11
MINIATURE ENGINEERING SYSTEMS GROUP MINIATURE ENGINEERING SYSTEMS GROUP : : COST ANALYSIS OF PRE-CHILLING AND COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION FOR HEAT LEAKAGE DURING OPERATION FOR LH2 VJ STORAGE & TRANSFER FACILITIES LH2 VJ STORAGE & TRANSFER FACILITIES AT NASA KSC AT NASA KSC Presented by – Presented by – K.V.Krishna Murty K.V.Krishna Murty

MINIATURE ENGINEERING SYSTEMS GROUP: MINIATURE ENGINEERING SYSTEMS GROUP: COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION FOR LH2 VJ STORAGE

Embed Size (px)

Citation preview

Page 1: MINIATURE ENGINEERING SYSTEMS GROUP: MINIATURE ENGINEERING SYSTEMS GROUP: COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION FOR LH2 VJ STORAGE

    MINIATURE ENGINEERING SYSTEMS GROUPMINIATURE ENGINEERING SYSTEMS GROUP::

COST ANALYSIS OF PRE-CHILLING AND COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION HEAT LEAKAGE DURING OPERATION

FORFORLH2 VJ STORAGE & TRANSFER LH2 VJ STORAGE & TRANSFER

FACILITIES AT NASA KSC FACILITIES AT NASA KSC

Presented by –Presented by –

K.V.Krishna MurtyK.V.Krishna Murty

Page 2: MINIATURE ENGINEERING SYSTEMS GROUP: MINIATURE ENGINEERING SYSTEMS GROUP: COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION FOR LH2 VJ STORAGE

ReferencesReferences:: A report on ‘NASA KSC Base Center Hydrogen Operations’ by Dr.Addison Bain, 2001-2002.

Communication of Mr.Thomas Tomsik (NASA GRC).

Communication of Mr.Bill Notardonato (NASA KSC).

Page 3: MINIATURE ENGINEERING SYSTEMS GROUP: MINIATURE ENGINEERING SYSTEMS GROUP: COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION FOR LH2 VJ STORAGE

LH2 Storage and Transfer facilities:LH2 Storage and Transfer facilities: LH2 Storage Tank: Outer Diameter of the outer shell = 70 ft, Inner Diameter of the inner shell = 62.5 ft, Material – Stainless Steel.

LH2 Transfer Line: Fill Rate to ET = 8,400 gpm to 10,000 gpm, Outer Jacket m/l – Stainless Steel, Inner Jacket m/l – Welded Invar,

Page 4: MINIATURE ENGINEERING SYSTEMS GROUP: MINIATURE ENGINEERING SYSTEMS GROUP: COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION FOR LH2 VJ STORAGE

Economic Analysis of Pre-Chilling of Economic Analysis of Pre-Chilling of metals:metals:

Assumptions and Values:

Latent Heat of Vaporization of LH2 (L): 56 W-hr/lb Cost of Electricity = 0.05 $/kW-hr LH2 cost = 2 $/lb Specific Heat of 304 SS at cryogenic temperature = 144 J/lb-K

• Density of 304 SS = 0.285 lb/in3 = 7,900 kg/m3

Specific Heat of Welded Invar at cryogenic temperature = 149 J/lb-K Density of Welded Invar = 0.291 lb/in3 = 8,055 kg/m3

• Thickness of storage tank = ½ in (assumed for calculations), VJ Transfer Line Length = 1500 ft Cooling Power of 1 RTBC = 1 kW @ 19K

Page 5: MINIATURE ENGINEERING SYSTEMS GROUP: MINIATURE ENGINEERING SYSTEMS GROUP: COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION FOR LH2 VJ STORAGE

Cost of Pre-ChillingCost of Pre-Chilling::

304 SS304 SS::

Cost of pre-chilling per lb of SS: 310K80K 80K19KLH2 Boil-off $0.328 $0.087RTBC $0.004 $0.018

Cost of pre-chilling 304 SS over the complete range (310K 19K):

cost/lb of SS SavingsBoil-off $0.414 0 %310K to 80K by RTBC, rest by boil-off $0.091 78 %310K to 19K by RTBC $0.022 95 %

Page 6: MINIATURE ENGINEERING SYSTEMS GROUP: MINIATURE ENGINEERING SYSTEMS GROUP: COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION FOR LH2 VJ STORAGE

Pre-chilling withtop stage to 80 K

Time Mass

(min) (lb)

7½ 208

15 417

22½ 625

30 833

Pre-chilling with bottom stage to 19K

Time Mass

(min) (lb)

37½ 208

75 417

112½ 625

150 833

Pre-Chilling of 304 SS (with 1 RTB):

Pre-chilling with 2 stages

Time Mass

(min) (lb)

45 208

90 417

135 625

180 833

Page 7: MINIATURE ENGINEERING SYSTEMS GROUP: MINIATURE ENGINEERING SYSTEMS GROUP: COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION FOR LH2 VJ STORAGE

Cost of Pre-ChillingCost of Pre-Chilling::

Welded InvarWelded Invar::

Cost of pre-chilling per lb of Welded Invar: 310K80K 80K19K

LH2 Boil-off $0.339 $0.090RTBC $0.004 $0.019

Cost of pre-chilling Welded Invar over the complete range

(310K 19K):cost/lb of WI Savings

Boil-off $0.429 0 %310K to 80K by RTBC, rest by boil-off $0.094 78 %310K to 19K by RTBC $0.023 95 %

Page 8: MINIATURE ENGINEERING SYSTEMS GROUP: MINIATURE ENGINEERING SYSTEMS GROUP: COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION FOR LH2 VJ STORAGE

Cost savings in maintaining the system Cost savings in maintaining the system at LH2 temperature by RTBCat LH2 temperature by RTBC:

Considering 1 kW of heat leakage,

If LH2 is let to boil-off:

Rate of LH2 boil-off = 430 lb/day

Cost of LH2 boil-off = 860 $/day

If RTBC is used to prevent LH2 boil-off:

Number of RTBC required = 1

Total cost of input power for 1 RTBC = 180 $/day

The savings from complete boil-off to RTBC use for Pre-

Chill = (860-180)/860 ≈ 79 %

Page 9: MINIATURE ENGINEERING SYSTEMS GROUP: MINIATURE ENGINEERING SYSTEMS GROUP: COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION FOR LH2 VJ STORAGE

Input power required to maintain the Input power required to maintain the Storage Tank (Pad B) at LH2 Storage Tank (Pad B) at LH2

temperaturetemperature::

LH2 Boil - Off = m = 600 gallons/day = 355 lb/day, LH2 Boil - Off = m = 600 gallons/day = 355 lb/day,

Cost of LH2 Boil-Off = $ 260,000/yr, Cost of LH2 Boil-Off = $ 260,000/yr,

Input power required = P where,

P= m*L = (355*56)/24 = 830 W.

So, a nominal cooling power of about 1 kW at 19K would be appropriate.

Page 10: MINIATURE ENGINEERING SYSTEMS GROUP: MINIATURE ENGINEERING SYSTEMS GROUP: COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION FOR LH2 VJ STORAGE

Time required to pre-chill the storage tank to 19 K with Time required to pre-chill the storage tank to 19 K with 1 RTB = 770 hr,1 RTB = 770 hr,Cost of LH2 Boil-Off for Pre-Chill = $ 105,000Cost of LH2 Boil-Off for Pre-Chill = $ 105,000

Pre-Chilling of Storage TankPre-Chilling of Storage Tank::

Pre-Chilling of Transfer LinePre-Chilling of Transfer Line::

LH2 Boil-Off Cost = $ 17,000,LH2 Boil-Off Cost = $ 17,000,

Number of RTBCs required to pre-chill the transfer Number of RTBCs required to pre-chill the transfer line to 19K in 9 hrs, I.e., with both stages = 15 (1 for line to 19K in 9 hrs, I.e., with both stages = 15 (1 for every 100 feet of the transfer line),every 100 feet of the transfer line),

Number of RTBCs required to pre-chill the transfer Number of RTBCs required to pre-chill the transfer line to 80K in 9 hrs, I.e., if only the top stage is used line to 80K in 9 hrs, I.e., if only the top stage is used = 3 (1 for every 500 feet of the transfer line).= 3 (1 for every 500 feet of the transfer line).

Page 11: MINIATURE ENGINEERING SYSTEMS GROUP: MINIATURE ENGINEERING SYSTEMS GROUP: COST ANALYSIS OF PRE-CHILLING AND HEAT LEAKAGE DURING OPERATION FOR LH2 VJ STORAGE

Conclusion:Conclusion:

The calculation shows that it is economically effective to use cryo-coolers for cooling the Liquid Hydrogen Vacuum Jacket storage & transfer facilities at NASA KSC.

Please NOTE: This analysis considers only the running costs associated with the cryocoolers. It does not take into account the installation and maintenance costs associated with the cryocoolers.