19
Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010 NSF Research Infrastructure Development

Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

Embed Size (px)

Citation preview

Page 1: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

Mark ColesDeputy Director, Large Facility Projects

Offi ce of Budget, Finance, and Award ManagementNational Science Foundation

October 1, 2010

NSF Research Infrastructure Development

Page 2: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

Brief overview of US picture, but mostly about NSF process:Overview of the Major Research and Facilities Construction

Account (MREFC):For acquisition, construction, and commissioning of capital

assets, with values exceeding 10% of annual budget of sponsoring Directorate or Office

Planning and preparatory activities, and essential characteristics of projects qualified to receive MREFC funds

2

Topics

Page 3: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

NSF’s large facility project planning process

Review science goals

Conceptual Design Stage ◦ Requirements, initial estimates of cost (including

operations), risk and schedule Preliminary Design (“Readiness”) Stage

◦ Definition and design of major elements, detailed estimates of cost, risk and schedule, partnerships, siting

Final Design Stage (“Board Approved”) Stage◦ Interconnections and fit-ups of functional elements, refined

cost estimates based substantially on vendor quotes, construction team substantially in place

3

NSB Approved

Preliminary Design

FinalDesign

Construction

Operations

Horizon planning and Conceptual Design

Readiness

Conceptual Design Review (CDR)

Preliminary Design Review (PDR)

FinalDesign Review (FDR)

Operations Review

DecisionReview

Page 4: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

Implementation

Formulation

Operations

ConceptStudies

Prelim Design & Tech

Completion

Final Design & Fabrication

Concept & Tech Devel

Pre-Phase A Phase A Phase B Phase C Phase D Phase E

KDP-A KDP-B KDP-C

Assembly, Integ &

Test, Launch

KDP-D KDP-E

Broad Similarities between NSF, DOE, NASA

4

NSB Approved

Preliminary Design

FinalDesign

Construction

Operations

Horizon planning and Conceptual Design

Readiness

ExecutionPre-

conceptualPlanning

OperationsConceptua

lDesign

CD-0Approve mission

need

CD-1Approve

alternatives

selection

CD-2Approve

Performance baseline

CD-4Approve

operations start

CD-3Approve

construction start

Initiation

Definition Prelimina

ryDesign

FinalDesign

Construction

DecisionReview

Key Decision Points:

Conceptual Design Review (CDR)

Preliminary Design Review (PDR)

FinalDesign Review (FDR)

Operations Review

DOE Critical Decisions:

Page 5: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

Importance of pre-construction planning to determine credible construction cost estimatePreconstruction investment of 5-25% of capital cost

Full-cost accounting for US contributionFull life-cycle cost estimating up front

Operating cost projections Budgeting for science useTermination liabilities Capacity to sustain operation is a key factor in decision to

support creation of new infrastructureRisk adjusted construction cost estimates

Budget, schedule, and scope contingency5

Some important similarities across US agencies

Page 6: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

Open researcher access to facilities based on merit review

Open data access policiesExperimental groups do not contribute to operating costs

of accelerators (ICFA guidelines), telescopes, and true for all NSF-funded facilities

Uncertain annual appropriation process“Earned Value” cost and schedule reporting requirements

– Federal Government mandate

6

Other similarities between US agencies

Page 7: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

“Mission Agencies” - DOE and NASALong term agency roadmaps for infrastructureMuch larger investment in infrastructure (15 DOE national

labs)NSF is reactive to research community initiatives

Near term plansCan respond to opportunities and discipline roadmap

recommendations in multiple waysAstro2010, HEPAP, etc.

Mixture of approaches is a national strength

7

Important Differences Between US Agencies

Page 8: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

NSF Program Officer:Key individual with discipline-specific knowledgePoint of contact with facility proponents and research

communityCoordinates other NSF resources: contracting, legal,

financial, project management (Large Facilities Office)Organizationally part of a Division and a Directorate.

Directorates manage budgets for planning, construction, operation, research

8

NSF Roles

Page 9: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

Large Facilities Office provides project management resources to Program Officer

Assistant Directors and NSF Deputy Director recommend cross-agency priorities for new facilities

Director and National Science Board decide on balance of facilities/research within context of other budget priorities, approve construction budget request

Office of Management and Budget approves construction budget request

Congress appropriates construction funds

9

Other NSF Roles

Page 10: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

NSF Large Facility Manual:http://www.nsf.gov/publications/pub_summ.jsp?ods_key=l

fmDescribes process steps and expectations in detail, and

coordination of processes for:project development by community oversight and review within NSFbudget development, request, appropriation, and

obligation process.

10

Details of the NSF’s MREFC Process

Page 11: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

International partnerships have an intrinsic overhead cost that must be recognized

Partnership agreements are founded on good will – structure must be carefully planned to align interests to avoid destabilizing collaboration

Synchronizing development process when there are other partners or potential partners

Exercising stewardship/oversight over US-funded scope in a complex environment

Defining the appropriate governance model

11

Challenges to international collaboration

Page 12: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

Big projects are inherently part of political dialogue because of the size of projected budgets

Projects have foundered when political influence has resulted in premature project start with incomplete plans (RSVP, ITER, SSC,…) and there has been painful re-scoping with others (ALMA, SODV…)

Cost growth between initial designs and FDR costs have sometimes been 2-3 times initial estimates, or more (ALMA, OOI, ARRV…)

NSF “No cost overrun” policy:Requires that the cost estimate have adequate contingency to

cover all foreseeable risks, and any cost increases not covered by contingency be accommodated by scope reduction

12

And Still More Challenges:

Page 13: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

US terminology – risk adjusted cost - not an international practiceMust be applied to US-funded portion of collaborative project

Part of the budget needed to accomplish the projectHeld by the project managerPays for known unknowns

Good experience with this approach – an algorithmic bottom-up assessment of project risk

Good experience at NSF with PDR and FDR sub-panels that do a complete drill down in several WBS areas to check basis of estimate and overall estimating methodology (ARRV, NEON, OOI..)

Risk management plan must encapsulate the known-unknowns and translate this risk into budget augmentation

13

Budget Contingency

Page 14: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

Schedule management is an important component of project risk management.

Projects need “industrial strength” project management software tools for creating and managing a resource loaded schedule, and optimizing use of float

Include defined schedule contingency and manage centrally.

14

Schedule and Schedule Contingency

Page 15: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

Many future projects are so large that they will almost certainly done through interagency, international, and public-private partnerships.Projected operations costs are large perturbations on

existing budgetsMultiple candidate projects with total project cost

estimates $500M $1000M+Current Divisional budgets are $250-400M eachCurrent Divisional operations budgets ~$50M - $100M+NSF can provide partial support for very large new facilities

as one of many funding sources

15

Looking forward

Page 16: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

16

Backup materials

Page 17: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

For 10 years, NSF has funded a workshop, held about annually, to provide training to community on planning for future infrastructure. Next one is: Nov 7-11, Fort Lauderdale

Info at http://www.projectscience.org/

17

Project Science

Page 18: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

MREFC funding in the FY 2011 Congressional Budget Request

18

      Millions of Dollars in Fiscal Year

    Total Cost,

$M

 Omnibus

ActualARRA Actual Estimate Request Estimate Estimate Estimate Estimate Estimate

Sponsor Facility   2009 2009 2010 2011 2012 2013 2014 2015 2016

BIO NEON 434 

- - - $20.0 $87.9 $101.1 $103.4 $86.2 $32.1

GEOOOI 386

 - $105.9 $14.3 $90.7 $102.8 $46.8 $20.0 - -

ARRV 200 

$14.1 $148.1 - - - - - - -

MPS

ATST 298 

-  *see note $13.0 $17.0 $20.0 $20.0 $20.0 $20.0 $20.0

AdvLIGO 205 

$51.4 - $46.3 $23.6 $21.0 $15.2 $14.9 - -

ALMA 499 

$82.3 - $42.8 $13.9 $3.0 - - -  

MPS/OPP IceCube 242 

$11.9 - $1.0 - - - - - -

OPP SPSM 149 

$1.1 - - -          

  

 Total: 

$160.8 $254.0 $117.3 $165.2 $234.7 $183.0 $158.4 $106.2 $52.1

*ATST’s FY 2009 $146M ARRA was obligated in FY 2010

Page 19: Mark Coles Deputy Director, Large Facility Projects Office of Budget, Finance, and Award Management National Science Foundation October 1, 2010

MREFC project portfolio: construction vs. funding

19

Sponsor Facility

OPP SPSM

MPS/OPP IceCube $1.0 M

MPS

ALMA 42.8 13.9 3.0

AdvLIGO 46.3 23.6 21.0 15.2 14.9

ATST 13.0 17.0 20.0 20.0 20.0 20.0 20.0

GEOARRV

OOI 14.3 90.7 102.8 46.8 20.0

BIO NEON 20.0 87.9 101.1 103.4 86.2 32.1

$0

$100

$200

$300

$117 M$165 M

$235 M$183 M

$158 M$106 M

$52 M

NEONIn construction

MREFC account funding ($M in Fiscal Year)

2010 2011 2012 2013 2014 2015 2016 2017

Oct-10 Oct-16

Apr-15

Jan-14

Feb-17

Sep-15

Dec-12

Feb-11

Mar-10

FY