    The CDM:Project-Cycle & Institutions

    Robert Kelly

    Regional Coordinator, CDM Capacity Development,Southern & Eastern Africa

    [email protected]

    Presentation 3, Addis Ababa, May 8th, 2008

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    2/35

    1

    1

    Agenda

    Governance structure of the CDMGovernance structure of the CDM

    CDM project cycle & institutions

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    3/35

    2

    2

    International CDM bodiesConference of Parties to the UNFCCC,

    Meeting of the Parties to the Kyoto Protocol (COP/MOP)

    Conference of Parties to the UNFCCC,Meeting of the Parties to the Kyoto Protocol (COP/MOP)

    CDM Executive Board (CDM-EB)

    CDM Executive Board (CDM-EB) CDM EB operates under the authority of the COM/MOP

    Methodology Panel

    Methodology Panel Recommend to the EB on baseline and monitoringmethodologies, revisions to the PDD, etc.

    Recommend to the EB on baseline and monitoringmethodologies, revisions to the PDD, etc.

    Accreditation Panel

    Accreditation Panel

    Afforestation and ReforestationWorking Group

    Afforestation and ReforestationWorking Group

    Small Scale CDM Panel

    Small Scale CDM Panel

    CDM Registration and IssuanceTeam

    CDM Registration and IssuanceTeam

    Recommend to the EB on baseline and monitoringmethodologies for small-scale project activity

    Recommend to the EB on baseline and monitoringmethodologies for small-scale project activity

    Recommends to the EB on baseline andmonitoring methodologies for A/R CDM

    Recommends to the EB on baseline andmonitoring methodologies for A/R CDM

    Recommends to the EB on the accreditation of anApplicant Entity (AE), suspension, withdrawaland/or re-accreditation of a DOE

    Recommends to the EB on the accreditation of anApplicant Entity (AE), suspension, withdrawaland/or re-accreditation of a DOE

    Assists the CDM EB by appraising requests forproject registration and requests for CER issuance

    Assists the CDM EB by appraising requests forproject registration and requests for CER issuance

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    4/35

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    5/35

    4 4

    6 to 12 months 1.5 months Crediting period of the project

    Project

    Developer

    DNA

    DOE

    CDM

    Executive

    Board

    Project

    feasibilityassessment/ PIN

    Project

    feasibilityassessment/ PIN

    CDM projectdevelopment

    / PDD

    CDM project

    development/ PDD

    Host countryapproval

    Host countryapproval

    ProjectvalidationProject

    validation

    Projectregistration

    Projectregistration

    CERissuance

    CERissuance

    Projectverification

    Projectverification

    The CDM project cycle

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    6/35

    5 5

    6 to 12 months 1.5 months Crediting period of the project

    Project

    Developer

    DNA

    DOE

    CDM

    Executive

    Board

    Project

    feasibilityassessment/ PIN

    Project

    feasibilityassessment/ PIN

    CDM projectdevelopment

    / PDD

    CDM project

    development/ PDD

    Host countryapproval

    Host countryapproval

    ProjectvalidationProject

    validation

    Projectregistration

    Projectregistration

    CERissuance

    CERissuance

    Projectverification

    Projectverification

    The CDM project cycle

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    7/35

    6 6

    The Project Idea Note (PIN)

    The PIN is typically a five-page document providing information on aCDM project

    Some countries require a PIN in order to be able to obtain a letter ofendorsement from the DNA of the host country

    The PIN is typically used as a marketing tool to distribute topotential CDM investors to begin negotiations on partnership orpurchase of CERs

    The PIN has three main components:

    Project description type of project, location, schedule, etc.

    Finance expected costs and expected revenues

    Expected environmental and social benefits

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    8/35

    7 7

    6 to 12 months 1.5 months Crediting period of the project

    Project

    Dev

    eloper

    DNA

    DOE

    CDM

    Executive

    Board

    Project

    feasibilityassessment/ PIN

    Project

    feasibilityassessment/ PIN

    CDM project

    development/ PDD

    CDM project

    development/ PDD

    Host countryapproval

    Host countryapproval

    ProjectvalidationProject

    validation

    Projectregistration

    Projectregistration

    CERissuance

    CERissuance

    Projectverification

    Projectverification

    The CDM project cycle

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    9/35

    8 8

    The Project Design Document (PDD)

    An official component of the CDM project cycle

    Official standardised template is available from the UNFCCC website

    Covers all the information essential for carbon layer assessment

    Incorporates significant project thinking project design, partnerships,funding, revenue and cost forecasts, due diligence, sensitivity analysis,etc.

    The PDD is validated by a Designated Operational Entity and describesthe baseline and monitoring methodology that must be carried out

    PDDs are public documents

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    10/35

    9 9

    6 to 12 months 1.5 months Crediting period of the project

    Pr

    oject

    Dev

    eloper

    DNA

    DOE

    CDM

    Executive

    Board

    Project

    feasibilityassessment/ PIN

    Project

    feasibilityassessment/ PIN

    CDM project

    development/ PDD

    CDM project

    development/ PDD

    Host countryapproval

    Host countryapproval

    ProjectvalidationProject

    validation

    Projectregistration

    Projectregistration

    CERissuance

    CERissuance

    Projectverification

    Projectverification

    The CDM project cycle

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    11/35

    1010

    The Designated National Authority (DNA) is the legal entity authorised tosign a Letter of Approval (LoA) for a CDM project

    Typically an inter-ministry agency (Environment, Economy, Energy,Meteorology, etc.) with a small secretariat

    The DNA provides written approval that the CDM project assists inachieving the countrys sustainable development

    The details of the approval procedure are up to each country

    Typically, 3 broad development criteria are employed:

    Economic: the project has a positive effect on economic

    development

    Environmental: the project leads to reduced pressure on theenvironment

    Social: the project has positive effects on social development

    The DNA and host country approval

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    12/35

    1111

    [State Forest Agency MOLDSILVA]

    No.018 03/9.04 from 2nd of September, 2004ref No. 01-07/401 from 20th of July 2004

    On examination of the project proposals

    Soil conservation in the Republic of Moldova

    Through the present, we acknowledge that the the Supreme Designated National Authority, responsible for the implementation ofthe Clean Development Mechanism of the Kyoto Protocol, has examined on its meeting from 9th of August 2004 the project Soil

    Conservation in the Republic of Moldova, elaborated and presented by the State Forest Agency MOLDSILVA. As result ofexamination, the National Commission concluded the following:

    The State Forest Agency MOLDSILVA is the only responsible for elaboration and implementation of the CDM Project SoilConservation in the Republic of Moldova. In the name of the Government of the Republic of Moldova, the Agency has negotiatedand contracted with the World Bank Prototype Fund all the conditions of the CDM Project (Government Resolution No. 1155 from26th of September 2003).

    In case of implementation of the CDM Project in its actual version, the planned activities would essentially contribute to thesustainable development of the Republic of Moldova and would positive influence the quality of the environment.

    Through this CDM Project, the Republic of Moldova is participating on voluntary basis on realization of the Clean DevelopmentMechanism of the Kyoto Protocol.

    Constantin MIHAILESCU

    Minister, Ministry of Ecology and Natural Resources,Chair of the National Commission

    Letter of approval - example

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    13/35

    1212

    Compliance with national policies:

    Environmental Impact Assessment

    Sectoral regulations (construction permits, licences, etc)

    Compatibility with local/sectoral strategies and priorities

    Public participation:

    Comments by local stakeholders directly and indirectlyinvolved with the project

    Infrastructure and technical capacity:

    Local availability of qualified human resources

    Local availability of adequate institutional resources

    Other host country requirements

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    14/35

    1313

    6 to 12 months 1.5 months Crediting period of the project

    Pr

    oject

    Dev

    eloper

    DNA

    DOE

    CDM

    Executive

    Board

    Project

    feasibilityassessment/ PIN

    Projectfeasibility

    assessment/ PIN

    CDM project

    development/ PDD

    CDM project

    development/ PDD

    Host countryapproval

    Host countryapproval

    ProjectvalidationProject

    validation

    Projectregistration

    Projectregistration

    CERissuance

    CERissuance

    Projectverification

    Projectverification

    The CDM project cycle

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    15/35

    1414

    Validation a process of systematic assessment leading to astatement on the reasonableness of the assertion of future

    greenhouse gas performance

    Basically is the plan reasonable?

    Project validation

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    16/35

    1515

    A required pre-approval step for CDM project registration

    Undertaken before the project crediting period, and (typically) beforeimplementation / construction of the project

    Requires assessment of the assumptions, calculations, methodologiesand justifications relating to the baseline scenario

    Is the project truly additional?

    Will the greenhouse gas emission reductions be monitoredand calculated appropriately?

    Provides no assurance of the projects future performance!

    Project validation

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    17/35

    1616

    Undertaken by Designated Operational Entities (DOEs):

    Essentially audit companies:

    Confirm that the PDD conforms to CDM requirements andcorrectly applies the baseline methodology andgreenhouse gas quantification procedures

    Check calculations are accurate and assumptions are

    reasonable in the PDD Confirm that the project satisfies the additionality

    requirement

    Make the PDD available for public review

    Submit the PDD to the CDM Executive Board for registration(together with Letter of Approval from the DNA)

    Project validation

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    18/35

    1717

    The independence of DOEs

    Validator/Verifier(DOE)

    (3rd party)

    Validator/Verifier(DOE)

    (3rd party)

    assurance

    independence

    CDMExecutive

    Board(2nd party)

    CDMExecutive

    Board(2nd party)

    GHGAssertion

    ProjectProponent

    (1st party)

    ProjectProponent

    (1st party)

    accountability

    sta

    tem

    ent

    Independenceshown by nofinancialinterest

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    19/35

    1818

    DOEs are accredited for specific sectoral scopes

    Agriculture15

    Afforestation & reforestation14

    Waste handling & disposal13

    Solvent use12

    Fugitive emissions from HFCs & SF611

    Fugitive emissions from fuels (solid, oil and gas)10

    Metal production9

    Mining / mineral production8

    Transport7

    Manufacturing industries4

    Chemical industries5

    Construction6

    Energy demand3

    Energy distribution2

    Energy industries (renewable / non-renewable sources)1

    Sectoral ScopeScope Number

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    20/35

    1919

    DOEs market shares

    DNV, 42%

    TV-SD, 25%

    SGS, 13%

    BV Cert, 6%

    TV-Nord, 6%TV-Rhein, 5%

    Other, 5%

    Share of CDM Validations, March 2008

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    21/35

    2020

    6 to 12 months 1.5 months Crediting period of the project

    Project

    Dev

    eloper

    DNA

    DOE

    CDM

    Executive

    Board

    Project

    feasibilityassessment/ PIN

    Projectfeasibility

    assessment/ PIN

    CDM project

    development/ PDD

    CDM project

    development/ PDD

    Host countryapproval

    Host countryapproval

    ProjectvalidationProject

    validation

    Projectregistration

    Projectregistration

    CERissuance

    CERissuance

    Projectverification

    Projectverification

    The CDM project cycle

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    22/35

    2121

    The CDM Executive Board checks that the submitted PDD and

    accompanying documents are complete

    The CDM Registration Fee is paid

    The PDD is then placed on the UNFCCC website for a period of 8

    weeks for public comment known as a request for registration

    The CDM Executive Board can request changes to the project designor can reject the project outright

    Otherwise, the project is formally registered as a CDM project

    Project registration

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    23/35

    2222

    Project registration fee The registration fee covers the Executive Boards administrative expenses

    The registration fee is:

    10 US cents per CER issued for the first 15,000 CERs

    20 US cents per CER issued for any amount in excess of 15,000 CERs for agiven year

    The maximum registration fee is $350,000

    No registration fee has to be paid for CDM project activities with expected

    average annual emission reductions below 15,000 CERs

    $ 18,500100,000 tCO2e

    $ 350,0001,757,500 tCO2e

    $ 350,0003,000,000 tCO2e

    $ 4,50030,000 tCO2e

    $ 1,50015,000 tCO2e

    -10,000 tCO2e

    US$Average Annual Emission Reduction

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    24/35

    2323

    Project registration fee

    No registration fee has to be paid for CDM project activities hosted in

    least developed countries:

    E.g. Ethiopia, Mozambique, Tanzania, Zambia

    But not (for example)Botswana, Kenya, Mauritius

    The PDD constitutes the basis for the calculation of the registration fee

    If an activity is not registered, any registration fee above $30,000 is

    reimbursed

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    25/35

    2424

    6 to 12 months 1.5 months Crediting period of the project

    Project

    Dev

    eloper

    DNA

    DOE

    CDM

    Executive

    Board

    Projectfeasibility

    assessment/ PIN

    Projectfeasibility

    assessment/ PIN

    CDM project

    development/ PDD

    CDM project

    development/ PDD

    Host countryapproval

    Host countryapproval

    ProjectvalidationProject

    validation

    Projectregistration

    Projectregistration

    CERissuance

    CERissuance

    Projectverification

    Projectverification

    The CDM project cycle

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    26/35

    2525

    Verification a process of systematic assessment leading to astatement confirming the assertion that past greenhouse gasperformance has been appropriately calculated and reported

    Basically provides confirmation of the greenhouse gas

    assertion

    Project verification

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    27/35

    2626

    Undertaken after the CDM project has been implemented and hasstarted to generate greenhouse gas reductions. Typically requiresrigorous data collection, testing and evaluation of evidence to present

    a complete audit trail

    Essentially, seeks to confirm two things:

    that past greenhouse gas performance has been appropriatelycalculated and reported

    that the project has been executed in accordance with thevalidated PDD

    Verification is undertaken by a DOE but not the one that performedthe validation

    Verification can take place as often as the project developerwishes represents a balance between cost and revenue

    Project verification

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    28/35

    2727

    Before the project

    Validation gives assurance that if the project is implemented according tothe Project Design Document (PDD) then it will meet CDM eligibility criteriaand that, once verified, CERs will be issued.

    - Once validation is achieved, the bargaining power of the project

    developer increases considerably as does the price of the CERs

    During the project

    Verification provides assurance that the project developer has adhered to

    the validated PDD and that emission reductions have, in fact, taken place.

    - Once results are verified, CERs can be issued. These are a uniform(hard) currency, and have a higher value than any projected CERs

    The link between validation and verification

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    29/35

    2828

    The cost of validation of a project depends on:

    The complexity of the project

    Quality of the PDD

    Quality of underlying control and information systems

    If the PDD fails validation you do not have a project!

    What you need to know about validation

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    30/35

    2929

    The best project in the world is worthless if not monitored properly:

    - If the project developer does not collect (with calibratedinstruments), process and record relevant data during theoperation of the project, it is usually not possible to reconstruct(back-cast) this data

    If data is not transparently available to the DOE, certification will not bepossible

    - If the Monitoring Report fails verification, the project cannot beissued with CERs

    What you need to know about verification

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    31/35

    3030

    6 to 12 months 1.5 months Crediting period of the project

    Project

    Developer

    DNA

    DOE

    CDM

    Executive

    Board

    Projectfeasibility

    assessment/ PIN

    Projectfeasibility

    assessment/ PIN

    CDM project

    development/ PDD

    CDM project

    development/ PDD

    Host countryapproval

    Host countryapproval

    ProjectvalidationProject

    validation

    Projectregistration

    Projectregistration

    CERissuance

    CERissuance

    Projectverification

    Projectverification

    The CDM project cycle

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    32/35

    3131

    Certification and CER issuance The DOE provides a verification report to the project participants and

    the executive board. The report is made publicly available.

    The verification report constitutes a request for issuance to theExecutive Board of CERs equal to the verified amount of reductionsof anthropogenic emissions by sources of greenhouse gases.

    The issuance of CERs is considered final 15 days after the date of

    receipt of the request for issuance.

    The Executive Board then instructs the CDM registry to issue thespecified quantity of CERs in the CDM registry:

    A Share of Proceeds (SOP-Admin) fee is deducted

    2% of the total CERs are deducted as a SOP-Adaptation fee

    The remaining CERs are forwarded to the registry accounts ofthe project participants involved

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    33/35

    3232

    Share of Proceeds Administration (SOP-Admin) payment

    The SOP-Admin fee is levied at the time of issuance of CERs

    The SOP-Admin fee covers the Executive Boards administrativeexpenses

    The SOP-Admin fee is:

    10 US cents per CER issued for the first 15,000 CERs

    20 US cents per CER issued for any amount in excess of 15,000CERs for a given year

    The registration fee is deducted from the SOP-Admin fee

    No SOP-Admin fee has to be paid for CDM project activities hosted inleast developed countries

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    34/35

    3333

    Share of Proceeds Adaptation (SOP-Adaptation) payment

    2% of issued CERs are diverted to an Adaptation Fund to enabledeveloping countries meet the costs of adapting to climate change

    CDM projects in least developed countries are exempt from the SOP-Adaptation payment

    Administered by the Adaptation Fund Board, with the GlobalEnvironment Facility (GEF) acting as interim Secretariat and the WorldBank acting as interim Trustee

    Controversies over management as the Adaptation Fund is not fundedby donors

    The Fund currently contains 2.7 million CERs and may contain 36million CERs by the end of 2012

    At a price of EURO 15/CER: EURO 540 million ($810 million)

  • 8/9/2019 Microsoft Power Point - Presentation 3 - The CDM Project-cycle

    35/35

    3434

    End

    Robert KellyRegional Coordinator, CDM Capacity Development,

    Southern & Eastern Africa

    [email protected]