Meeting of SEAC-Agenda of 38th meeting I N D E X Item No. Description Page No. 38.1 Re-consideration of Old Proposals for Environmental Clearance. 38.1.1 Application for grant of environmental clearance of M/s Mukesh Udyog Ltd. to establish an Induction Furnace of 20 MT/Heat capacity at Vill. Budhewal, Near Kohara, Distt. Ludhiana 2 38.1.2 Application for grant of environmental clearance for construction of Residential Township to be developed by M/s HPCL Mittal Energy Ltd. at Village Raman & Tarkhanwala, Distt. Bathinda. 3 38.1.3 Application for grant of environmental clearance for Residential Group Housing Project namely “SBP Homes” to be developed at Kharar, Distt. Mohali by M/s Vishav Real Estates Pvt. Ltd. 5 38.1.4 Application for grant of environmental clearance for its Township Project namely “Golf Links” Sector-114, Mohali by M/s Ansal Properties & Infrastructure Ltd. 9 38.2 Consideration of New Proposals for Environmental Clearance. 38.2.1 Application for environmental clearance for Residential Group Housing Project namely “Rosewood Green Housing” to be developed by M/s Virat Infra Projects Pvt. Ltd. at Vill. Sadhe Majra, Habitpur Road, Dera Bassi, Distt. Mohali. 11 38.2.2 Application for obtaining environmental clearance for installation of 7 MW D.G. set in existing grinding unit premises of Grasim Cement – Bathinda (a unit of M/s Grasim Industries Ltd.), behind Guru Hargobind Thermal Power Plant at Vill. Lehra Mohabbat, Tehsil Rampura Phul, Distt. Bathinda. 14 38.2.3 Application for grant of environmental clearance to set up Common Municipal Solid Waste Management Project comprising of processing plant at Jamsher in Jalandhar and Sanitary Landfill at Hoshiarpur. 15 38.2.4 Application for grant of environmental clearance for residential colony namely “Pearls City” at Goniana Road, Bathinda by M/s PACL India Ltd. 17

Meeting of SEAC-Agenda of 38th meetingseiaapunjab.co.in/Agenda of 38th meeting.pdfMeeting of SEAC-Agenda of 38th meeting I N D E X Item No. Description Page No. 38.1 Re-consideration

Embed Size (px)

Citation preview

Meeting of SEAC-Agenda of 38th meeting

I N D E X

Item No. Description Page No.

38.1 Re-consideration of Old Proposals for Environmental Clearance.

38.1.1 Application for grant of environmental clearance of M/s Mukesh Udyog Ltd. to establish an Induction Furnace of 20 MT/Heat capacity at Vill. Budhewal, Near Kohara, Distt. Ludhiana

2

38.1.2 Application for grant of environmental clearance for construction of Residential Township to be developed by M/s HPCL Mittal Energy Ltd. at Village Raman & Tarkhanwala, Distt. Bathinda.

3

38.1.3 Application for grant of environmental clearance for Residential Group Housing Project namely “SBP Homes” to be developed at Kharar, Distt. Mohali by M/s Vishav Real Estates Pvt. Ltd.

5

38.1.4 Application for grant of environmental clearance for its Township Project namely “Golf Links” Sector-114, Mohali by M/s Ansal Properties & Infrastructure Ltd.

9

38.2 Consideration of New Proposals for Environmental Clearance.

38.2.1 Application for environmental clearance for Residential Group Housing Project namely “Rosewood Green Housing” to be developed by M/s Virat Infra Projects Pvt. Ltd. at Vill. Sadhe Majra, Habitpur Road, Dera Bassi, Distt. Mohali.

11

38.2.2 Application for obtaining environmental clearance for installation of 7 MW D.G. set in existing grinding unit premises of Grasim Cement – Bathinda (a unit of M/s Grasim Industries Ltd.), behind Guru Hargobind Thermal Power Plant at Vill. Lehra Mohabbat, Tehsil Rampura Phul, Distt. Bathinda.

14

38.2.3 Application for grant of environmental clearance to set up Common Municipal Solid Waste Management Project comprising of processing plant at Jamsher in Jalandhar and Sanitary Landfill at Hoshiarpur.

15

38.2.4 Application for grant of environmental clearance for residential colony namely “Pearls City” at Goniana Road, Bathinda by M/s PACL India Ltd.

17

Meeting of SEAC-Agenda of 38th meeting

2

38.1.1 Application for grant of environmental clearance of M/s

Mukesh Udyog Ltd. to establish an Induction Furnace of 20 MT / Heat capacity at Vill. Budhewal, Near Kohara, Distt. Ludhiana

The industry has submitted an application for grant of environmental

clearance for setting up an Induction Furnace of 20 MT / Heat capacity at Village

Budhewal, Near Kohara, Distt. Ludhiana. The TORs were issued by the SEAC

vide letter no.10957 dated 27.3.09.

The project proponent submitted EIA report as per TORs approved

by the Committee and requested to exempt it from the public hearing as it falls in

Medium & Heavy Industry Zone as per Master Plan Ludhiana (2007-2021).

The case of the industry was considered by the Committee in its 35th

meeting held on 9/1/2010 wherein, the committee decided to exempt the unit from

public consultation, as the project falls in medium and heavy industrial zone in the

notified Master Plan of Ludhiana 2007-2021.

Meanwhile, the Ministry of Environment and Forests, New Delhi vide

its Office memorandum no.J-11013/5/2010-IA.II(I) dated 13.1.2010 has imposed

temporary restrictions on consideration of the development projects from critically

polluted industrial areas and has decided that the development projects from

industrial clusters with Comprehensive Environment Pollution Index (CEPI) score

above 70, received for grant of environmental clearance in terms of the provisions

of EIA notification, 2006 [(including project for stage I clearance i.e. scoping

(TOR’s)], which are presently in the pipeline for environmental clearance or which

would be received hereafter shall be returned to the project proponents.

The Authority in its 27th meeting held on 30/1/2010 has decided to

refer the case to SEAC for re-examining the same in view of Office Memorandum

dated 13/1/2010 issued by Ministry of Environment & Forests.

Accordingly, the case of the industry is placed before the Committee

for reconsideration.

Meeting of SEAC-Agenda of 38th meeting

3

38.1.2 Application for grant of environmental clearance for

construction of Residential Township to be developed by M/s HPCL Mittal Energy Ltd. at Village Raman & Tarkhanwala, Distt. Bathinda.

The project proponent has submitted application for grant of

environmental clearance for setting up residential township at Village Raman &

Tarkhanwala, Distt. Bathinda.

The case was considered by SEAC in its 23rd meeting held on

6.6.2009, wherein, the Committee awarded ‘Gold Grading’ to the project and

recommended the project to State Environment Impact Assessment Authority for

grant of environmental clearance subject to the conditions mentioned therein, only

after the receipt of following documents from the project proponent and thereafter

satisfactory acceptance of same by the Chairman and Secretary of State Expert

Appraisal Committee:-

i) The project proponent shall submit revised layout plan of the complex

indicating the area where the municipal solid waste will be collected.

ii) The project proponent is required to upgrade the water balance chart for

rainy season.

The project proponent submitted the desired documents to the

satisfaction of the secretary as well as Chairman of State Expert Appraisal

Committee. Accordingly, the case was forwarded by SEAC to SEIAA for grant of

environmental clearance.

The case was considered by the Authority in its 23rd meeting held on

7.11.2009, wherein, the authority requested the project proponent to submit the

following documents/information within 15 days.

1. Approved layout plan or documentary evidence from the Competent

Authority regarding exemption from obtaining approval of layout plan.

2. Water balance for the rainy season including details for justification

regarding quantity of water to be used/wastewater to be generated and

adequacy of land for disposal of wastewater.

3. Safety report from the competent authority to the effect that the distance

of township from the refinery unit is adequate.

The project proponent has submitted the information/documents

vide letter dtd.1.1.2010 (copy enclosed as Annexure-I).

Meeting of SEAC-Agenda of 38th meeting

4

Meanwhile, the Ministry of Environment and Forests, New Delhi vide

its notification no. GSR 826 (E) dtd.16.11.2009 has amended the schedule-VII

regarding National Ambient Air Quality Standards; these standards have become

effective from the date of its notification i.e. 16.11.2009.

The case was considered by the Authority in its 26th meeting held on

15/1/2010 has decided that the case be forwarded to SEAC to re-examine the

same in view of new notification dated 16/11/2009 for AAQM standards as well as

the reply dated 1/1/2010 submitted by the project proponent to the observations of

the Authority.

Accordingly, the case of the project proponent is placed before the

Committee for reconsideration.

Meeting of SEAC-Agenda of 38th meeting

5

38.1.3 Application for grant of environmental clearance for

Residential Group Housing Project namely “SBP Homes” to be developed at Kharar, Distt. Mohali by M/s Vishav Real Estates Pvt. Ltd.

The project proponent M/s Vishav Real Estates Pvt. Ltd. has applied

for grant of environmental clearance for development of a Residential Group

Housing project namely “SBP Homes” at Kharar, Distt. Mohali. The total area of

the proposed project is 22,458 sq. m. and the builtup area of the project is 29,820

sqm. The expected cost of the project is Rs.35 crore. The project will cover under

screening category 8 (a) of the schedule attached to EIA notification dated

14/9/2006.

The proposed project is coming up on the agricultural land as per

the Master Plan of GMADA and the expected population is 1665. The proposed

complex need 244 Kl of water per day. Out of which 150 Kl/day of fresh water will

be met through ground water and 94 Kl/day will be recycled treated water. The

project proponent proposes to install sewage treatment plant of capacity 200

Kl/day. The treated effluent will be used for flushing, green area and in sewer.

The project will require approx. 1600 KW of electricity and will be

supplied by the PSEB authorities. The project proponent has proposed to provide.

D.G. sets for power back up in case of electricity failure, wherever it is required.

The incompletions were conveyed to the promoter vide letter no.

37656 dated 13/10/2009 and then letter no. 38371 dated 23/11/2009.

The project proponent submitted certain reply vide letter dated

29/10/2009 & 11/12/2009 of observations conveyed to him vide letter no. no.

37656 dated 13/10/2009 & no. 38371 dated 23/11/2009, respectively.

The consolidated status of documents / reply submitted by the

project proponent is as under:-

1. Properly filled Form 1 & 1A Yes

2. Proof of ownership of land Not submitted

3. CLU status The project proponent has stated that it is not applicable as the project is within M.C. limits of Kharar.

4. Approved Layout plan and Building plan from Competent Authority.

Not submitted, however, the project proponent has stated that M.C. has technically approved the plans and

Meeting of SEAC-Agenda of 38th meeting

6

thereafter deposited Rs.28,78,027/- for approval of maps with M.C. Kharar and enclosed a copy of receipt dated 12/10/09.

5. Topographical map of the area showing Contour Plan.

Submitted

6. Status of construction, if any, alongwith photographs from all the four sides.

Submitted

7. 500 meter radius map of the area from periphery of project site clearly indicating the various industries (specifically red category industries) and structures lying in the area.

Submitted. A rice sheller exists at a distance of 12 m from the proposed site.

8. Certificates from authorized departments regarding

a) State Boundary not within 10 Km.

b) Project not lying in eco-sensitive and protected area including wild life sanctuaries.

c) Not lying in the critically polluted areas.

Not required

9. Site plan of the project showing the following i) Location of STP ; ii) Solid waste storage area. iii) Green belt iv) Parking space v) RWH and water recharge pits vi) Fire fighting equipment layout vii) First aid room viii) Location of Tubewells

i) Marked on the site plan ii) Marked on the site plan iii) Marked on the site plan iv) Marked on the site plan v) Marked on the site plan v) Marked on the site plan vii) Marked on the site plan viii) Not marked on the site plan

10. Permission of Competent Authority for;

a) Water and Sewerage connection

b) Collection of Solid waste

c) Use of Ground Water

a) Permission regarding discharge of sewage from M.C. submitted.

b) Permission regarding discharge of solid waste from M.C. submitted.

c) Not submitted, the project proponent stated that they will apply to CGWA in due course of time. However, the project proponent enclosed a certificate no. 1481 dated 8/1/2010 issued by M.C., Kharar to the effect that in case, the project

Meeting of SEAC-Agenda of 38th meeting

7

proponent deposits requisite charges with M.C., then M.C. has no objection for providing water supply to the project.

11. Water balance chart for summer, rainy and winter seasons indicating critical requirements.

Submitted

12. Availability of adequate land for use of treated sewage and plantation.

Not applicable as permission regarding discharge of sewage from M.C. submitted.

13. Analysis reports of ambient air, ground water and noise levels from NABL Accredited laboratories.

Submitted.

14. Quantification of energy saved and renewable energy devices used and permission of PSEB for power connection.

Submitted.

15. Drawing showing plumbing systems for use of fresh, treated and hot water

Submitted, but incomplete.

16. Construction schedule (PERT/CPM Chart)

Not submitted, the project proponent stated that it will be submitted at the time of presentation.

17. Affidavits for ;

a) Constitution of Environment Monitoring Cell

b) Use of ready mix concrete or use of fly ash during construction.

c) To provide Fire Fighting System

a) Affidavit dated 15/9/09 submitted b) Affidavit dated 15/9/09 and 20/10/2009 submitted. c) Marked on the site plan

18. a) To provide wind breaking curtains and water sprinkling system to minimize dust emissions.

b) To provide adequate safety measures for the construction workers during the construction phase.

a) Affidavit dated 15/9/09 submitted b) –do-

The reply submitted by the project proponent vide letter dated

29/10/2009 & 11/12/2009 was placed before State Expert Appraisal Committee in

its 35th meeting held on 9/1/2009, which was not attended by the project

proponent. Therefore, the Committee decided to defer the case.

Now, the project proponent vide letter dated 10/2/2010 (Copy

enclosed as per Annexure-II) has submitted basic information as per MoEF

Notification dated 1/12/2009 and also submitted ambient air quality monitoring

Meeting of SEAC-Agenda of 38th meeting

8

results as per MoEF Notification dated 16/11/2009. He has also enclosed a

certificate no. 1481 dated 8/1/2010 issued by Municipal Council, Kharar to the

effect that in case, the project proponent deposits requisite charges with M.C.,

then M.C. has no objection for providing water supply to the project.

Accordingly, the case is placed before the Committee for

reconsideration.

Meeting of SEAC-Agenda of 38th meeting

9

38.1.4 Application for grant of environmental clearance for its

Township Project namely “Golf Links” Sector-114, Mohali by M/s Ansal Properties & Infrastructure Ltd.

The project proponent M/s Ansal Properties and Infrastructure Ltd.

has applied for environmental clearance for establishment of a Township Project

namely ‘Golf Links’ at Sector-114, Mohali. The project proponent have earlier

obtained environmental clearance from MoEF vide no. 21-510/2007-IA.III dated

29/2/2008 for 168.09 acres. Now, the project proponent has submitted revised

application for an area of 227.30 acres. The project is covered under screening

category 8 (a) of the schedule attached to EIA notification dated 14/9/2006.

The case of the project proponent was considered in 33rd meeting of

State Expert Appraisal Committee held on 28/11/2009. After the detailed

deliberations, the Committee requested the project proponent to submit certain

details / data for considering their case for grant of environmental clearance.

Now, the project proponent vide letter dated 20/1/2010 has

submitted certain details / documents. The status of the documents / details

submitted by the project proponent is as under :-

Sr.No. Observation Reply submitted by the project proponent

1. Ambient Air Quality Monitoring for one

month period (twice a week 24 hourly

at uniform intervals) from the NABL /

MoEF accredited lab for all pollutants

mentioned in the notification no. GSR.

826(E) dated 16/11/2009.

Submitted

2. Permission from CGWA for

abstraction of ground water @ 2064

Kl/day.

Not submitted, however applied

to CGWA vide letter dated

10/12/2009

3. The promoter should submit

photographs of the project site from all

the four angles to oversee, if any

construction activity has been

undertaken or not.

Submitted

4. The promoter should submit copy of

permission from GMADA for collection

Not submitted, however a copy

of Memorandum of agreement

Meeting of SEAC-Agenda of 38th meeting

10

and disposal of solid waste generated

from the proposed project.

signed with State Govt.

submitted.

5. The project proponent should submit

construction schedule (CPM / PERT

chart).

Submitted

It is pertinent to mention here that Ministry of Environment & Forests

vide notification no. SO 3067(E) dated 1/12/2009 has substituted certain columns

in basic information of Form-I appended with the EIA Notification No. SO 1533(E)

dated 14/9/2006. The amended columns in basic information are required to be

filled by the project proponent.

The case of the project proponent is placed before the Committee

for consideration.

Meeting of SEAC-Agenda of 38th meeting

11

38.2.1 Application for environmental clearance for Residential Group

Housing Project namely “Rosewood Green Housing” to be developed by M/s Virat Infra Projects Pvt. Ltd. at Vill. Sadhe Majra, Habitpur Road, Dera Bassi, Distt. Mohali.

Earlier, the application submitted by the project proponent for grant

of environmental clearance for proposed Residential Group Housing Project

namely “Rosewood Green Housing” at Vill. Sadhe Majra, Habitpur Road, Dera

Bassi, Distt. Mohali was refused vide no. 37379 dated 16/11/2009 due to following

reasons :-

1. There is a rice sheller namely M/s Amrit Rice Mills falls at a distance of 290

m against the required distance of 500 m from the proposed site of the

project. As such, the proposed site violates the siting criteria framed by the

Govt. of Punjab for establishment of residential colonies / commercial

establishments etc. vide its notification No.3/6/07/STE(4)/2274 dated, 25th

July, 2008.

2. During 30th meeting of State Expert Appraisal Committee held on

10/10/2009, the Committee noted that a pesticide formulation unit is also

operating in the vicinity of site at a distance of 236 m which may prove

dangerous to the residents of colony. The project proponent has also

concealed the facts in the map of 500 m area from the periphery of site

submitted by it, which is a vital information for consideration of the case for

environmental clearance.

The project proponent has submitted fresh application for grant of

environmental clearance for Residential Group Housing Project namely

“Rosewood Green Housing” to be developed at Vill. Sadhe Majra, Habitpur Road,

Dera Bassi, Distt. Mohali. The project promoter has applied for screening category

8 (a) of the schedule attached to EIA notification dated 14/9/2006.

As per Form-I, Form-IA and EMP submitted by the project proponent

the plot area of the project is 3.92 acres / 1.58922 ha / 15892.2 sqm. and the

builtup area is 44780 sqm. In the complex, there will be 250 flats and the designed

population is 1250.

The water requirement shall be 159 Kl/day. The project proponent

proposed to install sewage treatment plant based on activated sludge process.

After treatment, the treated sewage would be used for gardening and in toilets for

Meeting of SEAC-Agenda of 38th meeting

12

flushing. The remaining treated sewage shall be discharged into sewer. Solid

waste @ 500 Kg/day would be generated. The total energy requirement for the

project is 2122 KW. The project proponent has proposed to install 2 no. D.G. sets

of capacity 750 KVA each as stand-by arrangements.

The other details of the project have been given in the Form 1 & 1-A

(Copy enclosed as Annexure-III) submitted by the promoter and the details of

the proposed project are as under:

1. Properly filled Form 1 & 1A Yes

2. Proof of ownership of land Not submitted.

3. CLU status Not submitted, however, the project proponent stated that the land falls under the mixed use as per Master Plan of Dera Bassi approved by DTP, SAS Nagar on 29/9/2009.

4. Approved Layout plan and Building plan from Competent Authority.

Approved layout plan submitted.

5. Topographical map of the area showing Contour Plan.

Submitted.

6. Status of construction, if any, alongwith photographs from all the four sides.

Not Submitted.

7. 500 meter radius map of the area from periphery of project site clearly indicating the various industries (specifically red category industries) and structures lying in the area.

Submitted.

8. Certificates from authorized departments regarding a) State Boundary not within 10 Km. b) Project not lying in eco-sensitive and

protected area including wild life sanctuaries.

c) Not lying in the critically polluted areas.

Not required.

9. Site plan of the project showing the following i) Location of STP ; ii) Solid waste storage area. iii) Green belt iv) Parking space v) RWH and water recharge pits vi) Fire fighting equipment layout vii) First aid room viii) Location of Tubewells

i) Marked on the site plan. ii) –do- iii) Landscaping plan submitted iv) Parking plan submitted v) Marked on the site plan vi) Fire fighting plan submitted vii) Not marked on the site plan viii)Marked on the site plan

Meeting of SEAC-Agenda of 38th meeting

13

10. Permission of Competent Authority for; a) Water and Sewerage connection b) Collection of Solid waste c) Use of Ground Water

a) M.C., Dera Bassi has given NOC vide letter no. 128 dated 28/1/2009. b) –do- c) Not submitted, however, applied to CGWA.

11. Water balance chart for summer, rainy and winter seasons indicating critical requirements.

Submitted

12. Availability of adequate land for use of treated sewage and plantation.

Not applicable, as the M.C. Dera Bassi has given NOC vide no. 128 dated 28/1/2009.

13. Analysis reports of ambient air, ground water and noise levels from NABL Accredited laboratories.

Submitted, however, the project proponent has got Ambient Air Monitoring done for one month period (once a week instead of twice a week).

14. Quantification of energy saved and renewable energy devices used and permission of PSEB for power connection.

Not submitted, but energy saving practices mentioned.

15. Drawing showing plumbing systems for use of fresh, treated and hot water

Not submitted.

16. Construction schedule (PERT/CPM Chart) Not submitted.

17. Affidavits for ; a) Constitution of Environment

Monitoring Cell b) Use of ready mix concrete or use of

fly ash during construction. c) To provide Fire Fighting System d) To provide wind breaking curtains and

water sprinkling system to minimize dust emissions.

e) To provide adequate safety measures for the construction workers during the construction phase.

a) Not submitted. b) –do- c) Fire fighting layout plan

submitted d) Not submitted e) Not submitted

The case of the project proponent is placed before the Committee

for consideration.

Meeting of SEAC-Agenda of 38th meeting

14

38.2.2 Application for obtaining environmental clearance for

installation of 7 MW D.G. set in existing grinding unit premises of Grasim Cement – Bathinda (a unit of M/s Grasim Industries Ltd.), behind Guru Hargobind Thermal Power Plant at Vill. Lehra Mohabbat, Tehsil Rampura Phul, Distt. Bathinda.

The project proponent has submitted application for obtaining

environmental clearance for installation of 7 MW D.G. set in existing grinding unit

premises of Grasim Cement – Bathinda (a unit of M/s Grasim Industries Ltd.),

behind Guru Hargobind Thermal Power Plant at Vill. Lehra Mohabbat, Tehsil

Rampura Phul, Distt. Bathinda.

As per Form-I and pre-feasibility report submitted by the industry,

the brief details of the project are as under :-

• The project is covered under Category-B {at sr. no. 1(d)} of the

Schedule attached to EIA notification dated 14/9/2006.

• The total area of the grinding unit is 40.46 hectare, however, the D.G.

set will be installed in an area of 1 hectare.

• The existing grinding unit as already obtained environmental clearance

from Ministry of Environment & Forests vide dated 5/2/2008 and

enclosed a copy of environmental clearance.

• The total power requirement of the existing cement grinding unit is 7.8

MW. As per project proponent, there is power scarcity in the area due to

which continuous power is not being obtained from PSEB, which results

in loss of production. To combat power crunch in the cement grinding

unit the industry is proposing to install D.G. set of capacity 7 MW to

supply the power to the existing grinding unit.

• The HFO / LOF @ 1.6 Kl/hr. will be used as fuel in the D.G. set. A stack

of 74 m will be installed with the D.G. set.

• The cost of the project is Rs.30 crores.

• The water requirement for the D.G. set cooling is 170 m3/day.

• The other details of the project have been given in the Form 1 and pre-

feasibility report (copy enclosed as Annexure-IV) submitted by the

promoter.

The case of the project proponent is placed before the Committee

for consideration.

Meeting of SEAC-Agenda of 38th meeting

15

38.2.3 Application for grant of environmental clearance to set up

Common Municipal Solid Waste Management Project comprising of processing plant at Jamsher in Jalandhar and Sanitary Landfill at Hoshiarpur.

The Department of Local Govt. Punjab, has initiated development of

project for scientific management of MSW in the State. For this purpose, the State

has been divided into 7 Regional Clusters viz GMADA / Patiala, Jalandhar,

Ferozepur, Bathinda, Pathankot, Ludhiana and Amritsar.

The integrated MSW management facility for Jalandhar Cluster

comprising of Jalandhar City and 25 other ULBs. For accomplishing the objective,

Department of Local Govt. Punjab has appointed IL&FS to develop and structure

the project, covering all ULBs in the region and obtains all required clearances /

authorizations to fasten the process of the project implementation.

As per Form-I and Pre-feasibility Report (Copy enclosed as

Annexure-V) submitted by the project proponent, the details of CMSWM is as

under :-

• The project is covered at Sr. No. 7(i) of the Schedule appended with EIA

notification dated 14/9/2006.

• The Integrated MSW Management Plant for Jalandhar Cluster shall

comprise of MSW processing facility at Jamsher Village in Jalandhar and

Engineered Sanitary landfill site at Hoshiarpur to dispose off processing

rejects / inerts. The facilities aimed at processing 750 TPD of MSW

generated from 26 ULBs constituting the Jalandhar Cluster.

• The processing facilities located near Jamsher Village occupies approx. 15

acres of land and is 10 Km away from Jalandhar City. The land has been

allocated by Jalandhar for the development of MSW Management System.

• The sanitary landfill site located at Hoshiarpur occupies approx. 25.6 acres

of land and is approx. 47 km from processing site and 4 Km from

Hoshiarpur City. The proposed integrated MSW processing facility would

comprise ;

a) At Jalandhar ;

i) Refuse Derived Fuel (RDF) Plant – 700 TPD

ii) Bio-methanization plant – 50 TPD

iii) Compost / Curing plant – 200 TPD

iv) A power plant of 6 MW (optional)

Meeting of SEAC-Agenda of 38th meeting

16

b) At Hoshiarpur ;

i) Engineered Sanitary Landfill facility

• The expected cost of the project is Rs.130 Crores (inclusive of power plant

component).

• The power requirement is 1200 KW, however, if there is a power plant the

project will be net energy producer. D.G. sets of capacity 250 KVA will be

installed as backup power supply.

• The consumption of the water would be 150 m3/day and the fresh water

demand will be 60 m3/day.

• The effluent treatment plant of capacity 120 m3/day will be designed. The

effluent from the integrated MSW processing plant will be treated before

discharging into a nearby drain / nallah.

• The other details of the project are included in Form 1 and EMP submitted

by the promoter.

The case of the project proponent is placed before the Committee

for consideration.

Meeting of SEAC-Agenda of 38th meeting

17

38.2.4 Application for grant of environmental clearance for

residential colony namely “Pearls City” at Goniana Road, Bathinda by M/s PACL India Ltd.

The project proponent has applied for grant of environmental

clearance for development of residential colony namely “Pearls City” at Goniana

Road, Bathinda by M/s PACL India Ltd. The plot area of the proposed project is

125.93 acres (50.95 hectares). The expected cost of the project is Rs.100 crore.

The land is a part of residential development as per the local land use plan of

Bathinda. The water consumption for the project will be 1415 Kl/day and will be

sourced through ground water. The 2 no. sewage treatment plants of capacity 600

m3/day each would be installed. The project will generate @ 2.5 MTD of municipal

solid waste. The power requirement in the project is 15 MW and the same will be

sourced through PSEB. The project proponent will provide D.G. sets for power

backup. The project proponent has submitted duly filled columns in basic

information of amended Form-I as notified vide notification no. SO 3067(E) dated

1/12/2009. The project will cover under screening category 8 (a) of the schedule

attached to EIA notification dated 14/9/2006.

The other details of the project have been given in the Form 1 & 1-A

submitted by the promoter (Copy enclosed as Annexure-VI) and the brief details

of the proposed project are as under:

1. Properly filled Form 1 & 1A Yes

2. Proof of ownership of land Submitted.

3. CLU status CLU granted for 125.93 acre by CTP, Punjab vide letter no. 9101 dated 20/11/2008.

4. Approved Layout plan and Building plan from Competent Authority.

Approved layout plan under PAPR Act submitted.

5. Topographical map of the area showing Contour Plan.

Submitted.

6. Status of construction, if any, alongwith photographs from all the four sides.

Submitted.

7. 500 meter radius map of the area from periphery of project site clearly indicating the various industries (specifically red category industries) and structures lying in the area.

Submitted.

8. Certificates from authorized departments regarding

Not required.

Meeting of SEAC-Agenda of 38th meeting

18

a) State Boundary not within 10 Km. b) Project not lying in eco-sensitive and

protected area including wild life sanctuaries.

c) Not lying in the critically polluted areas.

9. Site plan of the project showing the following i) Location of STP ; ii) Solid waste storage area. iii) Green belt iv) Parking space v) RWH and water recharge pits vi) Fire fighting equipment layout vii) First aid room viii) Location of Tubewells

i) Marked on the site plan. ii) As per 10 (b) iii) Marked on the site plan iv) Not marked on the site plan v) Marked on the site plan vi) Not marked on the site plan vii) Marked on the site plan viii)Marked on the site plan

10. Permission of Competent Authority for; a) Water and Sewerage connection b) Collection of Solid waste c) Use of Ground Water

a) & b) The project proponent has submitted an affidavit dated 18/3/2009 to the effect that they would develop MSW facility and disposing of part of their treated wastewater onland measuring 17 acres having Khasra Nos. of the land. c) Not submitted

11. Water balance chart for summer, rainy and winter seasons indicating critical requirements.

Submitted

12. Availability of adequate land for use of treated sewage and plantation.

As per 10 (a) above.

13. Analysis reports of ambient air, ground water and noise levels from NABL Accredited laboratories.

Analysis reports of noise and ground water submitted. Analysis report of ambient air not submitted.

14. Quantification of energy saved and renewable energy devices used and permission of PSEB for power connection.

Submitted.

15. Drawing showing plumbing systems for use of fresh, treated and hot water

Not submitted.

16. Construction schedule (PERT/CPM Chart) Submitted.

17. Affidavits for ;

Meeting of SEAC-Agenda of 38th meeting

19

a) Constitution of Environment Monitoring Cell

b) Use of ready mix concrete or use of fly ash during construction.

c) To provide Fire Fighting System d) To provide wind breaking curtains

and water sprinkling system to minimize dust emissions.

e) To provide adequate safety measures for the construction workers during the construction phase.

Submitted

The case of the project proponent is placed before the Committee

for consideration.

* * * * *

Meeting of SEAC-Agenda of 38th meeting

Meeting of SEAC-Agenda of 38th meeting

Sub: Agenda for the 38th meeting of State Expert Appraisal Committee.

The draft agenda of the 38th meeting of State Expert Appraisal

Committee has been prepared and included following items in the agenda :-

Sr. No. Description of the project

Re-consideration of Old Proposals for Environmental Clearance.

1 Application for grant of environmental clearance of M/s Mukesh Udyog Ltd. to establish an Induction Furnace of 20 MT/Heat capacity at Vill. Budhewal, Near Kohara, Distt. Ludhiana

2 Application for grant of environmental clearance for construction of Residential Township to be developed by M/s HPCL Mittal Energy Ltd. at Village Raman & Tarkhanwala, Distt. Bathinda.

3 Application for grant of environmental clearance for Residential Group Housing Project namely “SBP Homes” to be developed at Kharar, Distt. Mohali by M/s Vishav Real Estates Pvt. Ltd.

4 Application for grant of environmental clearance for its Township Project namely “Golf Links” Sector-114, Mohali by M/s Ansal Properties & Infrastructure Ltd.

Consideration of New Proposals for Environmental Clearance.

5 Application for environmental clearance for Residential Group Housing Project namely “Rosewood Green Housing” to be developed by M/s Virat Infra Projects Pvt. Ltd. at Vill. Sadhe Majra, Habitpur Road, Dera Bassi, Distt. Mohali.

6 Application for obtaining environmental clearance for installation of 7 MW D.G. set in existing grinding unit premises of Grasim Cement – Bathinda (a unit of M/s Grasim Industries Ltd.), behind Guru Hargobind Thermal Power Plant at Vill. Lehra Mohabbat, Tehsil Rampura Phul, Distt. Bathinda.

7 Application for grant of environmental clearance to set up Common Municipal Solid Waste Management Project comprising of processing plant at Jamsher in Jalandhar and Sanitary Landfill at Hoshiarpur.

8 Application for grant of environmental clearance for residential colony namely “Pearls City” at Goniana Road, Bathinda by M/s PACL India Ltd.

If approved, the 38th meeting of State Expert Appraisal Committee

may be convened in the Committee Room of Punjab Pollution Control Board,

Vatavaran Bhawan, Nabha Road, Patiala on 13/3/2010 at 9:30 a.m. and detailed

draft agenda of 38th meeting is also placed below for approval please.

AEE (SEAC)

EE (SEAC) Secretary (SEAC) Chairman (SEAC)

Meeting of SEAC-Agenda of 38th meeting

STATE EXPERT APPRAISAL COMMITTEE, PUNJAB Ministry of Environment and Forests, Government of India

O/O Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road,

Patiala – 147 001

Telefax:- 0175-2215802

No. SEAC/Gen./1/10782-89 Dated 2/3/2010 SPEED POST

To

1. Dr. Anil Kumar Jain, Director, SSS-National Institute of Renewable Energy, Kapurthala.

Chairman (SEAC)

2 Dr. Neelima Jerath, Executive Director, PSCST, Chandigarh.

Member (SEAC)

3. Dr. Vineet Kumar, Associate Professor, Deptt. of Chemical Engg. Indian Institute of Technology, Roorkee – 247667

Member (SEAC)

4. Dr. S.S. Marwaha, Chief Executive Officer, Punjab Bio-Technology Incubator, SCO-8 (Top Floor), Phase-V, Mohali.

Member (SEAC)

5. Dr. Rajiv Mohan Mathur, Director, Central Pulp & Paper Research Institute, Saharanpur.

Member (SEAC)

6. Dr. Girish Sahni, Director, Institute of Microbial Technology, Sector 39-A, Chandigarh.

Member (SEAC)

7. Dr. Maneek Kumar, Professor & Head, Deptt. of Civil Engineering, Thapar University, Patiala.

Member (SEAC)

8. Er. Malvinder Singh, Senior Environmental Engineer, Punjab Pollution Control Board, Patiala.

Secretary (SEAC)

Meeting of SEAC-Agenda of 38th meeting

Sub: Agenda of 38th meeting of State Expert Appraisal Committee to be held on 13/3/2010 at 9:30 a.m. at Patiala.

This is to inform you that the 38th meeting of State Expert Appraisal

Committee will be held on 13/3/2010 at 9:30 a.m. in the Committee Room,

Punjab Pollution Control Board, Vatavaran Bhawan, Nabha Road, Patiala. The

agenda of the meeting is enclosed herewith.

You are requested to make it convenient to attend the meeting on the

above said date, time and venue.

DA/- Agenda (Malvinder Singh) Secretary (SEAC)

Endst. No. _______ Dated _________

A copy of the above is forwarded to the following for information & necessary action:-

1. The P.S. to Chairman, Punjab Pollution Control Board, Patiala for information of the Chairman.

2. The P.A. to Member Secretary, Punjab Pollution Control Board, Patiala for information please.

3. Dr. Daljit Singh, Chairman, State Level Environment Impact Assessment Authority, 693, Sector-8, Chandigarh.

4. Er. Sukhminder Singh Gill, Engineer-in-Chief (Retd.), Member, SEIAA, 90-C, Bhai Randhir Singh Nagar, Near DAV School, Ludhiana.

5. The Member Secretary, State Environment Impact Assessment Authority, O/o Punjab Pollution Control Board, Patiala.

6. The Deputy Controller (F & A), Punjab Pollution Control Board, Patiala. He is requested to make arrangements for paying T.A./D.A. to the members of the Committee.

7. The Senior Environmental Engineer (Computer Section), Punjab Pollution Control Board, Patiala. He is requested to depute a data entry operator for operating the laptop during the meeting.

8. The Environmental Engineer (Construction), Punjab Pollution Control Board, Patiala. He is requested to depute an operator for operating the D.G. set during the meeting.

9. The Caretaker, Punjab Pollution Control Board, Head Office, Patiala for making proper arrangements to conduct the meeting.

DA/- Agenda

(Malvinder Singh) Secretary (SEAC)