Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
2655 North Sheridan Way, Suite 300
Mississauga, ON Canada L5K 2P8
t: 905.823.8500
f: 905.823.8503
www.mrc.ca
MEMO TO FILE
FROM: Andrew Shea
DATE: March 18th
, 2013
COPIES: David Veights, Metrolinx
Scott Bowers, MMM
OUR FILE: 3212006
SUBJECT: Traffic Investigation for LRT – West Section
On May 17, 2010, the Minister of the Environment for the Province of Ontario issued a Notice to
Proceed to the City of Toronto and the Toronto Transit Commission (TTC) for the Eglinton
Crosstown Light Rail Transit (ECLRT) Project, a 33-kilometre electrically powered Light Rail
Transit (LRT) line extending from the Lester B. Pearson International Airport in the City of
Mississauga to Kennedy Station in the City of Toronto. The Notice signified the completion of a
process carried out under the Transit Project Assessment Process (Ontario Regulation 231/08).
Subsequent to the issuance of that Notice by the Minister, changes to the Project have been
identified that are inconsistent with the project presented in the 2010 Environmental Project
Report (EPR) that served as the basis for the Minister’s Notice of May 17, 2010. As described in
Section 15 of Ontario Regulation 231/08, any significant change that is inconsistent with a
previously approved EPR requires a reassessment of the impacts associated with the project
where changes are proposed, the identification of potentially new mitigation measures, and
potentially new monitoring systems in an addendum to the previously approved EPR.
The 2010 ECLRT TPAP recommended a surface median LRT facility on Eglinton Avenue with
an at-grade connection to the proposed Black Creek MSF (requiring LRT vehicles to cross the
westbound general traffic lanes in order to access the facility, see Figure 1). The concept
proposed in the 2010 EPR converted two of the six general purpose traffic lanes between
(approximately) Weston Road and Black Creek Drive to a median LRT facility. The 2010 EPR
assessed the traffic impacts associated with the reduction in capacity.
Metrolinx has subsequently identified a need to implement an Automated Train Operation
(ATO) system for trains leaving the Black Creek MSF site in order to achieve the desired service
frequency and reliability along the line, therefore introducing a need to grade-separate the LRT
from general traffic at the Black Creek MSF site access and precluding the ability to implement
the Black Creek Drive LRT stop proposed in the 2010 EPR. Further, in light of a future GO Rail
station at Mount Dennis, as envisioned in the Georgetown South Corridor EA (2009), relocation
and redesign of the Weston LRT Stop to a full station under the rail corridor would allow for a
future, fully-integrated LRT/GO Rail station. The current plan is illustrated in Figure 2.
Memo
Date: March 18th
, 2013 Page 2
Under the approved 2010 EPR, the proposed western terminus of the Eglinton LRT facility was
to be at Toronto Pearson International Airport. While this remains the ultimate terminus in the
west, the current phased implementation approach will result in an interim western terminus at
the Mount Dennis LRT Station. As such, Eglinton Avenue west of Mount Dennis will continue
to be served by buses in the interim, until such a time when funding allows for the westerly
extension of the LRT. These bus services will serve or terminate at a new proposed bus terminal
at the Mount Dennis Station in order to connect passengers from the west with the Eglinton
Crosstown LRT in the first phase of implementation.
Under the current plan, it is proposed to introduce a new signalized intersection at the existing
No Frills site to provide bus-only left-turns into and out of the access. See Figure 3.
Memo
Date: March 18th
, 2013 Page 3
Figure 1: 2010 ECLRT EPR Plan – Weston Road to Black Creek Drive
Memo
Date: March 18th
, 2013 Page 4
Figure 2: Current Proposed ECLRT Plan
Memo
Date: March 18th
, 2013 Page 5
Figure 3: Proposed Signalized Intersection at No Frills Access
Methodology
As part of the 2010 EPR for the ECLRT, traffic impacts associated with the reduction of traffic
capacity in the study area were assessed, and the plan was approved by the Ministry of the
Environment. This approved plan was considered the “base case” for the purposes of the
analysis discussed herein.
Recognizing the potential for impacts associated with the proposed changes to the approved
ECLRT plan are expected to be localized within the study area, existing traffic conditions were
assessed on the basis of weekday AM and PM peak hour turning movement volumes recorded at
the signalized Eglinton Avenue intersections with Weston Road and Black Creek Drive, and at
the signalized Black Creek Drive intersection with Photography Drive. Representative
intersection capacity and level-of-service analyses were carried out using Synchro 7 to compare
relative traffic impacts associated with the proposed changes.
Analysis Parameters
An intersection’s overall operating conditions are typically characterized by two standard
measures: the volume to capacity ratio (V/C) and the level of service (LOS). Taken together,
they provide an indication of delay and the number of vehicles that can be accommodated
through an intersection. The V/C ratio is an indication of the volume of traffic attempting to
make a specific movement through an intersection (i.e., northbound left, westbound straight
through), versus the theoretical capacity of that movement given the lane configurations,
operating conditions and signal timings provided at the intersection. A V/C ratio of 1.0
represents a condition where all available capacity for a particular movement is being used.
Memo
Date: March 18th
, 2013 Page 6
The level of service (LOS) of the overall intersection or a particular movement is a measure of
the average vehicle delay experienced by the motorists attempting to travel through the
intersection. LOS is measured from “A” to “F” with peak hour LOS in the “A” to “D” range
being considered acceptable by most, and a LOS of F representing unacceptable delays.
Critical movements were identified as those operating with a volume-to-capacity (V/C) ratio of
0.85 or higher and/or the poorest level of service (LOS).
Background Traffic
Background traffic data, in the form of 8-hour Turning Movement Counts (TMCs), were applied
in the assessment to form a basis for understanding the overall magnitude of the impacts
associated with the proposed ECLRT. The TMCs were obtained from the City of Toronto, and
are included as Attachment 1. Per the approved 2010 EPR for the ECLRT, the Eglinton Avenue
corridor is assumed to be at or near capacity1, and therefore no growth to background traffic
volumes was applied in the future scenarios.
PPUDO Traffic
Under the current plan, there is an area of the MSF site immediately west of Kodak Building #9
dedicated to a future Passenger Pick-Up/Drop-Off (PPUDO) area associated with the future
Mount Dennis GO Rail Station. The PPUDO area is currently sized for approximately 30
vehicle stopping spaces, capable of accommodating the Kiss and Ride activity generated by the
forecast order-of-magnitude ridership activity2 at the GO Rail station of 400 boardings and 600
alightings in the AM peak hour.
It was assumed that virtually all of the GO Rail alightings at the future Mount Dennis station
would be destined to either local developments (existing or future), or transferring to another
transit system (ECLRT or TTC Bus). As such, the volume of PPUDO activity was limited to a
portion of AM peak hour boardings. For the purposes of the analysis, a 12.3%3 mode-split was
applied to the alighting passengers to determine the total PPUDO activity at the GO Rail Station,
consistent with that observed at the adjacent Weston GO Station. The traffic associated with this
volume was applied in both the AM and PM peak hour investigations.
Bus Traffic
The following TTC bus route changes are proposed for the new bus terminal at Mount Dennis:
• 32 Eglinton West bus service would be shortened to operate from Renforth Station to the
proposed Mount Dennis Bus Terminal, with peak service every 5 minutes.
• 34 Eglinton East bus service would be renamed “34 Eglinton”. Service would operate
from the proposed Mount Dennis Bus Terminal to Kennedy Station, via Eglinton/Yonge
and Eglinton West stations. Peak service would operate every 15 minutes.
• 89 Weston bus service would be revised to serve the proposed Mount Dennis Bus
Terminal in both directions via Weston Road / Black Creek Drive / Eglinton Avenue /
1 See 2010 ECLRT EPR, Appendix M, Section 2.2.
2 Per e-mail from I. Griffiths (Metrolinx), Friday, December 14
th, 2012
3 Per the 2011 GO Rail Passenger Survey, GO Transit
Memo
Date: March 18th
, 2013 Page 7
Weston Road. Local peak service would operate every 5 minutes, with additional
express service every 10 minutes.
• 35 Jane (Jane Station-Steeles) local bus would be split into two routes:
o 35 Jane (Mount Dennis Bus Terminal – Steeles West Station) would operate both
ways via Jane Street and Eglinton Avenue to/from the proposed Mount Dennis
Bus Terminal. Peak service would operate every 3 minutes.
o New 19 Jane South (Jane Station – Mount Dennis Bus Terminal) would operate
both ways via Jane Street / Eglinton Avenue to/from the proposed Mount Dennis
Bus Terminal. Peak service would operate every 6 miuntes.
• 35E Jane Express bus service would operate from the proposed Mount Dennis Bus
Terminal to Steeles West Station via Eglinton Avenue / Jane Street / Steeles Avenue both
ways. Peak service would operate every 10 minutes.
• New 170 Emmett bus service would operate to/from the proposed Mount Dennis Bus
Terminal via Eglinton Avenue / Emmett Avenue / Jane Street / Eglinton Avenue. Peak
service would operate every 15 minutes.
• 161 Rogers Road would be operated to the proposed Mount Dennis Bus Terminal, both
ways via Rogers Road, Weston Road, and Eglinton Avenue. Peak service would operate
every 8 minutes. Service west of Jane Street would be replaced by the revised 171
Mount Dennis service.
• 168 Symington would be extended from the Avon Loop to the proposed Mount Dennis
Bus Terminal, both ways via Weston Road and Eglinton Avenue. Peak service would
operate every 4 minutes.
• 71 Runnymede bus service would operate via the proposed Mount Dennis Bus Terminal,
both ways via Rockliffe Boulevard, Lambton Avenue, Ray Avenue, Industry Street, the
Mount Dennis garage, Industry Street, Todd Baylis Boulevard, Trethewey Drive, Black
Creek Drive, Eglinton Avenue, and return via the reverse routing. Peak service would
operate every 15 minutes.
• 171 Mount Dennis bus service would be changed to operate from the proposed Mount
Dennis Bus Terminal south on Black Creek Drive, west on Humber Boulevard, west on
Alliance Avenue, north on Jane Street, east on Lambton Avenue, south on Rockliffe
Boulevard, east on Alliance Avenue, north on Cliff Street, east on Cordella Avenue, east
on Louvain Street, east on Humber Boulevard, and north on Black Creek Drive. Peak
service would operate every 20 minutes.
The resulting forecast bus movements were reflected in the assessment of the potential impacts
associated with the proposed changes to the LRT plan presented 2010 ECLRT EPR.
Results
The results of the traffic investigation, for the AM and PM peak hours, are presented in the
following tables:
• Table 1: Existing Intersection Level of Service Summary;
Memo
Date: March 18th
, 2013 Page 8
• Table 2: Future (Base Case) Intersection Level of Service Summary; and
• Table 3: Future (w/ Bus Only Signals at No Frills Site Access) Intersection Level of
Service Summary
Note: In Tables 1 through 3, critical movements are highlighted.
Conclusions
The analysis shows that, with the changes proposed under the future scenarios, the study area
intersections are anticipated to operate at acceptable levels. However, the Eglinton Avenue and
Black Creek Drive intersection is approaching capacity, and experiencing critical movements -
LOS of E with V/C ratios approaching 1.0 – in the PM peak hour. This intersection will be very
sensitive to fluctuations in traffic volumes, and leaves little capacity to accommodate future
growth in traffic volumes. The Eglinton Avenue intersection at Weston Road appears to be less
affected, as the overall traffic demand at that intersection is lower than at the Black Creek Drive
intersection, and demand is focused largely on east-west movements.
The incremental impacts associated with the proposed changes (i.e. the signalized bus-only
intersection and PPUDO) appear to be minor over those associated with the approved 2010
ECLRT EPR plan. The introduction of the signal at the No Frills access, provided it is
adequately coordinated with the adjacent Eglinton Avenue/Black Creek Drive intersection, is not
likely to result in any significant impacts on the operation of the Black Creek Drive intersection.
The impact of traffic volumes associated with the proposed Mount Dennis Bus Terminal and
PPUDO do not appear to result in a notable impact on the overall operation of traffic in the study
area.
Next Steps
As indicated earlier, this analysis represents a comparison of the anticipated impacts associated
with the plan presented in the 2010 ECLRT EPR and the current proposed plan. The assessment
is based on high-level plans and does not constitute a formal traffic impact study. A formal
traffic impact study will be required for the recommended plan upon refinement and
confirmation of the MSF design, Mount Dennis Bus Terminal design, and updated ridership
forecasts for the future GO Rail service in light of the introduction of the Mount Dennis GO Rail
station. A formal traffic impact study will be required as part of the site plan application process
for the MSF.
Memo
Date: March 18th
, 2013 Page 9
Table 1: Existing Intersection Level of Service Summary (Optimized)
Balanced 2009/2010 Traffic Counts
Intersection/Movement Existing (2009/2010) AM Peak Hour Existing (2009/2010) PM Peak Hour
Traffic Existing Signal Timing Traffic Existing Signal Timing
Volume V/C Delay(sec) LOS Volume V/C Delay(sec) LOS
Eglinton Avenue at Weston Road
EB Left 209 0.87 48.7 D 142 0.63 25.8 C
EB Through 865 0.62 11.8 B 840 0.44 10.4 B
EB Right 121 0.62 11.8 B 96 0.44 10.4 B
WB Left 57 0.36 16.0 B 42 0.16 9.5 A
WB Through 770 0.48 10.5 B 1036 0.48 11.1 B
WB Right 121 0.17 8.5 A 125 0.13 8.0 A
NB Left 119 0.44 20.6 C 103 0.56 49.8 D
NB Through 513 0.48 16.5 B 371 0.41 37.2 D
NB Right 91 0.17 5.5 A 91 0.20 7.4 A
SB Left 194 0.84 52.1 D 86 0.46 44.8 D
SB Through 348 0.39 14.0 B 286 0.42 34.1 C
SB Right 67 0.39 14.0 B 90 0.42 34.1 C
Intersection Summary 3,475 0.87 16.9 B 3,308 0.63 18.9 B
Eglinton Avenue at Black Creek Drive
EB Left 108 0.51 22.3 C 132 0.67 35.2 D
EB Through 1028 0.89 34.2 C 945 0.88 37 D
EB Right 12 0.03 11.8 B 26 0.07 11.2 B
WB Left 67 0.32 16.9 B 136 0.69 37.1 D
WB Through 801 0.70 25.8 C 1011 0.95 44.4 D
WB Right 65 0.16 6.8 A 65 0.17 7.6 A
NB Left 18 0.18 33.1 C 44 0.48 48.8 D
NB Through 840 0.84 29.8 C 1090 0.9 32.2 C
NB Right 104 0.20 5.0 A 115 0.19 6.0 A
SB Left 132 0.75 54.6 D 124 0.89 84.6 F
SB Through 1130 0.98 44.2 D 1079 0.83 25.3 C
SB Right 129 0.22 4.0 A 148 0.22 3.5 A
Intersection Summary 4,434 0.98 32.5 C 4,915 0.95 33.9 C
Black Creek Drive at Photography Drive
EB Left 41 0.09 14.8 B 31 0.07 17.1 B
EB Right 34 0.08 6.3 A 34 0.08 7.2 A
NB Left 40 0.32 15.2 B 44 0.35 15.6 B
NB Through 919 0.54 9.9 A 1222 0.66 11.1 B
SB Through 1210 0.71 12.4 B 1233 0.67 11.2 B
SB Right 1 0.71 12.4 B 4 0.67 11.2 B
Intersection Summary 2,245 0.45 11.4 B 2,568 0.67 11.2 B
Memo
Date: March 18th
, 2013 Page 10
Table 2: Future (Base Case) Intersection Level of Service Summary
2 GPL / direction on Eglinton Avenue, 0% Growth (per ECLRT EPR 2010)
Intersection/Movement Future (2031) AM Peak Hour Future (2031) PM Peak Hour
Traffic Existing Signal Timing Traffic Existing Signal Timing
Volume V/C Delay(sec) LOS Volume V/C Delay(sec) LOS
Eglinton Avenue at Weston Road
EB Left 209 0.76 28.6 C 142 0.59 17.1 B
EB Through 865 0.57 11.2 B 840 0.53 10.6 B
EB Right 121 0.16 2.4 A 96 0.13 2.2 A
WB Left 57 0.36 20.1 C 42 0.21 14.6 B
WB Through 770 0.78 21.5 C 1036 0.85 24.1 C
WB Right 121 0.27 14.6 B 125 0.23 12.9 B
NB Left 119 0.42 18.8 B 103 0.35 19.9 B
NB Through 513 0.47 15.1 B 371 0.35 16.0 B
NB Right 91 0.17 5.7 A 91 0.17 4.9 A
SB Left 184 0.80 44.4 D 86 0.30 18.6 B
SB Through 348 0.38 12.7 B 286 0.35 13.1 B
SB Right 67 0.38 12.7 B 90 0.35 13.4 B
Intersection Summary 3,465 0.80 17.1 B 3,308 0.85 16.2 B
Eglinton Avenue at No Frills Site Access
EB Through N/A
N/A
EB Right N/A
N/A
WB Left N/A
N/A
WB Through N/A
N/A
NB Left N/A
N/A
NB Right N/A
N/A
Intersection Summary N/A N/A
Eglinton Avenue at Black Creek Drive
EB Left 108 0.6 27.5 C 132 0.89 70.6 E
EB Through 1028 0.94 41.7 D 945 0.9 41.4 D
EB Right 12 0.02 9.2 A 26 0.05 9.3 A
WB Left 67 0.38 18.0 B 136 0.92 77.1 E
WB Through 801 0.74 26.6 C 1011 0.96 50.4 D
WB Right 65 0.13 6.2 A 66 0.15 77.1 B
NB Left 18 0.19 25.7 C 44 0.44 36.9 D
NB Through 840 0.84 33.3 C 1090 0.91 39.3 D
NB Right 104 0.21 7.3 A 115 0.20 9.6 A
SB Left 132 0.67 34.2 C 124 0.84 58.3 E
SB Through 1130 0.79 23.9 C 1079 0.71 22.1 C
SB Right 129 0.19 3.4 A 148 0.20 4.1 A
Intersection Summary 4,434 0.94 29.3 C 4,916 0.96 38.3 D
Black Creek Drive at Photography Drive
EB Left 41 0.2 23.1 C 31 0.16 22.9 C
EB Right 34 0.16 10 B 41 0.5 10.1 B
NB Left 40 0.15 4 A 44 0.17 4.1 A
NB Through 919 0.34 2.7 A 1222 0.45 3.1 A
SB Through 1210 0.45 3.3 A 1233 0.46 3.1 A
SB Right 1 0.45 3.3 A 4 0.46 3.1 A
Intersection Summary 2,245 0.45 3.5 A 2,575 0.46 3.5 A
Memo
Date: March 18th
, 2013 Page 11
Table 3: Future (w/ Bus Only Signals at No Frills Site Access) Intersection Level of Service Summary
2 GPL / direction on Eglinton Avenue, 0% Growth (per ECLRT EPR 2010)
Intersection/Movement Future (2031) AM Peak Hour Future (2031) PM Peak Hour
Traffic Existing Signal Timing Traffic Existing Signal Timing
Volume V/C Delay(sec) LOS Volume V/C Delay(sec) LOS
Eglinton Avenue at Weston Road
EB Left 209 0.91 57.7 E 142 0.64 21.1 C
EB Through 909 0.7 18.2 B 884 0.54 10.9 B
EB Right 121 0.19 3.4 A 96 0.12 2.1 A
WB Left 70 0.58 41.7 D 55 0.27 15.5 B
WB Through 811 0.93 41.0 D 1082 0.83 22.4 C
WB Right 147 0.38 21.2 C 149 0.26 12.9 B
NB Left 119 0.49 25.5 C 103 0.36 21.8 C
NB Through 498 0.54 20.6 C 363 0.34 17.5 B
NB Right 109 0.23 8.2 A 109 0.20 5.8 A
SB Left 200 0.62 19.9 B 104 0.37 21.8 C
SB Through 336 0.29 10.3 B 278 0.34 14.5 B
SB Right 67 0.29 10.3 B 90 0.34 14.5 B
Intersection Summary 3,596 0.74 25.2 C 3,455 0.83 16.4 B
Eglinton Avenue at No Frills Site Access
EB Through 1089 0.83 25.1 C 935 0.72 23.1 C
EB Right 113 0.83 25.1 C 142 0.72 23.1 C
WB Left 11 0.09 41.3 D 11 0.11 46.2 D
WB Through 922 0.59 9.3 A 1180 0.73 22.9 C
NB Left 89 0.18 19.6 B 89 0.18 22.1 C
NB Right 50 0.08 7.1 A 160 0.24 5.0 A
Intersection Summary ,2274 0.83 18.2 B 2,517 0.73 21.9 C
Eglinton Avenue at Black Creek Drive
EB Left 108 0.58 21.8 C 132 0.89 63.3 E
EB Through 1012 0.94 30.2 C 927 0.95 46.3 D
EB Right 28 0.06 6.2 A 42 0.09 3.1 A
WB Left 80 0.46 20.4 C 152 0.91 71.4 E
WB Through 781 0.72 26.2 C 964 0.98 54.9 D
WB Right 65 0.13 5.9 A 66 0.14 11.8 B
NB Left 35 0.37 33.4 C 61 0.58 47.1 D
NB Through 849 0.84 33.4 C 1102 0.90 36.8 D
NB Right 116 0.23 7.3 A 125 0.21 9.2 A
SB Left 132 0.67 34.3 C 124 0.83 56.7 E
SB Through 1144 0.80 24.1 C 1092 0.70 21.3 C
SB Right 130 0.19 3.6 A 149 0.20 3.5 A
Intersection Summary 4,480 0.94 26.5 C 4,936 0.98 38.8 D
Black Creek Drive at Photography Drive
EB Left 79 0.35 26.7 C 70 0.32 26.5 C
EB Right 69 0.28 12.2 B 84 0.35 15.5 B
NB Left 72 0.31 7.8 A 79 0.35 8.7 A
NB Through 919 0.36 3.6 A 1222 0.48 4.1 A
SB Through 1210 0.50 4.4 A 1233 0.51 4.3 A
SB Right 40 0.50 4.4 A 44 0.51 4.3 A
Intersection Summary 2,389 0.50 5.1 A 2,732 0.51 5.3 A
Memo
Date: March 18th
, 2013 Page 12
ATTACHMENT 1
Weston Rd
EXISTING TRAFFIC
AM (PM) Peak Hour
NOTE: 2009 Traffic CountNOTE: 2007 Traffic Count
Eglinton Ave
No Frills
NOTE: 2010 Traffic Count
Photography Dr
Bla
ck C
ree
k D
r
129
1105
(90)
(286)
(81)
67
348
174 801 (940)
66 (163)
83 (134)
527 (1109)
39 (45)
65 (66)(124)
132
(138)
(1290)
975
121
(41)
(930)
(98)
771
(44)
(1402)
805
(1437)
119
513
86
(103)
(371)
(86)
121
(142) 209
(792) 817
(96)
(129) 113
(922) 1077
(25) 13
(35) 34
(50) 34
805
(1437)
1237
(995)
40
1236
(3)
(992)
1
(1288) 649 (1119) 948
(1076) 1203
1184
1114
(1478)
(1069)
(959) 1077
18
Weston Rd
EXISTING TRAFFIC (BALANCED)
AM (PM) Peak Hour
NOTE: 2009 Traffic CountNOTE: 2007 Traffic Count
Eglinton Ave
No Frills
NOTE: 2010 Traffic Count
Photography Dr
(1204) 948
(1103) 1148
Bla
ck C
ree
k D
r
(124)
(90)
(286)
(86)
(148)
(1079)
121 (125) 65 (66)
67
348
184
770 (1036)
129
1130
132
801 (1011)
57 (42) 67 (136)
(1204) 948 (1204) 948
(142) 209 (1018) 1140 (1018) 1140
839.8
104.2
(132) 108
(840) 865
119
513
91
(954) 1109
0
12
39
(945) 1028
18
(96) 121 (64) 31 (26)
(103)
(371)
(91)
(0)
(149)
(1090)
(115)
1211
959.5
(1237)
(1253)
(44)
(162)
(1237)
59
1211
(75) 21
959.5
(1253)
1211
959.5
(1237)
(1253)
(4)
(1233)
1
1210
(44)
(1222)
(31) 41
(50) 34
40
919
Weston Rd FUTURE (2031) TRAFFIC MOVEMENTS (BALANCED)
AM (PM) Peak Hour
Annual Growth (assumed) = 0%
Growth Period (years) = 20
NOTE: Eglinton LRT EPR indicated "turning movement, pedestrian, and bicycle volumes were assumed to remain the same in the future LRT condition"
Eglinton Ave
No Frills
Photography Dr
1148 (1102)
44
1222
948 (1203)
1391
1351
1013
1288
31 41
50 34
40
919
1237
1253
4 1233
1
1210
960
1253
1211
960
162
1242
59
1209
75 21
1090
115
1209
962
1242
1249
103
371
91
149
44
18
840
104
132 108
840 865
119
513
91
953 1109
96 121 64 31 26 12
39
945 1028
1203 948
142 209 1017 1140
801 (1011)
57 42 67 (136)
65 (66)
67
348
184 770 1036
129
1130
132
Bla
ck C
ree
k D
r
90
286
86
148
1079
124
121 125
Weston Rd FUTURE (2031) PPUDO TRAFFIC
AM (PM) Peak Hour
Estimated GO Rail Ridership Boardings in AM Pk Hr 400
Alightings in AM Pk Hr 600
Assumed 12.5% arrival by PPUDO per Weston GO, alightings are destined to LRT
Total PPUDO Traffic = 50 in/out
Distributed per existing traffic distribution
Eglinton Ave
No Frills
Photography Dr
4
9 11
14
Bla
ck C
ree
k D
r
10
13
11
6 13
9
8 6
(11)
17 17 17 17
14
10 12
16 16 16 16
16 16
11
11
39
38
40
39
17
10
12
17
38
39
39
38
12
39 38
11 12
9
40
39
40
39
Weston Rd
EXISTING BUS MOVEMENTS
AM (PM) Peak Hour
Eglinton Ave
No Frills
Photography Dr
0(0)
(0)
(0)
(0) 0
(0) 0
0 0
(0)
(0)
(0)
(0)
0 0
0 0
(0)
(0)
0 0
(0)
(0)
0 0
(0)
(0)
0 0
(0)
(0)
(0)
(0)
(8)
(0)
(0)
(0)
0
(0) 0 (0) 0 (0)
0 0
(0) 0
(18) 20
0 15 0
(18) 20
0
0
0
(18) 20
(23) 26 (23) 26
(0) 0 (18) 20 (18) 20
0 (0)
0 12 0
20 (17)
6 0 0
20 (17)
3 (3) 0 (0)26 (23)
Bla
ck C
ree
k D
r
(0)
(8)
(0)
(6)
(0)
(0)
3 (3)
6(6)
FUTURE BUS MOVEMENTS
AM (PM) Peak Hour
Weston Rd
BUS TERMINAL
Eglinton Ave
No Frills
Photography Dr
Bla
ck C
ree
k D
r
(0)
(0)
(12)
(7)
(0)
(0)
21 (21)
(0)
(0)
0 0 12
52 (52)
7 0 0
0 (0)
0 (0)
16 (16) 4 (4)
0
(0) 0 (82) 82
11 (11)
0
(52) 52
0 0 18
(0) 0
89
0
11
(0) 4
(0) 0 (82)
(0)
4 0
(4)
(0)
(0)
0
(89) 89
(0) 0
0
(0) 0
(23) 23
23
(0)
(0)
(18)
(89)
(11)
82 (0)
(23)
(0)
(7)
7
0
0
(0)
(0)
(0)
(0)
0 0
0(0)
0 0
(11)
(0)
11 0
(0)
0(0)
Weston Rd
BUS TERMINAL
Eglinton Ave
No Frills
Photography Dr
11
79
1222
44
1233
40
1210
79
50
849
1022
1300
84 69
72
919
70
998
1292
1250
998
1277
1292
173
1242
70
1285
1288
927 1012
1209
35
103
363
109
89
160
1102
125
1252
1000
61
116
132 108
42 28
1286 1028
142 209 1097 1218
935 1089
89
96 121 146 113
884 909
119
498
109
11
781 994
70 55 922 1180 80 152
65 66
Bla
ck C
ree
k D
r
1412
1371
0
67
336
200 811 1082
130
1144
132
0
90
278
104
149
1092
124
147 149