Upload
imran-ali
View
79
Download
8
Embed Size (px)
Citation preview
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 1 of 36
GENERAL INFORMATION
THIS DOCUMENT IS ENTENDED FOR REFRENCE PURPOSES ONLY. YOU CAN EDIT & MODIFY THE CONTENT.
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
OFFICIAL UNFOLD SECRETS WEBSITEhttp://www.unfoldsecrets.com
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 2 of 36
OUR BLOG ARTICLE PAGEhttp://www.unfoldsecrets.com/articles
SIGN OUR GUESTBOOKhttp://unfoldsecrets.com/Guest-book.php
JOIN US NOWhttp://unfoldsecrets.com/login/index.php
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 3 of 36
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 4 of 36
METHOD STATEMENT FOR chilled water risers
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 5 of 36
Project : *INSERT PROJECT HERE
Contractor : *INSERT CONTRACTOR NAME HERE
Document No. :
Document revision status : 1
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 6 of 36
0 04-09-2008 Issued for Review & Comments
Prepared by Checked by Approved by
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 7 of 36
Rev. Date Description *INSERT CONTRACTOR NAME
HERE
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 8 of 36
REVISION CONTROL SHEET
REV. NO. DATE PAGE NO. DESCRIPTION
0 04-09-2008 ALL FIRST ISSUE
1 05-24-2008 ALL SECOND ISSUE
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 9 of 36
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 10 of 36
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 11 of 36
TABLE OF CONTENTS
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 12 of 36
1. Introduction & Scope …………………………………………………………….. 4
2. Responsibilities....…………………………………………………………………. 4
3. Equipment...…………..……......…………………………………………………… 5
4. Materials……………………………………………………………………………… 6
5. Materials Handling and Storage at Site..……………………………………….. 6
6. Installation…………………………………………………………………………… 7
7. Preparing the Riser for HYDROTESTING…….………………………………… 8
8. Health and Safety…………………………………………………………………… 9
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 13 of 36
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 14 of 36
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 15 of 36
1. INTRODUCTION & SCOPE :
1.0 This method statement specify the detailed requirements and procedures for
installation of Chilled Water Risers from the main entrance piping , and
basement up to roof.
1.1 Applicable Project Specification :
1.1.0 Section 220510 Basic Mechanical Materials and methods
1.1.1 Section 220510 Hydronic PipingDOWNLOAD THIS DOCUMENT ON THIS BELOW LINK
http://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 16 of 36
1.2 Quality Control, Inspection and Testing are covered under Quality
Control procedure No. T1193 – Tol – PQP Inspection & Testing plan.
1.3 HSE and General Safety Rules are cover under Project Safety Plan and
Main Contractor Safety Rules and Regulation.
2. RESPOSIBILITIES :
2.0 The Construction Manager will ensure all preparations & installation works
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 17 of 36
are carried out according to Project Specification , the progress is carried
out according to the planned program, as per approved method statements
to cooperate with the main Contractor regarding the implementation of any
comments raise by the company & to ensure all safety & quality control
are implemented.
2.1 The Site Engineer will ensure that the installation works are carried out
according to: Project Specification ,Manufacturer data sheet , Approved
Method Statement , Safety Regulations & to distribute responsibilities
to his construction team & provide them with information for the installation
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 18 of 36
works.
2.2 To ensure the compliance of works with the related approved quality
control procedure & Company requirements & to coordinate with the Q.C.
Engineer to advise for the area raise for inspection.
2.3 The QC Engineer will ensure the executed work are carried out in
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 19 of 36
accordance with Contract Specification , Manufacturer Instruction,
Approved Method Statement & the compliance of these works to quality
procedures.
2.4 To inspect & satisfy him self of the soundness of the completed works
before requesting the Main Contractor to seek Company approval or
inspection.
2.5 To initiate inspection & test request for the Company approval through the
Main Contractor.
2.6 To advise the construction team of the specific requirements related to
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 20 of 36
work quality.
2.7 To maintain comprehensive inspection & test record any further reference
& documentation.
3. EQUIPMENT :
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 21 of 36
3.0 EQUIPMENTS USED FOR CHILLED WATER RISER WORKS
3.0.0 Fastening Hand Tools
3.0.1 Pipe Fitter Hand Tools
3.0.2 Portable Grinding Machine
3.0.3 Portable Drill Machine
3.0.4 Roll Grooving Machine
3.0.5 Spirit Level & Measuring Tape
3.0.6 Threading Machine
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 22 of 36
3.0.7 Mobile Scaffolding
4. MATERIALS :
4.0 PIPES :
4.0.0 MS Pipes Seamless 11/2” dia. Sch. 40 ASTM A 53
4.0.1 MS Pipes Seamless Smaller Sch.40 ASTM A 53DOWNLOAD THIS DOCUMENT ON THIS BELOW LINK
http://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 23 of 36
4.0.2 MS Pipes Seamless 2” dia. Sch.40 ASTM A53
4.0.3 MS Pipes Seamless Larger Sch.40 ASTM A53
4.1 FITTINGS :
4.1.0 Malleable iron threaded fitting PN 25 BS 123 & ISO 49 (UK)
4.1.1 BS 1256 Threads to BS 21 2500 Kpa for ¾” up to 1 ½” (UK)
4.1.2 Grooved Fittings to ASTM A 536 Grade 65-15-12 Ductile
Iron to 2” and Larger (USA)
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 24 of 36
4.2 OTHER MATERIALS REQUIRED :
4.2.0 Necessary Valves & Strainers
4.2.1 Clamps
4.2.2 Anchor Pins
4.2.3 Galvanized Threaded Rods ( FLAMCO)
4.2.4 Wooden Insert , Galvanized Angle Iron , U – Channels,
Nuts & Washers.
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 25 of 36
5. MATERIALS HANDLING & STORAGE AT SITE :
5.0 All Pipes & Fittings shall be off-loaded carefully at site ,stored in a
clean dry place, adequate cover shall be provided.
5.1 MS Pipes should be stacked on a flat surface free from sharp
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 26 of 36
projection, stones or other protuberance likely to cause point loading
or pipe deformation. It may be necessary to level the ground in order
that pipes may be uniformly supported throughout their length . And
alternative mean of storage to level the pipes on stout timber bearer
not less than 75 mm wide placed at not greater than 1.5 meter center.
5.2 Pipes fittings may be subjected to damage and /or the effects of
Corrosion or weathering if stored for long periods. For this reason
fittings should be stored in sheltered conditions. In such a way that
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 27 of 36
they are protected from the effect of weathering or accidental
damage.
6. INSTALLATION :
6.0 The site shall be investigated to confirm its ready & safe to start the
installation works.
6.1 Using the latest approved shop drawing check the routing of the pipes
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 28 of 36
confirm there is no clashing with other services & there is no
obstacles that will affect pipe installation.
6.2 The pipe sizes & quantity shall be then identify based on the latest
Approved shop drawing and shifted to place of installation.
6.3 The pipe shall be thoroughly cleaned made free of dust, oil, grease
& painted with anti-rust paint before installation.
6.4 The pipes shall be connected by means of threading for 1 ½” in pipe
size & larger as per approved material submittals & approved shop
drawings.
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 29 of 36
6.5 All isolating ,regulating ,drain ,vent valves & strainers shall be
installed in accordance with latest approve shop drawings.
6.6 Temperature ,pressure gauges and other flow measuring or metering
shall be installed in accordance with the latest approved shop
drawings.
6.7 All piping shall be supported by hangers as per approved materials
submittal & approved shop drawings.
6.8 Adequate spacing between supports & hangers shall be maintained
in accordance with latest approve shop drawings.
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 30 of 36
6.9 The installation shall be done allowing sufficient access to all
strainers, valves and gauges. Sufficient spacing shall be maintained
between pipes for installation.
6.10 Appropriate sleeves ,sealant shall be provided around pipes
penetrating floors, slabs & partitions walls as per approved shop
drawings.
7. PREPARING THE RISER FOR HYDROTESTING :
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 31 of 36
7.0 Identify the risers pipe work to be hydrotested , check all installation
in floors & shafts are completed.
7.1 Check the location of the isolating valves & double regulating valves
in the ground floor to confirm the pipe connection are ready for test.
7.2 Cap off the pipe at the location of isolating valves using blind flange or
threaded cap according to pipe size.
7.3 To utilize the time of testing its better to test piping for similar flat
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 32 of 36
from ground to roof. Isolating the risers using end caps or blind flanges
at valve connection for each riser located at the entry of each flat in
ground floor.
7.4 Ensure the riser pipe or section are fully isolated to perform testing.
7.5 Ensure all joints are tighten firmly & all sleeves for partition are in
place.
7.6 On completion of installation the system shall be pressure tested using
water at ambient temperature. At a pressure 1.5 times the operating
pressure for a period of 4 hours.
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 33 of 36
8. HEALH AND SAFETY :
8.0 All installation works will be undertaken in accordance with TS JV
Safety Rules and Regulation.
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 34 of 36
8.1 All site personnel shall be provided with personal protective items
like helmets, safety shoes & gloves, safety goggles and shall be worn
at all times at site.
8.2 All site work activities will be kept in a clean and tidy condition.
-------------------------------------Procedure Ends------------------------------------------------
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 35 of 36
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER
*INSERT LOGO HEHRE
*INSERT CLIENT NAME HEREDoc. No.:
*INSERT PROJECT HERE Date: 24 -05- 2008REV. 1
METHOD STATEMENT
Page No. : 36 of 36
DOWNLOAD THIS DOCUMENT ON THIS BELOW LINKhttp://www.unfoldsecrets.com/forum
PROJECT MANAGER