2
WHY Regenerator Cleaning? So that the furnace can «breathe» again To reduce fuel costs To avoid the need for an unscheduled furnace repair The problem of blocked regenerators is not new in the glass industry, in fact it has been accommodated in regenerator design over many years by building the passage dimensions fairly large and by building more of them than necessary to permit the flow of gases under natural draught conditions. It was generally understood that a regenerator was built twice the size necessary so that, as it gradually became blocked, the furnace would continue to function. The principal cause of regenerator blocka- ge is the condensation of sulphates in the checker work. The sulphates either come from the fuel, batch or additives to help melting the glass. The carry over from batch materials are also responsible for regene- rator blockage. These materials have much higher melting points and are much difficult to remove by thermal cleaning. However, in most cases batch par- ticles are stuck to the sulphates and will run down the regenerator once these start melting. Melt out of blocked Regenerator Chambers [email protected] www.hotwork.ag

Melt out of blocked Regenerator ChambersWHY Regenerator Cleaning? • So that the furnace can «breathe» again • To reduce fuel costs • To avoid the need for an unscheduled furnace

  • Upload
    others

  • View
    7

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Melt out of blocked Regenerator ChambersWHY Regenerator Cleaning? • So that the furnace can «breathe» again • To reduce fuel costs • To avoid the need for an unscheduled furnace

WHY Regenerator Cleaning?

• So that the furnace can «breathe» again

• To reduce fuel costs

• To avoid the need for an unscheduled furnace repair

The problem of blocked regenerators is not new in the glass industry, in fact it has been accommodated in regenerator design over many years by building the passage dimensions fairly large and by building more of them than necessary to permit the flow of gases under natural draught conditions.

It was generally understood that a regenerator was built twice the size necessary so that, as it gradually became blocked, the furnace would continue to function. The principal cause of regenerator blocka-ge is the condensation of sulphates in the checker work.

The sulphates either come from the fuel, batch or additives to help melting the glass. The carry over from batch materials are also responsible for regene-rator blockage. These materials have much higher melting points and are much difficult to remove by thermal cleaning. However, in most cases batch par-ticles are stuck to the sulphates and will run down the regenerator once these start melting.

Melt out of blocked Regenerator Chambers

[email protected]

Page 2: Melt out of blocked Regenerator ChambersWHY Regenerator Cleaning? • So that the furnace can «breathe» again • To reduce fuel costs • To avoid the need for an unscheduled furnace

The HWI Method

The method consists, briefly, of installing a service burner in the bottom of the regenerator chamber and gradually increasing the temperature.

The maximum permissible temperature limit is set in consultation with the customer with due regard to the refractory materials (normally the rider arches influence the limit).

By appr. 850°C the sulphates begin to melt and run down to the bottom of the regenerators, where they can be caught in a sand pit, and removed from there after resolidification.

This operation can be carried out on several cham-bers, simultaneously or consecutively, without inter-rupting production.

NOTE: This method has been successfully carried out on hundreds of regenerative furnaces

When the clogging of the regenerator is not due pri-marily to sulphates, or if the checker work has failed or in case of any other repair to the regenerator which is needed:

- HWI burners can be used to hold the furnace tem-perature while checkers are replaced or the repair has taken place

- HWI burners can be used for a controlled cool down and consequent heat-up after the repair of the damaged regenerator.

Hotwork International AGRomanshornerstrasse 1239322 EgnachSwitzerlandTel.: +4171 649 [email protected]://www.hotwork.ag

Partner:UAS Messtechnik GmbH

Swiss Quality and German Reliability .... complete engineering and supply

Hotwork International Inc.Cebu, PhilippinesTel.: +63 32 34 13 82 6

Hotwork Solutions Pvt. Ltd.Baroda, Gujarat, India+91 (98) 2516 6837

Hotwork International Inc.Shanghai, ChinaTel.: +86 135 60 79 59 96