Upload
thomasine-dawson
View
213
Download
0
Embed Size (px)
Citation preview
MINIATURE ENGINEERING SYSTEMS GROUPMINIATURE ENGINEERING SYSTEMS GROUP::
COST ANALYSIS OF PRE-CHILLING AND COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION HEAT LEAKAGE DURING OPERATION
FORFORLH2 VJ STORAGE & TRANSFER LH2 VJ STORAGE & TRANSFER
FACILITIES AT NASA KSC FACILITIES AT NASA KSC
Presented by –Presented by –
K.V.Krishna MurtyK.V.Krishna Murty
ReferencesReferences:: A report on ‘NASA KSC Base Center Hydrogen Operations’ by Dr.Addison Bain, 2001-2002.
Communication of Mr.Thomas Tomsik (NASA GRC).
Communication of Mr.Bill Notardonato (NASA KSC).
LH2 Storage and Transfer facilities:LH2 Storage and Transfer facilities: LH2 Storage Tank: Outer Diameter of the outer shell = 70 ft, Inner Diameter of the inner shell = 62.5 ft, Material – Stainless Steel.
LH2 Transfer Line: Fill Rate to ET = 8,400 gpm to 10,000 gpm, Outer Jacket m/l – Stainless Steel, Inner Jacket m/l – Welded Invar,
Economic Analysis of Pre-Chilling of Economic Analysis of Pre-Chilling of metals:metals:
Assumptions and Values:
Latent Heat of Vaporization of LH2 (L): 56 W-hr/lb Cost of Electricity = 0.05 $/kW-hr LH2 cost = 2 $/lb Specific Heat of 304 SS at cryogenic temperature = 144 J/lb-K
• Density of 304 SS = 0.285 lb/in3 = 7,900 kg/m3
Specific Heat of Welded Invar at cryogenic temperature = 149 J/lb-K Density of Welded Invar = 0.291 lb/in3 = 8,055 kg/m3
• Thickness of storage tank = ½ in (assumed for calculations), VJ Transfer Line Length = 1500 ft Cooling Power of 1 RTBC = 1 kW @ 19K
Cost of Pre-ChillingCost of Pre-Chilling::
304 SS304 SS::
Cost of pre-chilling per lb of SS: 310K80K 80K19KLH2 Boil-off $0.328 $0.087RTBC $0.004 $0.018
Cost of pre-chilling 304 SS over the complete range (310K 19K):
cost/lb of SS SavingsBoil-off $0.414 0 %310K to 80K by RTBC, rest by boil-off $0.091 78 %310K to 19K by RTBC $0.022 95 %
Pre-chilling withtop stage to 80 K
Time Mass
(min) (lb)
7½ 208
15 417
22½ 625
30 833
Pre-chilling with bottom stage to 19K
Time Mass
(min) (lb)
37½ 208
75 417
112½ 625
150 833
Pre-Chilling of 304 SS (with 1 RTB):
Pre-chilling with 2 stages
Time Mass
(min) (lb)
45 208
90 417
135 625
180 833
Cost of Pre-ChillingCost of Pre-Chilling::
Welded InvarWelded Invar::
Cost of pre-chilling per lb of Welded Invar: 310K80K 80K19K
LH2 Boil-off $0.339 $0.090RTBC $0.004 $0.019
Cost of pre-chilling Welded Invar over the complete range
(310K 19K):cost/lb of WI Savings
Boil-off $0.429 0 %310K to 80K by RTBC, rest by boil-off $0.094 78 %310K to 19K by RTBC $0.023 95 %
Cost savings in maintaining the system Cost savings in maintaining the system at LH2 temperature by RTBCat LH2 temperature by RTBC:
Considering 1 kW of heat leakage,
If LH2 is let to boil-off:
Rate of LH2 boil-off = 430 lb/day
Cost of LH2 boil-off = 860 $/day
If RTBC is used to prevent LH2 boil-off:
Number of RTBC required = 1
Total cost of input power for 1 RTBC = 180 $/day
The savings from complete boil-off to RTBC use for Pre-
Chill = (860-180)/860 ≈ 79 %
Input power required to maintain the Input power required to maintain the Storage Tank (Pad B) at LH2 Storage Tank (Pad B) at LH2
temperaturetemperature::
LH2 Boil - Off = m = 600 gallons/day = 355 lb/day, LH2 Boil - Off = m = 600 gallons/day = 355 lb/day,
Cost of LH2 Boil-Off = $ 260,000/yr, Cost of LH2 Boil-Off = $ 260,000/yr,
Input power required = P where,
P= m*L = (355*56)/24 = 830 W.
So, a nominal cooling power of about 1 kW at 19K would be appropriate.
Time required to pre-chill the storage tank to 19 K with Time required to pre-chill the storage tank to 19 K with 1 RTB = 770 hr,1 RTB = 770 hr,Cost of LH2 Boil-Off for Pre-Chill = $ 105,000Cost of LH2 Boil-Off for Pre-Chill = $ 105,000
Pre-Chilling of Storage TankPre-Chilling of Storage Tank::
Pre-Chilling of Transfer LinePre-Chilling of Transfer Line::
LH2 Boil-Off Cost = $ 17,000,LH2 Boil-Off Cost = $ 17,000,
Number of RTBCs required to pre-chill the transfer Number of RTBCs required to pre-chill the transfer line to 19K in 9 hrs, I.e., with both stages = 15 (1 for line to 19K in 9 hrs, I.e., with both stages = 15 (1 for every 100 feet of the transfer line),every 100 feet of the transfer line),
Number of RTBCs required to pre-chill the transfer Number of RTBCs required to pre-chill the transfer line to 80K in 9 hrs, I.e., if only the top stage is used line to 80K in 9 hrs, I.e., if only the top stage is used = 3 (1 for every 500 feet of the transfer line).= 3 (1 for every 500 feet of the transfer line).
Conclusion:Conclusion:
The calculation shows that it is economically effective to use cryo-coolers for cooling the Liquid Hydrogen Vacuum Jacket storage & transfer facilities at NASA KSC.
Please NOTE: This analysis considers only the running costs associated with the cryocoolers. It does not take into account the installation and maintenance costs associated with the cryocoolers.