New Contact

2

Page 3: Mike Wendt & Cara Abts WisDOT Regional Traffic March 10, 2015

WisDOT’s Lane Closure System (WisLCS) Populates WisDOT’s 511 System Gives public travel-related information:

Construction, maintenance, and utility projects Highway incidents

Crashes, flooding, winter road conditions, etc. OSOW load routing

Tool to coordinate work zones on our transportation system and analyze traveler delay

3

Lane Closure System

Page 4: Mike Wendt & Cara Abts WisDOT Regional Traffic March 10, 2015

http://www.511wi.gov/web/traffic/map.aspx 4

Page 5: Mike Wendt & Cara Abts WisDOT Regional Traffic March 10, 2015

5

transportal.cee.wisc.edu/closures

Page 6: Mike Wendt & Cara Abts WisDOT Regional Traffic March 10, 2015

WisDOT will be putting on LCS training To occur late March to early April Intended for new users to WisLCS

Attendees need to have an account set up on the Lane Closure System prior to the class https://transportal.cee.wisc.edu/forms/secure/lcsrequest.pl

LCS Training

6

Page 7: Mike Wendt & Cara Abts WisDOT Regional Traffic March 10, 2015

LCS Routes Priority Routes in the

North Central Region I-39/US 51, WIS 29, US 10,

Bus 51 WisDOT RTEs will

recommend approval Note: Press release

required

Non-Priority Routes WisDOT Project Leaders

and Coordinators will approve

7

Page 8: Mike Wendt & Cara Abts WisDOT Regional Traffic March 10, 2015

Lane closures* 14 calendar days Full roadway closures 14 calendar days System and service ramp closures* 14 calendar days Full system and service ramp closures 14 calendar days Project start 14 calendar days Construction stage changes 14 calendar days Detours 14 calendar days Lane closures** 3 business days System and service ramp closures** 3 business days Extending all closure types 3 business days

* With height, weight, or width restrictions (available width, all lanes in one direction ≤16’) ** Without height, weight, or width restrictions (available width, all lanes in one direction

>16’)

LCS Advanced Notification

8

Page 9: Mike Wendt & Cara Abts WisDOT Regional Traffic March 10, 2015

9

Page 10: Mike Wendt & Cara Abts WisDOT Regional Traffic March 10, 2015

10

Page 11: Mike Wendt & Cara Abts WisDOT Regional Traffic March 10, 2015

11

Page 12: Mike Wendt & Cara Abts WisDOT Regional Traffic March 10, 2015

12

Page 13: Mike Wendt & Cara Abts WisDOT Regional Traffic March 10, 2015

Can take 2-3 days to get LCS entries approved Depends on staff availability Providing all requested information early reduces

the turnaround time

Timeline for Approvals

13

Page 14: Mike Wendt & Cara Abts WisDOT Regional Traffic March 10, 2015

Answer Your Questions

Cara Abts 715.421.8024 [email protected]