ID Task Name Duration Start Finish 1 PROPOSED SERVICED APARTMENT IN LOT 1342 SELAYANG, MUKIM RAWANG 1103 days Mon 01/09/14 Wed 21/11/18 2 Architectural Planning / Layout 77 days Mon 01/09/14 Tue 16/12/14 3 Architect Planning & Layout Plan 77 days Mon 01/09/14 Tue 16/12/14 4 LAND CONVERSION APPROVAL 65 days Mon 19/01/15 Fri 17/04/15 5 Submission & Approval 65 days Mon 19/01/15 Fri 17/04/15 6 Soil Investigation Work 70 days Wed 24/09/14 Tue 30/12/14 7 Selection & Appointment of SI Contr 49 days Wed 24/09/14 Mon 01/12/14 8 SI Work (4 weeks) 21 days Tue 02/12/14 Tue 30/12/14 9 Geotechnical 67 days Wed 17/12/14 Thu 19/03/15 10 Doc Preparation 23 days Wed 17/12/14 Fri 16/01/15 11 Submission & Approval 44 days Mon 19/01/15 Thu 19/03/15 12 TIA & RSA 67 days Wed 17/12/14 Thu 19/03/15 13 Doc Preparation 23 days Wed 17/12/14 Fri 16/01/15 14 Submission & Approval 44 days Mon 19/01/15 Thu 19/03/15 15 Development Order (DO) 100 days Wed 17/12/14 Tue 05/05/15 16 Drawing & Doc Preparation 23 days Wed 17/12/14 Fri 16/01/15 17 Submission & Approval 65 days Mon 19/01/15 Fri 17/04/15 18 Precomp Plan Approval 12 days Mon 20/04/15 Tue 05/05/15 19 Earthwork Design 122 days Wed 17/12/14 Thu 04/06/15 20 Design Preparation 44 days Wed 17/12/14 Mon 16/02/15 21 Submission & Approval 34 days Mon 20/04/15 Thu 04/06/15 22 Infrastructure & Building Design 288 days Wed 17/12/14 Fri 22/01/16 23 Architectural Building Design 65 days Wed 17/12/14 Tue 17/03/15 24 Infra Design 66 days Thu 01/01/15 Thu 02/04/15 25 Structural Design 66 days Thu 15/01/15 Thu 16/04/15 26 M & E Design 66 days Thu 15/01/15 Thu 16/04/15 27 Landscape Design 45 days Thu 01/01/15 Wed 04/03/15 28 Submission & Approval - BP, INFRA & LANDSCAPE 34 days Fri 05/06/15 Wed 22/07/15 29 Issuance of Title 132 days Thu 23/07/15 Fri 22/01/16 30 APPLICATION FOR DEVELOPER LICENCE & ADV. PERMIT 76 days Thu 23/07/15 Thu 05/11/15 31 Doc. Preparation 10 days Thu 23/07/15 Wed 05/08/15 32 Submission & Approval DLAP 65 days Fri 07/08/15 Thu 05/11/15 33 Building Detail Design 119 days Wed 18/03/15 Mon 31/08/15 34 Architectural Detail 105 days Wed 18/03/15 Tue 11/08/15 35 Structural and M & E Detail 84 days Fri 17/04/15 Wed 12/08/15 36 Documentation 35 days Tue 14/07/15 Mon 31/08/15 37 Tender 47 days Wed 02/09/15 Thu 05/11/15 38 Tender Call and Close 22 days Wed 02/09/15 Thu 01/10/15 39 Tender Report 12 days Fri 02/10/15 Mon 19/10/15 40 Tender Clarification & Negotiation 5 days Tue 20/10/15 Mon 26/10/15 41 Final Tender Report 5 days Tue 27/10/15 Mon 02/11/15 42 BOD Approval 3 days Tue 03/11/15 Thu 05/11/15 43 Letter Award 0 days Thu 05/11/15 Thu 05/11/15 44 Construction (3 Years) 783 days Fri 20/11/15 Wed 21/11/18 45 Site Possession 0 days Fri 20/11/15 Fri 20/11/15 46 Earthwork, Blg. & Ext. Works 783 days Mon 23/11/15 Wed 21/11/18 47 Certificate of Completion and Comp 45 days Thu 20/09/18 Wed 21/11/18 48 Contractual Practical Completion (C 0 days Wed 21/11/18 Wed 21/11/18 01/09 16/12 19/01 17/04 24/09 01/12 02/12 30/12 17/12 16/01 19/01 19/03 17/12 16/01 19/01 19/03 17/12 16/01 19/01 17/04 20/04 05/05 17/12 16/02 20/04 04/06 17/12 17/03 01/01 02/04 15/01 16/04 15/01 16/04 01/01 04/03 05/06 22/07 23/07 22/01 23/07 05/08 07/08 05/11 18/03 11/08 17/04 12/08 14/07 31/08 02/09 01/10 02/10 19/10 20/10 26/10 27/10 02/11 03/11 05/11 05/11 20/11 23/11 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar 2015 2016 PROPOSED DEVELOPMENT OF SERVICED APARTMENTS IN LOT 1342 SELAYANG, MUKIM RAWANG, DAERAH GOMBAK, SELANGOR DARUL EHSAN WORK PROGRAMME Rev 4: 15 Dec 2014

Master Work Programme Rev4 15122014

Embed Size (px)

Citation preview

  • ID Task Name Duration Start Finish

    1 PROPOSED SERVICED APARTMENT IN

    LOT 1342 SELAYANG, MUKIM RAWANG

    1103

    days

    Mon

    01/09/14

    Wed

    21/11/18

    2 Architectural Planning / Layout 77 days Mon 01/09/14Tue 16/12/14

    3 Architect Planning & Layout Plan 77 days Mon 01/09/14Tue 16/12/14

    4 LAND CONVERSION APPROVAL 65 days Mon 19/01/15Fri 17/04/15

    5 Submission & Approval 65 days Mon 19/01/15Fri 17/04/15

    6 Soil Investigation Work 70 days Wed 24/09/14Tue 30/12/14

    7 Selection & Appointment of SI Contractor49 days Wed 24/09/14Mon 01/12/14

    8 SI Work (4 weeks) 21 days Tue 02/12/14 Tue 30/12/14

    9 Geotechnical 67 days Wed 17/12/14Thu 19/03/15

    10 Doc Preparation 23 days Wed 17/12/14Fri 16/01/15

    11 Submission & Approval 44 days Mon 19/01/15Thu 19/03/15

    12 TIA & RSA 67 days Wed 17/12/14Thu 19/03/15

    13 Doc Preparation 23 days Wed 17/12/14Fri 16/01/15

    14 Submission & Approval 44 days Mon 19/01/15Thu 19/03/15

    15 Development Order (DO) 100 daysWed 17/12/14Tue 05/05/15

    16 Drawing & Doc Preparation 23 days Wed 17/12/14Fri 16/01/15

    17 Submission & Approval 65 days Mon 19/01/15Fri 17/04/15

    18 Precomp Plan Approval 12 days Mon 20/04/15Tue 05/05/15

    19 Earthwork Design 122 daysWed 17/12/14Thu 04/06/15

    20 Design Preparation 44 days Wed 17/12/14Mon 16/02/15

    21 Submission & Approval 34 days Mon 20/04/15Thu 04/06/15

    22 Infrastructure & Building Design 288 daysWed 17/12/14Fri 22/01/16

    23 Architectural Building Design 65 days Wed 17/12/14Tue 17/03/15

    24 Infra Design 66 days Thu 01/01/15 Thu 02/04/15

    25 Structural Design 66 days Thu 15/01/15 Thu 16/04/15

    26 M & E Design 66 days Thu 15/01/15 Thu 16/04/15

    27 Landscape Design 45 days Thu 01/01/15 Wed 04/03/15

    28 Submission & Approval - BP, INFRA

    & LANDSCAPE

    34 days Fri 05/06/15 Wed

    22/07/15

    29 Issuance of Title 132 days Thu 23/07/15 Fri 22/01/16

    30 APPLICATION FOR DEVELOPER

    LICENCE & ADV. PERMIT

    76 days Thu 23/07/15 Thu 05/11/15

    31 Doc. Preparation 10 days Thu 23/07/15 Wed 05/08/15

    32 Submission & Approval DLAP 65 days Fri 07/08/15 Thu 05/11/15

    33 Building Detail Design 119 daysWed 18/03/15Mon 31/08/15

    34 Architectural Detail 105 days Wed 18/03/15Tue 11/08/15

    35 Structural and M & E Detail 84 days Fri 17/04/15 Wed 12/08/15

    36 Documentation 35 days Tue 14/07/15 Mon 31/08/15

    37 Tender 47 days Wed 02/09/15Thu 05/11/15

    38 Tender Call and Close 22 days Wed 02/09/15Thu 01/10/15

    39 Tender Report 12 days Fri 02/10/15 Mon 19/10/15

    40 Tender Clarification & Negotiation 5 days Tue 20/10/15 Mon 26/10/15

    41 Final Tender Report 5 days Tue 27/10/15 Mon 02/11/15

    42 BOD Approval 3 days Tue 03/11/15 Thu 05/11/15

    43 Letter Award 0 days Thu 05/11/15 Thu 05/11/15

    44 Construction (3 Years) 783 daysFri 20/11/15 Wed 21/11/18

    45 Site Possession 0 days Fri 20/11/15 Fri 20/11/15

    46 Earthwork, Blg. & Ext. Works 783 days Mon 23/11/15Wed 21/11/18

    47 Certificate of Completion and Compliance (CCC)45 days Thu 20/09/18 Wed 21/11/18

    48 Contractual Practical Completion (CPC)0 days Wed 21/11/18Wed 21/11/18

    01/09 16/12

    19/01 17/04

    24/09 01/12

    02/12 30/12

    17/12 16/01

    19/01 19/03

    17/12 16/01

    19/01 19/03

    17/12 16/01

    19/01 17/04

    20/04 05/05

    17/12 16/02

    20/04 04/06

    17/12 17/03

    01/01 02/04

    15/01 16/04

    15/01 16/04

    01/01 04/03

    05/06 22/07

    23/07 22/01

    23/07 05/08

    07/08 05/11

    18/03 11/08

    17/04 12/08

    14/07 31/08

    02/09 01/10

    02/10 19/10

    20/10 26/10

    27/10 02/11

    03/11 05/11

    05/11

    20/11

    23/11

    Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

    2015 2016

    PROPOSED DEVELOPMENT OF SERVICED APARTMENTS IN LOT 1342 SELAYANG, MUKIM RAWANG, DAERAH GOMBAK, SELANGOR DARUL EHSAN

    WORK PROGRAMME

    Rev 4: 15 Dec 2014