NC RegionConstruction Conference
Traffic SectionMike Wendt & Cara AbtsWisDOT Regional Traffic
March 10, 2015
New Contact
2
WisDOT’s Lane Closure System (WisLCS) Populates WisDOT’s 511 System Gives public travel-related information:
Construction, maintenance, and utility projects Highway incidents
Crashes, flooding, winter road conditions, etc. OSOW load routing
Tool to coordinate work zones on our transportation system and analyze traveler delay
3
Lane Closure System
http://www.511wi.gov/web/traffic/map.aspx 4
5
transportal.cee.wisc.edu/closures
WisDOT will be putting on LCS training To occur late March to early April Intended for new users to WisLCS
Attendees need to have an account set up on the Lane Closure System prior to the class https://transportal.cee.wisc.edu/forms/secure/lcsrequest.pl
LCS Training
6
LCS Routes Priority Routes in the
North Central Region I-39/US 51, WIS 29, US 10,
Bus 51 WisDOT RTEs will
recommend approval Note: Press release
required
Non-Priority Routes WisDOT Project Leaders
and Coordinators will approve
7
Lane closures* 14 calendar days Full roadway closures 14 calendar days System and service ramp closures* 14 calendar days Full system and service ramp closures 14 calendar days Project start 14 calendar days Construction stage changes 14 calendar days Detours 14 calendar days Lane closures** 3 business days System and service ramp closures** 3 business days Extending all closure types 3 business days
* With height, weight, or width restrictions (available width, all lanes in one direction ≤16’) ** Without height, weight, or width restrictions (available width, all lanes in one direction
>16’)
LCS Advanced Notification
8
9
10
11
12
Can take 2-3 days to get LCS entries approved Depends on staff availability Providing all requested information early reduces
the turnaround time
Timeline for Approvals
13