View
2.182
Download
52
Embed Size (px)
DESCRIPTION
Flushing Procedure for Chilled Water System Chemical Treatment Method Statement HQ
Citation preview
8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ
methodstatementhq.com/flushing-procedure-for-chilled-water-system-chemical-treatment.html 1/8
HomeDisclaimer
Construction Method Statements
Plumbing
Piping
Electrical
HVAC
Duct Works
HVAC PipingTesting & Commissioning
Pump Installation
Method Statement Template
Inspection ChecklistsRequest A Method Statement
Health & Safety
Sample Forms & Formats
Flushing Procedure For Chilled Water System ChemicalTreatment
Tweet
Like
0
Share
Listen to musicSearch
8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ
methodstatementhq.com/flushing-procedure-for-chilled-water-system-chemical-treatment.html 2/8
Tweet 0
Like 0
This method statement describes the methodology and
procedure for flushing of chilled water system and to ensure
that all concerned persons are familiar with the sequence of
activities, utilization of resources, and execution of the worksin compliance with applicable Safety and Quality
Procedures, and Project Documents and Specification.
Scope of Works
This method statement is intended to outline the activities and
the methods used in cleaning and flushing of chilled water
system and its chemical treatment. All activities will be
carried out in accordance with the contract details and in full
compliance to the project specifications. All work within therights-of-way of the standards and specifications will be
done in compliance with requirements issued by authorities.
Required Tools/Equipment
Tool box
Tool kitMeters/gauges
Power ToolsTemporary pump
HVAC Air Conditioning
www.siemens.com/climate-control
Climate Control by Siemens - Save up to60 percent of consumed energy
0 Email Share
8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ
methodstatementhq.com/flushing-procedure-for-chilled-water-system-chemical-treatment.html 3/8
Chilled Water Flushing Procedure
Preparation: The following preparation checks / works shall be carried out prior to commencement of flushing
and cleaning of chilled water system.
Check and ensure the system is hydro-statically pressure tested and verify test certificate.Check the provision of air vents at location as per approved drawings.
Check and ensure sufficient quantities of chemicals are available as per requirement.Place warning signs and warning tape as required.
Arrangements for draining the flushed water to be made before starting the flushing process. Drain shouldbe connected to main drainage line or as directed by authorities.
Flushing & Cleaning Steps
Cleaning With Fresh Water
Fill the system with clean water and drain the water after 30 minutes of circulation. The water quality will be as
per approved parameters.
Refill the system with clean water and run the chilled water pump for 2 hours. Take samples to check the quality
8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ
methodstatementhq.com/flushing-procedure-for-chilled-water-system-chemical-treatment.html 4/8
of water as per applicable requirements in the contract.
Open the drain valves in the main lines and drain the water completely.
Clean the strainers
During the above flushing process the drain valves shall be kept open while the pump is running, until the waterappears clean.
Close all the drain valves
Cleaning With Cleaning Chemical
Desired water quality should be achieved before adding the chemical.
Refill the system with clean water and add cleaning chemical in required quantities as per Specialistsupplier’s instructions i.e. 1Kg per cubic meter of system volume.
Once the cleaning process is started, samples of solution shall be collected from various parts of the
system to ensure the chemical solution has reached all parts of the system.
Run the pump and circulate the water (with chemicals added) for a minimum period of 24 hours as perspecialist supplier’s recommendations.
Samples to be taken and tested in 3rd party laboratory. The water quality must be achieved as per therequirements agreed in the contract or as applicable
Specialist contractor shall collect samples and conduct tests until satisfactory results are obtained as
required which is a condition when no increase in iron level is observed and a level of iron less than 1ppmis achieved and the water is clear, colourless and odourless.
After the cleaning process is completed as described above the cleaning solution shall be flushed out.
Addition of Corrosion & Scale Inhibitors
The entire system is re-filled with fresh and clean water and treated with corrosion and scale inhibiting treatment
chemical at the rate of 3Kg per cubic meter of the system volume or as applicable depending upon the chemical
concentration. After 24 hours of circulation samples are taken to ensure the concentration levels i.e. 800-100ppm as NaNo2
Biological Control
Biological control chemical, shall be dosed at the agreed rate per cubic meter using the manual dosing pot. This is
a shock dosing which shall be done after every three months.
Inspection
The inspection request shall be raised for consultant to witness the flushing and cleaning process at differentstages and results shall be noted on checklists.
8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ
methodstatementhq.com/flushing-procedure-for-chilled-water-system-chemical-treatment.html 5/8
Tags: Chemical Treatment of chw piping, chw piping cleaning, Flushing Procedure For Chilled Water System
◀ METHOD STATEMENT FOR CONCRETE SAMPLING AND TESTINGSample Forms & Checklists For HVAC Installation Testing & Commissioning ▶
Search Search
Like Us To Support Us
Electrical Installation
www.siemens.ae/green-buildings
Siemens Green Buildings - Save up to 60percent of consumed energy!
8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ
methodstatementhq.com/flushing-procedure-for-chilled-water-system-chemical-treatment.html 6/8
Methodstatementhq
Like
One person likes Methodstatementhq.
Facebook social plugin
Other Method Statements
Testing & Commissioning Of Fire Suppression System
August 20th, 2013
The scope of method statements covers the planning, preparation, and conduct of fire
suppression sys[...]
Welding Method Statement
August 13th, 2013
There are many different welding processes, but the most commonly used in the construction
industry [...]
Installation Of Reinforcement Steel Bars For Footing, Strap Beam, Raft, Slab & All
Structural Concrete - Steel Fixing
August 13th, 2013
The purpose of this method statement is to lay down the systematic procedures for the various
activi[...]
Method Statement For Installation Testing & Commissioning Of BMS Building
Management System
August 1st, 2013
Scope of Work This method statement is applicable for Installation, Testing & Commissioning
of [...]
8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ
methodstatementhq.com/flushing-procedure-for-chilled-water-system-chemical-treatment.html 7/8
Chilled Water Balancing For HVAC System Method Statement
July 31st, 2013
The aim of chilled water balancing is to apply a disciplined procedure of adjustment to water
flow r[...]
Method Statement For Air Balancing Of HVAC System FCU AHU Exhaust Fans &
Pressurization Unit
July 31st, 2013
Air Balancing Method Statement Air Balancing For Fan Coil Units Check that all automatic
contro[...]
Inspection Checklists / Forms For Electrical Works Installation Testing &
Commissioning
July 31st, 2013
Below are the links for downloading the sample inspection and testing check sheets and forms
which y[...]
Sample Forms & Checklists For HVAC Installation Testing & Commissioning
July 31st, 2013
You can download the sample forms and checklists for different activities which you can then
customi[...]
METHOD STATEMENT FOR CONCRETE SAMPLING AND TESTING
July 29th, 2013
This method statement is applicable for collecting samples for concrete before and during
concrete p[...]
METHOD STATEMENT FOR TESTING & COMMISSIONING OF
PRESSURIZATION UNIT
July 29th, 2013
The purpose of this procedure is to define the step by step method to implement the correctpractice[...]
8/25/13 Flushing Procedure For Chilled Water System Chemical Treatment | Method Statement HQ
methodstatementhq.com/flushing-procedure-for-chilled-water-system-chemical-treatment.html 8/8
Most Visited Tags
AC Ducting Method Statement blank performa blank proforma BMS Testing Procedure Building Management System BMS
Construction Method Statements Drainage Piping Installation Electrical Method Statements for GI Box Installation GI Conduit In The Wall
hvac HVAC Duct Work Installation Method Statement HVAC System Procedure installation Installation of GI Conduits &
Accessories method Method Of Statement Method Statement Method Statement
For Drainage Piping method statement for drainage works Method Statement For GI Box & Conduit Installation method statement forInstallation Method Statement For PVC Conduit Installation In Concrete Slab Method Statement Template MST MST For
BMS MST For Conduiting Work of Piping Installation Procedure pressure pumps PVC uPVC Underground Above Ground Piping Risk
Assessment sample check list sample checksheet Sample Format Electrical SOP statement swms template test
Testing & Commissioning Testing & Commissioning Method Statement water
HomePrivacy Policy
Disclaimer
Copyright © 2011 - 2012 MethodStatementHQ.Com. All Rights Reserved.