Mission Operations Cost Estimation Tool (MOCET)
Update
Marc Hayhurst, Brian Wood, Shirin EftekharzadehThe Aerospace Corporation
Cindy Daniels, Lissa Jordin, Washito Sasamoto, Waldo RodriguezNASA Langley Research CenterScience Office for Mission Assessments (SOMA)
NASA Cost Symposium 2016
Glenn Research Center, Cleveland Ohio
24 August 2016
© 2016 The Aerospace Corporation
Aerospace acknowledges NASA sponsorship under Contract NNL11AA01B Task Order NNL16AA49T.
2
Topics
• MOCET Overview & Status
Updates in MOCET v1.1
User Community
Common User Questions
Summary & Next Steps
•
•
•
•
.
4
•
MOCET’s First Year and Beyond
In August of FY15 MOCET was presented at the NASA Cost Symposium 2015
MOCET Excel tool was formally released as v1.0 to the NASA community at end of FY15
− Tool became available on the One NASA Cost Engineering (ONCE) Model Portal
− Approximately 30+ unique users downloads via ONCE to date
− MOCET has been used in Full Mission AO competitions since FY15
MOCET v1.1 was released in March of FY16
− More data from recent missions included in the tool
− More rigorous statistical methods applied to the model
First User’s Workshop was held virtually at the beginning of June FY16
NASA Cost Symposium 2016 Update and demo session
•
•
•
•
• Second User’s Workshop to be held virtually November FY17
More planned updates with new mission data and user’s feedback in FY17
SOMA has initiated the process to release MOCET on the NASA Software Catalog website at
https://software.nasa.gov
– No specific release date is known at this time.
– If you want to be notified when MOCET is available on the NASA Software Catalog website, send an email to
•
•
NOW
5
What Has Changed in v1.1?• Most CERs have been reformulated to produce better results
– Updated equations and performance comparison in following charts
Overall look and feel of the Excel tool and documentation remains the same
New Mission Data Added
– LADEE, MAVEN, OCO-2, GPM, New Horizons (Pluto Flyby)
More Comprehensive Statistical Process Applied
– Graphical analysis - Selecting independent variables, outlier detection
– Goodness of fit statistics - measures discrepancy between observed and expected values
– Analysis of residuals - Determines if linear regression is appropriate
– Significance testing - Determines if variables are necessary for the equation or if it is over-fitted
– Measures of performance -Test metrics to compare various models against each other
– Cross validation - Detects overfitting, compares regression forms, generalizes performance on an
independent data set, prevents throwing away data
Fewer inputs required from equation reformulation & significance testing
– No more enumerated variables
– Some inputs have changed, but follow similar assumptions
• For example, Number of Instruments was used in v1.0 which was favored for being simple and objective
• This has been replaced by Payload Mass in one CER and Peak Downlink in another for v1.1
• These parameters all attempt to quantify the amount of science/data analysis done in Phase E but those
used in v1.1 do a more effective job
•
•
•
•
6
MOCET Mission Types and Database Overview
Mission/CER Type
Planetary
Earth Science
Explorers
Near Earth Discovery Helio-Astro
Program
Discovery
Mars Scout
Robotic Lunar Exploration
New Frontiers
Mars Exploration
Earth System Science Pathfinder (ESSP)
Earth Systematic Missions (ESM)
Mission of Opportunity (MO)
Small Explorers (SMEX)
Medium Explorers (MIDEX)
Discovery
Solar Terrestrial Probes (STP)
Living With a Star (LWS)
Cosmic Origins
Physics of the Cosmos
Missions
MESSENGER, Dawn, Stardust, Deep Impact, GRAIL, NEAR
Phoenix
LRO, LADEE
Juno (Jupiter Ops), New Horizons (Pluto Flyby), OSIRIS-REx
MRO, Odyssey, MER, MSL, MAVEN
GRACE, CloudSat, CALIPSO, Aquarius, OCO-2, CYGNSS
Aqua, Aura, Terra, Jason-1, OSTM, ICESat, GPM, SMAP, Jason-
Suzaku (ASTRO-E2), TWINS, CINDI
NuSTAR, IRIS, IBEX, AIM, GALEX, RHESSI
THEMIS, Swift, WISE
Genesis, Kepler
STEREO, TIMED, MMS
RBSP, SDO
Spitzer
Fermi, Chandra
3
New Data in version 1.1 Potential New Data for version 1.X
– – –
Data Sources Utilized and Consulted
NASA SAP Business
Warehouse
• Monthly Expenditures
Monthly Flight Project Reviews (FPR)
and Monthly Status Reviews (MSR)
• Monthly Expenditures, Mission Events
& Schedule
NASA Cost Analysis Data
Requirements (CADRe)
• Project development costs used
to assign mission class
7
MOCET v1.1 CERs UpdatesPlanetary
CER NameNew Data New Eq. Form Additional Evaluation No Change Comments
Cruise CER X X XSeparated into two CERs: Checkout and Nominal/Quiescent
Approach/Orbit Insertion/Reduction CER X X X
Orbital Operations CER X X X
Flyby/Encounter CER X X
Approach EDL CER X No new/limited data. Not able to improve
First Landed Month CER X No new/limited data. Not able to improve
Landed Prime Operations CER X No new/limited data. Not able to improve
Data/Sample Analysis & Archiving CER X No new/limited data. Not able to improve
Extended Orbital Ops CER X Not primary focus
Extended Landed Ops CER X Not primary focus
Earth/Near-Earth Orbiting
CER NameNew Data New Eq. Form Additional Evaluation No Change Comments
Earth/Near-Earth Orbiting Checkout CER X X X
Earth Science Prime Operations CER X X X
Explorer Prime Operations CER X X
Near Earth Discovery Helio Astro Prime Operations CER X X
Updated in version 1.1
8
MOCET Cost Estimating Relationships (CERs)Planetary
CER Name
Nominal/Quiescent
Cruise CER
Checkout Cruise CER
Orbital Operations CER
Approach/Orbit
Insertion/Reduction
CER
Flyby/Encounter
Approach EDL
First Landed Month
Landed Prime
Operations
Data/Sample Analysis &
Archiving
Extended Orbital Ops
CER
Extended Landed Ops
CER
Equation Inputs
IL = Is the mission class Large? (0 No, 1 Yes)
IQ = Quiescent Ops (0 No, 1 Yes)
IL = Is the mission class Large? (0 No, 1 Yes)
EN = Does this checkout period require Enhanced Navigation? (0 No, 1
Yes)
PM = Payload Mass of NASA funded instruments
IM = Is Mars the operational environment? (0 No, 1 Yes)
PC = Estimated Preceding Cruise Phase Cost
PC = Estimated Preceding Cruise Phase Cost
PC = Estimated Preceding Cruise Phase Cost
PC = Estimated Preceding Cruise Phase Cost
PC = Estimated Preceding Prime Collection Phase Cost
P = Prime mission average monthly cost,
N = Number of times the mission is being extended or renewed (1 to N)
P = Prime mission average monthly cost,
N = Number of times the mission is being extended or renewed (1 to N)
No.
Inputs
2
2
2
1
1
1
1
1
1
2
2
N
6
7
7
6
5
3
3
3
3
15
11
Adj. R^2
or
r^2
0.87
0.97
0.86
0.99
0.97
0.97
0.97
0.70
0.99
0.94
0.99
SEE (%)
or
SE
(RSS)
0.21
0.17
0.22
0.11
0.10
13.3%
13.1%
31.0%
5.6%
7.2%
3.1%
Y = Average Monthly cost for phase (FY13)
N = Number of Data points
Adj. R^2 = Adjusted Coefficient of Determination
r^2 = Correlation Coefficient
SEE = Standard Error of the Estimate (Zero
Percentage Bias Minimum Percentage Error)
SE (RSS) = Standard Error (Root Sum of Squares)
Updated in version 1.1
8884.1* 0400.1* 1210.1* 7605.0* 7509.0* IMPM *4627.0*0133.03 PC*8836.017 IQIL *7805.0*8581.02 ENIL *2605.2*5666.091 YY PP**((00..209236**llnn((NN))00..61288443))
9
MOCET Cost Estimating Relationships (CERs)Earth Science, Explorers, and Near Earth Discovery Helio Astro
CER Name
Earth Science,
Explorers, and Near
Earth Discovery
Helio Astro
Checkout CER
Earth Science
Prime Operations
CER
Explorer Prime
Operations CER
Near Earth
Discovery Helio
Astro Prime
Operations
Equation Inputs
P = Prime mission operations average monthly cost
PD = Peak Downlink data rate from the spacecraft in megabits per
second
IFL = Is this a Large or Flagship mission class mission? (0 No, 1 Yes)
IMe = Is this a Medium mission class mission? (0 No, 1 Yes)
IMi = Is this a Micro mission class mission? (0 No, 1 Yes)
IA = Is this an Astrophysics mission? (0 No, 1 Yes)
IF = Is this a Flagship mission class mission? (0 No, 1 Yes)
No.
Inputs
1
2
3
2
N
13
13
12
Adj.
R^2
or
r^2
0.87
0.97
0.94
SEE (%)
or
SE
(RSS)
0.59
0.19
0.06
Y = Average Monthly cost for phase (FY13)
N = Number of Data points
Adj. R^2 = Adjusted Coefficient of Determination
r^2 = Correlation Coefficient
SEE = Standard Error of the Estimate (Zero
Percentage Bias Minimum Percentage Error)
SE (RSS) = Standard Error (Root Sum of Squares) 9741.1* IFIL *194.5*5894.0337 IFLPD *5782.1*0083.0204 IAIMiIMe *1204.0*3018.0*3135.0677 Updated in version 1.1
10
Model Performance
• The model was compared against actual mission costs to gauge performance
• Standard Deviation for all missions was found to be 20% (from 25% in v1.0)
• Planetary: 27% (v1.0 = 32%)
• Earth/Near Earth Orbiting: 16% (v1.0 = 22%)
v1.1
v1.0
11
MOCET User Community
• Since last years cost symposium and the release of v1.0 we have worked to engage the user
community
We have also briefed key personnel in the various NASA program offices for awareness of how
projects that fall under their portfolios will be evaluated
– Programs can also use MOCET to size program budgets for Phase E
As of late June 2016, approximately 30+ unique users have downloaded MOCET from ONCE
– A survey conducted by CAD (SID) in March 2016 showed 27 MOCET users
Expect user community to grow with proposal cycles and future release to contractors and
universities via the NASA Software Catalog at https://software.nasa.gov
User workshops are opportunities for users to learn more about MOCET and voice feedback that
can help steer future releases of MOCET
– First ever workshop was held virtually in June of 2016
– Next workshop will be held virtually in November of 2016
A feedback form is available with the tool for users to fill out
– We have already received a number of responses that have helped us make improvements to the tool this FY
•
•
•
•
•
12
Common User Questions
• What does MOCET estimate?
– MOCET estimates the total cost of Phase E
• WBS 1.0 Project Management
• WBS 2.0 System Engineering
• WBS 3.0 Mission Assurance
• WBS 4.0 Science/Data Analysis
• WBS 7.0 Mission Operations
• WBS 9.0 GDS/Data Analysis
• WBS 11.0 Education & Public Outreach
• Also any Phase E costs from WBS 5.0 Payload, 6.0 Spacecraft, 10.0 System I&T
– Only cost removed from MOCET estimates are LV related from KSC (WBS 8.0)
– This also does not include Deep Space Network (DSN) costs
• How was the data normalized?
– MOCET data is monthly data from SAP at the top level
– The only normalization is to remove any launch vehicle costs associated with KSC
– This means any post launch software development is included in MOCET
• The tool also has a Frequently Asked Questions (FAQ) section that should cover most questions
Email: [email protected]
anytime with questions
13
Summary & Next Steps
• New data has been added and CERs have been reformulated for MOCET v1.1
MOCET v1.1 has seen improvement over v1.0
The look and feel of the Excel tool is generally the same as v1.0
MOCET will continue to be periodically updated with new mission data
The model is currently being used by evaluators and proposers alike
We will continue to engage and grow the user community
•
•
•
•
•
Download MOCET
ONCE Model Portal https://oncedata.msfc.nasa.gov
Soon available external to NASA via https://software.nasa.gov