2
www.systra.com Conventional Passenger Rail The challenge The Vietnam National Railway network presents a 1,650 km max- imum extension from North to South and a 50 km minimum extension from West to East. On a 2,832 km track, 2,432 are meter gauge, 400 are standard gauge (1,435 mm), of which 228 km are dual gauge. It extends from the Chinese border in the North to Ho Chi Minh City in the South. Two connections with Chinese Railway network are operated, one-meter gauge at Lao Cai and one standard gauge at Dong Dang. The rolling stock includes 370 diesel locomotives, 920 passenger cars and 4,500 freight wagons. Hanoi–Vinh is the first 320 km section of the Hanoi–Ho Chi Minh City (formerly Saigon) main line of Vietnam National Railways (VNR). Its modernisation includes the renewal of signalling and tele- communications systems to improve the safety of operations, to increase both the speed and transport capacity and provide a better reliability of the train circulation. phase 1 The first phase consists in the installation of: for Signalling new electronic interlockings (SSI technology Alstom) in 3 main stations: Van Dien, Bim Son and Than Hoa, a new automatic level crossing equipment near Van Dien station, single track automatic block sections, on both sides of Than Hoa station. for Telecommunications an optical fibre cable along the 320 km of the line (24 fibres), a multi-service transmission network based on SDH technol- ogy (STM1 & STM4 Alcatel), Project Manager 5 new PABX along the line, Hanoi, Nam Dinh, Thanh Hoa, Cau Giat and Vinh (Matra), a new specific telephone network dedicated to railway oper- ation, with terminals in all the stations of the line. The works schedule foresees the commissioning of the new Sig- nalling and Telecommunications systems during the first quarter of 2005. phase 2 According to the preliminary studies, the second phase should include: for Signalling new electronic interlockings in the remaining main stations of the line, single track automatic block sections for all the line, for Telecommunications a track to train radio system, a new optical cable for backup of the telecom network phase 1 (securisation). SYSTRA’s role On July 8 th 1999, SYSTRA signed a Consultant Services Contract with the Railway Project Management Unit (RPMU) of the VNR, that included in a first stage: diagnostic of the existing equipment, feasibility study on site, preliminary studies for the modernisation of Signalling and Telecommunications systems (split into two phases), technical design and preparation of the call for tender for phase 1 (including specifications, cost and delay estimate for the reali- sation of the works), assistance to the RPMU for the call for tender: analysis of bids, designation of the contractor. modernization of the hanoi-vinh line vietnam signaling telecommunication project management

modernization of the hanoi-vinh line - SYSTRA · modernization of the hanoi-vinh line vietnam The second stage of the contract has started on April 1 st 2003, when the Alstom –

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: modernization of the hanoi-vinh line - SYSTRA · modernization of the hanoi-vinh line vietnam The second stage of the contract has started on April 1 st 2003, when the Alstom –

www.systra.com

Conv

entiona

l Pa

ssen

ger

Rai

l

The challengeThe Vietnam National Railway network presents a 1,650 km max-imum extension from North to South and a 50 km minimumextension from West to East. On a 2,832 km track, 2,432 are meter gauge, 400 are standard gauge (1,435 mm), of which 228 km are dual gauge.It extends from the Chinese border in the North to Ho Chi Minh City in the South. Two connections with Chinese Railway networkare operated, one-meter gauge at Lao Cai and one standard gauge at Dong Dang. The rolling stock includes 370 diesel locomotives,920 passenger cars and 4,500 freight wagons.

Hanoi–Vinh is the first 320 km section of the Hanoi–Ho Chi MinhCity (formerly Saigon) main line of Vietnam National Railways (VNR).Its modernisation includes the renewal of signalling and tele-communications systems to improve the safety of operations, to increase both the speed and transport capacity and provide a better reliability of the train circulation.

phase 1The first phase consists in the installation of: for Signalling•new electronic interlockings (SSI technology Alstom) in 3 main

stations: Van Dien, Bim Son and Than Hoa, •a new automatic level crossing equipment near Van Dien

station,•single track automatic block sections, on both sides of Than

Hoa station. for Telecommunications•an optical fibre cable along the 320 km of the line (24 fibres),•a multi-service transmission network based on SDH technol-

ogy (STM1 & STM4 Alcatel),

Proje

ct M

anag

er

•5 new PABX along the line, Hanoi, Nam Dinh, Thanh Hoa, Cau Giat and Vinh (Matra),

•a new specific telephone network dedicated to railway oper-ation, with terminals in all the stations of the line.

The works schedule foresees the commissioning of the new Sig-nalling and Telecommunications systems during the first quarter of 2005.

phase 2According to the preliminary studies, the second phase should include: for Signalling•new electronic interlockings in the remaining main stations

of the line,•single track automatic block sections for all the line, for Telecommunications•a track to train radio system,•a new optical cable for backup of the telecom network phase

1 (securisation).

SYSTRA’s roleOn July 8th 1999, SYSTRA signed a Consultant Services Contract with the Railway Project Management Unit (RPMU) of the VNR, that included in a first stage: diagnostic of the existing equipment, feasibility study on site, preliminary studies for the modernisation of Signalling and

Telecommunications systems (split into two phases), technical design and preparation of the call for tender for phase

1 (including specifications, cost and delay estimate for the reali- sation of the works), assistance to the RPMU for the call for tender: analysis of bids,

designation of the contractor.

modernization of the hanoi-vinh linevietnam

signaling

telecommunication

project management

Page 2: modernization of the hanoi-vinh line - SYSTRA · modernization of the hanoi-vinh line vietnam The second stage of the contract has started on April 1 st 2003, when the Alstom –

www.systra.com

modernization of the hanoi-vinh line vietnam

The second stage of the contract has started on April 1st 2003, when the Alstom – Alcatel CIT consortium, winner of the tender,started its design activities for the new Signalling and Telecom-munications systems. SYSTRA carried out the following activities: review of detailed design studies documents and installation

method statements prepared by the contractor in accordance with the specifications, equipment manufacturing, installation and Testing and Com-

missioning supervision, assistance to the RPMU for the management of the project, supervision of the maintenance training carried out by the

contractor.

facts and figuresLength: 320 km – single trackNumber of stations: 36

organisations involvedOwner: Railway Project Management Unit (RPMU) of the Vietnam National Railways (VNR)Contractor: Alstom – Alcatel ConsortiumConsultant: SYSTRA in association with Railway Investment & Construction & Consultant Company(RICCC)

costPhase 1Contractor: € 8.7 million and 35,466 million VND

Consultant: € 1.02 million (includingpreliminary studies for Phase 2)

financingFrench Government RPE: for the foreign part in Euros

key datesJuly 1999: signature of the Consultant services Contract between RPMU and SYSTRAFebruary 2001: tendering ProcessJuly 2002: signature of the Contractor’s contractApril 2003: start of the Contractor’s workMarch 2005: commissioning of the Phase 1 new Signalling and Telecommunications systems

at a glance

China Kunming

China Kunming

Giap Bat

Van Dien

Than HoaGau GiatNghia Dan

HANOI

VINH

Ho Chi Minh City

febr

uary

2013