering and Man-agement vol 16 no 3 pp 363ndash371 2011
[25] ACI Committee 435 Control of Deflection in ConcreteStructures ACI 435R-95 ACI Farmington Hills MI USA2003
[26] F B Angomas ldquoBehavior of prestressed concrete bridgegirdersrdquo All Graduate -eses and Dissertations Utah StateUniversity Logan UT USA 2009
[27] E H Gheitanbaf ldquoImproving the prediction of time-dependent effects on prestressed concrete bridgesrdquo Gradu-ate-eses and Dissertations Iowa State University Ames IAUSA 2015
[28] M K Tadros F Fawzy and K Hanna ldquoPrecast prestressedgirder camber variabilityrdquo PCI Journal vol 56 no 1pp 135ndash154 2011
Advances in Civil Engineering 13
International Journal of
AerospaceEngineeringHindawiwwwhindawicom Volume 2018
RoboticsJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Active and Passive Electronic Components
VLSI Design
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Shock and Vibration
Hindawiwwwhindawicom Volume 2018
Civil EngineeringAdvances in
Acoustics and VibrationAdvances in
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Electrical and Computer Engineering
Journal of
Advances inOptoElectronics
Hindawiwwwhindawicom
Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Control Scienceand Engineering
Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Journal ofEngineeringVolume 2018
SensorsJournal of
Hindawiwwwhindawicom Volume 2018
International Journal of
RotatingMachinery
Hindawiwwwhindawicom Volume 2018
Modelling ampSimulationin EngineeringHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Chemical EngineeringInternational Journal of Antennas and
Propagation
International Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Navigation and Observation
International Journal of
Hindawi
wwwhindawicom Volume 2018
Advances in
Multimedia
Submit your manuscripts atwwwhindawicom
Consequently the proposed multipliers method pro-vided not only the closest prediction values but also themost similar long-term behavior trend to the numericalanalysis
6 Conclusions
Since the current PCI Bridge Design Manual [18] providesthe long-term deformation multipliers only at erection andfinal it cannot consider various construction processesFurthermore the multipliers for the composite cross sectionare also required to be modified to reflect the characteristicsof the cross section used in modern PSC bridges -ereforein this study newmodified PCImultipliers were proposed toovercome these problems -e conclusions drawn from thisstudy are as follows
(1) -e new modified PCI multipliers were proposed byusing the rate of creep and shrinkage over timeUnlike the existing PCI Bridge Design Manual [18]method it is possible to reflect the actual girdererection time and predict the long-term deformationfor any construction schedule Moreover throughthe new method camber and deflection of PSCbridges can be predicted at any time including designstage construction stage and use stage
(2) -e ratio of noncomposite to composite moments ofinertia IoIc was 051ndash056 as a result of analyzingrepresentative cross sections used in practice byspan while the PCI Bridge Design Manual [18]suggests 065 of IoIc-erefore it is suggested to usethe average value of 053 for IoIc in order to predictthe long-term behavior of composite members
ndash80
ndash60
ndash40
ndash20
0
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
PS forceSelf-weight
ToppingAdditional DL
(a)
ToppingPS forceSelf-weight Additional DL
0
ndash80
ndash60
ndash40
ndash20
20
40
60
80
100
120
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 6 Predictions by the proposed multipliers for each load type (a) Bridge A (b) Bridge B
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
(a)
Proposed multiplierPCI BDMImproved PCI BDM
KR C-08090Numerical analysis
0
5
10
15
20
25
30
35
40
45
50
0 200 400 600 800 1000 1200 1400 1600 1800 2000
Mid
span
cam
ber (
mm
)
Time aer casting (days)
(b)
Figure 5 Comparison of various predictions for bridges (a) A and (b) B
Advances in Civil Engineering 11
(3) In order to verify the proposed multipliers for ac-tually constructed PSC bridges the predictions oflong-term camber and deflection by the proposedmultipliers were compared with those by the basicPCI multipliers [18] improved PCI multipliers [20]KR C-08090 [1] and numerical analysis As a resultKR C-08090 [1] predictions were significantly higherthan the other predictions and the basic PCI mul-tipliers [18] did not show a reasonable tendency inthe long-term behavior between the erection timeand the final Among all methods except the pro-posed method the improved PCI multipliers [20]showed the most similar predictions to the nu-merical analysis However this improved PCImultiplier method also has limitations in finding thelong-term deflection or camber of the bridge at anytime and there are several variables such as the creepcoefficient that must be known precisely in order touse the multipliers which is inconvenient for de-signers to use However the predictions through thenewly proposed multipliers showed a reasonablelong-term behavior trend and the amount of thefinal camber was also the most similar to the nu-merical analysis result Above all the proposedmethod can make it possible for the designer topredict the long-term behavior of the bridge veryeasily according to any construction schedule
Data Availability
-e data used to support the findings of this study areavailable from the corresponding author upon request
Conflicts of Interest
-e authors declare that they have no conflicts of interest
Acknowledgments
-is research was supported by a grant (17RTRP-B067919-05) from Railroad Technology Research Program funded byMinistry of Land Infrastructure and Transport of Koreangovernment
References
[1] Korea Rail Network Authority Railway Design Guidelines andHandbooks Bridge Concrete Track Ends Usability Review (KRC-08090) in Korean Korea Rail Network Authority DaejeonRepublic of Korea 2014
[2] ACI Committee 318 Building Code Requirements for Struc-tural Concrete (ACI 318-14) and Commentary AmericanConcrete Institute Farmington Hills MI USA 2014
[3] ACI Committe 209 Prediction of Creep Shrinkage andTemperature Effects in Concrete Structure American ConcreteInstitute Farmington Hill MI USA 1992
[4] AASHTO (American Association of State Highway andTransportation Officials) AASHTO LRFD Bridge DesignSpecifications AASHTO Washington DC USA 2007
[5] CEBFIP Model Code Comit Euro-International du BetonTelford Ltd London UK 1990
[6] H-G Kwak and Y-J Seo ldquoLong-term behavior of compositegirder bridgesrdquo Computers and Structures vol 74 no 5pp 583ndash599 2000
[7] H Yang ldquoUncertainty and updating of long-term predictionof prestress forces in PSC box girder bridgesrdquo Computers andStructures vol 83 no 25ndash26 pp 2137ndash2149 2005
[8] S Biswal and A Ramaswamy ldquoUncertainty based modelaveraging for prediction of long-time prestress losses inconcrete structuresrdquo Construction and Building Materialsvol 153 pp 469ndash480 2017
[9] W He and Z Zhang ldquoModeling creep fracture in rock byusing kelvin discretized virtual internal bondrdquo Advances inCivil Engineering vol 2018 Article ID 8042965 8 pages 2018
[10] Y-S Park Y-H Lee and Y Lee ldquoDescription of concretecreep under time-varying stress using parallel creep curverdquoAdvances in Materials Science and Engineering vol 2016Article ID 9370514 13 pages 2016
[11] Z Pan and S Meng ldquo-ree-level experimental approach forcreep and shrinkage of high-strength high-performanceconcreterdquo Engineering Structures vol 120 pp 23ndash36 2016
[12] H-G Kwak and Y-J Seo ldquoNumerical analysis of time-dependent behavior of pre-cast pre-stressed concrete girderbridgesrdquo Construction and Building Materials vol 16 no 1pp 49ndash63 2002
[13] I N Robertson ldquoPrediction of vertical deflections for a long-span prestressed concrete bridge structurerdquo EngineeringStructures vol 27 no 12 pp 1820ndash1827 2005
[14] T Lou S M R Lopes and A V Lopes ldquoA finite elementmodel to simulate long-term behavior of prestressed concretegirdersrdquo Finite Elements in Analysis and Design vol 81pp 48ndash56 2014
[15] P Liu Q Xing DWang andM Oeser ldquoApplication of linearviscoelastic properties in semianalytical finite element methodwith recursive time integration to analyze asphalt pavementstructurerdquo Advances in Civil Engineering vol 2018 Article ID9045820 15 pages 2018
[16] A Sagara and I Pane ldquoA study on effects of creep andshrinkage in high strength concrete bridgesrdquo Procedia En-gineering vol 125 pp 1087ndash1093 2015
[17] H Sousa J Bento and J Figueiras ldquoConstruction assessmentand long-term prediction of prestressed concrete bridgesbased on monitoring datardquo Engineering Structures vol 52pp 26ndash37 2013
[18] PCI Bridge Design Manual Second Release PrecastPrestressed Concrete Institute Chicago IL USA 3rd edi-tion 2014
[19] L D Martin ldquoA rational method for estimating camber anddeflection of precast prestressed membersrdquo PCI Journalvol 22 no 1 pp 100ndash108 1977
[20] PCI Bridge Design Manual PrecastPrestressed ConcreteInstitute Chicago IL USA 2nd edition 2003
[21] M K Tadros A Ghali and A W Meyer ldquoPrestressed lossand deflection of precast concrete membersrdquo PCI Journalvol 30 no 1 pp 114ndash141 1985
[22] Y Zhang ldquoOrthogonal test analysis on influencing factors ofprestressed concrete small box beam camberrdquo Applied Me-chanics and Materials vol 405-408 pp 1527ndash1530 2013
[23] Y Jianjun W Xun and H Xianzheng ldquoEffects of live load onthe deflection of long-span PC continuous rigid-framehighway bridge based on midasrdquo in Proceedings of 20147th International Conference on Intelligent ComputationTechnology and Automation pp 944ndash946 Changsha China2014
12 Advances in Civil Engineering
[24] T Grigorjeva A Juozapaitis and Z Kamaitis ldquoStatic analysisand simplified design of suspension bridges having variousrigidity of cablesrdquo Journal of Civil Engineering and Man-agement vol 16 no 3 pp 363ndash371 2011
[25] ACI Committee 435 Control of Deflection in ConcreteStructures ACI 435R-95 ACI Farmington Hills MI USA2003
[26] F B Angomas ldquoBehavior of prestressed concrete bridgegirdersrdquo All Graduate -eses and Dissertations Utah StateUniversity Logan UT USA 2009
[27] E H Gheitanbaf ldquoImproving the prediction of time-dependent effects on prestressed concrete bridgesrdquo Gradu-ate-eses and Dissertations Iowa State University Ames IAUSA 2015
[28] M K Tadros F Fawzy and K Hanna ldquoPrecast prestressedgirder camber variabilityrdquo PCI Journal vol 56 no 1pp 135ndash154 2011
Advances in Civil Engineering 13
International Journal of
AerospaceEngineeringHindawiwwwhindawicom Volume 2018
RoboticsJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Active and Passive Electronic Components
VLSI Design
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Shock and Vibration
Hindawiwwwhindawicom Volume 2018
Civil EngineeringAdvances in
Acoustics and VibrationAdvances in
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Electrical and Computer Engineering
Journal of
Advances inOptoElectronics
Hindawiwwwhindawicom
Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Control Scienceand Engineering
Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Journal ofEngineeringVolume 2018
SensorsJournal of
Hindawiwwwhindawicom Volume 2018
International Journal of
RotatingMachinery
Hindawiwwwhindawicom Volume 2018
Modelling ampSimulationin EngineeringHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Chemical EngineeringInternational Journal of Antennas and
Propagation
International Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Navigation and Observation
International Journal of
Hindawi
wwwhindawicom Volume 2018
Advances in
Multimedia
Submit your manuscripts atwwwhindawicom
(3) In order to verify the proposed multipliers for ac-tually constructed PSC bridges the predictions oflong-term camber and deflection by the proposedmultipliers were compared with those by the basicPCI multipliers [18] improved PCI multipliers [20]KR C-08090 [1] and numerical analysis As a resultKR C-08090 [1] predictions were significantly higherthan the other predictions and the basic PCI mul-tipliers [18] did not show a reasonable tendency inthe long-term behavior between the erection timeand the final Among all methods except the pro-posed method the improved PCI multipliers [20]showed the most similar predictions to the nu-merical analysis However this improved PCImultiplier method also has limitations in finding thelong-term deflection or camber of the bridge at anytime and there are several variables such as the creepcoefficient that must be known precisely in order touse the multipliers which is inconvenient for de-signers to use However the predictions through thenewly proposed multipliers showed a reasonablelong-term behavior trend and the amount of thefinal camber was also the most similar to the nu-merical analysis result Above all the proposedmethod can make it possible for the designer topredict the long-term behavior of the bridge veryeasily according to any construction schedule
Data Availability
-e data used to support the findings of this study areavailable from the corresponding author upon request
Conflicts of Interest
-e authors declare that they have no conflicts of interest
Acknowledgments
-is research was supported by a grant (17RTRP-B067919-05) from Railroad Technology Research Program funded byMinistry of Land Infrastructure and Transport of Koreangovernment
References
[1] Korea Rail Network Authority Railway Design Guidelines andHandbooks Bridge Concrete Track Ends Usability Review (KRC-08090) in Korean Korea Rail Network Authority DaejeonRepublic of Korea 2014
[2] ACI Committee 318 Building Code Requirements for Struc-tural Concrete (ACI 318-14) and Commentary AmericanConcrete Institute Farmington Hills MI USA 2014
[3] ACI Committe 209 Prediction of Creep Shrinkage andTemperature Effects in Concrete Structure American ConcreteInstitute Farmington Hill MI USA 1992
[4] AASHTO (American Association of State Highway andTransportation Officials) AASHTO LRFD Bridge DesignSpecifications AASHTO Washington DC USA 2007
[5] CEBFIP Model Code Comit Euro-International du BetonTelford Ltd London UK 1990
[6] H-G Kwak and Y-J Seo ldquoLong-term behavior of compositegirder bridgesrdquo Computers and Structures vol 74 no 5pp 583ndash599 2000
[7] H Yang ldquoUncertainty and updating of long-term predictionof prestress forces in PSC box girder bridgesrdquo Computers andStructures vol 83 no 25ndash26 pp 2137ndash2149 2005
[8] S Biswal and A Ramaswamy ldquoUncertainty based modelaveraging for prediction of long-time prestress losses inconcrete structuresrdquo Construction and Building Materialsvol 153 pp 469ndash480 2017
[9] W He and Z Zhang ldquoModeling creep fracture in rock byusing kelvin discretized virtual internal bondrdquo Advances inCivil Engineering vol 2018 Article ID 8042965 8 pages 2018
[10] Y-S Park Y-H Lee and Y Lee ldquoDescription of concretecreep under time-varying stress using parallel creep curverdquoAdvances in Materials Science and Engineering vol 2016Article ID 9370514 13 pages 2016
[11] Z Pan and S Meng ldquo-ree-level experimental approach forcreep and shrinkage of high-strength high-performanceconcreterdquo Engineering Structures vol 120 pp 23ndash36 2016
[12] H-G Kwak and Y-J Seo ldquoNumerical analysis of time-dependent behavior of pre-cast pre-stressed concrete girderbridgesrdquo Construction and Building Materials vol 16 no 1pp 49ndash63 2002
[13] I N Robertson ldquoPrediction of vertical deflections for a long-span prestressed concrete bridge structurerdquo EngineeringStructures vol 27 no 12 pp 1820ndash1827 2005
[14] T Lou S M R Lopes and A V Lopes ldquoA finite elementmodel to simulate long-term behavior of prestressed concretegirdersrdquo Finite Elements in Analysis and Design vol 81pp 48ndash56 2014
[15] P Liu Q Xing DWang andM Oeser ldquoApplication of linearviscoelastic properties in semianalytical finite element methodwith recursive time integration to analyze asphalt pavementstructurerdquo Advances in Civil Engineering vol 2018 Article ID9045820 15 pages 2018
[16] A Sagara and I Pane ldquoA study on effects of creep andshrinkage in high strength concrete bridgesrdquo Procedia En-gineering vol 125 pp 1087ndash1093 2015
[17] H Sousa J Bento and J Figueiras ldquoConstruction assessmentand long-term prediction of prestressed concrete bridgesbased on monitoring datardquo Engineering Structures vol 52pp 26ndash37 2013
[18] PCI Bridge Design Manual Second Release PrecastPrestressed Concrete Institute Chicago IL USA 3rd edi-tion 2014
[19] L D Martin ldquoA rational method for estimating camber anddeflection of precast prestressed membersrdquo PCI Journalvol 22 no 1 pp 100ndash108 1977
[20] PCI Bridge Design Manual PrecastPrestressed ConcreteInstitute Chicago IL USA 2nd edition 2003
[21] M K Tadros A Ghali and A W Meyer ldquoPrestressed lossand deflection of precast concrete membersrdquo PCI Journalvol 30 no 1 pp 114ndash141 1985
[22] Y Zhang ldquoOrthogonal test analysis on influencing factors ofprestressed concrete small box beam camberrdquo Applied Me-chanics and Materials vol 405-408 pp 1527ndash1530 2013
[23] Y Jianjun W Xun and H Xianzheng ldquoEffects of live load onthe deflection of long-span PC continuous rigid-framehighway bridge based on midasrdquo in Proceedings of 20147th International Conference on Intelligent ComputationTechnology and Automation pp 944ndash946 Changsha China2014
12 Advances in Civil Engineering
[24] T Grigorjeva A Juozapaitis and Z Kamaitis ldquoStatic analysisand simplified design of suspension bridges having variousrigidity of cablesrdquo Journal of Civil Engineering and Man-agement vol 16 no 3 pp 363ndash371 2011
[25] ACI Committee 435 Control of Deflection in ConcreteStructures ACI 435R-95 ACI Farmington Hills MI USA2003
[26] F B Angomas ldquoBehavior of prestressed concrete bridgegirdersrdquo All Graduate -eses and Dissertations Utah StateUniversity Logan UT USA 2009
[27] E H Gheitanbaf ldquoImproving the prediction of time-dependent effects on prestressed concrete bridgesrdquo Gradu-ate-eses and Dissertations Iowa State University Ames IAUSA 2015
[28] M K Tadros F Fawzy and K Hanna ldquoPrecast prestressedgirder camber variabilityrdquo PCI Journal vol 56 no 1pp 135ndash154 2011
Advances in Civil Engineering 13
International Journal of
AerospaceEngineeringHindawiwwwhindawicom Volume 2018
RoboticsJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Active and Passive Electronic Components
VLSI Design
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Shock and Vibration
Hindawiwwwhindawicom Volume 2018
Civil EngineeringAdvances in
Acoustics and VibrationAdvances in
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Electrical and Computer Engineering
Journal of
Advances inOptoElectronics
Hindawiwwwhindawicom
Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Control Scienceand Engineering
Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Journal ofEngineeringVolume 2018
SensorsJournal of
Hindawiwwwhindawicom Volume 2018
International Journal of
RotatingMachinery
Hindawiwwwhindawicom Volume 2018
Modelling ampSimulationin EngineeringHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Chemical EngineeringInternational Journal of Antennas and
Propagation
International Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Navigation and Observation
International Journal of
Hindawi
wwwhindawicom Volume 2018
Advances in
Multimedia
Submit your manuscripts atwwwhindawicom
[24] T Grigorjeva A Juozapaitis and Z Kamaitis ldquoStatic analysisand simplified design of suspension bridges having variousrigidity of cablesrdquo Journal of Civil Engineering and Man-agement vol 16 no 3 pp 363ndash371 2011
[25] ACI Committee 435 Control of Deflection in ConcreteStructures ACI 435R-95 ACI Farmington Hills MI USA2003
[26] F B Angomas ldquoBehavior of prestressed concrete bridgegirdersrdquo All Graduate -eses and Dissertations Utah StateUniversity Logan UT USA 2009
[27] E H Gheitanbaf ldquoImproving the prediction of time-dependent effects on prestressed concrete bridgesrdquo Gradu-ate-eses and Dissertations Iowa State University Ames IAUSA 2015
[28] M K Tadros F Fawzy and K Hanna ldquoPrecast prestressedgirder camber variabilityrdquo PCI Journal vol 56 no 1pp 135ndash154 2011
Advances in Civil Engineering 13
International Journal of
AerospaceEngineeringHindawiwwwhindawicom Volume 2018
RoboticsJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Active and Passive Electronic Components
VLSI Design
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Shock and Vibration
Hindawiwwwhindawicom Volume 2018
Civil EngineeringAdvances in
Acoustics and VibrationAdvances in
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Electrical and Computer Engineering
Journal of
Advances inOptoElectronics
Hindawiwwwhindawicom
Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Control Scienceand Engineering
Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Journal ofEngineeringVolume 2018
SensorsJournal of
Hindawiwwwhindawicom Volume 2018
International Journal of
RotatingMachinery
Hindawiwwwhindawicom Volume 2018
Modelling ampSimulationin EngineeringHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Chemical EngineeringInternational Journal of Antennas and
Propagation
International Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Navigation and Observation
International Journal of
Hindawi
wwwhindawicom Volume 2018
Advances in
Multimedia
Submit your manuscripts atwwwhindawicom
International Journal of
AerospaceEngineeringHindawiwwwhindawicom Volume 2018
RoboticsJournal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Active and Passive Electronic Components
VLSI Design
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Shock and Vibration
Hindawiwwwhindawicom Volume 2018
Civil EngineeringAdvances in
Acoustics and VibrationAdvances in
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Electrical and Computer Engineering
Journal of
Advances inOptoElectronics
Hindawiwwwhindawicom
Volume 2018
Hindawi Publishing Corporation httpwwwhindawicom Volume 2013Hindawiwwwhindawicom
The Scientific World Journal
Volume 2018
Control Scienceand Engineering
Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom
Journal ofEngineeringVolume 2018
SensorsJournal of
Hindawiwwwhindawicom Volume 2018
International Journal of
RotatingMachinery
Hindawiwwwhindawicom Volume 2018
Modelling ampSimulationin EngineeringHindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Chemical EngineeringInternational Journal of Antennas and
Propagation
International Journal of
Hindawiwwwhindawicom Volume 2018
Hindawiwwwhindawicom Volume 2018
Navigation and Observation
International Journal of
Hindawi
wwwhindawicom Volume 2018
Advances in
Multimedia
Submit your manuscripts atwwwhindawicom