View
63
Download
1
Embed Size (px)
Citation preview
CURICULUM VITAE
J.M. Janse Van Vuuren
Cellophane Number: 076 441 5100
Home Tel number: 016 971 3808
Email: [email protected]
PERSONAL DATA
Surname: Janse Van Vuuren
First Names: Johannes Marthinus (Martin)
Date of Birth: 28 April 1966
Language: Afrikaans and English
Driver’s License: Code 10
EDUCATION
High School Die Bult – George: Matric
EMPLOYMENT HISTORY :
Contractor: Stefanutti Stocks
Duties: Electrical Supervisor for the installation of new Compressor at the Sasol Sasolburg ATR plant.
Installed all cable works, earthing, tie-ins to existing MCC.
Year: 08 February 2016 - current (Limited duration Contract).
Contractor: Foster & Wheeler (EPCM)
Duties: Managing the subcontractor for the installation and quality control of the project.
Year: 03/2008 – 15 Dec 2015 (Was given EOC due to no projects available for Foster Wheeler at this stage)
Career Summary: Foster & Wheeler (EPCM)
2014 – 15 Dec 2015:
Managed the LPC & ESE Projects Temane Mozambique
Construction supervisor and QA/QC
Subcontractor : Kentz
Was appointed “Site Manager” while Site Manager was on leave.
Installation of new substation / low pressure compressors
Installation of MV switchgear /LV MCC and switchgear.
Installation of new Super Heater.
Installation of 4th MV Generator.
Changeover of existing Thyristor panels with new panels.
Nitrogen package and instrument air package.
Installation of electrical and instrumentation equipment
For the project.
2013 – 2014 Managed the C3 Stabilization project PP2 (FWSA)
Subcontractor: Stefanutti Stocks
Instrumentation quality control QA/QC
Assisting in getting the project to completion.
Installation of instrumentation for the C3 project
2010 – 2013 Managed the FT WAX (Work Pack 01)(FWSA)
Construction supervisor; QA/QC
Subcontractor: Stefanutti Stocks
Complete installation of WP01
Installation of new substation and rack room.
Installation of all MV switchgear /LV MCC switchgear
Installation of electrical equipment for the project
Installation of 11kV transformers complete with
Feeders and additional switchgear in the feeder substation.
2009 – 2010 Managed the 4t Land Lord project (FWSA)
Construction supervisor
Subcontractor: Kentz
Installation of new rack room and substation (DCS) KK-SS-03
Installation of electrical and instrumentation for the project.
QA/QC for the installation.
2008 – 2009 Managed the Nat Gas 149 Project Komatipoort (FWSA)
Construction supervisor
Subcontractor: Kentz
Installation of new substation and rack room
Installation of LV MCC and switchgear.
Installation of electrical and instrumentation equipment
For the project.
Assisting in completion of the project.
QA/QC for the project.
March 2008 Managed the PPS Project (FWSA)
Construction supervisor
Subcontractor: Energotec.
Installation of additional gas train for NG149
Installation of LV MCC and switchgear.
Installation of new substation and addition of equipment
Installation of electrical and instrumentation equipment
For the project.
QA/QC for the project.
---------------------------------------------------------------------------------------------------------
Contractor: B & W Instrument & Electrical
Project: Veolia
Duties: Construction Supervisor, QA/QC, Installation of extra lights,
Installation of Cables, Cable glanding and termination.
Year: 03/2007 – 02/2008
Contractor: B & W Instrument & Electrical
Project: Shutdown Rectisol
Duties: Construction Supervisor, QA/QC
Year: 01/2007 – 02/2007
Contractor: XSTRATA
Project: Vantech Mine
Duties: Electrical Supervisor, QA/QC
Year: 09/2006 – 12/2006
Contractor: B & W Instrument & Electrical
Project: Project Landlord – Veolia Water Systems.
Duties: Electrical Supervisor, Electrical QA/QC, First Aider,
KBC Induction, Legal Liability.
Year: 10/2005 – 08/2006
Contractor: B & W Instrument & Electrical
Project: Waste Recycle Facility Project.
Duties: Electrical Supervisor, Small Power and Lights,
Field Installation of Motors and MCC in Substation,
First Aider, KBC Induction, Legal Liability.
Year: 05/2004 – 10/2005
Other Experience:
2004 – 2008 B & W Instrumentation & Electrical
Construction Supervisor
Various projects ESD replacement at unit 040
ESD replacement at unit 240
UPS installation at unit 244
Lightning and small power installation at control room
Desalination plant
Installation of temporary truck stop
Additional Work:
QC for electrical installation at project Veolia
Additional work at WRF
Construction supervisor for WRF project with FW as client
E&I supervisor for Wade Walker PMR Rustenburg capacity
Increase project
E&I supervisor GLTA
Electrical supervisor Polokwane smelters green fields project
Electrical supervisor BMR Rustenburg Installation of all electrical equipment for the Cool isle project.
Contractor: Electrical Wade Walker
Duties: Electrical Supervisor, Small power and Lights,
First Aider, KBC Induction, Legal Liability.
Year: 07/2003 – 05/2004
Contractor: Grinaker LTA (MEIP)
Electrical and Maintenance
Duties: Foreman Electrical, Small power and Lights,
First Aider, KBC inducted, Legal Liability,
Excavation Inspector, install Construction Power
Up to 550 volt and Removal thereof, Safety Rep.
Year: 11/2001 – 07/2003
Contractor: Grinaker LTA
Electrical and Mechanical
Duties: Install motors, motor termination,
DB and MCC panel Terminations,
Small power and lights.
Year: 11/1998 – 10/2001
Contact Person: Keith Moss / Koos Janse Van Rensburg
Own Business: Breakdown Recovery
Year: 11/1997 – 11/1998
Machine Setter: Nestle Bethal
Duties: Maintenance and Running maintenance.
Removal of intake valves and shafts.
Weld up to size and machine down to size.
Reason for leaving: End of Contract
Year: 1995 – 1997
Millwright: Wepner Engineering
Contractual Basis
Duties: Foreman Pipe Fitter, and Machine Setter
Contact Person Chris Wepner
Year: 1994 – 1995
Self Employed: Bulawayo Zimbabwe
Millwright
1992 – 1994
Counter Sales: Timber City
Kempton Park
1991 – 1992
S.A.N.D.F: National Service
Heidelberg (TVL)
07/1988 – 12/1990
Apprentice: Electrician
C.T.C. Witbank
01/1986 – 06/1988
Apprentice: Instrument Technician
U.S.C.O. Vereeniging
1985
Education, Qualifications and Memberships:
Education:
Metric 1984
Qualifications:
20 years electrical experience.
15 years instrumentation experience.
Competant electrical supervisor.
Memberships:
None
Courses Done:
Venomous Snake Handling Course 2015.
Construction Regulations 2016.
Legal Responsibility and Accountability 2016.
Working at Heights 2016.
HIRA (Hazard Identification and Risk Assesment) 2016.
Radio detection RD8000/Accessories 2011
Fire & Gas Training Sasol 2006
Certificate of competence:
E&I Supervisor
2004
---------------------------------------------------
Summary:
I’m a hard worker and thrive on challenges.
I set myself goals to reach.
Completion of a project is an achievement.
I will be an asset for your company.
I am always willing to learn.
Please see “Letter of Recommendation” below.