View
623
Download
1
Embed Size (px)
Citation preview
1
1 Introduction
Nowadays, with the rapid development of technology and the increased in daily
consumption of people, the limited amount of resources in this world had been dropping
in a quick rate and this had put enormous pressure on the environment. As a result, a few
important criteria in designing new product for manufacturing had risen within this
decade and these included: quality and quantity of material used, energy input and carbon
footprint and the ease of assembly. These design criteria could be achieved by following
certain methodologies such as concurrent engineering (CE), computer simulation,
environmental conscious manufacturing (ECM), design for manufacturing (DFM)
material resources planning and lean manufacturing.
Drilling process was a common machining process in industry. When the location and
orientation of the hole machined by the drill needed to be accurate, a drill press was
usually required. A drill press was composed of a base that supported a column which in
turn supported a platform. The work can be supported on the platform with a vise or a
clamp. The height of the platform was adjustable and could also be secured at certain
position along the column by some means of fasteners. This platform was where the drill
was placed or clamped and it was connected with a handle where the operator could exert
a force in order to help the drilling process.
In this design project, a mechanical drill press was analyzed and redesigned in order to
reduce the waste of raw material, cost and energy input, impact on environment and
improve in the rate of assembly.
The requirement of this redesigned drill press was to be manufactured in a quantity of 30,
000 per annum.
2
2 Objectives
The objectives of this project was to improve the original design in terms of cost, energy
and material input, reduced amount of waste material, reduced environmental impact,
increased in assembly rate.
The followings were some of the main objectives of this project:
To analysis the original drill press design and investigate the basic functions and
problems relating to it.
To create or improve the design regarding to financial, social, risk and
environmental aspects.
To investigate the process of manufacturing a product in industry and make
comparisons between the original and new design with the aid of project
management skills.
Make use of the design principles: concurrent engineering, Design for
manufacturing and assembly, Material resource planning environmental conscious
manufacturing and lean manufacturing, etc to redesign the drill press.
3
3 Original drill press design (MK 1)
Table 3.1a: Different projections on original design
Top view
Front view
Side view
4
Detailed analysis was made on the original drill press design and the whole design was
disassembled and each component was analyzed and drawn using Computer simulation:
Solidworks Premium 2010. With the aid of computer simulation, this reduced the cost
and time of producing a prototype during redesigning process and ease of manufacturing
and assembly processes of the original design could be investigated in a much easier way.
Figure 3.1: Isometric view of the original drill press
Base
Handle
Shaft
C-shaped
(Top)
C-shaped
(Middle)
C-shaped
(Bottom)
Cage of roller Rectangular
clamp
Cylindrical
support
Cylinder
B
Cylinder
A
Cylinder
A
Threaded rod
(M8x200)
Drill
clamping bolt
(M10x75)
Hexagonal
Nut (M8)
5
Figure 3.2: Cage of roller connecting with handle
Figure 3.3: Base of the drill press
Figure 3.4: Clamping position of the hand drill
Roller
Washer
(M6)
Handle bolt
(M8x60)
Washer
(M10)
Base Bolt
(M10x16)
Drill clamping
bolt (M10x75)
Hexagonal nut
(M10)
Hexagonal Nut
(M6)
Roller spacer
Handle
spacer
2 screws
(M5x7.5)
6
Table 3.1: Bill of material of original design
Part
number Name of component
Quantity
of part
Volume of
material
(mm3)
Material type
Essential parts
1 Base 1 134673.38 Steel
2 Handle 1 68355.14 Steel
3 Shaft 1 150754.29 Steel
4 C-shaped part (Top) 1 51623.06 Steel
5 C-shaped part (Middle) 1 71158.40 Steel
6 C-shaped part (Bottom) 1 27039.44 Steel
7 Roller 1 2478.72 Steel
8 Cage of roller 1 10335.0 Steel
9 Rectangular clamp 1 36499.51 Steel
10 Cylindrical support 2 1229.23 Steel
11 Cylinder B 1 19738.70 Steel
Total number of essential parts 12
Non-essential parts
12 Cylinder A 2 8055.84 Brass
13 Washer (M6) 1 200.81 Steel
14 Washer (M10) 1 424.77 Steel
15 Threaded rod (M8x199) 1 6344.16 Carbon steel
16 Base bolt (M10x16-14) 1 2833.90 Carbon steel
17 Handle bolt (M8x60x23) 1 1391.95 Carbon steel
7
18 Drill clamping bolt
(M10x75x51.6) 1 4593.19 Carbon steel
19 Hexagonal nuts (M6) 1 348.92 Carbon steel
20 Hexagonal nuts (M8) 6 3718.08 Carbon steel
21 Hexagonal nuts (M10) 1 1546.51 Carbon steel
22 Cylindrical nut 1 3613.27 Steel
23 Cage of roller holding
screw (M5x8.5) 2 432.46 Steel
24 Roller spacer 1 585.28 Brass
25 Handle spacer 1 3613.27 Brass
Total number of non-essential parts 22
Total 34 625431.58
Design efficiency (%) 35.29
3.1 Essential basic functions analysis of the original design
Some of the essential basic features of the original design had to be kept constant
throughout the redesigning process. This could ensure the new design could at least
achieve the minimum required functions of this original product.
The Base of the drill press was to provide stability to the drill press; therefore, it has to be
heavy and its surface areas have to be large enough to achieve this function.
The shaft of the drill press could provide a sliding surface for the C-shaped parts to be
positioned at any required height.
There were two essential functions that had to be achieved by the C-shaped parts: one
was to clamp the hand drill and hold it in position and the other one was to measure the
depth of drill during the drilling operation.
The rectangular clamp provided a way to position the fulcrum point of the handle to
any required height along the shaft.
8
The handle provided a way for the user to exert a force on the C-shaped part which in
turn drove the hand drill into the workpiece.
The roller together with the cage of roller provided a smooth path of the handle to
follow when the user was exerting a force on the C-shaped part through the handle.
The Threaded roll together with the nuts (M8) could adjust the depth of the drilling on
the workpiece and this function had to be kept for the new design.
3.2 Problems with original design
In terms of assembly rate, welding was a manual process and it required a lot of time and
cost. As shown in Figure 3.1 below, the areas circled in red were the points where
welding was required. This showed that the C-shaped parts required a long time for
assembly and manufactured. The original drill press design consisted of many small and
different parts such as various size of nuts, bolt, washers and screw and this would
obviously affect the rate of assembly and not suitable for mass production. As shown in
Figure 3.5, the Threaded rod contained six nuts along its length and the order of
inserting the Rectangular clamp and the nuts on the Threaded rod had to be precise
and this would cause great difficulties to the workers doing the assembly and hence this
slowed down the assembly process. Apart from the Rectangular clamp, the overall
shape of the original design had sharp surface and edges. As it was unsafe for assembly
workers to work with parts with sharp edges, the Rectangular clamp had to be
redesigned.
9
Figure 3.1: Isometric view of the original
drill press
Figure 3.5: Threaded rod with nuts
3.3 Manufacturing process of Product
3.4 Justifications and limitations of data used
A brief explanation of the whole process of manufacturing for both original and new drill
press design would be discussed in the following sections. Starting from which type of
raw material, machining type, machining time, machining cost, labour cost and assembly
cost were explained in detail the following sections.
The total cost of the manufacturing a product included price for raw materials, wages for
the operator, equipment and tooling cost and the assembly cost.
Based on engineering assumptions and information researched, the price of raw material
was assumed based on its overall dimensions with the aid of machining estimator
(Custompart, 2010) online.
10
The time for each machining operation for each component included setting up,
positioning the parts on the machine, operation, collecting the machined parts and
transferring the parts to different machining process. The time for setting up the machine
and the transferring process was assumed to be negligible. The cost of machining process
included electricity for equipments and tooling cost and because of insufficient data
relating to the energy and cost consumed by each tools and equipments, only an average
value for each machining process could be assumed based on engineering knowledge and
knowledge from Industry Technology 343. A detail of expenses such as the overhead
within a factory, tooling costs such as cost of a cutting tools and its tool life, cost of a die
and a mold and the energy consumption for each equipment per annum, etc could not be
provided precisely in this report. In a real Part-manufacturing company, each of them
would have their own catalogue regarding to the cost for different machining process and
the equipment and so the data assumed in calculations in the following sections might be
far from the actual data in industry areas but it could act as a correct guide for the reader
on how to analysis a design.
The time for assembling the part was calculated based on Boothroyd-Dewhurst Method
(Tim, 2010) where relating tables were shown in the Appendix section.
The salary for the operator was based on a normal wage statistic (Migrationexpert, 2010)
in Western Australia as shown in the Appendix and the hourly pay rate for each operator
was AUD 26.12 per hour. The labor cost was calculated by multiplying the total amount
of time the operator spent on the machining process to the salary rate per minutes.
11
3.5 Machining process of each parts of the original design (Mark 1)
The following table showed all the required machining process for the manufacturing of
the original drill press.
Table 3.5.1: Total number and cost of machining process required in the original design
Number Source of cost Cost (AUD/ min)
1 Press brake forming 0.083
2 Punch press forming 0.083
3 CNC machining 0.3
4 Cold sawing 0.1
5 Lathe turning 0.1
6 Lathe drilling 0.1
7 Welding 0.13
8 Belt grinding 0.05
9 Labour cost 0.435
Table 3.5.2a: Schematic diagram of stock material required for original design
Flat sheet
Rectangular bar
Round bar
Round tube
12
Table 3.5.2b: Total cost and amount of stock material needed for unit product
Workpiece Material type Density
(kg/m3)
Dimensions
(mm) Cost (AUD)
Flat sheet Steel-medium
carbon (1040) 7830.00
300x280x2 0.93
440x40x5 0.53
200x70x3 0.24
190x35x3 0.45
150x70x4 0.25
Round bar
Steel-medium
carbon (1040) 7830.00
=20; L=480 0.94
=20; L=26 0.05
=40; L=20 0.31
=16; L=25 0.04
=13; L=11 0.04
=16; L=30 0.16
Brass alloy:360 8500.00 =31; L=25 0.63
Round tube Steel-medium
carbon (1040) 7830.00
=13; T=7;
L=7.5 0.15
Rectangular bar Steel-medium
carbon (1040) 7830.00
32x15x40 0.12
71x40x16 0.28
Total 5.12
13
Table 3.5.3: Manufacturing cost and time for Part 1
Base
Raw material Flat sheet Density
(kg/m3)
Stock
dimensions
(mm)
Price(AUD/kg) Cost (AUD)
Steel-
medium
carbon
(1040)
7830.00 300x280x2 0.79 0.93
Labour 2.82
Machining
Process Time
Punch press
forming 15.00sec 0.02
CNC
Machining 5.00 mins 1.50
Press brake
forming 15.00 sec 0.02
Welding 1.00 min 0.13
Total 6.30min 5.42
Note: Table 3.5.3 was shown as a sample of calculations, all the machining cost and time
for the remaining parts of the original design could be found from the Appendix section.
14
Fasteners of the assembly could be purchased instead of machining, the following table
showed all the required fasteners for the original design.
Table 3.5.15: Specifications of fasteners used in the original design (Boltsnutscrewonline,
2009)
Part Fasteners Designation Quantity Material Price
(AUD)
11 Split washer M6 1 Steel 0.04
12 Washer M10 1 Steel 0.11
13 Threaded rod M8x199 1 High tensile
steel 0.93
14 Base bolt M10x16 1 High tensile
steel 0.10
15 Handle bolt M8x60 1 High tensile
steel 0.38
16 Drill
clamping bolt M10x75 1
High tensile
steel 0.53
17 Hexagonal
nuts M6 1
Galvanized
steel 0.04
18 Hexagonal
nuts M8 6
Galvanized
steel 0.42
19 Hexagonal
nuts M10 1
Galvanized
steel 0.1
21 Screw M5x9.5 2 steel 0.4
Total 16 3.1
15
3.5.1 Analysis of assembly time of the original design
By using Boothroyd-Dewhurst DFA method and the relating Tables shown in Appendix
section, the total assembly time of the original design was shown in the following table.
The whole assembly process was visualised in the Appendix section.
Table 3.5.1.1: Assembly cost and time of original design
Process
number
Part
combination
Handling
code
Handling
time
(sec)
Insertion
code
Insertion
time
(sec)
Total
time
(sec)
1 Base +
Shaft 10 1.5 01 2.5 4
2
Base bolt +
Washer
(M10)
13 2.06 00 1.5 3.56
3
Bolt &
washer +
Shaft
10 1.5 01 2.5 4
4
C-Shaped +
Cylinder A
x2
12 2.25 01 2.5 9.5
5 C-shaped +
Shaft 10 1.5 03 3.5 5
6
Rectangular
clamp +
Shaft
11 1.8 00 1.5 3.3
7
Threaded
rod + C-
shaped (Top
and bottom)
00 1.5 01 2.5 4x2
=8
8
Threaded
rod +
Rectangular
clamp
00 1.5 00 1.5 3
16
9
Threaded
rod +
6 nuts (M8)
00 1.5 11 5 6.5x6
=39
10
Drill
clamping
bolt +
C-shaped
10 1.5 00 1.5 3
11
Drill
clamping
bolt +
2 nuts (M10)
00 1.5 01 2.5 4x2
=8
12
Drill clamp
bolt +
Cylindrical
nut
11 1.8 01 2.5 3.3
13
Cage of
roller +
2 screw
(M5)
11 1.8 11 5 6.8x2
=13.6
14
2 screw
(M5) +
C-shaped
32 2.7 08 6.5 9.2
15 Roller +
Roller spacer 01 1.5 00 1.5 3
16
Roller &
Roller spacer
+
Cage of
roller
11 1.8 00 1.5 3.3
17
Handle
spacer +
Handle
31 2.25 00 1.5 3.75
18 Handle +
Roller 30 1.95 00 1.5 3.45
19
Spilt washer
(M6) +
Roller
13 2.06 00 1.5 3.56
17
20 Roller +
Nuts (M6) 10 1.5 00 1.5 3
21
Handle Bolt
(M8x60) +
Handle
spacer
30 1.95 01 2.5 4.45
22
Handle Bolt
(Mx60) +
Rectangular
clamp
30 1.95 01 2.5 4.45
Total assembly time 145.42
Total assembly cost for worker (AUD) 1.05
18
Table 3.4: Summary of manufacturing process of original design
Environmental aspect
Total volume of material on the design (mm3) 625431.58
Total usage of stock material (mm3) 874863.69
Volume of material on the design without
fasteners (mm3) 606600.41
Total volume of wasted material (mm3) 268263.28
Percentage of waste (%) 30.66
Financial aspect
Total time of machining process (min) 46.41
Total assembly time (min) 2.42
Total time (min) 48.63
Total cost of raw material (AUD) 5.12
Total wage for operators (AUD) 22.02
Total cost of machining process 10.86
Total cost of fasteners (AUD) 3.10
Total assembly cost (AUD) 1.05
Total cost (AUD) 42.15
19
4 New drill press design (MK 2)
Table 4.1a: Different projections on new design
Top view
Front view
Side view
20
Figure 4.1b: Isometric view of the new drill press
Handle
Base
Cylinder
Shaft
T-shaped clamp
Spring
Threaded rod
M8x200
C-shaped
Handle
Hexagonal nut (M8)
21
Figure 4.2: ABS clip opened
Figure 4.3: C-shaped connected with handle
Figure 4.4: Base of the drill press
Handle bolt
(M8x40)
ABS clip
Hinge pin
Socket head
screw (M8x15)
Hinge pin head
Hexagonal nut
(M8)
Base washer
(M8)
Base Bolt
(M8x16)
22
Table 4.1: Bill of material of new design
Part
number Name of component
Quantity
of part
Volume of
material
(mm3)
Material
Essential parts
1 Base 1 134673.38 Recycled steel
2 Handle 1 28893.83 Recycled steel
3 Shaft 1 150754.29 Recycled steel
4 C-shaped 1 117262.67 Recycled aluminum
5 Spring 1 29145.19 Recycled steel
6 Cylinder 1 19738.70 Recycled steel
7 ABS clip 1 6954.13 Thermoplastic
8 Socket head (M8x15) 1 1978.12 Steel
9 T-shaped clamp 1 24623.14 Recycled brass
10 Hinge pin 1 82.79 Steel
Total number of essential parts 10
Non-essential parts
11 Base bolt (M8x16) 1 2275.63 Steel
12 Base washer (M8) 1 1656.40 Steel
13 Threaded rod (M8x200) 1 6344.16 Steel
14 Handle bolt (M8x40) 1 2770.99 Steel
15 Hexagonal nut (M8) 3 2770.99 Steel
16 Hinge pin head 1 17.28 Steel
Total number of non-essential parts 8
Total 18 529746.21
Design efficiency (%) 55.55
23
4.1 Machining process of each parts of the new design (Mark 2)
The following table showed all the required machining process for the manufacturing of
the new drill press.
Table 4.1.1: Total number and cost of machining process required in the new design
Number Source of cost Cost (AUD/ min)
1 Press brake forming 0.083
2 Punch press forming 0.083
3 CNC machining 0.3
4 Cold sawing 0.1
5 Lathe turning 0.1
6 Lathe drilling 0.1
7 Lathe milling 0.1
8 Permanent mold casting 0.2
9 Thermoforming 0.1
10 Welding 0.13
10 Labour cost 0.435
Table 4.1.2: Schematic diagram of stock material required for new design
Flat sheet
Rectangular bar
Round bar
Round tube
24
Table 4.1.3: Required cost and amount of stock material needed for unit product for new
design
Workpiece Material type Density
(kg/m3)
Dimensions
(mm) Cost (AUD)
Flat sheet
Recycled steel-
medium carbon
(1040)
7830.00
300x280x2 0.93
305x22.5x5 0.20
Acrylonitrile
Butadiene
Styrene
1100.00 63x22.5x5 0.02
Round bar Recycled steel-
medium carbon
(1040)
7830.00 =20; L=480 0.94
Round tube Recycled steel-
medium carbon
(1040)
7830.00
=40; T=10;
L=21 0.12
Rectangular bar Recycled brass
alloy: 360 8500.00
40x60x22.5 1.43
Total 3.64
25
Table 4.1.4: Manufacturing cost and time for Part 4
C-shaped
Raw material Flat sheet Density
(kg/m3)
Stock
volume
(mm3)
Price(AUD/kg) Cost (AUD)
Recycled
Aluminium
356.0 T7
2679.00 117223.77 2.09 0.66
Labour 2.17
Envelope (X×Y×Z) (mm) 160×250×26
Projected area (mm2) 9045
Tooling Permanent mold 0.67
Production Time
Casting 5.00 min 1.00
CNC
Machining 1 min 0.3
Total 5.00 min 4.50
Note: Table 4.1.4 was shown as a sample of calculations, all the machining cost and time
for the remaining parts of the new design could be found from the Appendix section.
The material cost included the cost of the metal in current market. These costs were
estimated from the part geometry and use up-to-date material prices. The production cost
included the cost of melting the metal, making the molds and cores, pouring the metal,
and removing and cleaning the castings. The production and labor rates for these
operations were assumed as the same as other machining process. For the tooling cost,
the cost of both the pattern and the core-boxes were estimated in a variety of materials,
and the optimal choice was provided.
26
Fasteners used in the assembly could be purchased instead of machining, the following
table showed all the required fasteners for the new design.
Table 4.1.11: Specifications of fasteners used in the new design (Boltsnutscrewonline,
2009)
Part Fasteners Designation Quantity Material Price
(AUD)
8 Socket head M8x15 1 High tensile
steel 0.15
10 Hinge pin M2 1 Steel 0.1
11 Base bolt M8x16 1 High tensile
steel 0.14
12 Base washer M8 1 Steel 0.1
13 Threaded rod M8x200 1 High tensile
steel 0.93
14 Handle bolt M8x40 1 High tensile
steel 0.2
15 Hexagonal
nut M8 3
High tensile
steel 0.3
16 Hinge pin
head - 1 Steel 0.1
Total 10 2.02
Spring used in the assembly could be purchased instead of machining, the following table
showed specifications of the spring used in the new design.
Table 4.1.12: Specifications of the spring used in new design (Ashfield spring, 2010)
Material Carbon steel
Outer diameter (mm) 35
Inner diameter (mm) 20
Wire diameter (mm) 7.5
Free length (mm) 100
Solid height (mm) 42.5
Spring rate (N/mm) 3.63
Price (AUD) 2.87
27
4.1.1 Analysis of assembly time of the new design
By using Boothroyd-Dewhurst DFA method and the relating Tables shown in Appendix
section, the total assembly time of the new design was shown in the following table. The
whole assembly process was visualised in the Appendix section.
Table 4.1.1.1: Assembly cost and time of the new design
Process
number
Part
combination
Handling
code
Handling
time
(sec)
Insertion
code
Insertion
time
(sec)
Total
time
(sec)
1 Base + Shaft 10 01 1.5 2.5 4
2
Base bolt +
Washer
(M8)
13 2.06 00 1.5 3.56
3
Base bolt &
Washer +
Shaft
10 1.5 01 2.5 4
4 C-shaped +
Shaft 00 1.5 01 2.5
4x2
=8
5
T-shaped
clamp +
Shaft
00 1.5 00 1.5 3
6 Spring +
Shaft 00 1.5 00 1.5 3
7 Hinge pin +
ABS Clip 03 2.18 00 1.5 3.68
8 Hinge pin +
C-shaped 03 2.18 00 1.5 3.68
28
9
Hinge pin +
Hinge pin
head
03 2.18 00 1.5 3.68
10
Threaded
rod
(M8x200) +
Hexagonal
nut (M8) x2
00 1.5 01 2.5 4x2
=8
11
Threaded
rod
(M8x200) +
C-shaped
00 1.5 00 1.5 3
12
Socket head
(M8x15) +
Handle
31 2.25 00 1.5 3.75
13
Socket head
(M8x15) +
C-shaped
31 2.25 01 2.5 4.75
14
Handle bolt
(M8x40) +
T-shaped
30 1.95 01 2.5 4.45
15
Handle +
Handle bolt
(M8x40)
30 1.95 00 1.5 3.45
16
Handle bolt
(M8x40) +
Hexagonal
nut (M8)
30 1.95 01 2.5 4.45
Total assembly time 68.45
Total assembly cost for worker (AUD) 0.49
29
Table 4.2: Summary of manufacturing process of new design
Environmental aspect
Total volume of material on the design (mm3) 529746.21
Total usage of stock material (mm3) 551212.24
Volume of material on the design without
fasteners and spring (mm3) 482900.14
Total volume of wasted material (mm3) 68312.10
Percentage of waste (%) 12.39
Financial aspect
Total time of machining process (min) 30.10
Total assembly time (min) 1.14
Total time (min) 31.24
Total cost of raw material (AUD) 4.30
Total wage for operators (AUD) 12.68
Total cost of machining process 6.70
Total cost of fasteners & spring (AUD) 4.89
Total assembly cost (AUD) 0.47
Total cost (AUD) 30.06
30
5 Discussion
5.1 Comparison and analysis between old design (Mark 1) and new
design (Mark 2)
5.1.1 Discussion and explanation on new Handle design
The material used, thickness and the overall dimensions of the new handle did vary a lot
from the old design. A new slot was created on the new handle so that a M6 socket head
screw connecting to the C-shaped could slide along in it. This design eliminated the
needed of extra parts in the old design such as the Roller, Cage of roller and the Roller
spacer. The machining time for this new design was longer than the old one because of its
increased in number of bends required but in return this design improved the ease of
assembly which in turn reduced the assembly time. The number of parts in the whole
assembly were reduced, thus the cost and time for manufacturing were reduced. Less
material waste was resulted and the impact on environment could be reduced.
Table 5.1.1.1: Comparison of specifications between old and new handle design
Old New
Material type Steel-medium carbon
(1040)
Recycled steel-medium
carbon (1040)
Stock dimension (mm) 440x40x5 305x22.5x5
Actual volume of material
on part (mm3) 68355.14 28893.83
Waste of material (%) 22.32 15.79
Machining time (min) 3.5 4
Cost (AUD) 2.99 2.9
31
Side view Side view
Top view Top view
Figure 5.1.1.1a: Old Handle design Figure 5.1.1.1b: New Handle design
5.1.2 Discussion and explanation on new C-shaped design
5.1.2.1 C-shaped
The old design of C-shaped required a lot of welding process and because the geometry
of this design, automated welding was not possible. Welding was a manual process which
required a lot of time and cost. It was unsuitable for mass production of product.
In the new design, permanent mold casting was used to manufacture this part. A
permanent mold needed to be created at the beginning of the casting process.
Characteristics of permanent mold casting process could be found in Section 8.7 in
Appendix. A permanent mold typical cost about AUD 20,000 (Kruse, 2006) which when
divided by the number of part required (30,000) would result in about AUD 0.67 per part.
This permanent mold would be considered as a high tooling cost only if quantity of part
was low. For this project, the required quantity of part was 30,000 parts per annum and
this could be reason to justify the use of a permanent mold. Permanent mold casting was
suitable for aluminum and it had low to moderate tooling lead time, casting lead time,
casting cost and finishing cost (Kruse, 2006). The cost material that used create internal
structure of the product was grey iron. The advantages of permanent mold casting were
32
good surface finished and tolerance of product and high production rate. The main
disadvantage of permanent mold casting was high equipment and tooling cost for low
quantity of production. By using this kind of casting method, this reduced the number of
the parts of the design, increased in rate of assembly, reduced in wastage material and the
energy input for the overall process. Together with the fact that 30,000 product needed to
be manufactured per annum, these factors could be the reasons to justify the use of this
high tooling-cost casting method.
Because of the difference in manufacturing process, the new C-shaped could be
manufactured in one piece instead of having 3 sheets of metal plated welded manually
together and 2 brass cylinder inserted manually. This resulted in a great decreased in
assembly time and wastage of material. Since casting was used, all the scrap material
could be collected and melted. This recycled all the wastage material, hence keeping the
waste of material to minimum level. Since the assembly time and material usage were
reduced, this resulted in a decrease in cost of each part.
The casting process was briefly explained as followings: the machining time shown in
Table 4.1.4 only included the casting period. This was because workers from one shift
would be responsible for pouring the molten metal into the mold and worker from
another shift would be responsible for collecting the cast and performed secondary finish
and machining processes. The cooling period of casting was not considered since after all
the required amount of molten metal was poured, the workers could move on and worked
on another parts of the product. This could result in a decrease in labor cost as well.
The material for the C-shaped was recycled aluminum while the material for the shaft
was recycled steel. As the C-shaped had to slide along the shaft; therefore two different
materials had to be used for these two parts or else the C-shaped could be worn out easily.
Since in the input material for the C-shaped was recycled aluminum; therefore, even after
the C-shaped finally worn out and needed replacement, the C-shaped could be sent to
recycling plant and this would not create any impact on the environment.
5.1.2.2 ABS clip
As shown in Figure 6.1.2.1b, a clip made of ABS (Acrylonitrile Butadiene Styrene) was
introduced to the new design. In the old design, a Drill clamping bolt together with the C-
33
shaped were required to hold the hand drill in position. By introducing this clip design,
this eliminated unnecessary parts, thus increasing assembly time and reduced material
used. Also, by using this integrated clip design, this reduced the use of an extra fastener.
The clip design could be opened and closed like a door hinge depending on the need of
the user. The clip of ABS which was made up of thermoplastic which was recyclable
which meant that at the end of product lifetime, this ABS material could be recycled
again. This reduced the impact on environment. Since ABS was a kind of thermoplastic,
it possessed certain amount of flexibility and good wear resistance compared to steel. It
had a Young’s modulus value 2x109 Pa comparing to the Young’s modulus of steel
which was 2.04x1011 Pa, this ABS clip was considered as strong enough for its
application.
The size of the ABS clip was designed to fit a hand drill of diameter of 20 mm with ±2
mm flexibility. This ensured that the current type of hand drill fitting on the original
design could be fixed on the new design as well. This ensured that basic essential
function of the drill press was kept constant.
The process required for manufacturing thermoplastic was pressure forming of
thermoforming. The starting raw material was a thermoplastic sheet. The advantages of
thermoforming were high production rate and low cost while its disadvantages were the
limited complexity of the design and trimming was required (Custompart, 2010). Since
the geometry of the clip was very simple, this disadvantage did not really affect the
design.
Table 5.1.2.1: Comparison of specifications between old and new C-shaped design
Old New
Material type Steel-medium carbon
(1040)
Recycled aluminium 356.0
T7
Total amount of raw
material needed (mm3) 200102.09 124316.87
Waste of material (%) 15.38 1-2
Machining time (min) 14.18 7.10
Cost (AUD) 13.82 5.24
34
Side view Side view
Top view Top view
Hand drill clamping postion Hand drill clamping clip
Figure 5.1.2.1a: Old C-shaped design Figure 5.1.2.1b: New C-shaped design
35
5.1.3 Discussion and explanation on new T-shaped clamp design
The functionality of the new T-shaped clamp remained the same as the old Rectangular
clamp design which was to provide a fulcrum point for the Handle to rotate. The main
difference was that all the sharp edged corners were changed to smooth fillet surfaces.
This increased the percentage of wastage material to 54.40 % which was not very
environmental friendly. However, sharp edges were considered stress raisers and would
increase stress concentration. Also, the sharp edges were unsafe for workers who were
responsible for assembly process. But the overall material needed for this part was
reduced compared to the old design. The scrap material could be collected after the
machining process and recycled for other purposes.
Table 5.1.3.1: Comparison of specifications between old and new clamp design
Old New
Material type Steel-medium carbon
(1040) Recycled Brass alloy: 360
Stock dimension (mm) 71x40x16 40x60x22.5
Actual volume of material
on part (mm3) 36499.51 24623.14
Waste of material (%) 19.67 54.40
Machining time (min) 8.10 8.10
Cost (AUD) 6.25 8.87
Top view
Top view
36
Side view
Side view
Figure 5.1.3.1a: Old rectangular clamp
design Figure 5.1.3.2b: New T-shaped design
5.2 Facts comparison between new drill press (Mark 2) and old drill
press (Mark 1)
By analyzing the data shown in the Table 3.4 and Table 4.2, it could be observed that the
total amount of time required for manufacturing the new design dropped from 48.63 min
to 31.24 min and the cost dropped from AUD 42.15 to AUD 30.06. The main reason for
this was because of the decreased in number of parts of the whole assembly. The old
design possessed 34 individual parts while the new design only had 18 parts. The design
efficiency between old and new design improved from 35.29% to 55.55%. The reason for
that was because a lot of unnecessary parts were eliminated or combined into a single
part. This simplicity of the new design had a great impact on the rate of assembly. The
new assembly time was 1.14 min while the old design required 2.42 min.
A lot of environmental friendly materials were introduced to the new design. The new
design made use of a lot of recycled material and thermoplastic which both processed less
carbon footprint and this resulted in less harmful effect on the environment. As shown in
Table 3.4 and Table 4.2, the wastage material between the old and new design dropped
from 30.66% to 12.39%. The reason for this was that apart from traditional machining
processes, permanent mold casting and thermoforming were also used. These processes
might have a higher tooling and equipment cost but in return the raw materials could be
utilized as much as possible. For example, the scrap material resulted from CNC
machining could melted into molten metal again and used in casting process. The total
volume of material used in the old design was 625431.58 mm3 while the one for new
design was 529746.21 mm3. The decreased in amount of material used was 15.29% thus
37
less material was required for manufacturing the product. This reduced the extraction of
virgin material from the environment.
The machining cost between old and new design dropped from AUD 10.86 to AUD 6.70.
The machining cost represented the energy input such as electricity of equipment and
tooling cost. This 38.31% reduction in cost showed that the energy input for
manufacturing the new design was lower than the old design.
The only cost item that increased compared to the old design was the cost for fasteners
and spring. This was because a spring was introduced to the new design which the old
design did not have. Because of the present of this new spring, a lot of unnecessary
fasteners in the old design were eliminated. Apart from the spring, total number of
fasteners between the old and new design dropped from 16 to 10 and this improved the
ease of assembly.
5.3 Functions comparison between new drill press (Mark 2) and old
drill press (Mark 1)
First, the base of the new drill press remained unchanged. The base of the original drill
press was considered as a footprint and provided stability for the drill press. Since the
base remained unchanged, it could be ensured that the stability of the new design must be
as good as the old one. As the base remained unchanged it became the only part and
locations of the whole assembly that required welding process. Comparing this fact with
the old design which required a lot of more locations of welding, this could increase the
rate of assembly and cost input for the new design.
The shaft of the new drill press remained unchanged and its function was still to provide
sliding movement for the C-shaped along itself.
The C-shaped from the new design was responsible for clamping the hand drill with its
new introduced clip and the Threaded rod and the nuts (M8) were also kept in place in
order to measure the depth of the drill similar as the old design. Therefore, these two
essential original functions could also be achieved by the new design as well. Other than
that, a new Spring part was introduced to provide an extra recoil force to help the user to
38
pull back the drill from the workpiece. This was considered as a new function from the
new design.
The rectangular clamp was modified into a T-shaped clamp with a smoother surface to
reduce stress concentration and improved in safety for assembly workers. Its function
remained the same which was to provide a fulcrum point for the handle to rotate.
The handle for the new design was still to provide a mean for the user to exert a force to
assist the drilling process. But in the new design, instead of using several parts such as
roller, cage of roller and the roller spacer, a M8 socket was used and it could slide along
the slot created on the handle. This could reduce the number of parts for the new
assembly.
Figure 5.3a: Old drill press design Figure 5.3b: New drill press design
39
5.4 Functionality of the new Spring part
The primary function of the new Spring was to support and keep C-shaped and the T-
shaped clamp apart before the start of any drilling operation. It provided a recoil action to
help the user to withdraw the drill from the workpiece. The total available depth of drill
of the old design was about 140 mm and this had been considered in the new design also.
This could be done by taking the thickness of the T-shaped clamp and the compressed
length of the Spring itself into account and worked out the lengthof overall height of the
C-shaped.
The Spring specifications were shown in Table 4.1.12 and the spring rate which was
usually known as spring stiffness was calculated by assuming a normal hand drill
weighting at 1.5 kg together with the weight of the C-shaped acting on the spring. Full
calculation was shown in Appendix section. Results showed that by having a spring rate
of 3.63 N/mm and a deflection of 5 mm, this Spring would have enough force to support
the whole structure without any external help. Hence, by knowing all of its specifications,
the spring could be purchased from online supplier (Ashfield spring, 2010).
Figure 5.3.1a: Default length position of
the spring
Figure 5.3.1b: Compressed length position
of the spring
40
5.5 Design Methodology
5.6 Concurrent Engineering
The redesigning process of the drill press was mainly based on the strategies from
concurrent engineering. Feedbacks and comments needed to be collected between design,
manufacturing and product use.
The factors considered during the redesigning process included aesthetic factor, product
performance factors, safety considerations for both workers and customers, maintenance
considerations, quantity needed to be produced, product life, the working environment of
this product and the weight and complexity of the product.
For example, by inspecting the old design, a lot of problems such as too many welding
procedures were required, too many fasteners with different sizes, number of parts and
sharp edges were found. The parts from old design had difficulties in manufacturing. By
getting feedback from manufacturing areas, the product specifications could be
redesigned according to the ease and the selection of manufacturing process. New
concepts and detail design could be proposed in order to improve the ease manufacturing
process. Better selection of material could also be achieved by looking at the impact of
the product on the environment. The benefits resulted from the use of principal of
concurrent engineering were reduced in assembly time (from 2.42 min to 1.14 min),
decreased in production cost (AUD 42.16 to AUD 30.06), reduced in wastage material
(30.66 % to 12.39 %) and reduced in number of parts (34 to 18).
5.7 Design for manufacturing (DFM)
The design cycle for this new drill press included conceptual design, detail design,
manufacturing and product support. In conceptual design, analysis was made on the old
design such as value analysis and functional analysis. Problems such as sharp edges,
excessive use of fasteners and complexity in assembly and manufacturing process were
identified. In detail design was where lists of required raw material was made, selection
of environmental friendly material and manufacturing process was carried out and detail
drawings using computer simulations was created. Finally, in manufacturing stage,
41
production planning strategies such as lean manufacturing and material requirement
planning was made to reduce cost and inventories.
5.7.1 Design for assembly (DFA)
A large number of parts were cut down from the old design, the number of part dropped
from 34 to 18. This reduction in number of parts greatly decreased the assembly time.
Also welding was a manual process and it required skilled worker so the number to
welding process was restricted only for the manufacture of the base of the new drill press.
This reduced a great amount of assembly time.
All the parts such as C-shaped and T-shaped clamp were designed to have a symmetric
shape and smooth surface and easy to handle so that it would be easily for workers to
assembly them since the direction of insertion of parts would be the same in any
directions if it was symmetrical.
Integrated clip was introduced instead of fasteners for the clamping area for the hand drill.
The number of fasteners used in the new design was 10 while the one for the old design
was 16. The new drill press was designed to have less fasteners and this improved the
ease of assembly. Also, the variation of fastener size of the new design was less than the
old one. Less bolt, screws and nuts were used and the sizes only consisted of M6 and M8
for the new design. This would help the workers to easily locate the required size
fasteners during assembly.
The new C-shaped was considered to be the most important part of the whole design as it
was responsible for clamping the hand drill and pushed it into the workpiece. The weight
of the C-shaped dropped from 1.33 kg to 0.3 kg between the old design and new design.
This was because of the use of lighter material, Aluminum; therefore, it would be easier
for the worker to handle a light part than heavier one during assembly process.
42
5.8 Environmental conscious manufacturing (ECM)
5.8.1 Design for environment (DFE)
All the source of raw material used was chosen to be with recyclable content such as
recycled aluminum, recycled steel, recycled brass and thermoplastic. Starting with virgin
material with recyclable content greatly reduced the impact on environment since
extraction of new natural resources was unnecessary. By using product lifecycle
assessment on the new design, all the material used on the new design could be recycled.
Wastage material could be greatly reduced and a “cradle to cradle” product lifespan for
each parts of the new design could be achieved.
The new machining process introduced to the new design compared to that of the old one
was permanent mold casting and thermoforming. Even though the initial cost for
permanent mold casting was high, this could be justified for fact of mass production.
Because of casting process, all the scraps metal that lost in the machining processes could
be collected, melted and reused again. This helped to reduce a great amount of waste
material. By introducing the new material type, thermoplastic which was recycled
compared to thermosets, no matter it was for maintenance, repair or recycle at the end of
its product life, this was a environmental friendly material which would not bring any
harmful effect on the nature.
With the help of Design of environment strategy, the percentage of wastage of material
dropped from 30.66 % to 12.39 %.
5.9 Material requirement planning (MRP)
By using material requirement planning principal, a list bill of material (BOM) as shown
in Table 4.1 and Table 4.1.3 were created for new design. These bills of material helped
to plan and control the acquisition of materials and the process of production. All the
required amount of stock regarding to their size, quantity and their type of material were
planned before any ordering of material started. This helped to control the waste of
material and kept the inventories level to a minimum level.
43
5.9.1 Lean production
For most production operations, only a small fraction of the total time and effort actually
added value in the product for the customer. By eliminating this usefulness energy and
cost input during manufacturing process, a large amount of saving could be achieved and
impact on environment could be reduced as well. The main benefits of using lean
manufacturing process was to save labor, cost, inventory and time. A large amount of
wastage material could be reduced and the speed of the operation could be increased as
well.
By implementing lean manufacturing strategy for the manufacturing of the production of
new design, several areas were improved:
A pull production system would be used. Only the required quantity of virgin material
depending on the orders from customers would be ordered and processed into products.
Unnecessary raw material or parts would not be produced and also when a part moved to
a production operation, was processed immediately, and move immediately to the next
operation. This ensured that the build-up of stock inventories was maintained to
minimum or zero in the warehouse.
As a pull production reduced inventories, equipment breakdowns could be reduced as
well. Properly trained operators were assigned primary responsibility for basic
maintenance since they were in the best position to detect signs of malfunction of the
equipment.
Machining processes and transportation on raw material were restricted or minimized to
essential ones only, this ensured that there would not be any time delays, delay in
material handling, idle time or unnecessary handling on parts.
By applying appropriate training on workers, they could participate in housekeeping,
quality inspection, minor equipment repair, rework, trouble shooting and problem solving
to improve quality and eliminate wastes. Since the quantity of production was in small
batch, faulty products could be found easier. As a result, better quality of products could
be produced (Free-business e-coach, 2010).
44
By applying lean manufacturing strategy, there were several benefits that could be
achieved:
Waste reduction by 80%
Production cost reduction by 50%
Manufacturing cycle times decreased by 50%
Labor reduction by 50% while maintaining or increasing throughput
Inventory reduction by 80% while increasing customer service levels
Capacity in current facilities increase by 50%
Higher quality
Improved cash flow through increasing shipping and billing frequencies
6 Conclusion
In conclusion, a drill press was redesigned successfully with the help of different design
methodologies such as concurrent engineering, design for manufacturing, environmental
conscious manufacturing, design for assembly, lean manufacturing and computer
simulation process. The results from using these methodologies were increased in
assembly rate, reduced in usage of material and wastage material and reduced in energy
and cost input. Therefore, the new design was suitable for a mass production with
quantity of 30,000 per annum.
45
7 Reference list
1. Ashfield spring, 2010. Compression spring. http://www.ashfield-
springs.com/index.html (Assessed 29th October, 2010)
2. Boltsnutscrewonline, 2009. http://www.boltsnutsscrewsonline.com/ (Assessed
29th October, 2010)
3. Custompart, 2010. Machining cost estimator.
http://www.custompartnet.com/estimate/machining/ (Assessed 29th October, 2010)
4. Free-business e-coach, 2010. Lean production.
http://www.1000ventures.com/business_guide/lean_production_main.html
(Assessed 29th October, 2010)
5. Kruse, S. 2006. Engineered casting solution.
http://www.metalcastingdesign.com/images/stories/castingbasics/processes/selecti
ngaprocess.pdf (Assessed 29th October, 2010)
6. Migrationexpert, 2010. Australian working condition and wage.
http://www.migrationexpert.com/australia/visa/australian_working_conditions_an
d_wages.asp (Assessed 29th October, 2010)
7. Tim, S. 2010. Lecture 3: Design for Assembly/Disassembly.
http://wiki.mech.uwa.edu.au/upload/3/38/MECH4403_Lecture_3_DFA.pdf
(Assessed 29th October, 2010)
8 Appendix
46
8.1 Tables
Figure 8.1.1: Manual handling code for assembly process (Tim, 2010)
Figure 8.1.2: Insertion code for assembly process (Tim, 2010)
8.2 Machining cost of each part of the original design
47
Table 3.5.4: Manufacturing cost and time for Part 2
Handle
Raw material Flat sheet Density
(kg/m3)
Stock
dimensions
(mm)
Price(AUD/kg) Cost (AUD)
Steel-
medium
carbon
(1040)
7830.00 440x40x5 0.79 0.53
Labour 1.52
Machining
Process Time
Punch press
forming 15.00sec 0.02
CNC
Machining 3.00 mins 0.9
Press brake
forming 15.00 sec 0.02
Total 3.30 min 2.99
Table 3.5.5: Manufacturing cost and time for Part 3
Shaft
Raw material Round bar Density
(kg/m3)
Stock
dimensions
(mm)
Price(/kg) Cost (AUD)
Steel-
medium
carbon
(1040)
7830.000 20 ;L=480 0.79 0.940
Labour 0.910
Machining
Process Time
Cold sawing 5.000 sec 0.008
Lathe turning 2.000 mins 0.200
Total 2.050 min 2.058
Table 3.5.6a: Manufacturing cost and time for Part 4
C-shaped part (Top)
48
Raw material Flat sheet Density
(kg/m3)
Stock
dimensions
(mm)
Price(/kg) Cost (AUD)
Steel-
medium
carbon
(1040)
7830.00 200x70x3 0.79 0.24
Labour 1.52
Machining
Process Time
Punch press
forming 15.00sec 0.02
CNC
Machining 3.00 mins 1.50
Press brake
forming 15.00 sec 0.02
Total 3.30 min 3.30
Table 3.5.6b: Manufacturing cost and time for Part 5
C-shaped part (Middle)
Raw material Flat sheet Density
(kg/m3)
Stock
dimensions
(mm)
Price(/kg) Cost (AUD)
Steel-
medium
carbon
(1040)
7830.00 190x135x3 0.79 0.45
Labour 0.65
Machining
Process Time
Punch press
forming 15.00sec 0.02
Drilling 1.00 mins 0.1
Press brake
forming 15.00 sec 0.02
Total 1.30 min 1.24
Table 3.5.6c: Manufacturing cost and time for Part 6
C-shaped part (Bottom)
49
Raw material Flat sheet Density
(kg/m3)
Stock
dimensions
(mm)
Price(/kg) Cost (AUD)
Steel-
medium
carbon
(1040)
7830.00 150x70x4 0.79 0.25
Labour 1.41
Machining
Process Time
Punch press
forming 15.00sec 0.02
CNC
machining 3.00 mins 0.90
Total 3.15 min 2.58
Table 3.5.6d: Manufacturing cost and time for Part 10
Cylindrical support
Raw material Round tube Density
(kg/m3)
Stock
dimensions
(mm)
Price(/kg) Cost (AUD)
Steel-
medium
carbon
(1040)
7830.00
=13
T=3
L=7.5
0.79 0.15
Labour 0.36
Machining
Process Time
Cold sawing 20.00 sec 0.02
Grinding belt 30.00 sec 0.03
Total 0.50 min 0.56
Table 3.5.6: Total manufacturing cost and time for sub-assembly of C-shaped parts
Assembly of C-shaped parts
50
Process Time Cost (AUD)
Machining of C-
shaped part (Top) 3.30 min 1.50
Machining of C-
shaped part (Middle) 1.30 min 1.24
Machining of C-
shaped part (Bottom) 3.15 min 2.58
Machining of
cylindrical supports 0.50 min 0.56
Welding of assembly
parts 3.00 min 0.90
Labour 5.25
Total 12.08 min 12.03
Table 3.5.7: Manufacturing cost and time for Part 7
Roller
Raw material Round bar Density
(kg/m3)
Stock
dimensions
(mm)
Price(/kg) Cost (AUD)
Steel-
medium
carbon
(1040)
7830.00 =20
L=26 0.79 0.05
Labour 2.28
Machining
Process Time
Cold sawing 15.00 sec 0.03
Lathe turning 5.00 mins 0.50
Total 5.15 min 2.86
Table 3.5.8: Manufacturing cost and time for Part 8
51
Cage of roller
Raw material Rectangular
bar
Density
(kg/m3)
Stock
dimensions
(mm)
Price(/kg) Cost (AUD)
Steel-medium
carbon (1040) 7830.00 32x15x40 0.79 0.12
Labour 2.24
Machining
Process Time
Cold sawing 10.00 sec 0.02
CNC
machining 5.00 mins 1.5
Total 5:10 min 3.88
Table 3.5.9: Manufacturing cost and time for Part 9
Rectangular clamp
Raw material Rectangular
bar
Density
(kg/m3)
Stock
dimensions
(mm)
Price(/kg) Cost (AUD)
Steel-medium
carbon (1040) 7830.00 71x40x16 0.79 0.28
Labour 3.55
Machining
Process Time
Cold sawing 10.00 sec 0.02
CNC
machining 8 mins 2.4
Total 8.10 min 6.25
Table 3.5.10: Manufacturing cost and time for Part 11
52
Cylinder A x2
Raw material Round bar Density
(kg/m3)
Stock
dimensions
(mm)
Price(/kg) Cost (AUD)
Brass
alloy:360 8500.00
=31
L=25 3.14 0.63
Labour 0.94
Machining
Process Time
Cold sawing 10.00 sec 0.02
Lathe drilling 1.00 min 0.10
Lathe turning 1.00 min 0.10
Total 2.10 min 1.79
Table 3.5.11: Manufacturing cost and time for Part 11
Cylinder B
Raw material Round bar Density
(kg/m3)
Stock
dimensions
(mm)
Price(/kg) Cost (AUD)
Steel-
medium
carbon
(1040)
7830.00 =40
L=20 0.79 0.31
Labour 0.47
Machining
Process Time
Cold sawing 5.00 sec 0.02
Lathe drilling 30.00 sec 0.05
Lathe turning 30.00 sec 0.05
Total 1.05 min 0.9
Table 3.5.12: Manufacturing cost and time for Part22
53
Cylindrical nut
Raw material Round bar Density
(kg/m3)
Stock
dimensions
(mm)
Price(/kg) Cost (AUD)
Steel-
medium
carbon
(1040)
7830.00 =16
L=25 0.79 0.04
Labour 0.94
Machining
Process Time
Cold sawing 10.00 sec 0.02
Lathe drilling 1.00 min 0.10
Lathe turning 1.00 min 0.10
Total 2.10 min 1.2
Table 3.5.13: Manufacturing cost and time for Part 24
Roller spacer
Raw material Round bar Density
(kg/m3)
Stock
dimensions
(mm)
Price(/kg) Cost (AUD)
Brass
alloy:360 8500.00
=13
L=11 3.14 0.04
Labour 0.54
Machining
Process Time
Cold sawing 15.00 sec 0.03
Lathe drilling 1.00 min 0.1
Total 1.15 min 0.71
Table 3.5.14: Manufacturing cost and time for Part 25
54
Handle spacer
Raw material Round bar Density
(kg/m3)
Stock
dimensions
(mm)
Price(/kg) Cost (AUD)
Brass
alloy:360 8500.00
=16
L=30 3.14 0.16
Labour 0.97
Machining
Process Time
Cold sawing 15 sec 0.03
Lathe drilling 1 min 0.1
Lathe turning 1 min 0.1
Total 2.15 min 1.36
8.3 Assembly process of the original design
55
Base + Shaft
Base bolt + Washer (M10)
Bolt & washer + Shaft
56
C-shaped + Cylinder A x2
C-shaped + Shaft
Rectangular clamp + Shaft
57
Threaded rod + C-shaped (Top and bottom)
Threaded rod + Rectangular clamp
Threaded rod + 6 nuts (M8)
58
Drill clamping bolt + C-shaped
Drill clamping bolt + 2 nuts (M10)
59
Drill clamp bolt + Cylindrical nut
Cage of roller 2 + screw (M5)
2 screw (M5) + C-shaped
60
Roller + Roller spacer
Roller & Roller spacer + Cage of
roller
Handle spacer + Handle
61
Handle + Roller
Spilt washer (M6) + Roller
Roller + Nuts (M6)
62
Handle Bolt (M8x60) +
Handle spacer
Handle Bolt (Mx60) +
Rectangular clamp
Assembly finished
63
8.4 Machining cost of each part of the new design
Table 4.1.5: Manufacturing cost and time for Part 1
Base
Raw material Flat sheet Density
(kg/m3)
Stock
dimensions
(mm)
Price(AUD/kg) Cost (AUD)
Recycled
steel-
medium
carbon
(1040)
7830.00 300x280x2 0.79 0.93
Labour 2.82
Machining
Process Time
Punch press
forming 15.00 sec 0.02
CNC
Machining 5.00 mins 1.50
Press brake
forming 15.00 sec 0.02
Welding 1.00 min 0.13
Total 6.30min 5.42
Table 4.1.6: Manufacturing cost and time for Part 2
Handle
Raw material Flat sheet Density
(kg/m3)
Stock
dimensions
(mm)
Price(AUD/kg) Cost (AUD)
Recycled
steel-
medium
carbon
(1040)
7830.00 305x22.5x5 0.79 0.20
Labour 1.74
Machining
Process Time
Punch press
forming 15.00sec 0.02
64
CNC
Machining 3.00 mins 0.9
Press brake
forming 30.00 sec 0.04
Total 4.00 min 2.90
Table 4.1.7: Manufacturing cost and time for Part 3
Shaft
Raw material Round bar Density
(kg/m3)
Stock
dimensions
(mm)
Price(/kg) Cost (AUD)
Recycled
steel-
medium
carbon
(1040)
7830.000 20 ;L=480 0.790 0.940
Labour 0.910
Machining
Process Time
Cold sawing 5.000 sec 0.008
Lathe turning 2.000 mins 0.200
Total 2.050 min 2.058
Table 4.1.8: Manufacturing cost and time for Part 6
Cylinder B
Raw material Round bar Density
(kg/m3)
Stock
dimensions
(mm)
Price(/kg) Cost (AUD)
Recycled
steel-
medium
carbon
(1040)
7830.00
=40;
T=10;
L=21 0.79
0.12
Labour 0.11
Machining
Process Time
Cold sawing 5.00 sec 0.02
65
Lathe drilling 5.00 sec 0.02
Lathe turning 5.00 sec 0.02
Total 15.00 sec 0.29
Table 4.1.9: Manufacturing cost and time for Part 7
ABS clip
Raw material Flat sheet Density
(kg/m3)
Stock
dimensions
(mm)
Price(AUD/kg) Cost
(AUD)
Acrylonitrile
Butadiene
Styrene
1100.00 63x22.5x5 2.81 0.02
Labour 0.51
Machining
Process Time
Thermoforming 1.00 min 0.10
Lathe milling 5.00 sec 0.01
Total 1.10 min 0.64
Table 4.1.10: Manufacturing cost and time for Part 9
T-shaped clamp
Raw material Rectangular
bar
Density
(kg/m3)
Stock
dimensions
(mm)
Price(/kg) Cost (AUD)
Recycled
Brass alloy:
360
8500.00 40x60x22.5 3.14 1.43
Labour 4.42
Machining
Process Time
Cold sawing 10.00 sec 0.02
CNC
machining 10 mins 3.00
Total 8.10 min 8.87
66
8.5 Assembly process of the new design
Base + Shaft
Base bolt + Washer (M8)
Bolt & washer + Shaft
67
C-shaped + Shaft
T-shaped clamp + Shaft
Spring + Shaft
68
Hinge pin +
ABS Clip
Hinge pin +
C-shaped
Hinge pin +
Hinge pin head
69
Threaded rod
(M8x200) +
Hexagonal nut (M8) x2
Threaded rod
(M8x200) +
C-shaped
Socket head (M8x15)
+
Handle
70
Socket head (M8x15) +
C-shaped
Handle bolt (M8x40) +
T-shaped
Handle +
Handle bolt (M8x40)
71
Handle bolt (M8x40) +
Hexagonal nut (M8)
Assembly finished
72
8.6 Calculation of spring rate
Figure 8.6.1: Schematic diagram for spring mass system
By using the following equation,
KxF (Eq 8.6.1)
By assuming a deflection of 5 mm,
)5(81.98.1 K
mmNK /53.3
The spring rate of 3.63 N/mm was chosen as it was the closest value that could be chosen
from online catalogue.
MASS= Hand drill (1.5 kg) + C-
shaped (0.3 kg)
73
8.7 Permanent mold casting
Permanent mold casting is a metal casting process that shares similarities to both sand
casting and die casting. As in sand casting, molten metal is poured into a mold which is
clamped shut until the material cools and solidifies into the desired part shape. However,
sand casting uses an expendable mold which is destroyed after each cycle. Permanent
mold casting, like die casting, uses a metal mold that is typically made from steel or cast
iron and can be reused for several thousand cycles (Custompart, 2010).
Permanent mold casting is typically used for high-volume production of small, simple
metal parts with uniform wall thickness. Non-ferrous metals are typically used in this
process, such as aluminum alloys, magnesium alloys, and copper alloys.
Figure 8.7.1: Schematic diagram of permanent mold casting (Custompart, 2010)
The permanent mold casting process consists of the following steps:
1. Mold preparation - First, the mold is pre-heated to around 300-500°F (150-260°C) to
allow better metal flow and reduce defects. Then, a ceramic coating is applied to the
mold cavity surfaces to facilitate part removal and increase the mold lifetime.
74
2. Mold assembly - The mold consists of at least two parts - the two mold halves and any
cores used to form complex features. Such cores are typically made from iron or steel,
but expendable sand cores are sometimes used. In this step, the cores are inserted and
the mold halves are clamped together.
3. Pouring - The molten metal is poured at a slow rate from a ladle into the mold through
a sprue at the top of the mold. The metal flows through a runner system and enters the
mold cavity.
4. Cooling - The molten metal is allowed to cool and solidify in the mold.
5. Mold opening - After the metal has solidified, the two mold halves are opened and the
casting is removed.
6. Trimming - During cooling, the metal in the runner system and sprue solidify attached
to the casting. This excess material is now cut away (Custompart, 2010).
Table 8.7.1: Characteristics Permanent mold casting (Custompart, 2010)
Typical
Shapes
Thin-walled: Complex
Solid: Cylindrical
Solid: Cubic
Solid: Complex
Part size Weight: 0.05 kg - 300 kg
Materials
Aluminum
Copper
Magnesium
Surface finish-Ra 125 - 250 μin
Tolerance ±0.015 in
Quantity 1000-100000
Advantages
Can form complex shapes
Good mechanical properties
Many material options
Low porosity
Low labor cost
Scrap can be recycled
Disadvantages High tooling cost
Long lead time possible
75
Table 8.2: Average weekly wage in Australia (Migrationexpert, 2010)
State Average weekly earnings (AUD)
Australian Capital Territory 1,130.50
New South Wales 916.10
Northern Territory 956.60
South Australia 856.30
Tasmania 790.00
Victoria 900.30
Western Australia 1045.50
Queensland 889.90
76
Table of Contents
1 Introduction ................................................................................................................. 1
2 Objectives ................................................................................................................... 2
3 Original drill press design (MK 1) .............................................................................. 3
3.1 Essential basic functions analysis of the original design ..................................... 7
3.2 Problems with original design .............................................................................. 8
3.3 Manufacturing process of Product ....................................................................... 9
3.4 Justifications and limitations of data used............................................................ 9
3.5 Machining process of each parts of the original design (Mark 1) ...................... 11
3.5.1 Analysis of assembly time of the original design ....................................... 15
4 New drill press design (MK 2) .................................................................................. 19
4.1 Machining process of each parts of the new design (Mark 2) ........................... 23
4.1.1 Analysis of assembly time of the new design ............................................. 27
5 Discussion ................................................................................................................. 30
5.1 Comparison and analysis between old design (Mark 1) and new design (Mark 2)
30
5.1.1 Discussion and explanation on new Handle design .................................... 30
5.1.2 Discussion and explanation on new C-shaped design ................................ 31
5.1.3 Discussion and explanation on new T-shaped clamp design ...................... 35
5.2 Facts comparison between new drill press (Mark 2) and old drill press (Mark 1)
36
5.3 Functions comparison between new drill press (Mark 2) and old drill press
(Mark 1) ........................................................................................................................ 37
5.4 Functionality of the new Spring part .................................................................. 39
5.5 Design Methodology .......................................................................................... 40
5.6 Concurrent Engineering ..................................................................................... 40
5.7 Design for manufacturing (DFM) ...................................................................... 40
5.7.1 Design for assembly (DFA) ........................................................................ 41
5.8 Environmental conscious manufacturing (ECM) ............................................... 42
5.8.1 Design for environment (DFE) ................................................................... 42
5.9 Material requirement planning (MRP) ............................................................... 42
5.9.1 Lean production .......................................................................................... 43
6 Conclusion ................................................................................................................ 44
7 Reference list ............................................................................................................ 45
77
8 Appendix ................................................................................................................... 45
8.1 Tables ................................................................................................................. 46
8.2 Machining cost of each part of the original design ............................................ 46
8.3 Assembly process of the original design ............................................................ 54
8.4 Machining cost of each part of the new design .................................................. 63
8.5 Assembly process of the new design.................................................................. 66
8.6 Calculation of spring rate ................................................................................... 72
....................................................................................................................................... 72
8.7 Permanent mold casting ..................................................................................... 73
78
List of Figures
Table 3.1a: Different projections on original design .......................................................... 3
Figure 3.1: Isometric view of the original drill press.......................................................... 4
Figure 3.2: Cage of roller connecting with handle ............................................................. 5
Figure 3.3: Base of the drill press ....................................................................................... 5
Figure 3.4: Clamping position of the hand drill .................................................................. 5
Figure 4.1b: Isometric view of the new drill press ........................................................... 20
Figure 4.2: ABS clip opened ............................................................................................. 21
Figure 4.3: C-shaped connected with handle .................................................................... 21
Figure 4.4: Base of the drill press ..................................................................................... 21
Figure 5.1.1.1a: Old Handle design .................................................................................. 31
Figure 5.1.1.1b: New Handle design ................................................................................ 31
Figure 5.1.2.1a: Old C-shaped design ............................................................................... 34
Figure 5.1.2.1b: New C-shaped design ............................................................................. 34
Figure 5.1.3.1a: Old rectangular clamp design ................................................................. 36
Figure 5.1.3.2b: New T-shaped design ............................................................................. 36
Figure 5.3a: Old drill press design .................................................................................... 38
Figure 5.3b: New drill press design .................................................................................. 38
Figure 5.3.1a: Default length position of the spring ......................................................... 39
Figure 5.3.1b: Compressed length position of the spring ................................................. 39
Figure 8.1.1: Manual handling code for assembly process (Tim, 2010) .......................... 46
Figure 8.1.2: Insertion code for assembly process (Tim, 2010) ....................................... 46
Figure 8.6.1: Schematic diagram for spring mass system ................................................ 72
Figure 8.7.1: Schematic diagram of permanent mold casting (Custompart, 2010) .......... 73
79
List of Table
Table 3.1: Bill of material of original design ...................................................................... 6
Table 3.5.1: Total number and cost of machining process required in the original design
........................................................................................................................................... 11
Table 3.5.2a: Schematic diagram of stock material required for original design ............. 11
Table 3.5.2b: Total cost and amount of stock material needed for unit product .............. 12
Table 3.5.3: Manufacturing cost and time for Part 1 ........................................................ 13
Table 3.5.15: Specifications of fasteners used in the original design (Boltsnutscrewonline,
2009) ................................................................................................................................. 14
Table 3.5.1.1: Assembly cost and time of original design ................................................ 15
Table 3.4: Summary of manufacturing process of original design ................................... 18
Table 4.1a: Different projections on new design .............................................................. 19
Table 4.1: Bill of material of new design ......................................................................... 22
Table 4.1.1: Total number and cost of machining process required in the new design .... 23
Table 4.1.2: Schematic diagram of stock material required for new design..................... 23
Table 4.1.3: Required cost and amount of stock material needed for unit product for new
design ................................................................................................................................ 24
Table 4.1.4: Manufacturing cost and time for Part 4 ........................................................ 25
Table 4.1.11: Specifications of fasteners used in the new design (Boltsnutscrewonline,
2009) ................................................................................................................................. 26
Table 4.1.12: Specifications of the spring used in new design (Ashfield spring, 2010) .. 26
Table 4.1.1.1: Assembly cost and time of the new design ................................................ 27
Table 4.2: Summary of manufacturing process of new design ......................................... 29
Table 5.1.1.1: Comparison of specifications between old and new handle design .......... 30
Table 5.1.2.1: Comparison of specifications between old and new C-shaped design ...... 33
Table 5.1.3.1: Comparison of specifications between old and new clamp design ........... 35
Table 3.5.4: Manufacturing cost and time for Part 2 ........................................................ 47
Table 3.5.5: Manufacturing cost and time for Part 3 ........................................................ 47
Table 3.5.6a: Manufacturing cost and time for Part 4 ...................................................... 47
Table 3.5.6b: Manufacturing cost and time for Part 5 ...................................................... 48
80
Table 3.5.6c: Manufacturing cost and time for Part 6 ...................................................... 48
Table 3.5.6d: Manufacturing cost and time for Part 10 .................................................... 49
Table 3.5.6: Total manufacturing cost and time for sub-assembly of C-shaped parts ...... 49
Table 3.5.7: Manufacturing cost and time for Part 7 ........................................................ 50
Table 3.5.8: Manufacturing cost and time for Part 8 ........................................................ 50
Table 3.5.9: Manufacturing cost and time for Part 9 ........................................................ 51
Table 3.5.10: Manufacturing cost and time for Part 11 .................................................... 51
Table 3.5.11: Manufacturing cost and time for Part 11 .................................................... 52
Table 3.5.12: Manufacturing cost and time for Part22 ..................................................... 52
Table 3.5.13: Manufacturing cost and time for Part 24 .................................................... 53
Table 3.5.14: Manufacturing cost and time for Part 25 .................................................... 53
Table 4.1.5: Manufacturing cost and time for Part 1 ........................................................ 63
Table 4.1.6: Manufacturing cost and time for Part 2 ........................................................ 63
Table 4.1.7: Manufacturing cost and time for Part 3 ........................................................ 64
Table 4.1.8: Manufacturing cost and time for Part 6 ........................................................ 64
Table 4.1.9: Manufacturing cost and time for Part 7 ........................................................ 65
Table 4.1.10: Manufacturing cost and time for Part 9 ...................................................... 65
Table 8.7.1: Characteristics Permanent mold casting (Custompart, 2010) ....................... 74
Table 8.2: Average weekly wage in Australia (Migrationexpert, 2010) .......................... 75